1 For updated estimate cost upto Rs.20 lakh Office SEEPAT ROAD POST BOX No. : 60 BILASPUR (C.G) पो.आ. : गेवरा ोजेट िजला : कोरबा (छ.ग.) पन : 495452 Under Jurisdiction of Korba Court only साऊथ ईटन कोलफस लमटेड SOUTH EASTERN COALFIELDS LIMITED (A Subsidiary of Coal India) OFFICE OF THE Dy GM (CIVIL) GEVRA AREA CIN (U10102CT1985GO1003161) FAX : 07815-275434 GRAM : GEVRA COAL PHONE : 07815-275438 (o) P.O. : GEVRA PROJECT DISTT. : KORBA (C.G.) PIN 495452 NIT No. SECL/GM/GA/DyGM(C)/e-Tender/2018-19/172 Date : 05.03.2019 e-TENDER NOTICE 1. Digitally signed and encrypted e-Tenders are invited under Two Part system on the website https://coalindiatenders.nic.in from the reputed and experienced contractors for the following work: Description of work Location Estimated Value (Updated Cost) (in Rs.) Earnest Money (in Rs.) Period of Completion (in Days) Development work around water ATM Urja Nagar colony of Gevra Area. TA, Gevra Area 2,94,428.00 3,700.00 30 days Details of GST Registration of SECL : GSTIN of SECL Chhattisgarh (CG) Madhya Pradesh (MP) West Bengal (WB) 22AADCS2066E9ZL 23AADCS2066E1ZR 19AADCS2066E1ZG Salient Details of Tender : Goods & Services Tax (GST) Applicable Input Tax Credit (ITC) to SECL Not-Applicable Price Variation Clause (Escalation) Not-Applicable Payment of Wages to Contractor’s Labours As per Minimum Wages Act Participation of Joint Venture Not Allowed Note : 1. NIT and Bid documents will be available on the website https://www.coalindiatenders.nic.in and can be downloaded by the bidder up to the bid submission end date. The details of the tender will be mirrored on the Central Public Procurement (CPP) Portal of Govt. of India (https://eprocure.gov.in) 2. Time Schedule of Tender SL. No. Particulars Date Time a. Tender e-Publication date 08/03/2019 10.00 hour b. Document download start date 08/03/2019 10.00 hour c. Document download end date 23/03/2019 17.00 hour d. Bid Submission start date 09/03/2019 10.00 hour e. Bid submission end date 23/03/2019 17.00 hour f. Start date for seeking Clarification on-line 08/03/2019 10.00 hour g. End date for seeking Clarification on-line 16/03/2019 17.00 hour h. Date of Pre-bid Meeting NA NA i. Date of Bid Opening [Cover-I (Technical-bid) and Cover-II (Price-bid)] 26/03/2019 11.00 hour 3. Deposit of EMD

Transcript of For updated estimate cost upto Rs.20 lakh Under ... coalfield.pdf · contractor will be taken into...

1

For updated estimate cost upto Rs.20 lakh

Office SEEPAT ROAD

POST BOX No. : 60

BILASPUR (C.G) पो.आ. : गेवरा �ोजे�ट

िजला : कोरबा (छ.ग.)

�पन : 495452

Under Jurisdiction of Korba Court only

साऊथ ई�टन कोलफ���स �ल�मटेड

SOUTH EASTERN COALFIELDS LIMITED (A Subsidiary of Coal India)

OFFICE OF THE Dy GM (CIVIL)

GEVRA AREA

CIN (U10102CT1985GO1003161)

FAX : 07815-275434 GRAM : GEVRA COAL PHONE : 07815-275438 (o) P.O. : GEVRA PROJECT DISTT. : KORBA (C.G.) PIN 495452

NIT No. SECL/GM/GA/DyGM(C)/e-Tender/2018-19/172 Date : 05.03.2019

e-TENDER NOTICE

1. Digitally signed and encrypted e-Tenders are invited under Two Part system on the website https://coalindiatenders.nic.in from the reputed and experienced contractors for the following work:

Description of work Location Estimated Value

(Updated Cost)

(in Rs.)

Earnest

Money

(in Rs.)

Period of

Completion

(in Days)

Development work around water ATM Urja Nagar colony of Gevra Area.

TA, Gevra Area

2,94,428.00 3,700.00 30 days

Details of GST Registration of SECL :

GSTIN of SECL Chhattisgarh (CG) Madhya Pradesh (MP) West Bengal (WB) 22AADCS2066E9ZL 23AADCS2066E1ZR 19AADCS2066E1ZG

Salient Details of Tender :

Goods & Services Tax (GST) Applicable

Input Tax Credit (ITC) to SECL Not-Applicable

Price Variation Clause (Escalation) Not-Applicable

Payment of Wages to Contractor’s Labours As per Minimum Wages Act

Participation of Joint Venture Not Allowed

Note : 1. NIT and Bid documents will be available on the website https://www.coalindiatenders.nic.in

and can be downloaded by the bidder up to the bid submission end date. The details of the

tender will be mirrored on the Central Public Procurement (CPP) Portal of Govt. of India

(https://eprocure.gov.in)

2. Time Schedule of Tender

SL.

No.

Particulars Date Time

a. Tender e-Publication date 08/03/2019 10.00 hour

b. Document download start date 08/03/2019 10.00 hour

c. Document download end date 23/03/2019 17.00 hour

d. Bid Submission start date 09/03/2019 10.00 hour

e. Bid submission end date 23/03/2019 17.00 hour

f. Start date for seeking Clarification on-line 08/03/2019 10.00 hour

g. End date for seeking Clarification on-line 16/03/2019 17.00 hour

h. Date of Pre-bid Meeting NA NA

i. Date of Bid Opening [Cover-I (Technical-bid) and Cover-II

(Price-bid)]

26/03/2019 11.00 hour

3. Deposit of EMD

2

The bidders have to make payment of EMD either through Net-banking or through NEFT/RTGS from any scheduled Bank. In case of payment through Net-banking the money will be immediately transferred to SECL’s designated Account. In case of payment through NEFT/RTGS the bidder will have to make payment as per the Challan generated by system on e-Procurement portal. Bidder will be allowed by the system to submit the bid only when the EMD is successfully received in SECL’s account and the information flows from Bank’s Server to e-Procurement portal.

4. Pre-bid Meeting : The pre-bid meeting shall be held in the office of Tender Inviting Authority on the scheduled date & time, if specified online. Non-attendance of pre-bid meeting will not be a cause for disqualification of the bidder and it shall be presumed that the bidder does not require any clarification. The purpose of Pre-bid meeting is to clarify the issues raised by bidders during the meeting. In case the Pre-Bid Meeting is held, the Minutes of Pre-Bid Meeting will be uploaded on the e-Procurement Portal.

5. Seeking Online Clarification by bidder : The bidder may seek clarification online within the specified period. The identity of the Bidder will not be disclosed by the system. The department will clarify as far as possible the relevant queries of bidders. The clarifications given by department will be visible to all the bidders intending to participate in that tender.

6. Eligibility Criteria:-

A. Work Experience: Work value excluding Good & Service Tax (GST) amount shall be considered for evaluation under eligibility criteria for work completed after 01.07.2017 (As per circular No.GM(C)/SECL/BSP/Circular/2018-19/174 dtd. 24.05.2018 The Intending bidder must have in its name or proportionate share as a member of Joint Venture experience of having successfully completed similar works, as a prime contractor, during last 7 (seven) years ending last day of month previous to the one in which bid applications are invited (i.e. eligibility period) should be any of the following :-

Three similar completed works each costing not less than the amount equal to 40% of the estimated cost put to tender.

OR Two similar completed works each costing not less than the amount equal to 50% of the estimated cost put to tender.

OR One similar completed work costing not less than the amount equal to 80% of the estimated cost put to tender.

Definition of Similar Work shall be: “Building construction and /or repair & maintenance of building

work, OR works identical in name & nature of the tendered

work”

Experience for those works only shall be considered for evaluation purposes, which match eligibility requirement stipulated above, on or before the last day of month previous to one in which tender has been invited (e-Publication date of NIT i.e. date of publication of NIT on e-Procurement portal, https://coalindiatenders.nic.in). The experience of incomplete/ongoing works as on last date of eligibility period will not be considered for evaluation. If the referred work includes construction as well as maintenance after construction, the experience of such work may be considered as ‘acceptable’ if the construction part is completed as on the last date of ‘eligibility period’, even if maintenance work is ongoing, and the certificate issued clearly stipulates the same .

In all the above cases, while considering the value of completed works, the full value of completed work be considered whether or not the date of commencement is within the said 7(seven) years period.

3

Cost of previous completed works shall be given a simple weightage of 5% per year to bring them at current price level, while evaluating the qualification requirement of the bidder. Such weightage shall be considered after end date of completion. Updating will be considered for full or part of the year (total no. of days / 365) i.e. considering 365 days in a year, till the last day of month previous to one in which bid has been invited (e-Publication date of NIT i.e. date of publication of NIT on e-Procurement portal, https://coalindiatenders.nic.in).

In case the bidder is not a prime contractor, but a sub-contractor, the bidder’s experience as sub-contractor will be taken into account, against suitable document that the contract in support of qualification is a sub-contract in compliance with the provision of such sub-contracts in the original contract awarded to prime contractor. The document may be issued by owner/Govt. department on behalf of the owner.

For work experience bidders are required to submit Satisfactory Work Completion Certificate indicating actual value of work done and actual period of execution, issued by the employer against the Experience of similar work containing all the information as sought online. In case of Sub-contractor suitable document as per provision of eligibility, if applicable.

Work order, BOQ and/or TDS may be sought during clarification or along with deficient documents.

[Joint Venture (JV) shall not be allowed to participate in the tender with estimated cost upto Rs.2.00

Crores]

In respect of the above eligibility criteria the bidders are required to furnish the following information on-line:

i) Name of work for each experience ii) Work order Number /Agreement Number of each experience

iii) Name & address of Employer/Work Order Issuing authority of each experience iv) Percentage (%) share of each experience (100% in case of an Individual/ proprietorship firm or a

partner in a partnership firm and the actual % of share in case of a Joint Venture). v) Executed Value of work against each experience

vi) Start date & end date of each experience

Note : In case the bidder is a Joint Venture, work experience of any of the partners of JV may be furnished as the work experience of the bidder.

B. Financial Turnover

Average annual financial turnover during the last 3 (three) years, ending 31st March of the previous financial year should be at least 30% of the estimated cost put to tender.

(The “Previous financial year” shall be computed with respect to the e-Publication date of NIT)

The intending bidder must submit the Turnover certificates issued by a Practicing Chartered Accountant having a membership number with Institute of Chartered Accountants of India containing the information as furnished by bidder on- line.

The qualifying criteria parameter e.g. financial resources (Turnover) of the individual partners of the J.V. will be added together, for the relevant financial year, and the total should not be less than as spelt out above.

Financial turnover shall be given a simple weightage of 5% per year to bring them at current price level, while evaluating the qualification requirement of the bidder. Such weightage shall be considered from

4

the end date of financial year. Updating will be considered for full or part of the year(total no. of days / 365) i.e. considering 365 days in a year, till the last day of month previous to one in which bid has been invited (e-Publication date of NIT i.e. date of publication of NIT on e-Procurement portal, https://coalindiatenders.nic.in).

In respect of the above eligibility criteria the bidders are required to furnish the following information on-line:

i) Annual turnover of each of the last 3 years ending 31st March of the previous financial year. ii) Name of the Chartered Accountant issuing the Profit and Loss A/c or the Turnover certificate. iii) Membership Number of the CA iv) Date of issue of financial Turnover certificate

Note :

a) If the bidder does not submit turnover value and certificate for any year out of the three years, system will not disqualify him and instead shall consider all three years for computing the average by assuming a value of “zero” for the year(s) for which no information is given by the bidder.

C. Permanent Account Number:

The bidder should possess Permanent Account Number (PAN) Card issued by Income Tax Department, Govt. of India.

In respect of the above eligibility criteria the bidders are required to furnish the following information on line:

i. Confirmation in the form of YES/NO regarding possessing of PAN Card.

D. Goods & Services Tax (GST) Registration :

The bidder should possess either GST Registration Certificate and submit GSTIN OR should submit Certificate from a Practicing Chartered Accountant certifying that the bidder is a GST Unregistered contractor (Supplier) in compliance with the relevant GST Act & Rules.

In respect of the above eligibility criteria the bidders are required to furnish the following information on-line:

i. Confirmation in the form of YES/NO regarding possessing of GST Registration Certificate (with GSTIN) OR Certificate from a practicing Chartered Accountant certifying that the bidder is a GST Unregistered contractor (supplier) in compliance with the relevant GST Act & Rules

7. All the bidders are to submit the information in objective manner confirmed by the uploaded documents. The documents related to the furnished online information, based on which the auto evaluation takes place will only be considered. If the bidder uploads any other document, it will be given no cognizance.

The scanned copy of following documents (valid on the end date of bid submission) will be submitted by the bidder online while submitting bid under Cover-I (Part-I).

Sl

No

Submission of Documents

related to Eligibility Criteria

Scanned copy of documents to be uploaded by bidder in support of

information/ declaration furnished online by the bidder against Eligibility

Criteria (CONFIRMATORY DOCUMENT)

1. Letter of Bid Letter of Bid on the bidder’s letter head, in the prescribed format (Annexure-I).

2. Work Experience a). Satisfactory Work Completion Certificate indicating actual value of work done and actual period of execution, issued by the employer against the Experience of similar work, containing all the information as furnished online.

b). In case of sub-contractor, suitable document as per provision of bid.

c). Copy of Work Order/TDS Certificate/Bill of Quantity (only when clarification is sought)

5

3. Financial Turnover

Financial Turnover certificate for last 3 (three) financial years issued by a Practicing Chartered Accountant having a membership number with Institute of Chartered Accountants of India.

4. Authorization for Digital

Signature Certificate

a). If the bidder himself is the DSC holder bidding on-line then self declaration of the bidder to this effect.

OR b). if the DSC holder is bidding online on behalf of the bidder then the Power of Attorney or any sort of legally acceptable document for authorization to submit bid on behalf of the bidder.

5. Undertaking & Written

Consent for Arbitration

Clause

(a).A commitment is to be uploaded in the form of UNDERTAKING on Bidder’s letter head as per the format given in the bid document (Annexure-II).

(b).WRITTEN CONSENT FOR ARBITRATION CLAUSE in the prescribed format

(Annexure-VIII) : (Applicable for Partnership Firm only)

6. Legal Status of the bidder Any one of the following document :

i. Affidavit or any other document to prove Proprietorship/Individual status

of the bidder.

ii. Partnership deed containing name of partners

iii. Memorandum & Article of Association with certificate of incorporation

containing name of bidder

7. Permanent Account Number (PAN)

PAN Card issued by Income Tax department, Govt. of India.

8. Goods & Services Tax (GST) Registration

(a).For GST Registered Bidders : GST Registration Certificate with GSTIN (Form GST REG-25)

OR

(b).For GST Unregistered Bidders : Certificate from a practicing Chartered Accountant certifying that the bidder is a GST unregistered contractor (supplier) in compliance with the relevant GST Act & Rules.

Note: Only one file in .pdf format can be uploaded against each eligibility criteria. Any additional/ other relevant documents to support the information/declaration furnished by bidder online against eligibility criteria may also be attached by the bidder in the same file to be uploaded against respective eligibility criteria.

8. Submission of Bid:

All the bids are to be submitted online and on the website https://coalindiatenders.nic.in. No bid shall be accepted offline.

a. The bidder should strictly comply with following instructions :

i. The bidders are requested to submit offers online in two parts in the links Cover-I and Cover-II.

ii. Two parts of the bid should contain the details as follows:

Part-I/Cover-I :

Letter of bid Details of Earnest Money Information on Eligibility/Qualifying criteria as detailed at Clause No.6 & 7 including necessary scanned documents as elaborated there

Part II/Cover-II : Prices only in the Excel format as indicated in the Bid document.

b. In order to submit the Bid, the bidders have to get themselves registered online on the e-Procurement portal of CIL/Subsidiary (https://coalindiatenders.nic.in) with valid Digital Signature Certificate (DSC) issued from any agency authorized by Controller of Certifying Authority (CCA), Govt. of India and which can be traced up to the chain of trust to the Root Certificate of CCA. The online Registration of the

6

Bidders on the portal will be free of cost and one time activity only. The registration should be in the name of bidder, whereas DSC holder may be either bidder himself or his duly authorized person. The bidder is one whose name will appear as bidder in the e-Procurement Portal.

c. The bidders have to accept the on-line user portal agreement which contains the acceptance of all the Terms and Conditions of NIT and Bid document, undertakings and the e-Tendering system through eProcurement Portal of CIL (https://coalindiatenders.nic.in) in order to become an eligible bidder. This will be a part of the agreement.

d. Letter of Bid : The format of Letter of Bid (Annexure-I) will be downloaded by the bidder and will be printed/typed on his letter head. This document will be signed by the bidder or authorized person of the bidder or DSC holder bidding with authorization from bidder and the scanned copy of the same will be uploaded during bid submission in cover-I. This will be the covering letter of the bidder for his submitted bid. The content of the “Letter of Bid” uploaded by the bidder must be the same as per the format downloaded from website and it should not contain any other information.

