Getting the Transmission Planning Rules Right for Competitive Markets
-
Upload
charles-pratt -
Category
Documents
-
view
212 -
download
0
Transcript of Getting the Transmission Planning Rules Right for Competitive Markets
Getting the TransmissionPlanning Rules Right forCompetitive Markets
The absence of region-wide transmission planning can beseen as another ‘‘seams’’ issue. This ‘‘transmissionplanning seam’’ should be eliminated as soon as possible.The development of rules specific to each RTO simplyperpetuate unnecessarily a seam among the threeNortheastern RTOs.
Charles Pratt
Charles Pratt is a Partner in theNew York office of Dickstein ShapiroMorin & Oshinsky LLP and advises
clients on energy industryrestructuring, regulatory matters,
and transmission issues. This articlerepresents the views of the author
alone and not of his firm nor itsclients. The author can be contacted
I. Introduction
The Federal Energy Regula-
tory Commission has identified
transmission congestion as a
major barrier to the development
of robust energy markets.1
Transmission congestion that
does not lead to economical
changes to the bulk power
system has the effect of limiting
the geographical scope of the
market and thus weakening
competition. Nevertheless, dur-
ing the restructuring of the
electric power industry there
has been limited investment in
transmission system facilities
beyond direct generation inter-
connections.2 One reason for
such limited investment is the
slow development of trans-
mission planning rules for
competitive markets. Even
after several years’ operating
experience, the three control
area operators in the Northeast
have not yet completed adop-
tion of transmission planning
rules.3
S everal recent Commission
orders identify significant
issues that contribute to the
Northeastern RTOs’ slow
August/September 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:10.1016/S1040-6190(03)00094-0 65
development of transmission
planning rules. In addition, each
of these RTOs is currently con-
sidering significant modifica-
tions to its transmission planning
rules. Thus, it is timely to con-
sider transmission planning in
these three RTOs. Resolution of
transmission planning issues in
the Northeast is likely to influ-
ence the development of plan-
ning rules elsewhere as
competitive markets develop in
other regions.
T his article, first, describes
how the three Northeastern
RTOs currently address trans-
mission planning. Second, it
explores three issues key to
establishing transmission plan-
ning rules: (a) how to select
among competing proposals to
reduce transmission congestion;
(b) how the cost of transmission
projects should be recovered; and
(c) whether RTOs should be
authorized to mandate trans-
mission expansion to resolve
congestion. Underlying these
issues is the question of the
appropriate extent of an RTO’s
authority to make system
planning decisions to address
transmission congestion. The
resolution of these questions in
this article supports the conclu-
sion that a model in which RTOs
have sufficient authority to
undertake transmission plan-
ning, but are subject to the
restraining policy of superseding
market initiatives to the mini-
mum extent possible, presents an
effective approach to transmis-
sion planning for competitive
markets.
II. TransmissionPlanning in the Northeast
A. PJM
PJM’s Operating Agreement
provides that PJM shall prepare
a Regional Transmission Expan-
sion Plan (RTEP) for the
enhancement and expansion of
transmission facilities in order
to meet the demands for firm
transmission service and to
support competition. The RTEP
‘‘shall consolidate the transmis-
sion needs of the region into a
single plan which is assessed on
the bases of maintaining the
reliability of the PJM Control
Area . . . in an economic and
environmentally acceptable man-
ner and of supporting competition
in the PJM Control Area . . ..’’4 The
RTEP is developed in consultation
with a stakeholder advisory
committee and then presented to
PJM’s Board for approval.
