Foundations in Building Constuction

95
Prepared by : Othman Hassan Senior Lecturer / Registered Interior Designer with Lembaga Arkitek Malaysia (Reg. No: ID/O 6) Department of Interior Architecture UiTM Perak c FOUNDATIONS INA105/151 Building Construction & Materials 1

description

foundations

Transcript of Foundations in Building Constuction

Page 1: Foundations in Building Constuction

Prepared by :

Othman Hassan

Senior Lecturer / Registered Interior Designer with Lembaga Arkitek Malaysia (Reg. No: ID/O 6)

Department of Interior Architecture

UiTM Perak

c

FOUNDATIONS

INA105/151Building Construction & Materials 1

Page 2: Foundations in Building Constuction

FOUNDATIONS INA105/151

The construction of foundation starts after all the tasks below completed.

1. Site Investigation2. Clearing the site3. Establishing level4. Setting out the building line

1. FOUNDATION AND ITS FUNCTIONS

1. As the base on which a building rests and its purpose is to safely transfer the load of a building to a suitable subsoil.2. Prevent possible movement of structure due to settlement (ground movement)3 Allow building over water or water-logged ground4.Resist uplifting or overturning forces due to wind5.Resist lateral forces due to soil movement6.Underpin (support) existing or unstable structures

Page 3: Foundations in Building Constuction

2. FACTORS THAT INFLUENCE THE CHOICE OF FOUNDATION TYPE

The choice and design of foundations for many types of building depend mainly on factors below:

1. The total loads of the building2. The nature and bearing capacity of the soil.3. Materials used for the foundation4. Economical consideration of using a right kinds of foundation5. Layout of the structures (building/floor plan, positioning loads)6. Conditional of the site (location and sufficient work space)

FOUNDATIONS INA105/151

Page 4: Foundations in Building Constuction

3. SUBSOIL AND BEARING CAPACITY

Subsoils are soils below the topsoil ; the topsoil being about 300mm deep from the ground level surface. Bearing capacity is safe load per unit area which the ground can carry.

Typical bearing capacities of subsoils are as follows:

Rock, granite 600 -10,000 kN/m2 (60,000-1,000,000kg)Non-cohesive soils, compact sand600 kN/m2

Cohesive soils, hard clay <600 kN/m2

Having ascertained the nature and bearing capacity of the subsoil the foundation can be determined by calculating the total (dead + imposed) load per meter run of foundation and relating this to the analyzed safe bearing capacity of the subsoil

Total load of building per meter = min. foundation widthSafe bearing capacity of subsoil

The average total loading for a two-storey house is 30-50 kN/m2

FOUNDATIONS INA105/151

Page 5: Foundations in Building Constuction

3. SUBSOIL AND BEARING CAPACITY

Example: If the total load of a house is 40 kN/m2 and the subsoil safe bearing capacity is 80 kN/m2, then the foundation width is:

40 = 0.5 m or 500mm (strip foundation) 80

FOUNDATIONS INA105/151

Page 6: Foundations in Building Constuction

SUBSOIL TYPE kN/m2

Hardpan overlaying rock 1290

Very compact sandy gravel 1075

Loose gravel and sandy gravel, compact sand and 645gravelly sand, very compact sand-inorganic silt soils

Hard, dry, consolidated clay 537

Loose coarse to medium sand, medium compact fine sand 430

Compact sand clay 322

Loose, fine sand, medium compact sand-inorganic silt soils 215

Firm or stiff clay 161

Loose, saturated sand-clay soils, medium soft clay 107

FOUNDATIONS INA105/151

3. SUBSOIL AND BEARING CAPACITY

High Bearing Capacity

MediumBearing Capacity

LowBearing Capacity

Page 7: Foundations in Building Constuction

Under pure vertical downward loads

Wind

4. FORCES ACTING ONTO BUILDING

Under lateral wind loads Combined effect

Downward loadUplifting action

Tendency to turn under

wind

Building BuildingBuilding

FOUNDATIONS INA105/151

Page 8: Foundations in Building Constuction

5. TYPES OF BUILDING FOUNDATION:

1. Shallow Foundation

a. Pad Foundation or Isolated Foundation

b. Raft Foundations - Solid Slab Raft Foundation

- Beam and Slab Raft Foundation

- Cellular Raft Foundation

c. Strip Foundation

d. Trench-Fill Foundation

2. Deep Foundation

a. Pile Foundation

FOUNDATIONS INA105/151

Page 9: Foundations in Building Constuction

1. Shallow Foundation

Shallow foundation or sometimes called ‘spread footing’ usually refers to those being rested on stratum with adequate bearing capacity and laid less than 3 meters below ground level. Examples included pad or isolated, raft, strip and trench-fill foundations.