If there is any change in the contents of Letter of Bid uploaded by bidder as compared to the format of Letter of Bid uploaded by the department with NIT document, then the bid will be rejected.

e. Confirmatory Documents :

All the confirmatory documents as enlisted in the NIT in support of online information furnished by the bidder are to be uploaded in Cover-I by the bidder while submitting the bid online.

f. Price Bid (Part-II) :

The Price bid containing the Bill of Quantity will be in .xls format (password protected) and will be uploaded during tender creation. This will be downloaded by the bidder and he will quote the rates for all items on this Excel file. Thereafter, the bidder will upload the same Excel file during bid submission in Cover-II. The Price-bid will be in Item Rate or Percentage Rate BOQ format and the bidder will have to quote for all the tendered items and the L-1 will be decided on overall quoted value (i.e. Cost to company). The Price-bids of the tenderers will have no condition. The Price Bid which is incomplete and not submitted as per instruction given above will be rejected. Any alteration/modification in the Excel format may lead to rejection of bid.

The rates quoted by bidder shall be inclusive of all Taxes, if any applicable, after implementation

of GST as per Govt. Notification, but excluding Goods & Service Tax (GST) and State Compensation

Cess (if applicable).

The system will compute the amount of GST and State Compensation Cess, as per predefined logic in the BOQ sheet.

Prior to quoting the rates in the BOQ sheet, the bidder will select the appropriate GST Status from the following list given in the BOQ sheet :

i). GST Registered Bidder ii).GST Unregistered Bidder

The Price bid file will be digitally signed and uploaded by the bidder in Part-II/Cover-II.

Decision about L-1 :

The L-1 will be decided based on “COST TO COMPANY” in the following manner :

(i). If Input Tax Credit is Applicable :

COST TO COMPANY = Quoted Price of Bidder excluding GST and State Compensation Cess.

(ii). If Input Tax Credit is Not Applicable :

COST TO COMPANY = Quoted Price of Bidder excluding GST and State Compensation Cess (+) Amount

of GST (+) State Compensation Cess.

7

For GST Registered Bidders, the Payment/ deposit of GST and State Compensation Cess (if applicable) is

the responsibility of the Contractor (Supplier). However, in case the contractor is Unregistered under

GST as per GST Act & Rules, the GST and State Compensation Cess (if applicable) will be deposited by

SECL directly to the concerned authorities under Reverse Charge Mechanism.

Payment of GST and State Compensation Cess (if applicable) would be made to the Contractor only on

submission of Bill/Invoice in accordance with the provision of relevant GST Act & Rules and after filing

of return online on the GST Portal. Input Tax Credit is to be availed by SECL as per rule.

9. It is the bidder’s responsibility to comply with the system requirement i.e. hardware, software and internet connectivity at bidder’s premises to access the e-tender portal. Under no circumstances, CIL/Subsidiary shall be liable to the bidders for any direct/indirect loss or damage incurred by them arising out of incorrect use of the e-tender system or internet connectivity failures.

10. Extension of Time Schedule of Tender :

If the number of bids received online is less than three on the end date of bid submission then the bid submission end date, bid opening date and date of Reverse Auction will be automatically extended by the System, initially for a period of two days and if the number of bids still remains less than three then for another five days.

11. Opening of Bid :

i) Tenders [Cover-I (Technical-bid) and Cover-II (Price-bid)] will be decrypted and opened online by the Bid Openers with their Digital Signature Certificate (DSC) on the pre-scheduled date & time of tender opening.

ii) The e-Procurement system will evaluate the Technical bids automatically on the basis of relevant data provided by the bidder while submitting the bid online. If the parameters furnished by bidder online in an objective and structured manner does not confirm to the required eligibility criteria as specified in the NIT, the bid will be automatically rejected by the system and the Price-bid of such bidders shall not be opened by the system.

iii) After decryption and opening of bids, the Comparative Statement showing the status of bidders will be generated by the System.

12. Evaluation of Tender :

i) After Opening of Price-bid, the documents submitted by L-1 bidder in Cover-I will be downloaded by the Evaluator and shall be put up to the Tender Committee. The Tender Committee will examine the uploaded documents against information/declarations furnished by the L-1 bidder online. If it confirms to all of the information/ declarations furnished by the bidder online and does not change the eligibility status of the bidder then the bidder will be considered eligible for award of Contract.

ii) In case the Tender Committee finds that there is some deficiency in uploaded documents by L-1 bidder then the same will be specified online by Evaluator clearly indicating the omissions/shortcomings in the uploaded documents and indicating start date and end date allowing 7 days (7 x 24 hours) time for online re-submission by L-1 bidder. The L-1 bidder will get this information on their personalized dash board under “Upload confirmatory document” link. Additionally, information shall also be sent by system generated email and SMS, but it will be the bidder’s responsibility to check the updated status/information on their personalized dash board regularly after opening of bid. No separate communication will be made in this regard. Non-receipt of e-mail and SMS will not be accepted as a reason of non-submission of documents within prescribed time. The bidder will upload the scanned copy of all those specified documents in support of the information/ declarations furnished by them online within the specified period of 7 days. If the L1 bidder fails to submit the specified document/s in 7 (Seven) days time or the uploaded documents still contain some deficiency, additional time of 5 days

8

(5 x 24 hours) shall be given to the L-1 bidder for re-submission, indicating start date and end date for re-submission of such document/s.

iii) The tender will be evaluated on the basis of documents uploaded by L-1 bidder online. The L-1 bidder is not required to submit hard copy of any document through offline mode. Any document submitted offline will not be given any cognizance in the evaluation of tender.

iv) In case the L-1 bidder submits requisite documents online as per NIT, then the bidder will be considered eligible for award of Contract.

v) In case the L-1 bidder fails to submit requisite documents online as per NIT or if any of the information/declaration furnished by L-1 bidder online is found to be wrong by Tender Committee during evaluation of scanned documents uploaded by bidder, which changes the eligibility status of the bidder, then his bid shall be rejected and EMD of L-1 bidder will be forfeited.

vi) In case the L-1 bidder is technically eligible but rejection is due to high rate quoted by him then the tender shall be cancelled and retendered.

vii) In case the L-1 bidder is rejected due to non-compliance of confirmatory documents, then the L-2 bidder will become L-1 bidder and confirmatory documents of L-2 bidder shall be evaluated by Tender Committee and the process shall be followed as mentioned in clause No. (i) to (vi) above.

viii) The process as mentioned at Clause No.(vii) shall be repeated till the work is either awarded or all the eligible bidders are exhausted.

ix) In case none of the bidders complies the technical requirement, then re-tender will be done.

x) It is responsibility of Bidders to upload legible/clearly readable scanned copy of all the required documents as mentioned above.

13. Bid Validity: The Bid Validity Period will be 120 (one hundred twenty) days from the end date of bid submission. The validity period of tender shall be decided based on the final end date of submission of bids, after extension, if any.

14. Modification and Withdrawal of Bid :

Modification of the submitted bid shall be allowed online only before the deadline of submission of tender and the bidder may modify and resubmit the bid online as many times as he may wish.

Bidders may withdraw their bids online within the end date of bid submission and their EMD will be refunded. However, if the bidder once withdraws his bid, he will not be able to resubmit the bid in that particular tender.

For withdrawal of bid after the end date of bid submission, the bidder will have to make a request in writing to the Tender Inviting Authority. Withdrawal of bid may be allowed till issue of work order/LOA with the following provision of penal action :

1. the EMD will be forfeited and 2. the bidder will be debarred for 1 (One) year from participating in tenders in SECL.

The Price-bid of all eligible bidders including this bidder will be opened and action will follow as under: i). If the bidder withdrawing his bid is other than L-1, the tender process shall go on. ii). If the bidder withdrawing his bid is L-1, then re-tender will be done.

15. Tender Status: It will be the bidder’s responsibility to check the status of their Bid online regularly, after the opening of bid till award of contract. Additionally, information shall also be sent by system generated e-mail and SMS at nodal points (Date of bid opening, Requisition for Clarification on Confirmatory document from L-1 bidder, award of work etc.). No separate communication will be required in this regard. Non-receipt of e-mail and SMS will not be accepted as a reason of non-submission of Confirmatory documents within prescribed time. The Tender Status will be in public domain and anyone visiting the site can view it by identifying the tender.

9

NIT No. SECL/GM/GA/DyGM(C)/e-Tender/2018-19/172 Date : 05.03.2019

16. Refund of EMD to Unsuccessful Bidders:

a. The EMD of rejected bidders will be refunded at any stage directly to the account from where it had been received (except the cases where EMD is to be forfeited).

b. No claim from the bidders will be entertained for non-receipt of the refund in any account other than the one from where the money is received.

c. If the refund of EMD is not received by the bidder in the account from which the EMD has been paid due to any technical reason then it will be paid through conventional system of e-payment. For this purpose, if required, Tender Inviting Authority will obtain the Mandate Form (as per format enclosed at Annexure-III) from the Bidder.

d. In case the tender is cancelled then EMD of all the participating bidders will be refunded unless it is forfeited by the department.

e. If the bidder withdraws his/her bid online (i.e. before the end date of submission of tender) then his/her EMD will be refunded automatically after the opening of tender.

f. The EMD of successful bidder (on Award of Contract) will be retained by SECL and will be adjusted to Performance Security Deposit.

17. The Company reserves the right to postpone the date of receipt and opening of tenders or to cancel the tenders without assigning any reason whatsoever.

18. This Tender Notice shall be deemed to be part of the Contract Agreement. 19. The Company does not bind itself to accept the lowest bid and reserves the right to reject any or all the bid

without assigning any reasons whatsoever and also to split up the work between two or more tenderers or accept the tender in part and not in its entirety, at its sole discretion.

20. Any addendum/corrigendum/date extension etc. in respect of this tender shall be issued on our website

(https://coalindiatenders.nic.in) only. No separate notification shall be issued in the press. Bidders are therefore requested to visit our website regularly to keep themselves updated.

Sd/-

Dy. General Manager (Civil)

SECL : Gevra Area

10

INSTRUCTIONS TO BIDDERS

1. SCOPE OF BIDDER

1.1 The SOUTH EASTERN COALFIELDS LIMITED (referred to as Employer in these documents) invites bids for the works as mentioned in the Bid Notice. The Bidders should submit Bids for all the works mentioned in the Notice. 1.2 The successful Bidder will be expected to complete the Work(s) by the Intended Completion period specified in the Bid document/Notice.

2. ELIGIBLE BIDDERS

2.1 The Invitation for Bid is open to all Bidders including an individual, proprietorship firm, partnership firm, company registered under Companies Act, any legal entity or joint ventures. The bidders shall be eligible to participate only if they fulfill the qualifying/eligibility criteria specified in e-Tender Notice and at Clause No.3. 2.2 Joint Venture:- Two or three companies/ contractors may jointly undertake contract/contracts. Each entity will be jointly and severally responsible for completing the task as per the contract (applicable for

tenders with estimated cost above Rs.2.00 crores).

Joint Venture details :

Name of all partners of a Joint Venture (not more than 3):

1. Lead partner 2. Partner 3. Partner

Joint Venture must comply the following requirements :

i) Minimum qualification requirements for Joint Venture a) The qualifying criteria parameter e.g. experience of the individual partners of the J.V will be as

deliberated under Cl.No.6A of e-Tender Notice towards fulfillment of qualification criteria related to experience.

b) The qualifying criteria parameter e.g. financial Turnover of the individual partners of the J.V. will be

added together, for the relevant period, and the total criteria should not be less than as deliberated under Cl.No.6B of e-Tender Notice towards fulfillment of qualification criteria related to financial turnover.

ii) The formation of joint venture or change in the Joint Venture character/ partners after submission of the

bid and any change in the bidding regarding Joint Venture will not be permitted. iii) The bid, and in case of a successful bid - the agreement, shall be signed so as to legally bind all partners

jointly and severally and any bid shall be submitted with a copy of the Joint Venture Agreement providing the joint and several liabilities with respect to the contract.

iv) The pre-qualification of a Joint Venture does not necessarily pre-qualify any of its partners individually or

as a partner in any other Joint Venture or association. In case of dissolution of a Joint Venture, each one of the constituent firms may pre-qualify if they meet all the pre-qualification requirements, subject to written approval of the employer.

11

INSTRUCTIONS TO BIDDERS

v) The bid submission must include documentary evidence to the relationship between Joint Venture

partners in the form of JV Agreement to legally bind all partners jointly and severally for the proposed agreement which should set out the principles for the constitution, operation, responsibilities regarding work and financial arrangements, participation (percentage share in the total ) and liabilities ( joint and several ) in respect of each and all of the firms in the Joint Venture. Such JV Agreement must evidence the commitment of the parties to bid for the facilities applied for (if pre-qualified) and to execute the contract for the facilities if their bid is successful.

vi) One of the partners shall be nominated as ‘In-charge’ of the contract and shall be designated as Lead

Partner. This authorization shall be evidenced by submitting with the bid a Power of Attorney signed by legally authorized signatories of all the partners.

vii) The JV Agreement must provide that the Lead Partner shall be authorized to incur liabilities and receive

instructions for and on behalf of any and all partners of the Joint Venture and the entire execution of the contract shall be done with active participation of the Lead Partner.

viii) The contract agreement should be signed by each Joint Venture Partners. Subsequent

declarations/letters/documents shall be signed by lead partner authorized to sign on behalf of the JV or authorized signatory on behalf of JV.

ix) The Agreement should be signed by all the partners of the Joint Venture. x) An entity can be a partner in only one Joint Venture. Bid submitted by Joint Venture including the same

entity as partner will be rejected. xi) The JV agreement may specify the share of each individual partner for the purpose of execution of this

contract. This is required to fulfill eligibility and also for the purpose of apportioning the value of the contract to that extent to individual partner for subsequent submission in other bids if he intends to do so for the purpose of the qualification in that Bid.

xii) The Earnest Money / Bid Security, Bank Guarantee can be submitted by the Joint Venture or one or more

partners of the Joint Venture. xiii) The JV agreement must specifically state that it is valid for the project for which bidding is done. If JV

breaks up midway before award of work and during bid validity period bid will be rejected. If JV breaks up midway before award of work and during bid validity/after award of work/during

pendency of contract, in addition to normal penalties as per provision of bid document, all the partners of the JV shall be debarred from participating in future bids for a minimum period of 12 months.

xiv) JV agreement shall be registered in accordance with law so as to be legally valid and binding on the

members before making any payment. xv) JV shall open a Bank Account in the name of JV and all payments due to the JV shall be credited by

employer to that account only. To facilitate statutory deductions all statutory documents like PAN, GST Registration Certificate with GSTIN (Form GST REG-25), CMPF Registration etc. in the name of the Joint Venture shall be submitted by JV after award of work at the time of execution of agreement/ before the payment of first Running on Account Bill.

2.3 The bidders shall have Digital Signature Certificate (DSC) issued from any agency authorized by Controller

of Certifying Authority (CCA), Govt. of India and which can be traced up to the chain of trust to the Root certificate of CCA.

12

INSTRUCTIONS TO BIDDERS

2.4 The bidders have to accept unconditionally the online user portal agreement which contains the acceptance

of all the Terms and Conditions of NIT and ITB, including General and Special Terms & Conditions, technical specifications, other conditions, if any, along with on-line undertaking in support of the authenticity of the declarations regarding the facts, figures, information and documents furnished by the bidder on-line in order to become an eligible bidder.

2.5 The Company reserves its right to allow Public Enterprises purchase preference facility as admissible under

prevailing policy. 2.6 No sub-letting of the work as a whole by the contractor is permissible. Prior permission is required to be

taken from the principle employer for engagement of sub-contractors in part work/piece rated work.

The Contract Agreement will specify major items of supply or services for which the contractor proposes to engage sub-contractor/sub-vendor. The contractor may from time to time propose any addition or deletion from any such list and will submit proposals in this regard to the Engineer-in–Charge / Designated Officer in charge for approval well in advance so as not to impede the progress of work. Such approval of the Engineer-in-Charge / Designated Officer in Charge will not relieve the contractor from any of his obligations, duties and responsibilities under the contract.

3. QUALIFICATION OF THE BIDDER

3.1 In the event that pre-qualification of potential bidders has been undertaken, only bids from pre-qualified bidders will be considered for award of contract.

3.2 If the employer has not undertaken pre-qualification of potential bidders, all bidders shall fulfill the

eligibility / qualifying criteria as detailed at Cl. No.6 & 7 of e-Tender Notice. Such details shall be submitted as deliberated at e-Tender Notice.

3.3 If the bidder is subsidiary of a company, the experience and resources of the holding company or its

other subsidiaries will not be taken into account. However, if the bidder is a holding company, the experience and resources of its wholly owned subsidiaries will be taken into consideration.

3.4 Even though the bidders meet the above eligibility/qualifying criteria, they are subject to be disqualified

if they have:

a. Made misleading or false representations in the forms, statements and attachments submitted in proof of the qualification requirements; and/or

b. Record of poor performance such as abandoning the works, not properly completing the contract,

inordinate delays in completion, or financial failures etc.

Notes : The documents to be furnished by the bidder to prove that he is satisfying the qualification criteria laid down should all be in the bidders name except in cases where though the name has changed, owners continued to remain the same and in cases of amalgamation of entities and when a holding company relies on credential of its wholly owned subsidiary.

4. ONE BID PER BIDDER

4.1 Each Bidder shall submit only one Bid, either individually, or as a partner in a partnership firm or a partner in a Joint Venture or a Public Ltd./Private Ltd. company or any legal entity. A Bidder who submits or participates in more than one Bid (other than as a subcontractor or in cases of alternatives that have been permitted or requested) will cause all the proposals with the Bidder's participation to be

13

INSTRUCTIONS TO BIDDERS

disqualified. 5. COST OF BIDDING

5.1 The Bidder shall bear all costs associated with the preparation and submission of his Bid, and the Employer will in no case be responsible or liable for those costs.

