FY 2015 APL

55
FY 2015 Annual Project Listing 09/01/2014 – 08/31/2015

Transcript of FY 2015 APL

Page 1: FY 2015 APL

FY 2015 Annual Project Listing09/01/2014 – 08/31/2015

Page 2: FY 2015 APL

The preparation of this report has been fi nanced in part through the Federal Highway Administration and Federal Transit Administration, United States Department of Transportation,

under the Metropolitan Planning Program, Section 104 (f) of Title 23, United State Code. The contents of this report have been generated by the Capital Area Metropolitan Planning Organization and do not necessarily refl ect the offi cial views or policies of the United States

Department of Transportation.

Page 3: FY 2015 APL

Table of ContentsPage

Introduction: Obligation and Reimbursement of Federal Funds Summary of Obligated Funds for FY 2005 – FY 2015Federal Highway Administration (FHWA) Highway Projects Programs and Studies Grouped ProjectsFederal Transit Authority (FTA) Transit

12

356

51

Page 4: FY 2015 APL

2015 Annual Project Listing1

INTRODUCTION: Obligation and Reimbursement of Federal Funds

Funding for projects is programmed or reserved for a project until they are obligated. Obligation is a way of ensuring that actual cash is available to pay for project expenditures. Obligation of funds occurs on a project phase basis (i.e. design, right of way or construction). Key activities under each phase will trigger obligation of funds. Typically these are critical points at which commitments are made, but expenditures have yet to start. Such items as advertisement of consultant or construction contracts and preparing offers for property acquisition are actions which will obligate funds.

Before an agency can obligate funds, it must have approval to do so. In the case of highway and streets projects, the authority to approve the obligation of funds is passed from the Federal Highway Administration (FHWA) on to the Texas Department of Transportation (TxDOT). The TxDOT has specifi c processes that must be followed for an agency to get to a point in which funds can be obligated. These vary depending on the program, but generally include submitting a "project authorization request" and/or entering into an Agreement with TxDOT. For transit related projects, the lead agency for the project must transmit specifi c information directly to the Federal Transit Authority (FTA).

Once an agency has authorization to proceed with a project, it can obligate funds. Every federal program will have specifi c time limits in which funds must be obligated. Typically these are by the end of a federal or state fi scal year, September 30th and August 30th, respectively. If funds are not obligated by those deadlines, those funds are withdrawn from the project. FTA projects have a longer window of opportunity, typically three years from the time the grant is approved.

Federal funding is typically transferred to an agency on a reimbursement basis. Therefore, the agency must ensure it has adequate cash fl ows to cover planned project expenditures. Typically once expenditures are incurred, the agency can request reimbursement for those costs. If the agency is required to provide matching monies to the federal funds, those must also be expended. Once the project is complete, the lead agency may have to conduct an audit to ensure funds were spent in accordance with the grant or funding program guidelines.

This document was developed by the Capital Area Metropolitan Planning Organization (CAMPO) for informational purposes and is not warranted for any other use. The information contained in the document was provided to CAMPO by transportation providers in the CAMPO region. No warranty is made by CAMPO regarding the accuracy or completeness of the information provide.

Page 5: FY 2015 APL

2015 Annual Project Listing2

Fund Summary

FY 2015 Federal Funds ObligatedCapital Area Metropolitan Planning Organization

Summary of Obligated Funds 2005 through 2015

Year Reported

Federal Highway Administration (FHWA)

Federal Transit Authority (FTA)

Number of Projects

Total Funds Obligated

Number of Projects Funds Obligated

Number of Projects Funds Obligated

2005 46 $56,054,284 9 $8,179,771 55 $64,234,055 2006 61 $373,373,817 9 $10,801,110 70 $384,174,927 2007 54 $147,673,448 4 $1,689,539 58 $149,362,987 2008 38 $38,518,055 33 $45,512,014 71 $84,030,069 2009 68 $104,820,661 11 $18,980,694 79 $123,801,355 2010 83 $143,040,434 22 $41,467,279 105 $184,507,713 2011 117 $202,334,668 32 $40,398,219 149 $242,732,887 2012 89 $82,868,660 42 $101,330,657 131 $184,199,317 2013 66 $141,949,177 41 $41,513,461 107 $183,462,638 2014 91 $207,032,066 18 $83,838,522 109 $290,870,588 2015 94 $102,498,523 1 $542,024 95 $103,040,547

Totals $1,600,163,793 $394,253,290 $1,891,376,536

Highway Projects

Transit Projects

Bicycle and Pedestrian Projects

Grouped Projects

Programs and Studies

FY 2015 Federal Funds Obligated by Type

Page 6: FY 2015 APL

2015 Annual Project Listing3

Highway ProjectsProject ID: STP 1502(521)MM Federal Cost ($): 17,876,611.20

CSJ Number: 0015-13-379 State Cost ($): 4,469,152.80

Project Name: IH 35 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: NORTH OF STASSNEY LANE Total ($): 22,345,764.00

Let Date: 11/2015

Funding Category: 7To: SOUTH OF WILLIAM CANNON DRIVE

Estimated Completion Date:

Summer 2018

Work Type: OPERATIONAL IMPROVEMENTS

Highway ProjectsProject ID: STP 1502(599)MM Federal Cost ($): 4,400,000.00

CSJ Number: 2102-01-061 State Cost ($): 1,100,000.00

Project Name: RM 2244 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 1000 FT. WEST OF BUCKEYE TRAIL Total ($): 5,500,000.00

Let Date: 11/2015

Funding Category: 7To: WALSH TARLTON

Estimated Completion Date:

Fall 2018

Work Type: CONST. 4 LN URBAN RDWY W CONT. LTL

Highway ProjectsFY 2015 Federal Funds Obligated

Page 7: FY 2015 APL

2015 Annual Project Listing4

Highway ProjectsProject ID: STP 1502(599)MM Federal Cost ($): 1,040,000.00

CSJ Number: 2102-01-061 State Cost ($): 260,000.00

Project Name: RM 2244 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 1000 FT. WEST OF BUCKEYE TRAIL Total ($): 1,300,000.00

Let Date: 11/2015

Funding Category: 1To: WALSH TARLTON

Estimated Completion Date:

Fall 2018

Work Type: CONST. 4 LN URBAN RDWY W CONT. LTL

Page 8: FY 2015 APL

2015 Annual Project Listing5

Programs and StudiesProject ID: STP 2015(769)MM Federal Cost ($): 1,000,000.00

CSJ Number: 0914-00-383 State Cost ($):

Project Name: VA Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: VARIOUS LOCATIONS IN THE CAMPO AREA

Total ($): 1,000,000.00

Let Date: 01/2015

Funding Category: 7To: TRAV, WILL, HAYS, BSTP, CALD &

BRNT Estimated Completion Date:

Summer 2018

Work Type: DTA MODELING

Programs and StudiesProject ID: NH 2016(110) Federal Cost ($): 200,000.00

CSJ Number: 0914-00-389 State Cost ($): 50,000.00

Project Name: IH 35 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: VARIOUS LOCATIONS ALONG IH 35 IN

Total ($): 250,000.00

Let Date: 08/2015

Funding Category: 10To: TRAVIS COUNTY.

