Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

78
 SUBSURFACE SOIL INVESTIGATION FSM COLLEGE OF MICRONESIA CHUUK CAMPUS WENO, CHUUK STATE GEOTECHNICAL ENGINEERING REPORT (Dynamic Cone Penetrometer Test)  Project Proponent: FEDERATED STATES OF MICRONESIA & COLLEGE OF MICRONESIA Prepared by: ENGINEE R ING MANAGEME NT & PL ANNING S ER VICES COR PORAT ION 199 8 ARMY DRIVE R OUT E 1 6, 2ND F LOO R E MPSCO , DEDE DO, GUAM 969 29 PO BOX 21 79 4 GMF, BARRI GADA, G U 96 92 1  T EL (671 ) 6 38 -471 6/ 57 16 FAX (671) 638-2136  November 2010

Transcript of Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    1/78

    SUBSURFACE SOIL INVESTIGATIONFSM COLLEGE OF MICRONESIA

    CHUUK CAMPUS

    WENO, CHUUK STATE

    GEOTECHNICAL ENGINEERING REPORT(Dynamic Cone Penetrometer Test)

    Project Proponent:

    FEDERATED STATES OF MICRONESIA

    &

    COLLEGE OF MICRONESIA

    Prepared by:

    ENGINEERING MANAGEMENT & PLANNING SERVICES CORPORATION

    1998 ARMY DRIVE ROUTE 16, 2ND FLOOR EMPSCO , DEDEDO, GUAM 96929

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    2/78

    TABLE OF CONTENTS Page No.

    Cover Page ---------------------------------------------------------- 1

    Table of Contents -------------------------------------------------- 2 - 3

    Executive Summary ----------------------------------------------- 4 6

    Terms of Reference ----------------------------------------------- 7 - 8

    1 INTRODUCTION

    1.1Background of the Project --------------------------------- 9

    1.2Geography ---------------------------------------------------- 9

    1.3Seismicity ----------------------------------------------------- 10

    1.4Location Map ------------------------------------------------ 11

    2

    SITE INVESTIGATION2.1Rationale ------------------------------------------------------ 12

    2.2Field Reconnaissance ---------------------------------------- 12

    2.3Field Procedures ---------------------------------------------- 12-14

    2.4Field Sampling and Data Recording ----------------------- 14

    2.5Location of Boreholes and Test Pits ----------------------- 14-15

    2.6Field Test Results -------------------------------------------- 16-21

    3 LABORATORY TESTING

    3.1Laboratory Test Procedures ------------------------------- 22

    3.2Laboratory Test Results ------------------------------------ 23-25

    4 EVALUATION AND ANALYSIS

    4.1Evaluation and Analysis on Building Area Foundation 26

    4.2

    Evaluation and Analysis on Road & Parking Lot Areas 26-27

    5 DESIGN RECOMMENDATIONS

    5.1Site Preparation and Grading ------------------------------- 28-29

    5.2Building Footing Design Recommendations ------------- 29-30

    5.3Road Pavement Design Parameters Recommendations 30

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    3/78

    7 APPENDICES

    7.1DCP Test Photographs -------------------------------------- 33-37

    7.2

    Laboratory Photographs ------------------------------------ 38

    7.3DCP Test Field Data, CBR & Bearing Calculations --- 6 sheets

    7.4Geotechnical Data Log --------------------------------------- 1 sheet

    7.5Determination of Water Content -------------------------- 1 sheet

    7.6Determination of Atterberg Limits ------------------------ 10 sheets

    7.7Particles Size Analysis --------------------------------------- 22 sheets

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    4/78

    EXECUTIVE SUMMARY

    The Program Management Unit (PMU) of the Federated States of Micronesia with

    office at Palikir, State of Pohnpei, is represented by Mr. Marcelino Actouka as the Acting

    Program Manager issued a Task Order No. 0001 on August 12, 2010 as part of IDP-A-

    0004 to EMSPCO Engineering Consultants represented by Mr. Ernesto A. Capulong Jr. as

    Principal. This task order is covered under the Indefinite-Delivery Contract for

    Architectural and Engineering for Compact Infrastructural Grants Projects.

    The geotechnical requirements and deliverables are as follows to wit:

    1. A-E will provide geotechnical report including but not limited to graphic

    logs and borings description and analysis of the surface and subsurface

    conditions, geohydrologic conditions, conclusions and geotechnical design

    recommendations.

    2. A-E shall conduct a minimum of 2 borings at 25 feet depths or upon the A-E

    Geotechnical Engineer sound judgment and professional experience to

    determine the actual location and depths of borings.

    3. A-E shall conduct drilling and sampling necessary to provide samples for

    laboratory testing and subsurface condition data.

    The project is to develop a new campus of FSM-College of Micronesia (COM)encompassing a total land area of approximately 1.2 hectares, located at uphill of the other

    government offices, Weno Island. The project is developed initially by FSM-COM Chuuk

    Campus Administration. The difference in elevations between the highest and lowest

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    5/78

    The site is vegetated with coconut trees and other local variety of trees and bushes.

    Much of the exposed natural soil outcrops are characterized by brownish sandy silty soil.

    Building Footing Design Recommendations

    Taking the field results, laboratory results, analysis and findings into considerations, the

    undersigned recommends the following:

    1.

    It is recommended that the bottom of footings shall be set at elevation 1.5metersfrom the existing natural ground surfaceand it is further recommended that the

    maximum usable bearing pressure is 1300 psf or 62 KPa which has an estimated

    foundation settlement of 35 mm.

    2. The footings shall be connected with adequate tie-beams to minimize

    differential settlement. It is also noted that foundation design criteria mentioned above is

    limited to building foundation only and does not include equipment or machine

    foundation.

    3. It is recommended that foundation improvement shall be employed using

    remove and replace method for footings at administration building, the following

    suggested modification procedure are as follows to wit:

    Over-excavate the foundation bed by at least 1.00 meter depth below the

    footing.

    Replace with imported materials compacted in lifts not exceeding 8

    inches (200 mm) in thickness to a maximum of 95 percent of maximum

    density as determined by ASTM Standard D-1557. In-place density shall

    be determined in accordance with ASTM D-1556, D-2167, ASTM D-

    2922, ASTM D-3017 or equivalent. In-situ compaction can also be

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    6/78

    It is strongly discourage not to use boulders as foundation improvement

    due to difficulty of compaction and filling of voids.

    Road Pavement Design Parameters Recommendations

    Taking the field results, laboratory results, evaluation analysis into considerations,

    the undersigned recommends the following:

    1.

    Pavement Structural Parameters:

    Location Average CBR Remarks

    BH-1/TP-1 Road 5.9 MH Sandy Elastic Silt

    BH-2/TP-2 Road 25.3 ML Sandy Silt

    BH-3/TP-3 Road 10.5 ML Sandy Silt

    BH-4/TP-4 Road 10.7 ML Sandy Silt

    BH-5/TP-5 Road 5.4 MH Sandy Elastic Silt

    BH-6/TP-6 Road 6.8 SM Silty Sand with Gravel

    BH-7/TP-7 Road 7 ML Sandy Silt

    BH-8/TP-8 Parking Lot 17.8 MH Sandy Elastic Silt

    2. Pavement Structures shall consist of Selected Fill, Subbase Course and

    Concrete Pavement.

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    7/78

    TERMS OF REFEERENCE

    Terms of Reference

    The Program Management Unit (PMU) of the Federated States of Micronesia with

    office at Palikir, State of Pohnpei, is represented by Mr. Marcelino Actouka as the Acting

    Program Manager issued a Task Order No. 0001 on August 12, 2010 as part of IDP-A-

    0004 to EMSPCO Engineering Consultants represented by Mr. Ernesto A. Capulong Jr. as

    Principal. This task order is covered under the Indefinite-Delivery Contract for

    Architectural and Engineering for Compact Infrastructural Grants Projects. This A-E

    Statement of Work (SOW) includes geotechnical testing the four separate college

    buildings in three states: Pohnpei, Kosrae and Chuuk:

    i.

    Pohnpei COM Campus in Kolonia Vocational Educational Building

    ii. Pohnpei National COM Campus in Palikir Student Center (Full size).

    iii. Kosrae COM Campus in Tofol Student Center and Learning Resource

    Center (revised smaller with library elements).

    iv. Chuuk COM Campus on Weno Island Two Floor Administration Buildings

    with Classrooms.

    The geotechnical requirements and deliverables are as follows to wit:

    1. A-E will provide geotechnical report including but not limited to graphic

    logs and borings description and analysis of the surface and subsurface conditions,geohydrologic conditions, conclusions and geotechnical design recommendations.

    2. A-E shall conduct a minimum of 2 borings at 25 feet depths or upon the A-E

    Geotechnical Engineer sound judgment and professional experience to determine the

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    8/78

    5. A-E shall backfilled properly all borings after completion of data collection.

    6.

    A-E shall take precautions preserve all historical, archeological and cultural

    resources encountered during the work.

    7. A-E soils boring samples after laboratory testing shall be stored and

    protected from undue environmental exposure for at least two years.

    8. A-E Geotechnical Engineer shall manage the laboratory testing program.

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    9/78

    CHAPTER 1

    INTRODUCTION

    Background of the Project

    The project is to develop a new campus of FSM-College of Micronesia (COM)

    encompassing a total land area of approximately 1.2 hectares, located at uphill of the other

    government offices at Weno Island in the State of Chuuk. The project is developed initially

    by FSM-COM Chuuk Campus Administration. The difference in elevations between the

    highest and lowest points within the area is approximately ____ meters.

    A dirt road with cross drain traversing the area is existent to serve as an access to

    the area. The road was mostly cut through the relatively thick clay with isolated armor

    rocks through the steep slopes.

    The site is vegetated with coconut trees and other local variety of trees and bushes.

    Much of the exposed natural soil outcrops are characterized by brownish sandy silty soil.

    Geography

    Chuuk is formerly Truk, Ruk Hogoleu, Torres, Ugulat anf Lugulus and is an

    island group in the south western part of the Pacific Ocean. It comprises one of the four

    states of the Federated States of Micronesia (FSM), along with Kosrae, Pohnpei and

    Yap. Chuuk is the most is the most populous of the FSMs states. Geographically,

    Chuuk is part of the larger Carolines Islands group. Chuuk means mountain and wasknown mainly as Truk until 1990. The main population center of Chuuk state is the

    Chuuk Lagoon, a large archipelago with mountainous islands surrounded by the string

    of islets on a barrier reef. The two major geographical and dialectic divisions of the

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    10/78

    Seismicity

    Chuuk State is located 7 25' 0 N, and 151 47 0 E approximately 1065 km

    southeast from the Mariana Ridge at the eastern edge of the Philippine Plate, which is

    forced to rise in elevation as the Pacific Plate dives below it in a northwesterly direction.

    At the same time, the descending Pacific Plate, while dragging the eastern edge of the

    Philippine Plate with it, forms the Mariana Trench where the two plates converge. The

    Mariana Trench contains the greatest measured depth of the world's oceans, approximately

    11 .3 km (37,000 feet), located to the southwest of Guam.

