Geotechncial Report - Tran Van Viet
Transcript of Geotechncial Report - Tran Van Viet
REPORT ON
GEOTECHNICAL INVESTIGATION
Item: main factory Stage: first phase for construction design
Reported by: P.E. TRAN VAN VIET
HANOI JANUARY 2010
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
2
TEXT
I INTRODUCTION 5 II OUTLINE OF NATURAL CONDITION 5 II.1 Location & Topographic Condition 5 II.2 Regional Climate Condition 5 II.3 Regional Geology Condition
II.4 Regional Earthquake Condition 9 III RESULT OF GEOTECHNICAL INVESTIGATION 12
III.1 Boring and Sampling 12 III.2 Standard Penetration Test (SPT) 12 III.3 Menard Pressuremeter Test (PMT) 13 III.4 Criterion for Soil & Rock Classification 14
III.5 Soil & Rock Description & Layers Division 15 III.6 Engineering Properties of Soil & Rock Layers 18
III.7 Groundwater 24 III.8 Embankment Material 25 IV GEOPHYSICAL EXPLORATION 26 IV.1 Earth Resistivity Sounding Method (RSM) 26 IV.2 Seismic Down-hole Sounding Method (SDM) 27 V GEOTECHNICAL ENGINEERING ANALYSIS 30
V.1 Principal Matters for Geotechnical Analysis 30 V.2 Analysis of Shallow Foundation 30 V.3 Analysis of Pile Foundation 33 V.4 Analysis of Liquefaction of Ground due to Seismic 40 VI CONCLUSION AND RECOMMENDATION 45 REFFERENCE DOCUMENTS 47 APPENDICES
Appendix 1 - Plan of Location of Boreholes Appendix 2 - Geotechnical Cross-Sections Appendix 3 - Record of Boring Logs
VOLUME 2
Appendix 4 - Synthesis Table of Laboratory Test on Soil & Rock Appendix 5 - Tables on Chemical Analysis for Groundwater and Soil Appendix 6 - Tables and Graphics of Pressuremeter Test Appendix 7 - Report on Earth Resistivity Sounding Method Appendix 8 - Report on Seismic Down-hole Sounding Method
Appendix 9 - Graphics and Tables of Laboratory Test on Soil
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
3
INTRODUCTION
This report presents the result on Geotechnical Investigation for Construction Design Stage of the Main Plant ….. The purposes of geotechnical investigation are:
- To clarify, as detail as possible, sub ground condition of the project items. - To make zoning of various subsurface areas with the same sub ground condition for
recommendation of the foundation design. - To analyze various foundation types and geotechnical process for suggestions in
foundation design study based on the comprehensive professional knowledge and local experiences.
The Geotechnical Investigation was carried out on the bases of:
- Geotechnical Engineering Investigation Outline for Construction Design Stage, which is prepared by Consultant Designer.
- Program of Geotechnical Investigation Work prepared by Subsurface Investigation Contractor (USCo).
- Economical Contract No……..: Order …………. ), dated November ….th, 2009, between the ………………………………………………………………. and the Union of Survey Companies (USCo-Vietnam).
- Appropriate actual Vietnamese Standards in combination with the developed countries standards (ASTM, JIS, BSI,CHINA, NF...), which are suggested in use by Ministry Of Construction (see Reference).
* * *
All Site Investigation Information collected from site was analyzed, synthesized and compiled in “Geotechnical Investigation Report” by P.E. Tran Van Viet, USCo.’s Soil & Foundation Specialist and his assistants.
* *
The completed quantity of the soil investigation for “Preliminary Phase” for EPC Construction Design Stage is summarized in the table 1.
Table 1: Summarized Implemented Quantity of Site Investigation
No Work Items Implemented Quantity Method
No. of boreholes 96 Total drilling length Drilling length in Soil
1
Dril
ling
Drilling length in Rock
Wash water rotary drilling and coring
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
4
2
Labo
rato
ry T
est
- Grain-size distribution - Physical Properties - Density - Organic matter - Direct Shear Test. - Unconfined Comp. Test - Triaxial Compression Test UU - Triaxial Compression Test CU - Long term Consolidation. - Short term Odometer - Permeability Test in Lab. - Test on rock cores - Chemical Anal. of Ground water - Chemical Analysis of Soil - Compaction Test of backfill
TCVN (4195 – 4202) –1995 & Appropriate ASTM
Standard Penetration Test (SPT) ASTM 1586-94 3 In-situ Menard Pressuremeter Test (PMT) D10, D60, FOND 72
Earth Resistivity Measurement Ρk (ohm-m) Electrical Deep Sounding
4 G
eoph
- Sy
cal
Wave Velocity by Seismic Down-holes Vp & Vs
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
5
II OUTLINE OF NATURAL CONDITION OF PROJECT’S REGION II.1 LOCATION & TOPOGRAPHIC CONDITION
The Mao Khe coal fired thermal power plant is located on a fairly high-land, which layout at the middle of Dong Trieu and Mao Khe towns and distanced from National Road 18 about 5km toward Northern (see figure 1). The site of main power plant and stack area (MPF) has been already razed-filled (see Drawing MK-KDC-00-G01-02), so it’s fairly smooth with ground elevation may vary about +9m to +10m.
The dimension of MPF is about 454m x 454m, which is distanced to Cam River about 5 Km and distance to Mountains about 3km. II.2 REGIONAL CLIMATE
The Quang Ninh area is located within the Red River Delta, so the climate is which is classified in “AIII.1 Climate Zone” (after QCVN 02:2009/BXD)[13], which are characterized by tropical climate, monsoon with 02 separated seasons:
- The rainy season (or summer season) extends from May to October with the weather is hot, wet, heavy precipitation and usually effected by typhoon, flood and torrent. This season is affected by South-East monsoon, so the wind-direction impacts from Tonkin Gulf. The maximum wind speed of storm may reach to grade XII or more (33.33 m/s or more).
- The Dry season (or winter season) extends from November to April (next year); where the weather is cool, some time coldly, less rainy and usually drizzling rain. This season is effected by North-East monsoon (cold-air from Siberia), so the wind-direction fans from China Continental. According to basic data of Metheology & Hydrology of Viet Nam[13,14], the main information of climate for region of Red-River Delta may be summarized as follows:
- Precipitation: Average annual precipitation about 1554.3mm and average evaporation is about 928.3mm. Yearly, the precipitation is highest in July and August (average monthly 288-318mm) and the lowest values occurred in January (average 18.6mm).
- Temperature: The average annual temperature is about 23.50C. The highest temperature occurred in Mai & June (annual average 280C, Max. 40.80C, Min. 210C; Max. Maximum 42.80C). The lowest temperature occurred in January (annual average 160C; Min. 2.70C; Max. 33.10C).
- Humidity varies monthly in the years with and annual average about is 83-84%. The highest humidity encountered in March & April & August (average 86 - 87%) and lowest humidity encountered in November & December (average 81%)
- Wind speed: varies monthly in the years with the highest values occurred from May to September (annual average is about 28 – 31m/s) and the lowest values occurred from January to March (annual average is 15m/s). II.3 REGIONAL GEOLOGY CONDITION
According to Geology & Mineralogical Map, (scale 1/200 000), Sheet of Quảng Ninh, the sedimentation of this area is characterized by following typical formations. II.4 REGIONAL EARTHQUAKE CONDITION
According to the “Report of seismic hazard in Quang-Ninh Area”, prepared by Prof. Dr. Nguyen Dinh Xuyen (Institute of Physical Globe), the scenario of earthquake in the Dong Trieu - Quang Ninh area (included Mao Khe thermal power plant) is follows:
II.4.1 Tectonic Structure
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
6
II.4.2 Tectonic Faults
II.4.3 Seismicity in Project Area
II.4.4 Selection of Seismic Parameters for Geotechnical Analysis
Based on analysis result of sub-ground condition of the project area and according to
TCXDVN – 375 – 2006, the anti-seismic design parameters may be summarized and presented in the Table 2.
Table 2: Summarise parameters for anti-seismic design from project area
Intensity, Imax (MSK) Grade VII (After Seismic Zoning Map of Intensity)
Grade VII (After correlation in Appendix K from TCXDVN – 375 – 2006)
Ground acceleration (PGA), Amax (g)
0.1118 (After TCXDVN – 375 – 2006 )
Magnitude M, (Richter degree)
Max. 5.9 (After Viet Nam Institute of Physical Globe - VIPG )
Soil type symbol, S C Dense to medium dense Sand and Gravel or stiff Clay with
ten to hundred meters (According to TCXDVN – 375 – 2006 - Table 3.1; Page 30)
Response spectrum horizontal Sc (T)
sTTT
TTSAgSc
TTTTT
SAgSc
TTTSAgSc
TTTTSAgSc
DDC
DCC
CB
BB
4.
5,2..
5,2..
5,2..
0)15,2(1..
2 ≤≤⇒⎥⎦⎤
⎢⎣⎡⋅⋅=
≤≤⇒⎥⎦⎤
⎢⎣⎡⋅⋅=
≤≤⇒⋅=
≤≤⇒⎥⎦
⎤⎢⎣
⎡−⋅⋅+=
η
η
η
η
Response spectrum of elastic displacement SDc (T)
2
.2)( ⎥⎦
⎤⎢⎣⎡⋅=
πTTScSDC
TR (s) 0.15 TC (s) 0.50
Period
TD (s) 2.0
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
7
III RESULT OF GEOTECHNICAL INVESTIGATION
Summarized data of boring, sampling, in-situ test and laboratory test for the Main Power Plant area (MPF), the synthesis of result shall be presented as follows: III.1 BORING AND SAMPLING According to boreholes plan layout for MPF area, 96 boreholes have been disposed by Kadi Consortium for the “first phase” of geotechnical investigation. All drilling and sampling methods are in accordance to Vietnamese Standards in combination with the relevant developed Ameriacano-Erropean’s countries. However, the boring depth of all boreholes has been decided by the Kadi’s Supervisor (Chinese) at site.