T he Operating Agreement’s
transmission planning pro-
visions were accepted in July 2001
by the Commission, with the
requirement that three aspects of
PJM’s transmission planning pro-
tocol be modified.5 The Commis-
sion stated that a regional
transmission plan must have a
broader orientation than main-
taining reliability, and should
make generation markets more
competitive. ‘‘[T]he planning
process should also focus on
identifying projects that expand
trading opportunities, better inte-
grate the grid, and alleviate con-
gestion that may enhance
generator market power.’’6 In
addition, the Commission directed
that all market participants should
have an opportunity for mean-
ingful participation in the plan-
ning process and that parties other
than traditional transmission
owners be permitted to sponsor
expansion plans. On rehearing,
two years later, PJM was directed
to explain how the transmission
planning process will identify
expansion projects that are needed
to support competition, as well as
to ensure reliability.7
In March 2003, PJM proposed
changes to its Open Access
Transmission Tariff (OATT) and
Operating Agreement regarding
transmission planning, which
would authorize PJM to designate
one or more transmission owners
or other entities to construct or
finance transmission enhance-
ments or expansions specified in
the RTEP to alleviate congestion.8
Such obligation would be trig-
gered when there is ‘‘unhedge-
able congestion.’’9 In addition,
the proposed transmission
enhancement or expansion must
be economically justified. These
provisions are in addition to
The underlying issue:the appropriate extent
of an RTO’s authorityto make system
planning decisions toaddress transmission
congestion.
66 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:10.1016/S1040-6190(03)00094-0 The Electricity Journal
PJM’s assessment of the system’s
compliance with applicable relia-
bility criteria.10
T he RTEP, as proposed in the
Compliance Filing, will
include designations of cost
responsibility for each enhance-
ment and expansion project,
based upon planning analysis and
participants’ willingness to bear
cost responsibility. In the absence
of agreement to revise the default
allocation plan, PJM proposes that
costs are to be allocated to: (a)
market participants in one or
more transmission zones that are
to be responsible for a transmis-
sion enhancement or expansion as
and to the extent provided by the
PJM OATT, or (b) if cost respon-
sibility is not established by the
OATT, market participants in one
or more transmission zones pur-
suant to a rate tariff to be filed
separately by transmission own-
ers.11 Allocations under the sec-
ond of these two formulas will be
based upon PJM’s ‘‘assessment of
the contributions to the need for,
and benefits expected to be
derived from, the pertinent
enhancement or expansion by
affected Market Participants.’’12
B. New England
During the past three years, the
Commission has addressed
transmission planning in ISO-NE
in a number of orders concerning
the RTO’s proposed congestion
management—multi-settlement
system and ISO-NE’s standard
market design.13 In February
2002, the Commission accepted a
transmission planning proposal
which vested sole responsibility
for transmission planning in the
RTO.14 Pursuant to this planning
protocol, the RTO prepares a
regional transmission plan, that is,
an RTEP. Earlier references to a
Transmission Planning Commit-
tee, which provided for a signifi-
cant role for transmission owners
in transmission planning, were
deleted. The planning protocol
provides for issuance of requests
for competitive bids to build
transmission upgrades included
in the RTEP.15 In addition to such
transmission upgrades, market
participants may also propose
alternative generation, merchant
transmission facilities, elective
transmission upgrades, demand-
side management, and load
response programs that substitute
for or make unnecessary a trans-
mission upgrade. In the event such
a proposal is selected, the trans-
mission upgrade is removed from
the plan. ISO-NE’s RFP process
has a limited scope as it focuses
only on the proposed transmission
upgrades included in ISO-NE’s
RTEP.16 The tariff does not specify
whether proposals originated
by market participants will be
considered in evaluating potential
transmission upgrades, or simply
constitute another option available
to ISO-NE. Transmission owners
remain potentially responsible for
constructing reliability upgrades
and upgrades that the RTO has
exempted from the competitive
bidding requirements.17
How the cost of transmission
upgrades is to be allocated has not
been resolved. The Commission
announced in mid-2002 that
continuation of a cost allocation
methodology which socializes
costs of transmission upgrades
over a broad customer base
should be replaced with a meth-
odology which permits parties to
see and respond to market signals
in planning and locating trans-
mission upgrades.18 In the Com-
mission’s order accepting the
proposal by ISO-NE and
NEPOOL to adopt a standard
market design, the Commission
directed ISO-NE to develop a
mechanism for allocating costs of
transmission expansion projects,
when the parties cannot agree
who benefits from the upgrade.
