EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator1
Leif Mortensen, Chief Consultant, Coal Expert
Gas and coal fired cogeneration plantGas and coal fired cogeneration plant
COCO IIIA successful coal & gas-fired cogeneration project in Thailand
2004 Cogeneration Week in Philippines21 - 22 June 2004 Mandarin Oriental Hotel, Manila
24 June 2004 Queen Jennifer Hotel, Isabela
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator2
Structure of the Thai electricity sectorStructure of the Thai electricity sector
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator3
Location of the SPPLocation of the SPP
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator4
Power Plant inMap Ta Phut
Power Plant inMap Ta Phut
1. Map Ta Phut Industrial Estate and Eastern Industrial Estate, Rayong
2. Strategic areas for development of petrochemical and steel industries
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator5
Power 514 MW, Steam 200 t/h, Demin. Water 150 cum/hOperation date: September 1999/March 2000Fuel type: Natural gas/imported bituminous coal/ diesel oilProject cost: 574 million USD
SPP Phase 3 Hybrid CogenerationSPP Phase 3 Hybrid Cogeneration
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator6
Customers of the plantCustomers of the plant
• Electricity Generating Authority of Thailand (EGAT)
PPA’s under the Small Power Producer (SPP) scheme
• 29 Industrial Customers
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator7
Bangkok Synthetics Co.,Ltd. (BST)
Thai Olefins Public Co.,Ltd. (TOC)
Vinythai Public Co.,Ltd. (VNT)
Siam Styrene Monomer Co.,Ltd. (SSMC)
Thai Plastic and Chemicals Public Co.,Ltd. (TPC)
Thai Polypropylene (1994) Co.,Ltd. (THPP-2)
The Aromatics (Thailand) Public Co.,Ltd. (ATC)
Crompton Specialties Ltd. (CROMPTON)
TPC Paste Resin Co.,Ltd.
Rayong Olefins Co.,Ltd. (ROC)
Thai Polyacetal Co.,Ltd. (TPAC)
Thai Polycarbonate Co.,Ltd. (TPCC)
Thasco Chemical Co.,Ltd. (THASCO)
Siam United Steel Co.,Ltd. (SUS)
BST Elastomers Co.,Ltd. (BSTE)
Thai Polyethylene Co.,Ltd. (HDPE-2/HDPE-3)
Carbide Chemical (Thailand) Limited
Siam Tinplate Co., Ltd. (STP)
Siam Polyethylene Co., Ltd. (SPE)
Thai MMA Co., Ltd. (TMMA)
Tuntex (Thailand) Public Co., Ltd. (TTC)
Bayer Thai Co., Ltd. (BTC)
Asia Silicones Monomer Ltd. (ASM)
GE Toshiba Silicones (Thailand) Ltd. (GETOS)
Shin-Etsu Silicones (Thailand) Ltd. (SEST)
Thai Aerosil Co., Ltd. (TAC)
BHP Steel Thailand Co., Ltd. (BHP)
Thai PET Resin Co., Ltd. (TPRC)
Electricity Generating Authority of Thailand (EGAT) under the SmallPower Producer Project (SPP)
Siam Mitsui PTA Co., Ltd. (SMPC)
Customers ListCustomers List
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator8
Electricity and Steam Contracted CapacityElectricity and Steam Contracted Capacity
Petrochemical Petrochemical and Plastic Industriesand Plastic Industries
Electricity: 30.9%Electricity: 30.9%Steam: 97%Steam: 97%
EGATEGAT
Electricity: 64.4%Electricity: 64.4%
Total contracted capacity 500 MW of Electricity and 200 t/h of Total contracted capacity 500 MW of Electricity and 200 t/h of SteamSteam
Fiber Industries Fiber Industries
Electricity: 1.1%Electricity: 1.1%
Steel IndustriesSteel Industries
Electricity: 3.6%Electricity: 3.6%
Steam: 3%Steam: 3%
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator9
COCO III area1990
COCO III area1990
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator10
COCO Phase IIICogeneration Plant today
COCO Phase IIICogeneration Plant today
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator11
The Hybrid Block ConceptThe Hybrid Block Concept
• Multiple fuel technology (coal/gas/diesel oil)
• Gas/oil fired combustion gas turbines for power production