11 drill rigs have been mobilized at the for boring exploration and the used are Model XY1A made in China (see Figure 3). Based on equipment characteristics, the rotary drilling method is appropriate for this sub-ground condition, with the function in sampling all type of soil & rock samples and pre-boreholes for in-situ tests (SPT, Pressuremeter and Groundwater…)
Single or double tube core barrels fitted with diamond or tungsten tipped core bits shall be selected at site
depending of the rock type and weathering-jointing degree. The conventional tube core barrel consists of a tube in diameter varies from 76mm to 127mm with 1,5m to 2.0m in length. Basically, drilling and boring method is according to TCVN 2683-1991 & 22TCN 259-2000 and reference to ASTM D 1452 -80 and BS 5390-1999.
Sampling of soil and rock samples in using of equipment and procedure is in accordance to 22TCN 259-2000 and referenced to standards: ASTM D 1587-00 or BS 5930-1999. Generally, the undisturbed samples are recovered by open-samples, thin-walled sampler (see Figure 4) and for hard residual soil and weathered rock; the samples are taken form core in single or double barrel samplers (see Figure 5). The disturbed samples shall be taken in SPT’s split-spoon sampler or rest soil from undisturbed sampling and coring.
III.2 STANDARD PENETRATION TEST (SPT)
Figure 3: Drilling rig Model XY1A
Figure 5: Coring samplers
Figure 4: Standard open sampler
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
8
SPT is the most widely in-situ test for sub ground investigation carried out right in boreholes and the equipment is attached with drilling rig. The result of SPT may provide the sol samples for identification and classification at site and test result for soil state judgment and for foundation analysis. Beside, dynamic resistance (illustrated by number of blows per conventional penetration, N30), the SPT may also provide the undisturbed samples contained in split-spoon sampler (see figure 6) for soil & rock identification, description and some identification tests. According Kadi Consortium’s Consultant’s requirement, the SPT needs to be carried out in all soils and weathered soft rock, with general spacing varies from 2.0m-3m and in every change of the stratum, but total tests are illustrated on table 1.
The equipment and procedure shall be in accordance to TCXD 226:1999 or ASTM D 1578-2000. The bottom of boreholes must be well cleaned before driving test.
Three driving attempts shall be executed for every 15cm penetration and the N30 values shall be the sum of the last two. All SPT result shall be illustrated on the Boring Logs and the values of N30 shall be presented on Charts (see Appendices 2, 3). In case of very dense gravel-cobble (or soft rock) encountered, if the first attempt (blows per 15cm) is more than 50 blows, test may be finished. The recording shall be 50 blows per the real penetration (example first: 50/8cm). Otherwise, the same manner shall be dealing with the second or the third attempt. III.3 MENARD PRESSUREMTER TEST (PMT)
Pressuremeter is an effective In-situ Test Method in Geotechnical Investigation, which is to provide concomitantly engineering properties of soil and rock layers such (Limit pressure “PL” and lateral modulus “EP” along borehole), which are the important parameters for foundation engineering analysis. The PMT is very effective for sub-ground investigation of jointed & weathered rocks; granular soils, where they are impossible in recovering of undisturbed samples or cores for Laboratory Test. Pre-borehole from PMT is also provide the soil for identification, description and simple classification and of soil and rock. The actual equipment used for this geotechnical investigation is the latest version “Type G” (see Figure 7). Testing standards and interpretation are in accordance to the Menard’s Notices and Technique Regles: D10 & D60; FOND.72 from LCPC-SEATRA, France’s Normes & Regles Techniques: NF-P94-110, DTU.13.2 and F62 (Note: There is still no Standard for PMT in Viet Nam).
03 positions of PMT have been requested by China’s supervisors, such as CK46.PR, CK80.PR & CK95.PR). The result is presented in form of 02 kinds of graphics (see Appendix 6):
• “Pressuremeter Test” presents the testing result for every depth in boreholes, which illustrates 03 curves: curve of “standard testing on sonde”, curve of “testing on ground” and curve of “difference time”.
Figure 7: Menard Pressuremeter
Figure 6: Split-spoon sampler from SPT
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
9
• Pressuremeter Logs presents 02 main engineering parameters (PL & EP) in function of depth, along soil & tock columns. Two above parameters may be used for calculation of shallow foundation, pile
foundation and pile subjected to lateral thrust. III.4 CRITERION OF SOIL & ROCK CLASSIFICATION
As mentioned above, based on geological map, there may identified two main zone of stratification within project area: 1) Covering Zone is formatted by Quaternary Deposit (included backfill), which includes two
main geological formations: * Vinh Phuc Formation (ambQIII vp) consists of clayey soil, sandy-gravely soils and organic soil. * Ha Noi Formation (apQII-III hn) consist silty-sandy gravel and pebble.
2) Bed rock Zone is formatted mainly by Hong Gai formation of Triassic System (K2 n-r hg1,2),
which consists of interbedding of claystone (included shale or coaly shale), silty claystone, silty sandstone, sandstone and conglomerate, and sometime quartzitic sandstone. This bedrocks have bee suffered various degree of weathering, from residual soil (grade V-VI) to fresh rock (grade I).
However, in combination with geotechnical investigation result and for “geotechnical
engineering purposes”, the stratification of project area site may shall be identified and classified by following principle: 1) For Covering Zone Based on Geological Stratification, the following strata may be identified and classified: a) Stratum number “1” is Made Ground. b) Stratum number “2” is cohesive soil. For “geotechnical engineering purposes”, stratum 2 shall be identified and classified into “geotechnical layers” based on its state:
• Layer “2a”: Stiff to very stiff Clay (or silty Clay). Commonly, the SPT resistance includes: N30 = 8 – 30.
• Layer “2b”: Soft to medium stiff Clay (or silty Clay) with little or no organic matter. Commonly, the SPT resistance includes: N30 = 2 – 7.
• In case of mud of pound or river-bed, the geotechnical layer number “2c” is continued.
c) Stratum number 3 is intermediate soils (clayey-silty Sand, sandy Clay, Sand intercalated clayey lenses). For “geotechnical engineering purposes”, stratum 3 shall be identified and classified into 02 “geotechnical layers” based on its state:
• Layer “3a”: Loose to medium dense clayey Sand (with/no gravel). Commonly, the SPT resistance includes: N30 = 5 – 25.
• Layer “3b”: Dense to very dense clayey Sand with Gravel (with/no cobble & rock fragments). Commonly, the SPT resistance includes: N30 > 30.
d) Stratum number “4” is Sand and Sand mixed Gravel & Cobble. For “geotechnical engineering purposes”, stratum 4 shall be identified and classified into 02 “geotechnical layers” based on its state:
• Layer “4a”: Medium dense Sand (usually medium to coarse grains) with variable gravel and may be with some cobble or rock fragments. Commonly, the SPT resistance includes: N30 < 30 (13-30).
• Layer “4b”: Dense to very dense Sand (usually medium to coarse grains) mixed variable gravel and may be with some cobble or rock fragments. Commonly, the SPT resistance includes: N30 > 30 (30 - >50).
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
10
e) Stratum number “5” is the second cohesive soil. For “geotechnical engineering purposes”, stratum 5 shall be identified and classified into single “geotechnical layer”, which is generally soft to medium stiff (firm) in state and with little (or no) organic matter and gravel. Commonly, the SPT resistance includes N30 = 2 - 17. 2) For Bedrock Zone Based on Geological Stratification, the following strata may be identified and classified: a) Stratum number “6” is silty Claystone. For “geotechnical engineering purposes”, stratum 6 shall be identified and classified into following “geotechnical layers” based on its weathering-jointing degree and state:
• Layer “6a” is very stiff to hard residual silty Clay, which is product of completely weathered silty Clayestone & Claystone, becoming “clayey soil”. Conventionally the SPT resistance taken: N30 < 70 blows.
• Layer “6b” is soft silty Claystone, which is product of highly to completely weathered silty Clayestone & Claystone, becoming very hard “clayey soil” but very soft “clayey rock”. Conventionally the SPT resistance taken: N30 > 70 blows.
• In cased of less weathering rock and more hard rorck encountered, the “geotechnical layer” number “6c” (or 6d) shall be continued.
b) Stratum number “7” is silty Sandstone. For “geotechnical engineering purposes”, stratum 7 shall be identified and classified into following “geotechnical layers” based on its weathering-jointing degree and state:
• Layer “7a” is very compact residual silty Sand, which is product of completely weathered silty Sandstone, becoming “silty-sandy soil”. Conventionally the SPT resistance taken: N30 < 100 blows.
• Layer “7b” is soft silty Sandstone, which is product of highly to completely weathered silty Sandstone becoming very dense sandy soil but very weal & broken “silty-sandy rock”. Conventionally the SPT resistance taken: N30 > 100 blows.
• In cased of less weathering rock and more hard rorck encountered, the “geotechnical layer” number “7c” (or 7d) shall be continued.
III.5 SOIL AND ROCK DESCRIPTION & LAYERS DIVISION
Based on the site observation and soil identification in combination with the in-situ test and laboratory test, the description of “geotechnical layers” for soils and rocks from ground surface downward as follows:
III.5.1 Covering Zone 1 of Quaternary Deposit (Q) Layer (1): Made ground (MG) consists of silty, sandy clay mixed gravel of rock fragments,
grayish brown to bluish grey in color spotted black, instable in compaction state. This is backfill of “residual soil & weathered rocks” excavated from next hills and mountains.
Made ground is encountered almost area of MPF with thickness varies from 0.3m to 1.4m.
Layer 2a: Siff Clay (CL): This is cohesive soil of clay and silty clay, reddish brown-bluish grey–
grayish iellow mottled in color, stiff to very stiff in state. Top layer is cultivated soil, so it’s usually blackish grey to bluish grey in color with little organic.
Layer 2a is usually developed just from ground surface, sometime under soft organic clay 2b, with layer top encountered from 0.20m (CK62) to 1.3m (CK93) in depth and respectively thickness varies from 1.1m (CK62) to 6.5m (CK06), average about 4m. According to geological map, layer 2a may be in Vinh Phuc Formation (amQIII vp).
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
11
Layer 2b: Soft to firm Clay (CL-CM): This is cohesive soil of clay and silty clay, blackish grey to grayish brown in color, soft to firm (medium stiff) in state. Sometime contained little organic and decay.
