FORM 1 APPENDIX I (See Paragraph-6) S. No Item...
Transcript of FORM 1 APPENDIX I (See Paragraph-6) S. No Item...
1
FORM – 1
APPENDIX – I
(See Paragraph-6)
(I) Basic Information
S. No Item Details
1 Name of the Project /s Integrated Common Hazardous Waste
Treatment, Storage, Disposal and
Recycling Facilities at Industrial Growth
Centre, Phase-II, Samba. Mandhera
Village, Samba Tehsil, Samba District.
J&K.
2 S.No. in the Schedule Common hazardous waste treatment, storage and disposal facilities (TSDFs). Item 7(d) of the schedule of EIA
notification of Sept 14, 2006 issued by
MOEF.
3 Proposed capacity / area / length /
tonnage to be handled /command area /
lease area / number of wells to be drilled
The Proposed treatment facilities at the
site are:
Phase-I Secured Landfill : 68 TPD
Treatment/
Stabilization
: 41 TPD
Bio Medical Waste : 2 TPD
E- Waste : 55 TPD
Spent Solvent
Recycling
: 9 KLD
Phase-II
Incineration : 27 TPD
Secondary Lead
Recycling
: 11 TPD
Used oil recycling : 6 KLD
Alternate Fuel &Raw
Material Facility
: 14TPD
4 New / Expansion / Modernization Proposed facility
5 Existing Capacity / Area etc. Nil. 8 acres allotted at Industrial growth
Centre, Phase-II, Samba. Mandhera
village, Samba tehsil, Samba district.
J&K.
6 Category of Project i.e. „A‟ or „B‟ Category „A‟
Common hazardous waste treatment,
storage and disposal facilities (TSDFs).
Project site is located around 9.0km away
from India-Pakistan international
boundary.
2
7 Does it attract the general conditions? If
yes, please specify
Yes
The international boundary of India-
Pakistan International boundary is
located at a distance of about 9.0km
towards south from the site.
8 Does it attract the Specific conditions? If
yes, please specify
No
9 Location Site is located at 32033‟16” North and
75006‟85” East. Average elevation is
374m above MSL.
Location map of the site attached in
Annexure-1 and 10km radius map
attached in Annexure-2.
Plot / Survey / Khasra No 8 acres, Industrial Growth Centre, Phase-
II, Samba. Mandhera village, Samba
Tehsil, Samba district. J&K.
Village Mandhera village
Tehsil Samba Teshsil
District Samba District,
State Jammu and Kashmir.
10 Nearest railway station / airport along
with distance in kms
Samba railway station-5km, South East.
11 Nearest town, city, district headquarters
along with distance in kms.
Samba town-2.0km-Northeast.
12 Village Panchayats, Zilla Parishad,
Municipal Corporation, Local body
(complete postal addresses with
telephone nos, to be given).
Industrial Growth Centre, Phase-II,
Samba. Mandhera village, Samba Tehsil,
Samba district. J&K.
13 Name of the applicant Mr. Ravi Chandra
Manager
Ramasethu Infrastructure Private Limited,
No. 4-4-1/3, Y V Rao Estate, Jakkampudi,
Near CNG Gas Bunk, Vijayawada,
Andhra Pradesh – 520012
14 Registered Address Ramasethu Infrastructure Private Limited,
No. 4-4-1/3, Y V Rao Estate,
Jakkampudi, Near CNG Gas Bunk,
Vijayawada, Andhra Pradesh – 520012
15 Address for Correspondence Ramasethu Infrastructure Private Limited,
No. 4-4-1/3, Y V Rao Estate,
Jakkampudi, Near CNG Gas Bunk,
Vijayawada, Andhra Pradesh – 520012
Name Mr. Ravi Chandra
Designation (Owner/Partner/CEO) Manager
3
Address Ramasethu Infrastructure Private Limited,
No. 4-4-1/3, Y V Rao Estate,
Jakkampudi, Near CNG Gas Bunk,
Vijayawada, Andhra Pradesh – 520012
Pin Code 520012
E-mail [email protected]
Telephone no 9100481399
Fax. no
16 Details of Alternate Sites examined, if
any. Location of these sites should be
shown on a topo sheet
Village District State
The proposed land belongs to J&K
SIDCO. No alternate sites were
considered.
17 Interlinked Projects None
18 Whether separate application of
interlinked project has been submitted.
None
19 If yes, date of submission None
20 If no, reason None
21 Whether the proposal involves approval /
clearance under: if yes, details of the
same and their status to be given
The Forest (Conservation) Act, 1980?
The Wildlife (Protection) Act, 1972?
The C.R.Z. Notification, 1991?
None
22 Whether there is any Government Order
/ Policy relevant / relating to the site
Department of Industry and commerce
allotted the site to J&K SIDCO for
industrial development.
23 Forest Land involved (hectares) Nil
24 Whether there is any litigation pending
against the project and / or land in which
the project is proposed to set up?
(a) Name of the Court
(b) Case No
(c) Orders / directions of the court, if
any and its relevance with the
proposed project.
No
4
(II) Activity
I. Construction, operation or decommissioning of the Project involving actions,
which will cause physical changes in the locality (topography, land use, changes
in water bodies, etc.).
S.No Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
1.1 Permanent or temporary
change in land use, land cover
or topography including
increase in intensity of land use
(with respect to local land use
plan)
Yes Changes in land use, land cover or
topography are envisaged.
The layout of the proposed facility is
attached as Annexure 3.
1.2 Clearance of existing land,
vegetation and buildings?
Yes Yes clearance of existing grass is
envisaged.
There are no buildings in the area hence no
clearance is envisaged.
1.3 Creation of new land uses? No None in the study area.
1.4 Pre- construction investigations
e.g. bore holes, soil testing?
Yes Geotechnical investigations. Report
enclosed as Annexure 4.
1.5 Construction works? Yes Civil construction activities are involved for
development of Integrated Common
Hazardous Waste Treatment, Storage,
Disposal and Recycling Facilities.
1.6 Demolition works? No Not Applicable
1.7 Temporary sites used for
construction works or housing
of construction works?
No No temporary sites are proposed for
housing of the workers as they are hired
from the surrounding area.
1.8 Above ground buildings,
structures or earthworks
including linear structures, cut
and fill or excavations
Yes The proposed construction involves
development of an Integrated Common
Hazardous Waste Treatment, Storage,
Disposal and Recycling Facilities
Excavation will be done for laying
foundations and basements. The excavated
soil is used for construction of earthen
bunds.
1.9 Underground works including
mining or funneling?
No Not applicable
1.10 Reclamation Works? No Not applicable
1.11 Dredging? No No dredging activities are required.
1.12 Offshore structures? No The site is not lying near the shore
1.13 Production and manufacturing
processes?
Yes The manufacturing details attached as
Annexure 5.
1.14 Facilities for storage of goods
or materials?
Yes Facilities for Hazardous material storage,
recyclable waste, Bio Medical waste
5
treatment, Recycle facilities etc will be
developed.
1.15 Facilities for treatment or
disposal of solid waste or liquid
effluents?
Yes Treatment of hazardous, Bio medical along
with leachate will be treated appropriately
and disposed to the greenbelt developed
within the boundary. The details of the
same are given Annexure 6.
1.16 Facilities for long term housing
of operational workers?
No No Housing is proposed.
1.17 New road, rail or sea traffic
during construction or
operation?
No Not Applicable
1.18 New road, rail, air waterborne
or other transport infrastructure
including new or altered routes
and stations, ports, airports
etc?
No None envisaged.
1.19 Closure or diversion of existing
transport routes or
infrastructure leading to
changes in traffic movements?
No None envisaged
1.20 New or diverted transmission
lines or pipelines?
Yes For power transmission existing lines will be
used.
1.21 Impoundment, damming,
culverting, realignment or other
changes to the hydrology of
watercourses or aquifers?
No Not Applicable
1.22 Stream crossings? No There is no stream crossing at the
proposed site.
1.23 Abstraction or transfers of
water from ground or surface
waters?
Yes Water requirement for the project will be
met through Tube wells by J&K SIDCO and
partly met through the bore wells within the
boundary premises.
