fuel gas
Click here to load reader
description
Transcript of fuel gas
0 23/9/04Revised as per SEC comments SEC\SIEMENS/127/L
Dated 18/9/04 & Issued for Construction
NS AA KH
B 24-08-04 FOR APPROVALNS AA KH
A 29/07/04 FOR INTERNAL REVIEW NS AA H.K
REV. NO. DATE DESCRIPTION REVD.BY CHKD. BY APPD. BY
Project Name: PP7 EXTENSION 3 PROJECT
Owner: SAUDI ELECTRICITY COMPANY – CENTRAL REGION BRANCH
Contractor: SIEMENS POWER GENERATION
Subcontractor: ARABIAN BEMCO CONTRACTING CO. TITLE:
DESIGN CRITERIA – FUEL GAS SYSTEM
NAME DATE
PREPARED BY
SSD 29/07/04
CHECKED BY
AA 29/07/04
APPROVED BY
H.K 29/07/04
SCALE :
DOC. No. SHEET NO. REV. NO.
SAR687 – XV00 – 00EK – B20500 1 OF 8 0
MANUFACTURER’S DRAWING NO. PROJECT CODE CAD FILE UNID #
- - - 10 780 701
PP7 EXTENSION 3 PROJECTDESIGN CRITERIA – FUEL GAS SYSTEM
Table of Contents
1. Introduction....................................................................................................................3
2. Objective........................................................................................................................ 3
3. Description of Fuel Gas System.....................................................................................3
3.1. Tie in point................................................................................................................4
3.2. Gas pressure reducing station skid........................................................................4
3.3. Gas condensate drain tank......................................................................................5
3.4. Unit Coalescer Filter.................................................................................................5
3.5. Gas consumption metering.....................................................................................5
3.6. Final Chance Filter...................................................................................................5
3.7. Gas Flare system......................................................................................................5
3.8. Fuel gas station control panel.................................................................................5
4. Design Criteria...............................................................................................................5
4.1. Plant Design..............................................................................................................6
5. Arrangement / Layout.....................................................................................................6
6. Control Philosophy.........................................................................................................6
7. Codes and Standards....................................................................................................6
8. Specified Design Data....................................................................................................7
9. Annexure (Fuel gas Analysis)........................................................................................8
PP7 Extension 3 Project – Units 23 & 24 Design Criteria – Fuel Gas System
SAR687 – XV00 – 00EK – B20500
Sheet
REV 02 of 8
/tt/file_convert/557212de497959fc0b911cc1/document.doc
1. Introduction
A fuel gas system for existing twenty two (22) simple cycle gas turbines of PP7
station has been installed and is presently in operation. The existing fuel gas system
consists of :
one emergency shut down valve
Three (3) nos. filter separators
Four (4) nos. water bath heaters
Six (6) nos. pressure reducing stations
Twenty two (22) coalescer filters (one for each existing gas turbine)
It is decided to add two simple cycle gas turbines (units # 23 & 24) of model
W501D5A supplied by Siemens. Fuel gas filtration and pressure reduction as per the
requirements of gas turbines is carried out in the new fuel gas extension system. This
design criteria has been prepared in line with Owner’s specification and the offer
submitted by Siemens.
2. Objective
The objective of this Design Criteria is
1) To establish the basic engineering parameters considering the fuel gas
requirement for the extension III power plant for sizing of pressure reducing
valves, coalescer filters, gas condensate drain tank, and connection to existing
flare system
2) To establish the sizing criteria for the equipment, the control philosophy, codes
and standards applicable for the system.
3) To provide specified design data for the ERP of the subject system.
4) To provide a brief description about the system.
3. Description of Fuel Gas System
The new fuel gas extension system shall consist of one main isolation valve with
bypass equalizing, one pressure reducing valve skid (2 x 100% Main PCV & 2 x
Start-up PCV), 2 x 100% coalescer filters for both gas turbines, one gas condensate
drain tank (two cubic meters capacity), 1 x 100 % gas consumption metering for
each GT, 1 x 100 % final chance filter for each GT and Shut off & vent valves for
each GT. Fuel gas is tapped at a maximum rate of 62,800 kg/hr from the down
stream of existing water bath heaters and upstream of the existing PCV #6.
The design fuel gas analysis is the attached Annexure A.