Layer 2b is usually developed under layer 2a (sometime overlying); with layer top encountered from 1.7m (CK07) to 7.5m (CK64) in depth and respectively thickness varies from 1.0m (CK71) to 3.5m (CK43). According to geological map, layer 2a may be in Vinh Phuc Formation (abQIII vp).
Layer 3a: Clayey Sand (SW-SC): This is intermediary soil of clayey Sand, ash grey to yellowish
grey in color, loose to medium dense in state. Sometime contained some gravel. Layer 3a is developed under stratum 2 with layer top encountered from 1.2m (CK01)
to 9.1m (CK80) in depth with variable thickness from 1.5m (CK87) to 4.0m (CK40). According to geological map, layer 3a may be in Vinh Phuc Formation (aQIII vp).
Layer 3b: Clayey Sand mixed Gravel (SC-SG): This is intermediary soil in nature of clayey
Sand mixed Gravel, light grey to yellowish grey in color, dense to very dense in state, contained variably gravel, some cobble and rock fragments.
Layer 3b developed jus under layer 3a, with layer top encountered from 5.0m (CK18) to 10.0m (CK93) in depth and respectively thickness varies from 2.9m (CK18) to 12.8m (CK51). According to geological map, layer 3b may be in Vinh Phuc Formation (aQIII vp).
Layer 4a: Medium dense Sand with Gravel (SP-SW): This is generally fine to medium Sand,
light grey to yellowish grey in color, commonly medium dense in state, sometime contained gravel and grits.
Stratums 4 is usually developed interbeddedly with stratum 3. The top of layer 4a is usually encountered in depth from 5.6m (CK22) to 10m (CK33) and respectively thickness varies from 2.3m (CK59) to 7.0m (CK22). According to geological map, layer 5a may be in Ha Noi Formation (aQII-III hn).
Layer 4b: Sand mixed Gravel (SW-SG): This is medium to coarse sand, ash grey to grayish
brown in color, dense to very dense in state, contained variably gravel cobble and rock fragments.
Layer top is encountered from 7.0m (CK65) to 12.1m (CK96) in depth and respectively thickness varies from 1.9m (CK26) to 17.2m (CK67). According to geological map, layer 5a may be in Ha Noi Formation (apQII-III hn).
Layer 5: Soft to firm Clay (CL-CM): This is cohesive soil clay and silty clay , blackish grey to
grayish brown in color, soft to firm (medium stiff) in state. Sometime contained little organic and decay.
Layer 5 is usually overlying developed just upper lying bedrock with layer top encountered from 11m (CK79) to 14m (CK49) in depth with variable thickness from 1.0m (CK49) to 5.2m (CK22). According to geological map, layer 2a may be in Vinh Phuc Formation (bQII-III hn).
III.5.2 Bedrock Zone 2 of Triassic System (T2 n-r hg1,2) Layer (6a): Residual silty Clay (W5,6-CMst): This is product of the completely weathered
claystone silty claystone or siltstone becoming soil of silty clay, brownish grey to grayish yellow in color, stiff to very hard in state. Basically, residual clay (6a) may be identified with soft claystone by lower in soil state (30< N30 <70).
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
12
Layer residual (6a) is usually developed at surface of bedrock silty-claystone, encountered at most boreholes with layer top encountered from 4.0m (CK13) to 19.5m (CK74) in depth with variable thickness from 3m (CK46) to 34m (CK22).
Layer (6b): Soft Claystone (W4-6.Cst): This is highly to completely weathered Claystone and
silty Claystone; thickly bedded no jointed so good coring (RQD > 80%); grayish brown spotted bluish gray in color. By its strength this material may be considered as but very soft rock but hard soil and core may be broken by hand. Generally, this layer 6b is identified with layer 6a by conventional N30 > 70.
Layer soft silty claystone (6b) developed almost project site and depth, usually under residual silty clay. The layer top encountered from 14.5m (CK45) to 29.8m (CK86) in depth with thickness tens meters.
Layer (7a): Residual silty Sand (W5,6-SMst): This is product of the completely weathered silty
sandstone and sandstone becoming residual silty sand with gravel and rock fragments; light gray to ash grey in color, dense to very dense in state. During drilling, soil layer 7a was been disintegrated in silty Sand mixed gravel with some stone-pieces. The identification of residual soil (layer 7a) with broken silty sandstone (layer 7b) by conventional SPT resistance in ranged about 30< N30 <100.
Residual soil (7a) is usually developed intercalate with layer “6a” with variation in depths encountered and thickness.
Layer (7b): Broken silty Sandstone (W4-5.CMst): This is highly to completely weathered
sandstone and silty sandstone becoming very weak silty sandstone. The coring is usually broken and des-integrated in silty sand mixed gravel and rock fragments. The identification broken rock “7b” with residual soil “7a” by SPT resistance, where usually N30 > 100 for layer “7b” and N30 < 100 for layer “7a”. This material may be considered as very soft rock mass but very compact soil.
This broken silty sandstone is usually intercalatedly developed with layer “6b” with variable depth encountered and thickness.
A typical cross-section along turbine hall-boiler-stack is illustrated on the figure 8.
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
13
Figure 8: Typical Cross-section along main “Power House & Stack”
III.6 ENGINEERING PROPERTIES OF SOIL AND ROCK LAYERS
The engineering properties of the geotechnical investigation for MPF are implemented by Laboratory Test and In-situ Tests of SPT and PMT. The in-situ test result is presented in boring logs and geotechnical cross-sections and the laboratory test result is shown in the appendices 2, 3, 4, 5, 6 and 9.
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
14
- For Laboratory Test on soil and rock, 251 soil & rock samples and 02 filling material were selected (by Kaidi’s Supervisor) for laboratory test. The detail testing result is shown in Appendices 4 & 9. Summarized representative engineering properties from laboratory test are shown in the table 3 (a & b).
- In-situ Test of SPT carried out in all boreholes and the detail result is presented boring logs (Appendix 3), geotechnical cross-section (Appendix 2). Representative result of SPT resistance (N30) and deducted engineering parameters are summarized in the table 3.
- Similarly, In-situ Test of PMT (Menard Pressurementer Test) was carried out in 03 boreholes within Main Power Plant (CK46.PR, CK80.PR, CK95.PR). Detail result of PMT is presented in Appendix 6 and representative values of PL & EP, and deducted engineering parameters for every soil and rock layer, are summarized in the table 3 (a & b).
Table 3a: Representative Engineering Properties of Soil & Rock Layers
Summarized Representative Engineering Parameters
No Soil Engineering
Parameters Layer
2a Layer
2b Layer
3a Layers
3b Layer
4a Layer
4b
Result of Laboratory Test Soil Group CL CL-OL SW-SC SW-SG SW-SP SW-SG
Gravel > 4.25mm 1.0 0.5 4.7 7.0 12 No sample Sand: 0.075 – 4.25 41.5 51.3 69.1 69.5 98 Requested
1
Finer < 0.075mm 57.5 48.2 26.2 23.5 0 Moisture, W (%) 23.3 31.7 19.4 19.1 Number of tests 62 16 10 7
2
Standard Deviation (STDEV) 2.3 0.5 1.9 1 Bulk Density, γ (kN/m3) 19.9 18.8 20.5 20.5 Number of tests 56 11 7 6
3
Standard Deviation (STDEV) 0.4 0.9 3 0.2 Dry Density, γd (kN/m3) 16.1 14.5 17.3 17.2 Number of tests 56 11 7 6
4
Standard Deviation (STDEV) 0.6 1.4 4 0.3 Spec Gravity, γs (kN/m3) 27.2 27.0 27 27.0 26.0 Number of tests 62 16 11 7 1
5
Standard Deviation (STDEV) 0.04 0.1 1 0.1 - Void Ratio e 0.690 0.891 0.568 0.577 Number of tests 56 11 7 6
6
Standard Deviation (STDEV) 0.063 0.19 0.036 0.033 Porosity n (%) 40.7 46.4 36.2 36.5 Number of tests 56 11 7 6
7
Standard Deviation (STDEV) 2.1 5.1 1.4 1.3 Saturation Sr (%) 91.8 93.2 88.9 90.3 Number of tests 56 11 7 6
8
Standard Deviation (STDEV) 2.3 3.0 2 0.4 Liquid Limit WL (%) 44.3 43.2 31 31.5 Number of tests 62 16 10 7
9
Standard Deviation (STDEV) 2.1 4.3 5.4 2.9 Plastic Limit WP (%) 22.8 23.5 20.6 22.5 Number of tests 62 16 10 7
10
Standard Deviation (STDEV) 0.8 1.1 1.6 1.2 Plastic Index, IP (%) 21.6 19.7 11 9.0 Number of tests 62 16 10 7
11
Standard Deviation (STDEV) 1.9 3.5 4 3.68 Liquid Index IL 0.019 0.41 -0.1 -0.47 Number of tests 31 16 9 7
12
Standard Deviation (STDEV) 0.115 0.23 0.22 0.3
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
15
Organic (%) 7.16 3.6 Number of tests 7 1
13
