Formulas Must

download Formulas Must

of 9

Transcript of Formulas Must

  • 8/12/2019 Formulas Must

    1/9

    Earned Value Management

    EV = BAC * % complete

    EV = PV * % complete (any point during project execution)

    EV=BCWP (budgeted cost of work performed)

    PV=BCWS (budgeted cost of work scheduled)

    AC=ACWP (actual cost of work performed)

    SV = EV-PV > 0 is good

    SPI = EV/PV > 1 is ahead of schedule

    CV = EV-AC > 0 is good

    CPI = EV/AC > 1 is under budget

    PV = SV/(SPI-1)

    AC = CV/(CPI-1)

    EAC = AC+bottom-up ETC : when initial estimates are flawed

    EAC = AC+(BAC-EV) : when ETC is predicted to be done at budgeted rate (ATYPICAL)

    EAC = BAC/CPI : when ETC is expected at current CPI (typical)

    EAC = AC+(BAC-EV)/(SPI*CPI) : at current SPI, CPI

    EAC=BAC-CV ?

    EAC = AC/%Complete

    ETC = EACAC :assuming work goes as per plan

    ETC = BACEV

    VAC = BACEAC

    %VAC = VAC/BAC * 100

    TCPI = (BAC-EV)/(BAC-AC) : accepting BAC value

    TCPI = work remaining/funds remaining

    TCPI = (BAC-EV)/(EAC-AC) : when BAC is not sufficient and EAC is calculatedTCPI > 1 is bad

    -

    Expected Monitory value: EMV=Impact*Probability

    -

    Communication channels = N*(N-1)/2

  • 8/12/2019 Formulas Must

    2/9

    7% of communication message is contained in words

    38% in vocal pitch

    55% in body language

    Albert Mehrabians book Silent Message

    -

    TEAM stagesTuckman (Jensen) Ladder

    forming

    storming

    norming

    performing

    adjourning

    Future value & Present value

    -

    FV = PV (1+r)^N : r=rate of interest, N=number of time periods

    PV = FV/(1+r)^N

    NPV : higher the better

    NPV > 0 investment will add value, accept the project

    Internal rate of return, IRR : Bigger the better

    Benefit Cost Ration, BCR : Bigger the better

    Payback period: Lesser the better : This is nothing but Breakeven period

    Payback period=Net investment/Avg annual cash flow

    -

    Probability distribution

    PERT: Normal: (O+M*4+P)/6

    Triangular: (O+M+P)/3

    SD of activity = (P-O)/6

    Variance of activity = [SD]squared

    -Float/Slack/total slack = LS-ES = LF-EF : =0 for activities on critical path

    -

    Cost Of Quality, COQ = EFTW+COPQ = POC+PONC

    Essential first time work

    Cost of poor quality

  • 8/12/2019 Formulas Must

    3/9

    Price of Conformance

    Price of non-conformance

    -

    Depreciation/Straight-line depreciation = Asset cost/Useful life

    Double declining balance = 2x((Asset costAccumulated depreciation)/Useful life)

    -

    Rough Order of Magnitude (ROM) -25% to +75%

    Budget Estimate -10% to +25%

    DefinitiveEstimates -5% to +10%

    -

    Remember, RETURN = Net Income Before Tax (NIBT) *or* Net Income After Tax

    (NIAT); & ON means /

    Return on Sales, ROS = NI*T/Total Sales

    Return on Assets, ROA = NI*T/Total Assets

    Retrun on Investment, ROI = NI*T/Total Investment

    Working Capital = Current AssetsCurrent Liabilities

    Discounted cashflow = Cashflow * Discount factor

    -

    Contract related formulas

    -

    Savings = Target costActual cost

    Bonus = Savings*Percentage

    Contract cost = Bonus+Fees

    Total cost = Actual cost + Contract cost

    -

    Point of total assumption

    PTA = [(Ceiling Price - Target Price)/Buyer's Share Ratio] + Target Cost

    Cost to buy = Initial cost + [#months * (monthly maintenance costs)]lifecycle cost = total cost + maintenance and support cost for lifetime of product

    -

    Normal Distribution

    -

    1 sigma = 68.26%

  • 8/12/2019 Formulas Must

    4/9

    2 sigma = 95.46%

    3 sigma = 99.73%

    6 sigma = 99.999%

    1 SD = 1 sigma

    -

    What Five Strategic Considerations may result in authorization of a project?

    (MOCkTaiLSMOCTLS)

    Market demand

    Organizational need

    Customer request

    Technological advances

    Legal requirements

    Social need

    -

    EVA = Net Operating Profit After TaxCost of Capital (RevenueOp. ExpTaxes)

    (Investment Capital X % Cost of Capital)

    EVA: Economic Value Add Benefit MeasurementBigger is better

    Source Selection = (Weightage X Price) + (Weightage X Quality)

    -

    Types of powers of PM:

    Legitimate

    Reward

    Expert

    Referent

    Coersive/Punishment

    -

    Motivational theories

    Hertzbergs highgyene-motivationMaslows hierarchy of needs

    McGregor Theory X, Y; / Z(assurance of permanent job position)

    McClellands Need Theory

    Victor Vroom Expectance theory

  • 8/12/2019 Formulas Must

    5/9

    Peter Principle=Halo effect

    range of variance on a budgetary estimate can be from -10% to +25%.