6. SITE VISIT

6.1. The Bidder, at the Bidder's own responsibility, cost and risk, is encouraged to visit and examine the Site of Works and its surroundings, approach road, soil condition, investigation report, existing works, if any, connected to the tendered work, drawings connected to the work, if / as available and obtain all information that may be necessary for preparing the Bid and entering into a contract for execution of the Works. The costs of visiting the Site shall be at the Bidder's own expense.

6.2. It shall be deemed that the Bidder has visited the site/area and got fully acquainted with the working conditions and other prevalent conditions and fluctuations thereto whether he actually visits the site/area or not and has taken all the factors into account while quoting his rates.

6.3. The bidder is expected, before quoting his rate, to go through the requirement of materials / workmanship, specification, requirements and conditions of contract.

6.4. The bidder, in preparing the bid, shall rely on the site investigation report referred to in the bid document (if available), supplemented by any information available to the bidder.

7.CONTENT OF BIDDING DOCUMENTS

7.1 The set of bidding documents comprises the documents (all or as available/applicable) listed in below:

i) e-Tender Notice, ii) Instructions to Bidders, iii) Conditions of Contract (General Terms & Conditions, Special Terms and conditions, Commercial Terms and conditions, Special notes and & additional terms & conditions, safety norms etc.), iv) Integrity Pact, if applicable; v) Various Forms of Securities, undertaking, form of Article of Agreement, vi) Bill of Quantities and technical specifications. vii) e-tender user portal agreement.

8. CLARIFICATION OF BIDDING DOCUMENTS

8.1 A prospective bidder requiring any interpretation or clarification of bidding document may seek clarification online or during pre-bid meeting (if any). The clarifications may be asked from the next day of e-Publication of NIT. The last date for seeking clarification will be as specified online. The department will clarify as far as possible only relevant queries. The clarifications given by department will be visible to all the bidders intending to participate in bid.

9. LANGUAGE OF BID

9.1 All documents relating to the Bid shall be in the English language.

10. BID PRICES

10.1. The bidder shall closely study specification in detail and scope of work which govern the rates for which he is quoting. The Bidders shall offer for the whole Works as described in Sub-Clause 1.1, based on the Bill of Quantities. Based on priced bill of quantities submitted by the Bidder, the Employer reserves the right to allot whole or part of the work at their discretion and no claims, whatsoever, shall be entertained in this regard.

10.2. The price bid containing the bill of quantity will be excel format and will be downloaded by the bidder and he will quote the rates for all items/heads/sub-heads on this excel file as detailed at clause No.8(f) of e-Tender Notice.

14

INSTRUCTIONS TO BIDDERS

10.3. All duties, taxes [excluding Goods & Services Tax and State Compensation Cess (if applicable) only] and

other levies, royalty, building and construction workers cess (as applicable in States), if any applicable,

after implementation of GST as per Govt. Notification, whether local, municipal, provincial or central

pertaining to the contract payable by the Contractor under the Contract (during the entire period of

contract), or for any other cause as applicable on the last date of submission of Bid, shall be included in

the rates, prices and the total Bid Price submitted by the Bidder. All investments, operating expenses,

incidentals, overheads, lifts, carriages, tools and plants etc. as may be attendant upon execution and

completion of works shall also be included in the rates, prices and total Bid price submitted by the

bidder.

However, such duties, taxes, levies etc. which is notified after the last date of submission of Bid and/or

any increase over the rate existing on the last date of submission of Bid shall be reimbursed by the

company on production of documentary evidence in support of payment actually made to the

concerned authorities.

Similarly if there is any decrease in such duties, taxes and levies the same shall become recoverable

from the contractor.

The rates quoted by bidder shall be inclusive of all Taxes, if any applicable, after implementation of GST

as per Govt. Notification, but excluding Goods & Service Tax (GST) and State Compensation Cess (if

applicable).

For GST Registered Bidders, the Payment/ deposit of GST and State Compensation Cess (if applicable) is

the responsibility of the Contractor (Supplier). However, in case the contractor is Unregistered under

GST as per GST Act & Rules, the GST and State Compensation Cess (if applicable) will be deposited by

SECL directly to the concerned authorities under Reverse Charge Mechanism.

Payment of GST and State Compensation Cess (if applicable) would be made to the Contractor only on

submission of Bill/Invoice in accordance with the provision of relevant GST Act & Rules and after filing

of return online on the GST Portal. Input Tax Credit is to be availed by SECL as per rule.

If CIL/Subsidiary fails to claim Input Tax Credit(ITC) on eligible Inputs, input services and Capital Goods

or the ITC claimed is disallowed due to failure on the part of supplier/vendor of goods and services in

incorporating the tax invoice issued to CIL/Subsidiary in its relevant returns under GST, payment of

CGST & SGST or IGST, GST (Compensation to State ) Cess shown in tax invoice to the tax authorities,

issue of proper tax invoice or any other reason whatsoever, the applicable taxes &cess paid based on

such Tax invoice shall be recovered from the current bills or any other dues of the supplier/vendor

along with interest, if any.

10.4. The rates and prices quoted by the Bidder shall be fixed for the duration of the contract and shall not be subject to variations on any account except to the extent variations allowed as per the conditions of the contract of the bidding document.

11. CURRENCIES OF BID AND PAYMENT

11.1.The unit rates and prices shall be quoted by the Bidder entirely in Indian Rupees.

12. BID VALIDITY

12.1 The Bid Validity Period will be 120 (one hundred twenty) days from the end date of bid submission. The validity period of tender shall be decided based on the final end date of submission of bids, after extension, if any.

15

INSTRUCTIONS TO BIDDERS

12.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request that the bidder(s) extend the period of validity for a specified additional period. The request and the bidder's response shall be in writing. A bidder may refuse the request without forfeiting his bid security. A bidder agreeing to the request will not be required or permitted to modify his bid but will be required to extend the validity of his bid security (if deposited in the form of BG) for the period of extension, and in compliance with Clause 14 in all respects.

13. BID SECURITY/EARNEST MONEY DEPOSIT

13.1. The Bid Security/Earnest Money may be forfeited :

a. if the Bidder withdraws the Bid after Bid opening during the period of Bid validity / extended validity with mutual consent; OR b. in the case of a successful Bidder, if the Bidder fails within the specified time limit to: (i) sign the

Agreement; OR(ii) Furnish the required Performance Security/ Security Deposit.

Additionally the bidder will not be allowed to participate in the re-tender. The company reserves the right to debar such defaulting contractor from participating in future bids in SECL for a minimum period of 12 months.

13.2. The Bid Security/ EMD deposited with the Employer will not carry any interest 14. DEADLINE FOR SUBMISSION OF BIDS

14.1. Bids shall be submitted online on the web site https://coalindiatenders.nic.in within the date and time

specified in the e-Tender Notice.

14.2. The employer may extend the deadline for submission of bids by issuing a corrigendum in accordance with provisions of e-Tender Notice/ITB, in which case all rights and obligations of the employer and the bidders previously subject to the original deadline will then be subject to the new deadline.

15. SIGNING AND SUBMISSION OF BID

15.1 The Letter of Bid will be digitally signed by DSC holder submitting bid online and it does not require any physical signature. However, if the Letter of Bid bears the physical signature in addition to the digital signature of DSC holder, it will be accepted without questioning the identity of person singing the bid.

15.2 Submission of bid shall be as detailed at Clause No.8 of e-Tender Notice. 16. EVALUATION AND COMPARISON OF BIDS.

16.1 Evaluation and comparison of Bids will be done by System online. This online evaluation will be validated by SECL at each stage as deliberated in e-Tender Notice. The bidder shall also comply with system requirement as deliberated in e-Tender Notice. Bid evaluation shall be done after taking into consideration overall quoted price by the bidder and effect of Goods & Service Tax (GST) and State Compensation Cess (if applicable). L-1 will be decided based on Cost to the Company.

16.2 If the Bid of the successful Bidder is seriously unbalanced in relation to the Company’s estimate of the

cost of work to be performed under the contract, the Employer may require the Bidder to produce detailed price analysis for any or all items of the Bill of Quantities, to demonstrate the internal consistency of those prices with the methods and schedule proposed.

After evaluation of the price analysis, the company may require that the amount of the performance security/security deposit is increased at the expense of the successful bidder to a level sufficient to protect the company against financial loss in the event of default on the part of the successful bidder

16

INSTRUCTIONS TO BIDDERS

under the contract.

Additional performance security shall be applicable if the bid price is below 15% of the justified price, finalized by the owner. The amount of such additional performance security shall be the difference between 85% of the owner's justified price and quoted price.

Justified price shall be finalized by the owner on the basis of prevalent market rate of materials and labour analysed as per standard analysis of rate of CPWD/ NBO, and shall be binding on the bidder.

Such additional performance security shall be applicable for Item-rate and Percentage Tenders.

Such additional performance security shall be furnished by bidder along with normal performance security as per Cl. No. 4 of GTC. Failure to submit such additional performance security may result into termination of the contract.

17. ABNORMALLY HIGH RATE & ABNORMALLY LOW RATE ITEMS.

PROVISIONS FOR DEALING WITH VARIATIONS IN RESPECT OF ABNORMALLY HIGH RATE AND ABNORMALLY LOW RATE ITEMS. The abnormally high rate items are those whose quoted rates are more than 20% of the justified rates decided by the owner. The abnormally low rate items are those whose quoted rates are less than 20% of the justified rates decided by the owner. In case of Item Rate Tenders, the revision of rates for (i) abnormally high rate items and (ii) abnormally low rate items, shall become operative under the following circumstances:- For increase in quantity of more than 25% in respect of works executed below plinth level and 10% in respect of works executed above plinth level. Quantity variation beyond the limit mentioned above shall be dealt by arriving at new rate based on prevalent market rate of materials and labour analysed as per standard analysis of rate of CPWD/NBO. Payment of extra quantity over the permitted quantity as explained above would be made on the basis of the new analysed rate.

The variation in quantity of abnormally low rate items for item rate tenders shall not be permitted below 25% for the items below plinth level and below 10% for the items above plinth level of the agreement schedule quantity, but in exceptional cases with written consent of Engineer-in-Charge arising out of technical necessity.

The above provisions shall be applicable for item rate tenders only and not applicable for percentage rate tenders for works based on standard schedule of rates of the company.

For the purpose of operation, the following works shall be treated as works related to foundation, unless otherwise defined in the contract :

a) For Buildings: All works up to 1.2 meters above ground level or up to floor 1 level whichever is lower. b) For abutments, piers and well steining : All works up to 1.2m above the bed level. c) For retaining walls, wing walls, compound walls, chimneys, overhead reservoirs / tanks and other

elevated structures: all works up to 1.2 meters above the ground level. d) For reservoirs / tanks (other than overhead reservoirs / tanks): All works up to 1.2 meters above the

ground level.

17

INSTRUCTIONS TO BIDDERS

e) For basement : all works up to 1.2m above ground level or up to floor 1 level whichever is lower. f) For Roads, all items of excavation and filling including treatment of sub base. 18. AWARD CRITERIA

18.1 Subject to Clause No.19, the Employer will award the Contract to the Bidder whose Bid has been determined to be substantially responsive to the Bidding documents and who has offered the lowest evaluated acceptable Bid Price, provided that such Bidder has been determined to be :

a) Eligible in accordance with the provisions of Clause 2; and b) Qualified in accordance with the provisions of Clause 3.

19. EMPLOYER'S RIGHT TO ACCEPT ANY BID, NEGOTIATE AND TO REJECT ANY OR ALL BIDS

19.1 Notwithstanding Clause No.18, the Employer reserves the right to accept, negotiate or reject any Bid, and to cancel the bidding process and reject all Bids, at any time prior to the award of Contract, without thereby incurring any liability to the affected Bidder or Bidders or any obligation to inform the affected Bidder or Bidders of the grounds for the Employer's action.

20. NOTIFICATION OF AWARD AND SIGNING OF AGREEMENT

20.1 The Bidder, whose Bid has been accepted, will be notified of the award by the Employer prior to expiration of the Bid validity period on e-Procurement portal and confirmed by registered/speed post. This letter (hereinafter and in the Conditions of Contract called the "Letter of Acceptance") will state the sum that the Employer will pay the Contractor in consideration of the execution and completion of the Works by the Contractor as prescribed by the Contract (hereinafter and in the Contract called "the Contract Price").

20.2 The notification of award will constitute the formation of the Contract. The works should be completed as per period specified in the NIT from expiry of 10 (ten) days from the

issue of letter of acceptance issued by department or from 7th day of handing over of the site or handing over of reasonable number of working drawings to the contractor or the period of mobilization allowed in the work order for starting the work in special circumstances whichever is latest.

20.3 The Agreement will incorporate all agreements between the Employer and the successful Bidder, work

programme etc. within 30 (thirty) days following the notification of award along with the letter of Acceptance and / or Work Order issued by department.

In case of failure to enter in to agreement within specified period or extended period on the written-request of the bidder, if any, the department in addition to other penal measures as per clause No.13.1 of ITB debars the selected bidder from participating in re-tender. In addition, the department may debar the bidder from participating in future bids in SECL for at least 12 months.

20.4 In the bidding process, the cause of rejection of Bid of any bidder should be intimated to non-qualified bidder after the award of the work to the successful one and the Security/ Earnest Money shall be refunded to unsuccessful bidders as per provision of e-Tender Notice.

20.5 The contractor shall enter into and execute contract agreement in the prescribed form. The cost of the stamp papers for the contract agreement shall be borne by the contractor. Two sets of contract document/agreements shall be prepared and signed by both the parties One of the sets shall be stamped "Original" and the other "Duplicate". The duplicate copy will be supplied to the contractor free of cost and the original is to be retained by the company. For additional copy, cost to be charged.

All additional copies should be certified by the Engineer-in-Charge.

18

INSTRUCTIONS TO BIDDERS

The contractor shall keep copy of these documents on the site/place of work in proper manner so that these are available for inspection at all reasonable times by the Engineer-in-charge, his representatives or any other officials authorized by the company for the purpose.

The contract document shall not be used by the contractor for any purpose other than this contract and the contractor shall ensure that all persons employed for this contract strictly adhere to this and maintain secrecy, as required of such documents.

21. PERFORMANCE SECURITY/SECURITY DEPOSIT

21.1 Security Deposit shall consist of two parts :

a. Performance Security to be submitted at award of work and

b. Retention Money to be recovered from running bills.

The security deposit shall bear no interest.

For details refer Clause No.4 of Conditions of Contract (General Terms and Conditions)

22. EMPLOYMENT OF LABOUR

22.1 Contractors are to employ, to the extent possible (as per policy decision of the company valid from time to time), local project affected people and pay wages not less than the minimum wages as per Minimum Wages Act or such other legislations or award of the minimum wage fixed by respective State Govt. or

Central Govt. as may be in force or minimum wages recommended by High Power Committee of CIL (for labours engaged in mining activities), as applicable and mentioned in the e-Tender Notice. Payment of arrears to the contract workers on account of revision of minimum wages shall be the responsibility of the contractor.

Payment of Provident Fund for the workmen employed by him for the work as per the Laws prevailing under provision of CMPF and allied scheme valid from time to time shall be the responsibility of bidder.

Bidder shall also submit statutory returns.

22.2 The bidder shall comply with statutory requirements of various acts including Child Labour (Prohibition & Regulation) Act, 1986 as mended from time to time and all rules, regulations and schemes framed thereunder from time to time in addition to other applicable labour laws.

22.3 The bidder shall also follow other guidelines as incorporated at Clause 13 of GTC covered under additional responsibilities of the contractor.

22.4 The payment to the contractor’s labourers has to be made through Bank only.

22.5 Bonus is to be paid to the contract workers engaged by the Contractors as per the provisions of

Payment of Bonus Act,1965.

22.6 The contractors shall register themselves on the Contract Labour Payment Management Portal (CLPMP)

of CIL within 30 days of issue of work order and will have to enter and update periodically the following

details in the portal :

a. Work Order details

b. Contractor workers details and Wages payment details in respect of each Work Order.

22.7 The contractor shall directly pay the ex-gratia amount of Rs. 5.00 (Five ) lakhs to the same dependent family members of the deceased contractor’s worker,who died in mine accident as certified by DGMS , to whome the statutory benefits under Employee Compensation Act , Provident Fund etc. have been paid , as per terms of contract or through Insurance Company by availing Group Personal Accident Insurance Policy for all its

19

INSTRUCTIONS TO BIDDERS

workers before commencement of the contract , which shall be renewed periodically to cover the entire duration of the contract. No reimbursement shall be made on this account by CIL/SECL. In order to comply with the above provision, contractor shall immediately on receipt of letter of acceptance /

work order shall obtain group personal accident insurance in respect of all the workmen eggaged in mining

activities for payment of Rs. 5.00 (Five ) lakhs in case of death in mine accident . A proof to such effect shall be produced to the satisfaction of the management before commencement of the work . However, the responsibility of payment of special relief / ex-gratia amount shall lie exclusively with the Contractor. If the contractor fails to disburse the special Relief /Ex-gratia within the due date, the subsidiary concerned may make payment to the eligible dependent as mentioned herein above. However, such amount shall be recovered from the Contractor from his dues eighter in the same and/ or other subsidiary of CIL.” AS per Letter No. GM( c ) / SECL/BSP/2018-19/H/334 DT. 26.10.2018 ISSUED BY GM ( C ),SECL,BILASPUR) 23. LEGAL JURISDICTION

23.1 For the Works tendered from SECL-HQ. : Matter relating to any dispute or difference arising out of this tender and subsequent contract awarded based on this tender shall be subject to the jurisdiction of Bilaspur Court.