Standard Deviation (STDEV) 3.85 -
Permeability k .10-5 (cm/s) 1.266 4.02 40.2 27.1 Number of tests 7 1 1 1
16
Standard Deviation (STDEV) 0.917 - - -
ϕ (deg) 15059’ 14039’ 25015’ No 18 3 1 STDEV 0056’ 1013’ - C (kPa) 31.7 29.7 11 No 18 3 1
17
Direct Shear Test (DST)
STDEV 3.3 4.4 -
ϕ’ (deg) 13044’ 8041’ 14026’ 10023’ No 23 3 3 1 STDEV 0044’ 0036’ 009’ - C’ (kPa) 30.2 26 26.5 31.9 No 23 3 3 1
18
Triaxial Compression
Test
TCT – CD
STDEV 0044’ 2.7 3.6 -
ϕcu (deg) 13041’ 8005’ 13041’ 10002’ No 23 3 3 1 STDEV 0038’ 0050’ 0025’ - Ccu (kPa) 29 24.8 23.6 30.4 No 23 3 3 1
19
Triaxial Compression
Test
TCT - CU STDEV 2.2 3 3.6 -
UCT, qu, (kPa) 85 72.5 78.5 51.4 Number of tests 17 5 1 1
20
Standard Deviation (STDEV) 7.6 11.5 - - Pc (kPa) 120 No 3 STDEV 19 Cc 0.14 No. 3 STDEV 0.038 Cv (cm2/s) No. STDEV a1-2 (m2/KN) 0.00029 0.00041 0.00027 0.00025 No. 40 8 3 1 STDEV 0.00003 0.00012 0.00002 - E0
1-2 kPa) 5850 5000 5880 6060 No. 40 8 3 1
21
Odometer Compression
Test (OTC)
STDEV 370 900 550 -
RESULT OF SPT AND DEDUCTED ENGINEERING PROPERTIES
1 N30 (SPT) 8 - 30 15
2 - 7 4
5÷ 25 11
30 ÷ 50 39
13 ÷ 30 21
30 ÷ 50 44
2 ϕ (deg) deducted After Terxaghi & Peck
0 0 26 ÷ 35 30
36 ÷ 40 37
31 ÷ 36 34
36 ÷ 42 40
3 C (kPa). Deducted After Sower
50.0 ÷ 187.5 93.8
13 ÷ 47 27
0 0 0 0
4 E1-2 (kPa) deducted After Anagnostapoulos
4200 ÷ 14800 10300
2400 ÷ 3900 3000
3900 ÷ 14900 6000
20200 ÷ 29200 24300
17300 ÷ 29200 22900
40000 ÷ 60000 54000
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
16
ESTIMATED BEARING CAPACITY using SPT DATA (N30)
ESTIMATED RESULT OF SHALLOW FOUNDAITON B = D
After CP 2004 – 72 (United Kingdom) 1 Allowable Resistance
Ru (kPa) for Fs = 3 80 – 300
150 < 70 50 – 250
110 300 – 500
400 130 – 300
210 300 – 600
450
ESTIMATED RESULT OF PILE FOUNDAITON After Mayerhof, Martin, Decourt’s Experiences for Pile
Driven
Pile 533 - 2000
1000 133 - 467
267 583 - 2917
1283 3500 - 5833
4550 1867 - 4000
2800 4500 - 7500
6600 1
Allowable Point Resistance,
qa (kPa) with Fs = 3
Bored Pile
533 - 2000 1000
133 - 467 267
250 - 1250 550
1500 - 2500 1950
650 - 1500 1050
1500 - 2500 2200
Driven Pile
18 - 55 30
8 - 17 12
20 - 40 26
45 - 65 54
28 - 45 36
45 - 65 59
2
Allowable Skin Friction, fa (kPa)
with Fs = 2 Bored Pile
8 - 30 15
2 - 7 4
4 - 19 11
23 - 38 29
10 - 23 16
23 - 38 41
RESULT OF PRESSUREMENTER & ESTIMATED BEARING CAPACITY
After FOND.73, Chapter 5.2 & F.62 (France) 1 Limit Pressure
PL (kN/m2) 440 ÷ 1010
703 No
Representative 370 ÷ 1090
730
1450 820÷ 1230
1075 1400÷1420
1410 2 Menard Modulus
EP (kPa) 3500÷9900
6700 - 2300÷5700
4000
20100 9900÷13700
11800 13600÷10500
12050
ESTIMATED RESULT OF SHALLOW FOUNDAITON 3 Allowable Resistance
Ra (kPa) for Fs = 3 147÷337
234 - 123÷363
243
483 273÷410
358 467÷473
470 ESTIMATED RESULT OF PILE FOUNDAITON
Driven Pile
264÷606 422
- 456÷1344 900
1788
1011÷1517 1326
1727÷1751 1739
4 Allowable Point Resistance,
qa (kPa) with Fs = 3
Bored Pile
176÷404 328
- 148÷436 292
580
328÷492 573
560÷568 564
Driven Pile
16÷30 23
- 16÷41 30
49
33÷45 41
48÷49 49
5 Allowable Skin Friction, fa (kPa)
with Fs = 2 Bored Pile
10÷30 23
- 9÷19 15
20
16÷19 18
20÷20 20
Table 3b: Representative Engineering Properties of Soil & Rock Layers (continued)
Summarized Representative Engineering Parameters
No Soil Engineering
Parameters Layer
5 Layer
6a Layer
6b Layers
7a Layer
7b
Result of Laboratory Test Soil Group CL-OL CL
(Re.CMst) CL
(W4-5.CMst) SC
Re.SMst SC
W4-5.SMst
Gravel > 4.25mm 0.4 0.3 0 13.1 0 Sand: 0.075 – 4.25 46.8 36 39.5 70.4 68.5
1
Finer < 0.075mm 52.8 63.7 60.5 16.5 31.5 Moisture, W (%) 29.6 20.0 19.0 22.5 18.3 Number of tests 28 33 85 3 3
2
Standard Deviation (STDEV) 3.7 2.0 1.0 6.1 0.7 Bulk Density, γ (kN/m3) 19.0 20.4 20.5 20 20.7
3 Number of tests 25 32 83 3 3
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
17
Standard Deviation (STDEV) 0.5 0.3 0.2 0.7 0.1 Dry Density, γd (kN/m3) 14.7 17.1 17.3 12.3 17.5 Number of tests 25 32 83 3 3
4
Standard Deviation (STDEV) 0.8 0.4 0.4 0.2 0.2 Spec Gravity, γs (kN/m3) 27.1 27.2 27.2 26.9 27.0 Number of tests 28 33 85 4 3
5
Standard Deviation (STDEV) 0.1 0.1 0.1 0.2 0.1 Void Ratio e 0.851 0.597 0.576 0.660 0.548 Number of tests 25 32 83 3 3
6
Standard Deviation (STDEV) 0.099 0.044 0.036 0.152 0.017 Porosity n (%) 45.7 37.2 36.5 39.2 35.4 Number of tests 25 32 83 3 3
7
Standard Deviation (STDEV) 3.0 1.6 1.4 5.2 0.7 Saturation Sr (%) 93.6 90.3 89.6 91.1 90.3 Number of tests 25 32 83 3 3
8
Standard Deviation (STDEV) 2.6 2.4 2.0 4.4 1.5 Liquid Limit WL (%) 42.6 45.7 45.0 32.4 38.6 Number of tests 28 33 85 3 3
9
Standard Deviation (STDEV) 2.7 1.6 2.1 5.4 4.4 Plastic Limit WP (%) 23.0 23.3 23.3 22.6 24 Number of tests 28 33 85 3 3
10
Standard Deviation (STDEV) 0.9 0.9 1.1 2.0 1.3 Plastic Index, IP (%) 19.6 22.4 21.7 9.8 14.5 Number of tests 28 33 85 3 3
11
Standard Deviation (STDEV) 3.3 1.1 1.6 4.4 5.1 Liquid Index IL 0.33 -0.14 -0.2 -0.26 -0.55 Number of tests 28 33 85 3 3
12
Standard Deviation (STDEV) 0.18 0.10 0.09 0.56 0.33 Organic (%) 3.21 3.3 Number of tests 8 1
13
Standard Deviation (STDEV) 0.94 -
Permeability k .10-5 (cm/s) 1.02 1.637 1.003 Number of tests 1 7 25
16
Standard Deviation (STDEV) - 1.316 0.374
ϕ (deg) 12058’ 15038’ 16000’ 16032’ 18051’ No 7 13 46 1 2 STDEV 2049’ 0056’ 1017’ - 3058’ C (kPa) 28.1 32.8 32.2 25.0 23.0 No 7 13 46 1 2
17
Direct Shear Test (DST)
STDEV 3.3 1.5 2.4 - 13
ϕ’ (deg) 12010’ 13059’ 14009’ 19007’ No 13 8 9 1 STDEV 0017’ 0044’ 0041’ - C’ (kPa) 29.3 31.6 33 13.1 No 13 8 9 1
18
Triaxial Compression
Test
TCT – CD
STDEV 3.8 1.6 0.5 -
ϕcu (deg) 11038’ 13052’ 13041’ 18018’ No 13 8 9 1 STDEV 1037’ 0040’ 0041’ - Ccu (kPa) 27.2 29.0 30.4 9.1 No 13 8 9 1
19
Triaxial Compression
Test
TCT - CU STDEV 4.1 1.5 0.6 -
UCT, qu, (kPa) 76.4 91.3 89.7 67.6 20 Number of tests 8 8 37 2
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
18
Standard Deviation (STDEV) 9.2 2.3 5 13.8 Pc (kPa) 125.8 No 4 STDEV 12.1 Cc 0.132 No. 4 STDEV 0.02 Cv (cm2/s) 0.952 No. 4 STDEV 0.024 a1-2 (m2/KN) 0.00036 0.00026 0.00026 0.00029 0.00025 No. 19 16 52 3 1 STDEV 0.00004 0.00002 0.00002 0.00006 - E0
1-2 (kPa) 5400 6070 6120 5820 6190 No. 19 16 52 3 1
21
Odometer Compression Test (OTC)
STDEV 540 360 340 650 -
RESULT OF SPT AND DEDUCTED ENGINEERING PROPERTIES
1 N30 (SPT) 3 ÷ 17 6
21 ÷ 70 48
> 100
16÷ 75 47
> 100
2 ϕ (deg) deducted After Terxaghi & Peck
0 No correlation
No correlation
No correlation
No correlation
3 C (kPa). Deducted After Sower
18.8 ÷ 106.3 37.5
No correlation
No correlation
No correlation
No correlation
4 E1-2 (kPa) deducted After Anagnostapoulos
2700 ÷ 10900 3600
No correlation
No correlation
No correlation
No correlation
ESTIMATED BEARING CAPACITY using SPT DATA (N30)
ESTIMATED RESULT OF SHALLOW FOUNDAITON B = D
After CP 2004 – 72 (United Kingdom) 1 Allowable Resistance
Ru (kPa) for Fs = 3 37 – 210
75 21 – 500
400
600 160 – 500
400
600
ESTIMATED RESULT OF PILE FOUNDAITON
After Mayerhof, Martin, Decourt’s Experiences for Pile
Driven Pile
200 - 1133 400
1400 - 3333 3200
3333
1333 - 4167 3917
4167
1
Allowable Point Resistance,
qa (kPa) with Fs = 3
Bored Pile
200 - 1133 400
1400 - 3333 3200
2500
800 - 2500 2350
2500
Driven Pile
10 - 33 15
40 - 88 84
88
31 - 65 62
65
2
Allowable Skin Friction, fa (kPa)
with Fs = 2 Bored Pile
3 - 17 6
21 - 50 48
50
12 - 38 35
38
RESULT OF PRESSUREMENTER & ESTIMATED BEARING CAPACITY
(After FOND.72, Chapitre 5.2 & Fascicule 62 - France)
1 Limit Pressure PL (kN/m2)
780 - 870 825
1720
1600 - 2780 2504
No Testing 2320 – 2770 2473
2 Menard Modulus EP (kPa)
5500 - 6500 6000
9600
16300-39500 28300
No Testing 2330 – 38100 29933
ESTIMATED RESULT OF SHALLOW FOUNDAITON 3 Allowable Resistance
Ra (kPa) for Fs = 3 260÷290
275
573 533÷927
835
No Result 773÷923
824
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
19
ESTIMATED RESULT OF PILE FOUNDAITON Driven
Pile 468÷522
495
1032 1333÷2317
900
No Result 2485÷2955
2638 4 Allowable Point
Resistance, qa (kPa)
with Fs = 3 Bored Pile
312 - 348 385
688
148÷436 1252
No Result
1165 - 1385 1237
Driven Pile
25 - 27 26
39
38÷40 40
No Result
60÷60 60
5 Allowable Skin Friction, fa (kPa)
with Fs = 2 Bored Pile
25 - 27 26
39
38÷40 40
No Result
40÷40 40
III.7 GROUND WATER CONDITION
III.7.1 Groundwater Level Recording in Boreholes
Ground water level was recorded in boreholes during drilling and the result is shown in “Record of Boring Logs” (see Appendix 3) and “Geotechnical Cross Section” (see Appendix 2).
