Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013...

53

Transcript of Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013...

Page 1: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing
Page 2: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing
Page 3: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing
Page 4: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing
Page 5: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing
Page 6: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

NR Foxton Level Crossing Closure GRIP 2 Feasibility Study Report

318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing Elimination GRIP 2 Report Rev C.docx

77

Appendix D. Signalling Sketches

Page 7: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

FOXTON INTERLOCKING

FOXTON LC ABOLITION

SIGNALLING SKETCH

0.1

1

Sign off for completed activities.Complete tester details in your own check marking colour.

2

3

4

5

TESTER NAME SIGNATURE DATE

Prep. Inspection

Prep. W.C. and Cont

Prep. S. & F. / C.F.T.

Cable core Loc. End

Cable core Equ. End

Changover Comp

ACTIVITY COMPLETE DATE

MMD-318484-C-DR-SG-01

NOT TO SCALE

CAMBRIDGE CONTROL AREA

PROPOSED HIGHWAY

(MMD-318484-C-DR-HW-07)

EXTRACT TAKEN FROM DRAWING NO. A44 FOX/1 VERSION FR2

CAD - A3

Produced

Checked

Issued

CAD GENERATED : ALTERATIONS TO BE MADE ON DESIGN FILE ONLY

Version CheckProd.

Current

Version

Last Full

Correlation

Date

Version

Source Record Updated

Drawing No

Network Records Group

PROPOSED FOOTBRIDGE AND RAMP

(MMD-318484-C-DR-BR-103)

Page 8: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

NR Foxton Level Crossing Closure GRIP 2 Feasibility Study Report

318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing Elimination GRIP 2 Report Rev C.docx

78

Appendix E. Cost Estimates

Page 9: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Oracle Project No.:

Project Description:

Estimate Stage:

Rev. Date Consultant Prepared by Checked

Rev00 19-Mar-13 F+AJames

YarnallRobert Walker

Rev 1 8-May-13 F+A Steve Jackson

Consultant's Name & Address

Level of Confidence - +/- 30%

Issue and Revision Record:

Standard Template for Stage 1-2 Estimates prepared by Consultants

135112

GRIP 2 (+/-30%)

Description

Draft for review

Network Rail Validation

Foxton Level Crossing - Option 1 (Overbridge)

Consultant to insert logo here

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates Rev 3, Date: 28 October 2011

Page 10: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Estimate Document Contents

1 User Notes (Consultant)

2 Assumptions

3 Estimating Risk Register

4 Estimate Summary Report

5 Indirect Costs (Auto generated)

6 Expenditure Profile (Summary by GRIP) (Auto generated)

7 10. Signalling, measured works

8 20. Electrification and Power, measured works

9 30. Track, measured works

10 40. Telecommunications, measured works

11 50. Operational Property, measured works

12 60. Structures, measured works

13

14 80. Utilities, measured works

15 Other Contractors Indirect Costs

16 Network Rail Direct Costs

70. General Civils, measured works

Rev 1, Date: 7 May 2010

Page 11: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

User Notes

1

2

3

4

5

6

7

8

i All documents used in the preparation of the estimate shall be listed within the estimate

ii All assumptions and exclusions applicable to the estimate must be described

iii Exclusions that result from a lack of knowledge will not be considered acceptable; exclusions of

this type will only be accepted with the agreement of the Estimating Manager

iv The Consultant shall ensure that estimate has been subject to an internal review by an

experienced staff member who must satisfy himself that it is free from errors, that the scope of

work has been accurately measured and that the level of pricing is appropriate

v The Consultant should submit a copy of his quantities 'take-off' to Network Rail with all

estimates submitted for approval

vi The consultant shall identify the source of rates used in pricing the estimate; when requested,

the consultant will provide copies of built-up rates and/or materials or sub-contract prices

obtained for the preparation of the estimate

vii The consultant must provide details of the basis for establishing the level of any provisional

sums and/or lump sum allowances where requested

vii The consultant shall include details of any particular risks seen by the estimator during

preparation of the estimate and give his view of their probability and potential impact - these

risks may relate to design, pricing, implementation etc and the risks are likely to be considered

as part of the projects quantified cost risk analysis process

9

10

11

The Consultant should note that the cost of certain materials and services provided as "free issue" to

the siteworks Contractor will generally be included in the rates at GRIP 1-2

The Consultant must comply with the following:

The Consultant should note that Network Rail's Estimating Manager (Enhancements) will be the

"approver" for all estimates and it should be anticipated that he will be asked to review/ revise certain

elements within the estimate (quantities and/or rates) as part of Network Rail's approval process

The Consultant shall check the accuracy of all formulas and links contained within this spreadsheet

and he shall ensure that these are maintained where any amendments are made to the spreadsheet

The Consultant shall indicate in the tables herein, the source of his unit rates and demonstrate how

his base rate has been uplifted for complexity (staging and constraints on access, working space,

use of plant etc) and possessions (out of normal hours working, short shifts etc); an adjustment may

be made for overheads & profit where this is not included within the base cost. The type and duration

of possessions shall be shown where work is to be carried out beyond normal hours.

The Consultant is required to prepare the estimate in accordance with GRIP Manual PM04 Cost

Estimating with particular reference to the requirements relating to the Type of Rates / Costs and the

Quantity Take Off Detail shown within Appendix A to this document

The Consultant should particularly note that all indirect costs will be based on percentage

calculations generated by the "Indirects" worksheet

It is recognised that certain costs that shall be included within the Project AFC are to be advised by

Network Rail

The Consultant shall prepare estimates in accordance with Network Rail's "Remit for Estimates

produced by Consultants" (some provisions of which are repeated hereunder)

The percentages used in the Indirects worksheet to calculate the Contractors and Network Rails

indirect costs may be adjusted by the Consultant in line with the range shown in PM04

The Consultant shall note that escalation will only be included within the Project Anticipated Final

Cost (Project AFC) where the Project AFC is in excess of £50m and where the site works will be over

2 years duration; escalation shall be calculated using RPI indices from the estimate 'base date' to the

mid-point of the construction phase

Where the project AFC is below £50m or the construction phase will be shorter than two years,

escalation shall not be included but it shall be calculated as described herein and shown in the

Estimate Summary Report under "Other Costs to the Customer"

Rev 1, Date: 7 May 2010

Page 12: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Estimate Stage: GRIP 2 (+/-30%)

Oracle Project No.: 135112

Project Description: Foxton Level Crossing - Option 1 (Overbridge)

Assumptions

G1

G2

G3

G4

G5

G6

G7

AssumptionsA1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12

A13

A14

A15

A16

A17

A18

A19

No demolitions necessary, we have included for re-locating a number of portable buildings

Palisade fence required to fence off level crossing. Post and rail fence allowed at the bottom of

the 'batters' and each side of the new highway works

Existing roads and footpaths require re-surfacing at tie ins with new highway works

Kerbs HB2 or similar

One carrier drain to new road construction (150mm diameter)

No allowance made for Pedestrian Access in the Station area (footbridge or subways etc)

10% of Construction Costs allowed for Structure Design and 10% 5% for General Civils due to

'simple' scheme with standard bridge design

Level Crossing to be de-commissioned and removed

Gullies at 25m centres both sides of the carriageway

Manholes at 50m centres

Safety barrier extends from road junction to end of embankment on opposite side of bridge

Retaining wall within embankment area has strip footings and a 2.5m retained height

Seeding required to embankment sides (circa 150mm of site won top soil)

Minor permanent way (tamp) and ole works required only (brackets and minor wiring work pre-

dominantly). No Signalling works required.