23.2 For the Works tendered from AREAS of SECL : Matter relating to any dispute or difference arising out of this tender and subsequent contract awarded based on this tender shall be subject to the jurisdiction of local court only, where the subject work is to be executed.

24. e-Payment

24.1 Successful bidder will be required to submit a Mandate Form duly signed by bidder and the Bank Officials for e-Payment.

25. Integrity Pact (applicable for tenders with estimated cost exceeding Rs. 2.00 Crores).

25.1 Bidders are required to submit the Pre-Contract Integrity Pact duly signed & witnessed as per enclosed format along with the bid Part-I/cover-I. This will be signed by the authorized signatory of the bidder (s) with name, designation and seal of the company. Bidder(s) who do not sign the pact shall be disqualified from participation in the bid process.

26. Change in the Constitution of Contracting Agency.

26.1 Prior approval in writing of the Company shall be obtained, before any change is made in the constitution of the contracting agency, otherwise it will treated as a breach of contract.

27. Miscellaneous.

27.1 The bidders should fill the bid document properly and carefully. They should avoid quoting absurd rates.

27.2 Throughout the bidding documents, the terms ‘bid’ and tender and their derivatives are synonymous.

27.3 The contractor will submit the following documents within 10 days of issue of LOA, for execution of Agreement :

i. Non Judicial Stamp Paper of Rs.100.00 ii. Site handover and takeover certificate, jointly signed by Engineer-in-Charge and the Contractor. iii. Labour License as per Contract Labour (Regulation & Abolition) Act, 1970, OR

An Undertaking, jointly signed by Engineer-in-Charge and the Contractor, for deployment of less than 20 labours.

20

INSTRUCTIONS TO BIDDERS

iv. Insurance Policy certificates duly pledged in the name of SECL, as per Clause No.13 (xviii) of General Terms & Conditions of Contract.

v. CMPF Registration certificate. vi. Detail Time and Progress Chart, jointly signed by Engineer-in-Charge and the Contractor. vii. List of Technical & Supervisory Personnel to be deployed for execution of the work.

28. An Amount of 1% (one percent) of the work value payable to the contractors will be deducted from all

Bills towards the worker’s welfare under Building and other Construction Worker’s Welfare Cess Rules’1998 and Building and other Construction Worker’s Welfare Cess Act’1996 (As applicable in the

States).

CONDITIONS OF CONTRACT

GENERAL TERMS AND CONDITIONS

1. Definitions

i) The word "Employer" or "Company” or “Owner” wherever occurs in the conditions, means the South Eastern Coalfields Limited, represented at Head Quarters of the Company by the General Manager (Civil) or his authorized representatives or any other officer specially deputed for the purpose who will employ the contractor.

ii)The word" Principal Employer" wherever occurs, means the officer nominated by the Company to function on its behalf.

iii)The word "Contractor/ Contractors" wherever occurs means the successful bidder /bidders who has/have deposited the necessary Earnest money and has/have been given written intimation about the acceptance of tender and shall include legal representative of such individual or persons composing a firm or a company or the successors and permitted assignees of such individual, firm or Company, as the case may be and any constitutional, or otherwise change of which shall have prior approval of the employer. iv) "Site" means the land and places including any building and erection thereon, over, under, in or through which the Permanent works or Temporary works designed by the Engineer-in-Charge are to be executed and any other lands and places provided by the Employer for working space or any other purpose as may be specifically designated in the Contract as forming part of the site. v) The term "Sub-Contractor" as employed herein, includes those having a direct contract with Contractor either on piece rate, item rate, time rate or any other basis and it includes one who furnishes work to a special design according to the plans or specifications of this work but does not include one who merely supplies materials. vi) "Accepting Authority" shall mean the management of the company and includes an authorized representative of the company or any other person or body of persons empowered on its behalf by the company.

vii) "Engineer-in-charge" shall mean the officer nominated by the company in the Civil Engineering cadre/ discipline who is competent to direct supervisors and authorised to be in charge of the works for the purpose of this contract. The Engineer-in-Charge /Designated Officer in Charge, who is of an appropriate seniority, will be responsible for supervising and administering the contract, certifying payments due to the contractor, valuing variations to the contract, awarding extension of time and valuing compensation events. The Engineer-in-Charge

21

CONDITIONS OF CONTRACT

/Designated Officer in Charge may further appoint his representatives i.e. another person/Project Manager or any other competent person and notify to the contractor who is directly responsible for supervising the work being executed at the site, on his behalf under their Delegation of Powers of the company. However, overall responsibility, as far as the contract is concerned, will be that of the Engineer-in-Charge/Designated Officer in Charge.

viii) The "Contract" shall mean the notice inviting tender, the tender as accepted by the Company, the work order issued to the contractor, and the formal contract agreement executed between the company and the contractor together with the documents referred to therein including general terms and conditions, special conditions, if any, scope of work, frozen terms & conditions/technical parameters/scope of work and revised offer, if any, specifications, drawings, including those to be submitted during progress of work, schedule of quantities with rates and amounts.

ix) A "Day" shall mean a day of 24 hours from midnight to midnight. x) The "Work" shall mean the works required to be executed in accordance with the contract/work order or parts thereof as the case may be and shall include all extra or additional, altered or substituted works or any work of emergent nature, which in the opinion of the Engineer-in-charge, become necessary during the progress of the works to obviate any risk or accident or failure or become necessary for security.

xi) "Schedule of Rates” referred to in this conditions shall mean the standard schedule of rates prescribed by the company and the amendments issued from time to time.

xii) "Contract amount" shall mean: a) in the case of turnkey / lump sum contracts the total sum for which tender is accepted by the company. b) in the case of other types of contracts the total sum arrived at based on the individual rate(s) / percentage rate(s)quoted by the tenderer for the various items shown in the Schedule of Quantities" of the tender document as accepted by the Company with or without any alteration as the case may be.

xiii) "Written notice" shall mean a notice or communication in writing and shall be deemed to have been duly served if delivered in person to the individual or to a member of the contractors firm or to an office of the company for whom it is intended, or if delivered at or sent by registered mail / e-mail to the last business address known to him who gives the notice.

xiv) "The constructional plant" means all appliances, tools, plants or machinery of whatsoever nature required in or about the execution, completion or maintenance of the works but does not include materials or other things intended to form part of the permanent work.

xv) "Letter of Acceptance of Tender" means letter giving intimation to the tenderer that his tender has been accepted in accordance with the provisions contained in that letter.

xvi) "Department" means the Civil Engineering Department of Coal India Limited or any of its subsidiary companies/units represented by the appropriate authority.

xvii) "Act of insolvency" means as it is designed by Presidency Town Insolvency Act or Provincial Insolvency Act or any act amending such originals.

xviii) The words indicating the singular only also include the plural and vice-versa where the context so requires.

xix) "Drawings"/"Plans" shall mean all: a. drawings furnished by the owner with the bid document , if any, as a basis for proposals, b. working drawings furnished by the Owner after issue of letter of acceptance of the tender to start the

work, c. subsequent working drawings furnished by the owner in phases during progress of the work, and d. drawings, if any, submitted by the contractor as per provision of the contract and duly approved by

22

CONDITIONS OF CONTRACT

the owner.

xx) "Codes" shall mean the following, including the latest amendments, and/or replacements, if any : a. Bureau of Indian Standards relevant to the works under the contract and their specifications. b. Indian Electricity Act and Rules and Regulations made there under. c. Indian Mines Act and Rules and Regulations made there under. d. Any other Act, rule and regulations applicable for employment of labour, safety provisions, payment

of provident fund and compensation, insurance etc. 2. Contract Documents and Miscellaneous Provisions :

The following documents shall constitute the contract documents :

i) Articles of Agreement. ii) Letter of Acceptance of Bid/ Work Order indicating deviation, if any, from the conditions of contract incorporated in the tender document issued to the bidder. iii) Notice Inviting Tender and Instructions to Bidders. iv) Conditions of Contract including General Terms & Conditions of contract, Additional Terms & Conditions, Special Terms & Conditions, and Commercial Terms & Conditions etc.- as applicable. v) Frozen terms & conditions / technical parameters and revised offer, if any. vi) Specifications/ scope of Work, if any. vii) Schedule of quantities (or Bill of Quantities)along with accepted rate. viii) Contract drawings and work programme. ix) Safety Code etc. forming part of the tender,

x) Integrity Pact ( If applicable ).

2.1The contractor shall enter into and execute contract agreement in the prescribed form. The cost of the stamp papers for the contract agreement shall be borne by the contractor. Two sets of contract document/agreements shall be prepared and signed by both the parties One of the sets shall be stamped "Original" and the other "Duplicate". The duplicate copy will be supplied to the contractor free of cost and the original is to be retained by the company. For additional copy, cost to be charged.

All additional copies should be certified by the Engineer-in-Charge. The contractor shall keep copy of these documents on the site/place of work in proper manner so that these are available for inspection at all reasonable times by the Engineer-in-charge, his representatives or any other officials authorized by the company for the purpose. 2.2The contract document shall not be used by the contractor for any purpose other than this contract and the contractor shall ensure that all persons employed for this contract strictly adhere to this and maintain secrecy, as required of such documents.

2.3 The local Court, where the subject work is to be executed shall have exclusive jurisdiction in all matter arising under this contract. 2.4 The Contract Agreement will specify major items of supply or services for which the contractor proposes to engage sub-contractor/sub-vendor. The contractor may from time to time propose any addition or deletion from any such list and will submit proposals in this regard to the Engineer-in–Charge / Designated Officer in charge for approval well in advance so as not to impede the progress of work. Such approval of the Engineer-in-Charge / Designated Officer in Charge will not relieve the contractor from any of his obligations, duties and responsibilities under the contract. 2.5Acceptance of Offer :

23

CONDITIONS OF CONTRACT

“Letter of Acceptance”- is an acceptance of offer by the company. The tenderer should acknowledge the receipt of the order within 10 days of mailing of LOA and any delay in acknowledging the receipt will be treated as a breach of contract and compensation for the loss caused by such breach will be declared by the company by forfeiting EMD.

3. Discrepancies in contract documents & Adjustments thereof

The documents forming part of the contract are to be treated as mutually explanatory of one another and in case of discrepancy between schedule of quantity, the specifications and/or drawing, the following order of preference shall be observed;

a) Description in Bill of Quantities of work. b) Particular specification and special conditions, if any c) Drawings. d) General specifications. e) BIS Specifications.

3.1. In the event of varying or conflicting provision in any of the document(s) forming part of the contract, the Accepting Authority's decision/clarification shall hold good with regard to the intention of the document or contract as the case may be. 3.2. Any error in description, quantity or rate in Bill of Quantities or any omission there from, shall not vitiate the contract or release the contractor from discharging his obligations under the contract including execution of work according to the Drawings and Specifications forming part of the particular contract document.

4.00. Security Deposit:

4.1. Security Deposit shall consist of two parts;

a) Performance Security to be submitted at award of work and b) Retention Money to be recovered from running bills.

The security deposit shall bear no interest. 4..2. Performance Security should be 5.00 % of contract amount and should be submitted within 28 days of issuance of LOA by the successful bidder in any of the form given below :

• a Bank Guarantee in the form given in the bid document from any Scheduled bank. The BG issued by outstation bank shall be operative at its local branch at …….. or branch at…………………….. Bank Guarantee against Performance Security shall be applicable if the amount of Performance Security exceeds Rs. 5.0 lakhs.

• Govt. Securities, FDR or any other form of deposit stipulated by the owner and duly pledged in favour of owner.

• Demand Draft drawn in favour of South Eastern Coalfields Limited on any Scheduled Bank payable at its Branch at ………..

The Earnest Money/ Bid Security deposited in the form of Bank Guarantee shall be discharged when the Bidder has signed the Agreement and furnished the required Performance Security/ 1st part of security deposit.

The bid security deposited in the form of Demand draft/ cash may be adjusted against the Performance security (1st part of security deposit) at bidder’s option. If Performance Security is provided by the successful bidder in the form of bank guarantee it shall be issued either –

(a) at Bidder’s option by a Scheduled Bank , or (b) by a foreign bank located in India and acceptable to the employer.

24

CONDITIONS OF CONTRACT

The validity of the Bank Guarantee shall be for a period of one year or ninety days beyond the period of contract /extended contract period (if any), whichever is more.

NOTE: (i) The Bank Guarantee issued by a scheduled bank shall be operative at its branch situated at Bilaspur

(Chhattisgarh State) or if the issuing bank does not have any branch at Bilaspur then Bank Guarantee shall be operative at any of its Kolkata Branch.

(ii). The Bank Guarantee (BG) issued by the issuing Bank on behalf of contractor in favour of “South

Eastern Coalfields Limited” shall be in paper form as well as issued under “Structured Financial

Messaging System (SFMS)”.

The details of beneficiary for issue of Bank Guarantee (BG) under SFMS platform is furnished below:

A. State Bank of India as advising Bank of SECL:

1. Name of the Beneficiary

and his details.

i Name South Eastern Coalfields Limited

(SECL)

ii Area SECL - HQ. Bilaspur

iii Name of Bank State Bank of India

iv Bank Account No. 30285470636

v Department Civil

2. Beneficiary Bank,

Branch and address.

i Name of Bank State Bank of India

ii Bank Branch name SME SBI Branch

iii Branch code 4177

iv Beneficiary Bank Branch

IFSC

SBIN0004177

v Beneficiary Bank Address SBI, Galaxy Height, Vyapar Vihar

Bilaspur, PIN-495001,

Chhattisgarh

B. ICICI Bank as advising Bank of SECL:

1. Name of the Beneficiary

and his details.

i Name SECL 14265

ii Area SECL – HQ. Bilaspur

iii Name of Bank ICICI Bank

iv Bank Account No. 028205003346

v Department Civil

2. Beneficiary Bank,

Branch and address.

i Name of Bank ICICI Bank

ii Bank Branch name Vyapar Vihar, Bilaspur,

Chhattisgarh

iii Branch code 0282

iv Beneficiary Bank Branch

IFSC

ICIC0000282

v Beneficiary Bank Address ICICI Bank Ltd. , Surya Chambers,

Plot No. A/09, Vyapar Vihar,

Bilaspur, Chhattisgarh, PIN-

495001

25

CONDITIONS OF CONTRACT

Failure of the successful bidder to comply with the requirement as above shall constitute sufficient ground for cancellation of the award of work and forfeiture of the bid security/ earnest money. In addition to the above penal measures, the bidder will not be allowed to participate in the re-tendering process. The bidder may also be debarred from participating in future tenders in the subsidiary for a minimum period of 12 Months. 4.3. Performance Security Deposit (5.00% of contract amount) should be refunded within 14 days of the issue of defect liability certificate (taking over certificate with a list of defects).

4.4. All running on account bills shall be paid at 95% (ninety five percent) of work value. The balance 5% shall be treated as Retention Money and will be second part of Security Deposit.

Retention Money may be refunded against equivalent Bank Guarantee, on written request of the contractor, on its accumulation to a minimum amount of Rs.5 lakhs subject to the condition that amount of any Bank Guarantee except last one, shall not be less Rs.5 lakhs. However, Bank Guarantee against Retention Money shall be with suitable validity based on nature of work which shall be 90 days beyond the defect liability period, but in no case less than the period of one year.

Bank Guarantee is to be submitted in the format prescribed by the company. Bank Guarantee shall be irrevocable and will be from Scheduled Banks as elaborated at Cl.4.2.

4.5. Retention Money should be refunded after issue of No Defect Certificate.

4.6. The Company shall be at liberty to deduct/appropriate from the security deposit such sums as are due and payable by the contractor to the Company as may be determined in terms of the contract, and the amount appropriated from the Security Deposit shall have to be restored by further deduction from the contractors subsequent on account running bills, if any. 4.7. REFUND OF SECURITY DEPOSIT: The refund of security deposit shall be subject to company's right to deduct/ appropriate its due against the contractor under this contract or under any other contract.

On completion of the entire work and issue of defect liability certificate (taking over certificate with a list of defects) by the Engineer-in-charge, Performance Security Deposit (5.00% of contract amount) i.e. 1st part of the Security Deposit remaining with the company shall be refunded as elaborated at Cl. No.4.3. Retention Money (5% recovered from running bills) i.e. 2nd part of the Security Deposit shall be refunded to the contractor after issue of No Defect Certificate by the Engineer-in-Charge on the expiry of Defect Liability Period of six months, subject to the following conditions: a) Any defect/defects in the work, if detected after issue of defect liability certificate (Taking over certificate with list of defects) is/are rectified to the satisfaction of the Engineer-in-Charge within the said defect liability period of six months or on its due extension till completion of the rectification works as required.

b) In the case of building work or other work of similar nature, the refund shall be made on the expiry of the said six months period or at the end of one full monsoon period i.e. June to September, whichever is later in point of time and any defects such as leakages in roof, effloresces in walls, dampness, defects in drainage etc. should be rectified to the satisfaction of Engineer-in-Charge.

NB: In case of Maintenance contracts, that ends with successful completion of work, where question of Defect Liability Period does not arise (e.g. sweeping / cleaning, horticulture, tank cleaning, jungle cutting, grass cutting,

26

CONDITIONS OF CONTRACT

surface dressing etc.), the Performance Security Deposit (1st part of the Security Deposit) and Retention Money (2nd part of the Security Deposit) can be released simultaneously after completion of work and taking over by department.