Generally, the groundwater level measured in boreholes during drilling varies from 2.15m to 3.13m, which may be mainly contained in granular soils (layers 3a, 3b, 3c and 4a, 4b).
The accurate ground water level have been determined in boreholes CK02, CK59 and CK81, where casing protection and wash pumping carried out for groundwater recording and sampling. The first recording data of groundwater depth, measured at 8h 27 November 2009, are shown: 3.76m (in CK02); 3.41m (in CK59) and 3.50m (in CK81).
III.7.2 Result of Chemical Analysis of Groundwater
02 water samples taken from Cam River and 03 groundwater samples recovered in
boreholes (CK02, CK59 and CK81) for chemical analysis in Laboratory. The detail result of chemical components of groundwater is shown in the Appendix 5 and summarized main corrosive components and corrosion appraisal for building material are presented in the table 4.
Table 4: Summarized Result of Chemical Analysis of Groundwater & Judgment of Corrosion to Building Materials
Chemical Analysis Result of Main Components
Components Unity Value range Components Unity Value range Goundwater in Boreholes
Ca2+ mg / lít 16.03 HCO3 - mgЗ / lit 0.6 – 2.4
pH 7.05 - 7.15 SO4– 2 Mg / lit 10.5 – 35
N+, K+ mg / lít 9.6 - 54.87 CL - Mg / lit 26.23 Mg 2+ mg / lít 9.73 CO2 (free) Mg / lit 13.2 - 26.4
Surface Water from Cam River Ca2+ mg / lít 16.03 HCO3
- mgЗ / lit 1.8 pH 7.45 - 7.50 SO4
– 2 mg / lit 14.0 – 15.5 N+, K+ mg / lít 15.82-16.53 CL - mg / lit 26.23 Mg 2+ mg / lít 9.73 CO2 (free) mg / lit 8.6 – 13.2
Corrosion Assessment to Building Material pH > 5
No corrosive to Ordinary Portland Cement (OPC). Rigid Hardening Portland Cement (RHPC). Portland Blastfurnace Cement (PBFC).
According to
BS 8004-1986 SO4
2- < 300 mg/L No Corrosive to Ordinary Portland Cement (OPC). Rigid hardening Portland Cement (RHPC). Portland Blast furnace Cement (PBFC).
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
20
pH > 6.5 No corrosive to “Normal Building Concrete” SO4
2- < 300 mg/L (CL- < 1000)
No corrosive to “Normal Building Concrete” with Normal Portland cement (NPC), Portland-Pusoland Cement (PPC) and Portland Cement with Slag (PCS)
HCO3 = 0.6 < 0.7 mgЭ/L
“Moderately corrosive” with “Normal Building Concrete”. But no corrosive with “Dense Building Concrete”
CO2 (free) = 26 > a[Ca2+] + b = 22.6
“Slightly corrosive” with “Normal Building Concrete” But no corrosive with “Dense Building Concrete”
Mg 2+ < 1000 mg/L No corrosive to “Normal Building Concrete”
According to CHuΠ II.28.74
(Russia)
(Na+ + K+) < 50 g/L No corrosive to “Normal Building Concrete”
III.8 EMBANKMENT MATERIAL
The project site is fairly high-land and the embankment is constructed for un-smooth ground surface. The plan site has been already filled up before time of site investigation. The filling material is residual soil extracted from next hills & mountains which consists of silty clay mixed gravel and pebble of weathered rock fragments. The embankment was not compacted as standard, but freely filled up, so its is denser next to ground surface and looser at embankment’s bottom, natural soil is organic clay of cultivated soil.
Some samples of embankment material have been recovered for Soil Compaction Test in using of 2.5 kg in ram weight, 30.48mm in falling height, 2118.8 cm3 in mould volume (modified mould). Detail testing result of prepared sample from made ground is presented in Appendices 4 & 9 and summarized result of soil compaction test is follows:
- Maximum Dry Density γdmax = 17.4 – 17.6 kN/m3
- Optimal Moisture Content Wopt = 16.0 – 16.7 % Comment & Recommendation 1:
1) The values of engineering properties of clayey Sand stratum 3 (3a & 3b) as shown in “Table 3”, are representative for “clayey soil” part only, which were recovered as undisturbed samples. However, the principal part of stratum 3 is “sandy soil”, even mixed gravel or cobble, so no undisturbed samples recovered unless disturbed samples taken from SPT’s sampler. Therefore, the representative engineering properties for foundation calculation taken from In-situ Tests (SPT & PMT) shall be more representative. Above situation is the same applied for layers 7a and 7b.
2) The values of PMT engineering parameters presented in “Table 3” (PL, EP) from layers 2b (soft to medium stiff Clay with little organic matter) seems to be not good compatible with SPT’s result and it seems to be “fewer representative” for this layer. The reason may be the testing layer is too thin (CK46.PR) while the “measurement probe”’ is long, so the “measuring sonde” may not be really posited in “soft part of soil” and may be in stiff part. Otherwise, only 3 or 4 locations of PMT were requested to be carried out, so the values must be “fewer representatives” for all geotechnical layers.
3) The values of SPT’s engineering parameters presented in “Table 3” (N30 & deducted parameters) are “more representative” for Quaternary deposit (strata 2, 3, 5 & 5), because they are quite compatible with Laboratory Test on soil samples. However, for the “residual soils” and “weathered soft rocks” (from strata 6 & 7), the SPT’s resistance is less compatible with Laboratory Test result on samples. The reason may be explicable by variation in weathering degree and in-place in deposition, which are always manifested specially characteristic in comparing with transported deposition. In reality, both SPT and Laboratory Test for residual soil & weathered soft rocks are “fewer representative”, so the “prudence” must be taken in calculation. In this case the pressuremeter test seems to be more reliable.
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
21
IV GEOPHYSICAL EXPLORATION IV.1 EARTH RESISTIVITY SOUNDING METHOD (ERM)
IV.1.1 Principle of Sounding Method
The principle of method is simple of a system of electrodes, as illustrated in figure 9,
which used to measure the apparent resistivity of ground. A current is passed through the ground between ‘current electrodes’ (A, B) and the potential drop between ‘voltage electrodes’ (M, N) is measured. Usually all four electrodes are spaced evenly apart and by altering of the spacing ‘L’, the “apparent resistivity” of the ground will change, depending of ground condition, and a plot can be obtained of apparent resistivity against electrodes spacing. This is then matched against standard curves of idealized condition. However, the result interpretation needs the skill and experience person and the reference with boring is required. This technique may provide an inexpensive investigation method for simple ground condition and it uses to detect with both horizontal and vertical variation in ground condition.
There are two methods for arrangement of the electrodes, which may apply for various investigation purposes: After Wenner’s :
ρa = 2 π a R (1) After Schlumberger’s:
ρa = π ( )
.L l
lx R
2 2
2−
(2)
IV.1.2 Result of Earth Resistivity Measurement
In order to determine earth receptivity within shallow depth of project, 11 survey lines were arranged in direction E-W with singed T1 to T11 and 172 measurement points were operated. The spacing of lines varies about 30m to 70m and the spacing of points varies about 20m t0 30m.
Equipment used is digital electrical instrument IPR-12 (made in Canada). The measuring apparent resistivity, ρa (oh-m), were analyzed by Software RESIXIP 2DIV4 manufactured by INTERPREX Firm (USA). Detail result is presentation in Appendix 7 and summarized result is shown in the table 5.
Table 5: Summarized result of earth receptivity measurement
Depth
(m) Range of Receptivity,
ρa (oh-m) Soil Type
Th¨m dß ®Þa vËt lý b»ng ph−¬ng ph¸p ®iÖn tr−êng
Figure 9: Electric Sounding at Site
a a a
C1 C2P2
L
A BM N
l l
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
22
From ground surface to 2m 184 – 714
Made ground & Stiff Clay
From 2m to 5m 115 - 4900 Stiff Clay
From 5m to 7m 98 – 472 Silty Clay & Silty Sand
IV.2 SEISMIC DOWN-HOLE SOUNDING METHOD (SDM)
IV.2.1 Principle of Sounding Method
The seismic down-hole method is ‘economic alternative’ to cross-hole testing (see figure
10). It needs only one borehole inside with the receivers is placed at various depths, while the source is at surface, 2 to 5m away.
Travel-time of body waves (S or P) between surface and receiver (s) are recorded, and then travel-time versus depth plots are constructed from which Vs or Vp of all layers can be determined.