    Earthquake History of the State of Chuuk

    Year of

    Occurrence

    Time Magn

    itude

    Depth Distance from nearby Islands

    Mar 12, 1974 15:11:5 UTC M5.5 33 km 48km Fayu, 64km Pisaras, 173km Weno

    Aug 10, 1985 17:02:12 UTC M5.2 33 km 87km Pikelot, 180km Ulul, 437km Weno

    Sep 23, 1993 17:16:60 UTC M5 33 km 256km Weno, 24km Magererik, 36km Ono

    Jun 11, 1998 5:40:41 UTC M4.6 33 km 320 km Weno, 109 km Pulusuk

    May 11,1999 5:04:54 UTC M4.8 10 km 364 km Weno, 84 km Pulusuk

    May 11, 2004 16:00:59 UTC M4.7 10 km 322 km Weno, 106 km Pulusuk

    Apr 28, 2006 10:38:39 UTC M4.7 10 km 428 km Weno, 199 km Pulusuk

    Aug 25, 2006 10:32:33 UTC M4.9 10 km 348 km Weno, 60 km Pulusuk

    The earthquake occurrences from 1998 to 2006 shows that the epicenter coordinates

    is approximately at the vicinity of 5 24' N, and 149 37 E.

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    11/78

    Location Map of Weno, Chuuk State, FSM

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    12/78

    CHAPTER 2

    SITE INVESTIGATION

    Rationale

    The objective of this geotechnical investigation is to determine subsurface soil

    conditions at the proposed building footprint, parking lot and the access road of the new

    FSM-COM campus. The field testing and laboratory testing will enable us to come-up

    with the recommendations regarding the footing design parameters and the access road

    pavement criteria.

    Field Reconnaissance

    Based on the available preliminary building and road layout, a quick field

    reconnaissance was conducted to determine the number and the location of the boreholes

    and test holes which were dependent on the available space in the area of interest.

    Field Procedures - Use of Dynamic Cone Penetrometer (DCP Test)

    1. Scope of DCP Test:

    This test method covers the measurement of the penetration rate of the Dynamic

    Cone Penetrometer with 8-kg hammer through undisturbed soil. The penetration rate may

    be related to in situ strength such as estimated in situ CBR (California Bearing Ratio) by

    US Army Corps of Engineers equation and in situ Bearing Capacity by PCA equation.2. Summary of Test Method:

    The operator drives the DCP tip into the soil by lifting the sliding hammer to the

    handle then releasing it. The total penetration for a given number of blows is measured and

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    13/78

    This test method is used to assess in situ strength of undisturbed soil. The

    penetration rate of the 8-kg DCP can be used to estimate in-situ CBR, Bearing Capacity, to

    identify strata thickness, shear strength strata, and other material characteristics.

    4. Apparatus:

    The 8-kg DCP consists of the following components: a 15.8 mm diameter steel

    drive rod with a replaceable point or disposable cone tip, a 8-kg hammer which is dropped

    a fixed height of 575 mm, a coupler assembly, and a handle. The tip has an angle of 60

    degrees and a diameter at base of 20 mm.

    5. Testing Sequence:

    Dropping the Hammer The DCP device is held in a vertical plumb position. The

    operator raises the hammer until it makes only light contact with the handle. The hammer

    shall not impact the handle when being raised. The hammer is then allowed to free-fall and

    impact the anvil coupler assembly. The number of blows and corresponding penetrations

    are recorded.

    Depth of Penetration The depth of penetration will vary with application. For

    typical highway applications, a penetration less than 900 mm will generally be adequate.

    Refusal - The presence of large aggregates or rock strata will either stop further

    penetration or deflect the drive rod. If after 5 blows, the device has not advanced more

    than 2 mm or handle has deflected more than 75 mm from the vertical position, the test

    shall be stopped, and the device moved to another test location. The new test location

    should be a minimum of 300 mm from the prior location to minimize test error caused bydisturbance of the material.

    Extraction Following completion of the test, the device should be extracted using

    the extraction using the extraction jack when using a replaceable point tip. When using a

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    14/78

    Field Procedures - Drilling/Boring Procedures for Building Footprint

    The boreholes/test pits were advanced by using open excavation method that is

    large enough for two (2) persons to enter the hole. Power equipment using backhoe is

    employed. The test pits were dug at 3 feet, 6 feet, 9 feet and 12 feet depth from the top of

    the existing ground. The DCP test were conducted at the top of the ground, at the top of 3

    feet hole, at top of 6 feet, at the top of 9 feet, and at the top of 12 feet.

    Field Procedures - Drilling/Boring Procedures for Access Road/Parking Lot

    The boreholes/test pits were advanced by using open excavation method that is

    large enough for two (2) persons to enter the hole. Power equipment using backhoe is

    employed. The test pits were dug at 3 feet and the DCP test were conducted at the top of

    the ground.

    Field Sampling and Data Recording

    Sampling Method Samples of soil were obtained from excavated test pit by hand.

    Test Specimens The objective of this test is to collect specimens of in-situ soils for

    laboratory analysis. Each sample will consist of not less than 800 grams of materials.

    Data Recording Describe the soil profile in a logbook noting in details of each

    soil layer according to the colors, thickness, and visual classification.

    Test Photographs Take photos on every sampling in the test pit.

    Location of Boreholes and Test Pits

    The boreholes BH-1, BH-2, BH-3, BH-4, BH-5, BH-6, BH-7 and test pits TP-1,

    TP-2, TP-3, TP-4, TP-5, TP-6, TP-7 were located in the proposed access road, while

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    15/78

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    16/78

    Field Test Results

    Borehole No. 1, Allowable Bearing Capacity using Factor of Safety FS = 2.0

    Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH)

    6 3 4 638 MH-Sandy Elastic Silt

    12 7 9 1198 MH-Sandy Elastic Silt

    18 4 5 790 MH-Sandy Elastic Silt

    24 5 6 933 MH-Sandy Elastic Silt

    30 4 5 790 MH-Sandy Elastic Silt

    36 5 6 933 MH-Sandy Elastic Silt

    Borehole No. 2, Allowable Bearing Capacity using Factor of Safety FS = 2.0

    Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH)

    6 4 5 790 ML-Sandy Silt

    12 9 12 1444 ML-Sandy Silt

    18 12 17 1789 ML-Sandy Silt

    24 12 17 1789 ML-Sandy Silt

    30 121 17 1789 ML-Sandy Silt

    36 50 84 5170 ML-Sandy Silt

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    17/78

    Borehole No. 3, Allowable Bearing Capacity using Factor of Safety FS = 2.0

    Layer Depthin inches

    Corrected No. ofBlows per 6

    cone penetration

    CBR AllowableBearing

    Capacity

    (lbs/ft2)

    Remarks(All soils or CL for

    CBR < 10 or CH)

    6 3 4 638 ML-Sandy Silts

    12 2 2 472 ML-Sandy Silts

    18 5 6 933 ML-Sandy Silts

    24 10 14 1562 ML-Sandy Silts

    30 12 17 1789 ML-Sandy Silts

    36 14 20 2006 ML-Sandy Silts

    Borehole No. 4A & 4B, Allowable Bearing Capacity using Factor of Safety FS =

    2.0

    Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH)

    6 4 5 790 ML-Sandy Silts

    12 3 4 638 ML-Sandy Silts

    18 6 8 1068 ML-Sandy Silt

    24 10 14 1562 ML-Sandy Silt

    30 11 15 1677 ML-Sandy Elastic Silt

    36 13 19 1899 ML-Sandy Elastic Silt

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    18/78

    Borehole No. 5, Allowable Bearing Capacity using Factor of Safety FS = 2.0Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH)

    6 3 4 638 MH-Sandy Elastic Silt

    12 4 5 790 MH-Sandy Elastic Silt

    18 4 5 790 MH-Sandy Elastic Silt

    24 6 8 1068 MH-Sandy Elastic Silt

    30 4 5 790 MH-Sandy Elastic Silt

    36 5 6 933 MH-Sandy Elastic Silt

    Borehole No. 6, Allowable Bearing Capacity using Factor of Safety FS = 2.0

    Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH)

    6 7 9 1198 SM-Silty Sand w/ Gravel

    12 8 11 1323 SM-Silty Sand w/ Gravel

    18 7 9 1198 SM-Silty Sand w/ Gravel

    24 8 11 1323 SM-Silty Sand w/ Gravel

    30 61 8 1068 SM-Silty Sand w/ Gravel

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    19/78

    Borehole No. 7, Allowable Bearing Capacity using Factor of Safety FS = 2.0Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH)

    6 4 5 790 ML-Sandy Silts

    12 4 5 790 ML-Sandy Silts

    18 7 9 1198 ML-Sandy Silts

    24 9 12 1444 ML-Sandy Silts

    30 11 15 1677 ML-Sandy Silts

    36 7 9 1198 ML-Sandy Silts

    Borehole No. 8, Allowable Bearing Capacity using Factor of Safety FS = 2.0

    Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH)

    6 3 4 638 MH-Sandy Elastic Silt

    12 6 8 1068 MH-Sandy Elastic Silt

    18 9 12 1444 MH-Sandy Elastic Silt

    24 13 19 1899 MH-Sandy Elastic Silt

    30 14 20 2006 MH-Sandy Elastic Silt

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    20/78

    Borehole No. 9, 9A, 9B, 9C, 9D, Allowable Bearing Capacity using Factor of

    Safety FS = 2.0Layer Depth

    in inches

    Corrected No. of

    Blows per 6

    cone penetration

    CBR Allowable

    Bearing

    Capacity

    (lbs/ft2)

    Remarks

    (All soils or CL for

    CBR < 10 or CH

    6 4 4 731 MH-Sandy Elastic Silt

    12 8 11 1372 MH-Sandy Elastic Silt

    18 4 5 790 MH-Sandy Elastic Silt

    24 5 6 933 MH-Sandy Elastic Silt

    30 4 5 790 MH-Sandy Elastic Silt

    36 5 6 933 MH-Sandy Elastic Silt

    42 5 6 905 MH-Sandy Elastic Silt

    48 5 6 905 MH-Sandy Elastic Silt

    54 7 9 1198 MH-Sandy Elastic Silt

    60 8 11 1323 MH-Sandy Elastic Silt

    66 10 14 1562 MH-Sandy Elastic Silt

    72 7 9 1198 MH-Sandy Elastic Silt

    78 7 10 1223 MH-Sandy Elastic Silt

    84 7 10 1223 MH-Sandy Elastic Silt

    90 7 9 1198 MH-Sandy Elastic Silt

    96 7 9 1198 MH-Sandy Elastic Silt

    102 5 6 933 MH-Sandy Elastic Silt

    108 4 5 790 MH-Sandy Elastic Silt

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    21/78

    138 7 9 1198 MH-Sandy Elastic Silt

    144 8 11 1323 MH-Sandy Elastic Silt

    150 8 10 1261 MH-Sandy Elastic Silt

    156 7 10 1223 MH-Sandy Elastic Silt

    162 6 8 1068 MH-Sandy Elastic Silt

    168 7 9 1198 MH-Sandy Elastic Silt

    174 5 6 933 MH-Sandy Elastic Silt

    180 5 6 933 MH-Sandy Elastic Silt

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    22/78

    CHAPTER 3

    LABORATORY TESTING

    Laboratory Test Procedures

    The following laboratory tests and their brief description were carried out on the soil

    samples obtained from site.

