From Apollo - NASA
Transcript of From Apollo - NASA
From Apolloto
Cognac
An aerospace-derivedtraining simulator, animportant aid tosuccessful installation ofthe worM's tallest oil
platform, highlightsspinoffs in the fieldof energy
Last year Shell Oil Company startedoil and gas production from a newoffshore platform called Cognac,located in the Gulf of Mexico about 20miles off the coast of Louisiana. The
world's tallest oil platform, slightlytaller than the Empire State Building,Cognac represents an investment ofsome $800 million by Shell and 14 othermembers of the Cognac consortium.
Its emplacement, at an unprecedentedwater depth of more than 1,000 feet,involved more than six years ofdevelopment and construction effort,a job termed by a trade journal "asmuch a breakthrough in the offshoreindustry as (Neil) Armstrong's first stepon the moon was to space exploration."
Coincidentally, space technology
played an important part in the Cognacproject. Like NASA's landings on themoon, deepwater siting of a structure
as large as Cognac was something thathad never before been done. The
magnitude of the job dictated use of anumber of high technology systems,including a training simulator whichallowed installation crews to practicebeforehand the complex tasks theywould have to perform. Shell awardedthe simulator contract to Honeywell'sMarine Systems Center, Seattle,Washington. In the resulting CognacCrew Trainer and Simulator, Honeywell
incorporated technologies earlierdeveloped under NASA contract for alunar landing simulator.
Because of Cognac's great size, itwas necessary to build the support
"jacket" in three sections--the topsection alone is larger than any
previous Gulf structure--and movethem by barge to the Cognac site.
•The installation plan called for four
major operations. First, the jacket'sbase section, suspended between twoderrick barges by multiple cables, wasto be water-ballasted and lowered
to a precise spot on the sea floor;there it would be anchored by24 huge piles driven deep into theseabed by a massive underwaterhammer remotely controlled from theprimary barge. Next, the midsectionwas to be lowered and mated to the
base section by means of a dockingmechanism--docking poles in the legsof the midsection which fitted into
"mating guides" on the base section.In similar fashion, the upper section
of the jacket would be mated with themidsection. Finally, the 2,0(0)-tonworking deck would be constructedatop the completed jacket.
Although it sounds simple enoughin brief outline, the installation job was
enormously complex. It required anelaborate array of informational anddisplay equipment, a key element ofwhich was a Honeywell acousticposition reference system, whereincomputer measurement of signals fromtransponders on the seabed allowedcontinuous determination of the
relative positions of the derrick barges,the jacket sections and the target siteon the sea floor. A radar ranging
system insured that the derrick bargeswere always properly positioned withrespect to each other. For dockingsections together, the acoustic systemprovided initial reference informationand underwater video cameras
permitted visual sighting for finalalignment. A telemetry system relayeddata from a variety of sensors on suchvital considerations as surface winds,
wave heights and current strength; the
amount of water ballast in the legs of
a section being lowered; the tilt angleof a submerged section, which had tobe controlled within a fraction of a
degree; the status of the barge-mountedwinches, how fast they were paying outcable and the amount of tension on
each cable. Processed by several
computers, all this information was fedto displays in the control center onthe primary barge.
The Honeywell-developed crewtrainer was capable of simulating eachevent involved in the installation task,
for example, positioning the surfacevessels, ballasting and lowering the
sections, pile driving and maneuveringa section into position for docking.All simulator controls and displaysreacted exactly as they would in the
real operation. The system alsosimulated emergencies to prepare thecrew for such abnormal occurrences
as unexpected changes in wind orcurrent, the snapping of a cable, lossof critical sensors or improper opera-tion of ballasting valves. Beginning in
1977, Cognac installation crews usedthe trainer/simulator repetitively tofamiliarize themselves with the vast
amount of data displayed in the control
center and to practice the sequenceof events involved in each of the
major operations.Cognac's base section was positioned
in the summer of 1977; installation of
the mid and top sections of the jacket
was completed a year later, then thetwo-acre deck and a pair of drilling rigswere added in the latter part of 1978.With the completion of a pipeline inmid-1979, oil began flowing from
Cognac to Shell's facilities at EastBay, Louisiana. Not until 1983, however,
At a site in the Gulf of Mexico, one
section of the huge Cognac oil platformis launched from its transport barge.The section was then water-ballasted
and lowered by cables to an underwatermating with another, previouslysubmerged section.
will Cognac reach full production,estimated at 50,000 barrels of oil and100 million cubic feet of natural gaseach day.
Considering the extraordinary natureof the job, Cognac's installation was
carried out in remarkably smoothfashion. The Honeywell trainer was
a major contributor, according to manyof those involved, because it instilledin installation crewmembers
confidence in their ability to handlethe exacting tasks assigned them. Infact, some said, the actual operations
seemed easier because the trainingsessions had been so demanding.
The highly complex job of installingCognac's support '_iacket" under watermore than a thousand feet deep wasdirected from this barge-based control
center. To enable crews to practice inadvance difficult tasks never before
accomplished, Honeywell Inc. de-veloped a system for simulating thevarious underwater operations. Intraining sessions, the displays andcontrols pictured reacted exactlyas they would in a real operation. 101
102
iiiiiiiiiiiiiii_iiiiiiiiiiiii!_iiiiiii_!_iiiiiiiiiiii_i_iii!iiiii_iiiiiiiiii_iii_iiiiiiiiiiiii_iii!iiiii_i!iiiiiii!iiiii!i_iii_i_i!iii_i:i:i:i:i:i:i:i:i:
Taller than the Empire State Building,Cognac was built in several sections atMorgan City, Louisiana. Here the8,O00-ton midsection--one of threesegments of the support jacket--isbeing towed through the Louisiana
bayous to the Cognac site.
At the Gulf of Mexico installation site
20 miles off the Louisiana coast,Cognac's midsection is readied forlaunching. The structure was lowered
by winches on the two derrick bargesand joined to the base section anchoredto the sea floor Later the topmostsection of the jacket was similarlylowered and mated. Operations were
remotely controlled from the primarybarge shown in the foreground.
ThesephotosillustrateoneofthemanysimulationsperformedbytheHoney-wellcrewtrainingsystem.Thedeviceatrightmodelsthemethodbywhich24giantpiles--eachmorethan600feetlong--weredrivendeepintotheseabedtoserveasanchorpostsforCognac'ssupportstructure.Thepileshadtobeloweredbyaspecialelevatorandmaneuveredbyoperatorsinthecontrolcentertoamatingwithguideframesontheseafloor.Theelevatorswereequippedwithinstrumentswhosesignalsreportedthepositionofthedescendingpilerelativetotheguideframe.A televisioncamerafixedtothepileprovidedvisualconfirmationontheconsoleshownbelow.RepetitivesimulationsofthisandotheroperationscontributedsignificantlytoCognac'ssuccessfulemplacement.
103