PP7 Extension 3 Project – Units 23 & 24 Design Criteria – Fuel Gas System
SAR687 – XV00 – 00EK – B20500
Sheet
REV 03 of 8
/tt/file_convert/557212de497959fc0b911cc1/document.doc
0
The new fuel gas system equipment are identified as class 1, group D, division 2
category under hazardous area classification according to API 500 & NFPA 497.
The pressure control valve actuators are operated by instrument gas to be tied-in to
the existing instrument gas system or alternatively to the nearest header of the
existing plant instrument air.
3.1. Tie in point
The tie in point with the existing fuel gas system is with the 16’’ dia. pipe feeding the
existing PRS # 6 which is located in the down stream of existing water bath heaters.
Refer preliminary as built drawing ‘PP7 process flow diagram’ (PP7 – ME – 22 – 02 –
10012), Rev 2, two sheets. The process parameters available at the tie in point are
Pressure (barg) : 20.2 – 40
Temperature (deg. C) : 14.7 – 65
The minimum pressure at the inlet to the unit final chance filter is 350psig as per
Siemens requirement. Based on this minimum pressure requirement, the tie-in point
parameters shall be;
Pressure (barg) : 27.8 – 40
Temperature (deg. C) : 27 – 65
3.2. Gas pressure reducing station skid.
2 x 100 % fuel gas pressure control valves (PCV) are provided to make available fuel
gas to gas turbines at set pressure. The fuel gas maximum pressure is 40 barg. The
control valves can maintain constant pressure in its downstream between a pressure
range (to be confirmed later) meeting the pressure conditions downstream of the PCV
up to the inlet of the Econopac. Each control valve is provided with upstream slam
shut off valve (SSV) for quick isolation purpose. SSV shall have provision to close
manually for isolation and maintenance of the stream and should have provision to
close automatically upon actuation of fire detection system downstream of the PCV.
Each main Pressure Controlling Valve shall have a secondary start up Pressure
Controlling Valve to ensure smooth and reliable start up of the Gas Turbine with the
minimum flow rate requirements.
Each stream of the PRS shall be provided with isolation valve upstream of the
SSV and motorized valve downstream of the PCV.
PP7 Extension 3 Project – Units 23 & 24 Design Criteria – Fuel Gas System
SAR687 – XV00 – 00EK – B20500
Sheet
REV 04 of 8
/tt/file_convert/557212de497959fc0b911cc1/document.doc
0
0
Vent lines are provided in the down stream of pressure control valves.
3.3. Gas condensate drain tank
The gas condensate drain tank collects all the condensate drains from new fuel gas extension system and disposes manually to existing oily water drain system to the condensate discharge header of gas condensate tank of units 21 & 22.
3.4. Coalescer Filter
2 x 100 % capacity coalescer filters are provided for both gas turbine located
downstream of the pressure reducing skid. The filters can remove from the fuel gas
particulate matter up to 0.3 -0.5 microns to 99 % to 100 % efficiency and all size liquid
droplets to around100 %.
The condensate collected from the coalescer filters shall be routed to the gas
condensate drain tank and vents shall be routed to existing flare system.
3.5. Unit Gas Flow Meter
1 x 100% unit gas flow meter will be provided for each gas turbine. The gas flow meter will measure the actual gas consumption of each gas turbine.
3.6. Unit Final Chance Filter
1 x 100% unit final chance filter is supplied by Siemens for each gas turbine. For further details, Siemens related drawings will be referenced.
3.7. Gas Flare System
All vents and relief valve’s discharges from the new gas system extension are routed to the existing vent header which connects to the existing flare stack. Wherever not feasible, vents are extended to a safe elevation.
3.8. Fuel Gas Station Control Panel
For PRS skid, local control panel/junction box will be provided. The control panel will be hard-wired to the existing DCS of the gas system.
For Coalescer filter, the junction box will be hard-wired to the Econopac Control system.
4. Design Criteria
Description Criteria
Main Pressure Control Valves
Sized for a capacity of 62,800 Kg/hr for each valve. Design pressure is 60 barg. Tight shut-off, fail to close.
Coalescer Filter Sized for a capacity of 62,800 Kg/hr for both units. Design pressure 40 barg (to be confirmed later)
Start-up Pressure Control Valves
Sized to cater for low flow operation of one GT unit in start-up conditions or full speed no load. At higher flow, the main PCV will take over.
