Innovations in Federal ESPC: Combined Heat & Power, ESPC ...
Future Plans. Overview Biomass Update Climate Commitment Update ECM ESPC Dashboard Deferred...
-
Upload
karlie-walton -
Category
Documents
-
view
214 -
download
0
Transcript of Future Plans. Overview Biomass Update Climate Commitment Update ECM ESPC Dashboard Deferred...
OverviewBiomass UpdateClimate Commitment UpdateECMESPCDashboardDeferred MaintenanceSupply Side Conservation
Biomass UpdateAugust 9 – received bids for test fuel
Carolina Wood Pellets selected520 tons purchased
August 31-September 1 – 20 tons to be deliveredPlan to burn the week after receiptDemonstrate suitability of feeding the fuel through the
existing coal handling and fuel feeding systemsBoiler maintenance outage
Document interior conditionInstall test portsInstall test ports and a fire detection/supression system
in ductwork going to the baghouseOptimize combustion fuel and air to optimize efficiency
Biomass UpdateEarly November – additional 500 tons
deliveredTest burn, expected to take 2 weeksVary fuel flow percentage of biomassCollect extensive test data at various load
points on the boilerMeasure efficiency and performanceUnderstand boiler operating characteristics
when cofiringMeasure stack gas emissions
Spring 2011 – Potential torrified wood test, dependent upon availability
Climate Commitment Update
120,000 metric ton reduction, back to 2003 levelFrom 30.6 to 24.6 total emissions per square foot
ECM Success 09-10Funds spent = $212,222
Annualized savings = $5-6 million
Equivalent to $68 million investment by ESCO
ECM Plans$200,000 annual budget
Remaining T12 lighting, survey and preliminary design for Kenan Center
Ductwork modifications in Global Education and Chapman
Matching portion of $865,843 in ARRA projects for lighting and HVAC
$100,000 supplemental (potential)Steam trap survey and replacementHVAC controls Wilson LibraryVariable speed drives Phillips and BeardPreliminary design, heat recovery, MBRB
Sta
te U
tili
ty A
pp
rop
riati
on
($)
“Baseline”
UNCDebt Obligation
Construction Loan to ESPC
2 - year averageutility costs
Contract Years
New “Baseline”
ESCO Guarantee Payment(if needed)
0-2 12 (typical)
Project Savings (Project Value)
ESPC
ESPCProcess (Two Years)
Measurement and Verification (Life of Project)Annual certified audits of
savingsUNC obligated for proper
operationESCO refunds savings
shortfall
Construction (12 months)
Fast paced to begin realized savings and make first bond payment
Final Contract
Termination possible if owner pays ESCO costs ($200-500k)
Investment Grade Audit (6-8 months)
Detailed analysis of all measures
Savings within 10% of proposal
Cost limited to 150% of proposal
ESCO Selection (4 months)
Bidders provide detailed cost proposals Best overall value selection
Application to SEO
Buildings defined Costs estimated
ESPCPreliminary Building Screening
Campus
Appropriated (130)
> $2.50/ft2(55)
> $200,000 Utility Cost
(35)
Stable Program (26
+/-)
ESPC 26 Candidate Buildings
2,747,588 square feet $14,156572 utility costs (variable only) $37,641,979 limit on performance contract (12 years,
30%)
20 of the Candidate Buildings were in the ECM Program 2, 213,810 square feet $11,808,301 utility costs (variable only) ECM project savings averaged 23% (range = 0% to 59%)
While ESPC offers little near-term benefit and we have other opportunities for low cost improvements that are outperforming ESPC investments, we have underlying capital needs could be addressed by ESPC
ESPC Plan 10-11Fall 2010 – invite ESCOs to quantify remaining
savings post-ECMWinter 2010 – Finalize candidate buildings
+/- 5 buildings in initial RFP$5 -$15 million contract value
Initial focusECM tuned buildings within 1 year of new
baseline dataBuilding automation system control upgradesLaboratory ventilation optimizationDedicated outdoor air systemsHeat recovery systems
DashboardDecided to reject all bids – too expensiveAgreement with Computer Science to write
the system in conjunction with current Energy Services applications programmersSupervised by Prof. Diane PozefskyMaster’s students
SchedulePrototype by end of Fall 2010Beta version by end of Spring 2011System live by Fall 2011
Deferred Maintenance$645 million backlog
$230 million is HVAC (2nd largest category is $57 million)
HVAC replacement normally must be completed as part of a comprehensive renovation, has been low priority because it requires relocation of building occupants
Divided workload into three groupsDemolishComprehensive renovationComponent replacement
Deferred MaintenanceDeveloping funding plan
Working on identifying new resourcesProjects in annual R&R allocation
Phillips Hall Lineberger Cancer Center
Need More R&R funding overall at state level Different allocation methodology at the state level
Need State of North Carolina to provide deferred maintenance capital infusion - $250 million range (received $515 in 2000 Higher Education Bond funding)
Supply Side InitiativesJu
ly
Aug
ust
Sep
tem
ber
Oct
ober
Nov
embe
r
Dec
embe
r
Janu
ary
Feb
ruar
y
Mar
ch
Apr
il
May
June
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
$140,000
$160,000
$180,000
$200,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
Cost Avoidance Thermal Energy Storage System
FY08 FY09 FY10 FY11 FY08 Cumulative FY09 Cumulative FY10 Cumulative
FY11 Cumulative
Mo
nth
ly (
$)
Cu
mu
lati
ve Y
TD
($)
Total avoided cost to date = $1.3 million, to date in 10-11 avoided costs = $282,460
Chilled Water Systems
Supply Side InitiativesChilled Water Systems
Increase production efficiencies33% efficiency increase at Cobb Chiller PlantInstalling a plate and frame heat exchanger at
the Tomkins Center in 10-11Rebuilding North Chiller Plant, will be most the
efficient plant at the end of projectGoal to increase chiller efficiencies by more than
1/3
District energy plant in the Imaging Research Building using heat recovery chillersRecover heat from chilled water systemUse to produce hot water for building use
Supply Side InitiativesCogeneration Systems
7% reduction in thermal losses in steam distribution system
Reduced average condensing rateReplaced VFDs on boilersOptimizing combustion of fluidized bed boilerReducing auxiliary energy usage by 10%
Electric Distribution SystemsLandfill gas project under construction in
2011 to supply electricity to Carolina North