Geotechnical Report Site Investigation and Design … · 2018-09-24 · SITE INVESTIGATION REPORT...
Transcript of Geotechnical Report Site Investigation and Design … · 2018-09-24 · SITE INVESTIGATION REPORT...
Geotechnical Report
Site Investigation and Design Recommendations
Ottawa Community Housing Project
3225 Uplands Drive Prepared for:
Atelier 292 Architect Inc.
292 Main Street
Ottawa, Ontario
K1S 1E1
Prepared by:
McIntosh Perry Consulting Engineers Ltd.
115 Walgreen Road
Carp, ON
K0A 1L0
June, 2017-Revised
CP-16-0469
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
i
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................................................. 1
2.0 SITE DESCRIPTION ............................................................................................................................. 1
3.0 FIELD PROCEDURES ........................................................................................................................... 1
4.0 LABORATORY TEST PROCEDURES ....................................................................................................... 2
5.0 SITE GEOLOGY AND SUBSURFACE CONDITIONS ................................................................................. 2
5.1 Site Geology ............................................................................................................................................................ 2
5.2 Subsurface Conditions ............................................................................................................................................ 2
5.2.1 Fill .................................................................................................................................................................... 2
5.2.2 Limestone Bedrock .......................................................................................................................................... 3
5.3 Groundwater ........................................................................................................................................................... 3
5.4 Chemical Analysis .................................................................................................................................................... 3
6.0 DISCUSSION AND RECOMMENDATIONS ............................................................................................ 4
6.1 General .................................................................................................................................................................... 4
6.1.1 Proposed Building ........................................................................................................................................... 4
6.2 Foundations ............................................................................................................................................................ 4
6.2.1 Strip or Spread Footings .................................................................................................................................. 5
6.2.2 Lateral earth Pressure ..................................................................................................................................... 5
6.2.3 Slab-on-Grade ................................................................................................................................................. 5
6.3 Rock Excavation ...................................................................................................................................................... 6
6.4 Frost Protection ...................................................................................................................................................... 6
6.5 Site Classification for Seismic Site Response .......................................................................................................... 6
6.6 Dewatering .............................................................................................................................................................. 7
6.7 Corrosion Potential and Cement Type .................................................................................................................... 7
6.8 Site Services ............................................................................................................................................................ 7
6.9 Pavement Structure ................................................................................................................................................ 7
7.0 CLOSURE ........................................................................................................................................... 8
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
ii
LIST OF TABLES
Table 5-1: Compressive Strength Test .................................................................................................................................... 3
Table 5-2: Soil Chemical Analysis Results ................................................................................................................................ 3
Table 6-1: Backfill Material Properties .................................................................................................................................... 5
Table 6-2: Proposed Pavement Structure ............................................................................................................................... 7
APPENDICES
APPENDIX A Limitations of Report
APPENDIX B Figures
APPENDIX C Borehole Records
APPENDIX D Laboratory Test Results
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
1
SITE INVESTIGATION REPORT AND
FOUNDAITON DESIGN RECOMMENDATIONS
for
Atelier 292 Architect Inc.
3225 Uplands Drive, Ottawa, Ontario
1.0 INTRODUCTION
This report presents the factual findings obtained from a geotechnical investigation performed at the above
mentioned site, for the proposed townhouses in Ottawa, Ontario. The field work was carried out on October 7,
2016 and comprised of three boreholes advanced to a maximum depth of 4.4 m below existing ground surface.
The purpose of the investigation was to explore the subsurface conditions at this site and to provide anticipated
geotechnical conditions influencing the design and construction of the proposed buildings.
McIntosh Perry Consulting Engineers Ltd (McIntosh Perry) carried out the investigation at the request of
Atelier 292 Architect Inc..
2.0 SITE DESCRIPTION
The site for the proposed buildings is located on Uplands Drive, in Ottawa. The property contains a housing
development, the area under consideration for development is a portion of land along the south section of the
property bordered on Uplands Drive. The topography of the site was observed to be sloped up from the road and
then plateauing. The site is located on a residential road, bordered by apartment and townhouse developments.
The property is covered with grass and occasional trees and bushes. Occasional cobble and boulder size rock were
also observed at the surface. The location of the site is shown on Figure 1 included in Appendix B. The proposed
building location is shown on Figure 2 included in Appendix B, it is understood that the proposed construction will
include seven townhomes and three triplexes.
3.0 FIELD PROCEDURES
Public utility clearance was carried out by USL-1 on behalf of McIntosh Perry. Public and private utility
authorities were informed and all utility clearance documents were obtained before the commencement of
drilling work.
The equipment used for drilling was owned and operated by CCC Geotechnical and Enviromental Drilling of
Ottawa, Ontario. Three boreholes were advanced at this site using a truck-mounted CME 45B drilling rig.
Boreholes were advanced using hollow stem auger. Samples were taken at 0.75 m interval, using a 51 mm
O.D. split spoon sampler in accordance with Standard Penetration Test (SPT) procedures, until refusal.
Boreholes were advanced beyond refusal into bedrock using by core barrel with diamond drill bit and the
cores were retrieved by wireline tool. Borehole locations are shown on Figure 2 included in Appendix B.
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
2
4.0 LABORATORY TEST PROCEDURES
Compressive strength test in accordance with ASTM-D7012 Method C was performed on selected segments
of the rock core samples. AME laboratories in Ottawa, Ontario performed the compressive strength test, on
behalf of McIntosh Perry. Test results provided by AME laboratory are included in Appendix D.