No ground improvement works required under the new embankment (soil columns or pre-cast

concrete piles etc). One layer of geotextile only required under new embankment allowed for in

the estimate. No surcharging allowed for

General / Drawings & Documents / Exclusions

General

The estimate base date is 1Q13

Nothing has been included in the estimate for inflation past 1Q13 as the programme is not

known. Where it has been necessary to inflate any historical rates when compiling the estimate

NR inflation indices number 34 has been used

See summary for further assumptions/exclusions

Where there is in-sufficient information for the works to be priced confidently within the +/- %

range we have included allowances within the estimate. These have been clearly identified and

will require review once more information becomes available

Possession working has been included for in the rates where thought required (generally

assumed that some long weekend possessions will be available for the main bridge deck works)

TOC / FOC compensation costs included within the estimate as 25% x 19% = 4.75% as it is

thought that majority of the works will be undertaken either 'off track' in a civils environment,

fenced green zone or where required non disruptive midweek night possessions

An uplift factor of 30% has been applied for cost and scope uncertainty which is consistent of the

requirements for a GRIP 2 estimate

Street lighting columns at 15m centres, staggered (therefore one light per 15m of highway)

Depth of road construction; 150 sub base, 120 base course, 60 binder, 40 surfacing

Car Parking along Cambridge Road Tarmacadam on Sub Base.

Depth of footpath construction; 150 sub base, 60 HRA binder, 40 surface course

Rev 1, Date: 7 May 2010

Page 13: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

D1

D2

E1

E2

E3

E4

E5

E6

E7

E8

E9

E10

E11

E12

MMD-318484-C-DR-HW-01 rev p1

MMD-318484-C-DR-BR-01 rev p1

The following documents have been used in the preparation of this estimate:

Exclusions

Service diversions unless specifically stated otherwise

VAT

Land take, temporary or permanent

Excludes any allowance for Optimism Bias

Drawings & Documents

Christmas or Bank Holiday working

Costs associated with licences and all associated costs and fees

Costs associated with changes in legislation and any form of applicable standards

Costs associated with changes in legislation, regulation and interpretation covering

3rd party compensation costs

Planning and approval charges

Costs associated with Statutory Fees (e.g. HMRI, Local Authority, etc.) unless confirmed

Costs associated with taxes and levies

Rev 1, Date: 7 May 2010

Page 14: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Estimate Stage: GRIP 2 (+/-30%)

Oracle Project No.: 135112

Project Description: Foxton Level Crossing - Option 1 (Overbridge)

Estimating Risk Register

Ref Risk Type Description Probability Potential Cost Impact

Ground improvement works required

Scope confidence Price confidence Risk confidence

Remarks

Notes:

Asset

Risk Confidence: Good = low risk scheme / works; Poor = high risk scheme /works

Price confidence: Good = we have good cost knowledge; Poor = poor cost knowledge and/or price certainty

Scope Confidence: High = good confidence scope will not change significantly; Medium = Limited scope growth predicted; Low =

scope may grow significantly#

The estimator is required to identify any risks to the project and/or estimate identified in preparing the estimate; this is to

inform the QCRA process only and any potential cost impacts will not impact on the estimate total. The estimator should

indicate his assessment of the level of cost impact (by percentage/ H/M/L assessment / cost value or range), it is

recognised that this will be a subjective assessment only

CONFIDENCE LEVEL MATRIX

Utilities

General Civils

Structures

OP Property

Telecoms

Track

E&P

Signalling

Stage 3 4 Estimate: Standard Template (Network Rail) Issue 2, Date : 6 April 2010

Page 15: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

1302MA0159 Revision Rev 1 Estimate Stage GRIP 2 (+/-30%)

08-May-13 1Q2013

TBC TBC

WBS Estimate Breakdown Value Escalation (Y/N)

%age of

Point

Estimate

Remarks

Contractor's direct costs -

10 Signalling 50,000 Y

20 Electrification & Plant 67,250 Y

30 Track 12,685 Y

40 Telecoms - Y

50 Operational Property - Y

60 Structures 1,973,700 Y

70 General Civils 4,504,629 Y

80 Utilities - Y Excluded

Contractor's Base Construction Cost inc OH&P: Sub-Total A 6,608,264

Network Rail's "direct costs"

tbc NDS - Materials Y Generally within the rates (direct costs) at Stages 0 - 2

tbc NDS - Fleet Y Generally within the rates (direct costs) at Stages 0 - 2

tbc - Engineering trains Y Generally within the rates (direct costs) at Stages 0 - 2

tbc - Tampers Y Generally within the rates (direct costs) at Stages 0 - 2

tbc NDS - Possession / Isolation Management 132,165

Sub - Total B 132,165

6,740,429 0.00%

Contractor's indirect costs

tbc 1,339,874 Y

tbc 674,276 Y

tbc 17,130 Y

tbc Y Generally within the rates (direct costs) at Stages 0 - 2

tbc Y Generally within the rates (direct costs) at Stages 0 - 2

tbc - Y

Sub - Total D 2,031,281

Total Construction Cost E (C+D) 8,771,710

Network Rail's indirect & other costs

tbc Network Rail Project Management, (COWD) N To be advised by NR; Apportionment of GRIP 1 cost

tbc Network Rail Project Management, (forecasted remaining costs) 991,240 Y Based on typical %

tbc 378,350 Y Calculated as 19% x 25% of construction costs

tbc DCO Charges 0% Y Excluded

tbc Land / Property Costs & compensation 0.00% Y Excluded

tbc Escalation (see Note 1) % - NA Excluded as mid-point of the programme not known

tbc Other ( State )

Sub - Total F 1,369,590

Point Estimate - Sub - Total G (E+F) 10,141,300

Uplift for Risk and Contingency

tbc To Mean (see Note 3) £ See Note 3

Project Budget (Point Estimate + Uplift to Mean) 10,141,300 for Project Manager's reference

tbc QRA Value - at P50 (see Note 3) £

tbc QRA Value - at P80 - incremental on P50 value (see Note 3) £

tbc Adjustment for residual factors (see Note 2) % 30% 3,042,390

Project Anticipated Final Cost (AFC) 13,183,690 Authorised AFC

Other Costs to the Customer

tbc Allowance for Escalation (see Note 1)See Note 1

tbc Allowance for Network Rail Fee Fund -

tbc Allowance for Industry Risk Fund -

tbc Allowance for Insurance Top-up

01/05/2002

Cost to Customer 13,183,690

Name :- Steve Jackson

Company :- Network Rail

Position :- Estimator - Anglia Route 08/05/2013 Estimator

Signed :-

Date :- Estimating Manager

Notes:-

1. Escalation will only be included within the Project Anticipated Final Cost (Project AFC) where the Project AFC is in excess of £50m and where the site works will be over 2 years duration; escalation shall be calculated using RPI indices from the

estimate 'base date' to the mid-point of the construction phase

Where the project AFC is below £50m or the construction phase will be shorter than two years, escalation shall not be included but it shall be calculated as described herein and shown in the Estimate Summary Report under "Other Costs to the 2. An 'Adjustment for residual factors' has been applied in accordance with the Guidance Notes on Estimating and Supplementary Note (dated 18th March 2010).