• Heat recovery units for feed water heating and steam re-heating
• Coal fired CFB boiler for steam production
• Steam turbine for power production
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator12
Hybrid Cogeneration ProcessHybrid Cogeneration Process
~
Exhaust
Hot watercoalLime stone
Heat Recovery Unit (HRU)
PTTFuel Gas
2 x 35 MW
Hot GasAir
Gas turbineGenerator water
Bottom ash
Fly ash
exhaust
MP steam
152 MW
Sea water cooling
Steam turbinegenerator
Circulating Fluidized
Bed Boiler (CFB)
Gas End Coal End
~
steam
HP Steam
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator13
Coal Harbour and Coal YardCoal Harbour and Coal Yard
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator14
Coal Ash ManagementCoal Ash Management
• Non-hazardous waste certified by Department of Industry
• Types of the ashFly ash 4,000 tons per monthBottom ash 1,000 tons per month
• Existing system of ash disposalUtilization for ready-mix concrete industry and cement industryPromotion of the fly ash brick to local communities
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator15
Air Quality ManagementAir Quality Management
• Emission Control at source
CFB BoilerFabric Filter Use of high quality coalUse of lime-stone for SO2 removal
• Continuous Emission Monitoring System (CEMS)
• Regular inspections and maintenance
• Third party audits as per EIA Approval
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator16
Hybrid Cogeneration EmissionsHybrid Cogeneration Emissions
ppm
March-April 2003
161
320
152
350
2.52
870
8.2560
0
100
200
300
400
500
600
700
800
900
SO2 Nox CO TSPGlow SPP Phase 3 StandardSPP Phase Standard
(mg/m3)
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator17
• Plant visit to get the public learn and understand Hybrid Cogeneration Process and bituminous coal utilization
The number of visitor as of 2002 : 72 groups: total 2,591 outside visitors
As of June 2003 = 589 persons
Community Relations ActivityCommunity Relations Activity
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator18
• Promotion of coal ash utilization.To sponsor the coal ash bricks production project
• Donation and sponsorship on educational, sports and religious programs
• Scholarship program
• Being active member and participate in the activities of Map Ta Phut Public Relations Club
• Sponsorship on leadership training programs for local teachers/students
Community Relations ActivityCommunity Relations Activity
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator19
Project implementation only if feasibility study shows positive net present value
• Comply with Environmental Impact Assessment (EIA) approval and other environmental regulations
• Work with local community from the start
• Strategically well located in an industrial area with growth
• Long term power purchase agreement with EGAT under the SPP scheme
• Medium to long term contracts with local industrial customers for power and steam sales
Key factors leading to success of SPP Cogeneration
Key factors leading to success of SPP Cogeneration
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator20
• Long term agreement with PTT on gas supply
• Long term agreement with local company on coal supply of high quality coal
• Long term land lease agreements, including additional land for potential expansion
• Use of proven and reliable equipment
• Clearly defined operational and maintenance strategies in order to achieve maximum reliability, availability and efficiency
• Continued search for and implementation of plant improvements
• Service oriented organization which focus on customer satisfaction
Key factors (cont.)Key factors (cont.)