Estimated Completion Date:

Summer 2017

Work Type: ICM STUDY

Programs and StudiesFY 2015 Federal Funds Obligated

Page 9: FY 2015 APL

2015 Annual Project Listing6

Grouped ProjectsProject ID: STP 2016(173) Federal Cost ($): 815,000.80

CSJ Number: 0265-04-060 State Cost ($): 203,750.20

Project Name: SH 21 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 2.535 MI. WEST OF FM 20 Total ($): 1,018,751.00

Let Date: 10/2015

Funding Category: 1To: SH 304

Estimated Completion Date:

Summer 2016

Work Type: MILL, SEAL & INLAY MAINLANES

Grouped ProjectsProject ID: STP 2015(882) Federal Cost ($): 3,438,480.00

CSJ Number: 1378-06-011 State Cost ($): 859,620.00

Project Name: FM 3406 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: 0.13 MI. EAST OF WYOMING SPRINGS DR

Total ($): 4,298,100.00

Let Date: 04/2015

Funding Category: 1To: 0.05 MI. WEST OF GTRR

Estimated Completion Date:

Summer 2016

Work Type: WIDEN TO 5-LANE WITH CENTER LTL

Grouped ProjectsFY 2015 Federal Funds Obligated

Page 10: FY 2015 APL

2015 Annual Project Listing7

Grouped ProjectsProject ID: STP 2016(173) Federal Cost ($): 1,113,833.60

CSJ Number: 0265-04-061 State Cost ($): 278,458.40

Project Name: SH 21 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 0.521 MI. WEST OF SH 304 Total ($): 1,392,292.00

Let Date: 10/2015

Funding Category: 1To: COLORADO RIVER

Estimated Completion Date:

Summer 2016

Work Type: MILL, SEAL & INLAY FRT RDS & RAMPS

Grouped ProjectsProject ID: STP 1502(386)HES Federal Cost ($): 583,709.40

CSJ Number: 0471-05-039 State Cost ($): 64,856.60

Project Name: SH 21 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 0.363 MI W OF MARTINS CROSSING Total ($): 648,566.00

Let Date: 07/2015

Funding Category: 8To: 0.223 MI E OF MARTINS CROSSING

Estimated Completion Date:

Spring 2016

Work Type: INSTALL CONTINUOUS TURN LANE

Page 11: FY 2015 APL

2015 Annual Project Listing8

Grouped ProjectsProject ID: STP 2015(736) Federal Cost ($): 345,360.00

CSJ Number: 0807-05-020 State Cost ($):

Project Name: FM 535 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 0.052 MI E OF TRAVIS C/L Total ($): 345,360.00

Let Date: 03/2015

Funding Category: 1To: 1.252 MI E OF TRAVIS C/L

Estimated Completion Date:

August-15

Work Type: FULL DEPTH REPAIR & SEAL COAT

Grouped ProjectsProject ID: BR 2014(690) Federal Cost ($): 369,024.00

CSJ Number: 0914-18-092 State Cost ($): 92,256.00

Project Name: CR Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: ON PAINT CRK RD AT PAINT CRK Total ($): 461,280.00

Let Date: 04/2015

Funding Category: 6To: AA01-62-001

Estimated Completion Date:

January-16

Work Type: REPLACE BRIDGE & APPROACHES

Page 12: FY 2015 APL

2015 Annual Project Listing9

Grouped ProjectsProject ID: STP 2015(552)FRS Federal Cost ($): 277,177.50

CSJ Number: 0914-18-106 State Cost ($): 30,797.50

Project Name: CR Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: ON CR 265_(BATEMAN ROAD) Total ($): 307,975.00

Let Date: 03/2015

Funding Category: 8To: AT UPRR X-ING (DOT NO. 415733T)

Estimated Completion Date:

Winter 2019

Work Type: INSTALL RAILROAD GRADE X-ING SGNLS

Grouped ProjectsProject ID: BR 1502(072) Federal Cost ($): 1,905,127.00

CSJ Number: 1073-01-020 State Cost ($): 0.00

Project Name: FM 696 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 1.165 MI N OF US 290 Total ($): 1,905,127.00

Let Date: 06/2015

Funding Category: 6To: 1.296 MI N OF US 290

Estimated Completion Date:

Fall 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Page 13: FY 2015 APL

2015 Annual Project Listing10

Grouped ProjectsProject ID: BR 1502(072) Federal Cost ($): 300,000.00

CSJ Number: 1073-01-020 State Cost ($): 0.00

Project Name: FM 696 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 1.165 MI N OF US 290 Total ($): 300,000.00

Let Date: 06/2015

Funding Category: 1To: 1.296 MI N OF US 290

Estimated Completion Date:

Fall 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Grouped ProjectsProject ID: BR 1502(031) Federal Cost ($): 960,000.00

CSJ Number: 2686-01-011 State Cost ($): 240,000.00

Project Name: FM 2571 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 3.586 MI EAST OF SH 304 Total ($): 1,200,000.00

Let Date: 06/2015

Funding Category: 6To: 3.768 MI EAST OF SH 304

Estimated Completion Date:

Spring 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Page 14: FY 2015 APL

2015 Annual Project Listing11

Grouped ProjectsProject ID: STP 2016(174) Federal Cost ($): 896,720.00

CSJ Number: 3115-01-010 State Cost ($): 224,180.00

Project Name: FM 3000 Local Cost ($):

County Name: BASTROP Local Contribution ($):

From: 0.007 MI. EAST OF LOOP 109 Total ($): 1,120,900.00

Let Date: 10/2015

Funding Category: 1To: 3.658 MI. EAST OF LOOP 109

Estimated Completion Date:

Fall 2016

Work Type: ACP, LVL-UP, FULL DEPTH REPAIR & SC

Grouped ProjectsProject ID: BR 1502(384) Federal Cost ($): 203,180.00

CSJ Number: 0273-02-023 State Cost ($): 50,795.00

Project Name: US 183 Local Cost ($):

County Name: BURNET Local Contribution ($):

From: AT NORTH ROCKY CREEK Total ($): 253,975.00

Let Date: 09/2015

Funding Category: 1To: .