    Paul Hersey/Ken blanchards Situational continuum/leadership

    change leadership style based on maturity of subbordinates/team.

    S1: Telling; S2: Selling; S3: Participating; S4: Delegating;

    system testing vs integration testing

    Seven Quality Mgmt and Control tools(NP, MAP IT)

    Network diagram

    PDPC

    Matrix diagram

    Affinity diagram

    Prioritization Metrics

    Interrelationship digraphs

    Tree diagram

    7 Basic Quality Tools (See See See, Husband and Father Playing Soccer)

    Check sheet

    Control chart

    Cause-and-effect diagram

    Histogram

    Flow chart

    Pareto chart

    Scatter diagram

    type II errorbeta riskACTIVITY ON ARROW/arrow diagramming method

    McKinseys 7Ss - Robert H. Waterman, Jr. and Tom Peters

    Hard Elements

    Strategy

  • 8/12/2019 Formulas Must

    6/9

    Structure

    Systems

    Soft Elements

    Shared Values

    Skills

    Style

    Staff

    7 reasons of conflicts on projects

    -

    schedule

    project priorities

    human resources

    technical opinions and performance trade-offs

    administrative procedures

    persnality conflict

    cost and budget

    Conflict management style

    -

    withdraw/avoid

    compromise

    smoothen/accomodate

    collaborating

    confront/problem solving

    force

    Collaborating: win/win;

    Compromising: win some/lose some; >> lose/lose

    Accommodating: lose/win;

    Competing: win/lose;

    Avoiding: no winners/no losersTest of Normality

    Paired Comparison Analysis

    opm3

    managemet by objective

    capability maturity model

  • 8/12/2019 Formulas Must

    7/9

    tqm

    Merrill and Reid in their employee motivation theory?

    personality traits: driver, expressive, amiable, and analytical.

    Joseph Juran:applied the Pareto principle to quality issues

    Jurans Trilogy: quality planning, quality control, and quality improvement.

    W. Edwards Deming

    PDCAalong with Shewart

    Philips CrosbyDIRFT (4 principles)

    The definition of quality is conformance to requirements (requirements meaning both

    the product and the customers requirements)

    The system of quality is prevention

    The performance standard is zero defects (relative to requirements)

    The measurement of quality is the price of nonconformance

    Vilfredo Federico Damaso Pareto

    80-20 principle

    Kaoru Ishikawa

    root-cause diagram: fishbone

    KJ Diagram ()

    William Ouchi (jap)

    Theory Z, permament job offer

    Genichi Taguchi

    Design of experiments

    F.C. Moore

    Delegation means assigning work to the others and giving them authority to do so

    Overlapping relationship

    Sequential relationship

    Multi-phase relationship

    Iterative relationshipPredictive/plan-driven

    Iterative and Incremental

    Adaptive/Agile

    NPV is defined as: The difference between the present value of cash inflows and the

    present value of cash outflows.

  • 8/12/2019 Formulas Must

    8/9

    critical chain methd by Eliyahu M. Goldratt

    The critical path method (CPM) is a project modeling technique developed in the late

    1950s by Morgan R. Walker (of DuPont) and James E. Kelley

    Parkinsons law is the adage which states that work expands so as to fill the time

    available for its completion.

    Students syndrom work is done at the last moment before deadline

    Group decision making criteria (BINAM)

    Brainstorming

    Idea/mind mapping

    Nominal technique

    Affinity diagrams

    Multi-criteria decision analysis

    Failure mode and effect analysisFMEA

    QFDquality function deployment (type of Facilitated workshops)

    Discrete, Apportioned, Level of EffortEMV effort types

    marginal analysis

    lifecycle costing

    demings 14 points?

    ARMA>

    zero sum processing

    issue log

    shannon-weaver model of communication

    code of ethics: Respect, Responsibility, Honesty, Fairness >>>> Aspirational and

    Mandatory

    direct, indirect, fixed, variable costs

    Thats about it. It may look a long one, but when you write one for yourself it certainly

    doesnt feel long. And moreover you write even tersely on paper. The only thing to keep

  • 8/12/2019 Formulas Must

    9/9

    in mind is to practice the brain-dump couple of times daily in the last week leading up to

    your actual PMP exam. The more you practice, the easier it is to write on paper in

    shortest time, and more confident you will feel during the exam!

    So, thats a secret to feel good and do good during the exam!

    If you need any help with your PMP preparation do not hesitate to write to me at shiv-at-

    pmexamsmartnotes-dot-com