The selection of the right type of shallow foundation normally depend on the the magnitude and disposition of the structural loads and the bearing capacity of subsoil. A combination of two or three type of shallow foundation in one single structure is not uncommon

a. Pad Foundation or Isolated Foundation

Pad foundations or isolated foundations are used to support an individual point load such as that due to a structural column. They may be circular,square or rectangular. They usually consists of a block or slab of uniform thickness to spread the load from a column. Pad foundations or isolated foundations are usually shallow. This type of foundation is suitable on high bearing capacity subsoils.

FOUNDATIONS INA105/151

Page 10: Foundations in Building Constuction

Stages of work in preparing Pad Foundation

Stage 1: Excavation worksStage 2: Formwork preparationStage 3: Reinforcement bar preparationStage 4: Installation of reinforcement and starter barsStage 5: Concreting worksStage 6: Installation of stumps

FOUNDATIONS INA105/151

Page 11: Foundations in Building Constuction

Stages of work in preparing Pad Foundation

Stage 1: Excavation works

FOUNDATIONS INA105/151

The first stage of works in preparing Pad Foundation is excavation works. Ground will be dug between 1m to 3m deep to make a trench.

Page 12: Foundations in Building Constuction

FOUNDATIONS INA105/151

Stages of work in preparing Pad Foundation

Stage 2: Formwork preparation

The second stage of works in preparing Pad Foundation is formworks preparation.

Formwork

Page 13: Foundations in Building Constuction

Reinforcement bar

FOUNDATIONS INA105/151

Stages of work in preparing Pad Foundation

Stage 3: Reinforcement bar preparation

The third stage of works in preparing Pad Foundation is reinforcement bar preparation.

Page 14: Foundations in Building Constuction

Stages of work in preparing Pad Foundation

Stage 4: Installation of reinforcement and starter bars

FOUNDATIONS INA105/151

The fourth stage of works in preparing Pad Foundation is installing reinforcement and starter bars in formworks.

Starter bar

Reinforcement bar

Page 15: Foundations in Building Constuction

Stages of work in preparing Pad Foundation

Stage 5: Concreting works

FOUNDATIONS INA105/151

The fifth stage of works in preparing Pad Foundation is concreting works.Concrete Grade M30 is used for this foundation.

Page 16: Foundations in Building Constuction

Concrete Grade

Concrete mixes (cement, fine aggregate, coarse aggregate) can be expressed as volume grade and ratios:

• Grade M5 (5N/mm²) - 1:5:10 = 1 part of cement, 5 parts of fine aggregate, 10 parts of coarse aggregate.(ordinary concrete)

• Grade M10 (10N/mm²) - 1:3:6 = 1 part of cement, 3 parts of fine aggregate, 6 parts of coarse aggregate.(ordinary concrete)

• Grade M15 (15N/mm²) - 1:2:4 = 1 part of cement, 2 part of fine aggregate, 4 parts of coarse aggregate. (ordinary concrete) - for solid ground floor

• Grade M20 (20N/mm²) - 1:1.5:2 = 1 part of cement, 1.5 parts of fine aggregate, 2 parts of

coarse aggregate. (standard concrete)• Grade M25 (25N/mm²) - 1:1:2 = 1 part of cement, 1 parts of fine aggregate, 2 parts of coarse

aggregate. (standard concrete) • Grade M30 (30N/mm²) - 1:1.5:3 = 1 part of cement, 1.5 parts of fine aggregate, 3 parts of coarse

aggregate. (standard concrete) - for structures and upper floor

• Grade M35 (35N/mm²) - 1:1.6:2.9 = 1 part of cement, 1.9 parts of fine aggregate, 2.9 parts of coarse aggregate. (standard concrete) - for structures

- Cement (Portland cement) - made from limestone and clay and is generally produced by wet process.- Fine Aggregate - those which will pass a standard 5mm sieve . (Sand)- Coarse Aggregate - those are retained on a standard 5mm sieve. (Gravel, crushed stone)

FOUNDATIONS INA105/151

Stages of work in preparing Pad Foundation

Page 17: Foundations in Building Constuction

FOUNDATIONS INA105/151

CoarseAggregate(gravel)

FineAggregate(sand)

Portland cement

Stages of work in preparing Pad Foundation

Page 18: Foundations in Building Constuction

Stages of work in preparing Pad Foundation

Stage 6: Installation of stumps

FOUNDATIONS INA105/151

The final stage of works in preparing Pad Foundation is installing stumps.