Estimated Completion Date:

Summer 2017

Work Type: REPLACE BRIDGE AND APPROACHES

Page 15: FY 2015 APL

2015 Annual Project Listing12

Grouped ProjectsProject ID: BR 1502(384) Federal Cost ($): 1,318,640.00

CSJ Number: 0273-02-023 State Cost ($): 329,660.00

Project Name: US 183 Local Cost ($):

County Name: BURNET Local Contribution ($):

From: AT NORTH ROCKY CREEK Total ($): 1,648,300.00

Let Date: 09/2015

Funding Category: 6To: .

Estimated Completion Date:

Summer 2017

Work Type: REPLACE BRIDGE AND APPROACHES

Grouped ProjectsProject ID: BR 1502(389) Federal Cost ($): 602,400.00

CSJ Number: 0700-05-007 State Cost ($): 150,600.00

Project Name: SS 191 Local Cost ($):

County Name: BURNET Local Contribution ($):

From: AT CYPRESS CREEK Total ($): 753,000.00

Let Date: 07/2015

Funding Category: 6To: STR 0700-05-030

Estimated Completion Date:

Late 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Page 16: FY 2015 APL

2015 Annual Project Listing13

Grouped ProjectsProject ID: STP 1502(390)HES Federal Cost ($): 2,413,890.00

CSJ Number: 2206-01-015 State Cost ($): 268,210.00

Project Name: RM 2341 Local Cost ($):

County Name: BURNET Local Contribution ($):

From: 0.85 MI N OF CR 114 Total ($): 2,682,100.00

Let Date: 07/2015

Funding Category: 8To: SH 29

Estimated Completion Date:

Spring 2017

Work Type: SAFETY TREATMENTS, ADD PAVE WIDTH

Grouped ProjectsProject ID: BR 1502(520) Federal Cost ($): 2,640,000.00

CSJ Number: 0152-03-056 State Cost ($): 660,000.00

Project Name: US 183 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: AT CLEAR FORK PLUM CREEK Total ($): 3,300,000.00

Let Date: 09/2015

Funding Category: 6To: (STR 152-3-9)

Estimated Completion Date:

Summer 2017

Work Type: REPLACE BRIDGE AND APPROACHES

Page 17: FY 2015 APL

2015 Annual Project Listing14

Grouped ProjectsProject ID: STP 1502(308)HES Federal Cost ($): 906,300.00

CSJ Number: 0286-02-031 State Cost ($): 100,700.00

Project Name: SH 80 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: 0.336 MI W OF FM 1984 Total ($): 1,007,000.00

Let Date: 06/2015

Funding Category: 8To: 0.246 MI E OF FM 1979

Estimated Completion Date:

November-15

Work Type: INSTALL CONTINUOUS TURN LANE

Grouped ProjectsProject ID: STP 2016(173) Federal Cost ($): 111,200.00

CSJ Number: 0286-03-016 State Cost ($): 27,800.00

Project Name: SH 80 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: 0.36 MI. WEST OF US 183 Total ($): 139,000.00

Let Date: 10/2015

Funding Category: 1To: US 183

Estimated Completion Date:

Summer 2016

Work Type: MILL, SEAL & INLAY

Page 18: FY 2015 APL

2015 Annual Project Listing15

Grouped ProjectsProject ID: STP 2016(173) Federal Cost ($): 355,920.00

CSJ Number: 0287-01-015 State Cost ($): 88,980.00

Project Name: SH 80 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: US 90 Total ($): 444,900.00

Let Date: 10/2015

Funding Category: 1To: 0.999 MI. SOUTH OF US 90

Estimated Completion Date:

Summer 2016

Work Type: MILL, SEAL & INLAY

Grouped ProjectsProject ID: STP 2015(571)HES Federal Cost ($): 47,900.00

CSJ Number: 0384-01-022 State Cost ($):

Project Name: SH 142 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: AT FM 1966 Total ($): 47,900.00

Let Date: 02/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: ADD FLASHING BEACON & SFTY LGHTNG

Page 19: FY 2015 APL

2015 Annual Project Listing16

Grouped ProjectsProject ID: BR 2014(691) Federal Cost ($): 246,576.80

CSJ Number: 0914-22-057 State Cost ($): 61,644.20

Project Name: CS Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: ON N WALNUT AVE AT SALT BRANCH CRK

Total ($): 308,221.00

Let Date: 06/2015

Funding Category: 6To: (STR C004-71-001)

Estimated Completion Date:

January-16

Work Type: REPLACE BRIDGE & APPROACHES

Grouped ProjectsProject ID: STP 2016(336)FRS3 Federal Cost ($): 281,947.50

CSJ Number: 0914-22-069 State Cost ($): 31,327.50

Project Name: CR Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: UPRR X-ING ON CR 295 [EASY STREET]

Total ($): 313,275.00

Let Date: 08/2015

Funding Category: 8To: DOT NO. 415722F__[DALE, TX]

Estimated Completion Date:

Winter 2019

Work Type: REPLACE RAILROAD CROSSING

Page 20: FY 2015 APL

2015 Annual Project Listing17

Grouped ProjectsProject ID: STP 2016(174) Federal Cost ($): 245,840.00

CSJ Number: 1375-01-010 State Cost ($): 61,460.00

Project Name: FM 1322 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: 4.914 MI. NORTH OF FM 86 Total ($): 307,300.00

Let Date: 10/2015

Funding Category: 1To: FM 86

Estimated Completion Date:

Summer 2016

Work Type: ACP, LVL-UP, FULL DEPTH REPAIR & SC

Grouped ProjectsProject ID: STP 2016(174) Federal Cost ($): 456,560.00

CSJ Number: 1375-02-017 State Cost ($): 114,140.00

Project Name: FM 1322 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: FM 86 Total ($): 570,700.00

Let Date: 10/2015

Funding Category: 1To: 9.068 MI. SOUTH OF FM 86

Estimated Completion Date:

Summer 2016

Work Type: LEVEL-UP & SEAL COAT

Page 21: FY 2015 APL

2015 Annual Project Listing18

Grouped ProjectsProject ID: STP 2016(174) Federal Cost ($): 986,392.00

CSJ Number: 1776-03-010 State Cost ($): 246,598.00

Project Name: FM 2001 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: SH 21 Total ($): 1,232,990.00

Let Date: 10/2015

Funding Category: 1To: US 183

Estimated Completion Date:

Summer 2016

Work Type: LVL-UP, FULL DEPTH REPAIR & SL COAT

Grouped ProjectsProject ID: STP 2016(174) Federal Cost ($): 157,440.00

CSJ Number: 1850-01-014 State Cost ($): 39,360.00

Project Name: FM 1966 Local Cost ($):

County Name: CALDWELL Local Contribution ($):

From: HAYS COUNTY LINE Total ($): 196,800.00

Let Date: 10/2015

Funding Category: 1To: SH 142

Estimated Completion Date:

Fall 2016

Work Type: SEAL COAT

Page 22: FY 2015 APL

2015 Annual Project Listing19

Grouped ProjectsProject ID: NH 2015(568) Federal Cost ($): 2,749,936.50

CSJ Number: 0016-02-136 State Cost ($): 305,548.50

Project Name: IH 35 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: SL 82 Total ($): 3,055,485.00

Let Date: 02/2015

Funding Category: 1To: YARRINGTON ROAD

Estimated Completion Date:

Fall 2015

Work Type: MILL, SEAL & OVERLAY NB/SB MAINLANE

Grouped ProjectsProject ID: STP 1502(144)HES Federal Cost ($): 668,500.00

CSJ Number: 0016-02-138 State Cost ($):

Project Name: IH 35 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: TRAVIS COUNTY LINE Total ($): 668,500.00

Let Date: 05/2015

Funding Category: 8To: LP 82 NORTH IN SAN MARCOS

Estimated Completion Date:

Fall 2016

Work Type: IMPROVE GUARDRAIL TO STANDARDS

Page 23: FY 2015 APL

2015 Annual Project Listing20

Grouped ProjectsProject ID: NH 2015(352) Federal Cost ($): 4,819,500.00

CSJ Number: 0016-02-140 State Cost ($): 535,500.00

Project Name: IH 35 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: AQUARENA SPRINGS DRIVE (LP 82) Total ($): 5,355,000.00

Let Date: 12/2014

Funding Category: 1To: IH 35-BL (SOUTH OLD HWY 81)

Estimated Completion Date:

Fall 2016

Work Type: BASE REPAIR & OVERLAY (IH 35 SBFR)

Grouped ProjectsProject ID: STP 1502(145)HES Federal Cost ($): 391,900.00

CSJ Number: 0016-03-099 State Cost ($):

Project Name: IH 35 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: LP 82 NORTH IN SAN MARCOS Total ($): 391,900.00

Let Date: 05/2015

Funding Category: 8To: COMAL COUNTY LINE

Estimated Completion Date:

Early 2016

Work Type: IMPROVE GUARDRAIL TO STANDARDS

Page 24: FY 2015 APL

2015 Annual Project Listing21

Grouped ProjectsProject ID: NH 2015(568) Federal Cost ($): 733,500.00

CSJ Number: 0016-03-105 State Cost ($): 81,500.00

Project Name: IH 35 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: SH 80 Total ($): 815,000.00

Let Date: 02/2015

Funding Category: 1To: SL 82

Estimated Completion Date:

Fall 2015

Work Type: OVERLAY IH 35 MAINLANES

Grouped ProjectsProject ID: NH 2015(352) Federal Cost ($): 18,360.00

CSJ Number: 0016-03-106 State Cost ($): 2,040.00

Project Name: IH 35 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: 350 FT. NORTH OF SL 82 Total ($): 20,400.00

Let Date: 12/2014

Funding Category: 1To: 740 FT. NORTH OF SL 82

Estimated Completion Date:

Fall 2015

Work Type: BASE REPAIR & OVERLAY

Page 25: FY 2015 APL

2015 Annual Project Listing22

Grouped ProjectsProject ID: STP 2015(880) Federal Cost ($): 1,952,320.00

CSJ Number: 0285-03-057 State Cost ($): 488,080.00

Project Name: RM 12 Local Cost ($): 0.00

County Name: HAYS Local Contribution ($):

From: SADDLERIDGE DR Total ($): 2,440,400.00

Let Date: 04/2015

Funding Category: 1To: HUGO RD

Estimated Completion Date:

Spring 2016

Work Type: ADD CENTER TURN LANE AND SHOULDERS

Grouped ProjectsProject ID: NH 2015(492) Federal Cost ($): 200,000.00

CSJ Number: 0286-01-055 State Cost ($): 50,000.00

Project Name: SH 80 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: AT IH 35 Total ($): 250,000.00

Let Date: 01/2015

Funding Category: 10To: .

Estimated Completion Date:

Late 2017

Work Type: LANDSCAPING AND IRRIGATION

Page 26: FY 2015 APL

2015 Annual Project Listing23

Grouped ProjectsProject ID: STP 1502(388) Federal Cost ($): 184,679.20

CSJ Number: 0683-05-011 State Cost ($): 46,169.80

Project Name: RM 12 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: AT OLD FITZHUGH RD. Total ($): 230,849.00

Let Date: 07/2015

Funding Category: 1To: .

Estimated Completion Date:

Winter 2016

Work Type: INSTALL FLASH BEACON/REALIGN INTER.

Grouped ProjectsProject ID: STP 1502(387)HES Federal Cost ($): 666,450.00

CSJ Number: 0683-05-012 State Cost ($): 74,050.00

Project Name: RM 12 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: 0.25 MI N OF OLD FITZHUGH RD. Total ($): 740,500.00

Let Date: 07/2015

Funding Category: 8To: 0.25 MI S OF OLD FITZHUGH RD.

