THE ARGUMENT FOR AN ASSET MANAGEMENT FRAMEWORK
FORCE MAINS – THE CHALLENGING ASSETS
Mark Seastead
NC AWWA-WEA 96TH ANNUAL CONFERENCE
• 7.5% of collection systems nationwide are composed of forcemains (WERF, 2004)
• Difficult to inspect – often need to be taken out of service
• Often do not have redundancy
• Typically have a high Consequence of Failure (CoF)
COMMON BACKGROUND WITH FORCEMAINS
3Courtesy: St. Louis,Metro Sewer District
• Unlike Gravity Systems - NoManhole Access
• Flow tends to be constant
• Location in low –lying areas canpose additional environmentstresses
• Soil conditions
• Moisture
• Corrosivity
COMMON CHALLENGES WITH FORCE MAINS
4
• Failure can be Significant
• Not just overflows
• Sinkholes
• Understand Risk and Incorporate as a Function of the EntireCollection System
• Consequence of Failure
• Likelihood of Failure
• Expected Level of Service to Customers
• Cost of Rehabilitation vs. Replacement
• Expected Remaining Life
• Inspection
• Maintain
• Track
WHAT TO DO?
5
Do theseterms soundfamiliar?
Create / Acquire
Utilize
Maintain
Renew / Dispose
A FRAMEWORK PROVIDES STRUCTURE FORINTEGRATED ASSET MANAGEMENT APPROACH
7
Organizational Strategic Plan
Asset Management Strategy
Asset Management Policy
Asset Management Plans
Asset Management Objectives
Planning
Implementation
Fun
ctio
nal
Pro
cess
es,
Pro
ced
ure
s
Life Cycle Activities Assets
Portfolio of asset systems and individual assets
Thank You WERF - SIMPLE
• Keep it Simple
• What is the current state
• Required level of service
• What assets are critical
• What is my minimum O&M/CIP
• Long-term Funding
AM FRAMEWORK BASICS
8
• Keep it Basic
• Do you know where force mains are located and are theyrecorded electronically?
• Do you know current condition of force mains?
• Do you know the remaining useful life?
• Do you have maintenance and inspection proceduresdocumented, reproducible, and history available?
• Source data:
• GIS, CADD, CMMS, CCTV,
FORCE MAINS – CURRENT STATE
9
• Suggestions
• Review GIS & Asset Registers to assess accuracy of assetdata
• Materials, age, composition, condition, LoF, specialcircumstance, etc.
• Define asset classifications by common attributes (size,material, composition, etc.)
• Develop condition scoring and require latest condition as anasset attribute
• Track historic condition through work orders or inspections
• Review/update inspection frequency based on prioritization
• Track in CMMS, GIS, CCTV, or standardized records.
FORCE MAINS – CURRENT STATE
10
• Keep it Basic
• What is the demand on your force mains?
• Service area, annual throughput, etc.
• What are the regulatory requirements
• What is my actual performance (uptime, reactivemaintenance, planned maintenance, pump performance,etc)?
• Source data: SCADA, GIS, CMMS, CRM/Billing, contractedtesting
FORCE MAINS – LEVEL OF SERVICE
11
FORCE MAINS – LEVEL OF SERVICE
12
Concept Definition Examples
Service Attributes Aspects of service Accessibility, affordability,efficiency, quality, etc.
Levels of Service What the organizationintends to deliver
Safe transport and treatment ofwastewater
CustomerPerformance Measure
How the customerexperiences theservice
Appearance of facilities,frequency of disruptions
Technical PerformanceMeasure
What the organizationdoes to deliver service
Break rate, odor complaints,SSOs,
FORCE MAINS – LEVEL OF SERVICE
Muddy CreekWWTP
Archie ElledgeWWTP
Transfer Force Main
• Suggestions
• Link Level of Service to inspection and/or PM frequency
• Use basic analytic tools - GIS, CMMS history, SCADAhistorian, CRM/Billing to associate volume to pipe location
• Keep it Basic
• Do I know key failure modes?
• What is LoF?
• What is CoF?
• Do I know how much is costs to repair?
