FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner,...

37
This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661, the State of Michigan and Michigan State University. Michigan State University designs and establishes FRIB as a DOE Office of Science National User Facility in support of the mission of the Office of Nuclear Physics. Matthaeus Leitner Superconducting RF Department Manager FRIB Cryomodule System Design

Transcript of FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner,...

Page 1: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661, the State of Michigan and Michigan

State University. Michigan State University designs and establishes FRIB as a DOE Office of Science National User Facility in support of the mission of the Office of Nuclear Physics.

Matthaeus LeitnerSuperconducting RF Department Manager

FRIB Cryomodule System Design

Page 2: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Cryomodule Overview

Detail Cryomodule Interfaces

Cryomodule – Linac Section Interfaces• Front End

• Stripper

• Folding Segments

• Warm Diagnostics Boxes

Summary

Outline

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 2

Page 3: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Cavity And Cryomodule Count Plus Need For Several Cavity Families Make FRIB Challenging

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 3

Cavity TypeQuantity of

Cavities

Quantity of

Modules

Quantity of

Solenoids

β=0.041 12 3 6

β=0.085 88 11 33

β=0.29 72 12 12

β=0.53 144 18 18

Additional

Bunching

Modules

6

4

4

2 (β=0.085)

2 (β=0.29)

1 (β=0.53)

n/a

Total 330 49 69Quant i t ies do no t inc lude 4 spare cryomodules and 17 spare cav i t ies .

Page 4: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

FRIB Superconducting Driver LinacLayout is Folded Into Three Accelerator Sections

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 4

Driver Linac

≥ 200 MeV/u Oxygen To Uranium

Primary Beam Power on Target: 400 kW

49 (+ 4 Spare) Cryomodules, 330 (+ 17 Spare) Cavities

High Power Accelerator Paired With Significant Operational Flexibility

Page 5: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

First FRIB-style Quarter Wave Cryomodule Under Construction: Cavities Operate At 2 K, Solenoids At 4.5 K

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 5

FRIB Bayonet Connections

Magnetic Shield

β=0.085 CavitySolenoid

2K Heat Exchanger Cryogenic Piping

Vacuum Vessel Base Plate

Alignment Support

Solenoid Leads

Coldmass Support Rails

ANL RF Coupler

Projected Heat Load Static Dynamic

2 K 4.0 W 32.0 W

4.5 K 20.5 W 2.1 W

38/55 K 167.2 W 33.4 W

Cold Beam

Position Monitor

Page 6: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Cryomodule Main Components Allow Modular Procurement And Assembly

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6

Vacuum vessel

Thermal shield

Cryogenics

Magnetic shielding

Coldmass

Bottom plate

Bayonet box

Alignment adjusters

• Subassemblies procured from industry

• Main assembly performed at MSU

Page 7: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Both Key Coldmass Designs FinalizedDesign and Prototyping Progress Supports Project Baseline

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 7

Quarter Wave Resonator Coldmass

Half Wave Resonator Coldmass

β=0.085 Cavity

(operated at 2 K)

Wire Position Monitor

(Alignment Verification)

Solenoid

Vapor-Cooled Leads

SC Solenoid

(operated at 4.5 K)

Power Coupler

Support Rail

β=0.53 Cavity

(operated at 2 K)

SC Solenoid

(operated at 4.5 K)

Support Rail

Power Coupler

Page 8: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Novel Self-Aligning, Kinematic Support-System Has Been Tested During Several Cool-Downs And Functions Consistently At High Repeatability and Accuracy

Alignment of cavities and solenoids stay well within alignment specifications

Optical target measurement results• Cavity alignment

» within +/- 0.003” (0.076 mm) horizontally

» within +/- 0.002” (0.05 mm) vertically

Wire Position Monitor measurements• Cavity alignment

» within +/- 0.003” (0.076 mm) horizontally

» within +/- 0.001” (0.03 mm) vertically

G-10 Posts

With Linear Bearings

Guided pin

Roller Capsule

Cavity mount provides stress-free thermal contraction with significant anti-rocking stiffness – essential for quarter wave resonators

Cavity Sliding System

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 8

Page 9: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Heat Treatment Data from Vendor