Estimated Completion Date:

Winter 2016

Work Type: ADD CENTER TURN LANE AND SHOULDERS

Page 27: FY 2015 APL

2015 Annual Project Listing24

Grouped ProjectsProject ID: BR 2016(249) Federal Cost ($): 2,000,000.00

CSJ Number: 0914-33-071 State Cost ($): 500,000.00

Project Name: CR Local Cost ($):

County Name: HAYS Local Contribution ($):

From: FISCHER STORE ROAD AT BLANCO RIVER

Total ($): 2,500,000.00

Let Date: 09/2015

Funding Category: 6To: .(STR NO. AA01-80-001)

Estimated Completion Date:

Spring 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Grouped ProjectsProject ID: STP 2016(304) Federal Cost ($): 242,960.00

CSJ Number: 2293-01-027 State Cost ($): 60,740.00

Project Name: FM 2439 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: MOORE ST Total ($): 303,700.00

Let Date: 11/2015

Funding Category: 1To: NORTH OF BISHOP ST.

Estimated Completion Date:

Fall 2016

Work Type: MILL, SEAL & OVERLAY

Page 28: FY 2015 APL

2015 Annual Project Listing25

Grouped ProjectsProject ID: STP 2016(175) Federal Cost ($): 847,040.00

CSJ Number: 3210-01-013 State Cost ($): 211,760.00

Project Name: FM 2770 Local Cost ($):

County Name: HAYS Local Contribution ($):

From: FM 1626 Total ($): 1,058,800.00

Let Date: 10/2015

Funding Category: 1To: RM 150

Estimated Completion Date:

Summer 2016

Work Type: MILL & THIN OVERLAY

Grouped ProjectsProject ID: STP 1502(300)HES Federal Cost ($): 161,354.00

CSJ Number: 0015-11-061 State Cost ($):

Project Name: SL 275 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT RUNDBERG LN Total ($): 161,354.00

Let Date: 06/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Page 29: FY 2015 APL

2015 Annual Project Listing26

Grouped ProjectsProject ID: NH 2015(567) Federal Cost ($): 2,340,000.00

CSJ Number: 0015-13-352 State Cost ($): 260,000.00

Project Name: IH 35 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: BEN WHITE BLVD. Total ($): 2,600,000.00

Let Date: 02/2015

Funding Category: 1To: HOLLY STREET

Estimated Completion Date:

Spring 2016

Work Type: REPAIR, MILL, SEAL & OVERLAY MAINLANES

Grouped ProjectsProject ID: STP 1502(632)HES Federal Cost ($): 1,434,940.20

CSJ Number: 0015-13-384 State Cost ($): 159,437.80

Project Name: IH 35 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: SLAUGHTER LANE <SL 275> Total ($): 1,594,378.00

Let Date: 11/2015

Funding Category: 8To: 0.705 MI NORTH OF STASSNEY LANE

Estimated Completion Date:

Summer 2018

Work Type: SAFETY LIGHTING

Page 30: FY 2015 APL

2015 Annual Project Listing27

Grouped ProjectsProject ID: NH 1502(381) Federal Cost ($): 576,000.00

CSJ Number: 0016-01-114 State Cost ($): 64,000.00

Project Name: IH 35 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: IH 35 AT SLAUGHTER LANE Total ($): 640,000.00

Let Date: 07/2015

Funding Category: 10To: .

Estimated Completion Date:

Summer 2018

Work Type: LANDSCAPING AND IRRIGATION

Grouped ProjectsProject ID: STP 2015(877) Federal Cost ($): 493,400.00

CSJ Number: 0113-09-071 State Cost ($):

Project Name: SL 343 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 1500 FEET SOUTH OF PANTHER TRAIL

Total ($): 493,400.00

Let Date: 04/2015

Funding Category: 1To: PANTHER TRL

Estimated Completion Date:

Fall 2015

Work Type: MILL, SEAL AND INLAY

Page 31: FY 2015 APL

2015 Annual Project Listing28

Grouped ProjectsProject ID: NH 2015(569) Federal Cost ($): 2,447,300.00

CSJ Number: 0113-13-154 State Cost ($):

Project Name: SL 360 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: US 183 Total ($): 2,447,300.00

Let Date: 02/2015

Funding Category: 1To: WALSH TARLETON LANE

Estimated Completion Date:

Fall 2015

Work Type: PAVEMENT REPAIR, SEAL & OVERLAY

Grouped ProjectsProject ID: NH 2016(063) Federal Cost ($): 1,200,000.00

CSJ Number: 0113-13-157 State Cost ($): 300,000.00

Project Name: SL 360 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: NORTH OF WALSH TARLTON Total ($): 1,500,000.00

Let Date: 09/2015

Funding Category: 11To: SOUTH OF SL 1

Estimated Completion Date:

Spring 2017

Work Type: WDN RDWY, OVRLY, SGLS, MBGF & PVMKS

Page 32: FY 2015 APL

2015 Annual Project Listing29

Grouped ProjectsProject ID: NH 2016(063) Federal Cost ($): 2,667,200.00

CSJ Number: 0113-13-157 State Cost ($): 666,800.00

Project Name: SL 360 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: NORTH OF WALSH TARLTON Total ($): 3,334,000.00

Let Date: 09/2015

Funding Category: 1To: SOUTH OF SL 1

Estimated Completion Date:

Spring 2017

Work Type: WDN RDWY, OVRLY, SGLS, MBGF & PVMKS

Grouped ProjectsProject ID: NH 1502(588) Federal Cost ($): 15,497.60

CSJ Number: 0113-13-161 State Cost ($): 3,874.40

Project Name: SL 360 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: COURTYARD DR. Total ($): 19,372.00

Let Date: 08/2015

Funding Category: 1To: WESTBANK DRIVE

Estimated Completion Date:

Summer 2016

Work Type: GRADING, BASE, ACP & PVMNT MARKINGS

Page 33: FY 2015 APL

2015 Annual Project Listing30

Grouped ProjectsProject ID: STP 1502(589)HES Federal Cost ($): 266,760.00

CSJ Number: 0114-01-058 State Cost ($): 29,640.00

Project Name: US 290 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: IH 35 Total ($): 296,400.00

Let Date: 08/2015

Funding Category: 8To: 0.04 MI W OF CAMERON RD

Estimated Completion Date:

Summer 2016

Work Type: INSTALL MEDIAN BARRIER

Grouped ProjectsProject ID: STP 1502(590)HES Federal Cost ($): 225,927.00

CSJ Number: 0114-01-059 State Cost ($): 25,103.00

Project Name: SS 69 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 0.571 MI W OF IH 35 Total ($): 251,030.00

Let Date: 08/2015

Funding Category: 8To: IH 35

Estimated Completion Date:

Summer 2016

Work Type: INSTALL MEDIAN BARRIERS

Page 34: FY 2015 APL

2015 Annual Project Listing31

Grouped ProjectsProject ID: NH 1502(382) Federal Cost ($): 720,000.00

CSJ Number: 0114-02-100 State Cost ($): 180,000.00

Project Name: US 290 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: US 183 Total ($): 900,000.00

Let Date: 07/2015

Funding Category: 10To: FM 734

Estimated Completion Date:

Summer 2018

Work Type: LANDSCAPING AND IRRIGATION

Grouped ProjectsProject ID: BR 2015(878) Federal Cost ($): 1,063,000.00

CSJ Number: 0114-03-025 State Cost ($):

Project Name: US 290 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 0.091 MI. WEST OF WILLOW CREEK Total ($): 1,063,000.00

Let Date: 04/2015

Funding Category: 6To: 0.083 MI. EAST OF WILLOW CREEK

Estimated Completion Date:

Spring 2016

Work Type: REPLACE BRIDGE

Page 35: FY 2015 APL

2015 Annual Project Listing32

Grouped ProjectsProject ID: STP 1502(302)HES Federal Cost ($): 85,438.00

CSJ Number: 0151-06-140 State Cost ($):

Project Name: US 183 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT OAK KNOLL Total ($): 85,438.00

Let Date: 06/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Grouped ProjectsProject ID: NH 2016(302) Federal Cost ($): 781,274.40

CSJ Number: 0152-01-076 State Cost ($): 195,318.60

Project Name: US 183 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 0.4 MI NORTH OF FM 973 Total ($): 976,593.00

Let Date: 11/2015

Funding Category: 1To: VON QUINTUS RD

Estimated Completion Date:

Fall 2016

Work Type: OVERLAY

Page 36: FY 2015 APL

2015 Annual Project Listing33

Grouped ProjectsProject ID: NH 1502(385) Federal Cost ($): 520,000.00

CSJ Number: 0440-06-014 State Cost ($): 130,000.00

Project Name: SH 130 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: SH 130 @ FM 812 Total ($): 650,000.00

Let Date: 07/2015

Funding Category: 10To: .

Estimated Completion Date:

Summer 2018

Work Type: LANDSCAPING AND IRRIGATION

Grouped ProjectsProject ID: STP 1502(596) Federal Cost ($): 800,000.00

CSJ Number: 0683-02-063 State Cost ($): 200,000.00

Project Name: RM 620 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 500 FT N OF LOHMANS CROSSING RD

Total ($): 1,000,000.00

Let Date: 09/2015

Funding Category: 11To: LADERA BLVD.

Estimated Completion Date:

Spring 2018

Work Type: OPERATIONAL IMPROVEMENTS

Page 37: FY 2015 APL

2015 Annual Project Listing34

Grouped ProjectsProject ID: STP 2015(574) Federal Cost ($): 720,000.00

CSJ Number: 0683-04-018 State Cost ($): 180,000.00

Project Name: RM 3238 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 0.31 MI W OF SH 71 Total ($): 900,000.00

Let Date: 02/2015

Funding Category: 1To: RM 12

Estimated Completion Date:

Spring 2016

Work Type: ADD SHOULDERS AND LEFT TURN LANE

Grouped ProjectsProject ID: STP 2015(572)HES Federal Cost ($): 150,640.00

CSJ Number: 0757-02-016 State Cost ($):

Project Name: FM 685 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT FM 1825 Total ($): 150,640.00

Let Date: 02/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Page 38: FY 2015 APL

2015 Annual Project Listing35

Grouped ProjectsProject ID: STP 1502(213) Federal Cost ($): 853,818.40

CSJ Number: 0914-00-310 State Cost ($): 213,454.60

Project Name: VA Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: VARIOUS_ON SYSTEM LOCATIONS Total ($): 1,067,273.00

Let Date: 03/2015

Funding Category: 1To: .

Estimated Completion Date:

Fall 2016

Work Type: NON-SITE SPECIFIC ITS MAINT

Grouped ProjectsProject ID: STP 1502(147) Federal Cost ($): 900,000.00

CSJ Number: 0914-00-343 State Cost ($):

Project Name: VA Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT VARIOUS LOCATIONS DISTRICTWIDE

Total ($): 900,000.00

Let Date: 05/2015

Funding Category: 1To: .

Estimated Completion Date:

Late 2016

Work Type: FY 2015 SITE-SPECIFIC SIGNALS

Page 39: FY 2015 APL

2015 Annual Project Listing36

Grouped ProjectsProject ID: NH 2015(575) Federal Cost ($): 1,306,090.40

CSJ Number: 0914-00-344 State Cost ($): 326,522.60

Project Name: VA Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT VARIOUS LOCATIONS DISTRICTWIDE

Total ($): 1,632,613.00

Let Date: 02/2015

Funding Category: 1To: .

Estimated Completion Date:

Late 2016

Work Type: FY 2015 NON-SITE SPECIFIC SIGNALS

Grouped ProjectsProject ID: NH 2016(104) Federal Cost ($): 296,000.00

CSJ Number: 0914-00-367 State Cost ($): 74,000.00

Project Name: VA Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT VARIOUS LOCATIONS DISTRICTWIDE

Total ($): 370,000.00

Let Date: 09/2015

Funding Category: 1To: INCLUDE IH 35, SH 71, SL 360, ETC

Estimated Completion Date:

Summer 2016

Work Type: FY 2016 SIGNING

Page 40: FY 2015 APL

2015 Annual Project Listing37

Grouped ProjectsProject ID: STP 1502(148) Federal Cost ($): 24,000.00

CSJ Number: 0914-00-381 State Cost ($): 6,000.00

Project Name: VA Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: VARIOUS LOCATIONS IN Total ($): 30,000.00

Let Date: 05/2015

Funding Category: 10To: BASTROP, LEE & CALDWELL

COUNTIES Estimated Completion Date:

Spring 2016

Work Type: CONSTRUCT ADA CURB RAMPS

Grouped ProjectsProject ID: STP 1502(148) Federal Cost ($): 771,929.60

CSJ Number: 0914-00-381 State Cost ($): 192,982.40

Project Name: VA Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: VARIOUS LOCATIONS IN Total ($): 964,912.00

Let Date: 05/2015

Funding Category: 10To: BASTROP, LEE & CALDWELL

COUNTIES Estimated Completion Date:

Spring 2016

Work Type: CONSTRUCT ADA CURB RAMPS

Page 41: FY 2015 APL

2015 Annual Project Listing38

Grouped ProjectsProject ID: STP 2015(604)HES Federal Cost ($): 113,193.00

CSJ Number: 0914-04-292 State Cost ($):

Project Name: CS Local Cost ($): 12,577.00

County Name: TRAVIS Local Contribution ($):

From: 1.2 MI. EAST OF OLD HWY 20 Total ($): 125,770.00

Let Date: 05/2015

Funding Category: 8To: 0.2 MI. WEST OF BITTING SCHOOL

RD. Estimated Completion Date:

Spring 2016

Work Type: HIGH FRICTION SURFACE TREATMENT

Grouped ProjectsProject ID: STP 2015(605)HES Federal Cost ($): 181,378.80

CSJ Number: 0914-04-293 State Cost ($):

Project Name: CS Local Cost ($): 20,153.20

County Name: TRAVIS Local Contribution ($):

From: OLD HWY 20 Total ($): 201,532.00

Let Date: 05/2015

Funding Category: 8To: KIMBRO ROAD

Estimated Completion Date:

Spring 2016

Work Type: HIGH FRICTION SURFACE TREATMENT

Page 42: FY 2015 APL

2015 Annual Project Listing39

Grouped ProjectsProject ID: NH 2016(065) Federal Cost ($): 12,800.00

CSJ Number: 1200-06-011 State Cost ($): 3,200.00

Project Name: SH 45 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: SL 1 Total ($): 16,000.00

Let Date: 09/2015

Funding Category: 1To: KENDRICK BLVD

Estimated Completion Date:

Spring 2016

Work Type: REPAIR BRIDGE JOINTS

Grouped ProjectsProject ID: STP 2015(738) Federal Cost ($): 316,422.40

CSJ Number: 1902-01-027 State Cost ($): 79,105.60

Project Name: FM 1825 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: 10TH STREET IN PFLUGERVILLE Total ($): 395,528.00

Let Date: 03/2015

Funding Category: 1To: FM 685

Estimated Completion Date:

Summer 2016

Work Type: FULL DEPTH REPAIR, SEAL & OVERLAY

Page 43: FY 2015 APL

2015 Annual Project Listing40

Grouped ProjectsProject ID: NH 2015(739) Federal Cost ($): 1,017,000.00

CSJ Number: 2100-01-056 State Cost ($):

Project Name: RM 2222 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: LP 1 Total ($): 1,017,000.00

Let Date: 03/2015

Funding Category: 1To: LAMAR BLVD

Estimated Completion Date:

Early 2016

Work Type: MILL, SEAL & OVERLAY

Grouped ProjectsProject ID: NH 2016(065) Federal Cost ($): 812,080.00

CSJ Number: 3136-01-161 State Cost ($): 203,020.00

Project Name: SL 1 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: US 290 Total ($): 1,015,100.00

Let Date: 09/2015

Funding Category: 1To: SH 45

Estimated Completion Date:

Spring 2016

Work Type: SEAL & THIN OVERLAY

Page 44: FY 2015 APL

2015 Annual Project Listing41

Grouped ProjectsProject ID: NH 2016(064) Federal Cost ($): 100,000.00

CSJ Number: 3136-01-182 State Cost ($): 25,000.00

Project Name: SL 1 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: SL 360 Total ($): 125,000.00

Let Date: 09/2015

Funding Category: 1To: 700 FEET SOUTH OF SL 360

Estimated Completion Date:

Spring 2017

Work Type: WIDEN BRDG & ADJUST PVMT MARKINGS

Grouped ProjectsProject ID: STP 1502(303)HES Federal Cost ($): 64,263.00

CSJ Number: 3417-01-025 State Cost ($):

Project Name: FM 734 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT SL 275 (N. LAMAR BLVD) Total ($): 64,263.00

Let Date: 06/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Page 45: FY 2015 APL

2015 Annual Project Listing42

Grouped ProjectsProject ID: STP 1502(304)HES Federal Cost ($): 85,438.00

CSJ Number: 3417-01-026 State Cost ($):

Project Name: FM 734 Local Cost ($):

County Name: TRAVIS Local Contribution ($):

From: AT SL 1 Total ($): 85,438.00

Let Date: 06/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Grouped ProjectsProject ID: STP 1502(301)HES Federal Cost ($): 204,072.00

CSJ Number: 0151-05-099 State Cost ($):

Project Name: US 183 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: AT ANDERSON MILL Total ($): 204,072.00

Let Date: 06/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Page 46: FY 2015 APL

2015 Annual Project Listing43

Grouped ProjectsProject ID: STP 2015(570)HES Federal Cost ($): 135,460.00

CSJ Number: 0204-01-061 State Cost ($):

Project Name: US 79 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: AT FM 1460 Total ($): 135,460.00

Let Date: 02/2015

Funding Category: 8To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Grouped ProjectsProject ID: STP 2015(570)HES Federal Cost ($): 198,017.60

CSJ Number: 0204-01-061 State Cost ($): 49,504.40

Project Name: US 79 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: AT FM 1460 Total ($): 247,522.00

Let Date: 02/2015

Funding Category: 1To: .

Estimated Completion Date:

Late 2016

Work Type: IMPROVE TRAFFIC SIGNAL

Page 47: FY 2015 APL

2015 Annual Project Listing44

Grouped ProjectsProject ID: NH 2015(632) Federal Cost ($): 2,432,900.00

CSJ Number: 0204-01-062 State Cost ($):

Project Name: US 79 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: 0.42 MILES W. OF FM 1460 Total ($): 2,432,900.00

Let Date: 02/2015

Funding Category: 1To: CR 110

Estimated Completion Date:

Summer 2015

Work Type: MILL, SEAL & THIN OVERLAY

Grouped ProjectsProject ID: BR 2015(573) Federal Cost ($): 149,760.00

CSJ Number: 0273-04-033 State Cost ($):

Project Name: US 183 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: 0.28 MI S OF RM 1869 Total ($): 149,760.00

Let Date: 02/2015

Funding Category: 6To: 0.22 MI N OF RM 1869

Estimated Completion Date:

Early 2016

Work Type: ADD TURN LANES AND SIGNAL

Page 48: FY 2015 APL

2015 Annual Project Listing45

Grouped ProjectsProject ID: STP 2015(879)HES Federal Cost ($): 874,400.00

CSJ Number: 0273-04-035 State Cost ($):

Project Name: US 183 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: 0.156 MI S OF CR 213/258 Total ($): 874,400.00

