![Page 1: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/1.jpg)
General Tolling Requirements (GTR)
James E. Beverly Jr.
2019
![Page 2: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/2.jpg)
Why does the GTR exist?
• Toll systems have specific infrastructure requirements for accuracy of performance
2
![Page 3: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/3.jpg)
Why does the GTR exist?
• Detailed criteria that provides toll site infrastructure for:• Toll site (includes tolling pavement area), (civil and electrical)
• Toll equipment building (TEB) (architectural, structural, mechanical, and electrical)
• Toll gantry (structural and electrical)
3
![Page 4: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/4.jpg)
Why does the GTR exist?
• Developed Tolling Infrastructure Requirements (TIR) for each project:• Created confusion for everyone
• Required staff to develop a TIR for each project
4
![Page 5: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/5.jpg)
Why does the GTR exist?
• A single document that can be used for FDOT toll sites, (including express lanes) which support all Tolling Equipment Contractors (TECs)
5
![Page 6: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/6.jpg)
Why does the GTR need to be updated?
• TEC’s toll system requirements change
• New TEC toll system is added
• Governing codes change (FBC, NEC, NFPA)
• Standard plans and specifications change
• Lessons learned during construction
• When specified equipment is no longer available
6
![Page 7: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/7.jpg)
PD&E
Design
Construction,Implementation,& Go-Live
Invo
lve
me
nt
AnnualT&R
O&M,Reporting, Sys. Monitoring,Troubleshooting,General support
Lifecycleequipment replacement
Time
Planning Design Construction Operations & Maintenance
When do you need the GTR?
• As early as possible
• During PD&E• Express lane diagram development• Validates approved concept alternative
• Before and during design
7
![Page 8: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/8.jpg)
Who is the GTR addressing?
• Written to the EOR• Blue boxes are for non-
conventional projects
• GTR Part 2, Appendix - 1 TSP sections are written to the Contractor
8
![Page 9: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/9.jpg)
Part 1 – Development and Processes
• Purpose• Procedure• Key terms
• Toll Site and Toll Facility• General Toll Lane (GTL)• General Use Lane (GUL)• Toll Equipment Building • Toll loop pavement area• Toll site envelope• Tolling movement
• Responsibilities• Department
• AOR/EOR
• TEC
• TSTM and GTR deviations
• Standard forms and templates
• Plan development process
9
![Page 10: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/10.jpg)
Part 1 – Development and Processes
10
![Page 11: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/11.jpg)
Part 1 – Development and Processes
11
![Page 12: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/12.jpg)
Part 1 – Development and Processes
• Toll Site and Toll Facility
• General Toll Lane (GTL)
• General Use Lane (GUL)
• Toll Equipment Building
• Toll loop pavement area
• Toll site envelope
• Tolling movement
12
![Page 13: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/13.jpg)
Part 1 – Development and Processes
• Prepare the Toll Siting Technical Memorandum (TSTM) from the approved PD&E concept alternative• Preliminary TSTM
• Express lane diagram
• GTR deviation form identifies and provides justification for design criteria that cannot be met
13
![Page 14: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/14.jpg)
Part 1 – Development and Processes
• Accepted express lane diagram must be included in the TSTM
14
![Page 15: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/15.jpg)
Part 1 – Development and Processes
15
![Page 16: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/16.jpg)
Part 1 – Development and Processes
16
![Page 17: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/17.jpg)
Part 2 – Design Criteria
• Toll site
• Toll Building (TEB)
• Toll gantry
• Communications
• Building permits
• Appendix -1 (TSP)
17
![Page 18: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/18.jpg)
Part 2 – Design Criteria
18
![Page 19: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/19.jpg)
Part 2 – Design Criteria
19
![Page 20: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/20.jpg)
Part 2 – Design Criteria
20
![Page 21: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/21.jpg)
Part 2 – Design Criteria
21
![Page 22: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/22.jpg)
Part 2 – Design Criteria
22
![Page 23: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/23.jpg)
Part 2 – Design Criteria
23
![Page 24: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/24.jpg)
Part 2 – Design Criteria
• Gantry types• Non-accessible
• Cantilever (Standard plans 700-040)
• Span (Standard plans 700-041)