Paracel Laboratories Ltd., in Ottawa carried out chemical tests on one representative soil sample to
determine the soil corrosivity characteristics.
The rest of the soil and rock samples will be stored in McIntosh Perry storage facility for a period of one
month after submission of the final report. Samples will be disposed after this period of time unless
otherwise requested in writing by the owner or its representatives.
5.0 SITE GEOLOGY AND SUBSURFACE CONDITIONS
5.1 Site Geology
Based on published maps of the area (Ontario Geological Survey), the site is located within the Physiographic
Region of Russell and Prescott Sand Plains. The Russell and Prescott Sand Plains extend to the south of the
Ottawa Valley Clay Plains, from Ottawa to Hawkesbury. The surface elevations are approximately 15 m higher
than those found within the lower lying clay plains to the north. The sand plains were deposited by the
Ottawa River and its north-bank tributaries into the Champlain Sea. Some sand and gravel deposits south of
Ottawa are of glaciofluvial origin.
Surficial geology maps of the area also indicate existence of the property is on Paleozoic bedrock, bordered
closely by till and coarse-textured glaciomarine deposits.
5.2 Subsurface Conditions
In general, the site stratigraphy within the proposed building footprints consisted of fill material overtop
Limestone Bedrock.
a) Fill
b) Limestone Bedrock
The soils encountered during the course of the investigation, together with the field and laboratory test
results are shown on the Record of Borehole sheets included in the Appendix C. Laboratory test results are
provided in Appendix D. Descriptions of the strata encountered are given below.
5.2.1 Fill
A layer of loose to compact fill was encountered in all boreholes. The fill consisted of a thin topsoil layer, with
combination of sand with depth. The fill contained occasional cobbles and boulders, and was found to be brown
and dry. The fill layer was found to range in thickness from 0.8 m to 1.1 m, with SPT ‘N’ values ranging from 8 to 11
blows/300 mm.
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
3
5.2.2 Limestone Bedrock
Boreholes were advanced beyond SPT and auger refusal to retrieve bedrock samples. The cores were
measured and logged both on site and in the office, and were observed to be medium to dark grey Limestone
from the Bobcaygon Formation, slightly weathered to fresh with fractures along roughly undulating shaly
partings. The bedrock elevation varied between El. 98.5 and El. 100.2.
The RQD measured within the limestone section of the retrieved rock cores varied largely and were observed
to increase with depth. Lower RQD values between 0% and 54% were found within the first 1.0 m to 1.2 m of
the rock surface, transitioning between elevations of El. 97.5 m and 99.0 m. Below the more fractured
weathered surface of the rock, the RQD values range between 76% and 100%. Based on the RQD values, the
limestone of the bedrock may be classified as poor to good quality. The majority of the fractures were
observed at the shale beddings.
Selected rock core samples were tested in the laboratory to determine the uniaxial compressive strength.
The results show an average compressive strength of 84.0 MPa. The results of rock core samples are included
in Table 5.1 below.
Table 5-1: Compressive Strength Test
Borehole Run No L/D Ratio Unit Mass
(kg/m3)
Strength
(MPa)
BH16-1 4 2.14:1 2,714 147.7
BH16-2 5 2.21:1 2,635 46.6
BH16-3 5 2.12:1 2,656 57.8
5.3 Groundwater
The core water from each borehole was purged in an attempt to measure the ground water table. The
ground water was observed between 3.01 m and 3.94 m below the ground surface, at an average elevation of
El. 96.9 m. Groundwater level may be expected to fluctuate due to the influence of seasonal changes.
5.4 Chemical Analysis
The chemical test results conducted by Paracel Laboratories in Ottawa, Ontario, to determine the resistivity,
pH, sulphate and chloride content of a representative soil sample. These results are shown in Table 5-2
below:
Table 5-2: Soil Chemical Analysis Results
Borehole Sample Depth pH Sulphate
(%)
Chloride
(%)
Resistivity
(Ohm-cm)
BH16-2 SS-1 0.0 – 0.6 7.69 0.0049 0.0010 1,800
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
4
6.0 DISCUSSION AND RECOMMENDATIONS
6.1 General
This section of the report provides recommendations for the design of the proposed buildings to be
constructed at 3225 Uplands Drive in Ottawa, Ontario. The recommendations are based on interpretation of
factual information obtained from the boreholes advanced during the subsurface investigation. The
discussions and recommendations presented are intended to provide sufficient information to the designer
of the proposed building to select the suitable type(s) of foundation to support the structure.
The comments made on the construction are intended to highlight those aspects which could have impact or
affect the detail design of the building, for which special provisions may be required in the Contract
Documents. Those requiring information on construction aspects should make their own interpretation of
the factual data presented in the report. Interpretation of the data presented may affect equipment
selection, proposed construction methods, and scheduling of construction activities.
6.1.1 Proposed Building
It is understood the proposed construction will include four independent structures. On the west side of the
access road, is planned to be a row house containing seven homes, and on the east side of the access road
three triplex units. It is understood all of these structures will be two story buildings with a basement.