4.8. Additional Performance Security: (applicable for item rate as well as percentage rate tenders):

Additional performance security shall be applicable if the bid price is below 15% of the justified price, finalized by the owner. The amount of such additional performance security shall be the difference between 85% of the owner's justified price and quoted price. Justified price shall be finalized by the owner on the basis of prevalent market rate of materials and labour analysed as per standard analysis of rate of CPWD/ NBO, and shall be binding on the bidder.

Additional performance security shall be furnished by bidder along with normal performance security. Failure to submit such additional performance security may result into termination of the contract.

This additional performance security will not carry any interest and shall be released in the following manner:

i) 30% of Additional performance security will be released after 60% of the total work is completed. ii) 50% of Additional performance security will be released after 80% of the total work is completed. iii) 100% of Additional performance security will be released after total work is completed.

Additional performance security may be furnished in the shape of BG or any of the forms as applicable for performance security.

4.9. Refund of Security Deposit regarding Specialized Item of Works (shall be applicable only when relevant item exists in the contract and shall be for 10% of value of such items in the contract or for 10% of value of contract with such specialized items only).

a) For some specialized items of work such as anti-termite treatment, waterproofing work, kiln seasoned and chemically treated wooden shutters, or any other item of work deemed as such ‘specialized’ by Engineer-in-Charge that are entrusted to specialized firms or contractors who associate specialized agencies, the contractor / firm executing the work should be asked to give a specific guarantee that they shall be responsible for removal of any defects cropping up in these works executed by them during the guarantee period. The form of the guarantee to be executed by the contractors shall be as enclosed.

b) 10.00% as the Security Deposit (Performance Security and Retention Money) deposited / deducted from the bills of the contractors, relevant to the item(s), shall be refunded to him after expiry of Guarantee period. The security amount relevant to the item(s) of work, may be released after 12 months of completion of work against equivalent BG and furnishing Guarantee as at (a) above.

4.10. Refund of security deposit for contracts with supply installation and commissioning of equipment i.e. with Mechanical & Electrical Works (shall be applicable only when relevant item exists in the contract)

For some specialized contracts like Pump house, Intake well etc. there may be Civil works as well as Mechanical and Electrical works. For such works 10.00% as the Security Deposit (Performance Security and Retention Money)- deposited / deducted from the bills of the contractors shall be refunded to him after expiry of guarantee period, which will be one year from the date of commissioning of equipment/ completion of work and/or rectification of any defect which may be detected in the individual equipment for the whole system under the contract, whichever is later. In addition, all types of manufacturers guarantee/warranty wherever applicable are to be issued/ revalidated in the name of the owner by the contractual agency and will be covered with relevant counter guarantee. Bank guarantees furnished against Performance Security and Retention Money shall be validated for a period 90 days beyond the guarantee period.

27

CONDITIONS OF CONTRACT

5. Deviations/Variations in Quantities and Pricing.

The quantities given in the “Schedule of Quantities" are based on estimates and are meant to indicate the extent of the work and to provide a uniform basis for tendering and any variation either by addition or omission shall not vitiate the contract. 5.1 The company through its Engineer-in-Charge or his representative shall, without radically changing the original scope and nature of the work, under contract, have power to make any alterations in or additions to or substitution of the original specifications, drawings, designs and instructions that may appear to be necessary or advisable during the progress of the work.

The contractor shall be bound to carry out the work(s) in accordance with the instructions given to him in writing by the Engineer-in-Charge or his representative on behalf of the company. Such altered or additional or substituted work, which shall form part of the original contract, shall be carried out by the contractor on the same terms and conditions in all respects on which they agreed to do the main work and at the same rate/rates as are specified in the contract/ work-order. 5.2 The right is reserved to cancel any items of work included in the contract agreement or portion thereof in any stage of execution if found necessary to the work and such omission shall not be a waiver of any condition of the contract nor invalidate any of the provisions thereof. 5.3 If the additional, altered or substituted work includes any class of work for which rate/rates is/are not specified in the contract/work order, rates for such items shall be determined by the Engineer-in-Charge as follows:

a) In the case of percentage tenders, if the rate for the extra item of work executed is available in the company's approved SOR, it will be paid at the schedule rate plus or minus the accepted percentage as per contract.

However, if the extra item is not available in company’s approved SOR, then the rate for such extra item(s) shall be dealt as at (c) below. b) In case of item rate tenders, the rate for extra item shall be derived from the rate for similar item or near similar item / class of work available in the agreement schedule of work or by analysis of rates as at below and the lower rate out of the above two shall be considered. In case of composite item rate tenders, where two or more schedule of quantities for similar item description may form part of the contract, the applicable rates shall be taken from the Schedule of Quantities of that particular part in which the deviation is involved, failing that at the lowest applicable rate for the similar item of work in the other schedule of quantities. For derivation of rates based on analysis, the same shall be done by analysis on prevalent market rate of materials and labour based on standard norms of analysis of rate of C.P.W.D/ N.B.O. c) In the case of extra item(s) that are completely new, and are in addition to the items contained in the contract, the contractor may within 15 days of receipt of order or occurrence of the item(s) claim rates, supported by proper analysis. The Engineer-in-Charge shall determine the rate(s) by analysis based on prevalent market rate of material and labour and on standard norms of analysis of rate of CPWD / NBO. d) In case of combined tender with partly item rate for non-schedule items & partly percentage tenders for SOR items, the rate for extra item shall be derived as at (b) & (c) above in case of non-schedule items rates and in case of percentage rates for SOR items the rate for extra item shall be derived as at (a) above. In case of any difference between the contractor and the Engineer-In Charge as to the fixation of rates, the matter shall be referred to the accepting authority of the company i.e. GM(C) of the company or Staff Officer(C) for the work awarded at Company Hqrs. level and Area level respectively, whose decision shall be final and binding on the contractor.

28

CONDITIONS OF CONTRACT

5.4 Alteration in the quantities shall not be considered as a change in the condition of the contract nor invalidate any of the provision thereof provided that a deviation estimate / revised estimate / supplementary agreement for the item(s) involved is made. Such approval shall be from appropriate authority.

5.5 Payment for such deviated items [additional/ altered / substituted items of work of the agreement schedule] shall be made in the contractors running on account bills, till the revised estimate / deviation estimate regularizing these items are sanctioned by the competent authority of the company, at the provisional rates and shall not exceed :

a) 75% of the rate recommended by the Engineer-in-Charge to the accepting authority of the company i.e. GM(C) of the company or SO(C) of the Area, if the rate is directly available in the SOR of the company/ if the rate is derived from available rate of BOQ.

b) 50% of the rate recommended by the Engineer-in-Charge to the accepting authority of the company, i.e. GM(C) of the company or SO(C) of the Area , if it is analysed item rates based on prevalent market rates of materials and labour following CPWD / NBO norms. Total payment for such extra items of work shall not exceed 10% of work order / agreement value / approved deviation estimate value. Also total payment including extra items of work shall not exceed the work order / agreement / approved deviation estimate value.

5.6 PROVISIONS FOR DEALING WITH VARIATIONS IN RESPECT OF ABNORMALLY HIGH RATE AND ABNORMALLY LOW RATE ITEMS. The abnormally high rate items are those whose quoted rates are more than 20% of the justified rates decided by the owner.

The abnormally low rate items are those whose quoted rates are less than 20% of the justified rates decided by the owner.

In case of Item Rate Tenders, the revision of rates for (i) abnormally high rate items and (ii) abnormally low rate items, shall become operative under the following circumstances:- For increase in quantity of more than 25% in respect of works executed below plinth level and 10% in respect of works executed above plinth level. Quantity variation beyond the limit mentioned above shall be dealt by arriving at new rate based on prevalent market rate of materials and labour analysed as per standard analysis of rate of CPWD/NBO. Payment of extra quantity over the permitted quantity as explained above would be made on the basis of the new analysed rate. The variation in quantity of abnormally low rate items for item rate tenders shall not be permitted below 25% for the items below plinth level and below 10% for the items above plinth level of the agreement schedule quantity, but in exceptional cases with written consent of Engineer-in-Charge arising out of technical necessity. The above provisions shall be applicable for item rate tenders only and not applicable for percentage rate tenders for works based on standard schedule of rates of the company. For the purpose of operation, the following works shall be treated as works related to foundation, unless otherwise defined in the contract.

a) For Buildings: All works up to 1.2 metres above ground level or up to floor 1 level whichever is lower.

b) For abutments, piers and well steining : All works up to 1.2m above the bed level. c) For retaining walls, wing walls, compound walls, chimneys, overhead reservoirs / tanks and other

elevated structures: all works up to 1.2 metres above the ground level. d) For reservoirs / tanks (other than overhead reservoirs / tanks): All works up to 1.2 metres above

the ground level.

29

CONDITIONS OF CONTRACT

e) For basement : all works up to 1.2m above ground level or up to floor 1 level whichever is lower. For Roads, all items of excavation and filling including treatment of sub base 5.7 The time of completion of the originally contracted work shall be extended by the company in the event of any deviation resulting in additional cost over the awarded value, if requested by the contractor as follows:-

(i) In the proportion which the additional cost of the altered, additional or substituted work (in value) bears to the original tendered value plus.

(ii) 25% of the time calculated in (i) above or such further additional time as may be considered reasonable by the Engineer-in-Charge.

5.8 The company through its Engineer-in-Charge or his representative, on behalf of the company, shall have power to omit any part of the work in case of non-availability of a portion of the site or for any other reason and the contractor shall be bound to carry out the rest of the work in accordance with the instructions given by the Engineer-in-Charge. No claim from the Contractor shall be entertained/ accepted on these grounds. 5.9 In the event of any deviation being ordered which in the opinion of the contractor changes radically the original scope/nature of the contract, the contractor shall under no circumstances suspend the work, either original or altered or substituted, and the dispute/disagreement as to the nature of deviation and the rate/rates to be paid for such deviations shall be resolved separately with the company as per the procedures/ norms laid down hereafter.

6. Time for Completion of Contract, Extension thereof, Defaults and Compensation for Delay

Time is the essence of the contract and as such all works shall be completed within the time stipulated in the contract/ work order. The work shall, throughout the stipulated period of contract, be carried out with all due diligence on the part of the contractor. Immediately after the contract is concluded i.e. LOA / Work Order is issued, the Engineer-in-Charge and the contractor shall agree upon a detailed time and progress chart prepared based on BAR CHART/ PERT CPM techniques on the basis of a construction schedule submitted by the contractor at the time of executing contract showing the order in which the work is proposed to be carried out within the time specified in the LOA /work order. For the purpose of this detailed time and progress chart, the work shall be deemed to have commenced on the expiry of 10* (ten) days from the issue of Letter of Acceptance of Tender or 7(seven) days after handing over the site of work or handing over reasonable number of working drawings to the contractor or the period of mobilization allowed in the work order for starting the work in special circumstances, whichever is later. * For Specialized Works/ High Value Works (above Rs. 5 crores), the period shall be 30 days. 6.1 If the contractor, without reasonable cause or valid reasons, commits default in commencing the work within the aforesaid time limit, the company shall, without prejudice to any other right or remedy, be at liberty, by giving 15 day’s notice in writing to the contractor to commence the work, failing which to forfeit the Earnest Money deposited by him and to rescind the Letter of Acceptance of Tender/Work Order and also to debar the contractor to take part in the future re-tender. The Company may debar such defaulting Contractors from participating in future Tenders for a minimum period of 12(twelve) months. 6.2 If the contractor fails to complete the work and clear the site on or before the date of completion or extended date of completion, he shall without prejudice to any other right or remedy available under the law to the company on account of such breach, pay as compensation (Liquidated Damages):

30

CONDITIONS OF CONTRACT

i) @ half percent (½ %) of the contract amount/Revised Contract amount whichever is less, per week of delay.

OR ii) ½ % of the contract-value of group of items/ revised completion value of group of items whichever is less, per week of delay, for which a separate period of completion is originally given. The aggregate of such compensation/ compensations shall not exceed:

i)10% (ten) percent of the total amount of the contract/ Revised contract amount, whichever is less. OR

ii) 10% of the contract-value of group of items/ revised completion value of group of items whichever is less, for which a separate period of completion is originally given. The amount of compensation may be adjusted or set off against any sum payable to the contractor under this or any other contract with the company. 6.2.1 The company, if satisfied, that the works can be completed by the contractor within a reasonable time after the specified time of completion, may allow further extension of time at its discretion with or without the levy of L.D. In the event of extension granted being with L.D, the company will be entitled without prejudice to any other right or remedy available in that behalf, to recover from the contractor as agreed damages equivalent to half percent of the contract value of the works for each week or part of the week subject to a ceiling as described at Cl.6.2.

6.2.2 The company, if not satisfied that the works can be completed by the contractor, and in the event of failure on the part of the contractor to complete work within further extension of time allowed as aforesaid, shall be entitled, without prejudice to any other right, or remedy available in that behalf, to rescind the contract. 6.2.3 The company, if not satisfied with the progress of the contract and in the event of failure of the contractor to recoup the delays in the mutually agreed time frame, shall be entitled to terminate the contract. 6.2.4 In the event of such termination of the contract as described in clauses 6.2.2 or 6.2.3 or both, the company, shall be entitled to impose penalty/LD as deliberated at Clause 10. Additionally the contractor shall be debarred from participating in the future tenders for a minimum period of 12 months. 6.3 The company may at its sole discretion, waive the payment of compensation on request received from the contractor indicating valid and acceptable reasons if the entire work is completed within the date as specified in the contract/work order or as validly extended date without stipulating any compensation for delay. 6.4 Extension of date of completion: On occurrences of any events causing delay as stated here-under, the contractor shall intimate immediately in writing to the Engineer-in-Charge.

a) Force Majeure:

i) Natural phenomena like unprecedented flood and draught, earthquakes & epidemics. ii) Political upheaval, civil commotion, strikes, lockouts, acts of any Govt. (domestic/foreign) including but not limited to war, proprieties, and quarantine embargoes.

The successful bidder/ contractor will advise in the event of his having to resort to this clause by a registered letter duly certified by the local chamber of commerce or statutory authorities, the beginning and end of the cause of delay, within fifteen days of the occurrence and cessation of such Force Majeure condition. In the event of delay due to Force Majeure for more than one month the contract may be terminated at the discretion of the company. Termination under such circumstances will be without any liability on either side.

31

CONDITIONS OF CONTRACT

For delays arising out of Force Majeure, the bidder / contractor will not claim extension in completion date for a period exceeding the period of delay attributable to the clauses of Force Majeure and neither company nor bidder / contractor shall be liable to pay extra cost (like increase in rates, remobilization advance, idle charges for labour and materials etc.) provided it is mutually established that Force majeure conditions did actually exists.

b) Serious loss or damage by fire and abnormally bad weather.

c) Non-availability of stores which are the responsibility of the company to supply as per contract.

d) Non-availability of working drawings in time, which are to be made available by the company as per contract during progress of the work.

e) Delay on the part of the contractors or tradesmen engaged by the company not forming part of the contract, holding up further progress of the work.

f) Non-availability or breakdown of tools and plant to be made available or made available by the company. g) The execution of any modified or additional items of work or excess quantity of work. h) Any other causes which, at the sole discretion of the company, is beyond the control of the contractor.

6.4.1 A HINDRANCE REGISTER shall be maintained by both department and the contractor at site to record the various hindrances, as stated above, encountered during the course of execution.

Hindrance register will be signed by both the parties. The contractor may also record his observations in the Hindrance Register. In case the contractor has a different opinion for hindrance and a dispute arises then the matter would be referred to the EIC and or the next higher authority whose decision would be final & binding on the contractor & the decision to be communicated within 15 days.

6.4.2The contractor shall request the company in writing for extension of time within 15 days of happening of such event causing delay stating also, the period for which extension is required. The company may, considering the genuinity of the request, give a reasonable extension of time for completion of the work. Such extension shall be communicated to the contractor in writing by the company through the Engineer-in-Charge within 1(one) month of the date of receipt of such request. 6.4.3 The opinion of the Engineer-in-charge, whether the grounds shown for the extension of time are or are not reasonable, is final. If the Engineer-in-charge is of the opinion that the grounds shown by the contractor are not reasonable and declines to the grant of extension to time, the contractor cannot challenge the soundness of the opinion. The opinion of the Engineer-in-charge that the period of extension granted by him is proper or necessary is not, however, final. If the contractor feels that the period of extension granted is inadequate he can appeal to the GM(Civil)/ CM(Civil) of the company for consideration on the question whether the period of extension is or is not proper or necessary. 6.4.4 Provisional extension of time may also be granted by the Engineer-in-Charge during the course of execution, on written request for extension of time within 15(fifteen) days of happening of such events as stated above, reserving the company's right to impose/ waive penalty at the time of granting final extension of time as per contract agreement. 6.4.5 When the period fixed for the completion of the contract is about to expire, the question of extension of the contract may be considered at the instance of the Contractor or the Department or of both. The extension will have to be by party's agreement, express or implied.

