North America’s first state-of-the-art advanced display manufacturing campus in the Village of Mount Pleasant, Racine County.
1,073 Acres
1,198 Acres 622 Acres
ABOUT THE PROJECT
•Largest economic development project in Wisconsin history
•Largest greenfield investment by a foreign-based company in U.S. history
•Largest corporate attraction project is U.S. history
•13,000 jobs when campus in complete•Average salary $53,000+, plus benefits
•10,000 direct construction jobs annually over 4-6 years
•20 million sq. ft. campus – equivalent to the size of 13 Lambeau Fields
FOXCONN’S INVESTMENT IN WISCONSIN
Request For Proposal: Cost, Speed, Workforce◦ First Community Site Tours
MOU Signed◦ $10 billion in investments, 13,000 jobs, $3 billion incentive
Act 58 Signed◦ Creation of an Electronics & Information Technology Manufacturing Zone
Site Announcement
WEDC Contract Agreement Signed
Infrastructure Design and Coordination Begins
Local Development Agreement Signed
Governor Announces Talent Attraction
Discussions beginning on workforce, transportation, and housing
May 2017
July 2017
October 2017
November 2017
December 2017
January 2018
PROJECT EVOLUTION
September 2017
FOXCONN BACKGROUND INFORMATION
•Foxconn generated total annual revenue of $135 billion and net income of $4.5 billion in 2016 and was ranked No. 27 on the 2017 Fortune magazine Global 500• Fourth-largest technology company in the world
•Foxconn specializes in design, manufacturing and assembly of global computer and high-tech consumer electronics products
•The company has facilities in Asia, Brazil, Europe and Mexico. The Wisconsin facility will be its first significant investment in the U.S.
899'
65'
896'
964'
1238'
65'
66'
171' 167' 220'
527'
1740' 2067'1596'
3336' 2067'
135'
Array - Phase 1 Color Filter Phase 1
Cell - Phase 1 Open CellPhase 1
LCM - Phase 1
ATC Terminal
Future Transformer SVC
Su
bst
atio
n
Parking Structure
ParkingLot
Logistics LCMPhase 2
LCMPhase 2
GlassPlant
Spec & Bulk Gas Yard
Pa
rkin
g L
ot
791'
730'
1266'
746' 558'
650'
726'
336'
117
0'
1000 spaces
350 spaces
Office
Waste WaterTreatment Phase 1
Array - Phase 2 Color Filter Phase 2
Cell - Phase 2 Open CellPhase 2
LCM - Phase 2
Waste WaterTreatment Phase 2
Parking Lot
Parking LotParking Lot
Parking Lot
1500 spaces
1300 spaces1350 spaces
1500 spaces
LCM Energy Plant
Truck Docks & Yard
Ref PointN: 170219.69E: 597981.44
TFT CUB Energy Plant
Phase 2
TFT CUB Energy Plant
Phase 1
N2 Plant
Chemical Plant
Parking Structure
WWT Materials Storage
Legend
- Water
- Landscape
- Road
- Security Barrier
- Parking Lot
PRELIMINARY - FOR INFORMATION ONLY 1/10/2018 2:36:36 PM
1" = 300'-0"
A -100Site MasterplanFlying Eagle
699403
- 1" = 300'-0"
1 SITE PLAN
KEY WEDC CONTRACT PROVISIONS
•Job creation and retention drive every aspect of Foxconn’s potential tax incentives
•All tax credits are “pay as you grow.”• Foxconn must create jobs and invest capital in Wisconsin before it is
eligible for any tax incentives
•The tax incentives must be earned. • Foxconn must meet all job creation and capital investment targets
contained in the WEDC contract to earn the maximum amount of tax benefit, $2.85 billion.
KEY WEDC CONTRACT PROVISIONS
•Prior to receiving tax credits each year, Foxconn is required to hire an independent CPA that will use industry standards to attest to the job creation and capital investment reports submitted to WEDC.
•There are stringent provisions in place to ensure Foxconn meets the terms of the contract as well as clawback provisions if the company defaults on the contract.
•Foxconn will report annually on its Wisconsin-based supply chain purchases.
