Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... ·...

23
Georgian Global Utilities BGEO Investor day 9 November 2017 Tbilisi, Georgia Speaker: Archil Gachechiladze

Transcript of Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... ·...

Page 1: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

Georgian Global Utilities

BGEO Investor day

9 November 2017

Tbilisi, Georgia

Speaker: Archil Gachechiladze

Page 2: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

Contents

• Industry overview

• Company overview

• Performance highlights

• Company strategy

page 2

Page 3: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

28%

72%

GGU (Tbilisi, Rustavi, Mtskheta)State

30%

70%

Telasi (Tbilisi)

Energo-Pro (regions)

Industry overview – utility market

Largely privatized utility sector with high barriers to entry

– Utilities sector in Georgia growing at CAGR 8.3% (2006-2016)

– Large part of the industry privatized, except for WSS utilities and irrigation

– Reforms in progress for aligning the sector with the EU regulations

GGU - only profitable player on Georgia’s WSS market

– Largely depreciated water and sanitation infrastructure with average water losses at

c. 70% (4-5 times higher than in western Europe)

– Average collection rates from households in Georgia - c. 50%

– GGU’s average collection rates - around 96%

– Water utilities other than GGU heavily subsidized by state

– c. 47% of the population serviced on the municipal level with bad service quality,

frequent interruptions and poor coverage

page 3

30%

63%

7%

KazTransGas (Tbilisi)

Socar Group

Other

Natural Gas (privatized)

Water

Electricity (privatized)

Coverage by population

Page 4: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

New CAPEX

Existing assets

Net book value

Total operating

expenses

WACC Return on assets

Depreciation

Allowed revenue

page 4

• Independent regulator – GNERC1

• New tariff setting methodology since August, 2017

• 3 year tariff setting period

• WACC of 15.99% for first regulation period (2018-2020), up from previous

13.54%

Note 1: GNERC stands for Georgian National Energy and Water Supply Regulatory Commission

Industry overview – water tariff setting methodology

Page 5: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

-

200

400

600

800

1,000

1,200

1,400

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Generation, renewables Generation, TPPs

Net imports Internal consumption

page 5

• Electricity deficit during Sep-Apr

• 8-month PPA policy in place

• 20.3% of total consumption produced by gas-fired TPPs, 4.2% - imported (2016 data)

Source: ESCO GWh

Electricity supply and consumption, 2016 Actual and forecasted consumption

2,000

7,000

12,000

17,000

22,000

Generation, actual Generation, forecast Consumption, +5%

6.1

TWh

GWh

Electricity exports and prices, 2011-2017

Source: ESCO, Geostat, EPIAS

GWh USc/kWh

• 9% growth of internal consumption in 9m 2017

• Consumption growth forecasted at 5% CAGR in coming 15 years

• Anticipated deficit of 6.1TWh by 2030

• Decreasing trend of electricity exports to Turkey since 2015 due to increased internal consumption

Industry overview – electricity market

219 79

236 419

294 284

712

449 450

309

240

265 401

-

3

6

9

12

-

200

400

600

800

1,000

2011 2012 2013 2014 2015 2016 9M17

Export to Turkey (LHS) Export to other countries (LHS) Price in Turkey (RHS)

Page 6: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

• Industry overview

• Company overview

• Performance highlights

• Company strategy

page 6

Contents

Page 7: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

At a glance

Utility Energy

GWP - Tbilisi Water

Rustavi Water

Mtskheta Water

Gardabani

WWTP1

Zhinvali HPP

(130.0MW)

Tetrikhevi HPP

(12.0MW)

Population

coverage:

c. 1.4m

Saguramo HPP

(4.4MW)

Pshavela HPP2

(2.9MW)

Committed projects

Operating HPPs

page 7

Notes:

1. WWTP stands for wastewater treatment plant

2. Under operating lease

Bodorna HPP

(2.5MW)

under construction

Mestiachala HPP

(50MW)

under construction

Zoti HPP

(44.3MW)

under development

EBITDA 2017E: GEL 62m EBITDA 2017E: GEL 10m

Company overview – GGU Group

Page 8: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

EXISTING

• 130MW Zhinvali HPP

• 12MW Tetrikhevi HPP

• 4.4MW Saguramo HPP

• 2.9MW Pshavela HPP

under management

UNDER

CONSTRUCTION

• 50MW Mestiachala

HPP

UNDER

DEVELOPMENT

• 44.3MW

Zoti HPP

• Natural monopoly in water supply and wastewater

services for Tbilisi, Rustavi and Mtskheta

• Serves c. 548K customers – 1.4m people

(1/3 of Georgia)