The Commission directed that
ISO-NE adopt an objective, non-
discriminatory default cost allo-
cation method that is consistent
with the principles of cost cau-
sation.19 More recently, the
Commission stated in an order on
rehearing that New England
should develop an objective, non-
discriminatory default mechan-
ism to allocate the costs of
upgrades which do not clearly
benefit a discrete party nor are
beneficial to the entire pool.20
Howthe cost oftransmissionupgrades isto be allocatedhas notbeen resolved.
August/September 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:10.1016/S1040-6190(03)00094-0 67
ISO-NE is considering cost allo-
cation options in stakeholder
discussions and anticipates com-
pleting such discussions and
submitting a proposal to the
Commission before the end of
summer 2003. This eventual cost
allocation mechanism will
address upgrades of transmission
facilities that function for the
benefit of the regional power grid,
i.e., Pool Transmission Facilities,
while the costs of upgrades of
other facilities are to be recovered
under each transmission owner’s
OATT.
C. New York
In contrast to PJM and ISO-NE,
the NYISO does not currently
prepare a transmission plan
comparable to an RTEP.21 Nor
does the NYISO otherwise direct
construction of transmission
expansion projects by transmis-
sion owners.22 While the New
York Public Service Commission
(NYPSC) is authorized to request
the NYISO to provide transmis-
sion reinforcement options for
interfaces having significant con-
gestion, it does not appear that
this provision is used regularly.
M oreover, New York does
not have a process for
allocating the cost of transmission
upgrades, apart from intercon-
nection-related upgrades. While
the NYISO’s market participants
have considered proposals to
allocate transmission congestion
contracts to entities that expanded
the transmission system, such a
system has not been implemented.
In a joint petition to form a single
RTO, ISO-NE and NYISO
included transmission planning
provisions, but that petition was
withdrawn shortly after its filing.23
T he NYISO has initiated stake-
holder discussions of a
transmission planning protocol,
which is not expected to be
implemented before the fall of
2003. It appears that the NYISO
favors, at least for the initial phase
of a planning protocol, distin-
guishing transmission expansion
for reliability reasons from other
types of projects.24
III. Key Issues
A. How to select among
competing proposals to reduce
transmission congestion
The Commission proposed in
the SMD NOPR that RTOs iden-
tify all needs for expansion of the
transmission system, i.e., both
reliability and economic needs.
When additional resources are
required, the RTO would
request market proposals. Parties
would be permitted to propose
transmission expansion, new
generation, and increased
demand response proposals. If
such a bidding process failed to
produce adequate proposals,
transmission owners would be
required to expand the system.25
While an RTO’s selections among
transmission upgrade and other
proposals could significantly
affect market initiatives, such
intrusion can be minimized by
limiting the RTO’s exercise of
transmission planning authority.
One approach to minimizing
RTOs’ exercise of planning
authority is the adoption of a
three-tiered set of restraints on
RTO authority to undertake
planning initiatives. First, the
RTO could provide market parti-
cipants time to respond to a
defined system need that is
causing transmission congestion.
In PJM, this step is referred to as
providing a ‘‘timing trigger.’’
Only in the absence of the mar-
ket’s failure to respond to such a
trigger would the RTO consider
further steps to build economic
upgrades. Second, an RTO could
include a transmission proposal
in the RTEP to satisfy economic
needs, only provided that trans-
mission congestion is significant.
While the specification of what
constitutes ‘‘significant conges-
tion’’ will be difficult, factors that
should be considered include (1)
the ratio of the congestion asso-
ciated with the need for an
upgrade to RTO-wide congestion,
(2) the persistence of congestion,
and (3) the impact of the trans-
mission congestion caused by a
constraint on the need for market
One approach tominimizing RTOs’
exercise of planningauthority is adoption
of a three-tieredset of restraints on
RTO authority.