PP7 Extension 3 Project – Units 23 & 24 Design Criteria – Fuel Gas System
SAR687 – XV00 – 00EK – B20500
Sheet
REV 05 of 8
/tt/file_convert/557212de497959fc0b911cc1/document.doc
0
Condensate drain tank Two cubic meters capacity with pressure control and relief valves directing the drain to the existing oily water drain system the condensate to the discharge header of gas condensate tank of units 21 & 22
Gas Flow Meter Sized for a capacity of 31,400 Kg/hr for each unit. Design pressure 40 barg (to be confirmed)
Final Chance Filter Supplied by Siemens
4.1. Plant Design
The new fuel gas extension system will be designed as mentioned above to supply
the required quantity and quality of fuel gas to GTs. All piping will be of carbon steel
except the stainless steel piping between the final chance filter and the terminal
connections of the gas turbine. Maximum fuel gas velocity of 18.3 m/sec is
considered in selection of pipe sizing. The piping is routed in a built up trench or
above ground on sleepers.
5. Arrangement / Layout
The new fuel gas extension system equipment will be located outdoor. The fuel gas
extension system equipment is located in three different locations as given below:
1. 01UEN area consists of equipment described under clause nos. 3.2 and 3.4.
2. 23UEN area consists of equipment described under clause nos. 3.5 and 3.6
for GT#23
3. 24UEN area consists of equipment described under clause nos. 3.5 and 3.6
for GT#24
The condensate generated in the new fuel gas receiving equipment is routed to a
new gas condensate drain tank located near 01UEN area from which it is discharged
periodically to the existing oily water drain system discharge header of gas
condensate tank of units 21 & 22.
6. Control Philosophy
The control philosophy of the new fuel gas system extension will be detailed in
Vendor technical submittal.
7. Codes and Standards
The fuel gas extension system equipment and all associated piping and fittings will be
designed and manufactured as per well established engineering practices and safety
PP7 Extension 3 Project – Units 23 & 24 Design Criteria – Fuel Gas System
SAR687 – XV00 – 00EK – B20500
Sheet
REV 06 of 8
/tt/file_convert/557212de497959fc0b911cc1/document.doc
0
codes of the latest applicable American standards. If suitable American standards are
not available equivalent British / DIN / ISO standards will be followed.
Design and manufacture of the equipment will conform to the applicable codes and
SEC standards.
8. Specified Design Data
CL.NO. DESCRIPTION UNIT DATA1.0 Coalescer Filters
a) No. of Coalescer Filter No 2 x 100% for both GT’s
b) Type Coalescer
c) Gas Flow Capacity Kg/hr 62,800
d) Material of construction Carbon Steel as per ASME Sec. VIII Div. 1Vessel: SA 516 Gr. 70Vessel Internal: SA 36/304 SS
e) Filtration Degree 99 – 100 % removal of all solid particles larger or equal to 0.3-0.5 microns.
(100%) removal of all liquid droplets.
2.0 Pressure Reducing Station
a) No. of Main PCV No. 2 x 100%
b) No. of Start-up PCV 2
c) Gas Flow Rate (Main PCV) Kg/hr 31,400 62,800
d) Gas Flow Rate (Start-up PCV) Kg/hr 0-10% of Main PCV Flow Rate (To be Confirmed)
c) Type Fail to close, tight shut off valve
d) Operating pressure range barg To be confirmed
4.0 Unit Gas Flow Meter
a) No. of Unit Gas Flow Meter No. 1 x 100% for each GT
b) Type To be decided later
5.0 Unit Final Chance Filter Supplied by Siemens
PP7 Extension 3 Project – Units 23 & 24 Design Criteria – Fuel Gas System
SAR687 – XV00 – 00EK – B20500
Sheet
REV 07 of 8
/tt/file_convert/557212de497959fc0b911cc1/document.doc
0
9. Annexure (Fuel gas Analysis)
SHEDGUM AND UTHMANIUYAH GAS PLANTS DRY GAS Nitrogen 0.5 mole % 12.0 mole %Methane 80.7 mole % 82.7 mole %Ethane 16.0 mole % 5 mole %Propane 2.8 mole % 0.3 mole %Total 100 mole % 100 mole %
Hydrogen Sulfide Less than 2 ppm Less than 2 ppmOther sulfur compounds Nil NilHHV (at 14.696 psi) 44 MJ/CM
(1170 BTU/SCF)35 MJ/CM(930 BTU/SCF)
The temperature of dry gas is 150° F (65°C)
PP7 Extension 3 Project – Units 23 & 24 Design Criteria – Fuel Gas System
SAR687 – XV00 – 00EK – B20500
Sheet
REV 08 of 8
/tt/file_convert/557212de497959fc0b911cc1/document.doc