1.24 Changes in water bodies or the
land surface affecting drainage
or run-off?
No Not envisaged
1.25 Transport of personnel or
materials for construction,
operation or decommissioning?
Yes Transport of personnel/material during the
construction and Operation phase is
envisaged for which local labor will be used.
1.26 Long-term dismantling or
decommissioning which could
have an impact on the
environment?
No None envisaged.
1.27 Ongoing activity during
decommissioning which could
No None envisaged.
6
have an impact on the
environment?
1.28 Influx of people to an area in
either temporarily or
permanently?
Yes Influx of people to the area will be seen
during construction and operation phase.
1.29 Introduction of alien species? No None envisaged
1.30 Loss of native species or
genetic diversity?
No None envisaged
1.31 Any other actions? No None envisaged
2. Use of Natural resources for construction or operation of the Project (Such as
land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
S.No Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
2.1 Land especially undeveloped or
agricultural land (ha)
Yes Undeveloped land
2.2 Water (expected source &
competing users) Unit : KLD
Yes Water requirement will met through the
Tube wells. Water requirement details
enclosed as Annexure 7.
2.3 Minerals (MT) No No Minerals are required.
2.4 Construction material – stone,
aggregates, and / soil
(expected source- MT)
Yes Stones, aggregates, soil etc will be taken
from local market.
2.5 Forests and timber (source –
MT)
No No forest cutting is involved in the project.
However the timber is purchased in local
timber depots for administration building
doors and windows.
2.6 Energy including electricity
and fuels (source, competing
users ) Unit : fuel (MT), energy
(MW)
Yes Energy Source: Power Development
Department, J&K.
About 1000KVA during implementation
stage is required for the facility.
2.7 Any other natural resources
(use appropriate standard
units).
No Not Applicable.
3. Use, storage, transport, handling or production of substances or materials which
could be harmful to human heath or the environment or raise concerns about actual
or perceived risks to human health.
S.No Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible) with
sources of information data.
3.1 Use of substance or materials,
which are hazardous (as per
No All the industrial Hazardous water collected
at proposed site will be scientifically treated /
7
MSIHC rules) to human health
or the environment (flora, fauna
and water supplies)
stabilized and detoxificated before storing in
secured landfill. Hence no health impacts
envisaged.
3.2 Changes in occurrence of
disease or affect disease
vectors (e.g. insect or water
borne diseases)
No Suitable drainage and waste management
measures will be adopted in both the
construction and operation al phase which
will restrict stagnation of water or
accumulation of waste. This will effectively
restrict the reproduction and growth of
disease vectors.
3.3 Affect the welfare or people
e.g. by changing living
conditions
Yes The proposed Integrated Hazardous waste
management facility will provide employment
to local people in the proposed area; it will
also improve hygienic conditions in the
landfill site.
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patient‟s,
children, the elderly etc.,
No There are no hospitals or other sensitive
locations located in the immediate vicinity of
the facility.
3.5 Any other causes No None envisaged
4. Production of solid wastes during construction or operation or decommissioning
(MT/ month).
S.No Information /
Checklist confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
4.1 Spoil, overburden or mine
wastes
No Not Applicable
4.2 Municipal waste (domestic and
or commercial wastes)
No Not applicable
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
Yes Hazardous Waste Treatment, Storage,
Disposal and Recycling Facilities will be
developed as per Hazardous and Other
Wastes (Management and Transboundary
Movement) Rules, 2016 and other
applicable rules/guidelines.
4.4 Other industrial process wastes Yes Electronic waste will be processed as per
E-waste (Management) Rules 2016, The
Batteries (Management and Handling)
Rules, 2001 and subsequent amendments.
4.5 Surplus product No Not Applicable as this is development of
Integrated Hazardous waste Management
facility.
4.6 Sewage sludge or other sludge
from effluent treatment
No Not applicable
8
4.7 Construction or demolition
wastes.
No Not envisaged
4.8 Redundant machinery or
equipment
No Not Applicable
4.9 Contaminated soils or other
materials
No No soil contamination is anticipated from
the proposed project as the land fill facility
will have liner systems to arrest any
contamination.
4.10 Agricultural wastes No Not Applicable as this is development of an
Integrated Hazardous waste management
facility for Hazardous waste treatment,
storage and disposal.
4.11 Other solid wastes Yes Treatment of Bio Medical Waste shall be as
per Bio-Medical Waste Management Rules,
2016.
5. Release of pollutants or any hazardous, toxic or noxious substances to air
(Kg/hr).
S.No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate quantities /rates, wherever possible) with sources of information data
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes PM, SO2 and NOX from DG set will be
dispersed into atmosphere through stack
meeting MoEF standards.
5.2 Emissions from production
processes
Yes Dust particulates will be controlled by Bag
filter.
5.3 Emissions from handling
including storage and transport
Yes Emissions from handling Hazardous waste
storage and transport are controlled by
handling in the closed containers.
5.4 Emissions from construction
activities including plant and
equipment
Yes Fugitive emissions are likely during the
construction & transportation activities due
to use of construction equipment. These
are temporary in nature.
5.5 Dust or odors from handling of
materials including construction
materials, sewage and waste.
Yes Dust is likely to be generated during
construction phase,
Water sprinkling will be done
Tarpaulin cover will be provided over stored
raw material to reduce dust emission.
Green belt development will be taken up
5m wide along boundary and open areas
will be provided
9
5.6 Emissions from incineration of
waste
Yes PM, SO2 and NOx will be generated from
the incinerator which is proposed in
Phase-II.
5.7 Emissions from burning of waste
in open air (e.g. slash materials,
construction debris)
No Not envisaged.
5.8 Emissions from any other
sources
No None envisaged
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
6.1 From operation of equipment
e.g. engines, ventilation plant,
crushers
Yes Noise levels are expected at DG set area,
and due to use o pumps and motors,
necessary PPEs (ear muffs, closed
chamber) will be provided for the
personnel‟s working in these area.
Most of the equipment structures are static,
vibration effect of these will be only local,
design of support and foundation will nullify
the intensity of vibrations.
6.2 From industrials or similar
processes
Yes As explained in 6.1.
6.3 From construction or demolition Yes Excavation, drilling and welding during
construction is temporary in nature.
6.4 From blasting or piling No Not Applicable
6.5 From construction or operational
traffic
Yes Noise from traffic movements is expected
from the proposed facility at the
construction and operational stage.
6.6 From lighting or cooling systems No Light emissions are not envisages in the
project.
Heat emission are not envisages in the
project.
6.7 From any other sources No Not applicable
7. Risks of contamination of land or water from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the sea :
S. No Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
7.1 From handling, storage, use or
spillage of hazardous materials
No The proposed facility will provide facilities
to treat hazardous waste materials only as
per the hazardous waste management
10
rules.
7.2 From discharge of sewage or
other effluents to water or the
land (expected mode and place
of discharge)
No Contamination of land or water is not
envisaged as the leachate generates is
treated in Leachate Treatment Plant and
partly treated leachate is recycled and
excess treated leachate will send to the
green belt.
7.3 By deposition of pollutants
emitted to air into the land or
into water
No The major emissions from the proposed
facility are PM, SO2 and NOx. Stack height
meeting MOEF guidelines will be provided
for proper dispersion of emissions. Hence
chances of contamination of land and
water by deposition of pollution is not
envisages.
7.4 From any other sources No None envisaged
7.5 Is there a risk of long term build
up of pollutants in the
environment from these
sources?
No The limited release of pollution will be
within the prescribed limits by proper EMP.
8. Risk of accidents during construction or operation of the Project, which could
affect human or the environment.
S. No Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
8.1 From explosions, spillages, fires
etc from storage, handling, use
or production of hazardous
substances
Yes Proposed project is an Integrated
Hazardous waste management facility
hence explosions, spillages, fires etc due
to storage, handling, use or production of
hazardous substances is not envisaged
due to the proper treatment methods
adopted at site.
Adequate steps for firefighting will be
taken to control fires in case of
emergency.
During construction all the labours will be
provided with suitable personal protective
equipment (PPE) as required under the
health & safety norms.