68 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:10.1016/S1040-6190(03)00094-0 The Electricity Journal
mitigation provisions in the con-
strained energy market. The stan-
dard set by PJM, ‘‘unhedgeable
congestion,’’ is both undefined
and may be set at too low a level to
bar unneeded intrusion into the
market.26 It does not appear that
either of these steps, or restraints,
is included in ISO-NE’s transmis-
sion planning rules, nor in the
NYISO’s limited transmission
planning provisions.
A third potential limitation
on centralized planning
involves the use of competitive
requests for proposal (RFP) for all
proposals addressing transmis-
sion congestion. While PJM pro-
poses to conduct cost benefit
analyses concerning proposed
economic transmission enhance-
ments and expansions,27 it
appears that such analyses will
not consider market-initiated
non-transmission options. Such
options may lead to changes in the
RTEP, but it does not appear that
they will be considered in the RFP
evaluation process. Thus, PJM’s
planning proposal may lead to the
selection of rate-base transmis-
sion options instead of more
efficient and cost effective solu-
tions, such as demand response,
merchant transmission, or gen-
eration.28 ISO-NE’s RFP process is
similarly limited to proposed
transmission upgrades.29
Transmission solutions should
not be mandated or favored in an
RTO’s planning rules, as market
solutions to congestion can
include specific generation and
demand-response alternatives
that make transmission solutions
unnecessary. Rather, in order to
avoid favoring one resource type
over others, the RTO should
review transmission enhance-
ments or expansions against
alternative market proposals,
including generation, merchant
transmission, and demand
response, in a process using spe-
cific standards available to market
participants. The transmission
planning rules should be
designed so that the most efficient
and cost effective solutions are
selected. While RTOs could
become responsible for what is
essentially integrated resource
planning if they are the gate-
keeper for selection of all types of
economic transmission upgrades,
or expansions, the three limita-
tions on the RTO’s planning role
discussed here—a trigger period
of at least one year for the market
to respond to perceived needs, the
limitation of a planned economic
upgrade to cases involving ‘‘sig-
nificant’’ congestion, and appli-
cation of rigorous economic
analysis to both market-initiated
projects as well as transmission
upgrades—constrain the RTO’s
planning power.
The limitation on the scope of
the RFP process in both PJM and
ISO-NE is compounded by a lack
of specification as to whether non-
transmission proposals origi-
nated by market participants will
serve as a threshold test for pro-
posed transmission upgrades or
as simply another option avail-
able to the RTO. Although trans-
mission projects may be removed
from the RTEP in favor of alter-
natives proposed by market par-
ticipants, such decisions would
not be made in the context of the
competitive RFP process. Thus, it
is not clear whether the decision
to replace a proposed transmis-
sion upgrade in favor of a market-
proposed option is to be made on
economic grounds or upon other
non-specific and non-quantified
grounds. The focus on the RTO as
a gatekeeper places a high pre-
mium on specifying how the RTO
will address transmission plan-
ning in documents filed with the
Commission in order to avoid
simply increasing the RTO’s dis-
cretion.
The requirement that the RTO
adopt the three substantive ‘‘self-
limiting’’ constraints discussed
above, together with making its
planning rules specific, are critical
limitations on an RTO’s power to
intrude in the market’s develop-
ment.
B. How should the cost of
transmission projects be
recovered?
The method of allocating the
cost of economic transmission
expansion projects remains
August/September 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:10.1016/S1040-6190(03)00094-0 69
unresolved by the three North-
eastern RTOs. PJM proposes to
designate market participants, in
addition to transmission owners,
as responsible for costs of trans-
mission expansion projects.30
Such allocations would be based
upon PJM’s ‘‘assessment of the
contributions to the need for, and
benefits expected to be derived
from, the pertinent enhancement
or expansion by affected Market
Participants.’’31
W hile PJM’s proposal does
not make clear how such
an allocation of costs to particular
market participants would be
made, fewer than all transmission
customers within a transmission
zone may be designated for
recovery of the cost of a particular
transmission expansion or
enhancement. In fact, it appears
that such an allocation could be
made among a limited group of
market participants, as PJM is
required to designate the pro-
portional responsibility among
market participants. Although
upgrade costs can be allocated to
load-serving entities (LSEs),
nothing in PJM’s proposal pre-
cludes allocating such costs to
other transmission customers.