Stump

Page 19: Foundations in Building Constuction

FOUNDATIONS INA105/151

Pad Foundation Is Completed

Stages of work in preparing Pad Foundation

Page 20: Foundations in Building Constuction

Pad Foundation

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Column starter bars

FOUNDATIONS INA105/151

Pad Foundation

Page 21: Foundations in Building Constuction

FOUNDATIONS INA105/151

Pad Foundation

(Shallow Foundation)

Pad Foundation

Stump

Pad Foundation reinforcement bar

Column starter bars

High bearing capacity subsoil

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Page 22: Foundations in Building Constuction

Soil

Starter bars

Reinforced concrete stump

Cross Sectional View(Not to scale)

FOUNDATIONS INA105/151

Pad Foundation (Shallow Foundation)

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Reinforced concrete (Grade M30)

Reinforcement bars 12mm diameter

High bearing capacity subsoil

Reinforced concrete stump

1m to 3mdeep

Ground Level

Page 23: Foundations in Building Constuction

Sand screed 25mm thk.

Floor finishes (tiles)Interior skirting

Soil

Interior part of buildingExterior part of building

Column reinforcement bars

Column

Drain

Plaster

Reinforcement bars 12mm diameter

Skirting

Hardcore

Concrete

Reinforced concrete stump

Concrete (Grade M25) Floor 150mm thk.

Concrete ground Beam (Grade M30)

Cement render

Hardcore 150mm thk.

Pad Foundation & Solid Ground Floor

Cross Sectional View(Not to scale)

FOUNDATIONS INA105/151

Reinforced concrete (Grade M30)

Starter bars

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Apron

High bearing capacity subsoil

Brick wall

Sand blinding 25mm thk.

Damp-proof MembraneGround Level

Page 24: Foundations in Building Constuction

b. Raft Foundations

The principle of any raft foundation is to spread the load over large area, normally the entire area of the structure. It usually consists of a concrete slab which extends over the entire loaded area. It may be stiffened by ribs or beams and floor incorporated into the foundation .This method often needed on soft or loose soils with low bearing capacity as they can spread the loads over larger area.

Raft foundation has the advantage of reducing differential settlements as the concrete slab resists differential movements between loading positions.

Three types of raft foundation:

1.Solid Slab Raft Foundation Solid slabs are constructed of uniform thickness over the whole raft area. This foundation suitable on soft or loose soils with low bearing capacity as it can spread the loads over larger area.

FOUNDATIONS INA105/151

Page 25: Foundations in Building Constuction

2. Beam and Slab Raft Foundation

Beam and slab rafts are an alternative to solid slab raft and are used where poor soils encountered. The beams are used to distribute the column loads over the area of the raft , which usually results in a reduction of the slab thickness. The beams can be upstand or downstand depending upon the bearing capacity of the soil near the surface.

3. Cellular Raft Foundation

This foundation can be used where a reasonable bearing capacity subsoil can only befound at depths where beam and slab techniques become uneconomic. The construction is similar to reinforced concrete basements except that internal walls are used to spread the load over raft and divide the void into cells.

FOUNDATIONS INA105/151

Page 26: Foundations in Building Constuction

1. Solid Slab Raft Foundation

FOUNDATIONS INA105/151

Page 27: Foundations in Building Constuction

2. Beam and Slab Raft Foundation

FOUNDATIONS INA105/151

Page 28: Foundations in Building Constuction

3. Cellular Raft Foundation

FOUNDATIONS INA105/151

Page 29: Foundations in Building Constuction

FOUNDATIONS INA105/151

Beam & Slab Raft Foundation & Ground Floor (Shallow Foundation)

Page 30: Foundations in Building Constuction

FOUNDATIONS INA105/151

Stages of work in preparing Beam & Slab Raft Foundation

Stage 1: Excavation worksStage 2: Installation of FormworksStage 3: Installation of Reinforcement Bars For BeamsStage 4: Installation of Damp Proof Membrane (DPM)Stage 5: Installation of Reinforcement Bars For SlabStage 6: Concreting works

Page 31: Foundations in Building Constuction

Stages of work in preparing Beam & Slab Raft Foundation

Stage 1: Excavation works

FOUNDATIONS INA105/151

The first stage of works in preparing Beam & Slab Raft Foundation is excavation works. Installing pipes for sewage and plumbing are done at this stage.

Page 32: Foundations in Building Constuction

FOUNDATIONS INA105/151

Stages of work in preparing Beam & Slab Raft Foundation

Stage 2: Formworks preparation

The second stage of works in preparing Beam & Slab Raft Foundation is formworks installation.At this stage valley are formed for beams and compacting works are done.

Page 33: Foundations in Building Constuction

FOUNDATIONS INA105/151

Stages of work in preparing Beam & Slab Raft Foundation

Stage 3: Installation of Reinforcement Bars For Beams

The third stage of works in preparing Beam & Slab Raft Foundation is reinforcement bar installation.