3. The project team or Risk & Value Manager should provide the values for uplifts to Mean, P50 and P80. The uplifts to Mean and P50 should be entered in the spaces provided; the incremental value to P80 (beyond P50) should be shown in the box

provided (i.e. P80 value - P50 value)

F & A

19/03/2013

provided by Sponsor

APPROVAL & ENDORSEMENT

Estimate Produced by :- Estimate Approved by (Network Rail) :- Estimate Endorsed by (Network Rail) :-

J Yarnall - R Walker

Sponsor to advise if P50 or P80 value shall apply See Note 3

Sponsor to advise if P50 or P80 value shall apply See Note 3

Uplift on Point Estimate Value (excluding the Cost of Work Done) See Note 2

provided by Sponsor

provided by Sponsor

Design

Testing & Commissioning

Training

Spares

Other

Compensation charges (TOC & FOC), (costs from NDS)

Project No. 135112

Project Title / Location Foxton Level Crossing - Option 1 (Overbridge)

Total Base Construction Cost inc OH&P: Sub-Total C (A+B)

Preliminaries

ESTIMATE SUMMARY REPORT

Estimate No.

Estimate Date Price 'Base date'

Anticipated Start Date Anticipated Finish Date

Rev 1, Date: 7 May 2010

Page 16: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Estimate Stage:

Oracle Project No.:

Project Name:

Calculation of Contractors and Network Rail's Indirect Costs

Asset Total Direct

Costs

% Preliminaries % Design % Test &

Commission

% Network Rail

Management

% Sponsor

Signalling 50,000 35% 17,500 10% 5,000 15% 7,500 12% 6,000 3% 1,500

Electrification & Plant 67,250 35% 23,537 30% 20,175 13% 8,742 12% 8,070 3% 2,017

Track 12,685 25% 3,171 10% 1,269 7% 888 12% 1,522 3% 381

Telecoms 0 25% 0 10% 0 10% 0 12% 0 3% 0

Operational Property 0 25% 0 10% 0 0% 0 12% 0 3% 0

Structures 1,973,700 20% 394,740 10% 197,370 0% 0 12% 236,844 3% 59,211

General Civils 4,504,629 20% 900,926 10% 450,463 0% 0 12% 540,555 3% 135,139

Utilities 0 25% 0 10% 0 0% 0 12% 0 3% 0

1,339,874 674,276 17,130 792,992 198,248

Total for TOC / FOC calculation (19% of Total Construction Cost maximum)

6,608,264 1,339,874 17,130

TOTAL 7,965,269

GRIP 2 (+/-30%)

135,112

Foxton Level Crossing - Option 1 (Overbridge)

Rev 1, Date: 7 May 2010

Page 17: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL 50,000.00£

Ref Description Quantity Unit Rate Cost

10 Signalling

10.1 Recoveries

10.1.1 De-commission and recover the existing Level Crossing - Allowance 1 item £ 50,000.00 £ 50,000.00

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 50,000.00

135112

Rev 1, Date: 7 May 2010

Page 18: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Ref Description Quantity Unit Rate Cost

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ -

Rev 1, Date: 7 May 2010

Page 19: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL 67,249.53£

Ref Description Quantity Unit Rate Cost

20 Electrification and Plant

20.1 Recoveries

20.1.1 OHL Wiring 80 m £ 22.06 £ 1,764.92

£ -

20.2 New OLE works £ -

20.2.1 Single Track OLE bracket fixed to bridge structure 4 nr £ 2,206.15 £ 8,824.59

20.2.2 Wiring (Contact, Catenary, droppers and return conductor) 80 m £ 66.18 £ 5,294.75

20.2.3 Connections to existing 4 nr £ 330.92 £ 1,323.69

£ -

20.3 Level Crossing £ -

20.3.1 Re-grading of OLE locally to removed level crossing 200 m £ 44.12 £ 8,824.59

£ - £ -

DNO Supply 1 nr £ 15,000.00 £ 15,000.00

DNO Cabinet 1 nr £ 12,000.00 £ 12,000.00

Turning Chambers 39 nr £ 340.00 £ 13,260.00

Distribution Panel 1 nr £ 957.00 £ 957.00

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 67,249.53

135112

Rev 1, Date: 7 May 2010

Page 20: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL 12,685.35£

Ref Description Quantity Unit Rate Cost

30 Track

30.1 Work to existing track

30.1.1 Design tamp upon removal of existing level crossing 1 shift £ 12,685.35 £ 12,685.35

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 12,685.35

135112

Rev 1, Date: 7 May 2010

Page 21: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL -£

Ref Description Quantity Unit Rate Cost

40 Telecoms

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 22: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL -£

Ref Description Quantity Unit Rate Cost

50 Operational Property

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 23: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL 1,973,700.00£