    1.

    Classification of Soils for Engineering Purpose

    ASTM D 2487-00 Standard Practice Classification of Soils for Engineering

    Purpose (Unified Soil Classification System)

    2. Particle Size Analysis of Soils

    ASTM D 422-63 Standard Practice Methods for Particle-Size Analysis of Soils:

    Soil was passed through a series of sieves, the weight of soil retained on each sieve

    determined and recorded. For each sample analyzed, a gradation curve was drawn based

    on the percent finer by weight.

    3. Liquid Limit, Plastic Limit & Plasticity Index of Soils

    ASTM D 4318-00 Standard Test Methods for Liquid Limit, Plastic Limit and Plasticity

    Index of Soils: The liquid limit and plastic limit of soils (along with the shrinkage limit)

    are often collectively referred to as the Atterberg limits. These limits distinguished the

    boundaries of the several consistency states of plastic soils.

    4. Laboratory Determination of Moisture Content of Soils.

    ASTM D 2216-98 Standard Test Methods for Laboratory Determination of Water

    Content (Moisture) of Soil and Rock by Mass: The ratio expressed as percentage of the

    weight of water in a given mass of soil to the weight of the solid particles.

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    23/78

    Laboratory Test Results

    Borehole No. 1Layer

    Depth,

    inches

    Sample

    No.

    USCS

    Symbol

    Description

    Grain Size Liquid Limit

    %

    Plastic Limit

    %

    Plastic Index

    %

    Moisture

    Content

    %

    6 to

    36

    SS1 MH

    Sandy

    Elastic Silt

    R4 = 0% ;

    R200= 47.6% ;

    F200= 52.4%

    LL = 50.2%; PL = 41% PI = 9.18% MC= 42.86%

    Borehole No. 2

    Layer

    Depth,

    inches

    Sample

    No.

    USCS

    Symbol

    Description

    Grain Size Liquid Limit

    %

    Plastic Limit

    %

    Plastic Index

    %

    Moisture

    Content

    %

    6 to

    36

    SS2 ML

    Sandy Silt

    R4 = 0% ;

    R200= 49.3% ;

    F200= 50.7%

    LL = 44.9%; PL = 38.3% PI = 6.57% MC= 33.75%

    Borehole No. 3

    Layer

    Depth,

    inches

    Sample

    No.

    USCS

    Symbol

    Description

    Grain Size Liquid Limit

    %

    Plastic Limit

    %

    Plastic Index

    %

    Moisture

    Content

    %

    6 to

    36

    SS3 ML

    Sandy Silt

    R4 = 0% ;

    R200= 46.1% ;

    F200= 53.9%

    LL = 45.6%; PL = 34.6% PI = 11.03% MC= 32.73%

    Borehole No. 4A and 4B

    Layer

    Depth,

    inches

    Sample

    No.

    USCS

    Symbol

    Description

    Grain Size Liquid Limit

    %

    Plastic Limit

    %

    Plastic Index

    %

    Moisture

    Content

    %

    6 to

    24

    SS4A ML

    Sandy Silt

    R4 = 0% ;

    R200= 48.7% ;

    F200= 51.3%

    LL = 42.9%; PL = 35.4% PI = 7.52% MC= 58.86%

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    24/78

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    25/78

    Borehole No. 9A, 9B, 9C and 9D

    Layer

    Depth,

    inches

    Sample

    No.

    USCS

    Symbol

    Description

    Grain Size Liquid Limit

    %

    Plastic Limit

    %

    Plastic Index

    %

    Moisture

    Content

    %

    6 to

    36

    SS9A MH

    Sandy

    Elastic Silt

    R4 = 0.3% ;

    R200= 46.7% ;

    F200= 53.3%

    LL = 57.1%; PL = 42.5% PI = 14.57% MC= 57.05%

    36

    to

    72

    SS9B MH

    Sandy

    Elastic Silt

    R4 = 0% ;

    R200= 45.5% ;

    F200= 54.5%

    LL = 52.3%; PL = 42.3% PI = 10.06% MC= 49.82%

    72

    to

    108

    SS9C MH

    Sandy

    Elastic Silt

    R4 = 0.3% ;

    R200= 46.7% ;

    F200= 53.3%

    LL = 57.1%; PL = 42.5% PI = 14.57% MC= 53.39%

    108

    to

    180

    SS9D MH

    Sandy

    Elastic Silt

    R4 = 0% ;

    R200= 45.5% ;

    F200= 54.5%

    LL = 52.3%; PL = 42.3% PI = 10.06% MC= 59.12%

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    26/78

    CHAPTER 4

    EVALUATION AND ANALYSIS

    Evaluation and Analysis on Building Area Foundation:

    The building footprint subsurface soil samples taken from the test pits with

    varying depth (from 3 feet to 12 feet) was found to be of MH using the USCS soil

    classification or sandy elastic silt. This type of silt is typically has medium toughness,

    high plasticity or high liquid limit, low to medium dry strength and low dilatancy.

    The supposed building foundation has low allowable bearing capacities as shown

    in the field test results of Chapter 2. This sandy elastic silt foundation will have enough

    strength to support the proposed Two Story Administration Building on shallow

    isolated spread footings but with much wider footing size. It is also necessary to

    interconnect the footings with tie-beams to limit the differential settlement. The in-situ

    foundation will have to be modified in order provided a stronger and more uniform soil

    support foundation bed. The idea is to over-excavate the existing soil foundation by at

    least one (1) meter and replace it with compacted engineered fill like sub-base course or

    base course or other equivalent materials. This modification process will in effect

    improved the bearing capacity at footing level by distancing from the in-situ sandy

    elastic silt foundation.

    Evaluation and Analysis on Road and Parking Lot Areas:

    The subsurface soil samples taken from 3 feet test pits (i.e BH-1/TP-1 to BH-

    8/TP-8) along the dirt roadway found to be of sandy silt (ML) and sandy elastic silt

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    27/78

    representative CBR for sandy silt subgrade, is quite a reasonable foundation base for

    Portland Cement Concrete Pavement (PCCP). However, ML and MH subgrade aretypically considered as fair to poor. The pavement structure for this type of subgrade

    shall include selected fill in addition to the typical section of PCC Pavement, that is,

    subbase and concrete pavement.

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    28/78

    CHAPTER 5

    DESIGN RECOMMENDATIONS

    Site Preparation and Grading:

    Clearing, Grubbing and Ground Preparation All surface objects and all trees,

    stumps, roots and other protruding obstructions, not designated to remain, shall be cleared

    and or/grubbed, including as required. The existing ground surface shall be prepared to

    receive fill by removing vegetation or any materials of non-complying fill, topsoil and

    other unsuitable materials, and by scarifying to provide a bond with the new fill.

    Road Excavation All excavation shall be finished to reasonably smooth and

    uniform surfaces. Excavation operations shall be conducted so that material outside of the

    limits of slope will not be disturbed. Prior to excavation, all necessary clearing and

    grubbing in the areas shall have been performed. The slopes of cut surfaces shall be not

    steeper than is safe for the intended use and shall be no steeper than 1 unit vertical in 2

    units horizontal.

    Structure Excavation Excavation for buildings or structures shall be constructed or

    protected such that they do not endanger life and property. If there are existing footings or

    foundations which may be affected by any excavation, it shall be underpinned adequately

    or otherwise protected by settlement and shall be protected against lateral movement.

    Fills Fills to be used to support foundations of any building or structure shall be

    placed in accordance with the accepted engineering practice.

    Fill Slopes - Fill slopes shall not be constructed on natural slopes steeper than 1 unit

    vertical in 2 units horizontal, provided further that benches shall be made to key in the

    subsequent fill material.

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    29/78

    in thickness to a maximum of 95 percent of maximum density as determined by ASTM

    Standard D-1557. In-place density shall be determined in accordance with ASTM D-1556,D-2167, ASTM D-2922, ASTM D-3017 or equivalent. For clean granular materials, the

    use of the foregoing procedures is inappropriate. Relative density criteria shall be used on

    ASTM D-5030-04. A minimum of three tests for every 500 m2(5380 ft

    2) area should be

    performed for every lift to verify compliance with the compaction requirements. In-situ

    compaction can also be determined in accordance with ASTM D-7380 Standard Test

    Method for Soil Compaction Determination at Shallow Depths using 5-lb (2.3 kg)

    Dynamic Cone Penetrometer

    Building Footing Design Recommendations

    Taking the field results, laboratory results, analysis and findings intoconsiderations, the undersigned recommends the following:

    1. It is recommended that the bottom of footings shall be set at elevation 1.5

    metersfrom the existing natural ground surfaceand it is further recommended that the

    maximum usable bearing pressure is 1300 psf or 62 KPa which has an estimated

    foundation settlement of 35 mm.

    2. The footings shall be connected with adequate tie-beams to minimize

    differential settlement. It is also noted that foundation design criteria mentioned above is

    limited to building foundation only and does not include equipment or machine

    foundation.

    3.

    It is recommended that foundation improvement shall be employed using

    remove and replace method for footings at administration building, the following

    suggested modification procedure are as follows to wit:

    O h f d i b d b l 1 00 d h b l h

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    30/78

    be determined in accordance with ASTM D-1556, D-2167, ASTM D-

    2922, ASTM D-3017 or equivalent.

    In-situ compaction can also bedetermined in accordance with ASTM D-7380 Standard Test Method

    for Soil Compaction Determination at Shallow Depths using 5-lb (2.3 kg)

    Dynamic Cone Penetrometer.

    Replace with base course materials or equivalent deposited in layers of

    200 mm in loose thickness.

    It is strongly discourage not to use boulders as foundation improvement

    due to difficulty of compaction and filling of voids.

    Road Pavement Design Parameters Recommendations

    Taking the field results, laboratory results, evaluation analysis into considerations,the undersigned recommends the following:

    1. Pavement Structural Parameters:

    Location Average CBR Remarks

    BH-1/TP-1 Road 5.9 MH Sandy Elastic Silt

    BH-2/TP-2 Road 25.3 ML Sandy Silt

    BH-3/TP-3 Road 10.5 ML Sandy Silt

    BH-4/TP-4 Road 10.7 ML Sandy Silt

    BH-5/TP-5 Road 5.4 MH Sandy Elastic Silt

    BH-6/TP-6 Road 6.8 SM Silty Sand with Gravel

    BH-7/TP-7 Road 7 ML Sandy Silt

    BH-8/TP-8 Parking Lot 17.8 MH Sandy Elastic Silt

    2 P m t St t h ll i t f S l t d Fill S bb C d

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    31/78

    In preparing this report, the professional services have been performed.

