Framework - The Canadian Council for Public-Private …€¦ · PPT file · Web view ·...
-
Upload
doankhuong -
Category
Documents
-
view
212 -
download
0
Transcript of Framework - The Canadian Council for Public-Private …€¦ · PPT file · Web view ·...
Issue/Opportunity
• Disraeli Bridge - Winnipeg, MB• Connects NE Winnipeg with
downtown• 42,000 vehicles per day• Freeway and bridge structures
in need of replacement
Class Exercise
• How does the City of Winnipeg build/replace this infrastructure?
Considerations
• Who designs it?
• Who builds it?
• Who pays the upfront costs to build it?
• Who operates it (e.g. salting/snow removal)?
• Who maintains/repairs it for the next 30…40 years?
Issues to Consider: Design
• If in-house City staff design it…– Resources to do it themselves?
• Engineering skills– Roadway and bridge design– Safe removal of existing structure
• Number of City staff available
• If they engage the private sector to design it…– Cost?– Oversight?
Issues to Consider: Construction
• Can the City build it themselves?– Resources (staff, skill, equipment, etc.)– How long will it take?
• If not, hire a contractor...– Who takes the risk of the budget/schedule going
over?– Will the contractor build what was designed?– How does the City enforce quality control?– What happens if the contractor goes bankrupt?
Issues to Consider: Financing
• Does the City have the money to pay for the construction?
• If not, where do they get it from?– Would the provincial/federal governments lend
money for this? – How are the borrowed funds repaid?– Do banks lend money to build bridges?– How much does it cost to borrow money?
Issues to Consider: Operation
• Can the City operate the bridge themselves?– Do they have adequate staff, equipment, etc.
• If not, can they hire a contractor?– How does the City ensure proper levels of service?– Who takes the risk of the budget going over (e.g.
more snow than expected)?– What happens if the contractor goes bankrupt?
Issues to Consider: Maintenance
• Can the City maintain the bridge themselves?– Do they have adequate staff, equipment, etc.– What happens if maintenance budgets are cut?
• If not, can they hire a contractor?– How does the City ensure the structure is properly
maintained?– Who takes the risk if it isn’t?
PPP Canada
INTRODUCTION TOPUBLIC-PRIVATE PARTNERSHIPS
Overview
• What is a P3?• When are they used?• Disraeli Bridge Case Study• Risk Transfer• Value for Money• P3 Project Team Structure• P3 Organizations and their Roles• Summary
What is a P3?
Background
• Governments struggling to keep up– Aging infrastructure– Growing population– Budget constraints and deficits– Risk of project delays and cost overruns
• Roads, bridges, hospitals, schools, etc. need to be built so governments looking for innovative approaches
What is a P3?
“P3s are a long-term performance-based approach for procuring public infrastructure where the private sector assumes a major share of the responsibility in terms of risk and financing for the delivery and the performance of the infrastructure, from design and structural planning, to long-term maintenance.”
- P3 Canada
What is a P3?
“A cooperative venture between the public and private sectors, built on the expertise of each partner, that best meets clearly defined public needs through the appropriate allocation of resources, risks and rewards.”
- The Canadian Council for Public-Private Partnerships
What is a P3?• Integration of roles (Design, Build, Finance, Operate,
Maintain)
• A long-term duration
• The provision of goods or services to meet a defined output specification (i.e., define what is required rather than how it is to be done)
• A transfer of risk to the private sector anchored with private sector capital at risk– Throughout the project life-cycle
• Entered into by a competitive process
What is a P3?
• Simply an additional way governments can deliver infrastructure
- P3 Canada
Strengths and Limitations of P3 Models
- P3 Canada
What is a P3?Traditional Procurement vs. P3 Procurement
Assets
Input terms (prescriptive)
Components of delivery are separated
Paid for during key construction milestones
Life-cycle risks are retained
Assets and services
Output terms (performance)
Components of delivery are bundled
Paid for once asset is delivered and over the life of the asset – payments linked with operational performance.