At present there is still no definitive information on the proposed elevation of the finished floor nor the
basement level. Therefore the foundation engineering recommendations were developed supposing the
founding level will be 1.8 m or lower below the average elevation of the west and east side of the property,
approximately El. 97.8 m or lower for the west side (row houses) and El. 99.2 m or lower for the east side
(triplexes). It is expected to receive finalized site grading and architectural plans before issuing the final
report, unless the present recommendations are deemed adequate.
6.2 Foundations
The subsurface conditions at this site consist of 0.8 m to 1.1 m of fill underlain by bedrock, at an elevation
ranging from El. 98.5 to El. 100.2. The bedrock encountered at this location is intensely fractured and very
poor quality to about El. 97.5 to El. 99.0, from west to east. The groundwater level was observed within the
bedrock at an average elevation of El. 96.9.
Considering the quality of bedrock at the founding level, the excavation should be extended just below El.
97.2 (west) to El. 98.7 (east), and covered with a layer of concrete as soon as practically possible. This will
prevent degradation of the bedrock surface upon exposure. All loose pieces of bedrock shall be removed
before placing the protective concrete slab. 75 mm of concrete is required underneath the footings. The
compressive strength of the concrete shall not be less than the bearing capacity which was used for structural
design or it should be equal to the compressive strength of proposed footings. This requirement may be
addressed with a note on the structural drawing for foundation and/or with a Non Standard Special Provision
(NSSP).
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
5
6.2.1 Strip or Spread Footings
Considering the order of load expected at the foundation level and the bedrock conditions at this site, it is
considered that provision of a conventional strip or spread footings will be adequate to support the proposed
structure. It is recommended that the footings for the structure placed below El. 97.2 m (west) and El. 98.7 m
(east) on limestone bedrock or on a concrete working to be designed using a geotechnical resistance of 750
kPa at Ultimate Limit State (ULS). This bearing capacity value is estimated based on minimum RQD of 75%.
Serviceability Limit State is not required for the expected structural loads. Settlements are expected to be
sub-millimeter for a conventional wood-frame residential building.
The compact to loose fill overburden does not provide a suitable bearing surface. It is important to install all
footings on similar bearing surface (bedrock) to avoid differential settlements.
Geotechnical resistance or the bearing pressure at SLS will not govern because of the bedrock at the founding
elevation and the load expected from the proposed structure at the footing level. The load required to
produce detrimental settlement of the structure will be much larger than the recommended value for
factored geotechnical resistance at ULS.
Strip footings shall not be narrower than 0.6 m in width.
All foundation walls shall be backfilled with free draining material conforming to OPSS Granular criteria.
Weeping tiles shall be installed around the foundation perimeter and at the subgrade level. These drainage
pipes shall provide positive flow to the existing storm services.
6.2.2 Lateral earth Pressure
Free draining material should be used as backfill for foundation walls. If proper drainage is provided “at rest”
condition may be assumed for calculation of earth pressure on foundation walls. Where clear stone is used
around the drainage or storm sewer, especially below the groundwater level, it should be surrounded by
suitable filter cloth or geotextile to eliminate migration of soil into the open voids of the stone. Migration of
soil, would likely result in surface settlement. The following parameters are recommended for the granular
backfill.
Table 6-1: Backfill Material Properties
Borehole Granular “A” Granular “B”
Effective Internal Friction Angle, �� 35° 30°
Unit Weight, ���� �⁄ � 22.8 22.8
Existing fill material is not considered suitable for foundation backfill.
6.2.3 Slab-on-Grade
Conventional slab-on-grade elements are suitable to be used for the basement floor. For basement floor
slabs, a layer of OPSS Granular A, compacted to minimum 100% SPMDD, with minimum thickness of 150 mm,
should be placed directly below the slab-on-grade. The elevation difference between the founding level (or
bottom of excavation) and the underside of the Granular A shall be backfilled with OPSS Granular B Type II or
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
6
Granular A, compacted to minimum 100% SPMDD, extending up to 500 mm below the slab. Any grade raise
required at elevations lower than 500 mm below the slab, OPSS granular material shall be compacted to
minimum 95% SPMDD.
All slab-on-grade units shall float independently from all load-bearing structural elements.
It is recommended to install a layer of vapor barrier below all slab-on-grade. All slab-on-grade units shall float
independently from all load-bearing structural elements.
6.3 Rock Excavation
The footings for the proposed structure are expected to be constructed on the limestone bedrock between
El. 97.2 (west) to El. 98.7 (east). Considering the quality of the bedrock to the founding level, rock excavation
may be conducted through line drilling in conjunction with hoe-ramming. Controlled blasting is not
recommended for this building due to close proximity of the proposed and existing structures to the area of
excavation.
In case any blasting is employed for rock excavation, the peak particle velocity during blasting shall be limited
to 50 mm per second to avoid any damage to the adjoining structures and it should be limited to 10 mm per
second to prevent any discomfort to residents. If blasting is selected as excavation method, a licenced
structural engineer shall confirm the excavation method will not damage the nearby structure. Adjacent
structures shall be protected by designing appropriate supporting system In case the excavation extends to
the proximity of those structures.
The excavation for the foundation of the buildings will be advanced through fill consisting of topsoil, sand
with occasional cobbles and boulders. The overburden excavation should be completed in accordance with
Ontario Regulation (O.Reg.) 213/91 under the Occupational Health and Safety Act (OHSA) with specific
reference to acceptable size slopes and stabilization requirements. The general stratigraphy outlined
herein fall into an OHSA Type 3 soil. For excavations through multiple soil types, the side slope geometry is
governed by the soil with the highest number designation.