Training and awareness about the safety
norms will be provided to all supervisors
and labours involved in construction
11
activity.
An agreement will be signed with the
contractor which will clearly deal with the
safety aspects during construction.
Proper EHS measures will be
implemented.
8.2 From any other causes Yes Accidents during equipment and
machinery operations are expected.
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g.
floods, earthquakes, landslides,
cloudburst etc)?
No The project area falls under seismic zone
IV as per the Seismic Zoning Map of India
(IS 1893-1984).
9. Factors which should be considered (such as consequential development)
which could lead to environmental effects or the potential for cumulative
impacts with other existing or planned activates in the locality
S.No Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
9.1 Lead to development of
supporting. facilities, ancillary
development or development
stimulated by the project which
could have impact on the
environment e.g.:
Supporting infrastructure
(roads, power supply, waste
or waste-water treatment
etc.)
Housing development
Extractive industries
Supply industries
Other
Yes There will be cumulative positive impact on
the environment in terms of better waste
management. More Employment
opportunities will be created and
aesthetics of the area will be improved.
Due to the proposed facility impact may be
felt on local infrastructure.
Demand for housing will increase.
Ancillary industries, shops, small hotels etc
will come up.
9.2 Lead to after use of the site,
which could have an impact on
the environment
No Proposed project is an Integrated
Hazardous Waste Management Facility.
Once the landfill is fully utilized, post
closure care of landfill shall be conducted
for at least 10-15 years.
Vegetative cover will be provided over
completed cells/site.
12
Monitoring leachate collection system in
accordance with requirement.
Monitoring and ground water in
accordance with requirements.
9.3 Set a precedent for later
developments
Yes The closed land fill site may be used for
playground , garden, golf court etc after
ensuring that gaseous leachate analysis
controlled with the laid down standards are
meet.
9.4 Have cumulative effects due to
proximity to other existing or
planned projects with similar
effects)
No The proposed project will follow the local
laws to keep cumulative effect under
control.
(III) Environment Sensitivity
S.No Areas Name/
Identy
Aerial distances (within 15 km.)
Proposed project location boundary.
1. Areas protected under
international conventions,
national or local legislation for
their ecological, landscape,
cultural or other related values.
Yes India Pakistan Boundary – 9.0km, South
2. Areas which are important or
sensitive for ecological reasons
– Wetlands, water courses or
other water bodies, coastal
zone, biospheres. Mountains,
forests
No Basanter River around 1.5km West
Reserved Forest -1.9 km East
3. Areas used by protected,
important or sensitive species
of flora or fauna for breeding,
nesting, foraging, resting, over
wintering, migration.
No None in the study Area
4. Inland, coastal, marine or
underground waters
No None in the study Area
5. State, National boundaries Yes International boundary India Pakistan
Boundary –9.0km, South
6. Routes or facilities used by the
public for access to recreation
or other tourist, pilgrim areas.
No None in the study Area
7. Defense installations No None in the study Area
8. Densely populated or built-up
area
Yes Samba town-2.0km-Northeast.
9. Areas occupied by sensitive No No sensitive areas are available like
14
List of Annexures
Annexure-1 Location map of the site
Annexure-2 Topo map of the study area
Annexure-3 Layout of the proposed facility
Annexure-4 Geotechnical Investigations report
Annexure-5 Manufacturing details of the project
Annexure-6 Wastewater generation details
Annexure-7 Water requirement of the facility
15
Annexure-1
Location map of the site
16
Annexure-2
Topographical map of the proposed site (10km)
17
Annexure-3
Layout of the proposed facility
18
Annexure-4
Geotechnical Investigations report
------Enclosed-----
1
RReeppoorrtt oonn GGeeoollooggiiccaall aanndd HHyyddrrooggeeoollooggiiccaall IInnvveessttiiggaattiioonnss WWiitthhiinn tthhee PPrrooppoosseedd IInntteeggrraatteedd CCoommmmoonn HHaazzaarrddoouuss WWaassttee TTrreeaattmmeenntt,, SSttoorraaggee,, DDiissppoossaall aanndd RReeccyycclliinngg FFaacciilliittiieess aatt IInndduussttrriiaall GGrroowwtthh CCeennttrree,, PPhhaassee--IIII,, MMaannddhheerraa VViillllaaggee,, SSaammbbaa TTeehhssiill,, SSaammbbaa DDiissttrriicctt,, JJ&&KK..
SSuubbmmiitttteedd ttoo MM//ss.. AAPPRR PPRROOJJEECCTTSS LLTTDD PPlloott NNoo:: 77&&88,, RRaaddhhaa KKrriisshhnnaa NNaaggaarr,, AAddjjaacceenntt ttoo AAmmbbiieennccee ffoorrccee,, AAttttaappuurr,, HHyyddeerraabbaadd--550000004488..
PPrreeppaarreedd bbyy MM//ss.. RRaammkkyy EEnnvviirroo EEnnggiinneeeerrss LLiimmiitteedd,, ((CCoonnssuullttaannccyy DDiivviissiioonn)),, 44tthh FFlloooorr,, TTSSRR TToowweerrss,, RRaajjbbhhaavvaann RRooaadd,, SSoommaajjiigguuddaa,, HHyyddeerraabbaadd –– 550000008822..
2
Table of Contents
Sl. No Contents Page No
1.0 Introduction & Objective 3
1.1 Scope 3
1.2 Topography of the Area 3
1.3 Climate & Rainfall 4
1.4 Geology and Geomorphology 5
1.5 Natural Drainage System 6
2.0 Geophysical Investigations 6
2.1 ERT Methodology 8
2.2 DC Resistivity Meter 9
2.3 Results of Resistivity Data 12
3.0 Surface Soil Infiltration Tests 23
3.1 Plan of Work 23
3.2 Theory 24
3.3 Methodology 24
3.4 Results 25
4.0 Hydrogeology & Depth of Aquifer 29
3
1. Introduction & Objective
Jammu & Kashmir State Industrial Development Corporation Ltd. (J&K SIDCO) has taken up the
task of developing the Industrial Hazardous Waste Management facility for Treatment, Storage
and Disposal Facility at Samba, Phase-II Industrial Estate. J&K SIDCO has appointed M/s. APR
PROJECTS LTD, Hyderabad for the development of project. As a part of the project, M/s. APR
Projects Ltd., selected M/s. Ramky Enviro Engineers Ltd., Hyderabad, as a technical consultant for
Preparation Form-I along with proposed ToR and Feasibility report for obtaining environmental
clearance. Subsequently the technical team of REEL was conducted detailed studies pertaining to
Geological and Hydrogeological studies within the proposed site between 8/5/2012 and
11/5/2012. This report will give all the details along with its results of Subsurface Geological and
Hydrogeological investigations conducted within the proposed site.
1.1 Scope
In the proposed site Electrical Resistivity Tests were conducted at 10 locations to know the
detailed picture of sub-surface lithological layers, their nature, thickness and depth range
including presence/absence of aquifer zones. Surface soil infiltration test was conducted at 3
locations to analyze the rate of infiltration of existing soils. Apart from this, information collected
on groundwater levels of wells present in and around the proposed site. All the collected
information is synthesized to have a meaningful Geological and Hydrogeological report.
1.2 Topography of the Area
Topographically the proposed site is located over an elevated mound. Most part of the site is on
the western flank of the mound exhibiting gentle to steep slope towards foot hill side (Refer Fig.1).
The eastern margin of the site is showing higher elevations comparatively middle and western
parts of the site. The maximum elevation within the site is observed along the eastern margin at
northern part. The elevation difference between lowest and highest is about 20m.
4
1.3 Climate & Rainfall
The proposed site and its surrounding areas experiences hot summers and severe winters.
Temperature is lowest between November & February when the minimum night temperature
touches zero degree in the hill area and 3° – 4° C in the outer plain area. Temperature rises from
March onward. It becomes unbearable during May-June. Maximum day temperature in June
touches sometime 47° C in the outer plain and about 30°- 35°C in the hills. Most of the rainfall is
received through the southwest monsoon which lasts from the last week of June to end of
September. During the remaining period, rainfall is sporadic and scanty. Average annual rainfall is
about 1052 mm.