    Subsurface Soil Investigation of FSM COM Chuuk Campus at Weno Island -

    Geotechnical Engineering Report (Dynamic Cone Penetrometer Test & Test Pits) has

    been prepared by the undersigned in accordance with generally accepted Engineering

    Principles and Practices.

    November 18, 2010

    Prepared by: Noted by:

    Lizardo P. Remojo, MEng, ASEP Reynaldo M.C. Arce, P.E.

    Geotechnical Engineer Principal

    Master of Engineering (Structural/Geotechnical) EMPSCO Engineering Consultants

    CE Reg No. 36528 CE 564, SE 774

    SE-ASEP No. 36528-00081-000 GUAM - PEALS

    Regular Member, Association of Structural Engineers of the Philippines (ASEP).

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    32/78

    CHAPTER 6

    LITERATURE REFERENCES

    ASTM Committee DO4 on Road and Paving Materials (2003, June). Standard Test

    Method for Use of the Dynamic Cone Penetrometer in Shallow Pavement

    Applications. ASTM International,, pp. 1 7.

    Kessler, K.C. (2001, January). Dynamic Cone Penetrometer Users Manual. KesslerSoils Engineering Products, Inc., Springfield VA.

    Wales, Jimmy (Founder) Wikipedia Internet Free Encyclopedia, Website:

    en.wikipedia.org

    Earthquake Hazard Program, U.S. Geological Survey Website:

    earthquake.usgs/earthquakes

    Das, Braja (2006). Principles of Geotechnical Engineering 5th

    Edition, PWS Publishing

    Company, ISBN 0-534-55144-0

    Google Earth

    Geo-Engineering and Testing, Inc., (1999, November) Subsurface Soil Investigation,

    College of Micronesia, Chuuk Campus, Federated States of Micronesia

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    33/78

    CHAPTER 7

    APPENDICES

    Dynamic Cone Penetrometer Test Photographs:

    BH-1 at ground level (Access Road):

    BH-2 at ground level (Access Road):

    BH-3 at ground level (Access Road):

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    34/78

    BH-4 at ground level (Access Road):

    BH-5 at ground level (Access Road):

    BH-6 at ground level (Access Road):

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    35/78

    BH-7 at ground level (Access Road):

    BH-8 at ground level (Building Parking Lot):

    BH-9A at 3 from ground level (Building Area):

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    36/78

    BH-9B at 6 from ground level (Building Area):

    BH-9C at 9 from ground level (Building Area):

    BH-9D at 12 from ground level (Building Area):

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    37/78

    Road & Test Pit Excavation Photographs:

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    38/78

    Laboratory Photographs:

    EMPSCO ENGINEERING CONSULTANTS

    DYNAMIC CONE PENETROMETER (DCP) WORKSHEET - FIELD DATA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    39/78

    Pro ject : Pro po sed F SM -C OM A dmi ni st ra ti on B ui ld in g w ith C lassro om Test No.

    Location: Weno, Chuuk, Federated of Micronesia

    Test Conducted By: EMPSCO ENGINEERING CONSULTANTS - GUAM

    (Office) (Date)

    Kind of Material: Sandy Soil (Visual)

    Sample Description: Hammer Weight : 17.6 lbs

    Location: Climate / Temperature during Testing: Quick Rain

    6 '' 6 '' 3 100% 3.0 50.80 4 1276 6 '' 6 '' 4 100% 4.0 38.10 5 1580 6 '' 6 '' 3 100% 3.0 50.80 4 1276 6 '' 6 '' 3 100% 3.0 50.80 4 1276 6 ''

    6 '' 12 '' 7 100% 7.0 21.77 9 2396 6 '' 12 '' 9 100% 9.0 16.93 12 2889 6 '' 12 '' 2 100% 2.0 76.20 2 944 6 '' 12 '' 6 100% 6.0 25.40 8 2137 6 ''

    6 '' 18 '' 4 100% 4.0 38.10 5 1580 6 '' 18 '' 12 100% 12.0 12.70 17 3578 6 '' 18 '' 5 100% 5.0 30.48 6 1866 6 '' 18 '' 9 100% 9.0 16.93 12 2889 6 ''

    6 '' 24 '' 5 100% 5.0 30.48 6 1866 6 '' 24 '' 12 100% 12.0 12.70 17 3578 6 '' 24 '' 10 100% 10.0 15.24 14 3124 6 '' 24 '' 13 100% 13.0 11.72 19 3797 6 ''

    6 '' 30 '' 4 100% 4.0 38.10 5 1580 6 '' 30 '' 12 100% 12.0 12.70 17 3578 6 '' 30 '' 12 100% 12.0 12.70 17 3578 6 '' 30 '' 14 100% 14.0 10.89 20 4012 6 ''

    6 '' 36 '' 5 100% 5.0 30.48 6 1866 6 '' 36 '' 50 100% 50.0 3.05 84 10340 6 '' 36 '' 14 100% 14.0 10.89 20 4012 6 '' 36 '' 26 100% 26.0 5.86 40 6358 6 ''

    Average 4.7 5.9 1761 16.5 25.3 4257 7.7 10.5 2467 11.8 17.1 3411

    CBR = 292 / PR1.12

    CBR Value for all soils except CL soils below CBR 10% and CH soils

    CBR = 1 /(.017019* PR)2

    CBR Value for CL soils (CBR < 10% ) qult = 3.794*CBR.664

    (in psi - ultimate bearing pressure by Portland Cement Association)

    .664

    10/25/2010

    Correl

    ated

    qult(psf)

    Ground Surface

    Borehole No.8

    Correc

    tionFactor

    Correl

    ated

    qult(psf)

    Ground Surface

    CBR(all

    soils

    excl

    CL,C

    H)

    PR

    (mm/blow)

    Ultimate Bearing Pressure - lbs/ft2

    by Portland Cement Association

    Correc

    ted

    NOB/6

    "

    PR

    (mm/blow)

    CBR(all

    soils

    excl

    CL,C

    H)

    LayerThick

    ness

    in

    inches

    Total

    Depthin

    inche

    s

    No.of

    Blow

    s / 6"

    (Fiel

    d)

    Ground Surface

    LayerThick

    ness

    in

    inches

    Total

    Depth in

    inche

    s

    Ground Surface

    LayerThick

    ness

    in

    inches

    Total

    Depth in

    inche

    s

    No.of

    Blow

    s / 6"

    (Field

    )

    PR

    (mm/blow)

    CBR(all

    soils

    excl

    CL,C

    H)

    Correl

    ated

    qult(psf)

    Correc

    ted

    NOB/6

    "

    Correc

    tionFactor

    Borehole No. 1 Borehole No. 2

    No.of

    Blow

    s / 6"

    (Fiel

    d)

    Corre

    ctionFactor

    Correc

    ted

    NOB/6

    "

    PR

    (mm/blow)

    CBR(all

    soils

    excl

    CL,C

    H)

    Correlat

    ed qult(psf)

    LayerThick

    ness

    in

    inches

    Total

    Depth

    in

    inches

    Borehole No.3

    Monday, October 04, 2010

    Corre

    cted

    NOB/6

    "

    No.of

    Blow

    s / 6"

    (Fiel

    d)

    Correc

    tionFactor

    Correc

    ted

    NOB/6

    "

    PR

    (mm/blow)

    CBR(all

    soils

    excl

    CL,C

    H)

    Ground Surface

    LayerThick

    ness

    in

    inches

    Total

    Depth in

    inche

    s

    No. of

    Blows /

    6"

    (Field)

    Correct

    ionFactor

    Correla

    ted qult(psf)

    CBR =1 / (.002871*PR) CBR Value for CH soi ls qult

    = (3.794*CBR.664

    )*144 (in psf - ultimate bearing pressure by Portland Cement Association)

    TEST PERFORMED BY:

    ENGR. LIZARDO P. REMOJO JAIME ANONUEVO KAE TAKOCH KIMPO REISON D-GSON RANUCH

    GEOTECHNICAL ENGINEER LOGISTIC /DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR

    CBR Graphs BH-1 CBR Graphs BH-2 CBR Graphs BH-3 CBR Graphs BH-8

    Bearing Capacity (ultimate) BH-1 Bearing Capacity (ultimate) BH-2 Bearing Capacity (ultimate) BH-3 Bearing Capacity (ultimate) BH-8

    EMPSCO ENGINEERING CONSULTANTS

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    40/78

    Project: Proposed FSM-COM Administration Building with Classroom

    Location: Weno, Chuuk, Federated of Micronesia

    Kind of Material: Sandy Soil (Visual) Date of Testing:

    Sample Description: Hammer Weight : 17.6 lbs

    Location: Climate / Temperature during Testing: Sunny

    4

    9

    5

    6

    56

    5

    12

    17

    17

    17

    84

    4

    2

    6

    14

    17

    20

    4

    8

    12

    19

    20

    40

    n = (CBR)ave

    15 (qult

    )ave

    = 2974 (qall

    )ave

    = 1487

    SD = Standard Deviation

    SD = ((qall-(qall)ave)2 /( n -1 )) = lbs/ ft2

    (qall)ave= lbs/ft2

    (qall)min= lbs/ft2

    (qall)max= lbs/ft2

    qall =

    FS = Factor of Safety = 2.0 ( 2.0 to 3.0 for footing) max= inch

    PREPARED BY:

    ENGR. LIZARDO P. REMOJO, MEng, ASEP

    GEOTECHNICAL ENGINEER

    qult/FS

    3013BH-8 24 6 36 26 3179 1692 2862952 2172 4186

    BH-8 23 6 30 14 2006 519 269510 9994012.22

    6357.98

    2452BH-8 22 6 24 13 1899 412 169393 891 2906

    BH-8 21 6 18 9 1444 -43 1822 4372888.57

    3797.07

    1645BH-8 20 6 12 6 1068 -419 175271 61 2076

    BH-8 19 6 6 3 638 -849 720723 -3691276.02

    2136.62

    2796BH-3 18 6 36 14 2006 519 269510 999 3013

    BH-3 17 6 30 12 1789 302 91119 7813577.65

    4012.22

    1940

    BH-3 16 6 24 10 1562 75 5631 555 2569

    BH-3 15 6 18 5 933 -554 307042 -741865.70

    3124.01

    1645BH-3 14 6 12 2 472 -1015 1030307 -535 1479

    BH-3 13 6 6 3 638 -849 720723 -3691276.02

    943.85

    1.5

    BH-1 1 6 6 3 638 -849 720723 -369BH-1 2 6 12 7 1198

    2494

    2494

    1007.336

    1487

    480

    24 (qall-(qall)ave)2 = 23338713 480

    Total Depth ininches

    Allowable Bearing Pressure - lbs/ft 2

    Corrected No.of Blows / 6" Correlated qall (lbs/ft^2) qall- (qall) ave (qall- (qall) ave)

    2 Min. AllowableBearing Pressure

    790 -697 485468 -217 1798

    933

    Layer Thicknessin inches Max. Allowable

    Bearing Pressure

    1645

    -289 83456 191 2205BH-1 3 6 18 4

    BOREHOLE No. 1, 2, 3, 8

    10/25/2010

    PCA BEARING CAPACITY CALCULATION USING DYNAMIC CONE PENETROMETER CORRELATION (ALLOWABLE)

    Monday, October 04, 2010

    BoreholeTest Sample

    No.Correlated qult(lbs/ft^2)

    1276.02

    2396.15

    1580.42

    CBR

    -554 307042 -74 1940

    BH-1 5 6 30 4 790 -697 485468 -217 1798

    BH-1 4 6 24 5 1865.70

    1580.42933 -554 307042 -74 1940BH-1 6 6 36 5 1865.70

    790 -697 485468 -217 1798BH-2 7 6 6 4 1580.42

    1444 -43 1822 437 2452BH-2 8 6 12 9 2888.57

    1789 302 91119 781 2796BH-2 9 6 18 12 3577.65

    1789 302 91119 781 2796BH-2 10 6 24 12 3577.65

    1789 302 91119 781 2796BH-2 11 6 30 12 3577.65

    5170 3683 13564864 4163 6177BH-2 12 6 36 50 10340.03

    Page 1 of 1

    EMPSCO ENGINEERING CONSULTANTS

    DYNAMIC CONE PENETROMETER (DCP) WORKSHEET - FIELD DATA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    41/78

    P roj ec t: P rop os ed FS M- COM Ad mi nis tr at io n B ui ldi ng wi th Cl as sr oo m Test No.