6.4 Frost Protection
In accordance with OPSD 3090.101, a minimum of 1.8 m earth cover is required to protect against the frost
penetration in the area where the site is located. The frost penetration depth is measured from the top of
the earth cover to the bottom of footings.
6.5 Site Classification for Seismic Site Response
The site can be classified as a Site Class “C” for the purposes of site-specific seismic response to earthquakes
based on Table 4.1.8.4.A OBC 2012.
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
7
6.6 Dewatering
Groundwater was observed to vary from a depth of 3.94 m to 3.01 m (El. 97.1 m to 96.5 m) below the existing
ground surface. The excavation for the structure foundation is not expected to extend below El. 97.2 m. In
the event the excavation is extended below expected water table, the amount of groundwater discharge into
the excavation may be substantial due to existing rock fractures.
6.7 Corrosion Potential and Cement Type
It is expected that footing installation will be on concrete protection slab placed on bedrock, no sulphate
attack is expected from limestone bedrock; General Use (Type GU) Portland cement will be adequate. Based
on the measured soil electrical resistivity and pH, a non-aggressive corrosive environment is expected for
buried steel elements in contact with native soil.
6.8 Site Services
The burial depth of water-bearing utility lines is typically 2.4 m below ground surface in Ottawa. If this depth
is not achievable due to design restrictions, equivalent thermal insulation should be provided.
The contractor should retain a professional engineer to provide detailed drawings for excavation and
temporary support of the excavation walls during construction.
Utilities should be supported on minimum of 150 mm bedding of Granular A compacted to minimum 95% of
standard Proctor maximum dry density (SPMDD). Since the native subgrade is fine grained, it is
recommended to separate the subgrade from the bedding material by a layer of geotextile to prevent cross
migration of materials. Utility cover can be Granular A or Granular B type II compacted to 95% SPMDD. All
covers to be compacted to 100% SPMDD if intersecting structural elements.
6.9 Pavement Structure
No traffic information has been provided to McIntosh Perry. It is understood as part of this construction, 7
additional parking spots will be added. The pavement structure most likely to be placed on existing sandy
material overlaying bedrock. The topsoil and any soft materials should be removed and the remainder of the
existing fill should be proof rolled under the supervision of a geotechnical engineer. Should grade raise be
required, compacted Granular B Type II or Granular A should be placed as needed and compacted to 98%
SPMDD prior to construction of pavement structure. The proposed pavement structure is included in Table
6-2.
Table 6-2: Proposed Pavement Structure
Material Thickness
(mm)
Surface Superpave 12.5 mm, Design Category B (or HL 3), PG 58-34 50
Base OPSS Granular A 150
Sub-base OPSS Granular B Type II 350
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
8
Both base and sub-base should be compacted to 100% standard Proctor maximum dry density (SPMDD).
Existing sandy material is not suitable to be used for pavement structure. Asphalt layers should be
compacted to comply with OPSS 310.
7.0 CLOSURE
We trust this report satisfies requirements of your project and provides adequate information for the defined
scope of work. Field investigations are conducted through limited subsurface sampling. A geotechnical
representative shall review the construction process. During the construction, in case of encountering any
site condition different from what predicted in this report, authors shall be immediately notified to evaluate
the situation. The “Limitations of Report” presented in Appendix A are an integral part of this report. Please
contact the undersigned should you have any questions or concerns.
McIntosh Perry Consulting Engineers Ltd.
Mary-Ellen Gleeson, M.Eng., EIT.
Geotechnical Engineering Intern
N’eem Tavakkoli, M.Eng., P.Eng.
Senior Geotechnical Engineer
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
9
REFERENCES
1) Canadian Geotechnical Society, “Canadian Foundation Engineering Manual”, 4th
Edition, 2006.
2) Ontario Ministry of Natural Resources (OMNR), Ontario Geological Survey, Special Volume 2, “The Physiography
of Southern Ontario”, 3rd
Edition, 1984.
3) Google Earth, Google, 2015.
4) Government of Canada, National Building Code of Canada (NBCC), “Seismic Hazard Calculation” (online), 2010.
5) Canadian Standards Association (CSA), “Concrete Materials and Methods of Concrete Construction”, A23.1, 2009
6) Government of Ontario, “Ontario Building Code (OBC),” (online), 2012.
7) MTO – Pavement Design and Rehabilitation Manual
8) Natural Resources Canada – Seismic Hazard Calculator
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
McIntosh Perry Consulting Engineers Ltd.
115 Walgreen Road, R.R. 3
Carp, ON K0A 1L0
Appendix A
Limitations of Report
McIntosh Perry Consulting Engineers Ltd.
115 Walgreen Road, R.R.3
Carp, ON K0A 1L0
McIntosh Perry Consulting Engineers Ltd. (MPCE) carried out the field work and prepared the report. This document is
an integral part of the Foundation Investigation and Design report presented.
The conclusions and recommendations provided in this report are based on the information obtained at the borehole
locations where the tests were conducted. Subsurface and groundwater conditions between and beyond the boreholes
may differ from those encountered at the specific locations where tests were conducted and conditions may become
apparent during construction, which were not detected and could not be anticipated at the time of the site
investigation. The benchmark level used and borehole elevations presented in this report are primarily to establish
relative differences in elevations between the borehole locations and should not be used for other purposes such as to
establish elevations for grading, depth of excavations or for planning construction.
