FS Uno Modules in Landscape - schletter.us · ALL CONCRETE WORK SHALL CONFORM WITH THE REQUIREMENTS...

10
FS Uno TM Ground Mount Installation Manual 1/10 © Schletter Inc 1001 Commerce Center Drive Shelby, North Carolina 28150 Tel: (704) 595 - 4200 Fax: (704) 595 - 4210 [email protected] www.schletter.us MI-009 040416 ISO 9001:2008 Q U A L I T Y C E R T IF IC A T I O N FS Uno Modules in Landscape The Schletter FS Uno for ground mount photovoltaic (PV) installation is specifically designed to meet or exceed applicable IBC and ASCE standards. Features Pre-assembled components Fully integrated and modular components Wind tunnel tested Includes grounding module clamps Each FS Uno is custom designed to meet specific structural load requirements. Included in the FS Uno are clamps specifically designed to secure and bond the frame of a PV module. In turn, the components and assemblies that comprise an FS Uno form an electrically bonded unit. While individual components and structural sections will vary between designs, the primary assemblies and installation methods will remain the same. During installation, fully assemble the system before securing bolts to the final torque. Key Components 1. Post 2. Steel Head 3. Strut 4. C-Rail (girder) 5. Retainer plate 6. Z-Rail (purlin) 7. Clamp adapter 8. Wedge 9. Grounding Module Clamp 1 2 3 4 5 6 9 7 8

Transcript of FS Uno Modules in Landscape - schletter.us · ALL CONCRETE WORK SHALL CONFORM WITH THE REQUIREMENTS...

FS UNO 2H SIDE VIEWSCALE 1 : 8

FS UnoTM Ground Mount Installation Manual

1/10© Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

FS Uno Modules in Landscape

The Schletter FS Uno for ground mount photovoltaic (PV) installation is specifically designed to meet or exceed applicable IBC and ASCE standards.

Features• Pre-assembled components• Fully integrated and modular components • Wind tunnel tested• Includes grounding module clamps

Each FS Uno is custom designed to meet specific structural load requirements. Included in the FS Uno are clamps specifically designed to secure and bond the frame of a PV module. In turn, the components and assemblies that comprise an FS Uno form an electrically bonded unit. While individual components and structural sections will vary between designs, the primary assemblies and installation methods will remain the same. During installation, fully assemble the system before securing bolts to the final torque.

Key Components1. Post2. Steel Head3. Strut 4. C-Rail (girder)5. Retainer plate6. Z-Rail (purlin)7. Clamp adapter8. Wedge9. Grounding Module Clamp

1

2

3

4

5

6

9

7

8

1

A

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

B

C

D

E

F

G

H

I

J

K

1 2 3 54 6 7 8 9 10 11 12 13 14 15 16 17

A

B

C

D

E

F

G

H

I

J

K

NO. DRAWN: CHECKED: REVIEWED: APPROVED: REVISIONS: Drawing Number:0 DugaKe 1/22/2015

Racking Structure v.01JOB NUMBER:

SHEET:

SCALE:

SEE DRAWING VIEWSISSUED BY: SCHLETTER INC.

PROPRIETARY AND CONFIDENTIAL

Client: Project Site:

NOT BE USED FOR CONSTRUCTION.

STRUCTURAL ENGINEER, IT ISA PRELIMINARY DESIGN AND SHALL

AND SEALED BY A LICENSEDUNLESS THIS DRAWING IS SIGNED

PRELIMINARY

v

New Drawing

3761 E. FARNUM PLACE | TUCSON, AZ 85706TEL: (520) 289 - 8700 | FAX: (520) 289 - 8695

EMAIL: [email protected]

Schletter Inc.FS Uno 4H x 11 20°

Dimensions and Specifications

1 of 2

Schletter Inc

DESIGN CRITERIA: 2013 EDITION OF THE CALIFORNIA BUILDING CODE, WITH LOCAL AMENDMENTS.