    Loc ation: Weno, Chuuk, Federated of Micronesia

    Test Conducted By: EMPSCO ENGINEERING CONSULTANTS - GUAM

    (Office) (Date)

    Kind of Material: Sandy Soil (Visual)

    Sample Description: Hammer Weight : 17.6 lbs

    Location: Climate / Temperature during Testing: Quick Rain

    1 6 '' 6 '' 4 100% 4.0 38.10 5 1580 6 '' 6 '' 3 100% 3.0 50.80 4 1276 6 '' 6 '' 7 100% 7.0 21.77 9 2396 6 '' 6 '' 4 100% 4.0 38.10 5 1580 6 ''

    2 6 '' 12 '' 3 100% 3.0 50.80 4 1276 6 '' 12 '' 4 100% 4.0 38.10 5 1580 6 '' 12 '' 8 100% 8.0 19.05 11 2646 6 '' 12 '' 4 100% 4.0 38.10 5 1580 6 ''

    3 6 '' 18 '' 6 100% 6.0 25.40 8 2137 6 '' 18 '' 4 100% 4.0 38.10 5 1580 6 '' 18 '' 7 100% 7.0 21.77 9 2396 6 '' 18 '' 7 100% 7.0 21.77 9 2396 6 ''

    4 6 '' 24 '' 10 100% 10.0 15.24 14 3124 6 '' 24 '' 6 100% 6.0 25.40 8 2137 6 '' 24 '' 8 100% 8.0 19.05 11 2646 6 '' 24 '' 9 100% 9.0 16.93 12 2889 6 ''

    5 6 '' 30 '' 11 100% 11.0 13.85 15 3353 6 '' 30 '' 4 100% 4.0 38.10 5 1580 6 '' 30 '' 6 100% 6.0 25.40 8 2137 6 '' 30 '' 11 100% 11.0 13.85 15 3353 6 ''

    6 6 '' 36 '' 13 100% 13.0 11.72 19 3797 6 '' 36 '' 5 100% 5.0 30.48 6 1866 6 '' 36 '' 5 100% 5.0 30.48 6 1866 6 '' 36 '' 7 100% 7.0 21.77 9 2396 6 ''

    Average 7.8 10.7 2545 4.3 5.4 1670 6.8 9.0 2348 7.0 9.3 2366

    CBR = 292 / PR1.12

    CBR Value for all soils except CL soils below CBR 10% and CH soils

    CBR = 1 /(.017019* PR)2

    CBR Value for CL soils (CBR < 10% ) qult = 3.794*CBR.664

    (in psi - ultimate bearing pressure by Portland Cement Association)

    CBR =1 / (.002871*PR) CBR Value for CH soils qult = (3.794*CBR.664

    )*144 (in psf - ult imate bearing pressure by Portland Cement Association)

    TEST PERFORMED BY:

    ENGR. LIZARDO P. REMOJO JAIME ANONUEVO KAE TAKOCH KIMPO REISON D-GSON RANUCH

    GEOTECHNICAL ENGINEER LOGISTIC /DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR

    CBR Graphs BH-4 CBR Graphs BH-5 CBR Graphs BH-6 CBR Graphs BH-7

    Bearing Capacity (ultimate) BH-4 Bearing Capacity (ultimate) BH-5 Bearing Capacity (ultimate) BH-6 Bearing Capacity (ultimate) BH-7

    Ground Surface

    Layer

    Thick

    ness

    in

    inche

    s

    Total

    Dept

    h in

    inche

    s

    No. of

    Blows /

    6"

    (Field)

    Correc

    tion

    Factor

    Correla

    ted qult

    (psf)

    Corre

    cted

    NOB/6

    "

    No.

    of

    Blow

    s / 6"

    (Fiel

    d)

    Correc

    tion

    Factor

    Correc

    ted

    NOB/6

    "

    PR

    (mm/blo

    w)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    Correc

    ted

    NOB/6

    "

    Correc

    tion

    Factor

    Borehole No. 4 Borehole No. 5

    No.

    of

    Blow

    s / 6"

    (Field

    )

    Corre

    ction

    Factor

    Correc

    ted

    NOB/6

    "

    PR

    (mm/bl

    ow)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    Correlat

    ed qult

    (psf)

    Layer

    Thick

    ness

    in

    inche

    s

    Total

    Depth

    in

    inches

    Borehole No.6

    Monday, October 04, 2010

    Ground Surface

    Layer

    Thick

    ness

    in

    inche

    s

    Total

    Dept

    h in

    inche

    s

    Ground Surface

    Layer

    Thick

    ness

    in

    inche

    s

    Total

    Dept

    h in

    inche

    s

    No. of

    Blows

    / 6"

    (Field

    )

    PR

    (mm/blo

    w)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    Correl

    ated

    qult

    (psf)

    10/25/2010

    Correl

    ated

    qult

    (psf)

    Ground Surface

    Borehole No.7

    Correc

    tion

    Factor

    Correl

    ated

    qult

    (psf)

    Ground Surface

    CBR

    (all

    soils

    excl

    CL,C

    H)

    PR

    (mm/bl

    ow)

    Ultimate Bearing Pressure - lbs/ft2

    by Portland Cement Association

    Correc

    ted

    NOB/6

    "

    PR

    (mm/blo

    w)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    Layer

    Thick

    ness

    in

    inche

    s

    Total

    Depth

    in

    inche

    s

    No.

    of

    Blow

    s / 6"

    (Field

    )

    EMPSCO ENGINEERING CONSULTANTS

    PCA BEARING CAPACITY CALCULATION USING DYNAMIC CONE PENETROMETER CORRELATION (ALLOWABLE)

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    42/78

    Project: Proposed FSM-COM Administration Building with Classroom

    Location: Weno, Chuuk, Federated of Micronesia

    Kind of Material: Sandy Soil (Visual) Date of Testing:Sample Description: Hammer Weight : 17.6 lbs

    Location: Climate / Temperature during Testing: Sunny

    5

    4

    8

    14

    15

    19

    4

    5

    5

    8

    5

    6

    9

    11

    9

    118

    6

    5

    5

    9

    12

    15

    9

    n = (CBR)ave 9 (qult)ave= 2232 (qall)ave= 1116

    SD = Standard Deviation

    SD = ((qall-(qall)ave)2 /( n -1 )) = lbs/ft2

    (qall)ave= lbs/ft2

    (qall)min= lbs/ft2

    (qall)max= lbs/ft2

    qall =

    FS = Factor of Safety = 2.0 ( 2.0 to 3.0 for footing) max= inch

    PREPARED BY:

    ENGR. LIZARDO P. REMOJO, MEng, ASEP

    GEOTECHNICAL ENGINEER

    790 -326 106162 790 790BH-5 11 6 30 4 1580.42

    933 -183 33556 933 933BH-5 12 6 36 5 1865.70

    1068 -48 2278 1068 1068BH-5 10 6 24 6 2136.62

    790 -326 106162 790 790BH-5 9 6 18 4 1580.42

    790 -326 106162 790 790BH-5 8 6 12 4 1580.42

    638 -478 228507 638 638BH-5 7 6 6 3 1276.02

    1677

    BH-4 4 6 24 10 3124.01

    3353.47

    1899 783 612312 1899 1899BH-4 6 6 36 13 3797.07

    BH-4 5 6 30 11 1677 561 314387 1677

    10/25/2010

    BH-4 1 6 6 4

    446 198888 1562 1562

    CBR

    1562

    Layer Thicknessin inches Max. Allowable

    Bearing Pressure

    790

    -478

    PCA BEARING CAPACITY CALCULATION USING DYNAMIC CONE PENETROMETER CORRELATION (ALLOWABLE)

    Monday, October 04, 2010

    Borehole

    Test SampleNo.

    Correlated qult(lbs/ft^2)

    1580.42

    1276.02

    2136.62

    228507 638 638BH-4 3 6 18 6

    BOREHOLE No. 4, 5, 6, 7

    Total Depth ininches

    Allowable Bearing Pressure - lbs/ft 2

    Corrected No.of Blows / 6" Correlated qall(lbs/ft^2) qall- (qall) ave (qall- (qall) ave)

    2 Min. AllowableBearing Pressure

    1068 -48 2278 1068 1068

    111624 (qall-(qall)ave)2 = 2828379 1116

    1.5

    765

    1467

    350.675

    1116

    qult/FS

    790 -326 106162 790BH-4 2 6 12 3 638

    1198BH-6 14 6 12 8 1323 207 42900 1323 1323

    BH-6 13 6 6 7 1198 82 6731 11982396.15

    2646.32

    1198

    BH-6 16 6 24 8 1323 207 42900 1323 1323

    BH-6 15 6 18 7 1198 82 6731 11982396.15

    2646.321068

    BH-6 18 6 36 5 933 -183 33556 933 933

    BH-6 17 6 30 6 1068 -48 2278 10682136.62

    1865.70

    790BH-7 20 6 12 4 790 -326 106162 790 790

    BH-7 19 6 6 4 790 -326 106162 7901580.42

    1580.42

    1198BH-7 22 6 24 9 1444 328 107749 1444 1444

    BH-7 21 6 18 7 1198 82 6731 11982396.15

    2888.57

    1677BH-7 24 6 36 7 1198 82 6731 1198 1198

    BH-7 23 6 30 11 1677 561 314387 16773353.47

    2396.15

    Page 1 of 1

    P roj ec t: P rop os ed FS M- COM Ad mi nis tr at io nB ui ldi ng wi th Cl as sr oo m Test No.

    EMPSCO ENGINEERING CONSULTANTS

    DYNAMIC CONE PENETROMETER (DCP) WORKSHEET - FIELD DATA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    43/78

    P roj ec t: P rop os ed FS M COM Ad mi nis tr at io n B ui ldi ng wi th Cl as sr oo m Test No.