14 hours

• 1,100 °C Max Temperature

• Cool Down in Inert Atmosphere

FRIB Develops Technical Innovations For Low-Beta Cryomodules

3D Shaped O-RingSeparated Cavity / Cryomodule Isolation Vacuum

Rail Assembly Optimized For Mass ProductionSelf-Aligning Support System

Custom Rail Heat TreatmentFull Stress Relieve To Minimize Distortion During Cool-Down

Reset To Austenitic State (Min. Permeability)

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 9

Page 10: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Local Magnetic Shielding is Designed to Keep Resonator Surfaces Below 15 mG When Transitioning to SC

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 10

Local Shielding Detail Design Is Based On ReA3 Experiences

Page 11: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

FRIB Cavity Tuner Designs Are Finalized Performance Has Been Validated

Stepper Motor

To Cavity Bottom

Tuning Plate

55 K Intercept

Cold Helium Piston Actuator

Support Frame

Tuning Arms

And Cavity

Flange Mount

Tuner TypeQWR

β=0.085HWR

β=0.53

Minimum Tuning Range [kHz] 30 120

Tuning Resolution (2% of Bandwidth) [Hz] 0.8 0.6

Maximum Backlash (5% of Bandwidth) [Hz] 2 1.5

Cavity Tuning Sensitivity (calculated) [kHz/mm] ~ 3.2 ~ 236.2

Maximum Displacement [mm] (*) port-to-port ±7.5 -0.5 (*)

Cavity df/dp (Free Tuner) (calculated) [Hz/torr] ~ -1.4 ~ -3.43

Cavity LFD (Free Tuner) (calculated) [Hz/(MV/m)2] ~ -0.7 ~ -3

Test Status: Operational In ReA3 Cryomodules Test Status: Operation Verified During Integrated Vertical Test

Increased cavity

frequency tunability by

welding “tuning puck” to

tuning plate providing

±30 kHz final tuning

range.

4.5 K Intercept

Cryomodule FlangeTension Cables

Cavity Beam

Port Tuning

Direction

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 11

Page 12: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

QWR Will Utilize ANL Coupler With Cold Window And 90 Degree Bend,HWR Will Utilize SNS-Style Coupler With Single Warm Window

Coupler TypeQWR

β=0.085HWR

β=0.53

Frequency [MHz] 80.5 322

Line Impedance [Ω] (*) will change to 75 Ω 50 50(*)

Cavity RF Bandwidth [Hz] 40 30

Installed RF Power [kW] 2.5 5

Max. Coupler Power Rating [kW] 4 10

Manual Coupling Adjustment ½ To 2 Times Bandwidth

Coupler Interface 1-5/8” EIA 3-1/8” EIA

Total Heat Load To 2 K At Nominal RF Power [W] 0.13 0.6

Total Heat Load To 4.5 K At Nominal RF Power [W] 1.3 2.7

Total Heat Load To 55 K At Nominal RF Power [W] 7.1 6.2

90 Degree Bend

55 K Cold Window

Adjustable Bellows

With 4.5 K Thermal Intercept

Warm Window

At Cryomodule

Feedthrough

Warm Transition

Cavity Flange

With 4.5 K Thermal Intercept

Single Warm Window

Adjustable Bellows For

Coupling Adjustment

Coaxial Line

With 55 K Intercept

RF Conditioning Teststand

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 12

Page 13: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Cryomodule P&ID

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 13

Page 14: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Requirements imposed by test plan (design verification) and operation (operating modes) drive specifications for instrumentation

Instrumentation specified for all major systems• Cryo systems (4K & 2K) – thermometry, pressure transducers, level

gauges, heaters, valves

• Thermal shields – thermometry

• Cavities – thermometry, heaters

• Solenoid – flow controller/indicator, thermometry, heater

• Magnetic shielding – thermometry, Hall probes, flux gates

• Support rails – thermometry

• Vacuum vessel – vacuum gauges & valves

• Beamline – thermometry, heaters, vacuum gauges & valves

P&ID includes all instrumentation and control elements

Captured in formal note: M40103-TD-000497 “ReA6-I Cryomodule Instrumentation List”

Instrumentation and P&ID

, Slide 14M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13

Page 15: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

FRIB Complex Cryomodule Cryogenic Circuit

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 15

2 K Circuit

(Cavities)

4 K Circuit

(Solenoids, Intercepts)

50-70 K Circuit

(Thermal Shield, Intercepts)

Relief ValvesCryogenic Valves

2K Heat Exchanger

Engineering design per ASME B31.3 process piping code and ASME BPVC, section VIII, division 1.