• Total water production – c. 560m m3

Wastewater

treatment plant

serves customer

base of water utility

companies

Notes:

1. Bodorna HPP with 2.5MW installed capacity is under construction on the existing infrastructure, which is not included in 149.3MW

2. UC refers to under construction

3. UD refers to under development

BGEO Group 100%

GGU

Utility

Tbilisi Water Utility

Rustavi Water Utility

Mtskheta Water Utility

Gardabani WWTP

Energy

149.3MW1 Existing Hydro

50MW

UC2 Hydro

44.3MW

UD3 Hydro

100MW Pipeline Hydro

100MW

Pipeline Wind

50MW

Pipeline Solar

RP Global 35%

page 8

Company overview – structure by shareholders and activities

Page 9: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017 page 9

Description of business cycle

Water production Water treatment, transportation and

dispatch Water distribution and sales

Wastewater collection and

treatment

– River water intake

– Wells

– Infiltration basins

– Wastewater collection system

– Gardabani WWTP

– 5 business centres managing the whole

network in Tbilisi

– Division by districts

Production Distribution Treatment

– Dispatch centre

– Trunk pipelines (<500dm)

– 6 water treatment plants

– 55 pumping stations

– 101 reservoirs

Note 1: Schematic diagram given above represents infrastructure of Tbilisi water supply

Company overview – utility business cycle

Page 10: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

2011 2012 2013 2014 2015 2016

Number of households Number of legal entities

– 2 types of customers:

• Legal entities – 100% metered clients

• Households – c. 75% non-metered clients

– Collection rates are around 96%

– Non-paying customers cut off the power supply

– c. 70% water losses

Efficiency gains

Number of clients 2011-2016 (thousand)

Collection rates 2011-2016

Overview

543

page 10

93.2%

95.3%

96.9%

95.6% 96.0% 96.0%

2011 2012 2013 2014 2015 2016

Collection rates37.4%

18.4%

32.1%

5.4%

6.4%

Level 0

Level 1

Level 2

Level 3

Level 4

Level 5

Elevation

0.4% Metering program and

grid rehabilitation

works focused on

higher elevation zones

kWh/m3

0.0

0.4

0.7

0.6

0.7

1.2

Company overview - utility sales

527 517 502 489 457

% of total water supply

Page 11: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

Company overview – share purchase agreement

page 11

– In 2008, the Government of Georgia sold 100% shares in GWP, RWC and MWC to GGU

– BGEO Group acquired 25% interest in GGU in 2014 and became 100% shareholder in 2016

– Within the Share Purchase Agreement (SPA), the government required the buyer to carry out number of obligations:

– There are two remaining obligations under SPA that are due in May, 2018 (all other obligations are already duly performed)

– Gardabani WWTP reconstruction is on track

– USD 220m investment obligation is also in the set timeline

January, 2014

Uninterrupted (24h) water

supply in Mtskheta

Rehabilitation of sewage

system in Gardabani

Uninterrupted (24h) water supply

in Tbilisi (new borders)

Elimination of effluent discharge

into Mtkvari river

Uninterrupted (24h) water

supply in Tbilisi (old

borders)

Rehabilitation of wastewater

treatment plant in Gardabani

January, 2011 May, 2013

January, 2013

January, 2015

May, 2018

Water quality corresponding to WHO standards in Tbilisi and Mtskheta

Investment obligation of not less than USD 220m (2008-2018)

Completed investment obligations – confirmed by the expert opinions and the Government

Completed investment obligations – confirmed by the expert opinions (Grant Thornton and Samkharauli National Forensics Bureau)

May 2008

Signing SPA

Outstanding investment obligations

Page 12: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

2017

50 MW HPP (Svaneti Hydro)

Status – under construction

Project cost – USD 62.7m

Completion – by the end of 2018

2.5 MW HPP (Bodorna HPP)

Status – under construction

Project cost – USD 3.6m

Completion – by September, 2018

2018

44.3 MW HPP (Zoti Hydro)

Status – Under development

Project cost – USD 57.5m

Completion – by December, 2020.