In case the contractor does not apply for grant of extension of time within 15(fifteen) days of the hindrance

32

CONDITIONS OF CONTRACT

occurring in execution of the work and the department wants to continue with the work beyond the stipulated date of completion for reason of the work having been unavoidably hindered, the Engineer-in-charge can grant extension of time even in the absence of application from the contractor. Such extension of time granted by the Engineer-in-Charge is valid provided the contractor accepts the same either expressly or implied by his actions before and subsequent to the date of completion. Such extension of time shall be without prejudice to Company's right to levy compensation under the relevant clause of the contract. The contractor shall however use his best efforts to prevent or make good the delay by putting his endeavors constantly as may be reasonably required of him to the satisfaction of the Engineer-in-Charge.

7. Material Supply & other facilities :

The contractor shall at his own expense, provide all materials required for the work, unless otherwise specified, and the rates quoted by the contractor shall be for finished work inclusive of all materials required for completion of the work as specified in the contract.

* The company may, of its own or at the request of the contractor, supply such materials as may be specified, if available, at rate/rates to be fixed by the Engineer-in-charge. 7.1 For the materials which the company has agreed to supply for the contract, the contractor shall give in writing of his requirements in accordance with the agreed phased programme to the Engineer-in-charge sufficiently in advance.

The value of materials so supplied shall be set off or deducted from the payment to be made for the items of work in which such materials have been consumed, or from any sum then due or to become due to the contractor thereafter.

7.2* The company will supply steel both reinforcement and structural and cement at the following rates inclusive of all taxes. The contractor shall bear all the cost for transportation; handling and storage from the issuing store of the company to contractor's work site store.

i) Reinforcement Steel *:- a) M.S. Round : Rs. b) Tor Steel : Rs. c) Structural Steel : Rs. ii) Cement * : Rs. [* delete whichever is not applicable ] 7.3 If the steel is issued by the department, the wastage of steel shall be the barest minimum. The wastage allowed from theoretical quantity will be upto a maximum of 5% to cover the wastage due to cutting into pieces, bending and other factors. No cut pieces or scrap less than 2 mtr. in length will be taken by the department. Efforts should be made to use the cut pieces of 2 mtr. or above length as far as possible. If the wastage of steel is more than the permissible variation mentioned above the cost of excess wastage made by the contractor shall be recovered at double the issue rates indicated above, or 115% of prevailing market rate including all taxes during the period of work, whichever is more. No allowances shall be entertained on account of Rolling Margin for the steel either issued by the department or procured by the contractor. 7.4 If the cement is issued by the department, the variation of 5% will be permitted over the theoretical consumption of cement for value of work up to Rs.10.00 lakhs and 3% for value of work above Rs.10.00 lakhs. In the event of cement consumed is more/less than specified above, the recovery for the quantity of cement consumed in excess or less than the specified quantity shall be made at double the issue rate or 115% of

33

CONDITIONS OF CONTRACT

prevailing market rate including all taxes during the period of work, whichever is more. 7.5 In case the department is not able to supply cement/steel as per the provisions of the contract, the Engineer-in-Charge may allow, with the approval of GM/HOD(Civil) of the company, the contractor in writing for procurement of cement/ steel from the approved sources and the extra on this account including transport charges, if any, over the issue rate shall be reimbursed to the contractor on production of authentic documents. Transportation of cement/ steel from the place of purchase to the site of work and proper storage of cement/steel at site shall be contractor's responsibility. He should maintain proper account of cement/steel issued/procured by him and should allow inspection of his godown and his cement/steel account by the concerned Engineer-in-charge or any other authorized officers of the company. Contractor should draw materials from the company on the basis of actual requirement as assessed by the Engineer-in-Charge on "as and when required" basis. 7.6 Recovery of cost of materials issued on sale A/c will be made as per actual consumption basis but the Engineer-in-Charge will have the discretion for making full recovery while processing a particular bill or asking for the return of the balance materials if the work is not progressing satisfactorily. The contractor shall keep accurate record of materials issued by the company, maintain proper account for the materials received and consumed in the work and shall be open to check by the Engineer-in-Charge or his authorized representative. The contractor shall ensure that such materials are consumed for the contract works only and the Register for the aforesaid account shall be signed both by the representatives of Engineer In Charge and the contractor. 7.7 All materials, tools and plants brought to site by the contractor including the materials supplied by the company shall be deemed to be held in lien by the company and the contractor shall not have the right to remove the same from the site, without the written permission of the Engineer-in-Charge. The company shall not however be liable for any loss, theft or damage due to fire or other cause during this period of lien, the responsibility for which shall lie entirely on the contractor. 7.8 The contractor shall bear the cost of loading, transportation to site, unloading, storing under cover as required etc. as may be necessary for the use and keeping the materials in good condition. 7.9 Any surplus materials issued by the company, remaining after completion or termination of the contract, shall be returned by the contractor at his cost to the place of issue and the Engineer-in-Charge shall accept the same at the rate not exceeding the rate at which these were originally issued taking into consideration the deterioration or damage, if any, that may have been caused during the custody of the contractor. In the event, the contractor fails to return the surplus materials out of those supplied by the company, the Engineer-in-Charge may, in addition to any other liability which the contractor would incur in this regard, by giving notice in writing require the contractor to pay the amount at double the issue rate for such unreturned surplus materials or 115% of the prevailing market rate including all taxes during the period of work, whichever is more.

7.10 On completion or on termination of the contract and on complete recovery of secured advance paid by the company, if any, in respect of materials brought to site, the contractor with due permission of the Engineer-in-Charge shall be entitled to remove at his expenses all surplus materials originally supplied by him and upon such removal, the same shall become the property of the contractor.

7.11 All charges on account of Taxes and Duties on materials obtained for the works from any source (excluding materials supplied by the company) shall be borne by the contractor and GST on supply of services shall be reimbursed to the contractor (supplier) by SECL as per GST Act & Rules. 7.12 The contractor shall arrange necessary electricity at his own cost for the work and his own establishment. However, if available and feasible the company may arrange electricity at one point near the work site and necessary recovery of cost of energy consumed will be made at rates prescribed by the company from time to time. Energy meter for this purpose shall be provided by the contractor.

34

CONDITIONS OF CONTRACT

7.13 The contractor shall arrange necessary water for the work and his own establishment and nothing extra will be paid for the same. Such water used by the contractor shall be fit for construction purposes. However, if available and feasible the company may arrange water, at the written request of the contractor, to the extent possible, at one point near the work site for which recovery @ 1% of the contract value of work done will be made from the contractor's bills. The contractor shall make his own arrangement of water connection and laying of pipe lines from main source of supply. Department do not guarantee to maintain uninterrupted supply of water. No claim of damage or refund of water charges will be entertained on account of such break down.

7.14 Explosives, detonators and other inflammable materials shall not be used in the execution of the work at site by the contractor without prior written permission of the Engineer-in-Charge. Transportation and storage of such materials shall be done in specified manner in accordance with the law in force. The contractor shall also obtain license under such laws for, transportation, storage, use and all other operations, connected with the handling of the same.

8. Quality Assurance - Materials and Workmanship

The contractor shall carry out and complete the work in every respect in accordance with the contract and shall ensure that the work conforms strictly to the drawings, specifications, (as enclosed or in absence of enclosed specifications current CPWD/BIS specifications) instructions of the Engineer-in-Charge. The Engineer-in-Charge may issue, from time to time, further drawings, detailed instructions/ directions in writing to the contractor. All such drawings, instructions/directions shall be consistent with the contract documents and should be reasonably inferable there from, along with clarifications/ explanations thereof, if necessary. However, the contractor will be solely responsible for design and erection of all temporary structures required in connection with the work. 8.1 For Quality Assurances of all the Civil Engineering Works the norms/ guidelines laid down by the company herein and elsewhere will form part of the contract for the purpose of quality of works. 8.2 The contractor shall be responsible for correct and complete execution of the work in a workman like manner with the materials as per specification which shall be subject to the approval of the company. All work under execution in pursuance of the contract shall be open to inspection and supervision by the Engineer-in-Charge or by his authorized representative or any other official of higher rank or any other person authorized by the company in his behalf & the contractor shall allow the same.

8.3 All materials to be provided by the contractor shall be in conformity with the specifications/schedule of work as per the contract and the contractor shall furnish proof, if so required by the Engineer-in-Charge to his satisfaction that the materials do so comply. 8.4 The contractor shall immediately after the award of work draw up a schedule giving dates for submission of samples as required or necessary as per the specification for approval of Engineer-in-Charge who shall approve, if found acceptable, promptly so that there is no delay in the progress of the work of the contractor or of the work of any of the sub-contractor. On receipt of samples as per schedule, the Engineer-in-Charge shall arrange to examine/test with reasonable promptness ensuring conformity of the samples with the required specification and complying with the requirements as per contract documents keeping in view that the work shall be in accordance with the samples approved by him. The contractor shall be bound to furnish fresh sample, if disapproved by the Engineer-in-Charge, for his approval. The contractor shall not start bringing materials at the site unless the respective samples are approved. Materials conforming to approved samples shall only be brought to site. However, Engineer-in-Charge’s approval for any sample, design / drawings (permanent / temporary structures) shall not alter contractor’s full responsibility whatsoever for the performance and safety of the executed job. Samples are to be supplied by the contractor at his own cost. The cost involved in tests shall be borne by the

35

CONDITIONS OF CONTRACT

contractor. If any test is ordered by the Engineer-in-Charge which is to be carried out by any independent person or agency at any place other than the site even then the cost of materials and testing charge etc. shall be borne by the contractor. If the test shows that the materials are not in accordance with the specifications, the said materials shall not be used in the work and removed from the site at contractors cost. 8.5 The company, through the Engineer-in-Charge, shall have full powers to reject any materials or work due to a defect therein for not conforming to the required specification, or for materials not being of the required quality and standard or for reasons of poor workmanship or for not being in accordance with the sample approved by him. The contractor shall forthwith remedy the defect/replace the materials at his expense and no further work shall be done pending such rectification/replacement of materials, if so instructed by the Engineer-in-Charge. In case of default on the part of the contractor, the Engineer-in-Charge shall be at liberty to procure the proper materials for replacement and/or to carry out the rectifications in any manner considered advisable under the circumstances and the entire cost & delay for such procurement/rectification shall be borne by the contractor.

8.6 The Engineer-in-Charge shall be entitled to have tests carried out for any materials, according to the standard practice followed for such tests, other than those for which satisfactory proof has already been furnished by the contractor who shall provide at his expense all facilities which the Engineer-in-Charge may require for the purpose. All such expenses born by the contractor are not to be paid separately by the employer and shall be assumed covered in accepted prices. The cost of any other tests, if so required by the Engineer-in-Charge, shall be borne by the company. However if the test shows the workmanship or materials not to be in accordance with the provision of the contract or the instruction of Engineer-in-Charge the cost shall be borne by the contractor. . 8.7 Access to the works: The Engineer-in-charge and any person authorized by the company shall at all times have access to the works and to all workshops and places where work is being prepared or from where materials, manufactured articles are being obtained for the works and the contractor shall afford every facility for and every assistance in or in obtaining the right to such access. 8.8 Inspection of works: i) No work shall be covered up or put out of view without the approval of the Engineer-in-charge or the Engineer-in-charge's representative or any other officer nominated by the company for the purpose and the contractor shall afford full opportunity for the EIC or EIC`s representative or any other officer nominated by the company for the purpose to examine and measure any work which is about to be covered up or put out of view and to examine foundations before permanent work is placed thereon. the contractor shall give due notice to the Engineer-in-charge's representative whenever any such work or foundations is ready or about to be ready for examination and the Engineer-in-charge's representative shall, without unreasonable delay, unless he considers it unnecessary and advises the contractor accordingly, attend for the purpose of examining and measuring such work or foundations. ii) The contractor shall uncover any part or parts of the works or making openings in or through the same as the Engineer-in-Charge may from time to time direct and shall reinstate and make good such part or parts to the satisfaction of Engineer-in-charge. If any such part or parts have been covered up or put out of view after compliance with the requirement of sub-clause above and are found to be executed in accordance with the contract, the expenses of uncovering, making openings in or through and making good the same shall be borne by the Employer, but in any other cases all costs shall be borne by the contractor. 8.9 Removal of Improper Work and Materials: i) The Engineer-in-charge shall during the progress of the works have power to order in writing from time to time:

36

CONDITIONS OF CONTRACT

a) The removal from the site, of any materials which in the opinion of Engineer-in-charge, are not in accordance with the contract/ work order/ approved sample.

b) The substitution with proper and suitable materials. c) The removal and proper re-execution, notwithstanding any previous test thereof or interim payment there from, of any work which in respect of materials or workmanship is not in accordance with the contract. ii) In case of default on the part of the contractor in carrying out such order, the Engineer-in -charge shall be entitled to employ and pay other agency to carry out the same and all expenses consequent thereon shall be recoverable from the contractor or may be deducted from any amount due or which may become due to the contractor. 8.10 Devaluation of Work : In lieu of rejecting work done or materials supplied not in conformity with the contract/work order/approved samples, the Engineer-in-charge or any other officer nominated by the company for the purpose may allow such work or materials to remain, provided the Engineer-in-Charge/ the officer nominated by the company is satisfied with the quality of any materials, or the strength and structural safety of the work, and in that case shall make such deduction for the difference in value, as in his opinion may be reasonable. 8.11 Final Inspection of Work: The Engineer-in-charge and any other officer nominated by the company for the purpose shall make final inspection of all work included in the contract/work order, or any portion thereof, or any completed structure forming part of the work of the contract, as soon as practicable after notification by the contractor that the work is completed and ready for acceptance. If the work is not acceptable to the Engineer-in-charge at the time of such inspection, he shall inform the contractor in writing as to the particular defects to be remedied before final acceptance can be made. 8.12 Defects appearing after acceptance: Any defects which may appear within the defect liability period and arising, in the opinion of the Engineer-in-charge, from lack of conformance with the drawings and specifications, shall, if so required by the Engineer-in-charge in writing, be remedied by the contractor at his own cost within the time stipulated by the Engineer-in-charge. If the contractor fails to comply, the Engineer-in-charge may employ other persons to remedy the defects and recover the cost thereof from the dues of the contractor. 8.13 Site Order Book : A Site Order Book is a Register duly certified by the Engineer-in-charge regarding number of pages it contains, each page being numbered, name of work, name of contractor, reference of contract/ work order and the aforesaid certificate should be recorded on its first page. Site Order Books shall be maintained on the sites of works and should never be removed there from under any circumstances. It shall be the property of the company. The Engineer-in-Charge or his authorized representative shall duly record his observations regarding any work which needs action on the part of the contractor like, improvement in the quality of work, failure to adhere to the scheduled programme etc. as per contract/work order. The contractor shall promptly sign the site order book and note the orders given therein by the EIC or his representative and comply with them. The compliance shall be reported by the contractor in writing to EIC in time so that it can be checked. The Site Order Book will be consulted by the Engineer-in-Charge at the time of making both running on account and final bills of the contractor. A certificate to this effect should be given in the Measurement books by the Engineer-in-Charge or his representative. 8.14 Samples and Testing of Materials: All the materials to be procured by the contractor and to be used in work shall be approved by the Engineer-in-Charge in advance, and shall pass the tests and analysis required by him, which will be as specified in the specifications of the items concerned and or as specified by BIS or the IRC / MORTH standard specifications acceptable to the Engineer-in-Charge. The method of sampling and testing shall be as per the relevant BIS, IRC/ MORTH and other relevant standards and practices. Minor minerals like

37

CONDITIONS OF CONTRACT

sand, stone chips etc. shall be conforming to relevant BIS standards. All bought out items including Cement and Steel shall be procured from such manufacturers who hold valid license conforming to relevant BIS standards for manufacturing of such items.

8.15 Storage of Materials: Materials shall be so stored as to ensure the preservation of the quality and fitness for the work. When considered necessary by the Engineer-in-charge, they shall be placed on wooden platforms or other hard, clean surfaces and not directly on the ground. Materials shall be placed under cover when so directed and the contractor shall erect and maintain at his own cost temporary weather-proof sheds at the work site for the purpose. Stored materials shall be so located as to facilitate prompt inspection. All stored materials shall be inspected at the time of use in the work, even though they may have been inspected and approved before being placed in storage or during storage. 8.16 Defective Materials: All materials not conforming to the requirements of the specifications shall be considered as defective, and all such materials, whether in place or not shall be rejected. They shall be removed immediately by the contractor at his expenses and replaced with acceptable material. No rejected material, the defects of which have been subsequently corrected, shall be used on the work until approval in writing has been given by the Engineer-in-Charge. Upon failure on the part of the contractor to comply with any instruction of the Engineer-in-charge made under the provisions of this article within the time stipulated by the Engineer-in-charge, the Engineer-in-charge shall have authority to remove and replace defective material and recover the cost of removal and replacement from the contractor. Further all such defective material lying at site not removed and replaced within 30 days after issue of notice by the Engineer-in-charge, if the Engineer-in-charge so decides shall dispose off such material in any manner without any further written notice to the contractor.

9. Measurement and Payments

Except where any general or detailed description of the work in the Bill of Quantities or specifications of the contract/ work order provides otherwise, measurement of work done shall be taken in accordance with the relevant standard method of measurement published by the Bureau of Indian Standards (BIS) and if not covered by the above, other relevant Standards/practices shall be followed as per instructions of the Engineer-in-Charge. 9.1 All items of work carried out by the contractor in accordance with the provision of the contract having a financial value shall be entered in the Measurement Book as prescribed by the company so that a complete record of the measurements is available for all the works executed under the contract and the value of the work executed can be ascertained and determined there from. Measurements of completed work / portion of completed work shall be recorded only in the Measurement Books. 9.2 Measurement shall be taken jointly by the Engineer-in-Charge or his authorized representative and by the contractor or his authorized representative. 9.3 Before taking measurements of any work, the Engineer-in-Charge or the person deputed by him for the purpose shall intimate the contractor to attend or to send his representative to attend the measurement. Every measurement thus taken shall be signed and dated by both the parties on the site on completion of the measurement. If the contractor objects to any measurements, a note to that effect shall be made in the Measurement Book / Log Book and signed and dated by both the parties. 9.4 The measurement of the portion of work/items of work objected to, shall be re-measured by the Engineer-in-Charge himself or the authority nominated by the company for the purpose in the presence of the contractor or his authorized representative and recorded in the M.B. which shall be signed and dated by both the parties. Measurements so recorded shall be final and binding upon the contractor and no claim whatsoever shall thereafter be entertained.