Ref Description Quantity Unit Rate Cost

60 Structures

60.1 Over Bridge

60.1.1 New Overbridge - Pre-cast Concrete Beam Construction 459.00 m2 £ 4,300.00 £ 1,973,700.00

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 1,973,700.00

135112

Rev 1, Date: 7 May 2010

Page 24: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL 4,504,628.97£

Ref Description Quantity Unit Rate Cost

70 General Civils

70.1 Miscellaneous

70.1.1 Site Clearance 16,212.00 m2 £ 5.00 £ 81,060.00

70.1.2 Excavate topsoil and move to on-site stockpile; 300 thick 5,440.00 m3 £ 13.20 £ 71,808.00

70.1.3 Geotextile 16,212.00 m2 £ 8.75 £ 141,855.00

70.1.4 Fill to embankment with imported fill 74,287.00 m3 £ 35.00 £ 2,600,045.00

70.1.5 Seeding to embankments inc circa 150mm of site won topsoil 37,422.00 m2 £ 4.95 £ 185,238.90

70.1.6 Kerbs 2,162.00 m £ 20.00 £ 43,240.00

70.1.7 Carrier drain - 150mm 580.00 m £ 60.00 £ 34,800.00

70.1.8 Connection to existing drainage system - Allowance 1.00 sum £ 5,000.00 £ 5,000.00

70.1.9 Gullies inc allowance for pipe to connect into carrier drain (3.7m per gulley) 48.00 nr £ 622.00 £ 29,856.00

70.1.10 Manholes 12.00 nr £ 1,500.00 £ 18,000.00

70.1.11 Safety barrier 1,150.00 m £ 120.00 £ 138,000.00

70.1.12 Lighting columns 39.00 nr £ 2,426.76 £ 94,643.71

70.1.13 Transition parapet 60.00 m £ 250.00 £ 15,000.00

70.1.14 Fencing off of old level crossing 70.00 m £ 120.00 £ 8,400.00

70.1.15 Move portable buildings; 2 nr - Allowance 1.00 sum £ 7,500.00 £ 7,500.00

70.1.16 Retaining wall near embankment (assumed retained height 2.5m) 70.00 m £ 1,875.00 £ 131,250.00

70.2 New road in embankment area

70.2.1 Sub base in new road embankment area; 150 thick 5,479.00 m2 £ 6.75 £ 36,983.25

70.2.2 Base course in new road embankment area; 120 thick 5,479.00 m2 £ 23.29 £ 127,621.95

Tack Coat 5,479.00 m2 £ 0.75 £ 4,109.25

70.2.3 Binder in new road embankment area; 60 thick 5,479.00 m2 £ 15.59 £ 85,436.50

70.2.4 Surfacing in new road embankment area; 40 thick 5,479.00 m2 £ 14.01 £ 76,761.22

70.3 New footpath in embankment area

70.3.1 Sub base in new footpath embankment area; 150 thick 5,130.00 m2 £ 6.75 £ 34,627.50

70.3.2 HRA binder in new footpath embankment area; 60 thick 5,130.00 m2 £ 15.59 £ 79,994.39

Tack Coat 5,130.00 m2 £ 0.75 £ 3,847.50

70.3.3 Surface course in new footpath embankment area; 40 thick 5,130.00 m2 £ 14.01 £ 71,871.70

70.4 New road out side of embankment area

70.4.1 Sub base, out of embankment area; 150 thick 1,789.00 m2 £ 6.75 £ 12,075.75

70.4.2 Base course , out of embankment area; 120 thick 1,789.00 m2 £ 23.29 £ 41,671.05

70.4.3 Binder course, out of embankment area; 60 thick 1,789.00 m2 £ 15.59 £ 27,896.68

Tack Coat 1,789.00 m2 £ 0.75 £ 1,341.75

70.4.4 Surfacing , out of embankment area; 40 thick 1,789.00 m2 £ 11.42 £ 20,426.18

70.5 New footpath out side of embankment area

70.5.1 Sub base in footpath,out side of embankment area; 150 thick 170.00 m2 £ 6.75 £ 1,147.50

70.5.2 HRA binder in footpath, out side of embankment area; 60 thick 170.00 m2 £ 15.59 £ 2,650.89

Tack Coat 170.00 m2 £ 0.75 £ 127.50

70.5.3 Surface course in footpath, out side of embankment area; 40 thick 170.00 m2 £ 14.01 £ 2,381.71

70.6 Works to tie into existing road

70.6.1 Plane out surface course in existing road 1,825.00 m2 £ 5.00 £ 9,125.00

70.6.2 Plane out surface course in existing footpath 1,000.00 m2 £ 5.00 £ 5,000.00

135112

Rev 1, Date: 7 May 2010

Page 25: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Ref Description Quantity Unit Rate Cost

70.6.3 Surface course, to tie in to existing road 1,825.00 m2 £ 14.01 £ 25,568.39

70.6.4 Surface course, to tie in to existing footpath 1,000.00 m2 £ 14.01 £ 14,010.08

Tack Coat 2,825.00 m2 £ 0.75 £ 2,118.75

Page Total £ 4,292,491.11

Rev 1, Date: 7 May 2010

Page 26: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Ref Description Quantity Unit Rate Cost

70.7 Car Parking

70.7.1 Form new Car Parking alongside Cambridge Road 85.00 nr £ 1,750.00 £ 148,750.00

70.8 Temporary Works

70.8.1 Traffic Management - Allowance 5.00 weeks £ 2,500.00 £ 12,500.00

70.8 Road Markings and Signage

70.8.1 Road Markings - Allowance 3.00 shifts £ 1,000.00 £ 3,000.00

70.8.2 Road Signs (non illuminated) - Allowance 10.00 nr £ 200.00 £ 2,000.00

70.9 Fencing

70.9.1 Post and rail fence 1,040.00 m £ 44.12 £ 45,887.86

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 212,137.86

Rev 1, Date: 7 May 2010

Page 27: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL -£

Ref Description Quantity Unit Rate Cost

80 Utilities

£ - £ -

Excluded £ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 28: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) -£

Ref Description Quantity Unit Rate Cost

Other Contractors Indirect Costs

Other Costs

(The Consultant shall enter details)

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

135112

Rev 1, Date: 7 May 2010

Page 29: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Overbridge) TOTAL 132,165.28£

Ref Description Quantity Unit Rate Cost

Network Rail Direct Costs

NDS - Materials £ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

NDS - Fleet

- Engineering trains £ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

-Tampers £ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 30: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Ref Description Quantity Unit Rate Cost

NDS Materials & Fleet (Tampers, etc.) costs generally within rates at GRIP 0-

2

NDS - Possession / Isolation management

Possession Management - Allowance 1% % £ 6,608,263.85 £ 66,082.64

Midweek Day nr £ - £ -

Midweek Night nr £ - £ -

Weekend nr £ - £ -

Bank Holiday nr £ - £ -

£ - £ -

OLE Isolations - Allowance 1% % £ 6,608,263.85 £ 66,082.64

Midweek Day nr £ - £ -

Midweek Night nr £ - £ -

Weekend nr £ - £ -

Bank Holiday nr £ - £ -

£ - £ -

DC Isolations £ - £ -

Midweek Day nr £ - £ -

Midweek Night nr £ - £ -

Weekend nr £ - £ -

Bank Holiday nr £ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ 132,165.28

Page Total £ 132,165.28

Rev 1, Date: 7 May 2010

Page 31: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Oracle Project No.:

Project Description:

Estimate Stage:

Rev. Date Consultant Prepared by Checked

Rev00 19-Mar-13 F+AJames

YarnallRobert Walker

Rev 1 8-May-13 F+A Steve Jackson

Consultant's Name & Address

Level of Confidence - +/- 30%

Issue and Revision Record:

Standard Template for Stage 1-2 Estimates prepared by Consultants

135112

GRIP 2 (+/-30%)

Description

Draft for review

Network Rail Validation

Foxton Level Crossing - Option 1 (Underpass)

Consultant to insert logo here

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates Rev 3, Date: 28 October 2011

Page 32: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Estimate Document Contents