Thus, under its proposal, PJM will
assume significant authority to
allocate costs based on its assess-
ment of each market participant’s
contribution to the need for, and
benefit from, each particular
transmission upgrade.
PJM’s proposed allocation
process leaves key questions
unanswered. First, the standards
for such assessment of market
participants’ contribution to the
need for or benefit from the
upgrade are not specified, but are
left to the discretion of the RTO.
While PJM promises to thor-
oughly vet a proposed cost-allo-
cation, the absence of decision-
making standards in the tariff
indicates that such vetting will be
within the RTO’s discretion. This
failure to spell out the rules
explicitly would appear to
enlarge the planning role of the
RTO, compared to making such
allocations pursuant to specific
rules. Moreover, the indefinite-
ness of the basis for determining
the benefit from a particular
transmission upgrade may lead to
disputes and litigation before the
Commission.
S econd, transmission custo-
mers, to which such costs
will be allocated, are in quite
different positions depending on
whether they are LSEs. Imposi-
tion of the cost of a transmission
upgrade on a party incapable of
collecting them pursuant to tra-
ditional rate-setting—such as a
merchant developer—is quite
different from imposing such
costs on an LSE, which can pass
the charges on to customers
through regulated rates.
In the case of ISO-NE and the
NYISO, the RTOs and market
participants have not finally
selected a method of allocating the
cost of economic transmission
expansion projects. Moreover, at
least the NYISO’s authority to
mandate that transmission owners
assume a share of the costs of an
economic expansion project is
limited.32 Such a limitation would
appear also to bar, at least in effect,
the NYISO from allocating such
costs to other market participants,
as such an incomplete allocation
would necessarily discriminate
among market participants.
The broad RTO discretion over
cost allocation proposed by PJM
may lead to numerous disputes
regarding cost allocation to non-
consenting market participants.
This potential for continued dis-
pute suggests, however, that the
existence of the parties’ mutual
agreement to an allocation of costs
of transmission upgrades may be
a de facto limit on RTOs’ ability to
allocate the cost of new economic
transmission projects. In the event
that the benefits from a trans-
mission upgrade are obvious,
market participants are likely to
undertake the expense. On the
other hand, upgrades with less
clear benefits to market partici-
pants may be constrained by
market participants’ opposition.
Thus, RTOs may find it expedient
to favor projects for which there is
a voluntary agreement to assume
the costs. To the extent RTOs are
effectively restricted to such
voluntary allocations, there is an
70 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:10.1016/S1040-6190(03)00094-0 The Electricity Journal
effective limit on RTOs’ power to
allocate the cost of transmission
projects, and thus a reduction in
RTO’s power to conduct centra-
lized planning. Such a result is
consistent with the premise of this
article that an RTO’s power to
undertake economic planning
should be limited.
T he scope of the RTO’s role in
transmission planning is
reduced to the extent the stan-
dards for cost allocation are spe-
cified. Moreover, to the extent that
disputes over allocation formulas
limit the allocations to cases in
which there is voluntary agree-
ment of market participants, the
scope of the RTO’s discretion
would appear to be limited
and thus its role in centralized
transmission planning would be
limited.
C. Should RTOs be
authorized to mandate
transmission expansion to
resolve congestion?