38

CONDITIONS OF CONTRACT

In case the contractor or his authorized representative does not attend to the joint measurements at the prefixed date and time after due notice, the measurements taken by the Engineer-in-Charge or his representative shall be final and binding on the contractor. Measurement of the extra items of work or excess quantities of work duly authorized in writing by the Engineer-in-Charge shall also be taken and recorded in the M.B. based on the existing items in the SOR of the company and if such items do not exist in the company's SOR, the description of the work shall be as per actual execution. Payment for such extra items will be based on the rates to be derived as described in the relevant clauses of the contract/ work-order. 9.5 No work shall be covered up or put out of view without the approval by the Engineer-in-Charge and recording of measurements and check measurement thereof duly accepted by the contractor. The contractor shall provide full opportunity to the Engineer-in-Charge or his representative to examine and measure all works to be covered up and to examine the foundations before covering up. The contractor shall also give notice to Engineer-in-Charge whenever such works or foundations are ready for examination and the Engineer-in-Charge shall without unreasonable delay arrange to inspect and to record the measurements, if the work is acceptable and advise the contractor regarding covering of such works or foundations. 9.6 In case of items which are claimed by the contractor but are not admissible according to the department, measurements of such items, will be taken for record purposes only and without prejudice so that in case it is subsequently decided by the department to admit the contractor's claims, there should be no difficulty in determining the quantities of such work. A suitable remark should, however, be made against such measurements to guard against payment in the ordinary way. 9.7 Payments: The running on account payments may be made once in a month or at intervals stipulated in the work order/ contract agreement. 9.7.01 Running on account bill/bills for the work executed/ materials supplied in accordance with the work order/ contract shall be prepared on the basis of detailed measurements recorded as described hereinbefore and processed for payments. 9.7.02 Payment of on account bill shall be made on the Engineer-in-Charge's certifying the sum to which the contractor is considered entitled by way of interim payment for the following : a) The work executed as covered by the bill/bills after deducting the amount already paid, the Security Deposit and such other amounts as may be deductible or recoverable in terms of the work order/ contract. b) (i) Payment for excess quantity of work done with the written instructions of the Engineer-in-Charge for items already appearing in the bill of quantities of work with approved rates, will be made along with the on account bills only up to 10% of the quantity provided in the agreement subject to overall value of work not exceeding the agreement value. (ii) The GM(Civil) of the company and / or the Staff Officer(C) of the Area may authorize interim payment for excess work done up to 20 % of the quantity of work provided in the Bill of Quantity of the work awarded from Company level and Area level respectively subject to overall value of work done does not exceed the contract value. This however, shall not be applicable for High Value Items. c) Extra items of work executed will be paid on specific written authorization of GM(C) of the company or Staff Officer (Civil) of the Area provided that the value of such extra items of work when added together is not more than 10% of the contract value and the total gross payment including excess quantity does not exceed the contract value. Balance amount on account of excess quantity and extra items of work executed shall be paid after the

39

CONDITIONS OF CONTRACT

deviation estimate / revised estimate regularizing the extra items and excess quantities of work is sanctioned by the competent authority of the company with the concurrence of the Finance Department of the company. d) On the Engineer-in-Charge's certificate of completion in respect of the work covered by the contract / final measurements of the work certified by the Engineer In Charge or his representative. 9.7.03 The measurements shall be entered in the M.B for the work done up to the date of completion and evaluated based on the approved rates for the items in the contract agreement/sanctioned revised estimate. In case of extra items of work, the rates shall be derived as stated in the relevant clause of the contract. The payments shall be released against the final bill subject to all deductions which may be made on account of materials supplied, water supply for construction, supply of electricity and any other dues payable by the contractor to the company, and further subject to the contractor having given to the Engineer-in-Charge a no claim certificate. The contractor shall indemnify the company against proof of depositing royalty on account of minor minerals used in the work before the final bill is processed for payments. The final payment to be made will also be subject to Clause-4.6 & 4.7 of the General Terms & Conditions of the contract. 9.7.04 Any certificate given by the Engineer-in-Charge for the purpose of payment of interim bill/bills shall not of itself be conclusive evidence that any work/materials to which it relate is/are in accordance with the contract and may be modified or corrected by the Engineer-in-Charge by any subsequent certificate or by the final certificate. 9.7.05 The company reserve the right to recover/enforce recovery of any overpayments detected after the payment as a result of post payment audit or technical examination or by any other means, notwithstanding the fact that the amount of disputed claims, if any, of the contractor exceeds the amount of such overpayment and irrespective of the facts whether such disputed claims of the contractor are the subject matter of arbitration or not.

The amount of such overpayments shall be recovered from subsequent bills under the contract, failing that from contractor's claim under any other contract with the company or form the contractor's Security Deposit or the contractor shall pay the amount of over payment on demand. In case of contractor's non-payment on such demand, the same should be realised from the contractor's dues, if any, with Coal India Limited or any of its subsidiaries. 9.7.06 The contractors are required to execute all works satisfactorily and according to the specifications laid down in the contract/ work order. If certain items of work, executed by the contractor, are below specifications, the contractor should re-do them according to the specifications and instructions of EIC and if the contractor fails to rectify the defect within the time and in the manner specified by the EIC, the work shall be got re-done or rectified by the department at the risk and cost of the contractor. Engineer-in-Charge may accept such work of below specifications provided the department is satisfied with the quality of such works and the strength/ structural safety of such works. In that case Engineer-in-Charge shall make such deductions for the difference in value, as in his opinion is reasonable and is approved by the accepting authority of the company i.e. GM/HoD(C) of the company in this case or any other officer nominated by GM/HoD(C) for the purpose. 9.7.07 Payment Stage: The payment stage involved will be as under,

i. Signature of Subordinate Engineer(Civil)/ EA(Civil)/ Sr. Overseer(C) / Overseer(C) in MB’s both in pages recording measurements, abstract of bill & the duly filled in bill form.

ii. Signature of Sr. Officer(C)/ Asstt. Manager(Civil) with appropriate check measurements in the MB’s and the bill form.

iii. Signature of Dy. Manager(C)/ Manager(C) with appropriate check measurements in MB’s and the bill form.

iv. Signature of Engineer-in-Charge as per definition as at clause 1(vii) of the General Terms and

40

CONDITIONS OF CONTRACT

Conditions, as a token of acceptance for payment of the bill. The EIC may sign in the abstract of the bill in the MB & the bill form. In between stage iii) and iv) accountal checking may be made by the concerned Accounts Officer/ Accountant.

(In case of non-availability of officials as at (i) above, company may authorize suitable executives for the works outlined at (i). Further for check measurement also company may authorize Executives based on availability.

9.7.08 Secured Advance: Secured advance can be paid for items of materials required for execution of the work and covered under categories A & B and supplied by the contractor at work site, supported by necessary vouchers, challans, test certificates etc. after execution of indemnity bond as per prescribed Form of the company on non-judicial stamp paper of prescribed value.

This advance shall be recovered in four equal installments or as per consumption whichever is higher. Engineer-in-Charge shall recover at his discretion all or any part of secured advance paid, if in his opinion the work is not progressing satisfactorily or the security of these materials at site is not adequately taken care of by the contractor. Secured advance shall be payable for contracts of value above Rs.50.00 lakhs only.

Secured advance for structural steel sections, reinforcement steel and cement, collected at site, will be paid up to 75% of the corresponding stock yard prices of SAIL for the corresponding steel items and Govt. approved/ D.G.S.D. prices for cement, if the same exist.

In case of non-availability of Govt. approved prices of cement & steel and for the materials falling under Category - A and B the secured advance will be paid at the basic rate available in the approved schedule of rates of the company plus or minus the overall percentage on which the work was awarded, provided such rate is not more than 60% of the quoted rate of the contractor for the actual work. At any point of time the outstanding recoverable secured advance shall not be more than 10% of the contract value. Items against which secured advance can be granted: Category-A Civil: 1. Bricks. 2. Stone and brick aggregate. 3. Stones. 4. Finished products of brass, iron and steel such as doors & windows frames, wire mesh, gate, GI Sheets. 5. Pre-cast R.C.C. products such as pipes, jali, water storage tanks etc. 6. Doors & Window fittings. 7. Pipes and sanitary fittings of CI, SCI & HCI Electrical : 1. Steel conduits 2. G.I. Pipes 3. I.C. Boards 4. Switchgears (Air circuit breakers and Air break switches) 5. C.I. Boxes. 6. A.C.S.R. Conductors 7. A.C. Plant & Machinery 8. Pumps 9. Generating sets (without oil) Items against which secured advance can be granted:

41

CONDITIONS OF CONTRACT

Category- B

Civil: 1. Glazed tiles, terrazzo tiles and similar articles. 2. Marble slabs. 3. Asbestos cements products. 4. Finished timber products such as doors, windows, flush doors, particle boards (subject to mandatory test being satisfactory) etc. 5. Bitumen in sealed drums. 6. Bitumen felt. 7. Polythene pipes and fittings and tanks. 8. Sanitary fittings and pipes of S.W., porcelain and chinaware materials 9. Laminated / Safety, one way vision, and bullet proof glasses. 10.Chemical required for anti-termite treatment (in sealed drums). 11. Paints, varnishes, distempers, pigment, spirits etc. Electrical: 1. Transformers 2. Oil-filled switch gears. 3. L.T. &H.T. Cables 4. Fans 5. Storage and Dry Batteries 6. Insulation tapes. 7. Epoxy cable compounds. 8. Electric light fittings. 9. Wooden battens, casing & capping and wooden boards. 10.Flexible wires. 11.PVC materials. 12.Oil and lubricants. 13.Rubber materials. 14.Glass wool, thermocole & other insulating materials. 15.Porcelain H.T. and L.T. insulators. In addition to indemnity bond, for materials listed under Category-B, the contractor shall be required to provide necessary insurance cover of equivalent value of materials. Items against which no secured advance shall be granted: Civil: 1. Glass products other than those indicated in Category-B. 2. Sand and moorum 3. Chemical compounds other than those indicated in Category-B. Electrical: 1. Glass gloves and shades 2. Bulbs and tubes 3. Petrol and diesel 4. Freon and other refrigeration gases. 9.8 Income tax deduction @ 2% (Two percent ) of the gross value (Excluding GST) of each bill or at the rate as amended from time to time, shall be made unless exempted by the competent authority of the Income Tax Department

42

CONDITIONS OF CONTRACT

Building and Construction Workers Cess (as applicable in States) shall be payable by the contractor. If, however, the company is asked to make deduction from the contractor's bills, the same shall be done and a certificate to this effect shall be issued to the contractor for dealing with the State Govt. and the company does not take any responsibility to do anything further in this regard.

9.9 No interest shall be payable on the amounts withheld, under the terms of the Contract Agreement/Work-order.

10 Termination, Cancellation, Suspension and Foreclosure of Contract

The company shall, in addition to other remedial steps to be taken as provided in the conditions of contract be entitled to cancel the contract in full or in part, and whether the date of completion has or has not elapsed, by notice in writing if the contractor:- a) makes default in proceeding with the works with due diligence and continues to do so even after a notice in writing from the Engineer-in-Charge, then on the expiry of the period as specified in the notice Or b) commits default/breach in complying with any of the terms and conditions of the contract and does not remedy it or fails to take effective steps for the remedy to the satisfaction of the Engineer-in-Charge, then on the expiry of the period as may be specified by the Engineer-in-Charge in a notice in writing. Or c) obtains a contract with the company as a result of ring tendering or other non-bonafide methods of competitive tendering Or d) shall offer or give or agree to give any person in the service of the company or to any other person on his behalf any gift or consideration of any kind as an inducement or reward for act/acts of favour in relation to the obtaining or execution of this or any other contract for his company. Or e) fails to complete the work or items of work with individual dates of completion, on or before the date/dates of completion or as extended by the company, then on the expiry of the period as may be specified by the Engineer-in-Charge in a notice in writing. Or f) transfers, sublets, assigns the entire work or any portion thereof without the prior approval in writing from the Engineer-in-Charge. The Engineer-in-Charge may by giving a written notice, cancel the whole contract or portion of it in default.

10.1The contract shall also stand terminated under any of the following circumstances: a) If the contractor being an individual in the case of proprietary concern or in the case of a partnership

firm any of its partners is declared insolvent under the provisions of Insolvency Act for the time being in force, or makes any conveyance or assignment of his effects or composition or arrangement for the benefit of his creditors amounting to proceedings for liquidation or composition under any Insolvency Act.

b) In the case of the contractor being a company, its affairs are under liquidation either by a resolution

passed by the contractors company or by an order of court, not being a voluntary liquidation proceedings for the purpose of amalgamation or reorganization, or a receiver or manager is appointed by the court on the application by the debenture holders of the contractor's company, if any.

c) If the contractor shall suffer an execution being levied on his/their goods, estates and allow it to be

continued for a period of 21 (twenty-one) days. d) On the death of the contractor being a proprietary concern or of any of the partners in the case of a

partnership concern and the company is not satisfied that the legal representative of the deceased proprietor or the other surviving partners of the partnership concern are capable of carrying out and

43

CONDITIONS OF CONTRACT

completing the contract. The decision of the company in this respect shall be final and binding which is to be intimated in writing to the legal representative or to the partnership concern.

10.2 On cancellation of the contract or on termination of the contract, the Engineer-in-charge shall have

powers: a. To take possession of the site, any materials, constructional plant, equipment, stores etc. thereon and carry out balance work through any means or through any other agency. b. To give the contractor or his representative of the work 7 (seven) days notice in writing for taking final measurement for the works executed till the date of cancellation or termination of the contract. The Engineer-in-Charge shall fix the time for taking such final measurement and intimate the contractor in writing. The final measurement shall be carried out at the said appointed time notwithstanding whether the contractor is present or not. Any claim as regards measurement which the contractor is to make shall be made in writing within 7 (seven) days of taking final measurement by Engineer-In-charge as aforesaid and if no such claim is received, the contractor shall be deemed to have waived all claims regarding above measurements and any claim made thereafter shall not be entertained. c. After giving notice to the contractor to measure up the work of the contractor and to take such whole or the balance or part thereof, as shall be unexecuted out of his hands and to give it to another contractor or take up departmentally, to complete the work. The contractor whose contract is terminated shall not be allowed to participate in future bidding for period of minimum twelve months. In such an event, the contractor shall be liable for loss/damage suffered by the employer because of action under this clause and to compensate for this loss or damage, the employer shall be entitled to recover higher of the following: i) Forfeiture of Security Deposit comprising of Performance Guarantee and Retention Money and Additional Performance Security, if any, at the disposal of the employer.

Or ii) 20% of value of incomplete work. The value of the incomplete work shall be calculated for the items and quantities remaining incomplete (as per provision of agreement) at the agreement rates including price variation as applicable on the date, when notice in writing for termination of work was issued to the contractor.

The amount to be recovered from the contractor as determined above, shall, without prejudice to any other right or remedy available to the employer as per law or as per agreement, will be recovered from any money due to the contractor on any account or under any other contract and in the event of any shortfall, the contractor shall be liable to pay the same within 30 days. In case of failure to pay the same the amount shall be debt payable. In the event of above course being adopted by the Engineer-in-charge, the contractor shall have no claim to compensation for any loss sustained by him by reasons of his having purchased materials, equipment or entered into agreement or made advances on any account or with a view to the execution of work or performance of the contract. And in case action is taken under any of provision aforesaid, the contractor shall not be entitled to recover or to be paid any sum for any work thereof or actually performed under this contract unless and until the engineer-in-charge has certified in writing the performance of such work and value payable in respect thereof and he shall only be entitled to be paid the value so certified. The need for determination of the amount of recovery of any extra cost/expenditure or of any loss/damage suffered by the company shall not however arise in the case of termination of the contract for death/demise of the contractor as stated in 10.1(d).

10.3 Suspension of Work:

44

CONDITIONS OF CONTRACT

Suspension of work – The Company shall have power to suspend the work. The contractor shall on receipt of the order in writing of Engineer-in -charge (whose decision shall be final and binding on the contractor), suspend the progress of work or any part thereof for such time in such manner as the Engineer-in-Charge may consider necessary so as not to cause any damage, or endanger the safety thereof for any of the following reasons:

a) on account of any default on the part of the contractor, or b) for proper execution of the works, or part thereof, for reasons other than the default of the contractor or, c) for safety of the works, or part thereof.