LOADS: MODULE DEAD LOAD = 2.35 PSF SNOW LOAD = 0 PSF

WIND DESIGN: DESIGN BASED UPON WIND TUNNEL TEST REPORT # RC 1127/0510-e BASIC WIND SPEED = 110 MPH (3 SECOND GUST). EXPOSURE: C Vasd = 85 MPH RISK CATEGORY = II

SEISMIC LOADS: SEISMIC DESIGN CATEGORY: D Sds = 0.877 SD1 = 0.493 Ie = 1.0 SS = 1.316 S1 = 0.489

INSTALLATION TOLERANCES: LATERAL POST PLACEMENT IS ±5.0" TOTAL LATERAL DEVIATION OF POSTS WITHIN AN ARRAY IS ±5.0" POST HEIGHT VARIATION TOLERANCE IS ±0.40" POST VERTICALITY TOLERANCE <2.0° IN ALL DIRECTIONS POST ROTATIONAL TOLERANCE <±7.0° ARRAY TILT ANGULAR TOLERANCE ±1.0°

GENERAL: 1. THE STRUCTURAL CONSTRUCTION DOCUMENTS REPRESENT THE FINISHED STRUCTURE. THEY DO NOT INDICATE THE METHOD OR SEQUENCE OF CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR AND PROVIDE ALL MEASURES NECESSARY TO PROTECT THE STRUCTURE DURING CONSTRUCTION. SUCH MEASURES SHALL INCLUDE, BUT NOT BE LIMITED TO, BRACING, SHORING FOR LOADS DUE TO CONSTRUCTION EQUIPMENT, ETC. THE STRUCTURAL ENGINEER SHALL NOT BE RESPONSIBLE FOR THE CONTRACTOR'S MEANS, METHODS, TECHNIQUES, SEQUENCES FOR PROCEDURE OF CONSTRUCTION, OR THE SAFETY PRECAUTIONS AND THE PROGRAMS INCIDENT THERE TO (NOR SHALL OBSERVATION VISITS TO THE SITE INCLUDE INSPECTION OF THESE ITEMS). THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE DESIGN AND IMPLEMENTATION OF ALL SCAFFOLDING, BRACING AND SHORING. 2. WHERE REFERENCE IS MADE TO VARIOUS TEST STANDARDS FOR MATERIALS, SUCH STANDARDS SHALL BE THE LATEST EDITION AND/OR ADDENDA.

ALUMINUM: 1. ALL ALUMINUM SHALL CONFORM WITH THE LATEST ALUMINUM DESIGN HANDBOOK. 2. ALL ALUMINUM SECTIONS SHALL BE: a. SEMI-HOLLOWS AND HOLLOWS SHALL BE 6105-T5, 6005A-T6, OR 6005-T5 b. SOLIDS SHALL BE 6063-T6

STEEL: 1: ALL BOLTS AND WASHERS SHALL BE 304 STAINLESS STEEL CLASS 2 (A2-70). 2. ALL NUTS SHALL BE 316 STAINLESS STEEL CLASS 2 (A4-70) 3. ROLL FORMED STEEL RAILS AND GIRDERS SHALL BE HSLA-F GRADE 70 G90 ASTM A653 4. ROLL FORMED STEEL POSTS AND STRUTS SHALL BE SAE J2340

TORQUE: TORX BOLT FOR RAPID 2+ MODULE CLAMPS IS 14 N-M (10.5 FT-LBS) M6 AND 1/4" BOLT TORQUE IS 6 N-M (4.5 FT-LBS) M8 AND 5/16" BOLT TORQUE IS 14 N-M (10.5 FT-LBS) M10 AND 3/8" BOLT TORQUE IS 30 N-M (23 FT-LBS) M12 AND 1/2" BOLT TORQUE IS 50 N-M (37 FT-LBS) M16 AND 5/8" BOLT TORQUE IS 121 N-M (89 FT-LBS) M20 AND 3/4" BOLT TORQUE IS 244 N-M (180 FT-LBS)

NOTE: RECOMMENDED SPEED FOR INSTALLATION OF SELF-DRILLING 1/4" DIAMETER SCREWS IS 1200-1800 RPMS.