Fig.1: Part of the Project Site area Representing Sloping Terrain
5
1.4 Geology and Geomorphology
Geologically the proposed site and its surroundings are forming a part of Upper Siwalik formations
of Himalayan terrain belonging to Cenozoic age. The formations existing in the study area are
locally known as the Kandi formations which are running northeast – southwest direction i.e.
parallel to the strike direction of other Siwalik formations; they consist red earthy clays with
massive beds of coarse pebbly sandstones (As shown in Fig.2) overlain by great thick beds of
siliceous boulder conglomerate. The coarseness of the conglomerate varies from that of a true
boulder conglomerate to that of a gravelly conglomerate.
Geomorphologically the study area is covered with flat toped hill with gentle to steep slopes
towards its flanks. The Basantar River is flowing at about few hundred meters west from the site.
It has developed flood plains on either bank. Several highly elevated structural hills present all
around the study area.
Fig.2: Boulders and Pebbles bed exposed
on the base of a drain.
6
1.5 Natural Drainage System
The drainage pattern in the area is mostly controlled by the geological and geomorphological
features. A number of dry, wide and flat boulder bottomed drainage lines, locally known as Khads,
present in the area are exhibiting Dendritic drainage pattern.
2 Geophysical Investigations
In–order to have detailed information about the occurrence of subsurface lithological layers their
nature and thickness; Electrical Resistivity Tests (ERT) were conducted in the proposed project
site. These tests were conducted at 10 possible locations. Figure 3 represents the location of 10
ER Tests conducted within the site. Several surface geophysical methods are deployed to reach
the purpose. All these methods rely upon the principle that each lithological assemblage has
independent physical properties. Identification of a property helps to recognize the formation.
One such property easily detectable is its electrical character, for the passage of known strength of
current. At every testing location the detailed information was collected up to 35m depth from
the surface.
There are two popular surface electrical resistivity methods are in practice namely, Schlumberger
and Werner configurations. The Schlumberger method of Electrical Resitivity Test (ERT) has been
used in the present study.
7
Figure 3:
8
2.1 ERT Methodology
In ERT method, current is sent into the ground through a pair of electrodes called current
electrodes and resulting potential difference across the ground is measured with the help of
another pair of electrodes called potential electrodes. The ratio between the potential difference
(ΔV) and the current (I) gives the resistance (R), which depends on the electrode arrangement
and on the resistivity of the subsurface formations. In Schlumberger configuration, all the four
electrodes are kept in a line. The outer electrode spacing is kept large, compared to the inner
electrode spacing, usually more than 5 times. The disposition of electrodes for Schlumberger
configuration is shown in Figure 4.
The apparent resistivity for this configuration is computed with the formula
a = k R
Where ‘k’ is the constant = [(AB/2)2 – (MN/2)2] MN
‘AB’ is current electrode spacing and
‘MN’ is potential electrode spacing
R = V / I
The apparent resistivity values obtained with increasing values of electrode separations are used
to estimate the thickness and resistivity of the subsurface formations. The plot between apparent
resistivity and the distance between any two successive electrodes separation is used for analysis
of thickness and resistivity of the subsurface formations.
The resistivity data is to be interpreted (analyzed) in terms of physical parameters viz., resistivity
and thickness of the formations and these parameters in-turn, along with hydro geological
information are to be used to infer the nature of subsurface formations. In the present study
Inverse Slope method of interpretation is used to interpret the data.
9
Figure 4: Schlumberger Configuration
2.2 DC Resistivity Meter
For field application of Schlumberger electrical configuration and obtaining the resistivity data, the
DC Resistivity Meter Model DDR-3 of IGIS make is used. It is having features with high quality data
acquisition capability as well as for its field worthiness. The meter consists of two units, a current
unit and a potential unit. While the current unit serves the purpose of sending the required output
of constant current, the potential unit provides an accurate measurement and display of
potential/resistance values directly over a liquid crystal display. The field measurements for DC
resistivity investigations basically involves sending a known strength of current into the ground
through the current electrodes and observing the resulting voltage across the potential
electrodes, to get the resistance values. The instrument has the facility to provide the operator the
direct readout of these resistance values on liquid crystal display. Figure 5 Shows the Resistivity
Meter used in the present study and Figure 6a,b & c represents the infield measurement of ERT
survey.
10
Figure 5: DC Resistivity
Meter Model
Fig.6a: Conducting
Electrical Resistivity
Tests within the site.
11
Fig.6b: Conducting
Electrical Resistivity
Tests within the site.
Fig.6c: Conducting
Electrical Resistivity
Tests within the site.
12
2.3 Results of Resistivity Data
The Resistivity Information collected from the 10 selected ERT points located in the proposed
project site are analyzed/ interpreted using inverse slope software. It is inferred from the analysis
of field resistivity data; there are three different lithological layers present up to 35m bgl viz. a low
compacted Sandy layer with Boulders, a low compacted Boulder Bed. These two formations are
exhibiting high resistivity range with varying thickness. A layer of comparatively low resistivity is
present which has anticipated as zone of clay with boulders.
Based on the results of the ER tests it is understood that most of the hill slope areas are having
only two layers viz. a zone of Sand with Boulders on the top with a maximum thickness of 5m
followed by Boulder Bed with more than 30m thick. These sequences are observed at ERT
locations 4,6,7,9 and 10. At the rest of the locations a zone of Clay with Boulders is present along
with other two layers. The vertical dispositions of these formations are represented in ERT logs
individually in the subsequent pages from Annexure 1 to 5. Based on the ERT logs 4 subsurface
lithological cross-sections were projected. They are presented in Figure 8 to 11. The location map
of cross-section lines is given in Figure 7.
Fig.6d: Site Inspection
along with SIDCO Officer
during Field Survey
13
Annexure: 1
14
Annexure: 2
15
Annexure: 3
16
Annexure: 4
17
Annexure: 5
18
Figure: 7
19
Figure: 8
20
Figure: 9
21
Figure: 10
22
Figure: 11
23
3 Surface Soil Infiltration Tests
Infiltration is one of the characteristic properties of soil. Water entering into the soil at the surface
is called infiltration. Infiltration rate is dependent upon the nature and proportion of clay and
sand, the type of vegetation, the granularity, angularity and texture of sand. Infiltration rates are
high in sandy soils and low in clayey soils.
3.1 Plan of Work
Surface soil infiltration tests were conducted at 3 representative locations within the proposed
site using Double Ring Infiltrometer (Figure 12). The test -1 is placed near ERT 1, test-2 is near ERT
5 and test-3 is at ERT 10. Figure 3 represents the location map of infiltration tests within the
proposed site.
Fig.12 Surface Soil Infilteration Test
using Double Ring Infiltrometer
24
3.2 Theory
Water entering the soil at the surface is called Infiltration. The Infiltration rate ‘f” at any time‘t’ is
given by Horton’s equation.
f = fc + (fo – fc) e-kt where
fo = Initial rate of infiltration capacity at time to
fc = Final constant rate of infiltration at saturation
k = A constant depending primarily upon the soil and vegetation
it is equal to
fo – fc
F
e = base of natural Logarithm = 2.71828 Fc = Shaded area in Fig.13.
For any two points x, y on the curve against time t1, t2 and infiltration rates f1, f2 log(f1-f2) - log(f2-fc)
k = log(t2 – t1)
3.3 Methodology
Infiltration tests were conducted by adopting Double Ring Infiltrometer method. In this method
two PVC rings of 15 cm and 7.5 cm diameter are driven into ground so that they penetrate into soil
uniformly without any tilt or undue disturbance of soil surface up to a depth of about 5 cm, after
driving is completed, soil disturbed adjacent to the sides is tampered gently. Clean water is
poured into rings to maintain depth of about 25 cm water column in both the inner and outer
rings. Fall in water column inside the ring is recorded periodically at close intervals of 2/3 minutes
Time ‘t’ in minutes
Infi
ltra
tio
n r
ate
cm
/hr
fc
f0
f1
f2
t1 t2 15 20 5 10 25 30 0
1
2
3
4
5
Fig.13: Soil Infiltration
Curve
25
in the beginning and increased interval of 5 minutes subsequently. Water is added immediately
after each measurement into both the rings to maintain original constant depth of 25 cm. Fall of
water level between two successive readings and total fall of water level from the beginning of the
test at each time is estimated (Refer Figure 14).