    Loc ation: Weno, Chuuk, Federated of Micronesia

    Test Conducted By: EMPSCO ENGINEERING CONSULTANTS - GUAM

    (Office) (Date)

    Kind of Material: Sandy Soil (Visual)

    Sample Description: Hammer Weight : 17.6 lbs

    Location: Climate / Temperature during Testing: Quick Rain

    6 '' 6 '' 3 120% 3.6 42.33 4 1461 6 ''

    6 '' 12 '' 7 120% 8.4 18.14 11 2744 6 ''

    6 '' 18 '' 4 100% 4.0 38.10 5 1580 6 ''

    6 '' 24 '' 5 100% 5.0 30.48 6 1866 6 ''

    6 '' 30 '' 4 100% 4.0 38.10 5 1580 6 ''

    6 '' 36 '' 5 100% 5.0 30.48 6 1866 6 '' 36 ''

    6 '' 42 '' 5.0 6 '' 42 '' 4 120% 4.8 31.75 6 1810 6 ''

    6 '' 48 '' 6 '' 48 '' 4 120% 4.8 31.75 6 1810 6 ''

    6 '' 54 '' 6 '' 54 '' 7 100% 7.0 21.77 9 2396 6 ''

    6 '' 60 '' 6 '' 60 '' 8 100% 8.0 19.05 11 2646 6 ''

    6 '' 66 '' 6 '' 66 '' 10 100% 10.0 15.24 14 3124 6 ''

    6 '' 72 '' 6 '' 72 '' 7 100% 7.0 21.77 9 2396 6 '' 72 ''

    6 '' 78 '' 6 '' 6.9 6 '' 78 '' 6 120% 7.2 21.17 10 2447 6 ''

    6 '' 84 '' 6 '' 6 '' 84 '' 6 120% 7.2 21.17 10 2447 6 ''

    6 '' 90 '' 6 '' 6 '' 90 '' 7 100% 7.0 21.77 9 2396 6 ''

    6 '' 96 '' 6 '' 6 '' 96 '' 7 100% 7.0 21.77 9 2396 6 ''

    6 '' 102 '' 6 '' 6 '' 102 '' 5 100% 5.0 30.48 6 1866 6 ''

    6 '' 108 '' 6 '' 6 '' 108 '' 4 100% 4.0 38.10 5 1580 6 '' 108 ''

    6 '' 114 '' 6 '' 6 '' 6.2 6 '' 114 '' 4 120% 4.8 31.75 6 1810 6 ''

    6 '' 120 '' 6 '' 6 '' 6 '' 120 '' 5 120% 6.0 25.40 8 2137 6 ''

    6 '' 126 '' 6 '' 6 '' 6 '' 126 '' 5 100% 5.0 30.48 6 1866 6 ''

    6 '' 132 '' 6 '' 6 '' 6 '' 132 '' 6 100% 6.0 25.40 8 2137 6 ''

    6 '' 138 '' 6 '' 6 '' 6 '' 138 '' 7 100% 7.0 21.77 9 2396 6 ''

    6 '' 144 '' 6 '' 6 '' 6 '' 144 '' 8 100% 8.0 19.05 11 2646 6 '' 144 ''

    6 '' 150 '' 6 '' 6 '' 6 '' 6.1 6 '' 150 '' 3 250% 7.5 20.32 10 2522

    6 '' 156 '' 6 '' 6 '' 6 '' 6 '' 156 '' 6 120% 7.2 21.17 10 2447

    6 '' 162 '' 6 '' 6 '' 6 '' 6 '' 162 '' 6 100% 6.0 25.40 8 2137

    6 '' 168 '' 6 '' 6 '' 6 '' 6 '' 168 '' 7 100% 7.0 21.77 9 2396

    6 '' 174 '' 6 '' 6 '' 6 '' 6 '' 174 '' 5 100% 5.0 30.48 6 1866

    6 '' 180 '' 6 '' 6 '' 6 '' 6 '' 180 '' 5 100% 5.0 30.48 6 1866

    6.3

    CBR = 292 / PR1.12

    CBR Value for all soils except CL soils below CBR 10% and CH soils

    CBR = 1 /(.017019* PR)2

    CBR Value for CL soils (CBR < 10% ) qult = 3.794*CBR.664

    (in psi - ultimate bearing pressure by Portland Cement Association)

    CBR =1 / (.002871*PR) CBR Value for CH soils qult = (3.794*CBR.664

    )*144 (in psf - ult imate bearing pressure by Portland Cement Association)

    TEST PERFORMED BY:

    ENGR. LIZARDO P. REMOJO JAIME ANONUEVO KAE TAKOCH KIMPO REISON D-GSON RANUCH

    GEOTECHNICAL ENGINEER LOGISTIC /DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR DCP OPERATOR

    10/25/2010

    Correl

    ated

    qult

    (psf)

    Ground Surface

    Borehole No. 9C

    Correc

    tion

    Factor

    Correl

    ated

    qult

    (psf)

    Ground Surface

    CBR

    (all

    soils

    excl

    CL,C

    H)

    PR

    (mm/bl

    ow)

    Ultimate Bearing Pressure - lbs/ft2

    by Portland Cement Association

    Correc

    ted

    NOB/6

    "

    PR

    (mm/blo

    w)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    LayerThick

    ness

    in

    inche

    s

    Total

    Depth

    in

    inche

    s

    No.

    of

    Blow

    s / 6"

    (Field

    )

    Ground Surface

    LayerThick

    ness

    in

    inche

    s

    Total

    Dept

    h in

    inche

    s

    Ground Surface

    LayerThick

    ness

    in

    inche

    s

    Total

    Dept

    h in

    inche

    s

    No. of

    Blows

    / 6"

    (Field

    )

    PR

    (mm/blo

    w)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    Correl

    ated

    qult

    (psf)

    Correc

    ted

    NOB/6

    "

    Correc

    tion

    Factor

    Borehole No. 9 Borehole No. 9A

    No.

    of

    Blow

    s / 6"

    (Field

    )

    Corre

    ction

    Factor

    Correc

    ted

    NOB/6

    "

    PR

    (mm/bl

    ow)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    Correl

    ated

    qult

    (psf)

    LayerThick

    ness

    in

    inche

    s

    Total

    Depth

    in

    inches

    Borehole No. 9B

    Monday, October 04, 2010

    Corre

    cted

    NOB/6

    "

    No.

    of

    Blow

    s / 6"

    (Fiel

    d)

    Correc

    tion

    Factor

    Correc

    ted

    NOB/6

    "

    PR

    (mm/bl

    ow)

    CBR

    (all

    soils

    excl

    CL,C

    H)

    Ground Surface

    LayerThick

    ness

    in

    inche

    s

    Total

    Dept

    h in

    inche

    s

    No. of

    Blows /

    6"

    (Field)

    Borehole No. 9D

    Correc

    tion

    Factor

    Correla

    ted qult

    (psf)

    EMPSCO ENGINEERING CONSULTANTS

    PCA BEARING CAPACITY CALCULATION USING DYNAMIC CONE PENETROMETER CORRELATION (ALLOWABLE)

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    44/78

    Project: Proposed FSM-COM Administration Building with Classroom

    Location: Weno, Chuuk, Federated of Micronesia

    Kind of Material: Sandy Soil (Visual) Date of Testing:

    Sample Description: Hammer Weight : 17.6 lbs

    Location: Climate / Temperature during Testing: Sunny

    4

    11

    5

    6

    5

    6

    66

    9

    11

    14

    9

    10

    10

    9

    9

    6

    5

    6

    8

    6

    8

    9

    11

    10

    10

    8

    9

    6

    6

    n = (CBR)ave 7 (qult)ave= 1785 (qall)ave= 1077

    SD = Standard Deviation

    SD = ((qall-(qall)ave)2 /( n -1 )) = lbs/ft2

    (qall)ave= lbs/ft2

    (qall)min= lbs/ft2

    (qall)max= lbs/ft2

    qall =

    FS = Factor of Safety = 2.0 ( 2.0 to 3.0 for footing) max= inch

    PREPARED BY:

    ENGR. LIZARDO P. REMOJO, MEng, ASEP

    GEOTECHNICAL ENGINEER

    CBR

    933BH-9D 30 6 180 5 933 -144 20861 9331865.70

    1198

    BH-9D 29 6 174 5 933 -144 20861 933 9331865.70

    1068BH-9D 27 6 162 6 1068 -9 81 10682136.62

    BH-9D 28 6 168 7 1198 121 14591 11982396.15

    1261

    BH-9D 26 6 156 7 1223 146 21362 1223 1223

    BH-9D 25 6 150 8 1261 184 33808 12612522.30

    2446.88

    1198

    BH-9C 24 6 144 8 1323 246 60455 1323 1323

    BH-9C 23 6 138 7 1198 121 14591 11982396.15

    2646.32

    933

    BH-9C 22 6 132 6 1068 -9 81 1068 1068

    BH-9C 21 6 126 5 933 -144 20861 9331865.70

    2136.62

    905

    BH-9C 20 6 120 6 1068 -9 81 1068 1068

    BH-9C 19 6 114 5 905 -172 29697 9051809.91

    2136.62

    933

    BH-9B 18 6 108 4 790 -287 82411 790 790

    BH-9B 17 6 102 5 933 -144 20861 9331865.70

    1580.42

    1198

    BH-9B 16 6 96 7 1198 121 14591 1198 1198

    BH-9B 15 6 90 7 1198 121 14591 11982396.15

    2396.15

    120150 731

    BH-9 2 6 12 8 1372

    BH-9B 14 6 84 7 1223

    2446.88

    2446.88

    107730 (qall-(qall)ave)2 = 1210071 1077

    204.271

    1077

    1.5

    873

    qult/FS

    1282

    -287 82411 790 790

    933

    Layer Thicknessin inches Max. Allowable Bearing

    Pressure

    731

    295 86888 1372 1372

    1223

    146 21362 1223 1223

    6 78

    BH-9 3 6 18 4

    BOREHOLE No. 9

    10/25/2010

    -144 20861 933 933

    BH-9 5 6 30 4 790 -287 82411 790 790

    BH-9

    PCA BEARING CAPACITY CALCULATION USING DYNAMIC CONE PENETROMETER CORRELATION (ALLOWABLE)

    Monday, October 04, 2010

    BoreholeTest Sample

    No.Correlated qult(lbs/ft^2)

    1461.31

    2744.10

    1580.42

    Total Depth ininches

    Ultimate Bearing Pressure - lbs/ft2Corrected No.of Blows / 6" Correlated qall (lbs/ft^2) qall- (qall) ave (qall- (qall) ave)