PJM’s Operating Agreement
authorizes the designation of one
or more transmission owners to
construct or finance transmission
enhancements or expansions
specified in the RTEP.33 Certain
transmission owners, however,
have challenged PJM’s author-
ity—and by implication, RTOs’
authority generally—to direct a
transmission owner to construct a
transmission enhancement or
upgrade.34 Moreover, the recent
decision in Atlantic City Electric
Company v. FERC,35 concerning
PJM’s authority with respect to
transmission owners, may
encourage transmission owners to
challenge RTOs’ assumption of
authority. Further, the NYPSC has
argued that an RTO should not be
authorized to approve transmis-
sion expansions or to solicit pro-
posals to expand the transmission
grid, add generation, or imple-
ment demand response, but
should simply make the results of
any needs assessment available
and allow the market to
respond.36
It is not necessary to resolve
these questions, however, as they
are beside the point to the extent
that the RTO’s planning rules
provide a basis for participants to
support needed expansions of the
transmission grid voluntarily. In
fact, the failure of market parti-
cipants to agree to fund trans-
mission upgrades may reflect the
absence of an effective device to
realize the apparent benefits. If
appropriate means of realizing
the benefits of transmission
upgrades can be created, market
participants are increasingly
likely to be willing to undertake
transmission upgrades on a
voluntary basis.37 There is thus a
priority need to create means of
realizing the benefits of trans-
mission upgrades in order to
capture the full value of the
upgrade.38 Development of such
market rules that permit parties to
realize the benefits of transmis-
sion upgrades would limit RTOs’
control of system planning, as it
would be unnecessary for RTOs to
mandate expansion projects in
such cases.
In the absence of effective
means of realizing the benefits of
transmission upgrades, a practi-
cal remedy for RTOs seeking to
secure an expansion of the trans-
mission grid would be for the
RTO to make specific requests to
the Commission for approval of
mandated transmission
upgrades. This approach avoids
the necessity for an RTO to contest
whether it has authority to man-
date new construction. Such
requests would also assist the
RTO, which is undertaking
nuanced decisions concerning
economic upgrades, from having
to review its own decision-mak-
ing. To the extent that a particular
upgrade is controversial, a case-
specific approval would free the
balance of the RTEP from the risk
that a complaint would retard its
being made effective.
IV. Conclusion
While the three key issues dis-
cussed in this article hardly
address all matters of concern
regarding transmission planning,
adoption of a model in which
RTOs are authorized to undertake
August/September 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:10.1016/S1040-6190(03)00094-0 71
transmission planning, while
being subject to a policy limiting
intervention in the market to the
minimum extent possible, pro-
vides a basis for transmission
planning. Thus, RTOs would be
able to carry out the essential task
of transmission planning, for
which they are uniquely suited.
At the same time, adoption of the
requirement that transmission
congestion be ‘‘significant’’
would limit the RTO from con-
sidering a number of cases.
Further, RTOs’ economic analysis
of potential changes to the grid in
an RFP process should not pre-
clude consideration of options
that do not involve transmission
upgrades, but are sponsored by
market participants.
T he standards upon which an
RTO makes cost allocation
decisions should be made explicit
and included in filings with the
Commission. This reduces the
discretion of an RTO. Alterna-
tively, costs should be collected,
to the maximum extent possible,
pursuant to agreements among
affected parties. This approach
both follows the Commission’s
policy of looking to funding by
participants, and recognizes pos-
sible limitations on an RTO’s
authority to impose cost collec-
tion. Instead of simply directing a
transmission owner to undertake
a transmission upgrade on the
RTO’s own authority, RTOs
should make the creation of an
effective means of realizing the
value of the upgrade a priority.
Finally, absent an effective means
of realizing the benefits of trans-
mission upgrades, RTOs seeking
to secure an expansion of the
transmission grid to address
economic needs should request
approval from the Commission of
mandated transmission
upgrades.
W hile references to
‘‘seams’’ often refer to
differences in transaction-related
market rules where conflicting
rules burden the development of
a regional market, the absence of
region-wide transmission plan-
ning is another form of a seam.