Long-term pipeline1

Hydro

Capacity – up to 100 MW

Project cost per MW USD 1.2 - 1.5m

Wind

Capacity – up to 100 MW

Project cost per MW: up to USD 1.3m

Solar

Capacity – up to 50 MW

Project cost per MW: up to USD 1.1m

Note 1: Pipeline projects are at a very early stage of development, therefore given information is highly indicative

page 12

Company overview – energy project pipeline

Page 13: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

Market price

(67.5%)

Project main characteristics

• Location – at the bottom of glacier, near city Mestia,

Svaneti region

• Cascade of 2 power plants - 20 MW and 30 MW

• Penstock routes – 2 km and 8 km

• Planned commissioning – September, 2018

Monthly generation and price

page 13

Note 1: equity IRR is calculated on the assumption that the HPP is sold as a 8% yielding asset after five years of operation

USD/MWh % of annual generation

(LHS) (RHS)

Company overview – energy (Svaneti hydro / 50 MW)

Project highlights

Total project cost (US$ k) 62,720

Total cost per MW (US$ k) 1,254

Nominal installed capacity (MW) 50.1

Net annual generation (GWh) 174.3

PPA for 8 months (cents) 5.5c

Debt/Equity structure 70/30

FCFF/investment (%) 10.1%

Equity IRR 19.5% 1

0%

6%

12%

18%

24%

-

50

100

150

200

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

PPA Generation

Page 14: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

Market price

(48%)

page 14

(LHS) (RHS)

USD/MWh % of annual generation

Company overview – energy (Zoti hydro / 44.3 MW)

Note 1: equity IRR is calculated on the assumption that the HPP is sold as a 8% yielding asset after five years of operation

Project highlights

Total project cost (US$ k) 57,485

Total cost per MW (US$ k) 1,297

Nominal installed capacity (MW) 44.3

Net annual generation (GWh) 164.3

PPA for 8 months (cents) Nov-Feb: 4.4c

Mar-Apr-Sep-Oct: 5.5c

Debt/Equity structure 70/30

FCFF/investment (%) 11.0%

Equity IRR 19.4% 1

Project main characteristics

• Location - village of Zoti, Guria region in Western Georgia

• Cascade of 2 power plants – 24 MW and 20 MW

• Penstock routes – 1.9 km and 5.8 km

• 2 tunnels – 1.2 km and 1.6 km

• Planned commissioning – December, 2020

44 44 55 55 55 55

44 44

0%

5%

10%

15%

20%

-

30

60

90

120

150

180

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

PPA Generation

Monthly generation and price

Page 15: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

-

200

400

600

800

1,000

1,200

1,400

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Generation, renewables Solar Consumptions

Internal Consumption

page 15

9% 8% 8%

9% 9% 7% 7% 7%

9% 9% 10% 9%

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

% of annual output

4% 3% 5%

14%

18% 15%

9% 7% 7% 8%

6% 5%

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

% of annual output

Distribution of wind generation Typical distribution of a run-of-river HPP

Source: ESCO GWh

Deficit

• Compared to HPPs, wind power plants (WPPs) have more even distribution

throughout the year, adding around 1.5x more output to domestic supply deficit

in the eight winter months

• Current PPA policy grants fixed tariffs for 8 winter months

• Merchant risk for wind projects is c.30% in May-Aug, as opposed to 48% on

average in run-of-river HPPs

• Lower merchant risk means higher leverage, better financing terms, and

enhanced returns on shareholders’ equity

Georgian electricity balance, 2016

Company overview – why invest in wind power

Page 16: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

100MW

100MW

20MW

50MW 100MW

20MW

Identifying wind project opportunities

• Feasibility MoUs available for 7 sites

• 3 locations at first stage of development

• Full year measurement data on 3 sites available by March 2018

• Targeting 100MW construction in 2019

Further development stage

Feasibility study stage

Existing government-owned wind farm

page 16

100MW

30MW

Tbilisi 1

Martkopi Tkibuli

Tbilisi 2

Company overview – energy (wind projects)

Page 17: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

50MW

50MW

• Exclusivity Feasibility MoUs with the

Government on 10 locations

• 2 locations defined for further development

(measurement stage)

• To make solar projects feasible:

– Better tariff terms from Government (at

least 15.6 US cents for 8 months or

10.3 cents for 12 months), or

– Decrease in hard cost/MW (at least by

50% to EUR 375k per MW)

Identifying solar project opportunities

Further measurement stage

Early feasibility stage

page 17

Company overview – energy (solar projects)