MODULE SIZE: RACKING SYSTEM DESIGNED FOR MODULE SIZE: 1954mm x 983mm x 40mm VERTICAL MODULE GAP: 5 mm HORIZONTAL MODULE GAP: 23 mm

FOUNDATIONS: 1. NO SOILS REPORT PROVIDED. FOUNDATION DESIGN IS BASED ON MINIMUM IBC SOIL BEARING VALUE = 1500 PSF PER IBC TABLE 1804.2. DRILLED SHAFT FOUNDATIONS SHALL BE BUILT IN UNDISTURBED SOIL OR COMPACTED FILL MATERIAL NOT LESS THAN 12" IN DEPTH. THE MINIMUM DEPTH OF FOOTINGS BELOW THE UNDISTURBED GROUND SURFACE SHALL BE 12". 2. THE STRUCTURAL ENGINEER IS NOT RESPONSIBLE FOR ANY GEOTECHNICAL ASPECTS OF THIS PROJECT. IT IS RECOMMENDED THAT THE OWNER RETAIN A REGISTERED GEOTECHNICAL ENGINEER TO CONDUCT A GEOTECHNICAL INVESTIGATION AND PREPARE A REPORT WITH RECOMMENDATIONS FOR FOUNDATION AND EARTHWORK PROCEDURES.

CONCRETE: 1. ALL CONCRETE WORK SHALL CONFORM WITH THE REQUIREMENTS OF ACI 301 AND ACI 318. CEMENT PER ASTM C150, TYPE II. AGGREGATE PER ASTM C33. CONCRETE SHALL BE READY MIXED IN ACCORDANCE WITH ASTM C94 AND SHALL BE DESIGNED FOR A MINIMUM 28 DAY COMPRESSIVE STRENGTH AS FOLLOWS: FOUNDATIONS…………………………………………………………3,000 PSI* *DESIGNED FOR 2,500 PSI

FRONT ELEVATIONSCALE 1 : 45

391 [1538 in] 1172 [46 3

16 in]

315 [1238 in] 11600 [45611

16 in]

20915 [823 716 in]

21544 [848 316 in]

391 [1538 in]1172 [46 3

16 in] TYP

315 [1238 in]9310 [366 9

16 in]

1298 [51 116 in]1298 [51 1

16 in] 4580 [180 516 in] TYP

1145 [45 116 in]

5 [ 316 in] TYP

SPLICE 1954 [761516 in] TYP

FINISHED GRADE

A

A

SECTION A-ASCALE 1 : 15

1160 [451116 in]

610 [24 in]

2806 [110 716 in]

1849 [721316 in]

612 [

241 16 in

]

86 [3

3 8 in]

1676

[66 i

n]

240 [

97 16 in

]96

0 [37

13 16 in

]

1200

[471 4 i

n]15

90 [6

25 8 in]

2790

[109

13 16 in

]

2029

[797 8 i

n]

20°

71 [2 1316 in]

79 [3 18 in]

1157 [45 916 in]

805 [31 1116 in]

1006 [39 58 in] TYP

4024 [158 716 in]

4174 [164 516 in]

ISOMETRIC VIEWSCALE 1 : 60

FINISHED GRADE

2.0' DIA X 5.5' DEEPCONCRETE FOOTING

983 [38 1116 in] TYP

FS UnoTM Ground Mount Installation Manual

2/10 © Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

Sample DrawingsSpecific drawings are provided for each project. Key information included on these drawings is as follows:

1. Design Criteria2. Notes Section3. Module Dimensions

4. Array Tilt5. Array Dimensions

6. Post Embedment7. Footing Size (if applicable)

2

1

SAMPLE DRAWING ONLY

45

6

37

FS UnoTM Ground Mount Installation Manual

3/10© Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

Installation Tools

• String line with wood line blocks

• Permanent marker

• Tape measure

for foundation post installation

for wedge

for girder-to-purlin connection

for all bolted connections

for standard module clamps

• Rubber mallet

• 2’ Carpenter’s square

• Torpedo level or protractor

• Wrench and/or socket

• Torque wrench

• Ratchet and/or rechargeable power drill

• Hex head wrench 6 mm

17 mm

19 mm

for self-drilling screws• 3/8” Socket

3/8” Socket

FS UnoTM Ground Mount Installation Manual

4/10 © Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

Foundation Post Installation

• Review final drawing. Drawing will include information vital to the proper installation of the foundation posts such as the embedment depth, post-to-post spacing, and installation tolerances.