The lack of consistent transmis-
sion planning rules across the
Northeast’s RTOs will bias mar-
ket participants’ choice of loca-
tions for new plants and may
retard development of a single
large market. Moreover, signifi-
cant differences in the way RTOs
address transmission planning
may result in decisions by market
participants to switch from one
RTO to another. This ‘‘transmis-
sion planning seam’’ should be
eliminated as soon as possible.
The development of rules specific
to each RTO simply perpetuate
unnecessarily a ‘‘seam’’ among
the three Northeastern RTOs.&
Endnotes:
1. Remedying Undue Discriminationthrough Open Access Transmission Ser-vice and Standard Electricity Market De-sign, Notice of Proposed Rulemaking,RM01-12-000 (SMD NOPR), at para.191–195 (July 31, 2002). On April 28,2003, the Commission issued a WhitePaper on a Wholesale Power MarketPlatform in Docket No. RM01-12-000,which identifies modifications to themarket design announced in the SMDNOPR (White Paper).
2. SMD NOPR, supra note 1, at 335;Leonard Hyman, The Next Big Crunch:T&D Capital Expenditures, POWER DAILY
N. AM., March 12, 2003, at 1.
3. PJM Interconnection, LLC (PJM);ISO New England Inc. (ISO-NE); andNew York Independent System Op-erator, Inc. (NYISO). The term regionaltransmission organization (RTO) isused in this article to describe all threecontrol area operators.
4. PJM Operating Agreement, Sche-dule 6, § 1.4(a).
5. PJM Interconnection, LLC, 96 FERC �61,061 (2001) (July 2001 Order).
6. July 2001 Order, at 61,240.
7. PJM Interconnection, LLC, 101 FERC� 61,345 (2002), at para. 24.
8. PJM Operating Agreement, Sche-dule 6, §§ 1.5.6(e) and 1.5.6(f) (asmodified by PJM’s March 2003 Com-pliance Filing) (Compliance Filing).PJM’s modified transmission planningprovisions are currently before theCommission but at the time of publi-cation of this article, the Commissionhas not accepted or otherwise acted onPJM’s proposal.
9. PJM proposes that it identifytransmission upgrades to addresscongestion only in cases in whichcongestion is ‘‘unhedgeable.’’ The term‘‘unhedgeable congestion,’’ however,is not defined in the Compliance Filingand there is considerable uncertaintyas to its meaning.
10. Compliance Filing letter, at 4. PJMargued in its comments on SMD NOPRthat solicitation of proposals would notprovide timely solutions to existingviolations of baseline reliability criteria.
72 # 2003, Elsevier Inc., 1040-6190/$ – see front matter doi:10.1016/S1040-6190(03)00094-0 The Electricity Journal
SMD NOPR, PJM’s Additional Com-ments, at 12–14 (Jan. 10, 2003).
11. PJM Operating Agreement, pro-posed Schedule 6, § 1.5.6(g). The costof transmission upgrades caused bynew interconnections are borne by theparties requesting interconnection, tothe extent that such costs would nothave been incurred under the RTEP.PJM’s OATT § 37.2.
12. PJM Operating Agreement, pro-posed Schedule 6, § 1.5.6(g).
13. ISO New England, Inc., 91 FERC �61,311 (2000); ISO New England, Inc., 95FERC � 61,384 (2001) (June 2001 Order);ISO New England, Inc., 98 FERC � 61,173(2002) (February 2002 Order); ISO NewEngland Inc., 100 FERC � 61,029 (2002)(July 2002 Order); New England PowerPool, 100 FERC � 61,287 (2002) (Sep-tember 2002 Order); New England PowerPool, 101 FERC � 61,344 (2002) (De-cember 2002 Order); and New EnglandPower Pool, 102 FERC � 61,112 (2003).
14. February 2002 Order, at para. 1,and ordering provision ‘‘A.’’
15. NEPOOL OATT, § 51.6(a).
16. Id.
17. NEPOOL OATT, §§ 51.6(e) and51.7.
18. July 2002 Order, at para. 8.
19. The September 2002 Order, atpara. 144.
20. December 2002 Order, at para. 51.
21. The NYISO does conduct areatransmission reliability assessments inaccord with the procedures of theregional reliability council.