The recommendations presented in this report for design are applicable only to the intended structure and the project
described in the scope of the work, and if constructed in accordance with the details outlined in the report. Unless
otherwise noted, the information contained in this report does not reflect on any environmental aspects of either the
site or the subsurface conditions.
The comments or recommendation provided in this report on potential construction problems and possible construction
methods are intended only to guide the designer. The number of boreholes advanced at this site may not be sufficient
or adequate to reveal all the subsurface information or factors that may affect the method and cost of construction. The
contractors who are undertaking the construction shall make their own interpretation of the factual data presented in
this report and make their conclusions, as to how the subsurface conditions of the site may affect their construction
work.
The boundaries between soil strata presented in the report are based on information obtained at the borehole
locations. The boundaries of the soil strata between borehole locations are assumed from geological evidences. If
differing site conditions are encountered, or if the Client becomes aware of any additional information that differs from
or is relevant to the MPCE findings, the Client agrees to immediately advise MPCE so that the conclusions presented in
this report may be re-evaluated.
Under no circumstances shall the liability of MPCE for any claim in contract or in tort, related to the services provided
and/or the content and recommendations in this report, exceed the extent that such liability is covered by such
professional liability insurance from time to time in effect including the deductible therein, and which is available to
indemnify MPCE. Such errors and omissions policies are available for inspection by the Client at all times upon request,
and if the Client desires to obtain further insurance to protect it against any risks beyond the coverage provided by such
policies, MPCE will co-operate with the Client to obtain such insurance.
MPCE prepared this report for the exclusive use of the Client. Any use which a third party makes of this report, or any
reliance on or decision to be made based on it, are the responsibility of such third parties. MPCE accepts no
responsibility and will not be liable for damages, if any, suffered by any third party as a result of decisions made or
actions taken based on this report.
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
McIntosh Perry Consulting Engineers Ltd.
115 Walgreen Road, R.R. 3
Carp, ON K0A 1L0
Appendix B
Figures
NepeanCreek
Rideau River
Kilborn Avenue
Hunt Club Road
Merivale Road
Heron Road
McCarthy Road
Bank Street
Baseline Road BrookfieldRoad
Hogs Back Road Walkley Road
Bronson Avenue
Albion Road
West Hunt Club Road
Viewmount D rive
Meadowlan
ds Drive
Daze
Street
Ryder
Street
River
Road
MeadowlandsDrive East
Limebank Road
Leitrim Road
Alta VistaDriv e
PrinceOf Wales Drive
Rive
rside
Drive
Colon
el By D
rive
Airport Parkway
Featherston Drive
LEGEND
³
GEOTECHNICAL INVESTIGATION3225 UPLANDS DR., OTTAWA, ON
SITE LOCATION
1FIGURE:
ATELIER 292 ARCHITECT INC.
Nov. 1, 2016JDMG
CP-16-0469
TITLE:
CLIENT:
PROJECT NO:
PROJECT:
DateGISChecked By115 Walgreen Rd., RR#3, Carp, ON K0A1L0
Tel: 613-836-2184 Fax: 613-836-3742H:\01
Proj
ect -
Prop
osals
\2016
Jobs
\CP\
0CP-
16-04
69 At
elier
292 A
rchite
ct Inc
., Tow
nhou
ses &
Apart
ments
, 322
5 Upla
nds (
Ottaw
a)\GI
S\mx
d\CP-
16-04
69_G
eotec
hnica
l_01_
SiteL
ocati
on32
25Up
lands
.mxd
REFERENCE
PropertyLocal RoadMajor RoadWooded Area
WatercourseWaterbodyUnevaluated WetlandProvincially Significant Wetland
GIS data provided by the Ontario Ministry of Natural Resources, 2016.
Site Location
Metres
1,500 0 1,500750
Scale 1:40,000
LEGEND
³
BOREHOLE LOCATIONS
2FIGURE:
JD
TITLE:
CLIENT:
PROJECT NO:
PROJECT:
DateGISChecked By115 Walgreen Rd., RR#3, Carp, ON K0A1L0
Tel: 613-836-2184 Fax: 613-836-3742H:\01
Proj
ect -
Prop
osals
\2016
Jobs
\CP\
0CP-
16-04
69 At
elier
292 A
rchite
ct Inc
., Tow
nhou
ses &
Apart
ments
, 322
5 Upla
nds (
Ottaw
a)\GI
S\mx
d\CP-
16-04
69_G
eotec
hnica
l_02_
Boreh
oleLo
catio
ns32
25Up
lands
.mxd
REFERENCE
@A Borehole LocationApproximate Area of InvestigationApproximate Outline of Proposed Townhome/Triplex
GIS data provided by the Ontario Ministry of Natural Resources, 2016.MG
GEOTECHNICAL INVESTIGATION3225 UPLANDS DR., OTTAWA, ON
ATELIER 292 ARCHITECT INC.
Nov. 1, 2016CP-16-0469
Metres
20 0 2010
Scale 1:600
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
McIntosh Perry Consulting Engineers Ltd.