1 User Notes (Consultant)

2 Assumptions

3 Estimating Risk Register

4 Estimate Summary Report

5 Indirect Costs (Auto generated)

6 Expenditure Profile (Summary by GRIP) (Auto generated)

7 10. Signalling, measured works

8 20. Electrification and Power, measured works

9 30. Track, measured works

10 40. Telecommunications, measured works

11 50. Operational Property, measured works

12 60. Structures, measured works

13

14 80. Utilities, measured works

15 Other Contractors Indirect Costs

16 Network Rail Direct Costs

70. General Civils, measured works

Rev 1, Date: 7 May 2010

Page 33: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

User Notes

1

2

3

4

5

6

7

8

i All documents used in the preparation of the estimate shall be listed within the estimate

ii All assumptions and exclusions applicable to the estimate must be described

iii Exclusions that result from a lack of knowledge will not be considered acceptable; exclusions of

this type will only be accepted with the agreement of the Estimating Manager

iv The Consultant shall ensure that estimate has been subject to an internal review by an

experienced staff member who must satisfy himself that it is free from errors, that the scope of

work has been accurately measured and that the level of pricing is appropriate

v The Consultant should submit a copy of his quantities 'take-off' to Network Rail with all

estimates submitted for approval

vi The consultant shall identify the source of rates used in pricing the estimate; when requested,

the consultant will provide copies of built-up rates and/or materials or sub-contract prices

obtained for the preparation of the estimate

vii The consultant must provide details of the basis for establishing the level of any provisional

sums and/or lump sum allowances where requested

vii The consultant shall include details of any particular risks seen by the estimator during

preparation of the estimate and give his view of their probability and potential impact - these

risks may relate to design, pricing, implementation etc and the risks are likely to be considered

as part of the projects quantified cost risk analysis process

9

10

11

The Consultant should note that the cost of certain materials and services provided as "free issue" to

the siteworks Contractor will generally be included in the rates at GRIP 1-2

The Consultant must comply with the following:

The Consultant should note that Network Rail's Estimating Manager (Enhancements) will be the

"approver" for all estimates and it should be anticipated that he will be asked to review/ revise certain

elements within the estimate (quantities and/or rates) as part of Network Rail's approval process

The Consultant shall check the accuracy of all formulas and links contained within this spreadsheet

and he shall ensure that these are maintained where any amendments are made to the spreadsheet

The Consultant shall indicate in the tables herein, the source of his unit rates and demonstrate how

his base rate has been uplifted for complexity (staging and constraints on access, working space,

use of plant etc) and possessions (out of normal hours working, short shifts etc); an adjustment may

be made for overheads & profit where this is not included within the base cost. The type and duration

of possessions shall be shown where work is to be carried out beyond normal hours.

The Consultant is required to prepare the estimate in accordance with GRIP Manual PM04 Cost

Estimating with particular reference to the requirements relating to the Type of Rates / Costs and the

Quantity Take Off Detail shown within Appendix A to this document

The Consultant should particularly note that all indirect costs will be based on percentage

calculations generated by the "Indirects" worksheet

It is recognised that certain costs that shall be included within the Project AFC are to be advised by

Network Rail

The Consultant shall prepare estimates in accordance with Network Rail's "Remit for Estimates

produced by Consultants" (some provisions of which are repeated hereunder)

The percentages used in the Indirects worksheet to calculate the Contractors and Network Rails

indirect costs may be adjusted by the Consultant in line with the range shown in PM04

The Consultant shall note that escalation will only be included within the Project Anticipated Final

Cost (Project AFC) where the Project AFC is in excess of £50m and where the site works will be over

2 years duration; escalation shall be calculated using RPI indices from the estimate 'base date' to the

mid-point of the construction phase

Where the project AFC is below £50m or the construction phase will be shorter than two years,

escalation shall not be included but it shall be calculated as described herein and shown in the

Estimate Summary Report under "Other Costs to the Customer"

Rev 1, Date: 7 May 2010

Page 34: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Estimate Stage: GRIP 2 (+/-30%)

Oracle Project No.: 135112

Project Description: Foxton Level Crossing - Option 1 (Underpass)

Assumptions

G1

G2

G3

G4

G5

G6

G7

Assumptions

A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12

A13

A14

A15

A16

A17

A18

A19

A20

A21

A22

A23

A24

Palisade fence required to fence off level crossing. Post and rail fence allowed at the bottom of

the 'batters' and each side of the new highway works

Existing roads and footpaths require re-surfacing at tie ins with new highway works

One carrier drain to new road construction (150mm diameter)

See summary for further assumptions/exclusions

No demolitions necessary, we have included for re-locating a number of portable buildings

Where there is in-sufficient information for the works to be priced confidently within the +/- %

range we have included allowances within the estimate. These have been clearly identified and

will require review once more information becomes available

Possession working has been included for in the rates where thought required (generally

assumed that some long weekend possessions will be available for the main bridge deck works)

TOC / FOC compensation costs included within the estimate as 50% x 19% = 9.50% as it is

thought that majority of the works will be undertaken either 'off track' in a civils environment,

fenced green zone or where required non disruptive midweek night possessions

General / Drawings & Documents / Exclusions

General

The estimate base date is 1Q13

Nothing has been included in the estimate for inflation past 1Q13 as the programme is not

known. Where it has been necessary to inflate any historical rates when compiling the estimate

NR inflation indices number 34 has been used

An uplift factor of 30% has been applied for cost and scope uncertainty which is consistent of

the requirements for a GRIP 2 estimate

Manholes at 50m centres

Depth of road construction; 150 sub base, 120 base course, 60 binder, 40 surfacing

Safety barrier extends from road junction to end of embankment on opposite side of bridge

Retaining wall within embankment area has strip footings and a 2.5m retained height

Seeding required to embankment sides (circa 150mm of site won top soil)

Substantial Permanent Way Works required including P Way, Signalling and OLE.

Medium to Large Drainage Pumping Station required due to negative drainage associated with

this option.

Depth of footpath construction; 150 sub base, 60 HRA binder, 40 surface course

OLE Gantries to be Twin Track Cantilever.

Excavated Material 80% Inert, 20% non hazardous.

Bridge installed by SPMT or slide

10% of Construction Costs allowed for Structure Design and 10% 5% for General Civils due to

'simple' scheme with standard bridge design

No Piling required to Box.

Street lighting columns at 15m centres, staggered (therefore one light per 15m of highway)

Level Crossing to be de-commissioned and removed

Gullies at 25m centres both sides of the carriageway

Car Parking Spaces along Cambridge Road tarmacadam on Sub Base.