Page 18: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

• Industry overview

• Company overview

• Performance highlights

• Company strategy

page 18

Contents

Page 19: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

22 21 25

59 64 8 8

8

23 24

2 2 4

6 7

2 1 2

3 4

34 32 39

91 99

0

15

30

45

60

75

90

105

3Q16 2Q17 3Q17 9M16 9M17

Water supply to legal entities Water supply to individuals Electric power Technical support and other

20 23 22 24 23 23 27 12 29

97 48 17

106 166

429

0

100

200

300

400

500

2014A 2015A 2016A 2017E 2018E 2019E

Maintenance capex Development capex (water) Development capex (energy)

55 61 67 72 85

107

45% 51% 52% 53% 55%

59%

0%

15%

30%

45%

60%

75%

-

20

40

60

80

100

120

2014A 2015A 2016A 2017E 2018E 2019E

page 19

Strong performance

Revenue composition

EBITDA and capex evolution

GE

L m

illi

ons

EBITDA 2014-2019E Capex 1 2014-2019E

GE

L m

illi

ons

GE

L m

illi

ons

CAGR: 11.4%

Note 1: Capex figures are presented including VAT

50 36 57

226 237

469

+9%

Water: Funding secured from FMO, DEG, EIB, local

bonds – GEL 265m

Energy: Funding secured from Proparco, DEG, OeeB

for Svaneti Hydro (D/E ratio of 70/30)

17 16 22

44 52

-

10

20

30

40

50

60

3Q16 2Q17 3Q17 9M16 9M17

EBITDA

EBITDA

52% 50% 49% 56% 48%

GE

L m

illi

ons

EBITDA margin

+18%

Performance highlights

Page 20: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

• Industry overview

• Company overview

• Performance highlights

• Company strategy

page 20

Contents

Page 21: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

IPO

in

2-3

yea

rs t

ime

WATER

UTILITY

ENERGY

1

CURRENT STANDING

REVENUE 2017E: GEL 125m

EBITDA 2017E: GEL 62m

REVENUE 2017E: GEL 15m

EBITDA 2017E: GEL 10m

149.3MW existing capacity

MEDIUM TERM GOAL

EBITDA 2019E: GEL 70m +

EBITDA 2019E: GEL 35m +

200MW existing capacity

DIVIDEND

PROVIDER

VALUE CREATION

UPSIDE

TARGETING

2

page 21

Company strategy

Page 22: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017

Q&A

page 22

Page 23: Georgian Global Utilities - BGEO GROUPbgeo.com/uploads/presentations/bgeo-investor-day... · Company overview – energy (Zoti hydro / 44.3 MW) Note 1: equity IRR is calculated on

GGU November 2017 page 23

DISCLAIMER – Forward Looking Statements

This presentation contains forward-looking statements, including, but not limited to, statements concerning expectations, projections, objectives, targets, goals,

strategies, future events, future revenues or performance, capital expenditures, financing needs, plans or intentions relating to acquisitions, competitive strengths

and weaknesses, plans or goals relating to financial position and future operations and development. Although BGEO Group PLC believes that the expectations and

opinions reflected in such forward-looking statements are reasonable, no assurance can be given that such expectations and opinions will prove to have been

correct. By their nature, these forward-looking statements are subject to a number of known and unknown risks, uncertainties and contingencies, and actual results

and events could differ materially from those currently being anticipated as reflected in such statements. Important factors that could cause actual results to differ

materially from those expressed or implied in forward-looking statements, certain of which are beyond our control, include, among other things: currency

fluctuations, including depreciation of the Georgian Lari, and macroeconomic risk; corporate loan portfolio exposure risk; regional tensions; regulatory risk; cyber

security, information systems and financial crime risk; investment business strategy risk; and other key factors that we have indicated could adversely affect our

business and financial performance, which are contained elsewhere in this presentation and in our past and future filings and reports, including the 'Principal Risks

and Uncertainties' included in BGEO Group PLC's Annual Report and Accounts 2016 and in its Half Year 2017 Results announcement. No part of this presentation

constitutes, or shall be taken to constitute, an invitation or inducement to invest in BGEO Group PLC or any other entity, including any future entity such as BGEO

Investments PLC or Bank of Georgia PLC, and must not be relied upon in any way in connection with any investment decision. BGEO Group PLC undertakes no

obligation to update any forward-looking statements, whether as a result of new information, future events or otherwise, except to the extent legally required.

Nothing in this presentation should be construed as a profit forecast.