115 Walgreen Road, R.R. 3
Carp, ON K0A 1L0
Appendix C
Borehole Records
SS
SS
RC
RC
RC
RC
8
50/50mm
REC92%
REC75%
REC94%
REC100%
1
2
3
4
5
6
________________________________RQD = 42%________________________________
147.7 MPa
RQD = 54%
________________________________
RQD = 83%
_______________________________
RQD = 100%
1.1
4.3
FILL, topsoil, sand, occasional cobbles andboulders, loose, brown, dry
LIMESTONE BEDROCK light to mediumgrey, slight to not weathered, fractures roughlyundulating gnerally occurring at shaly partings
END OF BOREHOLE
98.5
95.3
ST
RA
T P
LOT
wP
LIQUIDLIMIT
McIntosh Perry Consulting Engineers Ltd1-1329 Gardiners RdKingston, Ontario K7P 0L8
METRIC
MG
MG
NT
kN/m3
SAMPLES
SI
UN
IT
WE
IGH
T REMARKS
&
GRAIN SIZE
DISTRIBUTION
(%)
SHEAR STRENGTH kPa
NATURALMOISTURECONTENT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
FIELD VANE
SA
RECORD OF BOREHOLE No 16-1
Numbers refer toSensitivity
25 50 75
"N"
VA
LUE
S(R
QD
)
20 40 60 80 100
, 3
PLASTICLIMIT
ELE
VA
TIO
N S
CA
LE
DATE
w
QUICK TRIAXIAL
UNCONFINED
ORIGINATED BY
COMPILED BY
CHECKED BY
1 OF 1
99.60.0
ELEVDEPTH
LAB VANE20 40 60 80 100
SOIL PROFILE
3%STRAIN AT FAILURE
CL
LOCATION
COORDINATE
DATUM
07/10/2016
CP-16-0469
Atelier 292 Architect Inc
99.6
ID
CLIENT
ELEVATION
GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
wL
WATER CONTENT (%)
GR
NU
MB
ER
TY
PE
:
DESCRIPTION
3225 Uplands Dr
Co-ord; 45.323691;-74.687398
Geodetic
3
99
98
97
96
MP
MT
O T
EM
PLA
TE
(U
SE
) U
PLA
ND
S D
R B
OR
EH
OLE
LO
GS
.GP
J D
UN
NIN
G R
OA
D C
ULV
ER
T.G
DT
11
/11/
16
SS
SS
RC
RC
RC
RC
10
50/100mm
REC65%
REC93%
REC100%
1
2
3
4
5
6
_______________________
RQD = 27%
_______________________
46.6 MPa
RQD = 76%
_______________________
RQD = 75%
1.1
4.2
FILL, topsoil, sand, occasional cobbles andboulders, loose, brown, dry
LIMESTONE BEDROCK light to mediumgrey, slight to not weathered, fractures roughlyundulating gnerally occurring at shaly partings
END OF BOREHOLE
98.9
95.8
ST
RA
T P
LOT
wP
LIQUIDLIMIT
McIntosh Perry Consulting Engineers Ltd1-1329 Gardiners RdKingston, Ontario K7P 0L8
METRIC
MG
MG
NT
kN/m3
SAMPLES
SI
UN
IT
WE
IGH
T REMARKS
&
GRAIN SIZE
DISTRIBUTION
(%)
SHEAR STRENGTH kPa
NATURALMOISTURECONTENT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
FIELD VANE
SA
RECORD OF BOREHOLE No 16-2
Numbers refer toSensitivity
25 50 75
"N"
VA
LUE
S(R
QD
)
20 40 60 80 100
, 3
PLASTICLIMIT
ELE
VA
TIO
N S
CA
LE
DATE
w
QUICK TRIAXIAL
UNCONFINED
ORIGINATED BY
COMPILED BY
CHECKED BY
1 OF 1
100.00.0
ELEVDEPTH
LAB VANE20 40 60 80 100
SOIL PROFILE
3%STRAIN AT FAILURE
CL
LOCATION
COORDINATE
DATUM
07/10/2016
CP-16-0469
Atelier 292 Architect Inc
100
ID
CLIENT
ELEVATION
GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
wL
WATER CONTENT (%)
GR
NU
MB
ER
TY
PE
:
DESCRIPTION
3225 Uplands Dr
Co-ord; 45.323721;-74.687165
Geodetic
3
99
98
97
96
MP
MT
O T
EM
PLA
TE
(U
SE
) U
PLA
ND
S D
R B
OR
EH
OLE
LO
GS
.GP
J D
UN
NIN
G R
OA
D C
ULV
ER
T.G
DT
11
/11/
16
SS
SS
RC
RC
RC
RC
11
50/50mm
REC71%
REC33%
REC98%
REC94
1
2
3
4
5
6
________________________________
RQD = 0%
________________________________
RQD = 0%
________________________________
57.8 MPa
RQD = 96%
_______________________________
RQD = 90%
0.8
4.4
FILL, topsoil, sand, occasional cobbles andboulders, loose, brown, dry
LIMESTONE BEDROCK light to mediumgrey, slight to not weathered, fractures roughlyundulating gnerally occurring at shaly partings
END OF BOREHOLE
100.2
96.6
ST
RA
T P
LOT
wP
LIQUIDLIMIT
McIntosh Perry Consulting Engineers Ltd1-1329 Gardiners RdKingston, Ontario K7P 0L8
METRIC
MG
MG
NT
kN/m3
SAMPLES
SI
UN
IT
WE
IGH
T REMARKS
&
GRAIN SIZE
DISTRIBUTION
(%)
SHEAR STRENGTH kPa
NATURALMOISTURECONTENT
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
FIELD VANE
SA
RECORD OF BOREHOLE No 16-3