The infiltration rate in the beginning of the test is high. After the soil attains saturation the rate
decreases and stabilizes at a fixed rate. The infiltration rates in cm/hr to all elapsed time readings
are calculated. The
infiltration rates (cm/hr)
against the elapsed time
(minutes) are drawn on
coordinate graph. A fitted
straight line is the final
infiltration curve. The rate
per day is estimated using
this graph.
3.4 Results
To have an idea about the soil infiltration capacity, surface soil infiltration tests were conducted at
three representative locations within the site using double ring infiltrometer. Each test was
conducted for about 90 minutes using constant head measurement. The observed infiltration
values are high at beginning stage and are comparitively low at the ending. The field data was
analyzed and the results are indicating that the infiltration capacity is 0.264 Cm/hr to 2.181 Cm/hr.
The recorded observations and data plots are given from Annexure 6 to 8.
Fig.14 Conducting Infiltration Tests within the Proposed Site
26
Annexure – 6
SOIL INFILTRATION TEST-1
Date of test: 10/5/2012 Location: Near ERT No:01
Duration of time in minutes for each Filling
Time elapsed since test started (T)
minutes
Fall in water Column(h) in cm for time (t) in minutes
Cumulative fall In water column (H)
in cm for time (T) in minutes
Infiltration rate in Cm/hr [H/T*60
minutes]
2 2 0.4 0.4 12.0
2 4 0.3 0.7 10.5
2 6 0.2 0.9 9.0
2 8 0.2 1.1 8.3
2 10 0.2 1.3 7.8
5 15 0.6 1.9 7.6
5 20 0.5 2.4 7.2
5 25 0.5 2.9 7.0
5 30 0.5 3.4 6.8
10 40 1 4.4 6.6
10 50 0.8 5.2 6.2
10 60 0.8 6 6.0
10 70 0.8 6.8 5.8
10 80 0.7 7.5 5.6
10 90 0.7 8.2 5.5
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
0 10 20 30 40 50 60 70 80 90
Infi
ltra
tio
n R
ate
(C
m/h
r)
Time Elapsed (Minutes)
Soil Infiltration Test - 01, TSDF Site, SAMBA, J&k
27
Annexure – 7
SOIL INFILTRATION TEST-2
Date of test: 10/5/2012 Location: Near ERT No:05
Duration of time in minutes for each Filling
Time elapsed since test started
(T) minutes
Fall in water Column(h) in cm for time (t) in minutes
Cumulative fall In water column (H) in cm for time (T)
in minutes
Infiltration rate in Cm/hr [H/T*60 minutes]
2 2 2.3 2.3 69.0
2 4 2.1 4.4 66.0
2 6 2.1 6.5 65.0
2 8 2 8.5 63.8
2 10 2 10.5 63.0
5 15 2.2 12.7 50.8
5 20 2.2 14.9 44.7
5 25 2.1 17 40.8
5 30 2 19 38.0
10 40 2.5 21.5 32.3
10 50 2.5 24 28.8
10 60 2.3 26.3 26.3
10 70 2.3 28.6 24.5
10 80 2.3 30.9 23.2
10 90 2.2 33.1 22.1
20.0
25.0
30.0
35.0
40.0
45.0
50.0
55.0
60.0
65.0
70.0
0 10 20 30 40 50 60 70 80 90
Infi
ltra
tio
n R
ate
(C
m/h
r)
Time Elapsed (Minutes)
Soil Infiltration Test - 02, TSDF Site, SAMBA, J&k
28
Annexure – 8
SOIL INFILTRATION TEST-3
Date of test: 10/5/2012 Location: Near ERT No:10
Duration of time in minutes for each Filling
Time elapsed since test started (T)
minutes
Fall in water Column(h) in cm for time (t) in minutes
Cumulative fall In water column (H) in cm for time (T)
in minutes
Infiltration rate in Cm/hr [H/T*60
minutes]
2 2 2.5 2.5 75.0
2 4 2.5 5 75.0
2 6 2.4 7.4 74.0
2 8 2.4 9.8 73.5
2 10 2.4 12.2 73.2
5 15 2.8 15 60.0
5 20 2.8 17.8 53.4
5 25 2.6 20.4 49.0
5 30 2.5 22.9 45.8
10 40 2.6 25.5 38.3
10 50 2.6 28.1 33.7
10 60 2.6 30.7 30.7
10 70 2.5 33.2 28.5
10 80 2.5 35.7 26.8
10 90 2.5 38.2 25.5
20.0
25.0
30.0
35.0
40.0
45.0
50.0
55.0
60.0
65.0
70.0
75.0
80.0
0 10 20 30 40 50 60 70 80 90
Infi
ltra
tio
n R
ate
(C
m/h
r)
Time Elapsed (Minutes)
Soil Infiltration Test - 03, TSDF Site, SAMBA, J&k
29
RESULTS OF INFILTRATION TESTS
4. Hydrogeology & Depth of Aquifer
The occurrence and movement of groundwater is mainly controlled by many factors such as rock
types, landforms, geological structures, soil, land use, rainfall etc.
In-order to evaluate the hydro geological conditions in and around the proposed project site, a
systematic well inventory was conducted within a 5km radius. During well inventory information
pertaining to total depth of wells, groundwater levels, quality of water, pre and post monsoon
water level fluctuations, condition of wells during summer months, geological formations
encountered during construction of wells and all other inter related information was collected.
This information was synthesized and presented in the table given below. Based on the observed
groundwater levels, water level contour maps were prepared and are presented in Figure 15 & 16.
It is observed from the field data that the aquifers are present at deeper depths. In general they
are present below 50m depth at almost all locations. The ground water is occurring within the
boulder beds under confined to semi-confined conditions. The observed ground water levels are
between 27 to 37m bgl. The quality of water is in potable condition. Based on the information
Test
No.
Location Surface soil
Characteristics
Infiltration Rate
m/day
Remarks
1 Near ERT-01 Sand with Boulders (Hill Top) 0.264 Rate of Infiltration is Moderate
2 Near ERT-05 Sand with Boulders (Hill Slope) 1.653 Rate of Infiltration is High
3 Near ERT-10 Sand with Boulders (Hill Slope) 2.181 Rate of Infiltration is High
Average Rate of Soil Infiltration 1.366 Rate of Infiltration is High
30
collected from the local villagers it is anticipated that the water level fluctuation between post
monsoon to pre monsoon is in between 3m to 6m. The water level contour map generated based
on the field data is indicating that the ground water flow direction is towards northwest and
southeast from the central part of the study area.
Wells Inventoried within 5Km Radius of the Proposed TSDF Site, Samba, J&K
Sl.No. Code Village Name Type of Well
Total Depth (mbgl)
Depth to Water Level (mbgl)
Water Level Fluctuation (m)
Water Quality
1 GW-1 Plant Site BW 91 34 3 Potable
2 GW-2 Samba BW 98 37 4 Potable
3 GW-3 Sapwal BW 91 30 4 Potable
4 GW-4 Chak Nanak BW 98 34 4 Potable
5 GW-5 Raipur BW 98 27 5 Potable
6 GW-6 Sangawari BW 110 37 6 Potable
7 GW-7 Mandharai BW 91 27 5 Potable
8 GW-8 Katli BW 101 30 4 Potable
9 GW-9 Ralyer BW 107 27 3 Potable
10 GW-10 Bulo BW 107 29 3 Potable
31
32
19
Annexure-5
Process Description
Hazardous Waste Management Facility
Collection, transportation, reception, treatment, storage, re-use, recycle, blending and
disposal of industrial hazardous wastes, bio-medical waste and E-Waste generated in the
state of Jammu & Kashmir.