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator21
Generation of electricity & heat based on Generation of electricity & heat based on biomass in large scalebiomass in large scale
A presentation made by Jon Kringelum & Stig Møller Andersen, ENERGI E2, Denmark
Presented by Leif Mortensen, Chief Consultant, Coal Expert
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator22
ENERGI E2 ENERGI E2 –– KeyKey figuresfigures
• Largest power generating company in Eastern Denmark• 7 large- and 10 small-scale power plants in Eastern Denmark -
mainly Combined Heat and Power (CHP)• Generating capacity (Europe), electricity:
– 4,500 MW • Generating capacity (Denmark), heat:
– 2,600 MJ/s (district heat)– 1,800 t/h (steam)
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator23
Target for the use of biomass in Danish power plants by 2000:1,2 mil. tonnes of straw0,2 mil. tonnes of wood chips
Additional agreement by July 1st. 1997:0,2 mil. tonnes of straw is converted to the same amount of wood chips
Follow up on original agreement by March 22nd. 2000:The time limit for the fulfilment of the agreement is postponed to the end of 2005
Newest revision by march 29th. 2001 (New yearly capacity):ENERGI E2 (Eastern Denmark):
300.000 tonnes of wood pellets at the Avedøre, unit 2130.000 tonnes of straw pallets at the Amager, unit 2
ELSAM (Western Denmark):250.000 tonnes of straw200.000 tonnes of wood chips
BackgroundBackground for for biomassbiomass activitiesactivitiesThe biomass agreement from 1993The biomass agreement from 1993
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator24
0
100
200
300
400
500
600
700
800
900
1000
1989 1991 1993 1995 1997 1999 2001 2003 2005 2007 2009
1,00
0 to
nnes
/yea
r
Haslev straw Slagelse straw Masnedø straw Maribo Sakskøbing strawJunckers wood chip Avedøre straw AVV2 wood pellets Amager straw pellets
Amager Unit 2 Straw-pellets
Avedøre Unit 2 Wood-pellets
Avedøre Straw in Bales
Junckers Wood Chips
ENERGI E2ENERGI E2’’s s ExpectedExpected BiomassBiomass ConsumptionConsumption
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator25
KKøøge ge BiopelletBiopellet FactoryFactory
Production capacity, wood: 180,000 tonnes / year
Production capacity, straw: 130,000 tonnes / year
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator26
KKøøge ge BiopelletBiopellet FactoryFactory -- StrawStraw
Hammer mills
Pellet machinery
Straw Shredder
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator27
14 bar process steam
4 bar
To sewer
Flare
4 bar process steam
Buhler
Wood pellets
Wet wood chips pile
KKøøge ge BiopelletBiopellet FactoryFactory -- WoodWood
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator28
AvedAvedøørere Power StationPower StationCommissioned in 1989 (unit 1) and 2001 (unit 2)Commissioned in 1989 (unit 1) and 2001 (unit 2)
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator29
AvedAvedøøre Power Station unit re Power Station unit 22
Straw bales(Grate firing)
Natural Gas
Fuel Oil
Wood Pellets(max 70% load,Dust firing)
Natural Gas
Main Boiler
580 / 600°C & 300 BarSteam Turbine
Gas Turbine unit
Electrical power
Electrical power
District heat
570 MWel/ 0 MJ/s490 MWel / 570 MJ/sBiomass Boiler
545°C & 300 Bar
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator30
Amager Power Station, unit 1, 2 and 3Amager Power Station, unit 1, 2 and 3
3 2 1
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator31
District heat
Amager Power Station, unit 2Amager Power Station, unit 2
AMV unit 2 Coal StrawIn operation 1972 2003Electricity MW 109 59District Heating MJ/s 190 166Steampressure bar 141 120Steamtemperature °C 537 480Electrical efficiency % 37 26.7
Main Boiler
Steam TurbineFuel Oil
Straw Pellets(max 70% load,Dust firing)
Electrical power
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator32
Summary and Summary and conclusionsconclusions
• Increased use of biomass in ENERGI E2• Target amount: 850.000 tonnes each year• Greater market flexibility• Know-how on refining technologies• New challenges in large-scale biomass dust firing• Ongoing improvements of grate firing technology
EC-ASEAN COGEN Programme Phase IIIProven, Clean & Efficient Biomass, Coal, Gas Cogeneration
The EC-ASEAN Business Facilitator33
Thank You !