An effective and economic S-wave source consists of a steel-jacked rigid beam weighted down the ground and struck horizontally with the sledge-hammer.
However, if the source is place too close to the borehole, parasitic waves are created and S-wave arrivals cannot be easy identified. In reverse if it’s too far from the source, the direct wave path may not be straight line. These problems are largely avoided by seismic cross-hole method (SCM).
IV.2.2 Result of Wave Velocity Measurement
The seismicity measured by down-holes were operated in 05 boreholes (CK13, CK 17CK 64, CK67 and CK72) with depths from 30m to 60m and total 200 observation points. The sounding procedure, presentation and interpretation result are in accordance to “The Guide of Geophysical Exploration in Suevey for Engineering and Environment” and the equipment used is recording station of Strata Visor NZII-48 manufactured by Geometric (USA).
Detail survey result of seismic down-hole test is shown in Appendix 8. Equipment used is Strata-Visor-NZ made in Geometrics (USA) with sample step 125 μs. The elastic properties of soil and rock shall be determined in using wave’s velocity as follows:
G = ρ Vs
2 (3)
E = 2 (1+ ν).G (4)
ν = 0 5 1
1
2
2
, . ( / )
( / )
V V
V Vp s
p s
−
− (5)
Where: E : Elastic modulus, G : Shear modulus
ν : Poison coefficient,
Figure 10: Sketch of Seismic Down-hole
Geophone
Lateral Impact
Transducer
Wave path
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
23
ρ : Bulk density.
The seismic wave velocity and deducted engineering properties of soil and rock layers are summarized in Table 6:
Table 6: Representative Seismic Parameters and Deducted Engineering Properties
Soil & Rock Layer
ρ kN/m3
Vp m/s
Vs m/s
E Mpa
G Mpa
ν
Covering Zone of Quanternary Deposit Made Ground: Silty Clayey mixe rock fragements
18 474 231 2574.14 960.50 0.34
Layer 2a: (N30 = 8 – 30/ 15) Stiff to very stiff Clay
19.9 1031 249 3627.43 1233.82 0.47
Layer 2b: (N30 = 2 - 7/ 4) Sof to firm Clay.
18.8 742 177 1731.63 588.99 0.47
Layer 3a: (N30 = 5 - 25/ 11) Loose to medium dense clayey Sand
18.5
902
211
2421.50
823.64
0.47
Layer 3b : (N30 = 30 - >50/ 39) Clayey Sand mixed gravel & cobble.
19 1277
292
4762.86
1620.02
0.47
Layer 4a : (N30 = 13 - 30/ 21) Fine to medium Sand
19 1095 244 3325.67 1131.18 0.47
Layer 4b: (N30 = 30 - >50/ 44) Medium to coarse Sand
19 1303 296 4894.22 1664.70 0.47
Layer 5: (N30 = 3 - 17/ 6) Soft to stiff Clayl.
19 948 193 2094.88 707.73 0.48
Bedrock Zone of Weathered Silty Claystone & Silty Sandstone Stratum 6a: (N30 = 21 – 70 / 48) Residual silty Claystone
20.4 1742 440 11610.06 3949.44
0.47
Stratum 6b: (N30 > 100) Soft silty Clayeystone
20.5 1921 522 16308.20 5585.92 0.46
Stratum 7a: (N30 = 26 - 75 / 47) Residual silty Sand
20.0 1595 378 8779.66 2986.28 0.47
Stratum 7b: (N30 > 100) Broken silty Sandstone
20.7 1678 409 10180.40 3462.72 0.47
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
24
Figure 11: Some Figures of Subground Investigation at Project Area
a) Drilling & Sampling b) Standard Penetration Testing d) Undisturbed & Core Samples
d) Menard Pressuremeter Test e) Seismic Down-hole Sounding f) Earth-resistivity Survey
f) Groundwater Measurement Well g) Off-shore Drilling h) Filling Material Sampling
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
25
V GEOTECHNICAL & FOUNDATION ENGINEERING ANALYSIS V.1 PRINCIPAL MATTERS FOR GEOTECHNICAL ANALYSIS
V.1.1 Foundation Analysis for Main Building Structures There are various components within Main Power Plant area (MPF), from which the most heavy and important structures are the turbine hall, boiler, stack, heavy oil storage tank… The other shall be medium to light structures. Therefore, the foundation problems of building structure in MPF area shall be consecutively analyzed as follows:
- Firstly is to analyze shallow foundation founded direct on natural soil for typical sub-ground condition. Generally, different footing sizes and raft foundation are usually taken in computation for various scales of structures.
- Secondly to analyze pile foundation penetrated to good bearing layers and from its order, the various foundation types (driven, bored…) and sizes shall be taken in computation.
- Finally, the appropriate foundation type & size selected for every structure scale is implemented by principle for safe in bearing capacity for foundation supported super-structure and acceptable for structural and foundation displacement.
V.1.2 Stability Analysis for Main Earth Structure
The most important Earth-structure in the Thermal Power Plant is Coal Yard, where dimension of stockpile may attain: B = 20 – 35m, L = 140m, H = 10 – 20m, γ = 16 kN/m2 V.2 ANALYSIS OF SHALLOW FOUNDATION
Shallow foundation founded directly on natural soil is usually applied following types: isolated footing, continued-footing with tie-beams and raft foundation. In calculation of shallow foundation shown that they are satisfied two main below conditions, the application of shallow foundation shall always be the most simple and economic:
- Safety in bearing capacity of ground (qa ≥ PST), and - Acceptable in displacement (St ≤ Sgh
ST, ΔS ≤ ΔSghST),
V.2.1 Calculation Method
a) Theoretical Soil-mechanic Method In this sub-ground condition and superstructure, the theoretical soil-mechanic method
applied is suitable and the Caquot-Kerisel and Terxaghi’s methods are commonly used in many design codes – included in DTU.13.1 - France [8, 2] - with the main expressions:
Resistance: ]).C.NLB0.3(11).(Nqq'N.
B/L)2(1B[
Fs1q coa ++−+
+⋅= γγ (6)
Settlement: St = Σoi
i
Eh.iσ
= Σ hi )P
Plog(e1
C
ci
0zizi
0i
ci +Δ+
σ (7)
b) Menard Pressuremeter Method
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
26
Based on Menard’s theory, the calculated of
shallow foundation in using of PMT’s parameters shall be in accordance to Menard’s regles (D.60) or FOND.72 (LPC) or France’s Codes F62, which are described in “Geotechnical Engineer’s Handbook”[2], the following main expressions shall be applied:
qp = kp. PLe qa = 3)Fs(2
Dkp.PLe−+ γ
(8)
PLe = 1
b 3aP (z).dzL
D b
D 3a
+ −
+
∫ (9)
St = .R.q.λ4,5.Eα
RR.λq.R
3Eν1
3p
α
020
p
+⎟⎟⎠
⎞⎜⎜⎝
⎛+ (10)
V.2.2 Calculation Result
All required design parameters introduced in a computer program of “shallow foundation calculation” as follows:
- Conventional footing dimensions: B = 2m with B/L ratio = 1, 2, 3, 5, 10 and D = 2.0m. - Conventional raft-foundation with dimension: B x L x D = 30m x 40m x 2.0m. - Foundation base founded right on stiff clay (2a) with sub-ground condition of boreholes
CK46 & CK.46.PR and engineering parameters presented in tables 2 and 3,
a) Result of Classical Method A Computer program used with input data as mentioned above and the calculation result
is shown in the table 7.
Table 7: Result of Shallow Foundation Analysis using Classical Method
z
B
D
Log PL
1,5B
PLe
Figure 12: Calculation of Shallow Foundation using PMT method
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
27
b) Result of Pressuremeter Method Similarly, a computer program used with input data as mentioned above and the
calculation result is shown in the table 8.
Table 8: Result of Shallow Foundation Analysis using PMT Method
Comment & Recommendation 2:
• For conventional shallow footings (B = 2m, L/B = 1, 2, 3, 5, 10) founded right upon
stiff clay layer 2a (D = 2m) may provide: + Allowable resistance under foundation base shall be:
qa = 190 kPa (Classical Method), and qa = 255 kPa (Pressurementer Method).
+ Respectively, the expected settlement under net applied pressure (Pn = qa - Po) may reach:
St = 2.8 – 3.6 cm (Classical Method), and St = 1.6 – 2.3 cm (Pressurementer Method).
• For a conventional raft foundation (B = 30m, L = 30m) founded right upon stiff clay layer 2a (D = 2m) may provide:
+ Allowable resistance under foundation base shall be: qa = 292 kPa (Classical Method)
+ Respectively, the expected settlement under net applied pressure (Pn = qa - Po) may reach:
St = 2.8 cm (Pn = 100kPa); = 5.7 cm (Pn = 200kPa); = 8.5cm (Pn = 300kPa)
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
28
V.3 ANALYSIS OF PILE FOUNDATION
Pile foundation must be applied when the shallow foundation was not acceptable. Depending of the sub-ground condition and superstructure, the selection of the appropriate pile type, sizes and bearing layers for an adequate design bearing capacity are required.