Life-cycle risks are transferred
- P3 Canada
Perceived Benefits
• Cost savings• Time savings• Projects begin sooner• Effective risk transfer• Value for money• Improved price and schedule certainty• Infrastructure funds attract investors
Source:Synthesis of Practices for Implementing Public-Private Partnerships in Transportation Related Projects - Transportation Association of Canada
Perceived Benefits
• User pay options (e.g. tolls)• Innovation through integrating phases• Redeployment of government resources• Improved asset maintenance• Improved quality• Lifecycle cost considerations
- Transportation Association of Canada
Perceived Concerns
• Additional costs– Risk premiums, higher financing costs for private
sector, higher procurement and monitoring costs for government
• Longer upfront procurement/negotiation process
• High cost to renegotiate long-term contracts when policy changes occur– Termination is costly and complex
- Transportation Association of Canada
Perceived Concerns
• Foreign control of domestics assets– Issue when foreign companies are involved
• Public may not accept private sector’s role• Risk of private partner bankruptcy
– Risk is low in today’s P3 domain• High level of government expertise required
– Skills in P3 procurement, negotiation, and project management
- Transportation Association of Canada
When are they used?
When are they used?
• P3 benefits do not always outweigh costs– Screening process is required to determine if the P3
method is appropriate• P3 method is suitable for a project when:
– It is feasible to develop output specifications and performance requirements
– Risks can be identified and transferred– Deal size is large enough to offset bidding costs– Project is highly complex– Competitive market exists (multiple bidders)
- Transportation Association of Canada
When are they used?
• TAC identified 16 common screening criteria• Canadian projects employed the P3 model
when it offered:– Value for money– Risk transfer to the private partner– Schedule certainty– Sufficient project size/scope– Sufficient private sector competition– Benefits for taxpayers
- Transportation Association of Canada
When are they used?– Lower total-life costs (capital, construction, operations and
maintenance, rehabilitation)– Private sector innovation– Measurable outputs– Public ownership of the infrastructure– Operation and maintenance components– No outstanding issue that would prevent project– No legislative or legal impediments– Clearly defined private partner’s responsibilities– The maintenance of public sector accountability– A transparent process
- Transportation Association of Canada
What sectors are employing P3s?• Total of 198 Canadian P3s
– Hospitals and healthcare (75)– Transportation (42)– Environmental (22)– Justice/Corrections (19)– Recreation and culture (17)– Education (10)– Government services (5)– Energy (4)– Real estate (3)– Defense (1)
http://projects.pppcouncil.ca/ccppp/src/public/search-project?pageid=3d067bedfe2f4677470dd6ccf64d05ed The Canadian Council for Public-Private Partnerships - July 25, 2013
Example: Highway 407Greater Toronto Area, Ontario
• Purpose: Reduce 401 congestion through City• World’s first all-electronic open-access toll
highway• 407 ETR (private sector entity)
– Construction and finance– Operation and maintenance– All other services (police, customer service, etc.)
• Built and operated based on toll revenue only (no tax dollars spent)
Example: Abbotsford HospitalAbbotsford, B.C.
• Fraser Health/BC Cancer Agency– 650,000 ft2 hospital– 300 bed acute care with
ambulatory facility– Regional cancer centre
• ABN Amro, PCL, Johnson• Design, build, finance, operate, maintain
• Built on time with $0 in change orders
Example: Water Treatment FacilityMoncton, N.B.
• Treatment facility built using P3 model– Serves approximately 125,000 residents– 102,000 m3/day with expansion up to 136,400– Uses local surface water reservoir
• State of the art clarification process• High water quality
– Subsequent location of Molson brewery in Moncton
P3 Success Factors
• Strong political and public sector leadership and support
• Clear legal and administrative framework• Active public involvement• Skilled government personnel• Well defined outcomes • Oversight of public interest, appeal processes• Rigorous analysis - objective technical and financial
analysis/value for money
P3 Success Factors
• Clear risk transfer • Whole-of-life costing• Performance-based contract, including non
performance penalties• Efficient and competitive procurement • Stable and predictable processes• Transparency, accountability and monitoring
systems (e.g. use of an independent fairness advisor)
What can go wrong in a P3?