Reinforcement bars

Page 34: Foundations in Building Constuction

FOUNDATIONS INA105/151

Stages of work in preparing Beam & Slab Raft Foundation

Stage 4: Installation of Damp Proof Membrane (DPM)

The fourth stage of works in preparing Beam & Slab Raft Foundation is installation of Damp Proof Membrane(DPM)

DPM sheet

Page 35: Foundations in Building Constuction

Stages of work in preparing Beam & Slab Raft Foundation

Stage 5: Installation of Reinforcement Bar For Slab and Starter Bar

FOUNDATIONS INA105/151

The fifth stage of works in preparing Beam & Slab Raft Foundation is installation of reinforcement bars for slab and starter bar after installation of DPM

Slab reinforcement bar

Starter bar

Page 36: Foundations in Building Constuction

FOUNDATIONS INA105/151

5. Concreting

Stages of work in preparing Beam & Slab Raft Foundation

Stage 6: Concreting works

The sixth stage of works in preparing Beam & Slab Raft Foundation is concreting works. The suitable concrete is Grade M25.

Page 37: Foundations in Building Constuction

FOUNDATIONS INA105/151

The Raft Foundation

Stages of work in preparing Beam & Slab Raft Foundation

Page 38: Foundations in Building Constuction

FOUNDATIONS INA105/151

Beam & Slab Raft Foundation

Compacted Hardcore

Beam & Slab Raft Foundation (Grade M25 concrete)

Column starter bars

Low Bearing Capacity Subsoil DPM

Slab Reinforcement bar

Beam Reinforcement bar

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

A

Page 39: Foundations in Building Constuction

Hardcore 150mm thk.

Column starter bars

Reinforced concrete (Grade M25) foundation forming ground floor slab 150mm thk.

Sand Blinding 25mm thk.

Damp-Proof Membrane(DPM)

Slab Reinforcement bars

Beam Reinforcement bars

Beam & Slab Raft Foundation (Shallow Foundation)

Cross Sectional View (Detail A)(Not to scale)

FOUNDATIONS INA105/151

Formwork

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Low bearing capacity subsoilDownstand beam

Page 40: Foundations in Building Constuction

Sand screed 25 mm thk

Floor FinishesSkirting

Cement render

Drain

Low bearing capacity subsoil

Interior part of building

Exterior part of building Column reinforcing bars

Column

Concrete slabHardcore

Hardcore 150mm thk

Plaster Reinforced concrete (Grade M25) forming ground floor slab150mm thk.

Sand Blinding 25mm thk

Damp-proof Membrane(DPM)

Slab Reinforcement bars

Beam Reinforcement bars

Beam & Slab Raft Foundation & Solid Ground Floor

Skirting

Cross Sectional View(Not to scale)

FOUNDATIONS INA105/151

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Apron

Downstand beam

Damp-proof Course(DPC)

Column starter bars

Brick wall

Page 41: Foundations in Building Constuction

c. Strip Foundation

Strip foundation is used to support a line of loads, either due to a load-bearing wall, or if a line of columns need supporting where column positions are so close that individual pad foundations would be inappropriate. This type of foundation is suitable on high bearing capacity subsoil.

FOUNDATIONS INA105/151

Page 42: Foundations in Building Constuction

Stages of work in preparing Strip Foundation

1.Excavation works2.Reinforcement bar preparation3.Concreting

FOUNDATIONS INA105/151

Page 43: Foundations in Building Constuction

Strip Foundation

FOUNDATIONS INA105/151

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Strip Foundation (Grade M30 concrete) To support a line of loads, either due to a load-bearing wall

Page 44: Foundations in Building Constuction

Soil

FOUNDATIONS INA105/151

Strip Foundation (Shallow Foundation) with cavity wall

Cross Sectional View(Not to scale)

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

High bearing capacity subsoil

Reinforced concrete (Grade M30)

Longitudinal reinforcement bars 12mm diameter

Weak concrete filling to base cavity

Damp-proof course (DPC)

Brick Cavity wallInsulation

Ground Level

1m

Page 45: Foundations in Building Constuction

FOUNDATION INA105/151

Strip Foundation with

Cavity Wall

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Weak Concrete filling

Strip Foundation

Insulation

DPC

Cavity Wall

High bearing capacity subsoil

Page 46: Foundations in Building Constuction

Drain

Interior skirting

Floor finishes

Interior part of buildingExterior part of building

Plaster

Concrete floor slab 150mmthk

Cement/sand screed 25mm thk

Damp-proof membrane(DPM)

Concrete slab

Hardcore

Strip Foundation with cavity wall and Solid Ground Floor

Skirting

Hardcore 150mm thk

Sand blinding 25mm thk

Cross Sectional View(Not to scale)