V.3.1 Calculation Method for Pile Foundation General formulas for pile foundation include:
Bearing capacity of ground: Qa = S2
F
S1
P
FQ
FQ
+ = S1
SS
S1
PP
F.Af
F.Aq
+ (11)
Bearing capacity of material: Qm = AP.f’C.αC (12)
Selected design load: Qw ≤ Min ( Qa , Qm) (13)
The determination of unit point-resistance (qp) and unit shaft friction (fs) of pile may be calculated by following methods:
1) Meyerhof’s Method using SPT resistance (N30) When pile founded in soils (especially coarse grains soil or highly weathered rock where
no undisturbed samples recovered) the Meyerhof’s method [5, 2] using of N30(SPT) is suitable and commonly applicable (included in TCVN 205:1998). However, it should be in combination with the experiences of Martin’s, Decourt’s, Shoiu-Fukui’s, Yamashita for various pile and soil types. The main calculation expressions as follows:
qp = Kp.N30 L
n.Bb ≤ qL (Kp.N30) (14)
fs = α + β.N30 (15)
2) Menard’s Method using Pressuremeter Data (PL , EP)
For granular soil and weathered rock where the undisturbed samples are impossibly recovered for laboratory testing, the pressuremeter test (PMT) is the most adequate. In calculation of shallow foundation (in using PMT) the following expressions may be applied in accordance to France’s norms [2, 6, 7] D60, FOND.52 Chapitre 5.2 and F60:
qp = kp. PLe (16)
Where:
pLe = 1
b 3aP (z).dzL
D b
D 3a
+ −
+
∫ (17)
fs = qPP
2PPsn
L
n
L
n. −
⎛
⎝⎜
⎞
⎠⎟ with
PP
1L
n≤ (18)
3) Method of Pile Calculation for Rock There are various methods for calculation of pile foundation founded in rock. However,
the Ladanyi & Roy’s method (1974) [12, 2] may be suitable for a fairly good jointed-weathered
PL
Figure 13: Pile Foundation using PMT
De
3a
b Lb
PLeD
z
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
29
rock in using 03 parameters: compressive strength (qu), joint spacing (s), aperture (δ) and including the socket condition (Ksp, d). The main expressions of method are follows:
Qa = qa Ap and qa = qu.Ksp.d (19)
Ksp = 3
10 1 300++
s / Bs. . /δ
(20)
4) Method for Settlement of Pile The settlement of single pile shall be calculated after Woodward, Gardner & Greer‘s
Method [12; 2] and pile group settlement shall be calculated in according to Skempton’s or Vesic‘s empirical methods [12, 2]. Similarly, negative skin friction of pile uses the method described in FOND-72 (LCPC) [6, 2].
V.3.2 Analysis of Driven Pile Driven pile is one of the commonly used in pile foundation, which is usually effective for
moderate structure, caused by its advantages: + Facile in piling work, which is traditionally and commonly used techniques, equipments and procedure for long time. + Quick in piling work and it’s reasonable in cost price. + Easily in controlling of pile material and piling work and driven pile makes densification of surrounding soil, so it’s bearing mobilization is usually over-estimated.
However, driven pile foundation may present some its limitations: + Limited in pile sizes and difficult in penetration through hard lenses, so the mobilization possibility of pile bearing capacity is limited. + Difficult socket in sloping layer of hard soil or rock that is susceptible in failure or slipping of pile, especially pile penetrated through thick soft clay overlain. + Vibration produced during piling that may damage the surrounding structures. In overcoming of vibration from driven piles, the compressed pile (jacked piles) is usually used within city area.
V.3.3 Analysis of Bored Pile
In dealing with important and heavy structure, cast in place bored pile is commonly used because of advantages: + Pile diameter may be widened as required (may be reached to 2m or more), may be deeply penetrated (down to 50/70m or more) and may be penetrated through rock, even sound rock. + Therefore, it may mobilize high to very high bearing capacity (thousand tons/pile or more). + Piling work shall not make vibration and may be carried out at many site conditions.
However, bored pile may be manifested the limitations: + Complicated and sophistic in equipments, techniques, materials and piling technology that lead to high price cost. Therefore, bored pile is un-suitable for small projects. + Difficulty in control of piling and concreting quality, especially flushing-out and clearance of slurry settled at holes-end before concreting and uniformity of concrete. Some recent checking shown that the poor concrete or slurry-concrete mixture is discovered about 0.5m to 1.5m from end of bored piles.
V.3.4 Calculation Result of Pile Foundation
Generally, the thickness of foundation-cap may vary about 2 - 3m, so foundation-cap may be founded right on stiff clay (2a) or on sandy clay (3a) or dense sand with gravel 3b, 3c. Because of thin soft organic clay is usually just overlying upon granular soil stratum (5) or soft rocks, so he pile-tips must be deeply penetrated in such soft rocks (layer 6b or 7b).
A typical “soil-pile modeling” of “main power house & stack” is presented in the figure 14.
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
30
Figure 14: Soil-structure model of pile foundation
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
31
1) Calculation Result of Driven Pile a) Selection of Parameters: • 03 sizes in section: a x b = 0.3m x 0.3m; 0.4 x 0.4m; 0.5 x 0.5m. • Pile depth must be penetrated in dense sand mixed gravel (N ≥ = 30) and
embedded in under soft rock surface about 0.5m with conventional N30 = 50. Therefore, the conventional depth for driven pile is 17m, but the actual depths shall be changed from position to position due to variation of rock surface.
• Conventional borehole CK70 with its SPT resistance (N30) is selected for classical method and boreholes CK.46.PR is selected for PMT method.
b) Computation Result of Driven Pile A computer program for “Pile Foundation Analysis” is established for calculation. The
result of SPT method is shown in the table 9a and result of PMT method is shown in the table 9b.
Table 9a: Calculation Result of Driven Pile using SPT Method
Table 9b: Calculation Result of Driven Pile using PMT Method
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
32
Comment & Recommendation 3:
1) In referring to driven pile with pile-sizes: 0.3; 0.4; 0.5m and embedded about 0.5m in soft rock (6a, 6b, 7a, 7b), the following “design bearing parameters” may be referenced for design study:
a) Working design load of a pile:
• For SPT Method: Qw = 800 kN (Pile 0.3m); Qw = 1200 kN (Pile 0.4m); Qw =
1700 kN (Pile 0.5m). • For PMT Method: Qw = 720 kN (Pile 0.3m); Qw = 1000 kN (Pile 0.4m); Qw =
1300 kN (Pile 0.5m). b) Expected settlement of single pile under design load:
• For SPT Method: Si = 3.7mm (Pile 0.3m); Si = 4.3mm (Pile 0.4m); Si = 5.0mm
(Pile 0.5m). • For PMT Method: Si = 2.7mm (Pile 0.3m); Si = 2.7mm (Pile 0.4m); Si = 3.0mm
(Pile 0.5m). However, the settlement of pile group is higher depending of group dimension.
2) Basically, result of pile foundation calculated by both SPT & PMT methods are quite
agreement. However, above values are typical representative for location of CK.46. The sub-ground condition and the surface depth of soft bed-rock are varied from location to location (about from 15m to 18m), so the actual pile depth (or length) shall be varied accordingly.
2) Calculation Result of Bored Pile
a) Selection calculation parameters • Diameters of pile for computation shall be selected conventionally 03 sizes:
Ф0.8m, Ф1.0m, Ф1.2m. • Pile penetrated in soft rocks as bearing layer (6b or 7b) with conventional 02
embedment length: Lp1 = 5m and Lb2 = 10m.
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
33
• Representative location for calculation is borehole CK46 using for SPT method, on which the N30 resistance is conventionally taken maximum 50 for both soft silty claystone (6b) and weak silty sandstone (7b). For PMT method, the pressuremeter log of CK.46.PR is selected for typical calculation.
b) Computation Result
A computer program for “Pile Foundation Analysis” used for calculation and the result of
SPT method is shown in the table 10a and result of PMT method is shown in the table 10b.
Table 10a: Calculation Result of Bored Pile using SPT Method
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
34
Table 10b: Calculation Result of Bored Pile using PMT Method
Comment & Recommendation 4:
1) In referring to bored pile with pile-diameters: Ф0.8m, Ф1.0m, Ф1.2m, embedded about from 5m to 10m in soft silty claystone (6b) or weak silty sandstone (7b), may mobilize following design parameters:
c) Working design load of a pile:
• For SPT Method (conventionally taken max-value of N30 = 50):
+ Embedded 5m in 6b: Qw = 2750 kN (Ф0.8m); Qw = 3840 kN (Ф1.0m); Qw = 5080 kN (Ф1.2m).
+ Embedded 10m in 6b: Qw = 3230 kN (Ф0.8m); Qw = 4430 kN (Ф1.0m); Qw = 5780 kN (Ф1.2m).
• For PMT Method:
+ Embedded 5m in 6b: Qw = 2530 kN (Ф0.8m); Qw = 3320 kN (Ф1.0m); Qw = 4170 kN (Ф1.2m).
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
35
+ Embedded 10m in 6b: Qw = 3030 kN (Ф0.8m); Qw = 3950 kN (Ф1.0m); Qw = 4926 kN (Ф1.2m).
d) Expected settlement of single pile under design load:
• For SPT Method:
+ Embedded 5m in layer 6b: Si = 6.6mm (Ф0.8m); Si = 9.9mm (Ф1.0m); Si = 14.9mm (Ф1.2m).
+ Embedded 10m in layer 6b: Si = 6.7mm (Ф0.8m); Si = 10.2mm (Ф1.0m); Si = 14.8mm (Ф1.2m).
• For PMT Method: + Embedded 5m in layer 6b: Si = 8.2mm (Ф0.8m); Si = 9.5mm (Ф1.0m); Si =
10.8mm (Ф1.2m). + Embedded 10m in layer 6b: Si = 9.7mm (Ф0.8m); Si = 10.7mm (Ф1.0m); Si =
11.9mm (Ф1.2m). However, the settlement of pile group shall be higher depending of group dimension.
2) Basically, result of pile foundation calculated by both SPT & PMT methods are quite
agreement. However, above values are typical representative for location of CK.46. The sub-ground condition and the surface depth of soft bed-rock are varied from location to location, so the actual pile depth (or length) shall be varied accordingly.
V.4 ANALYSIS OF LIQUEFACTION OF GROUND DUE TO SEISMIC V.4.1 Japan’s Method for Liquefaction due to Seismic
According to “Standard Specifications for Highway Bridge, Vol.- Earthquake-Proof
Design; 1996 Japan Highway Association”, liquefaction of ground due to earthquake is presented as follows:
1) Necessary Condition: The saturated sandy soil has a possibility to occur the
liquefaction phenomenon, which the ground becomes liquid state due to the increase of pore water pressure caused by seismic repeated shearing force and the sandy soil spouts on the ground surface, in case of fulfilling as the following three conditions:
- Depth of ground water is in being the range between 0.0 to 20 m from ground surface, - Fine grained content (Fc) is less than 35 %, or the plastic index (Ip) is less than 15 in
case of that Fc is more than 35%, - Average grading size (D50) is less than 10.0 mm and the grading size of 10 % (D10) is
less than 1.0 mm.