• Contracts can fall through– Lack of public support– Lack of political support– Policy/government changes
• Delays can occur in starting work– Lengthy proposal/negotiation process– Inexperience in P3 contracts– No one will bid if contract/pricing isn’t done well
Saint John, NB - Peel Plaza
• New police headquarters to also integrate four other functions
• Started 2007 – Completed 2013• Delays caused by three issues:
– Not flexible on design– Lack of public support– City’s lack of P3 expertise
Costa Rica: San José - San Ramón Concession Road
• Termination of $524 million contract with OAS– Repair and expansion of road
• Lack of support from all sides– Business– Technical– Political
• Fierce public opposition to tolls– Social unrest was leading to violence
Disraeli Bridge Case Study
City of Winnipeg: Disraeli Bridge
• Procurement options available:– Design-bid-build (Traditional)– Design-build (Traditional)– Design-build-operate-maintain (P3)– Design-build-finance-operate-maintain (P3)
• Which method is the most suitable?
Source:Disraeli Bridges Project – Value for Money Report- Deloitte & Touche LLP
Option #1: Design-Bid-Build
• Design and Construction– City develops a close-to-complete design of the
asset and tenders the work to the lowest bidder• Financing
– City finances through progress payments during the construction period
• Operation & Maintenance– City maintains the asset following completion
- Deloitte & Touche LLP
Option #2: Design-Build
• Design and Construction– A single contractor develops the design and is
responsible for construction• Financing
– City finances through progress payments during the construction period
• Operation & Maintenance– City maintains the asset following completion
- Deloitte & Touche LLP
Option #3: Design-Build-Maintain
• Design and Construction– A single contractor is responsible for the design
and construction• Financing
– City finances through progress payments during the construction period
• Operation & Maintenance– Following completion, the contractor maintains
the asset based on a maintenance fee- Deloitte & Touche LLP
Option #4: Design-Build-Finance-Maintain
• Design and Construction– A single private sector entity is responsible for design and
construction• Financing
– Private sector entity finances the construction through debt/equity
• Operation & Maintenance– Following completion, the private sector entity maintains the
asset• Payment Mechanism
– Entity is paid an annual service fee- Deloitte & Touche LLP
Process to Select Contract Method
• Qualitative Analysis– High level analysis to determine if P3 method
should be considered (and VfM undertaken)• Value for Money Analysis
– Detailed analysis to determine if the P3 method will be cheaper than traditional procurement
• Market Soundings– Determine if the private sector is interested
- Deloitte & Touche LLP
Qualitative AnalysisCriteria DBB DB DBM DBFOM
1 Retained risks are reduced
2 Key retained risks can be mitigated
3 Financing costs to City can be minimized
4 City maintains operational flexibility
5 Industry best practice for risk mitigation
6 Industry best practice for life-cycle risk mitigation
7 Value for money to the City
8 Consistent with City’s previous projects
- Deloitte & Touche LLP
Value for Money
A VfM analysis compares these two
• Estimated costs to the public sector of delivering the project as a P3
• Estimated costs to the public sector of delivering the project based on the public sector’s traditional method of procuring public infrastructure.
Costs of Traditional Procurement
Costs of P3 Procurement
Consider the total cost of ownership over the life of the asset adjusted to consider total cost of risk and expressed in present value terms
Risk Transfer
Risk Transfer
• What does it mean to transfer risk?
• What does the cost of risk mean?
• What does it mean to assume risk in a project?
• What is a risk premium?
Risk Transfer: Car Insurance Analogy
• Risk Transfer:– A person who drives a car is at risk of causing a collision– This person enters into a contract with an insurance
company to transfer that risk from the person to the insurance company
• Cost of Risk:– The person pays the insurance company a yearly fee for
this risk transfer, thus assigning a cost to the risk– This cost is calculated based on the type of risk and the
probability of a collision (driver history)
Risk Transfer: Car Insurance Analogy
• Assuming a risk:– The contract will stipulate which risks the
insurance company will assume and which risks the person is still responsible for (e.g. PLPD versus comprehensive)
• Risk Premiums:– Built into the yearly fee is a premium the
insurance company charges to make it worth their while to assume the risk
Disraeli Bridge Project Risk
Design PhaseRoles and Responsibilities
City of Winnipeg Private Sector• Preliminary Design Report• Design Specifications (Technical
Requirements)• Review and Comment on Detailed
Design (ensure compliance with technical requirements)
• Detailed and final design in compliance with technical requirements
• Consider roles and responsibilities of the public and private sector:
- Deloitte & Touche LLP
Risk: Roles and ResponsibilitiesConstruction Phase
Roles and ResponsibilitiesCity of Winnipeg Private Sector
• Provide access to site and rights of way • Construction of project in compliance with technical requirements
FinancingRoles and Responsibilities
City of Winnipeg Private Sector• The City will pay a commissioning
payment at substantial completion• All financing for the design and
construction of the project
- Deloitte & Touche LLP
Risk: Roles and ResponsibilitiesOperation and Maintenance Phase
Roles and ResponsibilitiesCity of Winnipeg Private Sector
• Monitoring and enforcement of payment adjustment regime
• E.g. payments withheld if performance not met
• Regulatory signs• Roadway lighting and sign control
maintenance
• Inspection and reporting• Emergency maintenance• Operational maintenance of
pedestrian level lighting, landscaping, drainage, pavement markings, guide signs, cleanup, snow clearing and ice control
• Pavement surface maintenance• Bridge structure maintenance
(structural and operational repairs)• Snow clearing and ice control• Landscape maintenance• Drainage maintenance
- Deloitte & Touche LLP
Class Exercise: Risk Allocation
Based on these roles and responsibilities, who assumes what risk?