No ground improvement works required under the new embankment (soil columns or pre-cast

concrete piles etc). One layer of geotextile only required under new embankment allowed for in

the estimate. No surcharging allowed for

Kerbs HB2 or similar

No allowance made for Pedestrian Access in the Station area (footbridge or subways etc)

Rev 1, Date: 7 May 2010

Page 35: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

D1

D2

E1

E2

E3

E4

E5

E6

E7

E8

E9

E10

E11

E12

VAT

Excludes any allowance for Optimism Bias

Drawings & Documents

Costs associated with changes in legislation, regulation and interpretation covering

3rd party compensation costs

Planning and approval charges

Costs associated with Statutory Fees (e.g. HMRI, Local Authority, etc.) unless confirmed

Costs associated with taxes and levies

Costs associated with licences and all associated costs and fees

Costs associated with changes in legislation and any form of applicable standards

Christmas or Bank Holiday working

Land take, temporary or permanent

MMD-318484-C-DR-BR-02 rev p1

MMD-318484-C-DR-HW-02 rev p1

Service diversions unless specifically stated otherwise

Exclusions

The following documents have been used in the preparation of this estimate:

Rev 1, Date: 7 May 2010

Page 36: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Estimate Stage: GRIP 2 (+/-30%)

Oracle Project No.: 135112

Project Description: Foxton Level Crossing - Option 1 (Underpass)

Estimating Risk Register

Ref Risk Type Description Probability Potential Cost Impact

Ground improvement works required

Scope confidence Price confidence Risk confidence

Remarks

Notes:

Asset

Risk Confidence: Good = low risk scheme / works; Poor = high risk scheme /works

Price confidence: Good = we have good cost knowledge; Poor = poor cost knowledge and/or price certainty

Scope Confidence: High = good confidence scope will not change significantly; Medium = Limited scope growth predicted; Low =

scope may grow significantly#

The estimator is required to identify any risks to the project and/or estimate identified in preparing the estimate; this is to

inform the QCRA process only and any potential cost impacts will not impact on the estimate total. The estimator should

indicate his assessment of the level of cost impact (by percentage/ H/M/L assessment / cost value or range), it is

recognised that this will be a subjective assessment only

CONFIDENCE LEVEL MATRIX

Utilities

General Civils

Structures

OP Property

Telecoms

Track

E&P

Signalling

Stage 3 4 Estimate: Standard Template (Network Rail) Issue 2, Date : 6 April 2010

Page 37: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

1302MA0160 Revision Rev 1 Estimate Stage GRIP 2 (+/-30%)

08-May-13 1Q2013

TBC TBC

WBS Estimate Breakdown Value Escalation (Y/N)

%age of

Point

Estimate

Remarks

Contractor's direct costs -

10 Signalling 280,000 Y

20 Electrification & Plant 99,014 Y

30 Track 536,435 Y

40 Telecoms - Y

50 Operational Property - Y

60 Structures 2,420,900 Y

70 General Civils 6,777,882 Y

80 Utilities - Y Excluded

Contractor's Base Construction Cost inc OH&P: Sub-Total A 10,114,232

Network Rail's "direct costs"

tbc NDS - Materials Y Generally within the rates (direct costs) at Stages 0 - 2

tbc NDS - Fleet Y Generally within the rates (direct costs) at Stages 0 - 2

tbc - Engineering trains Y Generally within the rates (direct costs) at Stages 0 - 2

tbc - Tampers Y Generally within the rates (direct costs) at Stages 0 - 2

tbc NDS - Possession / Isolation Management 202,285

Sub - Total B 202,285

10,316,517 0.00%

Contractor's indirect costs

tbc 2,106,520 Y

tbc 1,031,226 Y

tbc 92,422 Y

tbc Y Generally within the rates (direct costs) at Stages 0 - 2

tbc Y Generally within the rates (direct costs) at Stages 0 - 2

tbc - Y

Sub - Total D 3,230,169

Total Construction Cost E (C+D) 13,546,685

Network Rail's indirect & other costs

tbc Network Rail Project Management, (COWD) N To be advised by NR; Apportionment of GRIP 1 cost

tbc Network Rail Project Management, (forecasted remaining costs) 1,517,135 Y Based on typical %

tbc 1,169,752 Y Calculated as 19% x 50% of construction costs

tbc DCO Charges 0% Y Excluded

tbc Land / Property Costs & compensation 0.00% Y Excluded

tbc Escalation (see Note 1) % - NA Excluded as mid-point of the programme not known

tbc Other ( State )

Sub - Total F 2,686,886

Point Estimate - Sub - Total G (E+F) 16,233,572

Uplift for Risk and Contingency

tbc To Mean (see Note 3) £ See Note 3

Project Budget (Point Estimate + Uplift to Mean) 16,233,572 for Project Manager's reference

tbc QRA Value - at P50 (see Note 3) £

tbc QRA Value - at P80 - incremental on P50 value (see Note 3) £

tbc Adjustment for residual factors (see Note 2) % 30% 4,870,071

Project Anticipated Final Cost (AFC) 21,103,643 Authorised AFC

Other Costs to the Customer

tbc Allowance for Escalation (see Note 1)See Note 1

tbc Allowance for Network Rail Fee Fund -

tbc Allowance for Industry Risk Fund -

tbc Allowance for Insurance Top-up

01/05/2002

Cost to Customer 21,103,643

Name :- Steve Jackson

Company :- Network Rail

Position :- Estimator - Anglia Route 08/05/2013 Estimator

Signed :-

Date :- Estimating Manager

Notes:-

1. Escalation will only be included within the Project Anticipated Final Cost (Project AFC) where the Project AFC is in excess of £50m and where the site works will be over 2 years duration; escalation shall be calculated using RPI indices from the

estimate 'base date' to the mid-point of the construction phase

Where the project AFC is below £50m or the construction phase will be shorter than two years, escalation shall not be included but it shall be calculated as described herein and shown in the Estimate Summary Report under "Other Costs to the 2. An 'Adjustment for residual factors' has been applied in accordance with the Guidance Notes on Estimating and Supplementary Note (dated 18th March 2010).

3. The project team or Risk & Value Manager should provide the values for uplifts to Mean, P50 and P80. The uplifts to Mean and P50 should be entered in the spaces provided; the incremental value to P80 (beyond P50) should be shown in the box

provided (i.e. P80 value - P50 value)

F & A

19/03/2013

provided by Sponsor

APPROVAL & ENDORSEMENT

Estimate Produced by :- Estimate Approved by (Network Rail) :- Estimate Endorsed by (Network Rail) :-

J Yarnall - R Walker

Sponsor to advise if P50 or P80 value shall apply See Note 3

Sponsor to advise if P50 or P80 value shall apply See Note 3

Uplift on Point Estimate Value (excluding the Cost of Work Done) See Note 2

provided by Sponsor

provided by Sponsor

Design

Testing & Commissioning

Training

Spares

Other

Compensation charges (TOC & FOC), (costs from NDS)

Project No. 135112

Project Title / Location Foxton Level Crossing - Option 1 (Underpass)

Total Base Construction Cost inc OH&P: Sub-Total C (A+B)

Preliminaries

ESTIMATE SUMMARY REPORT

Estimate No.