• Are force mains prioritized by criticality?
• Source data: CMMS or manual inspection records, AssetManagement Plans, Decay Curves, GIS
FORCE MAINS – CRITICALITY
14
• Keep it Basic
• Do I know key failure modes?
• What is LoF?
• What is CoF?
• Do I know how much is costs to repair?
• Are force mains prioritized by criticality?
• Source data: CMMS or manual inspection records, AssetManagement Plans, Decay Curves, GIS
FORCE MAINS – CRITICALITY
15
• Suggestions
• Begin and track failure mode analysis
• Define priority
• Probability of Failure (PoF)xConsequence of Failure (CoF)= Risk
• Add parameters to suit your complexity (e.g. redundancy)
• PoF x CoF x Redundancy = Risk w/ expure
FORCE MAINS – CRITICALITY
16
Capacity10%
Internal Corrosion26%
External Corrosion19%
Surge Pressure10%
Joint Leakage15%
3rd Party Damage20%
WERF Defined Ferrous Force Main Failures (2010)
• Basic Info:• Pipe Length
• Pipe Material
• Pipe Age
• Pipe Break Data
• Material in Pipe
FORCE MAINS – SAMPLE PROBABILITY OFFAILURE
17
GIS Data CMMS Data
• Basic Info:• Pipe Diameter
• Pipe Alignment
• Pipe Location
• Est. Duration ofServiceInterruption
• Adjacent LandUse
FORCE MAINS – SAMPLE CONSEQUENCE OFFAILURE
18
GIS Data LOS/CMMS Data
• Keep it Basic
• Do I need redundancy?
• What alternatives exist?
• How frequently do I inspect, clean, test, etc.?
• Do failure response plans exist?
• What CIP planning exists?
• Source data: CIP tools, CMMS or inspection records,Asset Management Plans, GIS, Document Management
FORCE MAINS – O&M STRATEGIES
19
• Keep it Basic
• Aggregated costs of force mains and components
• Define management strategies by asset class
• Optimized financial strategy
• Does it fit within my overall asset management plan
• How confident can you tell this story?
• Source data: CIP tools, CMMS or inspection records,Asset Management Plans, GIS, Document Management
FORCE MAINS – FUNDING STRATEGIES
20
• GIS, CADD, CMMS, CCTV
• SCADA, GIS, CMMS, CRM/Billing,Specialized Testing (ultrasonic, EM,RFEC, Pigging/Cleaning Balls, LeakDetection)
• CMMS, GIS, Hard Copy, AMP, O&M,Decay Curves, Leak Detection
• CIP tools, CMMS or inspectionrecords, Asset Management Plans,GIS, Document Management
• What do I have and where?
• Level of Service
• Criticality
• O&M Strategies & Funding
COMMON DATA SOURCES
22
CMMS InspectionCondition
AssessmentsCCTV
Specialized TestingPigging/Cleaning
CMMS InspectionCondition
AssessmentsCCTV
Specialized TestingPigging/Cleaning
23
PDProgramDevelopment &Implementation
AM ProgramStrategic AM & Tactical AMP
AMISAssetManagementInformation Systems
Pump AssetsLinear Assets
BRE & CIPBusiness Risk Exposure& CIP ProjectIdentification
FRAME-WORK
GIS
WBMDWeb-Based ManagementDashboards
PERFORMANCEMANAGEMENTDASHBOARDS
CCPComprehensiveCIP Prioritization
CIP PRIORITIZATION
GOOD DATA AND PROCESSESSUPPORT GOOD DECISIONS
23
SUP
PO
RTIN
GTO
OLS
(INFO
SYSTEM
S)
GIS orCMMS/Other
Example: Potential Software Linkages
24
GIS HydraulicModels
PipelinePrioritizationCMMS
CapacityAssessment
CIP
PipeInspection
Tools
- Asset Management- Engineering Management
Common IntegrationRecommended Integration
• Force Mains are a fact of life
• They are more challenging to assess and manage
• Using basic tools common in your organizationsnow to improve and track management
• Apply an Asset Management Framework
• Consolidate data and share between systems
SUMMARY