Friends of The FoundationAction Schedule
Week commencing:21 July 2014
Updated by:Zokwanda Rasmeni
Project Team:Bokang Pooe (BP) SK Zuma (SK)
Thando Sipuye (TS) Kudzai Vanyoro (KV)
Obenewa Amponsah (OA) Bruce Waters (BW)
Zokwanda Rasmeni (ZR)
DESCRIPTIONRES
(COMPANY)
RES
(PERSON)ACCOUNT DEADLINE STATUS
BUDGET Draft tentative budget
Items:
-Design
-Photography if and when
required
-Printing
-Enabling payment facility on
website
PB ZR OA&BW 11/08
BRIEFS Design Team
BriefPrinterboyson all design
requirements
SBF ZR ZR 11/08
Participants
Draft briefing letter to all
participants
SBF ZR ZR 11/08
Communications Team SBF TS&KV ZR 12/08
1
-
7/26/2019 Friends of the Foundation Campaign Action Schedule
2/4
Brief TS and KV on:
-Requirements for external
communication plans
-Twitter campaign
Team
Circulate briefing document
to team
SBF ZR ZR 12/08
CONTRACTS -Draft contract for use of
external material if and
when required
-Finalise membership benefits
SBF ZR OA If required
CREATIVE
ELEMENTS
-Design Membership card
-Design Website visuals-Design Posters
BP
SBF
BP
SK
ZR
SK
ZR 12/08
12/08
12/08
DIARIES -Secure dates for each
respective Tweep to upload
pic
SBF ZR ZR 12/08
PARTICIPANTS
LIST
-Identify active Tweeps across
various demographics
-Compile list of suitable
Tweeps and SBF unofficialfriends to invite to take part
in the Twitter campaign
SBF ZR&BP OA 11/08
INVITATIONS Send letters to participant list SBF ZR ZR 13/08
INTERNET -Manage Twitter campaign
-Manage Facebook
notifications
-Add campaign to google ads
SBF KV
KV
ZR 18/08
18/12
Ad-hoc
2
-
7/26/2019 Friends of the Foundation Campaign Action Schedule
3/4
-Updates website
-Ensure website payment
capabilities if/when
required
-Send invitation letter to
participants
-Send e-mail notifications to
SBF guest list
KV
KV
KV
ZR
KV
18/08
15/0915/08
18/08
18/08
LOGOS Ensure the logo is displayedon:
- Membership card
- Website
- e-mail communiqu
- Facebook communiqu
- Twitter communiqu
SBF
ZR
KV
KV
KV
KV
ZR WhenRequired
PHOTOGRAPHY - If and when required SBF KV ZR When
required
PROGRAMME - Draft timeline for Twitter
campaign
SBF ZR ZR 12/08
PRINTING - If and when required SBF KV ZR When
required
POSTERS - Design posters
- Print posters
PB&SBF SK & KV ZR When
required
TWITTER - Draft strategy document for SBF ZR TS&KV See brief
3
-
7/26/2019 Friends of the Foundation Campaign Action Schedule
4/4
COMPAIGN campaign
- Draft timeline for execution
of campaign
- Mange Campaign
ZR
KV
TS&KV
TS&KV
12/08
18/09-30/12
4