Estimate Date Price 'Base date'

Anticipated Start Date Anticipated Finish Date

Rev 1, Date: 7 May 2010

Page 38: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Estimate Stage:

Oracle Project No.:

Project Name:

Calculation of Contractors and Network Rail's Indirect Costs

Asset Total Direct

Costs

% Preliminaries % Design % Test &

Commission

% Network Rail

Management

% Sponsor

Signalling 280,000 35% 98,000 10% 28,000 15% 42,000 12% 33,600 3% 8,400

Electrification & Plant 99,014 35% 34,655 30% 29,704 13% 12,872 12% 11,882 3% 2,970

Track 536,435 25% 134,109 10% 53,644 7% 37,550 12% 64,372 3% 16,093

Telecoms 0 25% 0 10% 0 10% 0 12% 0 3% 0

Operational Property 0 25% 0 10% 0 0% 0 12% 0 3% 0

Structures 2,420,900 20% 484,180 10% 242,090 0% 0 12% 290,508 3% 72,627

General Civils 6,777,882 20% 1,355,576 10% 677,788 0% 0 12% 813,346 3% 203,336

Utilities 0 25% 0 10% 0 0% 0 12% 0 3% 0

2,106,520 1,031,226 92,422 1,213,708 303,427

Total for TOC / FOC calculation (19% of Total Construction Cost maximum)

10,114,232 2,106,520 92,422

TOTAL 12,313,175

GRIP 2 (+/-30%)

135,112

Foxton Level Crossing - Option 1 (Underpass)

Rev 1, Date: 7 May 2010

Page 39: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL 280,000.00£

Ref Description Quantity Unit Rate Cost

10 Signalling

10.1 Recoveries

10.1.1 De-commission and recover the existing Level Crossing - Allowance 1 item £ 50,000.00 £ 50,000.00

10.1.2 Signalling Modifications in association with Permanent Way Renewal -

Allowance

1 item £ 50,000.00 £ 50,000.00

10.1.3 Allowance for Temporary Services Bridge to carry Signalling/Telecoms

Cabling - Allowance

1 item £ 100,000.00 £ 100,000.00

10.1.4 Slew S&T Cables onto Services Bridge and return on completion -

Allowance

400 m £ 200.00 £ 80,000.00

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 280,000.00

135112

Rev 1, Date: 7 May 2010

Page 40: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL 99,014.45£

Ref Description Quantity Unit Rate Cost

20 Electrification and Plant

20.1 Recoveries

20.1.1 OHL Wiring 200 m £ 22.06 £ 4,412.29

20.1.2 Take Down and Set Aside for Re - Use existing OLE Structures (Assumed

Twin Track Cantilever)

2 nr £ 5,000.00 £ 10,000.00

20.2 New OLE works

20.2.1 Re Install OLE Structures Previously Set Aside for Re Use (Assumed Twin

Track Cantilever)

2 nr £ 10,000.00 £ 20,000.00

20.2.2 Wiring (Contact, Catenary, droppers and return conductor) 200 m £ 66.18 £ 13,236.88

20.2.3 Connections to existing 4 nr £ 330.92 £ 1,323.69

20.3 Level Crossing

20.3.1 Re-grading of OLE locally to removed level crossing 200 m £ 44.12 £ 8,824.59

DNO Supply 1 nr £ 15,000.00 £ 15,000.00

DNO Cabinet 1 nr £ 12,000.00 £ 12,000.00

Turning Chambers 39 nr £ 340.00 £ 13,260.00

Distribution Panel 1 nr £ 957.00 £ 957.00

Page Total £ 99,014.45

135112

Rev 1, Date: 7 May 2010

Page 41: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL 536,435.24£

Ref Description Quantity Unit Rate Cost

30 Track

30.1 Work to existing track

30.1.1 Design tamp upon removal of existing level crossing. 1 shift £ 12,685.35 £ 12,685.35

30.1.2 Take Up Existing Track and Set Aside for Re-Use. 400 m £ 65.00 £ 26,000.00

30.1.3 Remove Track Ballast To Tip assumed 50% Contaminated and 50% Inert 800 m3 £ 106.55 £ 85,240.00

30.1.4 Take Up Existing Turnouts and Set Aside for Re-Use. 2 nr £ 25,000.00 £ 50,000.00

30.1.5 New Top and Bottom Ballast. 800 m3 £ 50.00 £ 40,000.00

30.1.6 Relay Existing Track previously set aside for re-use. 400 m £ 350.00 £ 140,000.00

30.1.7 Re Install Turnouts previously set aside for re-use. 2 nr £ 50,000.00 £ 100,000.00

30.1.8 New Cess Walkway 700mm wide. 200 m £ 93.76 £ 18,752.25

30.1.9 Install new Cess Drainage. 400 m £ 132.37 £ 52,947.53

30.1.10 Catchpit 14 nr £ 772.15 £ 10,810.12

Page Total £ 536,435.24

135112

Rev 1, Date: 7 May 2010

Page 42: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL -£

Ref Description Quantity Unit Rate Cost

40 Telecoms

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 43: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL -£

Ref Description Quantity Unit Rate Cost

50 Operational Property

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 44: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL 2,420,900.00£

Ref Description Quantity Unit Rate Cost

60 Structures

60.1 Under Bridge

60.1.1 New Underpass - Concrete Box Construction 563.00 m2 £ 4,300.00 £ 2,420,900.00

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 2,420,900.00

135112

Rev 1, Date: 7 May 2010

Page 45: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL 6,777,882.19£

Ref Description Quantity Unit Rate Cost

70 General Civils

70.1 Miscellaneous

70.1.1 Site Clearance 20,974.00 m2 £ 5.00 £ 104,870.00

70.1.2 Excavate topsoil and move to on-site stockpile; 300 thick 6,120.00 m3 £ 13.20 £ 80,784.00

70.1.3 Geotextile 20,974.00 m2 £ 8.75 £ 183,522.50

70.1.4 Excavate for cutting and dispose of material Off Site (Inert) - assumed 80% 63,795.00 m3 £ 25.00 £ 1,594,875.00

70.1.5 Excavate for cutting and dispose of material Off Site (Non Hazardous) -

assumed 20%

15,949.00 m3 £ 188.10 £ 3,000,006.90

70.1.6 Seeding to embankments inc circa 150mm of site won topsoil 40,994.00 m2 £ 4.95 £ 202,920.30

70.1.7 Kerbs 2,162.00 m £ 20.00 £ 43,240.00

70.1.8 Carrier drain - 150mm 570.00 m £ 60.00 £ 34,200.00

70.1.9 Connection to existing drainage system - Allowance 1.00 sum £ 5,000.00 £ 5,000.00

70.1.10 Gullies inc allowance for pipe to connect into carrier drain (3.7m per gulley) 46.00 nr £ 622.00 £ 28,612.00

70.1.11 Manholes 12.00 nr £ 1,500.00 £ 18,000.00

70.1.12 Safety barrier 1150.00 m £ 120.00 £ 138,000.00

70.1.13 Lighting columns 38.00 nr £ 2,426.76 £ 92,216.94

70.1.14 Containment Parapet to Top of Underpass Included

70.1.15 Fencing off of old level crossing 70.00 m £ 120.00 £ 8,400.00

70.1.16 Move portable buildings; 2 nr - Allowance 1.00 sum £ 7,500.00 £ 7,500.00

70.1.17 Retaining wall near embankment (assumed retained height 2.5m) 30.00 m £ 1,875.00 £ 56,250.00

70.1.18 Drainage Pumping station including 100m of rising main to outfall - Allowance 1.00 item £ 256,000.00 £ 256,000.00

