USEAct Thematic Network I Urban sustainable environmental actions
USEAct CASE STUDIES Catalogue
FORMER BREWERY REGENERATION
USEACT CASE STUDY
Municipality of Nitra, Slovakia
Theme 2: Interventions to “reuse” urban areas:
management, partnerships, funding, functions.
Subtheme 2.2: Improving public administration ability on
controlling and managing “high quality” and “sustainable”
reuse interventions.
Summary abstract
The Former brewery area creates important part of the City identity. The beer, which was brewed in
Nitra, carries the name of Corgoň, according the Corgoň statue in the Upper City, one of the most
famous landmarks in Nitra. Even when in 2004 the beer production was moved to Hurbanovo brewery,
the mark is still identified with Nitra all across the Slovakia. In 2007 the intent of the new owner
concerning the site regeneration was announced. Because of the site location in the Centrum of the City
and its scale as well, the project was under the strict scrutiny of managing authorities in Nitra. The
designs were evaluated from the point of view of the General plan regulative, quality of architecture
and public spaces, traffic solutions and capacities, accessibility and surrounding urban structure
synchronization.
Very challenging was the goal of regenerating some original structures of the brewery /Malt house,
Heating facility, 2 historical villas/. All the structures of the brewery were evaluated also of their
historical values and qualities, technical conditions and the results were the main arguments in process
of decision, which structures should be rescued and regenerated, and which ones are beyond help,
should be raised down and the new ones should take their place.
Setting and Key
questions/Challenges
max 3.000
characters (spaces
included.
Please note: a
summary table/chart-
flow providing a
visual summary of
the issues is
welcomed.
Characters of the
“summary flow-
char/table” have not
to be counted
BASIC REGENERATION STRATEGY OF THE FORMER BREWERY :
The selected area lays within the borders of the former brewery facility in Nitra,
neighboring the complex of the Nitra hospital, historical villas and the main
road connecting the city to the southern part of the country. The site has a mild
altitude, no more than 6m facing the City Centre. The General plan of Nitra
regulate the area by the function of public services and housing in the southern
part of the area /Špitálska str./. Recently, the former brewery is owned by 1
owner, the fact has a positive influence on the flexibility of design and
construction process as such. According to the owner’s intents, the site is
nowadays regenerated, some original structures will be reused as a
multifunctional facilities including hotel, retail and leisure services, newly
designed structures will be used for commerce and housing capacities. The site
is under construction, some new building being raised during the 2013.
Main goals:
Creating of the new attractive area as the portal to the City
Maximum efficiency by using the site potential by respecting the character
of surrounding areas
Using the access to the train and bus station in the vicinity of the site
Perceptive reuse of the original structures and their regeneration in the
project /Malt house, Heating facility, 2 villas/
Synchronization of the design with the surrounding area and the technical
infrastructure
Variability in the realization of the design
Optimal disposition of the site concerning the sun trajectory
The quality of design towards the contemporary architecture is highly
stressed
Creation of the quality full micro scale public spaces, strict respect of the
urban composition rules
Esthetical and artistic tools used with common sense in the design
Applying the modern environmental approach in order to achieve healthy
nature like environment for the commoners.
Procedures and
actions
max 7.000
characters (spaces
included,
Please note: a
summary table/flow-
chart providing a
visual summary of
the issues is
welcomed.
Characters of the
“summary chart-
flow/table” have not
to be counted
Former military barracks in Nitra - Basic facts:
total area 4,9ha
Building area 15 556m2 /31,75%/
Floor area 97 355m2
Max. Construction height 24m /165,8m asl./
Greenery area 16 081m2 /32,82%/
Communications and solid areas 17 244m2 /35,20%/
Timeline:
1896 origins of the brewery
1920 wider offer of beers brewed in Nitra
1926 close-up due to the economical issues
1949 re-opening of the brewery
1992 private owner /reconstruction, modern technologies = increase of
production by 89%, 5. Largest brewery in Slovakia/
1997 brewery sold to Heineken corp.
2004 production moved to Hurbanovo, just administration left in Nitra.
2007 the announcement of the site regeneration project
2013 first structures were constructed
Main stakeholders:
Real invest assets, ltd. /investor/
City of Nitra, local managing authority
Architects and designers /GFI Studio, s.r.o., AAKH, s.r.o., Barak Architekti,
s.r.o., Nonconform architektur, s.r.o./
Local and regional authorities /Building permission process/
Inpek, s.r.o /construction enterprise/
Issues and challenges:
New functional use of the site /reutilization of historical buildings, public
spaces quality increase, commerce, leisure, housing.../
Reuse of the former structures, design of the new structures, urban growth
management
Agreement among the stakeholders, supervising of the project from the
point of General plan regulative.
Traffic solutions /concept, connections, capacities.../
Monument structures and historical values preservation, reuse of some
original structures
Greenery areas regeneration and preservation, evaluation of the necessary
cutting, new tree and shrubs planting quotas
Technical infrastructure reconstruction.
Urban and spatial regulative of the site /how, where, what.../.
Lessons learned and
utility
max 3.000
characters (spaces
include)
Please note: a
summary table/flow-
chart providing a
visual summary of
the issues is
welcomed.
Characters of the
“summary chart-
flow/table” have not
to be counted
The Former brewery area project is the example of the regeneration of the
Brownfield in the Centrum of the City, where the approach to the new design of
the place is perceptive, and offers the ways, how to regenerate the site by
keeping the quality full original structures and adding the new value of the
urban regeneration. The tools to achieve the goal putting aside the new
modern design of the site are the simple owners structure /the facility being
owned by 1 owner/ and the regular standard cooperation with the local
managing authorities. In the Building permission process the project was
evaluated firstly in the phase of Urban feasibility study, where all the important
aspects /General plan regulative, Historical structures preservation,
architecture, technical infrastructure, traffic solutions, greenery…/ could be
annotated by the professionals of the Municipal office and other public
managing authorities /Regional Monument board office, Local Environmental
office…/.
By acceptance of the regulative from the investor and designers the following
communication with the authorities, working out the next stages of the project
and finally obtaining the Building permission was smoother, comparing to the
other struggles, held by different stubborn investors elsewhere in the city.
Lesson learned: Communication between the investor and the managing
authority is the key to the successful regeneration of the abandoned urban
areas.
Bibliographic and
further sources
a) Bibliographic sources /web-sites
http://www.novanitra.sk/content/view/39/2/
b) Contacts/interviews
Name/Surname: Ing. Peter Malecký, Project Manager
Role in the USEAct Project: -
e-mail: [email protected]
tel. /mob. : +421 (37) 651 3888
Enclosed Pictures
Picture n. 1: Original picture of the brewery /round 1920/
Picture n. 2: Complex design of regeneration of the site /team of architects, 2007/