FOTH Hudad Projects Overview and Status...leaks, digging them up, and fixing them This is a...
Transcript of FOTH Hudad Projects Overview and Status...leaks, digging them up, and fixing them This is a...
FOTH Hudad ProjectsOverview and Status
May 2018
Ethiopia, located in the Horn of Africa, is a landlocked country of ~ 110 million
people. It is split by the Great Rift Valley and contains the headwaters of the Nile
river. With archaeological finds dating back more than 3 million years, it is a place of
ancient history and culture. Among its most important sites is Lalibela with the
ancient, hewn from rock, Christian churches of the 12th and 13th centuries.
Lalibela is a town of about 20,000 people in the Wollo zone of the Amhara region in
Northern Ethiopia. It is located at an altitude of ~ 2600 meters or 8500 feet and
the population is primarily Amharic speaking Ethiopian Orthodox Christian
Lalibela is a couple of hours walking downhill in this
direction…roughly Southwest and 2500 feet lower
Most of the villages and people being
served are scattered uphill along this trail
Eco-lodge guest house or Tukul.
Trekking tourists and FOTH workers
stay here
Eco-lodge main building and kitchen. We eat, socialize, and
generally enjoy hanging out here
Approximate site of school classroom and community buildings
This entire area is for Community Development
– school, water points, toilet block teachers
residences, gardens, etc.. This portion of the plateau
is at ~3300 meters or 10,800 feet elevation
Location of “School Reservoir” and gravity
feed pipeline to the school
School Building
May 2018
All the concrete and mortar is mixed on site by hand. Water, sand, and cement
are all hauled to the site by either donkeys or people
White and pink stone for the walls is quarried from
the ground nearby
Black stone for the foundations is hauled
mostly by the school kids from nearby locations
Getting the foundation dug and the stone and concrete
in place is back-breaking work
Walls continue to rise as tons of material are
transported, mixed, lifted, placed, and finished
Brick by brick was the motto of the Aussie and Brummie led masonry team
A couple of weeks of really hard labor and the team
works its way up to scaffolding, window, and
finally full wall height
Our “window” team came up with a really cool design to let lots of light into the school. They
built the frames, purchased the shatter resistant plastic, and assembled them in the US. The design allowed for the windows to be dis-assembled for transport to the Hudad and re-
assembled and installed there.
Roof trusses are built using locally harvested eucalyptus
poles. Plywood used for strength at the joints was hauled up the mountain
from Lalibela
Roof trusses were heavy and took a lot of folks to
place them up on top of the walls
Status at the end of Oct 2017 trip
Roof purlins and plywood sheathing installation
underway in May 2018
Spacers going on top of the plywood and metal
sheathing being finished up
Finished eave view and opening window installation
~20 simple 2-3 children metal and wooden desks
were built at the industrial arts training school in
Lalibela and hauled up to the School by community
members
Most of the May 2018 “foreigners” with the completed and occupied school
Here are some video links to School Construction Videos
Quarrying rock locally
Mortar mixing
Wall building
Truss construction
Roofing
Tour of the School inside
Toilet Block Construction
May 2018
Jennifer created this sketch of the toilet block and it was a wonderful tool to
communicate with the local people about various design elements. It is divided down the middle for male and female and has a privacy screening wall and outside hand
washing stations
This is during the initial layout of the toilet block. The guy in the red coveralls is the
local stone mason.
This is the point that was reached at the end of the May 2018 trip. The screening wall is
complete, the hand washing faucets are installed, and the pits for the composting
toilets are well underway.
Water System
May 2018
Currently most all of the families on the plateau obtain their water from
“undeveloped” springs. These springs flow from the ground. Typically the water is dipped out with a small container and
transferred to a “jerry” can. Animals can step in it and foul it with waste.
Prior water supply situation
Hauling water is Women’s work and in this case they are hauling the 20 liter jugs to the school construction site to produce concrete and mortar
Hauling beer for the Eco-lodge is apparently Men’s work
• #1 – Three springs and 25,000 liter or 6500 gallon upper reservoir
• #2 – 63mm or 2.5 inch water transfer pipe – 2.5 kms or 1.5 miles long
• #3 – Lower or “School” reservoir
• #4 – School and Community water stations
FOTH Water System Overview
25,000 liter masonry reservoir with mounting provisions for
solar panel array
One of three adjacent capped springs feeding into the upper reservoir
This dam and capping structure was built to retain the water running out
of the cliff, protect it from contamination, and provide a way to
channel it to the reservoir
Reservoir inlet pipe
Spring #1Spring #2
Spring #3
This “stock trough” provides access for local people and their
animals right below the reservoir. Turning the valve will
provide a great deal of water quickly
Reservoir drain and stock trough
Solar Installation Construction Photos – Oct 2017
Solar array is 8” X 24” - 16 panels at full power deliver maximum 2580 watts at 280 volts
Solar Controller & Wiring
Pump mount to secure in place
Power wire to solar controller
Pump inlet is above floor to prevent the intake of
sediment and debris
Tank level sensor that is wired to the
controller
Inside the upper reservoir with pump
installation
100 meter rolls of pipe being unrolled
and installed
Hand dug 2.5 km trench
Pipe from the upper reservoir
Reservoir inlet
This 25,000 liter or 6600 gallon reservoir sits above the school on the hill side and provides gravity pressure water
Outlet pipe with valve and strainer that
supplies the school site through the distribution
vault
Individual line valves
63mm main line
This plumbing vault was built to contain and protect the distribution valves and meters. It has a lockable steel cover and allows for water to be sent to the gardens, toilets, community water point, and any other future expansion. Community water monitors have the responsibility to record readings on a regular basis
Individual line meters
25mm supply lines
Telltale wet ground where the pump pressurized the
pipeline causing it to leak
The biggest challenge on the water system for the last trip was finding all the leaks in the pipeline. We worked for about 4-5 days doing nothing but finding
leaks, digging them up, and fixing them
This is a accidental pick-axe puncture where the pipe was to shallow as it passed through a
barley field that was hand plowed with a pick-axe
This is poor workmanship from the
contractor that was hired to help with the pipeline installation a couple of years ago
Conrad found this poorly installed joiner
in the pipeline that allowed the Eucalyptus
roots to encroach while seeking water
Here are some video links to Water System Videos
Pipe repair
First water pumped by solar power to the school reservoir
First water to flow at the school site
Kids playing with water
Longer water system description video