FOUNDATIONS INA105/151

Longitudinal reinforcement bars

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Apron

High bearing Capacity subsoil

Weak concrete filling

Reinforced concrete (Grade M30)

Damp-poof course (DPC)

Cement render

Ground Level

InsulationBrick cavity wall

Page 47: Foundations in Building Constuction

d. Trench-Fill Foundation

Trench -fill foundation is almost similar to strip foundation. Trench-fill foundations can be dug deeper and bigger than strip, which means they are particularly practical where the water table is high, where soil is loose and unstable, and in areas with heavy clay soils. The thickness of any trench -fill foundation should be not less than 500mm and the foundation concrete should finish about 150mm to 100mm below ground level. The trench sides may need to be lined with a slip membrane unless the soil is firm. This type of foundation is suitable on high bearing capacity subsoils.

FOUNDATIONS INA105/151

Page 48: Foundations in Building Constuction

Stages of work in preparing Trench-Fill Foundation

1.Excavation works2.Reinforcement bar preparation3.Concreting

FOUNDATIONS INA105/151

Page 49: Foundations in Building Constuction

Trench-Foundation

FOUNDATIONS INA105/151

Trench-Foundation (Grade M25 concrete) To support a line of loads, either due to a load-bearing wall

Page 50: Foundations in Building Constuction

Soil

FOUNDATIONS INA105/151

Trench-Fill Foundation (Shallow Foundation)

Cross Sectional View(Not to scale)

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

High bearing Capacity subsoil

Reinforced concrete Grade M30

Longitudinal reinforcement bars 12mm diameter

Weak concrete filling to base cavity

Brick Cavity wall

Insulation

Ground Level

1-2mdeep

Damp proof course (DPC)

Page 51: Foundations in Building Constuction

Cavity Wall

FOUNDATION INA105/151

Trench-Fill Foundation with

Cavity Wall

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

DPC

Weak Concrete filling

Insulation

Trench-Fill Foundation

High bearing capacity subsoil

Page 52: Foundations in Building Constuction

2. Deep Foundation

1. Pile Foundation

Pile foundation is a form of foundation using piles to transfer the loads of a structure down to a firm soil stratum with sufficient load-taking capacity. Suitable for multi storey building and on low bearing capacity subsoil.

Materials for piles can be of:

1.Precast concrete2.‘H’ section steel piles3.Metal sheets piles4.Timber or bakau (mangroves) piles5.CISS or Cast-In-Steel-Shell/pipes piles

FOUNDATIONS INA105/151

Page 53: Foundations in Building Constuction

Precast concrete piles

MATERIALS FOR PILING

FOUNDATIONS INA105/151

Precast cylindrical concrete piles

1. Pre-Cast Concrete Pile

Pre-cast or pre-stressed concrete piles are one of the most commonly used concrete piles. Pre-cast concrete piles are typically made with steel reinforcing and pre-stressing tendons to obtain the tensile strength required, to survive handling and driving, and to provide sufficient bending resistance. Long piles can be difficult to handle and transport. Pile joints can be used to join two or more short piles to form one long pile. Pile joints can be used with both precast and pre-stressed concrete piles. Pre-cast concrete piles are driven into the ground and used for deep foundations to support structures in residential houses, commercial construction, such as buildings and bridges. They are also used for: heavy highway, public works, marine, and industrial applications.

Page 54: Foundations in Building Constuction

FOUNDATIONS INA105/151

Pre-Cast Concrete Pile

MATERIALS FOR PILING

Page 55: Foundations in Building Constuction

FOUNDATIONS INA105/151

Pre-Cast Concrete Pile

MATERIALS FOR PILING

Page 56: Foundations in Building Constuction

FOUNDATIONS INA105/151

MATERIALS FOR PILING

Page 57: Foundations in Building Constuction

Steel ‘H’ section piles

FOUNDATIONS INA105/151

2. H-Pile

H- piles are the ideal solution when foundations are required for complex structures or where the ground conditions are difficult. The properties of steel mean that they can be used to resist tensile as well as compressive loads and they can be designed for bending. They are ideally suited to hard driving through difficult ground conditions eg. silty, fine, water bearing sand containing cobles and boulders/ dense sands and gravels/ glacial till and are particularly effective when founded on rock or a similar hard stratum

MATERIALS FOR PILING

Page 58: Foundations in Building Constuction

FOUNDATIONS INA105/151

Steel Sheet piles

3. Metal Sheet Pile

A sheet pile wall is a row of interlocking, vertical pile segments installed to form an essentially straight wall with aplan dimension sufficiently large enough for its behavior to allow for the analysis of a .3048-meter (1 foot) widevertical segment of the wall cross-section. Sheet pile walls are typically used as earth retaining structures alongshorelines to allow for higher exposed grades to occur adjacent to lower river bottoms, dredge or mud lines. Sheetpiling can also be used to retain fill around open landside excavations via rectangular trenches or circularcofferdams.