The proposed project is very unique to itself. The Facility shall be the first of its kind
integrated waste management facility in the country. In fact it will be a giant step in the drive
towards environment protection by the state of Jammu & Kashmir.
The quantities of hazardous wastes generated in the project area are estimated to be about
30,000 TPA (expected to be received at the facility) and are expected to comprise of the
following groups:
ETP sludges
Iron Sludges
Still Bottom residues and process sludges
Spent Carbon
Evaporation salts/ other process salts
Incineration ash
Slags
Asbestos and glass fibers
Spent catalysts and resins
Other hazardous wastes
Based on the quantities available the following general information could be inferred:
ETP sludges can go directly to landfill either directly or after stabilization.
Still bottom residues, process residues and other organic wastes can be sent for
incineration including spent carbon depending on the characteristics of the impurities.
Incineration ash, slags, asbestos and glass fibers are essentially inorganic in nature and
can go to landfill directly or with simple stabilization techniques.
Spent catalysts and resins would have to be characterized on a case-by-case basis to
assess their nature and characteristics. However, the percentage of wastes generated
through these sources is likely to be very small as most of it is taken back by the
manufacturers.
Salts will have to be bagged and land filled.
20
Based on the above compiled information wastes have been classified by their pathway of
disposal:
Wastes going to direct landfill
Wastes that require stabilization prior to landfill
Wastes requiring storage until alternate economically viable techniques are made
available.
Wastes requiring incineration
The following general guidelines shall relate to daily activities associated with the operations
of TSDF:
The facility shall operate only during day light hours throughout the year.
The landfill will be staged in cells so that the minimum practical area of waste is exposed
and maximum practical area of waste has the final cap in place i.e., progressive filling
and capping of the landfill ensuring minimization of infiltration of wastes.
The Weight Bridge at the main entrance will record all movements and weights and
receive waste tracking receipt as required by the waste manifest system.
The standpipe forming part of the leachate collection system shall be checked regularly
for the presence of leachate. Once leachate is detected it shall be regularly pumped out
and transferred to the leachate treatment facility on-site. The level of leachate in the
standpipe shall not be allowed to rise above the level of the leachate collection system.
Materials Safety Data Sheets (MSDS) for every chemical used or handled at the landfill
shall be provided on the premises.
Monitoring and auditing of the facility shall be performed on a periodic basic.
Met-station shall be installed with continuous recording system.
A security system shall be maintained to avoid trespassing and hazard to the public.
Once a waste is received at the TSDF, a sample of waste shall be collected, at the
sampling bay/temporary storage facility and shall undergo laboratory analysis based on
which its pathway of treatment/ disposal shall be determined.
A waste manifest system shall be developed in accordance with the requirement of the
regulatory agencies to cover the transportation of the waste to TSDF and to provide for
record of waste manifestation. The manifest system shall include details of the waste
generator, waste transporter, quantity of waste, characteristics of waste, physical
description, consistency of waste in terms of physical state and waste category number
as per HW (M&H) Rules, 2003.
Each load of waste arriving at the facility shall be located properly and logged to identify
its pathway of treatment/ storage/ disposal.
An inventory shall be maintained at the arrival and departure dates of waste loads in and
out of the intractable waste storage area.
21
Waste Disposal Operations:
Physico Chemical Treatment
The basic unit mentioned above covered under the concept of waste stabilization in addition
to this facility recovery / recycling plants shall be provided based on the waste characteristics
and demands.
Waste stabilisation is designed to convert industrial wastes in the form of liquids, semi-solids
or reactive solids into low leachable materials that can be deposited into a secure landfill.
The stabilisation operation will be carried out for all waste that require this to minimize their
contaminant leaching potential. This will change the nature of these wastes to a less
hazardous category. Stabilisation involves the immobilisation of leachable materials by
fixation as non-reactive solids. The treated wastes shall be assessed for compatibility with
other wastes before being landfill and for compatibility with the HDPE and the pipe network.
The term stabilisation covers a number of mechanisms including:
Immobilisation/ Chemical Fixation – the chemical binding of contaminants within a
cementing structure to reduce the mobility or leachability of the waste.
Encapsulation – the occlusion or entrapment of contaminant particles within a solid
matrix.
Solidification – the conversion of slurries that do not readily de-water, into solids by
addition of adsorption agents.
Typical reagents that would be used for the stabilization process include: cement, lime, fly
ash, bentonite clay, saw dust and other. Where required sodium silicate solution would be
used as an additive binding agent. The reagent to be used for stabilization shall be decided
depending upon the type of the waste to be stabilized, price and availability. These regents
shall generally be stored in sufficient quantities.
Infrastructure proposed for the stabilization unit would include:
Storage facilities for regents
Tanks/Drums for storage of reagents as required
Stabilization bins for mixing the wastes
Earth moving equipment for movement of wastes and mixing.
Place for curing the treated waste
Trucks for hauling the wastes.
Treatment facility utilizes a range of techniques and processes designed to change the
physical, chemical or biological characteristics of the waste. This may include changing the
composition so as to neutralise the waste, to recover energy or natural resources from the
22
waste, to render the waste non-hazardous or less hazardous, safer to transport, store, or
dispose off or to reduce its volume.
Typical operations at Stabilization unit are as follows:
Waste receivable
Reagent addition
Mixing
Curing
Analysis of the stabilized wastes
Approval by the laboratory for disposal
Transfer of the waste materials to the truck
Disposal in the secured landfill
Landfill Operations
The landfill will be designed and constructed as a secure facility to contain the waste
material and any leachate, which is formed by the entrapped moisture or by infiltration of
rainfall. To meet these requirements the base of the landfill has been designed as an
engineered liner constructed prior to the placement of waste and also an engineered
capping over the surface after completion of filling to minimise the infiltration of rainfall.
The base liner of the landfill containment system is proposed to be a double composite liner
with synthetic geo-membrane plus clay. Adequate leachate collection system has been
incorporated at the base to collect and remove the leachate. These shall incorporate HDPE
pipes embedded in drainage layers of sand/ gravel and /or geonet/ geotextile. The
composite liner (Secondary liner) shall comprise of a 0.45-m thick clay compacted to a
permeability less than 10 –9 m/s and above this shall be a HDPE liner with permeability less
than 10 –14 m/s above which a complete drainage system shall be placed. Above the
secondary base liner shall be placed a primary liner comprising of primarily clay layer and
HDPE membrane which will prevent infiltration into the secondary layer. A leachate
collection and removal system shall also be placed over the primary liner to collect and
remove any leachate generated by infiltration of precipitation or by the moisture entrapped in
the waste. This makes the secondary system to serve as a leak detection system and an
early warning of potential future liabilities to necessitate action for remediation. Above the
drainage system of the primary liner shall be placed a geo-textile filter to act as a filter/
barrier between the waste and the drainage system. This entire system would make the
base liner a double composite liner meeting the national laws.
23
HA
ZA
RO
DU
S W
AS
TE
L
AN
DF
IL
L C
RO
SS
SE
CT
ION
(D
OU
BL
E C
OM
PO
SIT
E L
IN
ER
SY
ST
EM
& C
OV
ER
S
YT
EM
)
285 gsm GEOTEXTILE
DRAWING NOT TO SCALE
60 cm
45 cm
= 1.5mm HDPE Geo MembraneCLAY.
7-8mm Drainage Composite
Vegetation
Sub Soil
HAZARDOUS WASTE]
SOIL COVER
GAS COLLECTION MEDIA
Top Soil
Vegetative Soil
GEO NET
Gas Vent
15 cm
45 cm
= 2mm HDPE Geo Membrane
Compacted Clay / Compacted Amended Soil
400 G.S.M Geo Textile
30 cm
285 gsm GEOTEXTILE 200mm Thick Filter
Media (20mm
Gravels)
100mm Thick SandLeachate Collection Pipe
45 cm
= 2mm HDPE Geo Membrane
Compacted Clay / Compacted Amended Soil
400 G.S.M Geo Textile
30 cm
400 gsm GEOTEXTILE 200mm Thick Filter
Media (20mm
Gravels)
100mm Thick SandLeachate Collection Pipe
Leachate Collection/ Treatment and Disposal
Leachate collection and removal shall be provided above the geo-membrane in two layers viz.,
the primary and the secondary liners. The primary liner shall serve as leachate collection and
removal system, while the secondary liner shall serve as leak detection system and a signal of
potential liabilities in terms of environmental pollution
Bio-Medical Waste
Growth in population, industrialization and changing life styles and food habits have brought
with it various health related issues. More and more people are suffering from ailments.