In other words, who is financially responsible for any issues related to the item?
Risk AllocationDesign and Construction Phase The City Private Sector
Design deviation from concept approval
Design error
Patent infringement
Weather
Water/soil/air pollution – known pre-existing
Water/soil/air pollution – unknown pre-existing
Water/soil/air pollution – arising from work
Land acquisition
Permits and regulatory authorizations
- Deloitte & Touche LLP
Risk AllocationDesign and Construction Phase The City Private Sector
Delays by agencies, regulators, etc. other than the City
Delays by the City
Construction cost overruns
Sub-contractor bankruptcy
Changes in design/construction standards during construction period
Labour disputes
Defective materials
Quality assurance and quality control
- Deloitte & Touche LLP
Risk AllocationOperation and Maintenance Phase The City Private Sector
Weather (e.g. heavier snowfall than expected)
Labour disputes
Actual maintenance costs higher than anticipated (e.g. due to increased traffic)
Increased usage of authorized overweight vehicles
Increased legal weight limits on bridge
Traffic accidents due to the performance of the contractor
Meeting hand-back standards (i.e. bridge must be in a certain condition at end of contract)
- Deloitte & Touche LLP
Risk AllocationOperation and Maintenance Phase The City Private Sector
Meeting performance standards
Labour and material availability
Change in law (that may affect operation/maintenance)
Force majeure (e.g. act of God)
Financing The City Private Sector
Changes in inflation - construction cost portion of payment
Changes in inflation - maintenance portion of payment
- Deloitte & Touche LLP
Disraeli Bridge Project Risk
- Deloitte & Touche LLP
Value for Money
Value for Money Process
- P3 Canada
Base Costs
•Direct costs of labour, materials, equipment rental and building systems and components that are required to construct the asset•Costs of design and engineering consultants, approvals and permitting
Construction Costs
•Items related to the ongoing operations and maintenance of the asset. Includes costs of providing services such as cleaning, waste management, building management and general maintenance
Operating and Maintenance Costs
•Costs of periodic , planned, major capital repair and/or replacement, typically at 5-15 year intervals. This could include replacement of boilers or elevator systems (accommodation facility), or road re-surfacing
Lifecycle Costs
- P3 Canada
Risk Adjustment
Most jurisdictions have developed standard risk matrices for public infrastructure projects (50-150 common risks)
Risk workshops are typically used to identify which risks apply to a given project
Risk workshops or research on historic projects are used to estimate the likelihood that risks will occur and their impacts under different procurement options
Transferred and Retained Risks are modeled using Monte Carlo simulation
Typically the total amount of estimated risk is lower under a P3, reflecting a better allocation of risk between public and private sector
- P3 Canada
Transaction Costs
Procurement Costs are costs borne by the public sector authority to implement the procurement and manage the project
These costs tend to be different under the traditional and PPP because of differences in the procurement process and due to differing requirements on public sector authority level of effort during the construction and operating periods
Transaction costs for the public sector authority tend to be higher under the P3 because there is a larger requirement for external legal, technical, financial and transactional advisors
The public sector authority must take on a larger role, and higher costs, during construction and operations in a Traditional Procurement in the absence of a Project Co.
