Getting Certified In Consultant Selection Steps and Processes Diana Foster.
Transcript of Getting Certified In Consultant Selection Steps and Processes Diana Foster.
Getting Certified In Consultant Selection
Steps and Processes
Diana Foster
Where we are going…
What are the differences between A&E and Non-A&E consultant selection?
What are the 14 steps to selecting A&E consultants?
What other facts or stories that you need to know about?
Differences: A&E vs. Non-A&E
A&E Non-A&E
Selection Process
Qualification Based Selection (QBS)
Cost can be Weighted in Qualifications
Details
Independent evaluator(s) ranks & scores consultants according to qualifications matching the RFP
The top ranked consultant shall be selected to begin negotiations
Pricing can only be addressed after selection has occurred
Independent evaluator(s) ranks & scores consultants according to qualifications matching the RFP- cost can be a criterion
Top ranked consultant shall be selected to begin negotiations
Describe weighted importance of cost & other qualifications
ExamplesA&E Non-A&E
Drafting support Preparation of Right of Way
maps Work zone traffic control
plans Determine & evaluation site
geology Construction inspection Project design Aerial mapping control &
cert.
Accounting Auditing Counseling employees Fundraising Lobbying Policy development Air quality& noise studies Plan control of solid &
hazardous waste Public meetings
** The LAG Manual Consultant Selection Chapter (Appendix) provides more examples.
The 14 Step Selection Process: Steps 1-4
1. Identify & Define the Project■ STIP requirement
2. Determine Consultant Need & Project Phases■ LA’s QBS process■ ODOT’s two-tiered contracting process
3. Appoint Contract Administrator ■ Ensures contract completion, accuracy &
consistency ■ Appropriate Record Retention
Steps 4-6:
4. Create Scope – determine deliverables & timelines
■ SOW5. Prepare Cost Estimate
■ Past experiences■ Percent of cost of service relative to other similar
total project costs6. Formulate Selection Criteria
■ Ranking and scoring■ Transparency of criteria weights■ Specialties & resources
Steps 7-8:
7. Identify DBE Program & Goals■ ODOT’s Office of Civil Rights ■ Seek approval
8. Advertise & Solicit Bids for the RFP Major newspaper or technical publication Identify specialists Questions answered in writing or addendum up to a
week before closing Cost Estimates
A&E- at time of negotiations to determine fair & reasonable cost
Non-A&E personal services- estimate of hours, fees and classifications
Steps 9-11:
9. RFP Protest Procedures
10. Closing the Solicitation Process Evaluation of proposals-- Pass/Fail Evaluation Panel
11. Screening & Selection Interviews Transparency Fair and equitable No conflicts of interest
Steps 12-14:12. Consultant Selection & Negotiation
Highest rank Negotiate on SOW & Compensation Refine scope of services and schedule Unable to negotiate -- move down qualification list
successively 13. Award
Written notice14. Contract Administration
Oversight of daily work Consultant submits invoices to LA for review LA remits payment LA requests ODOT reimbursement
Completed Project Debrief
Ensure contract compliance & completion of work
Final payment & release Evaluate performance and document
Tidbits of Information
Importance of Agreement Clearly defined scope & statement of work Billing rates & classifications Independent contractor status &
relationships
Questions???