    2 Min. Allowable BearingPressure

    790

    BH-9 1 6 6 4 731 -347

    4 6 24 5 1865.70

    1580.42

    933 -144 20861 933 933BH-9 6 6 36 5 1865.70

    905 -172 29697 905 905BH-9A 7 6 42 5 1809.91905 -172 29697 905 905BH-9A 8 6 48 5 1809.91

    1198 121 14591 1198 1198BH-9A 9 6 54 7 2396.15

    1323 246 60455 1323 1323BH-9A 10 6 60 8 2646.32

    1562 485 234954 1562 1562BH-9A 11 6 66 10 3124.01

    1198 121 14591 1198 1198BH-9A 12 6 72 7 2396.15

    BH-9B 13 7 1223 146 21362 1223

    Page 1 of 1

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    45/78

    WATER (MOISTURE) CONTENT - ASTM D 2216 - 98

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    46/78

    ( )PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    WT. of WT. of WT. of WT. of WT. of Water

    Empty Can Wet Sample Dry Sample Water Dry Sample Content

    (grams) plus Can plus Can (grams) (grams) w , %

    (grams) (grams)

    SS1 34.50 122.36 96.00

    26.36 61.50 42.86%

    SS2 29.50 105.07 86.00 19.07 56.50 33.75%

    SS3 41.00 133.91 111.00 22.91 70.00 32.73%

    SS4-A 33.50 138.35 99.50 38.85 66.00 58.86%

    SS4-B 28.50 114.12 83.00 31.12 54.50 57.10%

    SS5 30.50 127.51 91.50 36.01 61.00 59.03%

    SS6 8.79 95.01 65.02 29.99 56.23 53.33%

    SS7 23.00 128.05 94.50 33.55 71.50 46.92% `

    SS8 8.87 87.88 59.18 28.70 50.31 57.05%

    SS9-A 22.50 76.93 57.00

    19.93 34.50 57.77%

    SS9-B 23.50 134.37 97.50 36.87 74.00 49.82%

    SS9-C 30.00 127.40 93.50 33.90 63.50 53.39%

    SS9-D 28.50 122.38 87.50 34.88 59.00 59.12%

    Sample

    Friday, November 05, 2010

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    47/78

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-1 BOREHOLE 1

    PHYSICAL DESCRIPTION :

    LIQUID LIMIT

    FLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 12.76 11.67 14.26 13.33

    Mass of Dry Soil + Can 11.39 10.52 12.37 11.73

    Mass of Can 8.53 8.25 8.62 8.47

    Mass of Dry Soil, Ws 2.86 2.27 3.75 3.26

    Mass of Moisture, Ww 1.37 1.15 1.89 1.60

    No. of Blows, N 41 27 24 20

    Water Content, w(%) 47.90% 50.66% 50.40% 49.08%

    0.4790 0.5066 0.5040 0.4908 50.22%1 2 3 4

    LL = 49.51%

    COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.0378 w1 = 50.40%

    IF2 = 0.1521 N1 = 24

    IF3 = 0.1074 w @ 25 = 50.22%

    Iave = 0.09908

    Liquid Limit @ 25 Blows = 50.22% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 9.61 10.12 10.25 9.51

    Mass of Dry Soil + Can 9.27 9.75 9.82 9.30

    Mass of Can 8.58 8.79 8.65 8.77

    Mass of Dry Soil 0.69 0.96 1.17 0.53

    Mass of Moisture 0.34 0.37 0.43 0.21Water Content, w(%) 49.28% 38.54% 36.75% 39.62%

    w = 41.05%

    Liquid Limit, LL = 50.22%

    Plastic Limit, PL = 41.05%

    Plasticity Index, PI = 9.18%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    50%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    100%

    90%

    80%

    70%

    50%

    60%

    30%

    20%

    10%

    0%

    Flow Curve

    1

    234

    Atterberg Limit Chuuk 11.11.10 new.xlsxSS1

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    48/78

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-2 BOREHOLE 2

    PHYSICAL DESCRIPTION :

    LIQUID LIMIT

    FLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 12.57 13.54 13.35 13.00

    Mass of Dry Soil + Can 11.33 12.14 12.01 11.67

    Mass of Can 8.70 8.81 8.97 8.70

    Mass of Dry Soil, Ws 2.63 3.33 3.04 2.97

    Mass of Moisture, Ww 1.24 1.40 1.34 1.33

    No. of Blows, N 16 24 28 32

    Water Content, w(%) 47.15% 42.04% 44.08% 44.78%

    0.4715 0.4204 0.4408 0.4478 44.89%1 2 3 4

    LL = 44.51%

    COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.0786 w1 = 44.08%

    IF2 = 0.2900 N1 = 28

    IF3 = 0.1263 w @ 25 = 44.89%

    Iave = 0.16497

    Liquid Limit @ 25 Blows = 44.89% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 9.23 9.17 9.35 9.60

    Mass of Dry Soil + Can 9.01 9.05 9.15 9.37

    Mass of Can 8.49 8.71 8.66 8.71

    Mass of Dry Soil 0.52 0.34 0.49 0.66

    Mass of Moisture 0.22 0.12 0.20 0.23Water Content, w(%) 42.31% 35.29% 40.82% 34.85%

    w = 38.32%

    Liquid Limit, LL = 44.89%

    Plastic Limit, PL = 38.32%

    Plasticity Index, PI = 6.57%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    50%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    F

    100%

    90%

    80%

    70%

    50%

    60%

    30%

    20%

    10%

    0%

    Flow Curve

    123

    4

    F

    Atterberg Limit Chuuk 11.11.10 new.xlsxSS2

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    49/78

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-3 BOREHOLE 3

    PHYSICAL DESCRIPTION :

    LIQUID LIMIT

    FLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 11.86 11.59 12.64 11.84

    Mass of Dry Soil + Can 10.77 10.70 11.50 10.87

    Mass of Can 8.72 8.66 8.82 8.48

    Mass of Dry Soil, Ws 2.05 2.04 2.68 2.39

    Mass of Moisture, Ww 1.09 0.89 1.14 0.97

    No. of Blows, N 8 15 34 42

    Water Content, w(%) 53.17% 43.63% 42.54% 40.59%

    0.5317 0.4363 0.4254 0.4059 45.62%1 2 3 4

    LL = 44.98%

    COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.1748 w1 = 42.54%

    IF2 = 0.3496 N1 = 34

    IF3 = 0.1692 w @ 25 = 45.62%

    Iave = 0.23118

    Liquid Limit @ 25 Blows = 45.62% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 9.38 9.43 9.82 9.01

    Mass of Dry Soil + Can 9.21 9.29 9.62 8.87

    Mass of Can 8.71 8.82 9.09 8.49

    Mass of Dry Soil 0.50 0.47 0.53 0.38

    Mass of Moisture 0.17 0.14 0.20 0.14Water Content, w(%) 34.00% 29.79% 37.74% 36.84%

    w = 34.59%

    Liquid Limit, LL = 45.62%

    Plastic Limit, PL = 34.59%

    Plasticity Index, PI = 11.03%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    50%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    F

    100%

    90%

    80%

    70%

    50%

    60%

    30%

    20%

    10%

    0%

    Flow Curve

    1

    2

    3

    4

    F

    Atterberg Limit Chuuk 11.11.10 new.xlsxSS3

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    50/78

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-4A BOREHOLE 4PHYSICAL DESCRIPTION :

    LIQUID LIMIT

    FLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 12.82 13.66 12.57 12.71

    Mass of Dry Soil + Can 11.49 12.20 11.43 11.51

    Mass of Can 8.44 8.80 8.77 8.76

    Mass of Dry Soil, Ws 3.05 3.40 2.66 2.75

    Mass of Moisture, Ww 1.33 1.46 1.14 1.20

    No. of Blows, N 14 24 31 41

    Water Content, w(%) 43.61% 42.94% 42.86% 43.64%

    0.4361 0.4294 0.4286 0.4364 42.90%

    1 2 3 4

    LL = 43.26%

    COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = w1 = 42.94%

    IF2 = 0.0284 N1 = 24

    IF3 = 0.0217 w @ 25 = 42.90%

    Iave = 0.02507

    Liquid Limit @ 25 Blows = 42.90% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 9.16 9.05 9.57 9.40

    Mass of Dry Soil + Can 9.03 8.91 9.40 9.27

    Mass of Can 8.67 8.56 8.87 8.88

    Mass of Dry Soil 0.36 0.35 0.53 0.39

    Mass of Moisture 0.13 0.14 0.17 0.13

    Water Content, w(%) 36.11% 40.00% 32.08% 33.33%

    w = 35.38%

    Liquid Limit, LL = 42.90%

    Plastic Limit, PL = 35.38%

    Plasticity Index, PI = 7.52%

    Friday, Novemb er 05, 2010

    ave

    F

    100%

    90%

    80%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    F

    2

    100%

    90%

    80%

    70%

    50%

    20%

    10%

    0%

    13

    Flow Curve

    4

    F

    Atterberg Limit Chuuk 11.11.10 new.xlsxSS4-A

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    51/78

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-5 BOREHOLE 5

    PHYSICAL DESCRIPTION :

    LIQUID LIMITFLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 14.34 14.23 13.86 12.64

    Mass of Dry Soil + Can 12.20 12.05 11.78 10.90

    Mass of Can 8.71 8.59 8.67 8.28 67.56%

    Mass of Dry Soil, Ws 3.49 3.46 3.11 2.62

    Mass of Moisture, Ww 2.14 2.18 2.08 1.74

    No. of Blows, N 40 31 27 16

    Water Content, w(%) 61.32% 63.01% 66.88% 66.41%

    0.6132 0.6301 0.6688 0.6641

    1 2 3 4

    LL = 64.40%COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.1280 w1 = 66.88%

    IF2 = 0.1525 N1 = 27

    IF3 = 0.3259 w @ 25 = 67.56%

    Iave = 0.20212

    Liquid Limit @ 25 Blows = 67.56% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 10.13 10.42 10.30 9.98

    Mass of Dry Soil + Can 9.53 9.80 9.72 9.60

    Mass of Can 8.45 8.68 8.61 8.87

    Mass of Dry Soil 1.08 1.12 1.11 0.73

    Mass of Moisture 0.60 0.62 0.58 0.38

    Water Content, w(%) 55.56% 55.36% 52.25% 52.05%

    w = 53.80%

    Liquid Limit, LL = 67.56%

    Plastic Limit, PL = 53.80%

    Plasticity Index, PI = 13.75%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    F

    2

    100%

    90%

    80%

    70%

    50%

    20%

    10%

    0%

    1

    3

    Flow Curve

    4

    F

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION COLLEGE OF MICRONESIA CHUUK CAMPUS FEDERATED STATE OF MICRONESIA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    52/78

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-6 BOREHOLE 6

    PHYSICAL DESCRIPTION :

    LIQUID LIMITFLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 12.35 14.30 12.08 13.80

    Mass of Dry Soil + Can 10.90 12.49 11.03 12.18

    Mass of Can 8.20 8.72 8.72 8.70

    Mass of Dry Soil, Ws 2.70 3.77 2.31 3.48

    Mass of Moisture, Ww 1.45 1.81 1.05 1.62 47.23%

    No. of Blows, N 10 22 38 43

    Water Content, w(%) 53.70% 48.01% 45.45% 46.55%

    0.5370 0.4801 0.4545 0.4655

    1 2 3 4

    LL = 48.43%COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.1129 w1 = 48.01%

    IF2 = 0.1663 N1 = 22

    IF3 = 0.1423 w @ 25 = 47.23%

    Iave = 0.14048

    Liquid Limit @ 25 Blows = 47.23% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 10.64 9.70 9.40 10.19

    Mass of Dry Soil + Can 10.12 9.44 9.19 9.82

    Mass of Can 8.99 8.81 8.70 8.96

    Mass of Dry Soil 1.13 0.63 0.49 0.86

    Mass of Moisture 0.52 0.26 0.21 0.37

    Water Content, w(%) 46.02% 41.27% 42.86% 43.02%

    w = 43.29%

    Liquid Limit, LL = 47.23%

    Plastic Limit, PL = 43.29%

    Plasticity Index, PI = 3.94%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    40%

    60%

    30%

    20%

    10%

    0%ave.

    ave

    ave

    F

    2

    100%

    90%

    80%

    70%

    50%

    20%

    10%

    0%

    1

    3

    Flow Curve

    ave.