Designed With JLAB Assistance

Page 16: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Half-Wave Resonators Require Careful Attention To Vibration Isolation

Welded Bellow

Flexible Connections

To Resonators

Once cryogenic circuits are welded, structure will be

lifted off the support rails for vibration isolation.

Tension rods support cryogenic circuits from top of cryostat

vacuum vessel and allow longitudinal contraction.

• Cavities are rigidly connected

to stiff rails but only weekly

linked to cryogenic circuit.

• Ball-bearing cartridges allow

transverse motion due to

thermal contraction.M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 16

Page 17: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Cavities2 K Thermosyphon Circuit

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 17

Relief Valves

Redundant Level Sensors

2K Sub-Atmospheric Return

2K Sub-Atmospheric Return

(31-35 mbar)4K Supply

(2.5 – 3.5 atm)

Cavity Supply

Cavity Return

2K Heat Exchanger

2K Additional Volume

With Heater For ControlJT-Valve

Page 18: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Solenoids And Intercepts4 K Thermosyphon Circuits

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 18

4K Return

(1.3-1.5 atm)4K Supply

(2.5 – 3.5 atm)

4K Beamline

Intercept

(both sides)

Thermosyphon

Supply Lines

Thermosyphon

Return Lines

Cryogenic

Control Valve

Relief Valves

Solenoid

Return Lines

Rail Connection

(both sides)

Page 19: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Thermal Shield And Intercepts Use50 K Gaseous Forced Flow Circuit

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 19

Thermal Shield Is Divided In Three Segments

To Allow For Longitudinal Contraction

• Thermal Shield Segments Are Cooled Utilizing Series Flow

• Couplers Are Cooled Utilizing Parallel Flow

(Design Is An Optimization Between Flow Velocity And Pressure Drop)

Material: 1100 Aluminum For Maximum Thermal Conductivity

Shield Supply: 35 - 45 K, 2.0 - 3.5 atm

Shield Return: 35 - 55 K, 2.0 - 3.5 atm

Page 20: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Coupler Interfaces

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 20

Warm Window

Thermal Transition

Elbow

Cold Window

Bellows

Thermal Shield

Page 21: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Cryomodule Vacuum Interfaces

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 21

Gate Valve To Beamline

Diagnostics Box

Cryomodule Beamline

Pumping Access During Storage

Cryomodule Beamline

Pumping Access During Storage

Thermal Intercepts Beam Position Monitor

Cold Cathode Gauge

Ion Pump

Maintenance Valve

Page 22: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Interface to Front End

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 22

Page 23: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Split into 3 vacuum models:• Pre-RFQ = Extraction Region (ER) + CSS + LEBT

• RFQ

• MEBT (from RFQ exit to first cryomodule in LS1)

Front End (FE)

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 23

RFQ

VENUS

Source

ARTEMIS

SourceCSS

LEBT

MEBT

ER

Page 24: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Requirement < 5x10-8 Torr

RFQ is 80.5 MHz copper structure• 5 meters long

• Isolation valves at each end

• Heavy initial conditioning is expected

Pumping through 2 ports per quadrant (8 total)• Pumping requirements are understood

• 8” CF flanges integrated into structure for headers

• 4 – ~700 l/s turbo pumps on headers

• O-rings are used at section joints

• Large, high conductance structure

• Optimization is ongoing

• May require a pump on the RF coupler

Vacuum Layout – RFQ

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 24

Page 25: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Requirement < 1x10-8 Torr

MEBT• 4 SC solenoids

• 2 RT bunchers

• 1 RT dipole» Beam dump

• Fast valve

Pumping• 9 – 150 l/s ion pumps (125 l/s used in calculations)

» Pumps applied in an “opportune” fashion

» Standardized on a larger size ion pump due to the bunching cavities* • *Calculations showed the 75 l/s to be too small

» Number may be reduced in final design

Beginning of the particulate free installation near cryomodules

Vacuum Layout – MEBT

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 25

Page 26: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Interface to Stripper

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 26

Page 27: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Requirement• LS1 < 5.E-9 In the warm regions

Linac Segment 1 Transport Region• 6 diagnostic chambers

» 2 – 47.5 mm

» 4 – 40 mm (included in accelerating systems count)

» All Include 75 l/s ion pumps

Pump and diagnostic chamber added after matching module to protect cryomodule vacuum