• Accessible
24
![Page 25: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/25.jpg)
Part 2 – Design Criteria
• Gantry types• Non-accessible
• Cantilever (Standard plans 700-040)
• Span (Standard plans 700-041)
• Accessible
25
![Page 26: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/26.jpg)
Part 2 – Design Criteria
• Gantry types• Non-accessible
• Cantilever (Standard plans 700-040)
• Span (Standard plans 700-041)
• Accessible
26
![Page 27: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/27.jpg)
Part 2 – Design Criteria
• Toll equipment layout• Horizontal
Adjustability
27
![Page 28: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/28.jpg)
Part 2 – Design Criteria
• Toll equipment layout• Non-accessible
28
![Page 29: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/29.jpg)
Part 2 – Design Criteria
• Toll equipment layout• Accessible
29
![Page 30: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/30.jpg)
Part 2 – Design Criteria
• Gantry electrical• Non-accessible
30
![Page 31: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/31.jpg)
Part 2 – Design Criteria
• Gantry typical section• Accessible
31
![Page 32: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/32.jpg)
Part 2 – Design Criteria
32
![Page 33: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/33.jpg)
Part 2 – Design Criteria
• Gantry electrical• Accessible
33
![Page 34: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/34.jpg)
Part 2 – Design Criteria
34
![Page 35: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/35.jpg)
Part 2 – Design Criteria
• Communications• Black and red
buffer tubes (fusion spliced into each TEB)
35
![Page 36: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/36.jpg)
Part 2 – Design Criteria
36
![Page 37: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/37.jpg)
Part 2 – Instructions to Contractor
• Technical Special Provision (TSP)• Provided for EOR• Part 2 – Appendix - 1
• Civil• Structural• Architectural• Mechanical• Electrical
• Shop Drawings• Included in each TSP section
37
![Page 38: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/38.jpg)
Part 3 – Plans Production
• Toll submittal requirements• Conventional
• Non-conventional
38
![Page 39: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/39.jpg)
Part 3 – Plans Production
• Master plans• Master key sheet
• Signature sheet(s)
• Toll site location map
39
![Page 40: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/40.jpg)
Part 3 – Plans Production
• Subcomponents• Toll facility demolition plans
• Toll facility site plans
• Toll facility building plans
• Toll facility gantry plans
40
![Page 41: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/41.jpg)
Part 3 – Plans Production
• Subcomponents• Toll facility demolition plans
• Toll facility site plans
• Toll facility building plans
• Toll facility gantry plans
41
![Page 42: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/42.jpg)
Part 3 – Plans Production
• Phase submittals• Conventional
• Non-conventional
42
![Page 43: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/43.jpg)
Part 3 – Plans Production
• Phase submittals• Conventional
• Non-conventional
43
![Page 44: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/44.jpg)
Part 3 – Plans Production
• Design analysis reports• Mechanical
• Building load analysis and equipment selection
• Fuel oil piping
• Electrical• Power design
• Short circuit calculations
• Electrical distribution
• Generator sizing
• Photometric calculations
44
![Page 45: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/45.jpg)
Part 3 – Plans Production
• Pay items• Each toll site (lump sum) per Basis of Estimates (BOE)
• New construction – Toll plaza
• Modify existing or phased demolition – Toll plaza (Modify existing)
• Toll plaza island / lane work – Toll plaza island
• Toll site demolition – Clearing and grubbing
45
![Page 46: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/46.jpg)
Part 3 – Plans Production
• Roadway pay items not included in the Toll’s lump sum pay item• Roadway pavement
• Concrete barriers
• Guardrail
• Sodding
• Traffic control
• Retaining walls (any type)
• CIAC for primary power
• Removal pavement, sidewalks, slabs, etc.
• Delivery of salvageable materials
• Flowable fill
46
![Page 47: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/47.jpg)
How to obtain the GTR and related documents?
• GTR (redacted)
• TSTM template
• GTR deviation form
• EOR estimates template
• External website:• http://www.floridasturnpike.com/design.html
47
![Page 48: General Tolling Requirements (GTR)...(TSTM) from the approved PD&E concept alternative •Preliminary TSTM •Express lane diagram •GTR deviation form identifies and provides justification](https://reader035.fdocuments.us/reader035/viewer/2022071419/6117aa3bd0c6a51c5b694152/html5/thumbnails/48.jpg)
James E. Beverly Jr.Tolls Design Administrator