Alongside this is the growing awareness towards utilizing proper medical facilities.
To enable effective management and handling of the bio-medical wastes, the Ministry of
Environment and Forests (MoEF) has issued regulations for the management and handling
of these wastes. The rules are formulated and known as the Bio-Medical Wastes
(Management and Handling) Rules 1998, under the aegis of Environment (Protection) Act,
1986.
In response to these rules, Government and major Private Hospitals initiated their
arrangements for treatment and disposal of bio-medical wastes. However, the smaller
nursing homes, clinics and other similar institutions which do not have or can afford such
24
facilities need alternate modalities and arrangements to dispose their wastes, in accordance
with the Rules.
Waste Classification and Characterization
Wastes generated by the hospitals can primarily be classified into 3 groups:
Conventional Wastes/ Municipal Solid Wastes: General refuse similar to the domestic/
municipal solid wastes and includes artificial linens, paper, food, cans, diapers, and
plastic cups. This waste is non-infectious if it is not brought in contact with the infectious
wastes and properly managed.
Hazardous Wastes: Laboratory and Pharmaceutical Chemicals and containers including
off-specification and other chemicals, alcohols, disinfectants, anti-neoplastic agents,
heavy metals (e.g. Mercury), etc. These wastes are hazardous in nature and if properly
segregated and managed can be transported to hazardous waste management facility
for treatment/ storage/ disposal.
Infectious Wastes: Commonly referred to as Clinical and pathological Wastes and
include: isolation wastes (refuse associated with infectious patients), cultures and stocks
of infectious agents and associated biological, human blood and blood products,
pathological wastes, contaminated sharps, amputated body parts, placenta and others.
Typical wastes falling under each of the above groups of infectious wastes is presented
in the following Table
Categorization of Infectious Wastes
Waste Group Typical Wastes
Isolation Wastes Wastes from patients with diseases considered communicable and requiring isolation
Cultures and Stocks of Infectious agents and associated biologicals
Specimens from medical and pathological laboratories
Cultures and stocks of infectious agents from clinical, research and industrial laboratories, disposable culture dishes, and devices used to transfer, inoculate and mix cultures
Wastes from the production of biologicals
Discarded live and attenuated vaccines
Human blood and Blood Products Waste blood, serum, plasma and blood products
Pathological Wastes Tissue organs, body parts, placenta, blood and body fluids removed during surgery, autopsy and biopsy.
Contaminated Sharps Contaminated hypodermic needles, syringes, scalpel blades, Pasteur pippettes and broken glass.
25
Collection and Transportation
Developer shall collect the waste from each health care establishment on a regular basis.
Wastes shall be segregated as per the colour coding, properly packed and placed at a
secure designated point by the health care establishment from where developer shall collect
the waste. Upon collection wastes shall be placed into closed containers enclosed in a
containerized vehicle. Transportation of the wastes shall also be the responsibility of
developer.
The proposed vehicles shall be dedicated for the purpose and shall adopt the conditions
specified in the BMW (Management & Handling) Rules-1998.
Disinfection and Destruction
Upon receipt at the facility, wastes containers shall be unloaded. Wastes based on their
colour codes shall be separated and properly treated and disposed off. Categories 1, 2, 3
and 6 (as per MoEF rules) shall be directly loaded into the incinerator while categories 4 and
7 shall be loaded into the autoclave for dis-infection. Residue from these units shall be
disposed into a landfill. Detailed process description of the treatment technologies is
presented in the subsequent sections.
Disposal
Ash, residue from high temperature incineration and other material residues from the
process shall be collected into containers and shall be disposed into a secure landfill.
Treatment Technologies
Incineration
Incineration incorporates the right technology featuring for a complete destruction of the
waste into completely safe end products. A process combination of pyrolysis and controlled
air combustion, where heat and air for combustion is regulated in such a way as to first
volatalise/ gasify the waste in conditions of inadequate air, i.e., below stochiometric air
conditions and heat, and then totally destroy it in adequate heat and excess air, thereby
making the end products environmentally safe. The process is not only safe but is also
today’s answer to the rampant problem of hospital waste management and pollution.
The primary purpose of incineration is to burn the waste to ashes through a combustion
process. Developer intends to set up incinerators of optimum capacity at each of the
locations. The unit shall be a dual chambered incinerator.
26
The primary chamber’s main purpose would be combustion of the waste materials into safe
end products (ash). The temperature of the primary chamber would be 850o C and above
wherein wastes are completely destroyed. The primary chamber would have an attached
burner with auxiliary fuel supply to augment the fuel requirements and ensure maintenance
of temperatures. The purpose of the secondary chamber would be to burn the off-gases and
ensure safe end products (gaseous). The secondary chamber would operate at a
temperature of 1050o C and above. The gases would be completely burnt and safe gases
then shall be let out of the incinerator unit.
Both the primary and secondary burners proposed are imported Italian burners. The
incinerator is completely automated with control panel and continuous recording of
temperatures. The entire system is very simple and is easy to operate. The system is
environmentally safe without any hazard.
E - Waste Recycling
1. Upon client request, developer shall arrange a suitable and secured transport to
collect the material from Clients premises.
2. Collected material shall be weighed, if desired by clients at their premises using their
own weighing machine and witnessed by both Developer & Client personnel.
3. Manifest to be issued by generator to transport with 6 coloured copies as per HW
Rules, 2008.
4. Delivery Order will be issued by Client prior to collection from their premises.
Collected material is to be provided in good packaging condition and thereafter will
be transported to the facility.
5. After inspection by Developer security guard, material shall be weighed at Developer
weighbridge to determine the gross weight of the material and will then be sent to its
warehouse for acceptance.
6. Goods Receive Note (GRN) for the gross weight will be issued upon receiving the
material at the warehouse.
7. Material will then be sent for dismantling section under IDO (Internal Delivery Order)
for dismantling.
8. Destruction process can be witnessed by Client, if required.
9. Upon data destruction completed, official destruction certificate will be issued to
Client for records.
10. Dismantled material will then be sent to suitable recycling process.
27
Process Flow Sheet:
Process description
The process involved in proposed facility is basically physical destruction and recovery of
PGM’s. The steps of proposed process is described in following paragraphs
The e-waste received from generator shall be stored at earmarked covered shed
having concrete floor and leak proof roof. Wooden or plastic pallets shall be provided
to store the waste.
Metal Non- Metal
To auth.
auth.
Recyclers To auth. Recyclers
CRT Cutting Machine
Glass
Other E-waste (PCB’s)
Shredding
Crushing
Separation
Generator
Collection
Transportation
Storage
Dismantling
To auth. Recyclers
28
Waste which may contain mainly electronic and electrical material and monitors of
computer or TV’s, shall be shifted to manual dismantling section in hand trolleys
A set of 8 to 10 no. of work stations are proposed with a suction hood for any dust
particle coming out of the dismantling process. A team of experts in dismantling shall
be deputed for dismantling purpose with all the required tools and tackles. The tools
and tackles shall be identified with best available brand to ensure optimization in
working and to avoid small accidents in the process. The employees at this section
shall be provided with all the required PPE’s i.e. apron, safety shoes, gloves, dust
mask etc. Fire extinguishers shall be provided in the working area.
The team deputed shall dismantle all the waste articles Eg computer CPU box, hard
drive, CD ROM, cables, PCB’s etc. and monitor into back cover and picture tube. The
hard drive, PCB’s shall be further dismantled into components attached and naked
PCB’s
The dismantled PCB’s shall be sent for shredding followed by crushing and
pulverizing. The product shall be powder of PCB from which metal and non metal
part which shall be segregated by physical process. Both the products shall be stored
in bags for disposal for recovery (metal part) and for making of toys and monuments
(non metal part). In case the non- metal part fails to be recycled, the same shall be
disposed into incinerator as this consists of residue with high C.V.