Numbers refer toSensitivity
25 50 75
"N"
VA
LUE
S(R
QD
)
20 40 60 80 100
, 3
PLASTICLIMIT
ELE
VA
TIO
N S
CA
LE
DATE
w
QUICK TRIAXIAL
UNCONFINED
ORIGINATED BY
COMPILED BY
CHECKED BY
1 OF 1
101.00.0
ELEVDEPTH
LAB VANE20 40 60 80 100
SOIL PROFILE
3%STRAIN AT FAILURE
CL
LOCATION
COORDINATE
DATUM
07/10/2016
CP-16-0469
Atelier 292 Architect Inc
101
ID
CLIENT
ELEVATION
GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
wL
WATER CONTENT (%)
GR
NU
MB
ER
TY
PE
:
DESCRIPTION
3225 Uplands Dr
Co-ord; 45.323825;-74.686471
Geodetic
3
100
99
98
97
MP
MT
O T
EM
PLA
TE
(U
SE
) U
PLA
ND
S D
R B
OR
EH
OLE
LO
GS
.GP
J D
UN
NIN
G R
OA
D C
ULV
ER
T.G
DT
11
/11/
16
ROCK CORE DESCRIPTION
Borehole ID: BH16-1
3225 Uplands Rd, CP-16-0469:
CORE RECOVERY CORE DESCRIPTION
RC No. DEPTH (m) % CR* % RQD** DEPTH (m) DESCRIPTION
3
1.11 – 1.22
92%
42%
1.11 – 4.27
LIMESTONE (Bobcaygeon Formation) – Light to medium grey
sublithographic to finely crystalline limestone. Bedding is chaotic with
stylolites and bioturbation. Fractures roughly undulating to smoothly
undulating generally occurring at shaly partings.
Slight weathering to 1.4 m, fresh below. Open fractures with silty clay
infilling at 1.73 m and between 3.53 m to 3.56m.
Vugs with calcite infilling between 1.83 – 2.08 m.
4
1.22 – 2.08
75%
54%
5
2.08 – 3.61
94%
83%
6
3.61 – 4.27
100%
100%
CR* - Core Recovery Logged by: D. Arnott, P.Eng
RQD** - Rock Quality Designation
Note: Depths are approximate where core recovery is less than 100%
ROCK CORE DESCRIPTION
Borehole ID: BH16-2
3225 Uplands Rd, CP-16-0469:
CORE RECOVERY CORE DESCRIPTION
RC No. DEPTH (m) % CR* % RQD** DEPTH (m) DESCRIPTION
4
1.14 – 2.08
65%
27%
1.14 – 4.16
LIMESTONE (Bobcaygeon Formation) – Light to medium grey
sublithographic to finely crystalline limestone with <1 cm thick shaly
partings. Chaotic bedding with stylolites and bioturbation. Fractures
roughly undulating generally occurring at shaly partings.
Slightly weathered to 1.5 m, fresh below.
Open fractures with silty clay infilling at 1.73 m and between 3.53 m to
3.56m.
5
2.08 – 3.61
93%
76%
6
3.61 – 4.16
100%
75%
CR* - Core Recovery Logged by: D. Arnott, P.Eng
RQD** - Rock Quality Designation
Note: Depths are approximate where core recovery is less than 100%
ROCK CORE DESCRIPTION
Borehole ID: BH16-3
3225 Uplands Rd, CP-16-0469:
CORE RECOVERY CORE DESCRIPTION
RC No. DEPTH (m) % CR* % RQD** DEPTH (m) DESCRIPTION
3
0.81 – 1.42
71%
0%
0.81 – 4.37
LIMESTONE (Bobcaygeon Formation) – Light to medium grey
sublithographic to finely crystalline limestone with <1cm thick shaly
partings. Bedding is chaotic with stylolites and bioturbation. Fractures
roughly undulating, generally occurring at shaly partings.
Slight weathering to 2.03 m, fresh below. Slight weathering at 3.73 m.
Vugs with calcite infilling between 2.03 – 2.59 m.
4
1.42 – 2.03
33%
0%
5
2.03 – 3.35
98%
96%
6
3.35 – 4.37
94%
90%
CR* - Core Recovery Logged by: D. Arnott, P.Eng
RQD** - Rock Quality Designation
Note: Depths are approximate where core recovery is less than 100%
3225 Uplands Drive, Ottawa, ON Geotechnical Report, CP-16-0469
McIntosh Perry Consulting Engineers Ltd.
115 Walgreen Road, R.R. 3
Carp, ON K0A 1L0
Appendix D
Laboratory Test Results
215 Stafford Rd. West, Unit 104
Ottawa, Ontario K2H 9C1
Phone: 613-726-3039
Fax: 613-726-3004
e-mail: [email protected]
Kilo Diameter Height Mass Area Volume Age Type of Unit Mass Strength L/D Correction Corrected
Newtons (m) (m) (kg) (m 2 ) (m 3 ) (Years) Fracture (kg/m 3 ) (Mpa) Ratio Factor Strength (MPA)
Comments:
H. Smith Reviewed By (Signature) : 11/04/2016Reviewed By (Print):
Rock Cores
Project Number: 60182.002 (CP-16-0469)
Core #
BH16-01 255.1 0.0469 0.1003 0.4702 N/A N/A
RC-4
2635 46.6 2.21:1 N/A N/A
Project Name: 3225 Uplands Dr.