- P3 Canada
Disraeli Bridge Value for Money
DBFOM is Chosen – What Next?• Market soundings
– See if anyone is interested• Request for Qualifications
– Make sure those interested are capable• Request for Proposals
– Qualified bidders prepare detailed proposals– Interim/final submissions received and evaluated against
predetermined criteria– Fairness advisor oversees process
• Closing– Agreements, financing in place, contract signing
• Project Starts!
P3 Project Team Structure
What does a P3 project team look like?
- P3 Canada
- Deloitte & Touche LLP
Disraeli Bridge Results
• Infrastructure built on-time (32 months):– Two new bridge structures built over the Red River
and a CP Rail mainline– 2km of four lane freeway– Dedicated bridge for peds and cyclists– 30-year maintenance term
• Innovation– Kept traffic moving during construction– Linked to existing Active Transportation network
P3 Organizations and their Roles
PPP Canada
What is PPP Canada?
• A Federal Crown Corporation• Report to Parliament through the Minister of Finance• Led by an accomplished private sector Board of Directors
Mandate
• To improve the delivery of public infrastructure by achieving better value, timeliness and accountability to taxpayers, through P3s
• To deliver more P3s by leveraging incentives, demonstrating success, and providing expertise
• To deliver better P3s by promoting P3 best-practices and capacity-building• Facilitate the movement toward DBFOM as the optimal method
Advancing Federal P3s
Federal Screen
•Require all infrastructure projects with an asset lifespan of 20 years, and having capital costs of $100 million to be subject to a P3 screen
• Work with Federal partners to create clarity and consistency in decision-making and P3 procurement practices
Strategic Partnerships
• P3 Screening Tool• Value for Money Methodology• Procurement Framework• Deliver Advisory Services
Federal Tools
• To stimulate the adoption of P3 procurement by Provinces, Territories, Municipalities and First Nations
• Support useful public infrastructure in 15 categories• Projects that build the P3 market
$1.2 Billion Fund
Canadian Council for Public-Private Partnerships
• Member based national non-profit, non-partisan organization comprised of public and private sector members
• Promotes innovative approaches to infrastructure development and service delivery through:– Collaborative partnerships between public sector
agencies/departments and industry– Educating stakeholders and the community on the economic and
social benefits of P3s– Advocating for evidence-based public policy in support of P3s– Facilitating the adoption of international best practices– Promoting Canada’s P3 model and expertise globally
Provincial P3 Agencies
• Public sector specialized P3 agencies:– Partnerships New Brunswick– Partnerships B.C.– Alberta Transportation: Major Capital Projects
Branch– Infrastructure Ontario– Infrastructure Quebec
- Transportation Association of Canada
Summary
Summary
• What is a P3• Why/when P3s are used• What can go wrong in a P3• What a P3 project team looks like• Risk transfer/Cost of Risk• The Value for Money calculation
Curriculum Overview
Introduction to P3s
Engineering Business Administration
Public Administration and
Political Science
P3 Stream: Engineering
• Proposals• Agreements• Engineer’s role in a P3
– Public sector P3 governance– Private sector engineers
• Performance based project management• Public consultation and communication as an
Engineer
P3 Stream: Business Administration
• Screening a project for P3 viability• P3 business cases• Risk valuation and transfer• Proposals and agreements• Role of Business Admin.
– Public sector governance– Private sector equity partners
• P3 business and payment models• Communication with the public in a P3
P3 Stream: Public Admin/Poli Sci
• The role of government in a P3• Procurement strategies• Agreements• Business models• Payment models• Public consultation and communication as a
public servant
References/Links• PPP Canada
– http://www.p3canada.ca/home.php
• The Canadian Council for Public Private Partnerships– http://www.pppcouncil.ca/
• Synthesis of Practices for Implementing Public-Private Partnerships in Transportation Related Projects - Transportation Association of Canada– http://www.tac-atc.ca/english/bookstore/
• Disraeli Bridges Project Value for Money Report – Deloitte and Touche LLP– http://
www.winnipeg.ca/publicworks/majorprojects/disraelibridges/Disraeli-Bridges-Project-VFM-Report-Final.pdf
• Partnerships New Brunswick– http://www.gnb.ca/0113/PartnershipsNB/index-e.asp
• Partnerships BC– http://www.partnershipsbc.ca/index.php