Gardner Urban Revitalization Plan

11
Urban Revitalization Plan: City of Gardner, Massachusetts Urban Revitalization Plan: City of Gardner, Massachusetts September 4, 2007 September 4, 2007 Prepared by: Prepared by: RKG Associates, Inc. RKG Associates, Inc. Economic, Planning and Real Estate Consultants Economic, Planning and Real Estate Consultants 277 Mast Road 277 Mast Road Durham, NH 03824 Durham, NH 03824 BSC Group/TerraSphere BSC Group/TerraSphere 15 Elkins Street 15 Elkins Street Boston, MA 02127 Boston, MA 02127 Gardner Urban Revitalization Plan

description

Gardner Urban Revitalization Plan. Urban Revitalization Plan: City of Gardner, Massachusetts September 4, 2007 Prepared by:RKG Associates, Inc. Economic, Planning and Real Estate Consultants 277 Mast Road Durham, NH 03824 BSC Group/TerraSphere 15 Elkins Street - PowerPoint PPT Presentation

Transcript of Gardner Urban Revitalization Plan

Page 1: Gardner Urban Revitalization Plan

Urban Revitalization Plan: City of Gardner, MassachusettsUrban Revitalization Plan: City of Gardner, MassachusettsSeptember 4, 2007September 4, 2007

Prepared by:Prepared by: RKG Associates, Inc.RKG Associates, Inc.Economic, Planning and Real Estate ConsultantsEconomic, Planning and Real Estate Consultants277 Mast Road277 Mast RoadDurham, NH 03824Durham, NH 03824

BSC Group/TerraSphereBSC Group/TerraSphere15 Elkins Street15 Elkins StreetBoston, MA 02127 Boston, MA 02127

Gardner Urban Revitalization Plan

Page 2: Gardner Urban Revitalization Plan

204/19/23

Presentation Outline

Plan Purpose and TimelinePlan Purpose and Timeline

Urban Revitalization Plan SummaryUrban Revitalization Plan Summary

Alternative Development Options and Preferred PlanAlternative Development Options and Preferred Plan

Implementation ActionsImplementation Actions

Questions and AnswersQuestions and Answers

Page 3: Gardner Urban Revitalization Plan

304/19/23

Plan Purpose Goals of planGoals of plan

Plan of work to enhance, reposition and redevelop properties in Urban Renewal Area (URA)

Stimulate and encourage private investment in URA through strategic public investments

Enhance sense of community and pride in the downtown & provide a place where residents and visitors come to live, shop, eat and recreate

Two objectivesTwo objectives Develop a current baseline of economic and market data which will

serve as a foundation for strategic, long term planning for the downtown urban renewal area

Envision and test a series of development scenarios focused on existing, tangible properties that can serve as catalysts for the larger, future redevelopment of the City

Page 4: Gardner Urban Revitalization Plan

404/19/23

Project Timeline Initial public forum November 2005Initial public forum November 2005

Steering Committee formed January 2006 Met 5 times in 2006 Consultant Mike Lanava on board August 2006 Urban renewal planning focus – demarcation of URA

RKG/BSC on board in March 2007RKG/BSC on board in March 2007 Four Steering Committee meetings Surveys of businesses and property owners Interviews with Gardner businesses and institutions Public Forums I & II – May and July 2007

Excellent public turnout and response

Page 5: Gardner Urban Revitalization Plan

504/19/23

Plan Summary Housing analysisHousing analysis Economic development analysisEconomic development analysis Building assessmentsBuilding assessments Downtown case studiesDowntown case studies Demographic and market analysesDemographic and market analyses Recommendations, strategies & preferred planRecommendations, strategies & preferred plan

Conceptual plans, drawings and financial analysis & pro-forma

Major findings and conclusionsMajor findings and conclusions Stable growth compared to regional communities Current uncertainty for potential market-based redevelopment Overwhelming public support for revitalization Public investment needed to stimulate private investment

Page 6: Gardner Urban Revitalization Plan

604/19/23

Preferred Plan Informed by…Informed by…

Socioeconomic and market trends and projections Building assessments Business survey Public Forums I & II Review by Steering Committee

Many potential development optionsMany potential development options Limited by resources, coordination, property assemblage, etc.