• Please note: Schletter does not provide construction layouts.

• For longer racks, intermediate stakes may be required.

• Installation tolerances:

Lateral post placement is ±5.0”

Total Lateral deviation of posts within an array is ±5.0”

Post height variation tolerance ±0.40”

Post verticality tolerance <2.0° in all directions

Post rotational tolerance <±5.0°

Array tilt angular tolerance ±1.0°

1. Survey Proposed Site

Lateral cantilever Support distance

4 inches

Tolerance

Embedment depth E-W slope

±5°

Rotation Elevation difference between adjacent post

Maximum 7°

4” Maximum

±0.4”

FS UnoTM Ground Mount Installation Manual

5/10© Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

Position hydraulic ram and lift post into position beneath ram head

Hammer head touching top string line indicates correct depth is reached

2. Post Installation

• Position each post at respective installation locations based on the completed stake-out (use a forklift).

• Position the hydraulic ram (GAYK) at the installation location and lift the post into position beneath the ram head.

• Level hammer using bubble level on hydraulic ram.

• Level mast of hydraulic ram.

• Level post using a torpedo level.

• Advance the post approximately two feet into the subsurface then re-check level.

• Advance the post to the embedment depth as shown on the final drawing.

• Position string lines: bottom string line is used for correct placement of post; top string line is measured from the top of the post to bottom of the hammer head indicating the correct embedment depth.

• When installing subsequent posts, ram until the hammer head touches the top string line. Use string line as guide to determine

correct placement and depth of posts

Mark each post location using soil nails with flagging

Position posts on marked locations (use a forklift)

Ram two posts at opposite ends of array for string line

FS UnoTM Ground Mount Installation Manual

6/10 © Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

Individual Assembly Groups1. Install of Optional Post Splice

2. Attach Steel Head

• Verify torque on all bolts.

• Splices are used to extend the length of a post.

• Splice location will vary depending on project.

• Consult project specific drawings.

• Once the head assembly is aligned, verify the torque of the bolts.

• Head piece attaches to inside right of the post

Feed the M12 bolts through the pre-punched hole in the strut and ti ghten loosely with nut and washer to the steel head

Align steel head to the inner side of the post and fasten using M12 bolts, washers and nuts (front view of post)

Install shim plates between post and splice tubing using 3/4” bolts, nuts, and washers

DETAIL ASCALE 1 / 2

A B

1

1

2

2

3

3

4

4

A A

B B

C C

D D

MATERIAL:

DATEREV BYSHEET: OF

TOLERANCES:

REVISION#

WEIGHT:

AREA:

PART NUMBER:

DESCRIPTION / PROJECT / CUSTOMER:

RT PART #:

SIZE:

SCALE: AS SHOWN

ENG APPROVAL DATE:

MFG APPROVAL DATE:

CREATION DATE:

CHECKED DATE:

DRAWN BY:

APPROVED:

STATUS:

CHECKED:

MFG:

christopher.schatz

WorkInProgress

11/25/2014

C

N/A

FS UNO Head Mount

OLD PART # :

kg/m or kg/sq m:

N/A

ISSUED BY: SCHLETTER INC. - PROPRIETARY AND CONFIDENTIALAll rights reserved. Reproduction of any kind only with the express, written consent of the Co: Schletter Inc.

3rd ANGLE PROJECTION RDC # APPROVEDNOTE:

DESIGN STATUS DATE:

Mounted head assembly with multiple holes for adjustment flexibility (rear view of post)

3. Mount Girders

• Steel head has multiple bolt holes to allow for adjustment.