Let Date: 04/2015

Funding Category: 8To: 0.483 MI S OF CR 213/258

Estimated Completion Date:

Spring 2016

Work Type: CONSTRUCT LEFT TURN LANE

Grouped ProjectsProject ID: BR 1502(592) Federal Cost ($): 1,800,000.00

CSJ Number: 0320-03-083 State Cost ($): 450,000.00

Project Name: SH 95 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: AT WILLIS CREEK Total ($): 2,250,000.00

Let Date: 08/2015

Funding Category: 6To: (STR 0320-03-032)

Estimated Completion Date:

Fall 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Page 49: FY 2015 APL

2015 Annual Project Listing46

Grouped ProjectsProject ID: BR 1502(594) Federal Cost ($): 240,000.00

CSJ Number: 0334-01-043 State Cost ($): 60,000.00

Project Name: FM 112 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: AT DRAW 1.0 MI E OF US 79 Total ($): 300,000.00

Let Date: 08/2015

Funding Category: 6To: STR 0334-01-003

Estimated Completion Date:

Summer 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Grouped ProjectsProject ID: BR 1502(594) Federal Cost ($): 560,000.00

CSJ Number: 0334-01-043 State Cost ($): 140,000.00

Project Name: FM 112 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: AT DRAW 1.0 MI E OF US 79 Total ($): 700,000.00

Let Date: 08/2015

Funding Category: 1To: STR 0334-01-003

Estimated Completion Date:

Summer 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Page 50: FY 2015 APL

2015 Annual Project Listing47

Grouped ProjectsProject ID: BR 2014(427) Federal Cost ($): 372,000.00

CSJ Number: 0914-05-173 State Cost ($): 93,000.00

Project Name: CS Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: COLORADO ST @ WILLIS CREEK BRANCH

Total ($): 465,000.00

Let Date: 03/2015

Funding Category: 6To: STR# 246-J001-15-001

Estimated Completion Date:

Fall 2015

Work Type: REPLACE BRIDGE & APPROACHES

Grouped ProjectsProject ID: BR 1502(149) Federal Cost ($): 1,206,864.00

CSJ Number: 0986-01-042 State Cost ($): 0.00

Project Name: FM 619 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: 0.089 MI. NORTH OF BRUSHY CREEK Total ($): 1,206,864.00

Let Date: 05/2015

Funding Category: 6To: 0.100 MI. SOUTH OF BRUSHY CREEK

Estimated Completion Date:

Fall 2016

Work Type: REPLACE BRIDGE

Page 51: FY 2015 APL

2015 Annual Project Listing48

Grouped ProjectsProject ID: BR 1502(353) Federal Cost ($): 535,532.80

CSJ Number: 1200-04-011 State Cost ($): 133,883.20

Project Name: FM 1466 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: AT DRAW Total ($): 669,416.00

Let Date: 06/2015

Funding Category: 6To: (STR 1200-4-6)

Estimated Completion Date:

Early 2016

Work Type: REPLACE BRIDGE AND APPROACHES

Grouped ProjectsProject ID: STP 2015(737) Federal Cost ($): 4,574,048.00

CSJ Number: 1201-02-018 State Cost ($): 1,143,512.00

Project Name: FM 487 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: IH35 Total ($): 5,717,560.00

Let Date: 03/2015

Funding Category: 1To: BELL COUNTY LINE

Estimated Completion Date:

Early 2016

Work Type: REHAB RDWY

Page 52: FY 2015 APL

2015 Annual Project Listing49

Grouped ProjectsProject ID: STP 1502(073) Federal Cost ($): 3,080,000.00

CSJ Number: 1202-01-017 State Cost ($): 770,000.00

Project Name: FM 972 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: IH 35 Total ($): 3,850,000.00

Let Date: 09/2015

Funding Category: 1To: 0.128 MILES WEST OF CR 150

Estimated Completion Date:

Summer 2017

Work Type: REHAB PVMT, ADD SHLDR & SAFTY TREAT

Grouped ProjectsProject ID: BR 2015(881) Federal Cost ($): 491,308.80

CSJ Number: 1202-03-015 State Cost ($): 122,827.20

Project Name: FM 1063 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: 0.046 MI N OF SPRING BRANCH Total ($): 614,136.00

Let Date: 04/2015

Funding Category: 6To: 0.019 MI S OF SPRING BRANCH

Estimated Completion Date:

Spring 2016

Work Type: REPLACE BRIDGE

Page 53: FY 2015 APL

2015 Annual Project Listing50

Grouped ProjectsProject ID: STP 2015(882) Federal Cost ($): 3,438,480.00

CSJ Number: 1378-06-011 State Cost ($): 859,620.00

Project Name: FM 3406 Local Cost ($):

County Name: WILLIAMSON Local Contribution ($):

From: 0.13 MI. EAST OF WYOMING SPRINGS DR

Total ($): 4,298,100.00

Let Date: 04/2015

Funding Category: 1To: 0.05 MI. WEST OF GTRR

Estimated Completion Date:

Summer 2016

Work Type: WIDEN TO 5-LANE WITH CENTER LTL

Page 54: FY 2015 APL

2014 Annual Project Listing51

Transit Projects - Round Rock Transit DistrictProject ID: TX-90-Y131-00 Federal Cost: $542,024

CSJ Number: Transportation Development Credits:

Project Name: Round Rock Transit District Local Cost: $766,286

County Name: Williamson Local Contribution:

From: City of Round Rock and ETJ Total: $1,308,310

To: Let Date: 5/13/2015

Work Type: Transit Capital Funding Category: 5307Estimated Completion Date:

8/30/2017

Transit Projects - UrbanFY 2015 Federal Funds Obligated

Transit Projects - Capital Metro Transportation AuthorityProject ID: NOTE: Capital Metro Transportation

Authority did not obligate any federal funds during the period of 10/1/2014 through 9/30/2015.

Three (3) federal formula grants programmed under FY 2015 were executed in November 2015.

Federal Cost:

CSJ Number: Transportation Development Credits:

Project Name: Local Cost:

County Name: Local Contribution:

From: Total:

To: Let Date:

Work Type: Funding Category:Estimated Completion Date:

Page 55: FY 2015 APL

2014 Annual Project Listing52

Transit Projects - RuralFY 2015 Federal Funds Obligated

NOTE: TxDOT-PTN has not yet provided information on rural transit lettings for FY 2015.