Key points Key points Long-term (10 to 15 year) view of URA and City Provide parking and support for existing businesses and property owners

along Main Street Introduce green space and public amenities into URA Make connections to other public transportation options and North Central

Pathway Narrow Rear Main Street area street(s) - not a downtown bypass Public investment as catalyst for private development

Page 7: Gardner Urban Revitalization Plan

704/19/23

Development Options Cont’d Two preliminary development scenariosTwo preliminary development scenarios

Development Option 1 (conservative) Bank office (40,550 SF) Medical office (16,200 SF) Market rate condominiums (redevelop existing 5-story mill) Medical office (14,400 SF)

Development Option 2 (more aggressive) Same as above, except… Eliminate (14,400 SF) medical office New Police station (19,000 SF) Main Street streetscape and Willow Street improvement

Preferred Development PlanPreferred Development Plan Additional market rate condominiums (10,000 SF) 2 mixed use retail buildings (12,000 SF & 5,000 SF) Extensive green space, park and streetscape treatments

Page 8: Gardner Urban Revitalization Plan

804/19/23

Implementation Actions 1. Formulate local incentives to encourage investment1. Formulate local incentives to encourage investment

Establish a District Improvement Finance (DIF) or Tax Increment Finance (TIF) zone(s)

Review, amend and promote Façade improvement program Chapter 43 D permitting process

2. Eliminate eyesores/blighted buildings2. Eliminate eyesores/blighted buildings Public investment needed

3. Commit local resources and take advantage of all available 3. Commit local resources and take advantage of all available State and Federal funding to implement identified actionsState and Federal funding to implement identified actions

4. Redevelop Rear Main Corridor and Main Street in accordance 4. Redevelop Rear Main Corridor and Main Street in accordance with preferred development planwith preferred development plan

5. Create public amenities and green space throughout the 5. Create public amenities and green space throughout the Study AreaStudy Area Pocket parks, public gathering space, bike/pedestrian ways

Page 9: Gardner Urban Revitalization Plan

904/19/23

Implementation Actions Cont’d 6. Review City’s development review process every 3 to 5 years6. Review City’s development review process every 3 to 5 years

Clearly defined, ensures flexibility, business-friendly attitude, and encourages high-quality developments

Implement 43D expedited permitting process Quality design standards

7. Expedite redevelopment or demolition of tax title properties7. Expedite redevelopment or demolition of tax title properties 8. Construct new Police HQ in downtown/Rear Main area8. Construct new Police HQ in downtown/Rear Main area 9. Support Square 2 in promotion and expansion of (year round) 9. Support Square 2 in promotion and expansion of (year round)

festival(s) at locations within the Study Areafestival(s) at locations within the Study Area Encourages spending and retention of existing businesses Food, music, children’s activities Encourage participation of service organizations and community

groups

Page 10: Gardner Urban Revitalization Plan

1004/19/23

Implementation Actions Cont’d 10. Prioritize and reposition (at least) one of the three key 10. Prioritize and reposition (at least) one of the three key

propertiesproperties Existing Police Station/Theatre Travers Welding site Former Stewart’s Garage

11. Enhance code enforcement11. Enhance code enforcement 12. Encourage the development of market-rate housing in URA12. Encourage the development of market-rate housing in URA 13. Create a Parking Improvement District within the downtown13. Create a Parking Improvement District within the downtown 14. Establish a Business Improvement District (BID)14. Establish a Business Improvement District (BID)

Promote a progressive business climate Support existing firms for maximum business retention

15. Reflect on the history of Gardner, but embrace new 15. Reflect on the history of Gardner, but embrace new directions for the City and downtowndirections for the City and downtown

Page 11: Gardner Urban Revitalization Plan

1104/19/23

Grow Gardner – Be A Part Grow Gardner – Be A Part of It!of It!

Gardner Redevelopment AuthorityGardner Redevelopment AuthorityRobert L. HubbardRobert L. Hubbard

Executive DirectorExecutive Director

(978) 630-4011(978) 630-4011

[email protected]@gardner.ma.gov

www.gardner.ma.gov/redevelopment.htmlwww.gardner.ma.gov/redevelopment.html