3 June 2003 FT Status and Plans Overall CTS Used to test VRBC boards Qualified several AFE boards Lots of changes made to VRBC’s Current status 50 >> old VRBC, new firmware 51 >> old VRBC, new firmware 52 >> new VRBC, new firmware 53 >> new VRBC, new firmware AFE board swap Installed CFT board in FPD Worked on CFT and FPS boards

description

FT Status and Plans. Overall CTS Used to test VRBC boards Qualified several AFE boards Lots of changes made to VRBC’s Current status 50 >> old VRBC, new firmware 51 >> old VRBC, new firmware 52 >> new VRBC, new firmware 53 >> new VRBC, new firmware AFE board swap - PowerPoint PPT Presentation

Transcript of FT Status and Plans

Page 1: FT  Status and Plans

3 June 2003

FT Status and Plans

• Overall

– CTS

• Used to test VRBC boards

• Qualified several AFE boards

• Lots of changes made to VRBC’s

– Current status

• 50 >> old VRBC, new firmware

• 51 >> old VRBC, new firmware

• 52 >> new VRBC, new firmware

• 53 >> new VRBC, new firmware

• AFE board swap

– Installed CFT board in FPD

– Worked on CFT and FPS boards

Page 2: FT  Status and Plans

3 June 2003

July Shutdown

• General items being considered– Cryostat work

• About 1 degK left in setting• Have been moving about 0.1• Will not warm up “unless” have further problems

– Cassette work• Only if we warm up• Perhaps install ‘testing’ cassette

– Will do• Pull and modify ALL AFE boards

– Unused channel fix for AFE brds– 53MHz readout

• Check/calibrate/fix AFE lvps monitoring• Add SEQ crate monitoring• Finish LED pulser boards and cabling• New firmware• Fix slot problems – AFE & SEQ

– 4B6 SVX Downloads– 6B2/3 SEQ signals @ SEQ BP

– May do• AC remote shutoff for AFE lvps• Re-cable back of SEQ crate PC04

– Will not do• CPS• FPS• CTT• FPD

Starts ~Aug 28 >> 7 weeks