    4

    F

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA CHUUK CAMPUS FEDERATED STATE OF MICRONESIA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    53/78

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-7 BOREHOLE 7

    PHYSICAL DESCRIPTION :

    LIQUID LIMITFLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 12.41 14.73 13.02 14.84

    Mass of Dry Soil + Can 11.34 13.06 11.73 13.25

    Mass of Can 8.41 8.53 8.17 8.94

    Mass of Dry Soil, Ws 2.93 4.53 3.56 4.31

    Mass of Moisture, Ww 1.07 1.67 1.29 1.59 36.27%

    No. of Blows, N 11 16 22 30

    Water Content, w(%) 36.52% 36.87% 36.24% 36.89%

    0.3652 0.3687 0.3624 0.3689

    1 2 3 4

    LL = 36.63%COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = -0.0085 w1 = 36.24%

    IF2 = -0.0213 N1 = 22

    IF3 = 0.0094 w @ 25 = 36.27%

    Iave = -0.00681

    Liquid Limit @ 25 Blows = 36.27% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 9.81 9.60 9.60 9.79

    Mass of Dry Soil + Can 9.58 9.38 9.38 9.68

    Mass of Can 8.85 8.71 8.69 9.32

    Mass of Dry Soil 0.73 0.67 0.69 0.36

    Mass of Moisture 0.23 0.22 0.22 0.11

    Water Content, w(%) 31.51% 32.84% 31.88% 30.56%

    w = 31.70%

    Liquid Limit, LL = 36.27%

    Plastic Limit, PL = 31.70%

    Plasticity Index, PI = 4.58%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    40%

    60%

    30%

    20%

    10%

    0%ave.

    ave

    ave

    F2

    100%

    90%

    80%

    70%

    50%

    20%

    10%

    0%

    1 3

    Flow Curve

    ave.

    4

    F

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA CHUUK CAMPUS FEDERATED STATE OF MICRONESIA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    54/78

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-8 BOREHOLE 8

    PHYSICAL DESCRIPTION :

    LIQUID LIMITFLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 15.90 14.73 15.71 14.39

    Mass of Dry Soil + Can 13.37 12.54 13.03 12.15

    Mass of Can 8.77 8.83 8.72 8.72

    Mass of Dry Soil, Ws 4.60 3.71 4.31 3.43

    Mass of Moisture, Ww 2.53 2.19 2.68 2.24 59.49%

    No. of Blows, N 36 30 21 14

    Water Content, w(%) 55.00% 59.03% 62.18% 65.31%

    0.5500 0.5903 0.6218 0.6531

    1 2 3 4

    LL = 60.38%COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.2513 w1 = 62.18%

    IF2 = 0.5089 N1 = 21

    IF3 = 0.3068 w @ 25 = 59.49%

    Iave = 0.35565

    Liquid Limit @ 25 Blows = 59.49% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 10.45 9.83 9.30 9.75

    Mass of Dry Soil + Can 9.97 9.50 9.09 9.29

    Mass of Can 8.96 8.76 8.63 8.30

    Mass of Dry Soil 1.01 0.74 0.46 0.99

    Mass of Moisture 0.48 0.33 0.21 0.46

    Water Content, w(%) 47.52% 44.59% 45.65% 46.46%

    w = 46.06%

    Liquid Limit, LL = 59.49%

    Plastic Limit, PL = 46.06%

    Plasticity Index, PI = 13.43%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    F

    2

    100%

    90%

    80%

    70%

    50%

    20%

    10%

    0%

    4

    3

    Flow Curve

    4

    F

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    55/78

    , ,

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-9A and SS-9C BOREHOLE 9A and 9C

    PHYSICAL DESCRIPTION :

    LIQUID LIMITFLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 12.26 11.84 13.84 13.44

    Mass of Dry Soil + Can 10.87 10.57 12.04 11.68

    Mass of Can 8.74 8.61 8.66 8.50

    Mass of Dry Soil, Ws 2.13 1.96 3.38 3.18

    Mass of Moisture, Ww 1.39 1.27 1.80 1.76 57.07%

    No. of Blows, N 17 23 44 31

    Water Content, w(%) 65.26% 64.80% 53.25% 55.35%

    0.6526 0.6480 0.5325 0.5535

    1 2 3 4

    LL = 59.66%COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.3799 w1 = 55.35%

    IF2 = 0.0352 N1 = 31

    IF3 = 0.1375 w @ 25 = 57.07%

    Iave = 0.18421

    Liquid Limit @ 25 Blows = 57.07% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 9.49 9.39 9.24 9.99

    Mass of Dry Soil + Can 9.23 9.17 9.00 9.63

    Mass of Can 8.61 8.72 8.38 8.74

    Mass of Dry Soil 0.62 0.45 0.62 0.89

    Mass of Moisture 0.26 0.22 0.24 0.36

    Water Content, w(%) 41.94% 48.89% 38.71% 40.45%

    w = 42.50%

    Liquid Limit, LL = 57.07%

    Plastic Limit, PL = 42.50%

    Plasticity Index, PI = 14.57%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    F

    2

    100%

    90%

    80%

    70%

    50%

    20%

    10%

    0%

    1

    3

    Flow Curve

    4

    F

    ATTERBERG LIMITS TESTS: ASTM D 4318 - 00PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    56/78

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO.: SS-9B and SS-9D BOREHOLE 9B and 9D

    PHYSICAL DESCRIPTION :

    LIQUID LIMITFLOW CURVE FOR LIQUID LIMIT DETERMINATION

    Can Description LL1 (grams) LL2 (grams) LL3 (grams) LL4 (grams)

    Mass of Wet Soil + Can 12.74 14.54 13.70 14.25

    Mass of Dry Soil + Can 11.40 12.51 11.92 12.08

    Mass of Can 9.01 8.50 8.67 8.47

    Mass of Dry Soil, Ws 2.39 4.01 3.25 3.61

    Mass of Moisture, Ww 1.34 2.03 1.78 2.17 52.32%

    No. of Blows, N 40 27 21 16

    Water Content, w(%) 56.07% 50.62% 54.77% 60.11%

    0.5607 0.5062 0.5477 0.6011

    1 2 3 4

    LL = 55.39%COMPUTATION :

    Flow Index: Equation of Flow Line:

    Flow Index, I = (w1-w2) = w = - IF log (25/N1) + w1

    log ( N2 / N1)

    IF1 = 0.4175 w1 = 54.77%

    IF2 = 0.4523 N1 = 21

    IF3 = 0.1016 w @ 25 = 52.32%

    Iave = 0.32380

    Liquid Limit @ 25 Blows = 52.32% 10 15 20 25 30 35 40 45 50 55

    Number of Blows, N ( log scale )

    PLASTIC LIMIT

    Can Description PL1 (grams) PL2 (grams) PL3 (grams) PL4 (grams)

    Mass of Wet Soil + Can 9.66 9.24 9.66 9.61

    Mass of Dry Soil + Can 9.37 8.92 9.42 9.27

    Mass of Can 8.71 8.18 8.81 8.47

    Mass of Dry Soil 0.66 0.74 0.61 0.80

    Mass of Moisture 0.29 0.32 0.24 0.34

    Water Content, w(%) 43.94% 43.24% 39.34% 42.50%

    w = 42.26%

    Liquid Limit, LL = 52.32%

    Plastic Limit, PL = 42.26%

    Plasticity Index, PI = 10.06%

    Friday, November 05, 2010

    ave

    F

    100%

    90%

    80%

    40%

    60%

    30%

    20%

    10%

    0%

    ave

    ave

    F

    2

    100%

    90%

    80%

    70%

    50%

    20%

    10%

    0%

    13

    Flow Curve

    4

    F

    PARTICLE SIZE ANALYSIS (ASTM D422)PROJECT : PROPOSED ADMINISTRATION BUILDING

  • 8/10/2019 Geotechnical Engineering Report Chuuk FSM-COM 11.18.10 Final (1)

    57/78

    PROJECT : PROPOSED ADMINISTRATION BUILDING

    LOCATION: COLLEGE OF MICRONESIA, CHUUK CAMPUS, FEDERATED STATE OF MICRONESIA

    DATE:

    TESTING BY : EMPSCO ENGINEERING CONSULTANTS

    SAMPLE NO. SS-1 BOREHOLE 1 / TEST HOLE 1

    PHYSICAL DESCRIPTION :

    WT. OF UNWASHED SAMPLE+CAN 282.45 Grams

    WT. OF WASHED SAMPLE+CAN 182.50 Grams

    WT. OF CAN 25.50 Grams

    WT. OF UNWASHED SAMPLE 278.45 Grams

    WT. OF WASHED SAMPLE 157.00 Grams

    LOOSES : By Weight 99.95

    Sieve No. Sieve Weight of Weight Percent CUMMULATIVE

    Size Empty Sieve Retained retained Wt. Passing Passing Retained REMARKS

    mm gms gms % gms % %

    1-1/2'' 37.500 0.000% 278.450 100.00% 0.00% Gravel

    1" 25.400 0.000% 278.450 100.00% 0.00% Gravel

    3/4" 19.050 0.000% 278.450 100.00% 0.00% Gravel

    1/2" 12.700 0.000% 278.450 100.00% 0.00% Gravel

    3/8" 9.530 0.000% 278.450 100.00% 0.00% Gravel

    # 4 4.760 507.0 507 0.000 0.000% 278.450 100.00% 0.00% Gravel

    # 8 2.360 0.000% 278.450 100.00% 0.00% Sand

    # 10 2.000 482.0 482 0.000 0.000% 278.450 100.00% 0.00% Sand

    # 16 1.180 0.000% 278.450 100.00% 0.00% Sand

    # 20 0.840 408.0 411.5 3.500 1.257% 274.950 98.74% 1.26% Sand

    # 30 0.590 0.000% 274.950 98.74% 1.26% Sand

    # 40 0.420 382.5 438 55.500 19.932% 219.450 78.81% 21.19% Sand

    # 50 0.297 0.000% 219.450 78.81% 21.19% Sand

    # 60 0.274