2714 147.7 2.14:10.0017 0.00017
Compressive Strength
Test Report
BH16-02 82.5 0.0475 0.1048 0.4894 0.00177 0.00019
RC-5
BH16-03 101.5 0.0473 0.1001 0.4672 0.00176
RC-5
2656 57.8 2.12:1 N/A N/A0.00018
CCIL Certified Concrete Testing Laboratory
www.paracellabs.com1-800-749-1947
Ottawa, ON, K1G 4J8300 - 2319 St. Laurent Blvd
Attn: Mary Ellen GleesonRR#3 Carp, ON K0A 1L0115 Walgreen RoadMcIntosh Perry Consulting Eng. (Carp)
Certificate of Analysis
This Certificate of Analysis contains analytical data applicable to the following samples as submitted:
Paracel ID Client ID
Order #: 1643332
Order Date: 20-Oct-2016 Report Date: 24-Oct-2016
Client PO: CP-16-0469
Custody: 106522 Project: Uplands
1643332-01 BH16-2 SS-1
Any use of these results implies your agreement that our total liabilty in connection with this work, however arising, shall be limited to the amount paid by you for this work, and that our employees or agents shall not under any circumstances be liable to you in connection with this work.
Approved By:
Page 1 of 7
Lab Supervisor
Mark Foto, M.Sc.
Order #: 1643332
Project Description: Uplands
Certificate of AnalysisClient:
Report Date: 24-Oct-2016
Order Date: 20-Oct-2016
Client PO: CP-16-0469
McIntosh Perry Consulting Eng. (Carp)
Analysis Summary Table
Analysis Method Reference/Description Extraction Date Analysis Date
EPA 300.1 - IC, water extraction 21-Oct-16 22-Oct-16AnionsEPA 150.1 - pH probe @ 25 °C, CaCl buffered ext. 22-Oct-16 22-Oct-16pH, soilEPA 120.1 - probe, water extraction 21-Oct-16 21-Oct-16ResistivityGravimetric, calculation 22-Oct-16 22-Oct-16Solids, %
Page 2 of 7
Order #: 1643332
Project Description: Uplands
Certificate of AnalysisClient:
Report Date: 24-Oct-2016
Order Date: 20-Oct-2016
Client PO: CP-16-0469
McIntosh Perry Consulting Eng. (Carp)
Client ID: BH16-2 SS-1 - - -Sample Date: ---07-Oct-16
1643332-01 - - -Sample ID:MDL/Units Soil - - -
Physical Characteristics
% Solids ---86.90.1 % by Wt.
General Inorganics
pH ---7.690.05 pH Units
Resistivity ---18.00.10 Ohm.m
Anions
Chloride ---105 ug/g dry
Sulphate ---495 ug/g dry
Page 3 of 7
Order #: 1643332
Project Description: Uplands
Certificate of AnalysisClient:
Report Date: 24-Oct-2016
Order Date: 20-Oct-2016
Client PO: CP-16-0469
McIntosh Perry Consulting Eng. (Carp)
Method Quality Control: Blank
Analyte ResultReporting
Limit UnitsSourceResult %REC
%RECLimit RPD
RPDLimit Notes
AnionsChloride ND 5 ug/g Sulphate ND 5 ug/g
General InorganicsResistivity ND 0.10 Ohm.m
Page 4 of 7
Order #: 1643332
Project Description: Uplands
Certificate of AnalysisClient:
Report Date: 24-Oct-2016
Order Date: 20-Oct-2016
Client PO: CP-16-0469
McIntosh Perry Consulting Eng. (Carp)
Method Quality Control: Duplicate
Analyte ResultReporting
Limit UnitsSourceResult %REC
%RECLimit RPD
RPDLimit Notes
General InorganicspH 7.74 0.05 pH Units 7.75 100.1Resistivity 108 0.10 Ohm.m 108 200.1
Physical Characteristics% Solids 87.7 0.1 % by Wt. 86.0 252.0
Page 5 of 7
Order #: 1643332
Project Description: Uplands
Certificate of AnalysisClient:
Report Date: 24-Oct-2016
Order Date: 20-Oct-2016
Client PO: CP-16-0469
McIntosh Perry Consulting Eng. (Carp)
Method Quality Control: Spike
Analyte ResultReporting
Limit Units SourceResult
%REC %RECLimit
RPDRPDLimit Notes
AnionsChloride 97.7 97.7 78-1135 ug/g Sulphate 100 100 78-1115 ug/g
Page 6 of 7
Order #: 1643332
Project Description: Uplands
Certificate of AnalysisClient:
Report Date: 24-Oct-2016
Order Date: 20-Oct-2016
Client PO: CP-16-0469
McIntosh Perry Consulting Eng. (Carp)
Qualifier Notes :None
Sample Data RevisionsNone
Work Order Revisions / Comments :
None
Other Report Notes :
MDL: Method Detection Limit
n/a: not applicable
Source Result: Data used as source for matrix and duplicate samples%REC: Percent recovery.RPD: Relative percent difference.
ND: Not Detected
Soil results are reported on a dry weight basis when the units are denoted with 'dry'.Where %Solids is reported, moisture loss includes the loss of volatile hydrocarbons.
Page 7 of 7