2) Calculation Method: In the case of that the below FL-value is less than 1.0 the ground is shall be regarded to be subjected by liquefaction:
FL = LR
(21)
Where, FL : Liquefaction resistance rate L : Shearing stress ratio during earthquake R : Dynamic shearing strength ratio
- Shearing Stress Ratio during Earthquake: L
'KrL
v
vhd
σσ・・=
(22)
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
36
Where rd : Decrease coefficient proportional to depth rd = 1.0 - 0.015z, in which z is depth (m) Kh : Design horizontal seismic coefficient, σv : Total overburden pressure (kg/cm2) σ’v : Effective overburden pressure (kg/cm2)
- Dynamic Shearing Strength Ratio: R
7.1Na0882.0R:14Na =<
(23) 5.46 )14Na(106.1
7.1Na
0882.0R:Na14 −×+=< − ・ (24)
Where, for Sandy Soil: Na = c1N1 + c2 (25)
7.0'N7.1N
v1
+=σ
・
⎪⎪⎩
⎪⎪⎨
⎧
<−
<<+
<<
=
)Fc%60(120/Fc
%)60Fc%10(50/)40Fc(
%)10Fc%0(1
c1
⎪⎩
⎪⎨⎧
<−
<<=
)Fc%10(18/)10Fc(
%)10Fc%0(0c2
for Gravely Soil:
)2
Dlog36.01(NNa
501 10−= ・ (26)
7.0'N7.11N
v +=σ
・
Where, N : N-value from standard penetration test N1 : Corrected N-value, equal with 1.0 kg/cm2 of effective Over-burden pressure
Na : Corrected N-value considered with fine grained content Fc : Fine grained content (%)
2) Result of Liquefaction Determination after Japanese’s Method
Based on the result of the sub-ground condition, the following observations may be
provided: - The stratum 3 is basically clayey sand, fine sand or sand interbedded lenses of silty clay.
Layer 3a is generally loose to medium state and no or little gravel, so the liquefaction possibility is susceptible occurred. The other dense gravelly sand layers (3b, 4a, 4b) may difficulty to be liquefied.
- More-ever, above loose silty fine sand is mostly under groundwater level, so the liquefaction this more susceptible to be occurred. The groundwater depth recorded in April 2009 (starting of rainy season) is about 1.9m. However, groundwater depth recoreded in Dember 2009 (dry season) is about 3.2m, so the depth of 2.0m shall be taken in calculation.
The result of liquefaction analysis due to a “computer program” for some typical locations
within project area is shown in the table 11.
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
37
Table 11: Calculation Result of Liquefaction Possibility
a) Result from Soil Investigation in March 2009
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
38
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
39
b) Result from Soil Investigation in December 2009
Comment & Recommendation 5:
Based on liquefaction analysis from both stages (feasibility soil investigation stage for
bidding implemented in March 2009 and preliminary stage for construction design implemented in December 2009), the following comments and recommendations may be made:
1) The liquefaction may be occurred in layer 3a (silty fine sand, clayey sand) developed under groundwater, especially it’s susceptible occurred in loose soil (N30 < 10). Result of both analysis methods (Japan’s standard & China’s standard) shown that the liquefaction may be occurred with seismicity grade VII to VIII in intensity.
2) Based on “Japan Highway Bridge Design Standard”, the design parameter (coefficient of ground reaction, skin friction of pile, and elastic modulus of ground, and so on) shall be reduced according to FL-value, by multiplying with the following decrease parameter (DE):
Table 12: Decrease Parameter DE
FL-value Depth
(m) Decrease coefficient
DE 0 < z < 10 0 FL < 0.6 10 < z < 20 1/3 0 < z < 10 1/3 0.6 < FL < 0.8 10 < z < 20 2/3 0 < z < 10 2/3 0.8 < FL < 1.0 10 < z < 20 1
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
40
VI CONCLUSION AND RECOMMENDATION 1 - Subsurface condition of project item is fairly clarified by two main geological zones (unless
made ground), which is described from ground surface as follows:
a) Quaternary System (Q) includes Vinh Phuc Formation (abQIII vp) anf Ha Noi Formation (abQII-III hn), which consists of: Stiff to very stiff brown clay (2a), sof to firm grey silty Clay (2b); loose to medium dense clayey sand (3a), medium dense clayey sand mixed gravel-cobble (3b), medium dense sand with little or no gravel (4a), dense and coarse sand mixed gravel-cobble and soft to medium stiff clay (5).
This Quaternary Zone is usually developed from ground surface to about 15-18m in depth.
a) Weathered Rocks of Cretassic System, Hong Gai Formation (T2 n-r hg1,2) includes claystone & silty claystone (stratum 6), silty sandstone & sandstone (stratum 7), which may be classified by various jointing-weathering degree and strength (6a, 6b… and 7a, 7b…). Basically, these silty claystone and sandstone interbedded each other, highly to completely weathered becoming very soft in rock state, but very hard in soil state, which are developed to more than 60m in depth.
2 - The engineering properties of “geotechnical layers” for above soils and rocks are studied by
both in-situ test (by SPT, MPT) and laboratory test in soil and rock samples, which are presented in the paragraph III.6 and tables 3 (q,b).
3 - The groundwater level was measured in boreholes and the result is presented in paragraph
III.7. The static water depth recorded during drilling (at 8h 27 November 2009), are shown that: 3.76m in CK02; 3.41m in CK59 and 3.50m in CK81. This groundwater depth is recorded in dry season, so in rainy season, groundwater level shwll be higher.
The chemical analysis of groundwater and corrosion to building material is shown in the table 4.
4 - The geophysical exploration was carried out by earth resistivity method, seismic down-hole
sounding method. Detail result is shown in Appendices 7, 8 and summarized result is shown in the tables 5 & 6.
5 - Shallow foundation founded right upon stiff clay (layer 2a) may mobilize allowable bearing
resistance qa ≠ 190 – 220 kPa (of footing width B = 2m width) may attained St = 3 - 5 cm , (under net applied pressure Pn). The design parameters may be referenced to “Comment and Recommendation 2”, which may be suitable for light to medium heavy building structures.
5 – Driven Pile shall be alternatively useful for moderately heavy structure, where shallow
foundation is not compatible. The pile-tip should be penetrated in dense sand (layers 3b, 4a, 4b). However, the pile tip must be penetrated through soft to firm clayey layer 5 (where it’s encountered) and at least 0,5m in soft claystone (6b). The typical design loads of various pile-sizes may be referenced to “Comment and Recommendation 3”.
6 – Bored Pile must be used for very heavy and important structures and the pile must be
embedded deeply in soft rocks of silty claystone (6b) and silty sandstone (7b). Detail analysis result is described in paragraph V.3 and the typical design parameters may be referenced to “Comment and Recommendation 4”.
7 - The loose silty-clayey fine sand layer 3a is susceptible with liquefaction due to seismic
intensity grade VII & VIII. Analysis result presented in paragraph V.4 and “Comment & Recommendation 5” may be referenced for design study.
Union of Survey Companies (USCo.) 91 Phung Hung, Ha Noi, Viet Nam - Phone: (04) 39231540, Fax: 38245708
41
8 – Note: All above geotechnical analysis (on shallow, deep foundation and embankment) were
carried out at some representative locations of sub ground condition and using the calculation methods stated in the report. The result shall be considered as “reference for design study” only. The detail foundation design on every project structure depends of the sub ground condition at such position, in using of appropriate engineering parameters of this report and of the commonly used calculation methods, which are the “task and responsibility” of the Project’s Consultant Designer.
Hanoi 30 December 2009 Geotechnical Specialist: TRAN VAN VIET
REFERENCE DOCUMENTS [1] Việt Nam Construction Engineering Standards – NXBXD, 1997. TCXDVN 375: 2006
Anti-seismic Design for Engineering Building. TCVN 205:1998 – Pile Foundation Design. TCVN 206:1998 Bored Pile – Construction Requirement.
[2] Trần Văn Việt, 2004 – Geotechnical Engineer’s Handbook - Construction Engineering Edition, Ha Noi
[3] Trần Văn Việt, Vũ Công Ngữ, Nguyễn Văn Túc, 2007 – Soils, Groundwater & Foundation Engineering of Ha Noi Area and Surrounding, 2007 – Scientific research - VUSTA, Ha Noi
[4] “Report on Soil Investigation for Project” – implemented in 2009. [5] Canadian Foundation Engineering Manual, 1985 – Canadian Geotechnical Society –
Canada. [6] FOND 72 – Document LCPC/SETRA. Ministry de la Construction, October 1972 [7] DTU 13.2 – Travaux de Fondations Profondeur pour le Batiments, 1978. [8] F62. T5 - Regles Techniques de Conception de Calcul des Foundations de Genie Civil,
1995, Paris. [9] M. Carter – Geotechnical Engineering Handbook, 1984 – Pentech Press, London. [10] Earthquake Proof Design, 1996 – Japan Highway Association. Tokyo [11] M.J. Tomlinson – Foundation Design and Construction, 1980 – Pitman, London. [12] DAS - 1985 – Principle of Foundation Engineering Design. [13] Nguyễn Trọng Hiệu, Trần Thanh Xuân (Chủ biên), 1989. Số liệu Khí Tượng Thủy văn
Việt Nam (Chương trình tiến bộ KHKT cấp Nhà nước 42A (Tập I – Số liệu khí hậu, do TS. Nguyễn Trọng Hiệu chủ biên; Tập 2 – Số liệu thủy văn. TS. Trần Thanh Xuân chủ biên).
[14] QCVN 02 : 2009/BXD - Quy chuẩn kỹ thuật quốc gia số liệu điều kiện tự nhiên dùng trong xây dựng.
[15] Geological & Mineral Resourses Map of Viet Nam, 1: 200 000. Ha Noi.
[16] Thành tựu nghiên cứu Vật lý Địa cầu 1987 - 1997; Viên Vật lý Địa cầu thuộc Trung tâm KHTNCNQG, Hà Nội.
[17] George Gazetas, Ph.D, P.E – Foundation Vibrations. Foundation Engineering Handbook – Hsai Yang Fang.
[18] Techniques de Menard - Regle D’Utilisation des Techniques Pressiometriques et D’Exploitation des Reultatas Obtenus Pour le Calcul des Foundations – Notice General D60, 1975.