Historical Oil Spill Averages For Oct - Feb Time PeriodActual (gallons) Potential (gallons) Federalized Cases Total Number of cases Oct11-Feb123913, Oct12-Feb Oct13-Feb145.51,79207 Oct14-Feb

Transcript of FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

Page 1: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

FOSC Prince William SoundJanuary 2015

CDR J. T. Lally CG Marine Safety Unit Valdez

Page 2: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

COTP Prince William Sound October 2014 – February 2015 Incident Summary

Total Incidents: 7 actual & 3 potential

Amount Discharged: 17.5 gallons

Total Potential: 200 gallons

OSLTF Supported: 0

Page 3: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

Historical Oil Spill Averages For Oct - Feb

Time Period Actual (gallons)

Potential (gallons)

Federalized Cases

Total Number of cases

Oct11-Feb12 391 3,720 1 11Oct12-Feb13 58 965 0 11Oct13-Feb14 5.5 1,792 0 7Oct14-Feb15 22.5 200 0 10

Page 4: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

Planning Efforts

Outreach

Community Response Concept

Active Participation and Integration Training Exercises & Drills Partnerships

Page 5: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

PWS Subarea Contingency Plan

Letter of Promulgation Signed OCT 2014

Project Proposals

Approved GRS Project

Page 6: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

Prince William Sound Subarea Committee

PWSACP revision comment matrix (ADEC website)

Next Meeting: March 5, 2015

Tribal Consultation

BP Exercise Response Community Concept

Page 7: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

Vital ARRT Support2015 BP Tanker Exercise

28-30SEP (Monday to Wednesday) Full scale exercise (IMT only) Crude oil tanker incident Critical need for ARRT active participation Critical need for ARRT liaison at exercise

Page 8: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

Training & Exercises Tribal Consultation Training: March 4, 2015

Response Community Training: March 12, 2015

VMT Terminal Drill: March 13, 2015

ICS300a Training: August 10-14, 2015

Response Community Training: September 28, 2015

BP Tanker Full Scale Exercise: September 29-30, 2015

Page 9: FOSC Prince William Sound January 2015 CDR J. T. Lally CG Marine Safety Unit Valdez.

QUESTIONS?