MATERIALS FOR PILING

Page 59: Foundations in Building Constuction

FOUNDATIONS INA105/151

3. Metal Sheet piles

MATERIALS FOR PILING

Page 60: Foundations in Building Constuction

FOUNDATIONS INA105/151

Metal Sheet Pile

Steel Sheet piles

MATERIALS FOR PILING

Page 61: Foundations in Building Constuction

Bakau piles (mangrove)

FOUNDATIONS INA105/151

4. Timber Pile

The mangrove piles are widely used in peninsular Malaysia for most building and homes. The use of mangrove piles is also recognized in other countries, Malaysia contractors and developers are so confident that the mangrove piles can actually be used for piling in all buildings and homes due to the mangrove wood nature superb density and its wood’s strength.

The mangrove piles are not only cheap, but it is also easy to handle in most pilling during construction work. The buildings which are using mangrove piles as foundation can at least stand for a decades or more than 10 years. The use of mangrove wood in piling brings so much of benefits and advantages. Cheap, Strong Strength, High Density, Long Lasting

MATERIALS FOR PILING

Page 62: Foundations in Building Constuction

FOUNDATIONS INA105/151

CISS or Cast-in-Steel-Shell piles Steel pipes pilesSource: http://www.foundationpiledriving.com/ciss.htm 200px-Metal_tubes_stored_in_a_yard[1]

5. CISS or Cast-in-Steel-Shell piles

MATERIALS FOR PILING

Page 63: Foundations in Building Constuction

TYPES OF PILE CONSTRUCTION

There are two common types of pile construction:

1.Displacement piles

Displacement piles cause the soil to be displaced radially as well as vertically as the pile shaft is driven or jacked into the ground.

2. Non-displacement or replacement piles

Non-displacement, soil is removed and the resulting hole filled with concrete or a precast pile is dropped into the hole and grouted in.

FOUNDATIONS INA105/151

Page 64: Foundations in Building Constuction

Pile is driveninto the soil

1. Displacement pile 2. Non-displacement or Replacement pile

Soil is removedby using boring rig and drillto form a hole

Soil

Ground level

or

Precast pile is dropped into the hole

FOUNDATIONS INA105/151

Bed rock or stratum soil on firm base

Concrete is pored into the steel pipes in the hole to form pile

TYPES OF PILE CONSTRUCTION

Page 65: Foundations in Building Constuction

LOADING SUPPORT TO PILE

Load from a superstructure is transmitted to the subsoil either by:

1.Skin friction - load is supported by the frictional resistance so created between the contact surface of the pile and the embracing soil.

2.End-bearing - load is support by resting onto a firm stratum such as bed-rock or stratum of subsoil with the required bearing capacity.

FOUNDATIONS INA105/151

Page 66: Foundations in Building Constuction

1. Skin friction support

Piles

Loading Support to Pile

Bed rock or stratum soil

on firm base

2. End-bearingsupport

Pile caps

Friction

FOUNDATIONS INA105/151

Ground level

Soil

Friction

Building

Page 67: Foundations in Building Constuction

METHODS OF PILING

Piling methods can be done in several way depending on factors mentioned earlier, they are:

1.Driven piling (Displacement)

Piles are driven into the ground using a pile driver. Driven piles are either wood, reinforced concrete, or steel.

a. Gravity hammerb. Diesel hammerc. Hydraulic hammerd. Vibratory pile drivere. Silent pile hammer

f. Air hammer

FOUNDATIONS INA105/151

Page 68: Foundations in Building Constuction

2. Drilled piling (Non-displacement)

Piling in which boring is done until the hard rock or soft rock layer is

reached in the case of end bearing piles.

a. Caissonsb. Boring rig and auger drillc. Bucket barrel

FOUNDATIONS INA105/151

METHODS OF PILING

Page 69: Foundations in Building Constuction

1. Driven piling (Gravity (Drop) hammer)

FOUNDATIONS INA105/151

Gravity pile for bakau

The drop hammer consists of a heavy ram in between the leads. The ram is lifted up to a certain height and released to drop on the pile. This type is slow and therefore not in common use. It is used in the cases where only a small number of piles are driven.