• Do not fully tighten the bolt on the steel head. The connector must be loose for mounting the strut.

DETAIL ASCALE 1 / 2

A B

1

1

2

2

3

3

4

4

A A

B B

C C

D D

MATERIAL:

DATEREV BYSHEET: OF

TOLERANCES:

REVISION#

WEIGHT:

AREA:

PART NUMBER:

DESCRIPTION / PROJECT / CUSTOMER:

RT PART #:

SIZE:

SCALE: AS SHOWN

ENG APPROVAL DATE:

MFG APPROVAL DATE:

CREATION DATE:

CHECKED DATE:

DRAWN BY:

APPROVED:

STATUS:

CHECKED:

MFG:

christopher.schatz

WorkInProgress

11/25/2014

C

N/A

FS UNO Head Mount

OLD PART # :

kg/m or kg/sq m:

N/A

ISSUED BY: SCHLETTER INC. - PROPRIETARY AND CONFIDENTIALAll rights reserved. Reproduction of any kind only with the express, written consent of the Co: Schletter Inc.

3rd ANGLE PROJECTION RDC # APPROVEDNOTE:

DESIGN STATUS DATE:

FS UnoTM Ground Mount Installation Manual

7/10© Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

• Attach strut to girder and post with provided M10 and M12 hardware.

• The strut must be slotted into the open side of post.

• Once all connections are in place, tighten bolts according to torque specifications.

Install one end of strut to connector on girder and the other end to post

Strut to girder connection

Strut to post connection

4. Install Strut

5. Mount Purlins

• Purlin must be mounted at a 90° angle to the girder.

• The distances between purlins must be observed as specified in the drawing.

• Use rubber mallet to drive in the wedge.

• Retainer plate has slotted holes for adjustment.

Insert purlins into pre-assembled retainer plates

Hammer in the wedge

Wedge

FS UnoTM Ground Mount Installation Manual

8/10 © Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

• Install Proklip-F cable tube support onto post.

• Proklip-F will accommodate 2.5-inch diameter conduit.

• Combiner box mount is installed against exterior end of foundation post as shown in image (combiner box not included).

1. Cable Management

Optional Accessories

ProKlip-F

Combiner box mount (exploded view)

Cable Management Installation Guide

6. Splice Connection

• Mount splice on the front side of the purlin.

• Splices to be located according to system specific drawings.

• Torque to specification.

Secure splice connection with M12 bolt and washer, and M12 nut

Side view

FS UnoTM Ground Mount Installation Manual

9/10© Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

Allowable gaps between modules

1. Position Modules

Module Mounting

2. Secure Modules

• Verify that the module clamp is fully engaged on the clamp adapter and is aligned with the module frame.

• When mounting modules, please observe the clamping points specified by module manufacturer.

• Torque clamp bolts to 10.5 ft lbs.Modules are positioned on purlins according to specified dimensions

• Position and secure clamp adapter on purlin; refer to system specific drawings to locate connection points.

• End clamps are positioned approximately 20 mm from the end of the purlin.

Snap clamp adapter into place as shown on image

Secure clamp adapter with self-drilling screw

1.5 mm maximum

FS UNO 2H FRONT VIEWSCALE 1 : 10

5 mm

23 mm

FS UnoTM Ground Mount Installation Manual

10/10 © Schletter Inc • 1001 Commerce Center Drive • Shelby, North Carolina 28150 • Tel: (704) 595 - 4200 • Fax: (704) 595 - [email protected] • www.schletter.us

MI-009 040416ISO

9001:2008

QUALITY

CERTIFICATION

Torque Specifications and TolerancesSystems are specifically designed for each project. Please reference your specific project drawing for allowable tolerances and recommended torque for each size of bolt used in the system.

In the event of deviation from approved drawings, contact Schletter immediately.

Safety PrecautionsFollow proper installation and safety procedures at all times. Edges of parts may be sharp. Follow proper lifting procedures.

FS Uno Product SheetExample Drawings

Assembly AnimationGAYK Hydraulic Ram Product Sheet

For More Information