70.2 New road in embankment area

70.2.1 Sub base in new road embankment area; 150 thick 5,479.00 m2 £ 6.75 £ 36,983.25

70.2.2 Base course in new road embankment area; 120 thick 5,479.00 m2 £ 23.29 £ 127,621.95

Tack Coat 5,479.00 m2 £ 0.75 £ 4,109.25

70.2.3 Binder in new road embankment area; 60 thick 5,479.00 m2 £ 15.59 £ 85,436.50

70.2.4 Surface course in new road embankment area; 40 thick 5,479.00 m2 £ 14.01 £ 76,761.22

70.3 New footpath in embankment area

70.3.1 Sub base in new footpath embankment area; 150 thick 5,771.25 m2 £ 6.75 £ 38,955.94

70.3.2 HRA binder in new footpath embankment area; 60 thick 5,771.25 m2 £ 15.59 £ 89,993.69

Tack Coat 5,771.25 m2 £ 0.75 £ 4,328.44

70.3.3 Surface course in new footpath embankment area; 40 thick 5,771.25 m2 £ 14.01 £ 80,855.67

70.4 New road out side of embankment area

70.4.1 Sub base, out of embankment area; 150 thick 1,788.50 m2 £ 6.75 £ 12,072.38

70.4.2 Base course , out of embankment area; 120 thick 1,788.50 m2 £ 23.29 £ 41,659.40

70.4.3 Binder course, out of embankment area; 60 thick 1,788.50 m2 £ 15.59 £ 27,888.88

Tack Coat 1,788.50 m2 £ 0.75 £ 1,341.38

70.4.4 Surface Course , out of embankment area; 40 thick 1,788.50 m2 £ 11.42 £ 20,420.47

70.5 New footpath out side of embankment area

70.5.1 Sub base in footpath,out side of embankment area; 150 thick 191.25 m2 £ 6.75 £ 1,290.94

70.5.2 HRA binder in footpath, out side of embankment area; 60 thick 191.25 m2 £ 15.59 £ 2,982.25

Tack Coat 191.25 m2 £ 0.75 £ 143.44

70.5.3 Surface course in footpath, out side of embankment area; 40 thick 191.25 m2 £ 14.01 £ 2,679.43

70.6 Works to tie into existing road

70.6.1 Plane out surface course in existing road 1,825.00 m2 £ 5.00 £ 9,125.00

70.6.2 Plane out surface course in existing footpath 1,000.00 m2 £ 5.00 £ 5,000.00

135112

Rev 1, Date: 7 May 2010

Page 46: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Ref Description Quantity Unit Rate Cost

70.6.3 Surface course, to tie in to existing road 1,825.00 m2 £ 14.01 £ 25,568.39

70.6.4 Surface course, to tie in to existing footpath 1,000.00 m2 £ 14.01 £ 14,010.08

Tack Coat 2,825.00 m2 £ 0.75 £ 2,118.75

Page Total £ 6,565,744.33

Rev 1, Date: 7 May 2010

Page 47: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Ref Description Quantity Unit Rate Cost

70.7 Car Parking

70.7.1 Form new Car Parking alongside Cambridge Road 85.00 nr £ 1,750.00 £ 148,750.00

70.8 Temporary Works

70.8.1 Traffic Management - Allowance 5.00 weeks £ 2,500.00 £ 12,500.00

70.8 Road Markings and Signage

70.8.1 Road Markings - Allowance 3.00 shifts £ 1,000.00 £ 3,000.00

70.8.2 Road Signs (non illuminated) - Allowance 10.00 nr £ 200.00 £ 2,000.00

£ - £ -

70.9 Fencing

70.9.1 Post and rail fence 1,040.00 m £ 44.12 £ 45,887.86

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ 212,137.86

Rev 1, Date: 7 May 2010

Page 48: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL -£

Ref Description Quantity Unit Rate Cost

80 Utilities

£ - £ -

Excluded £ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 49: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) -£

Ref Description Quantity Unit Rate Cost

Other Contractors Indirect Costs

Other Costs

(The Consultant shall enter details)

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

135112

Rev 1, Date: 7 May 2010

Page 50: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Oracle Project

No.

Project

Description Foxton Level Crossing - Option 1 (Underpass) TOTAL 202,284.64£

Ref Description Quantity Unit Rate Cost

Network Rail Direct Costs

NDS - Materials £ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

NDS - Fleet

- Engineering trains £ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

-Tampers £ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ -

Page Total £ -

135112

Rev 1, Date: 7 May 2010

Page 51: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Ref Description Quantity Unit Rate Cost

NDS Materials & Fleet (Tampers, etc.) costs generally within rates at GRIP 0-

2

NDS - Possession / Isolation management

Possession Management - Allowance 1% % £ 10,114,231.89 £ 101,142.32

Midweek Day nr £ - £ -

Midweek Night nr £ - £ -

Weekend nr £ - £ -

Bank Holiday nr £ - £ -

£ - £ -

OLE Isolations - Allowance 1% % £ 10,114,231.89 £ 101,142.32

Midweek Day nr £ - £ -

Midweek Night nr £ - £ -

Weekend nr £ - £ -

Bank Holiday nr £ - £ -

£ - £ -

DC Isolations £ - £ -

Midweek Day nr £ - £ -

Midweek Night nr £ - £ -

Weekend nr £ - £ -

Bank Holiday nr £ - £ -

£ - £ -

£ - £ -

£ - £ -

£ - £ -

To Estimate Summary Report £ £ 202,284.64

Page Total £ 202,284.64

Rev 1, Date: 7 May 2010

Page 52: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Oracle Project No.:

Project Description:

Estimate Stage:

Rev. Date Consultant Prepared by Checked

Rev00 1-Mar-13 F+A Zoe Heeley Robert Walker

Rev01 12-Mar-13 F+AJames

YarnallRobert Walker

Rev02 19-Mar-13 F+AJames

YarnallRobert Walker

Rev 3 8-May-13 F+A Steve Jackson

Consultant's Name & Address

Level of Confidence - +/- 30%

Issue and Revision Record:

Standard Template for Stage 1-2 Estimates prepared by Consultants

135112

GRIP 2 (+/-30%)

Description

Draft for review

Draft for review

Draft for review

Network Rail Validation

Foxton Level Crossing - Option 4 (Overbridge)

Consultant to insert logo here

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates Rev 3, Date: 28 October 2011

Page 53: Foxton Level Crossing Elimination GRIP 2 Report Rev C Foxton...318484/WTD/MID/001/C May2013 P:\Birmingham\BNI\318484 Foxton Level Crossing Elimination\Reports\Foxton Level Crossing

Enhancements Estimating

Standard Template for Stage 1 and 2 Estimates

Estimate Document Contents

1 User Notes (Consultant)

2 Assumptions

3 Estimating Risk Register

4 Estimate Summary Report

5 Indirect Costs (Auto generated)

6 Expenditure Profile (Summary by GRIP) (Auto generated)

7 10. Signalling, measured works

8 20. Electrification and Power, measured works

9 30. Track, measured works

10 40. Telecommunications, measured works

11 50. Operational Property, measured works

12 60. Structures, measured works

13

14 80. Utilities, measured works

15 Other Contractors Indirect Costs

16 Network Rail Direct Costs

70. General Civils, measured works

Rev 1, Date: 7 May 2010