Vacuum Layout – LS1 Transport Region

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 27

FV

Page 28: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 28

Vacuum Layout – Charge Stripping Area [1]

Part of FS1 in overall design

“Dog Leg”

Page 29: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Vacuum Layout – Charge Stripping Area [2]

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 29

Vacuum

requirements

are met

• Requirements (*FRIB Driver Linac Vacuum Requirements)

» 1 x 10-5 Torr in stripper system during operation (from F. Marti)

» < 1 x 10-6 Torr near the Li stripper* (presumed at 1st diagnostic box)

» < 1 x 10-8 Torr near the matching cryomodules* (presumed at or before diagnostic box adjacent to upstream and downstream matching cryomodule)

• Turbo pump Li chamber for pump out; ion pump during Li operation

• Isolation of charge stripper for maintenance and replacement – added valves

• No direct line of sight to matching cryomodules (5 degree dog legs at both ends)

• Fast valves protect cryomodules from a vacuum event in the Stripper

Page 30: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Interface To Folding Segments

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 30

Page 31: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Vacuum Layout – FS1

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 31

FV

Requirements» FS1 Beam Bending Section < 5.E-8 After the second

45 deg dipole

» FS1 Matching Section < 1.E-8

Folding Segment 1• RT dipoles, quads, and correctors

• 2 beam dumps» BD1-a – 15 w

» BD1-b – 3 kW

• Beam collimator

• 1 matching module (place for additional)

• Beam diagnostics

• 1 fast valve

• 3 isolation valves

Page 32: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Vacuum Layout – FS2

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 32

Requirement• FS2 < 1.E-8

Folding Segment 2• SC dipoles

• RT quads and correctors

• 1 matching module

• 1 beam dump

• 2 fast valves

• 3 isolation valves

• 300 l/s ion pump in bends and beam dump line

• 75 l/s ion pump in transport areas

FV

Page 33: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Interface To Warm Diagnostics Boxes

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 33

Page 34: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

The diagnostic box stand will be developed in final design to utilize common components among other stands following all requirements• Adjustment capability; +/- 1” vertical and +/- ½” in horizontal and longitudinal

• Adjustability to meet the FRIB Driver Linac Placement Requirements which are defined by properly locating the BPM; 0.2 / 0.2 / 1.0 mm

• Temperature» Tunnel temperature is regulated to minimize

movement due to expansion and contraction

of the stands

• Seismic requirements

Diagnostic Box [1]

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 34

Page 35: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Ultra-high vacuum due to cryomodule and overall accelerator vacuum requirements• Appropriate fabrication processes enforced and shown on

manufacturing drawings

UHV Cleanroom techniques for assembly/installation• Minimize particulates adjacent to cryomodules

• Draft installation plan completed

Pump down and venting handled by PVS • Portable Vacuum System (PVS) or “pump cart”

Box used 90 times in the accelerator• 57 with 3 3/8” CF flanges and 40 mm I.D. (@ cryomodules)

• 33 with 3 3/8” CF flanges and 47.5 mm I.D. (@ beam transport)

• Includes 65 l/s – 75 l/s ion pump (depending upon type)

• Lower value used for calculations

Diagnostics installed as specified by physics group and detailed in FRIB Parameters List / Lattice File• All installations adjacent to cryomodules have:

» BPM

» Halo Ring diagnostic (design TBD)

Diagnostic Box [2]

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 35

Optional

Diagnostic Port

BPM

FV Sensor

Halo Ring

Page 36: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

Diagnostic boxes adjacent to cryomodules will be preassembled, prequalified, and baked (as required) prior to installation• Final blow-out and qualification will be done in a

class 100 clean room

Field installation will be done using class 1000 portable clean room sets• 1 for covering work area

• 1 for a prep, gowning, and parts control area

• Minimum of 2 sets required (3 preferable)

• A mock-up will be done as soon as possible to» Validate diagnostic box installation process

» Determine exact clean room size requirements

Diagnostic Box [3]

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 36

Proposed portable clean rooms and

layout for installation

Page 37: FRIB Cryomodule System Design Main Components Allow Modular Procurement And Assembly M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 6 Vacuum vessel Thermal shield

FRIB cryomodule interfaces and operational modes are defined

FRIB quarter wave cryomodule P&ID and detail design complete

Until 2015 we will build two prototype cryomodules to validate performance

Summary

M. Leitner, March 2014 Workshop on Cryomodule Maintenance - 13, Slide 37