22. The NYISO appears to be pre-cluded from directing a transmissionowner to construct new facilities or tomodify existing facilities pursuant toSection 18.01 of the NYISO Agreement.A transmission owner may be requiredto construct transmission facilities inconnection with new interconnections,provided that such transmission owneris compensated in rates. NYISO OATT,Attachment S, Second Revised SheetNo. 663.
23. Joint Petition for Declaratory Or-der Regarding the Creation of aNortheastern Regional TransmissionOrganization, filed Aug. 23, 2002, in
Docket No. RT02-3-000. The JointPetition was withdrawn three monthslater in the face of stakeholder oppo-sition. In the case of transmissionupgrades required because of newinterconnections, however, New Yorkhas adopted a process to allocate costsamong sponsors of new projects andthe transmission owner. This costallocation approach is subject to acomplaint before the Commission.Docket No. EL02-125-000.
24. SMD NOPR, NYISO’s AdditionalComments, at 4 (Jan. 10, 2003).
25. SMD NOPR at para. 347–348. Inaddition, if an entity proposing aproject is willing to assume the marketand regulatory risk, it should be free toundertake the project.
26. PJM has reported informally thatits standard is intended to apply to allelectrical demand that does not havedirect access to inexpensive energy,either locally or at a distance coupledwith existing hedges. William W.Hogan, Transmission Market Design,April 2003, at 21, available at http://ksgwww.harvard.edu/hepg/in-dex.html.
27. PJM Operating Agreement, §1.5.6(d) (as set forth in the pendingCompliance Filing).
28. National Transmission Grid Study,U.S. Dept. of Energy, May 2002, at 51–52.
29. NEPOOL OATT, § 51.6; New York,as noted above, does not have acomparable transmission planningprotocol.
30. PJM Operating Agreement, §1.5.6(g); pending Compliance Filingletter, 12. PJM transmission ownersfiled changes to PJM’s Schedule 12providing for collection of the costof economic transmission upgrades.Filing Letter, Docket No. ER03-738-000(April 11, 2003) 103 FERC � 61,3192003.
31. PJM Operating Agreement, §1.5.6(g); and see proposed Schedule 12,which provides for the allocation ofthe cost of a transmission enhancementor expansion among responsible cus-tomers.
32. See Note 22.
33. PJM Operating Agreement, Sche-dule 6, § 1.7 (as modified in itspending Compliance Filing).
34. ‘‘Application for Rehearing andRequest for Clarification of the NewYork Transmission Owners,’’ PJM In-terconnection, LLC, RT01-2-005 (Jan. 21,2003). The owners contend that theCommission’s (and by extension anRTO’s) authority to mandate con-struction under Sections 210 and 211Federal Power Act is limited. Othershave argued that the Commission maynot direct the construction of newtransmission facilities without makingcase specific findings, and that theCommission is not authorized tomandate construction of economictransmission upgrades on the basis ofremedying undue discrimination assuch upgrades do not appear likely toaddress discrimination. The Commis-sion has not ruled on the application.
35. 329 F.3rd 856 (D.C. Cir. 2003).
36. SMD NOPR, NYPSC’s AdditionalComments, Jan. 31, 2003, at 7–12.
37. See, for example, Energy SecurityAnalysis, Inc., Occasional Memo(March 27, 2003), in which there is adiscussion of a ‘‘locational capacityreduction payment right’’ as a meansto accelerate the development of mer-chant AC transmission projects.
38. The existing approach to fundingtransmission upgrades in PJM and theNYISO, the award of transmissioncongestion revenues to the party re-sponsible for an expansion project, doesnot appear to create sufficient incentiveto encourage such construction.
August/September 2003 # 2003, Elsevier Inc., 1040-6190/$–see front matter doi:10.1016/S1040-6190(03)00094-0 73