The dismantled picture tube shall sent to CRT cutting m/c, which is a closed chamber
attached with a hood connected to cyclone and baghouse. The CRT shall be put into
the control panel connected automatic CRT cutting frame. The CRT shall be cut into
two pieces i.e. front glass and funnel glass.
The glass which is free from all coating etc shall be crushed further and stored in
bags to be dispatched for recycling
The components removed from PCBs shall be segregated and stored in bags for
further disposal and/or reuse.
The ferrous material i.e. cabinet, body of monitor etc shall be baled and disposed for
recycling
Plastic from cabinet, monitor shall be shredded in the shredder and sold out for
recycling to authorized recyclers
The chemical process for recovery of PGM shall be established during phase – II
The waste generated from above process shall be stored at earmarked area with all
the provision by not allow in this waste to be exposed to the environment.
29
Alternate Fuel & Raw Material Facility
Alternative fuel platforms will be developed with in a area of 25 x 50 m as below:
“S” Type
Alternative Fuel Preparation Facility
“L”Type
Alternative fuel preparation Facility
‘L’ Type Alternative Fuels Area:
‘L’ Type Alternative Fuels are basically Liquid Type Incinerable Waste which are more than
2500 Kcal.
- Common Neutralization Tank to maintain pH level 7
- 25 KL Mixing Tank with Cooling Coil and External Jacket to control the heat for
Exothermic Liquid Waste
- 25 KL Mixing Tank for the Non-Exothermic Liquid Waste
- Agitator set up made by Stainless Steel
- Pump
‘S’ Type Alternative Fuels Area:
‘S’ Type Alternative Fuels are basically Solid Type Incinerable Waste which are more than 2500 Kcal
1. Common Neutralization Tank to maintain pH level 7 2. Mixing pit of 5 x 5 m
3. Jaw mixer for premixing of the solid and semisolid Waste.
4. Blender
Solid blend is prepared through mixing in an appropriate quantity of solid/ semi solid
waste with binders. The first step of preparing solid blend is to selection of waste.
The segregation of waste according to their pH & calorific value helps in it. Source
materials for solid substitute fuel include Paint Sludge, Oily Filter Cake, Spent Carbon,
Organic waste, Tarry waste, Biomass, Resin, Distillation Residues, Grease, ETP
sludge, and alumina sludge etc.
Assortment of waste is done according blending norms.
A general waste selection criteria for high calorific value fuel is Low moisture content,
High LOI & TOC, High calorific value, Good compressibility, Less ash content, Non
toxic, Less pollutant, Sustainable combustion.
30
Solvent Recovery Unit
Spent solvents are recovered using a distillation methodology. Following are few solvents
proposed to be separated /distilled initially:
1. Isopropyl alcohol
2. Butanol
3. Dimethyl formamide
4. Toluene and
5. Ortho dichloro benzene
Storage of spent solvents
The waste solvent shall be received in durms (MS/Plastic) and shall be stored in
shed which will be provided with garland drain, fire hydrant system, lined floor etc.
The drums shall be stacked as per the best practices. The leakages shall be avoided
at any point of time.
A separate storage shed sized 35 X 40 m is proposed adjacent to facility to store the
solvent drums.
The stacking of drums shall be in the manner that mixing of solvent drums shall be
avoided at maximum extent.
Distillation process is suitable for the recovery of many spent solvents. Distillation can be a
batch or continuous operation. It is proposed to adopt batch process in the proposed facility.
The process involves pre-treatment of neutralization and separation of spent solvent feed
mixture in a Reactor. After layer separation, the spent solvent mixture will be sent to distillation
still connected to distillation column.
The solvent mixture is heated by steam and the distillation column will be under total reflux for a
specific period. Fractionation of solvent takes place solvent / water as the case may be are
separated initially under atmospheric pressure and later under vacuum (if required). Distilled
solvents are analyzed, stored and recycled, liquid effluent mostly condensate will be recycled
back into system and solid residue sent for incineration / landfill. Steam for heating will be donor
from the boiler. The process diagram of the solvent recovery is depicted below:
31
Incinerator
Cooling Tower
Chiller
Main Product
receiver
Solvent received in
Drums
Pre - Treatment
( Adjusting pH,
removal of SS etc.)
Pump
Feed Tank
Pump
Agitated Vessel
Sludge
Column
Condenser
Cooler
Trail product receiver
Collection Tank Collection Tank
Pump
Feed Tank/
Incinerator
Pump
Drums
Process diagram of the solvent recovery
32
Waste Oil / Used Oil Recycling Unit
Used oil is termed as hazardous. Lube oil does not wear out with use it only gets
contaminated with water, carbon and fuel etc. that means used oil when it is ready for
rejection can be re-used.
The methods of disposal being followed are Dumping, Burning or Reprocessing. The Used / Waste Oil generated are not easily biologically degradable. Therefore, dumping of Used / Waste oil is harmful to environment.
Burning of Used / Waste Oil is not desirable for the following reasons:
Waste Fuel Oil contains substantial quantity of water that will prevent proper burning of fuel and lead to generation of carbon monoxide. In the case of Used Oil (used lubricants, Transformer oils etc), they may contain chemicals, metallic compounds, Polychlorinated Biphenyl (PCBs) etc which when burned will release gas to the atmosphere. Therefore, burning of used / Waste Oil should not be encouraged.
The other option is Repressing. Improper reprocessing methods can lead to generation of waste which is even more hazardous than Used / Waste Oil. Therefore, reprocessing should be allowed only with approved methods. Reprocessing of Used / Waste will not only be a solution for disposal of waste but it will have tremendous economic advantage.
The process diagram of the waste/ used oil recycling plant will be as below:
Was te Oil R ec eiv ing Tanks
Was te Oil R ec eiv ing Tanks
MIC R O F IL TR ATION
MIC R O F IL TR ATION
C E NTR IF UG EC E NTR IF UG E DE HY DR ATION
DE HY DR ATION
Dis tillation 1 (v ac uum Dis tillation )
Dis tillation 1 (v ac uum Dis tillation )
Water Water
Dis tillation 2 (Vac uum Dis tillation)
Dis tillation 2 (Vac uum Dis tillation)
Distillate to
fuel
B leac hingB leac hingB as e Oil for dis patc h
B as e Oil for dis patc h
Spent Fuller Earth
for disposal
Base OilBase Oil
Process Sludge
for disposal
33
Lead Recycling Unit
Lead is a soft heavy toxic and highly malleable metal. It is bluish white when freshly cut but
tarnishes to dull gray when exposed. It is usually found in ore with zinc, silver and more
commonly with copper.
The schematic diagram of the lead and lead alloys is given in Figure Extraction of Lead from
used Lead Acid Battery Plates, Lead Scrap, lead dross and other lead bearing wastes by
using Rotary Furnace and Reverberatory Furnace.
Conventional method of lead extraction from used lead acid battery plates, lead scrap, lead
dross and other concentrate generates huge amount of sludge which becomes very difficult
for disposal in the landfill. However, the combination of rotary furnace and Reverberatory
furnace with high calorific furnace oil as fuel reduces the quantum of slag generation and
improves the recovery of lead metal considerably. Furnace oil will be used as fuel to melt the
battery and other scrap.
Schematic Diagram of Lead and Lead alloys manufacturing
34
Annexure-6
Wastewater generation details in m3/day
Sl. No Utility Discharge
cum/day
1 Domestic 4.0
2 Floor Washings 2.0
3 Work Shop/ Vehicle maintenance shed 4.0
4 Hazardous waste treatment -
5 Bio medical waste 2.0
6 Recycling -
7 Green belt -
Total 12.0
35
Annexure-7
Water Requirement details in m3/day
Sl. No Utility Total requirement
cum/day
1 Domestic 5.0
2 Floor Washings 3.0
3 Work Shop/ Vehicle maintenance shed 5.0
4 Hazardous waste treatment 5.0
5 Bio medical waste 3.0
6 Recycling -
7 Green belt 4.0
Total 25.0