KEY WEDC CONTRACT PROVISIONS
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
11000
12000
13000
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
Jobs Tax Credit Requirements
Minimum FTE Jobs to Receive Any Credits FTE Jobs Target to Receive Full Credits
KEY ELEMENTS OF DEVELOPMENT AGREEMENT
•Foxconn guarantees the campus will contain at least $1.4 billion in taxable value by Jan. 1, 2023
•Construction Commencement
•Jobs• Foxconn will “exercise good faith in striving to hire, retain and contract, whenever
reasonably possible, with qualified individuals and businesses residing and/or based in the County as well as veterans and minority-owned businesses.”
•Key Timing
•Public Improvements
ENVIRONMENTAL REQUIREMENTS
•What is the Same•Air Permitting
• Storm Water Control
•Hazardous Waste
•Wastewater Regulation
•Great Lakes Water Use Regulation
•What is Different•Wetland Regulations
•Waterway Regulations
• Environmental analysis requirements under the Wisconsin Environmental Policy Act (WEPA)
ENVIRONMENTAL REQUIREMENTSWETLAND REGULATIONS
•Each acre of federal or nonfederal wetland filled must be compensated at a 2:1 acre ratio and DNR will oversee the mitigation process.
•All other projects in Wisconsin are generally only required to mitigate 1.2 to 1 wetland acre ratio.
•Discharges of dredged or fill material into federal wetlands require a federal permit. No state wetland permit is required.
PERMIT APPLICATIONS
Permit Applications Required Surrounding the Development
•Air
•Wetlands
•NOI Land Disturbance
•Storm Water / Flood Plain
•Endangered Species
•Archaeological
•Navigable Waterways
•Water Diversion
DIVERSION REQUEST
Diversion request would be 0.07% of the existing total withdrawals from Lake Michigan (in 2016).
TENTATIVE CONSTRUCTION TIMELINE
•Tentative Construction Timeline Goals•Groundbreaking
• Spring 2018
•LCM Assembly Operations
•Winter 2018/Spring 2019
•Project Complete
• 2021
NEED FOR DOT COORDINATION
•Time of Projects•First LET June 2018
•Completion by end of 2021
•Coordination Needs
•Cost Savings•Planning level cost estimate of $150M to $165M
•Minimize Traffic Congestion
CONSTRUCTION ACCESS &
TRAFFIC MANAGEMENT
• Pavement along these routes will be strengthened to accommodate anticipated heavy traffic due to development, and diverted freeway traffic during I-94 reconstruction.
• Materials hauling and heavy equipment required for reconstruction.
ROAD IMPROVEMENT CONSTRUCTION SCHEDULE
International Drive◦ 2018/19
Braun Road◦ 2018/19 and 2021
County KR◦ 2018/19 and 2021
Wisconn Valley Way◦ 2019
WIS 11◦ 2019 and 2021
County H◦ 2020
WORKFORCE TRAINING
•Meeting with potential partners in January 2018
•Plan finalization spring of 2018
WORKFORCE OPPORTUNITIES
JOB SOURCES
• Construction (Public and Private)
• Foxconn Positions
• Positions with Existing Racine County Employers
CANDIDATE POOLS
• Existing Residents
•Under and Unemployed
• Focus on Youth
•Workforce Recruitment
SUPPLY CHAIN OPERATIONS
With the large number of potential suppliers in Wisconsin, coordination with Foxconn is ongoing to develop a structure for supply chain operations.
WISCONSIN’S FOXCONN BONUS
•Foxconn announced the purchase of a seven-story office building located in downtown Milwaukee from Northwestern Mutual Life Insurance Co., which will serve as the headquarters for the company’s operations in Wisconsin and the Wisconn Valley Innovation Center.
•This purchase goes above and beyond the company’s agreement with the state as it is independent of any state investment incentives, and it comes in addition to the company’s plans for a 20 million square-foot facility in Racine County.
WISCONN VALLEY NEWS
Sign up for the Wisconn Valley News to stay up-to-date on news surrounding this historic development.
•Wisconnvalley.wi.gov/newsletter
QUESTIONS?
•For Further Information Please Visit•www.foxconnracinecounty.com•www.wisupplychainmarketplace.com•Wisconnvalley.wi.gov