METHODS OF PILING

Page 70: Foundations in Building Constuction

FOUNDATIONS INA105/151

1. Driven piling (Diesel Hammer)

Diesel hammer piling in action

A modern diesel pile hammer is a very large two-stroke diesel engine. The weight is the piston, and the apparatus which connects to the top of the pile is the cylinder. Piled riving is started by having the weight raised by auxiliary means usually a cable from the crane holding the pile driver — which draws air into the cylinder. The weight is dropped, using a quick-release. The weight of the piston compresses the air, heating it to the ignition point of diesel fuel. Diesel fuel is added/injected into the cylinder. The mixture ignites, transferring the energy of the falling weight to the pile head, and driving the weight back up.

METHODS OF PILING

Page 71: Foundations in Building Constuction

1. Driven piling (Hydraulic Hammer)

Hydraulic hammer piling in action

FOUNDATIONS INA105/151

A hydraulic hammer is a modern type of piling hammer used in place of diesel and air hammers for driving steel pipe precast concrete, and timber piles. Hydraulic hammers are more environmentally acceptable than the older, less efficient hammers as they generate less noise and pollutants. However, in many cases the dominant noise is caused by the impact of the hammer on the pile, or the impacts between components of the hammer, so that the resulting noise level can be very similar to diesel hammers.

METHODS OF PILING

Page 72: Foundations in Building Constuction

Vibratory pile driver in action

FOUNDATIONS INA105/151

1. Driven piling (Vibratory Pile Driver)

Vibratory pile hammers contain a system of counter-rotating eccentric weights, powered by hydraulic motors, and designed in such a way that horizontal vibrations cancel out, while vertical vibrations are transmitted into the pile. Vibratory hammers can either drive in or extract a pile; extraction is commonly used to recover steel "H" piles used in temporary foundation shoring.

METHODS OF PILING

Page 73: Foundations in Building Constuction

1. Driven piling (Silent Pile Driver)

Silent pile driver in action

FOUNDATIONS INA105/151

The Silent Piler is a hydraulic machine for vibration-free installation or extraction of sheet piles. The machine operates by gripping previously driven piles to provide reaction force for pressing in the next pile. The Silent Piler works on top of the reaction piles and self-moves to the next position as illustrated in the adjacent picture. This technique allows pile driving at sites which are not accessible for conventional piling techniques. Only a relatively light-weight service crane is needed to pitch the sheet piles.

METHODS OF PILING

Page 74: Foundations in Building Constuction

FOUNDATIONS INA105/151

1. Driven piling (Air Hammer)

Air hammer pile in action

Very basic hammer design, impact based with a rapid blow action and air powered . Less affected by ground type, typically used to finish drive to depth, if not for the full drive. Can be handled by an excavator. Will drive sheets into virtually all ground conditions.

METHODS OF PILING

Page 75: Foundations in Building Constuction

FOUNDATIONS INA105/151

2. Drilled piling (Caissons)

Caissons pile driling in progress

A caisson is a retaining structure that is normally water tight that is used to allow construction work to be undertaken under dry conditions below the water table (including below the surface of a river or lake). Examples of when a caisson might be used include on a river bed during the construction of bridge pillars and foundations, or during the construction of a shaft. A pile is a type of deep foundation which usually extends to a significant depth in the ground compared to it's cross sectional area. Piles may be either driven or cast in place. 

METHODS OF PILING

Page 76: Foundations in Building Constuction

2. Drilled piling (Boring Rig and Auger Drill)

Boring rig and auger drilling in progress

FOUNDATIONS INA105/151

This piling method is ideal for use in cohesive soils. The rotating auger screws into the strata reaming out the soil. Once the required depth has been achieved the steel cage and concrete is placed. These highly mobile rigs are economic to use on large open sites with cohesive ground, and on some chalk or sand, which have good access. Smaller models are suitable for internal use. As a rotary auger causes minimal vibration it is ideal for use next to buildings or underground services

METHODS OF PILING

Page 77: Foundations in Building Constuction

2. Drilled piling (Bucket Barrel)

Bucket barrel drilling in action

FOUNDATIONS INA105/151

METHODS OF PILING

Page 78: Foundations in Building Constuction

Stages of work in preparing Deep Foundation

Stage 1: Piling worksStage 2: Excavation and pile cutting worksStage 3: Preparation and fabrication of reinforcement for pile capStage 4: Preparation of pile cap formworkStage 5: Installation of pile cap reinforcement bar and starter bar Stage 6: Concreting worksStage 7: Installation of stumps

FOUNDATIONS INA105/151

Page 79: Foundations in Building Constuction

FOUNDATIONS INA105/151

Stages of work in preparing Deep Foundation

Stage 1: Piling works

Point for piling

The first stage of works in preparing Deep Foundation is piling works that involve 1. Points setting. 2. Piling 3. Piling Jointing (where more piles are required).

Page 80: Foundations in Building Constuction

FOUNDATIONS INA105/151

Jointing the pile coupling end plates

Welding the end plates

Stages of work in preparing Deep FoundationStage 1: Piling works

Page 81: Foundations in Building Constuction

Stages of work in preparing Deep Foundation

Stage 2: Excavation and pile cutting works

FOUNDATIONS INA105/151

Concrete piles

The second stage of works in preparing Deep Foundation is excavation and pile cutting works. Backhoe loader is needed to excavate the soil and hydraulic pile cutter is required to cut the piles.

Page 82: Foundations in Building Constuction

Pile cutting in action

FOUNDATIONS INA105/151

Stages of work in preparing Deep Foundation

Stage 2: Excavation and pile cutting works

Hydraulic pile cutter

Concrete piles

Page 83: Foundations in Building Constuction

Stages of work in preparing Deep Foundation

Stage 3: Preparation & Fabrication of reinforcement bar for pile cap

FOUNDATIONS INA105/151

Pile Cap reinforcement bar

The third stage of works in preparing Deep Foundation is preparing and fabricating reinforcement bar for pile cap..

Page 84: Foundations in Building Constuction

Stages of work in preparing Deep Foundation

Stage 4: Preparation of formworks for pile cap

FOUNDATIONS INA105/151

Formwork

The fourth stage of works in preparing Deep Foundation is preparing formworks for pile cap

Page 85: Foundations in Building Constuction

Stages of work in preparing Deep Foundation

Stage 5: Installing pile cap reinforcement & starter bars in formworks

FOUNDATIONS INA105/151

The fifth stage of works in preparing Deep Foundation is installing pile cap reinforcement & starter bars in formworks.

Pile Cap reinforcement bar

Starter bar

Page 86: Foundations in Building Constuction

Stages of work in preparing Deep Foundation

Stage 6: Concreting works

FOUNDATIONS INA105/151

The sixth stage of works in preparing Deep Foundation is concreting. The suitable concrete is Grade M30.

Page 87: Foundations in Building Constuction

FOUNDATIONS INA105/151

Pile Caps

Stages of work in preparing Deep Foundation

Stage 6: Concreting works

Page 88: Foundations in Building Constuction

FOUNDATIONS INA105/151

Stages of work in preparing Deep Foundation

Stage 7: Installation of stumps

StumpPile Cap Starter bar

The final stage of works in preparing Deep Foundation is installing the stumps.

Page 89: Foundations in Building Constuction

FOUNDATIONS INA105/151

Deep /Pile FoundationDeep foundation is completed and ready for ground beams works

Deep FoundationsStarter bar

Page 90: Foundations in Building Constuction

Pile Foundation

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Piles

Piles Cap

Column starter bar

FOUNDATIONS INA105/151

Page 91: Foundations in Building Constuction

FOUNDATIONS INA105/151

Pile Foundation

(Deep Foundation)

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Low bearing capacity subsoil

Pile CapPile

Stump

Pile Cap reinforcement bar

Column starter bar

Page 92: Foundations in Building Constuction

Soil

Cross Sectional View(Not to scale)

Pile Foundation (Deep Foundation)

FOUNDATIONS INA105/151

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Low bearing capacity subsoil

Piles

Reinforced concrete stump

Reinforced concrete pile cap (Grade M30)

Reinforcement bars 12mm diameter

Pile Cap

1m to 3mdeep

Starter bar

Ground Level

Page 93: Foundations in Building Constuction

Pile Foundation & Suspended Ground Floor

SkirtingSand screed 25mm

Floor finishes (tiles)

Damp-proof Membrane

Cement render

Drain

Reinforcement bars 12mm diameter

Interior part of building

Hardcore 150mm thk.

Column

Columnreinforcement bars

Sand blinding 25mm

Piles

Floor reinforcement bars 10mm diameter

Reinforced concrete (Grade M25) ground floor slab 150mm thk.

Reinforced concrete stump

Starter bars

Skirting

Concrete Ground Beam (Grade M30)

Ground beam reinforcement bars

Cross Sectional View(Not to scale)

FOUNDATIONS INA105/151

Note: Graphic symbols illustrated are not to architectural standard symbols. Students are advised to refer to the building construction books for proper symbols available at the library.

Apron

Exterior part of building

Low bearing capacity subsoil

Plaster

ConcreteHardcore

Damp-proof Course

Concrete pile cap (Grade M30 )

Ground Level

Page 94: Foundations in Building Constuction

References:

1. Ivor H. Seeley (1995):Building Technology. Fifth edition. MacMillan.

2. Roland Ashcroft (1992); ConstructionFor Interior Designers. Second Edition. Longman.

3. Roger Greeno (1998):Advanced Construction Technology.

FOUNDATIONS INA105/151

Page 95: Foundations in Building Constuction

THE END

FOUNDATIONS INA105/151