The contractor shall, during such suspension properly protect and ensure the works to the extent necessary and carry out the instruction of the Engineer-in-charge. If the suspension is ordered for reasons (b) & (c), the contractor shall be entitled to an extension of time equal to the period of every such suspension plus 25%. This shall also be applicable for completion of the item or group of items of the work for which a separate period of completion as specified in the contract and of which the suspended work forms a part. The contractor shall carry out the instructions given in this respect by the Engineer-In Charge & if such suspension exceeds 45 (forty five) days, the contractor will be compensated on mutually agreed terms. 10.4 Foreclosure of contract:

If at any time after acceptance of the tender the company decides to abandon or reduce the scope of work for any reason whatsoever the company, through its Engineer-in-Charge, shall give notice in writing to that effect to the contractor and contractor shall act accordingly in the matter. In the event of abandonment, the contractor shall have no claim to any payment of compensation or otherwise whatsoever, other than those mentioned below:-

a) to pay reasonable amount assessed and certified by the Engineer-in-Charge of the expenditure incurred, if any, by the contractor on preliminary works at site e.g. temporary access roads, temporary construction for labour and staff quarters, office accommodation, storage of materials, water storage tanks and water supply for the work including supply to labour/ staff quarters, office etc.

b) to pay the contractor at the contract rates full amount for works executed and measured at site up to the date of such abandonment.

c) to pay for the materials brought to site or to be delivered at site, which the contractor is legally liable to pay, for the purpose of consumption in works carried out or were to be carried out but for the foreclosure, including the cost of purchase and transportation and cost of delivery of such materials. The materials to be taken over by the company should be in good condition and the company may allow at its discretion the contractor to retain the materials in full or in part if so desired by him and to be transported by the contractor from site to his place at his own cost with due permission of the EIC. d) to take back the materials issued by the company but remaining unused, if any, in the work on the date of abandonment/reduction in the work, at the original issue price less allowance for any deterioration or damage caused while in custody of the contractor. e) to pay for the transportation of tools and plants of the contractor from site to contractor's place or to any other destination, whichever is less. 10.4.01 The contractor shall, if required by the Engineer-in-Charge, furnish to him books of accounts, papers, relevant documents as may be necessary to enable the Engineer-in-Charge to assess the amounts payable in terms of clauses10.4(a) (c) & (e) of the contract. The contractor shall not have any claim for compensation for abandonment of the work, other than those as specified above.

11. Carrying out Part Work at Risk & Cost of Contractor.

If the progress of the work or of any portion of the work is unsatisfactory, the Engineer-in-Charge, after giving the

45

CONDITIONS OF CONTRACT

contractor 15 days’ notice in writing, without cancelling or terminating the contract, shall be entitled to employ another Agency for executing the job or to carry out the work departmentally or contractually through tendering / limited tendering process, either wholly or partly, debiting the contractor with cost involved in engaging another Agency or with the cost of labour and the prices of materials, as the case may be. The certificate to be issued by the Engineer-in-Charge for the cost of the work so done shall be final and conclusive and the extra cost, if any, shall be borne by the contractor. However, when this clause is invoked, penalty will not be applicable other than on account of delayed completion.

The value of the work taken away shall be calculated for the items and quantities taken away at the agreement rates including price variation as applicable on the date, when notice in writing for taking away part work was issued to the contractor. The contractor, from whom part work is being taken out, shall not be allowed to participate in the tendering process if any. If the expenses incurred by the department is less than the amount payable to the contractor at his agreement rates, the difference shall not be payable to the contractor.

In the event of above course being adopted by the Engineer-in-Charge, the contractor shall have no claim to compensation for any loss sustained by him by reasons of his having purchased or procured any materials or entered into any engagements or made any advance on any account or with a view to the execution of the work or the performance of the contract.

12. Completion Certificate / Defect Liability Certificate

Except in cases where the contract provides for "Performance Test" before issue of Defect Liability certificate, in which case the issue of Defect Liability certificate shall be in accordance with the procedure specified therein, the contractor shall give notice of completion of work, as soon as the work is completed, to the Engineer-in-Charge. The Engineer-in-Charge and or any other Officer, nominated for the purpose by the company, shall within 30 (thirty) days from the receipt thereof, inspect the work and ascertain the defects/deficiencies, if any, to be rectified by the contractor as also the items, if any, for which payment shall be made at reduced rate.

If the defects, according to the Engineer-in-Charge are of a major nature and the rectification of which is necessary for the satisfactory performance of the contract, he shall intimate in writing the defects and instruct the contractor to rectify the defects/remove deficiencies within the period and in the manner to be specified therein. In such cases Defect Liability Certificate will be issued by the EIC after the above rectifications are carried out/ deficiencies are removed by the contractor to the satisfaction of EIC.

In the event there are no defects or the defects/ deficiencies are of a minor nature and the Engineer-in-Charge is satisfied that the contractor has already made arrangements for rectification, or in the event of contractor's failure to rectify the defects for any reason whatsoever, the defects can be rectified by the company departmentally or by other means and the Retention Money (5% recovered from running bills) i.e. 2nd part of the Security Deposit of the contractor shall be sufficient to cover the cost thereof, he shall issue the Defect Liability Certificate ( Taking Over Certificate with list of defects )indicating the date of completion of the work, defects to be rectified, if any, and the items, if any, for which payment shall be made at reduced rate indicating reasons there for and with necessary instructions to the contractor to clear the site/place of work or all debris/ waste materials, scaffoldings, sheds, surplus materials etc. making it clean.

12.1 In cases where separate period of completion for certain items or groups of items are specified in the contract, separate Defect Liability certificate for such items or groups of items may be issued by the Engineer-in-Charge after completion of such items on receipt of notice from the contractor only in the event the work is completed satisfactorily in every respect. Refund of Security Deposit and payment of Final Bill shall, however, be made on completion of the entire contract work, but not on completion of such items of work. 12.2 Before the date fixed for completion of work, the work as well as the site of work are to be made clean after removal of rubbish, scaffolding, surplus materials, temporary structures etc.

46

CONDITIONS OF CONTRACT

12.3 In case of contractor's failure to clear the site, the EIC shall have right to get the work done. The cost thereof shall be recovered from the final bill of the contractor.

13. Additional Responsibilities of the Contractor(s)

The cost on account of the "Additional Responsibilities of the Contractors" under this clause is deemed to be included in the tendered rates. i) The company reserves the rights to let other contractors also work in connection with the Project and the contractor/contractors shall co-operate in the works for the introduction and stores and materials and execution of his/their works. ii) The contractor/contractors shall keep on the work site during the progress a competent and experienced Resident Engineer exclusively for the work and necessary assistants who shall represent the contractor(s). The contractor shall employ, on the site in connection with the execution and maintenance of the work, technical and managerial staff as mentioned below.

Sl.No. Value of Work Manpower Requirement

1. More than 10 Crores One Resident Engineer (Degree Holder), One Engineer (Degree Holder), Two Engineers (Diploma Holder)

2. 5 Crores to 10 Crores One Resident Engineer (Degree Holder), Two Engineers (Diploma Holder)

3. 2 Crores to 5 Crores One Resident Engineer (Diploma Holder), One Engineer (Diploma Holder)

4. 50 lakhs to 2 crores One Resident Engineer (Graduate/ Diploma Holder) For works below Rs. 50 lakhs, the deployment of manpower shall be as assessed by Engineer.

The contractor shall intimate the Engineer-in-Charge in writing the names, qualifications, experience and full postal address of each and every technical personnel employed at site by him. The contractor(s) shall not be allowed to execute the work unless he/they engage the required technical staff as assessed by Engineer-in-charge or as specifically mentioned in the bid. The delay on this account, if any, shall be the contractor's responsibility. Important instructions shall be confirmed to the contractor(s) in writing. If the contractor/contractors in course of the works finds/find any discrepancy between the drawing, forming part of the contract documents and the physical conditions of the locality or any errors or omissions in drawings except those prepared by himself / themselves and not approved by the Engineer-in-Charge. It shall be his/their duty to immediately inform the Engineer-in-Charge in writing and the Engineer-in-Charge shall verify the same. Any work done after such discovery and without intimation as indicated above will be done at the risk of the contractor/contractors.

iii) The contractor / contractors shall employ only competent, skillful and orderly men to do the work. The Engineer-in-Charge shall have the right to ask the contractor/ contractors to remove from the work site any men of the contractor/contractors who in his opinion is undesirable and the contractor/contractors will have to remove him within 3 (three) hours of such orders. The contractor shall employ apprentices in the execution of the contract work as required under Apprentices Act. The contractor shall further be responsible for making arrangements at his own cost, or accommodation and social needs of the staff and workers under his employment. iv) Precautions shall be exercised at all times by the contractor(s) for the protection of persons (including

47

CONDITIONS OF CONTRACT

employees) and property. The safety required or recommended by all applicable laws, codes, statutes and regulations shall be observed by the contractor(s).In case of accidents, the contractor(s) shall be responsible for compliance with all the requirements imposed by the Workmen's Compensation Act or any other similar laws in force and the contractor shall indemnify the company against any claim on this account. All scaffoldings, ladders and such other structures which the workmen are likely to use shall be examined by the Engineer-in-Charge or his authorized representative whenever they want and the structure must be strong, durable, and safe and of such design as required by Engineer-in-Charge. In no case any structure condemned by the Engineer-in-Charge or his authorized representatives shall be kept on the work and such structure must be pulled down within three hours of such condemnation and any certificate or instructions, however, shall in no way absolve the contractor/contractors from his/their responsibility, as an employer, as the company shall in no way be responsible for any claim. The contractor / contractors shall at all times exercises reasonable precautions for the safety of employees in the performance of his/their contract and shall comply with all applicable provisions of the safety laws drawn up by the State Govt. or Central Govt. or Municipalities and other authorities in India. The contractor/contractors shall comply with the provision of the safety hand book as approved and amended from time to time by the Government of India. v) The contractor / contractors shall familiarize themselves with and be governed by all laws and rules of India and Local statutes and orders and regulations applicable to his/ their work. vi) The contractor shall maintain all records as per the provision made in the various statutes including Contract Labour (Regulation & Abolition) Act, 1970 and the Contract Labour (Regulation & Abolition) Central Rules,1971, Minimum Wages Act, Workmen Compensation Act etc. and latest amendment thereof. Such records maintained by the contractor shall be opened for inspection by the Engineer-in-Charge or by the nominated representative of the Principal Employer.

vii) The contractor/ contractors shall provide facilities for the sanitary necessities of all persons employed on the work shall be constructed and maintained in the number, manner and place approved or ordered by the Engineer-in-Charge. The contractor/ contractors shall vigorously prohibit committing of nuisance at any other place. Cost of all works under this item shall be covered by the contractor/contractor's tendered rates. viii) The contractor/contractors shall furnish to the Engineer-in-Charge or his authorized representative with work reports from time to time regarding the contractor / contractors organization and the progress made by him / them in the execution of the work as per the contract. ix) All duties, taxes [excluding Goods & Services Tax and State Compensation Cess (if applicable) only] and other levies, royalty, building and construction workers cess (as applicable in States), if any applicable, after implementation of GST as per Govt. Notification, whether local, municipal, provincial or central pertaining to the contract payable by the Contractor under the Contract (during the entire period of contract), or for any other cause as applicable on the last date of submission of Bid, shall be included in the rates, prices and the total Bid Price submitted by the Bidder. All investments, operating expenses, incidentals, overheads, lifts, carriages, tools and plants etc. as may be attendant upon execution and completion of works shall also be included in the rates, prices and total Bid price submitted by the bidder.

However, such duties, taxes, levies etc. which is notified after the last date of submission of Bid and/or any increase over the rate existing on the last date of submission of Bid shall be reimbursed by the company on production of documentary evidence in support of payment actually made to the concerned authorities.

Similarly if there is any decrease in such duties, taxes and levies the same shall become recoverable from the contractor.

The rates quoted by bidder shall be inclusive of all Taxes, if any applicable, after implementation of GST

48

CONDITIONS OF CONTRACT

as per Govt. Notification, but excluding Goods & Service Tax (GST) and State Compensation Cess (if applicable).

For GST Registered Bidders, the Payment/ deposit of GST and State Compensation Cess (if applicable) is the responsibility of the Contractor (Supplier). However, in case the contractor is Unregistered under GST as per GST Act & Rules, the GST and State Compensation Cess (if applicable) will be deposited by SECL directly to the concerned authorities under Reverse Charge Mechanism.

Payment of GST and State Compensation Cess (if applicable) would be made to the Contractor only on submission of Bill/Invoice in accordance with the provision of relevant GST Act & Rules and after filing of return online on the GST Portal. Input Tax Credit is to be availed by SECL as per rule. If CIL/Subsidiary fails to claim Input Tax Credit(ITC) on eligible Inputs, input services and Capital Goods or the ITC claimed is disallowed due to failure on the part of supplier/vendor of goods and services in incorporating the tax invoice issued to CIL/Subsidiary in its relevant returns under GST, payment of CGST & SGST or IGST, GST (Compensation to State ) Cess shown in tax invoice to the tax authorities, issue of proper tax invoice or any other reason whatsoever, the applicable taxes &cess paid based on such Tax invoice shall be recovered from the current bills or any other dues of the supplier/vendor along with interest, if any. The rates and prices quoted by the Bidder shall be fixed for the duration of the contract and shall not be subject to variations on any account except to the extent variations allowed as per the conditions of the contract of the bidding document. The company reserves the right to deduct/ withhold any amount towards taxes, levies, etc. and to deal with such amount in terms of the provisions of the Statute or in terms of the direction of any statutory authority and the company shall only provide with certificate towards such deduction and shall not be responsible for any reason whatsoever.

In case of collection of minor minerals in area (both virgin and non-virgin), acquired by the Company under the Coal Act, the contractor will have to produce a royalty clearance certificate from the District Authorities before full and final payment. x) The contractor / contractors shall make his / their own arrangement for all materials, tools, staff and labourer required for the contract, which shall include cost of lead, lift, loading, unloading, railway freight, recruiting expenses and any other charges for the completion of the work to entire satisfaction of the company. xi) The contractor / contractors shall make their own arrangement for carriage of all materials to the work site at his/their own cost. xii) The work shall not be sublet to any other party, unless approved by Engineer-in-Charge, in writing. Prior permission is required to be taken from the owner for engagement of sub-contractor in part work/ piece rated work. xiii) a) No fruit trees or valuable plants or trees with trunk diameter exceeding 150mm shall be pulled, destroyed or damaged by the contractor/contractors or any of his/their employees without the prior permission of the company, failing which the cost of such trees or plants shall be deducted from the contractor/contractors dues at the rate to be decided by the company. The rates quoted are supposed to include clearance of shrubs and jungles and removal of such trees up to 150 mm dia., as will be permitted by the Engineer-in-Charge in writing.

b) Anything of historical or other interest or of significant value unexpectedly discovered on the site is the property of the employer. The Contractor is to notify the Nodal Officer or his nominee of such discoveries and carry out the Nodal Officer or his nominee’s instructions for dealing with him. xiv) The contractor / contractors shall not pay less than the minimum wages to the labourer engaged by him/them as per Minimum Wages Act or such other legislation or award of the minimum wage fixed by the

49

CONDITIONS OF CONTRACT

respective State Govt. or Central Govt. as may be in force or minimum wages recommended by High Power Committee of CIL (for labours engaged in mining activities), as applicable. The contractor / contractors shall make necessary payments of the provident fund for the workmen employed by him for the work as per the laws prevailing under provisions of CMPF and allied scheme and Miscellaneous Provisions Act, 1948. xv) All accounts shall be maintained properly and the company shall have the right of access and inspection of all such books of accounts etc., relating to payment of labourer including payment of provident fund considered necessary and the company may arrange for witnessing the payment to the labourer by its representatives.

xvi) The contractor shall in additions to any indemnity provided by the relevant clauses of the agreement or by law, indemnify and keep indemnified for the following: a) The company or any agent or employee of the company against any action, claim or proceeding relating to infringement or use of any patent or design right and shall pay any royalties or other charges which may be payable in respect of any article or material included in the contract. However, the amount so paid shall be reimbursed by the company in the event such infringement has taken place in complying with the specific directions issued by the company or the use of such article or material was the result of any drawing and/or specifications issued by the company after submission of tender by the contractor. The contractor must notify immediately after any claim being made or any action brought against the company, or any agent or employee of company in respect of any such matter.

b) The company against all claims, damages or compensation under the provisions of payment of Wages Act, 1938, Minimum Wages Act, 1948, Employer's Liability Act, 1938, The Workmen's Compensation Act, 1923, Industrial Dispute Act, 1947, Mines Act as applicable, Employees State Insurance Act 1948 and Maternity Benefit Act, 1961, Acts regulating P.F. or any modification thereof or any other law relating thereto and rules made there under from time to time, as may be applicable to the contract which may arise out of or in consequence of the construction or maintenance or performance of the work under the contract and also against costs, charges and expenses of any suit, action or proceedings arising out of any accident or injury.

c) The company against all losses and claims for injuries or damages to any third party or to any property belonging to any third party which may arise out of or in consequence of the construction or maintenance or performance of the work under the contract and against all claims/demands proceedings/damages, cost charges and expenses whatsoever in respect of or in relation thereto.

xvii)The contractor is under obligation to hand over to the company the vacant possession of the completed building structures failing which the Engineer-in-Charge can impose a levy upon the contractor upto 5% of the total contract value for the delay in handing over the vacant possession of the completed works after giving a 15 (fifteen) days notice to the contractor.

xviii) (A) Insurance - The contractor shall take full responsibility to take all precautions to prevent loss or damage to the works or part thereof for any reasons whatsoever (except for reasons which are beyond control of the contractor or act of God, e.g. flood, riots, war, earthquake, etc.) and shall at his own cost repair and make good the loss/damage to the work so that on completion, the work shall be in good order and condition and in conformity with the requirements of the contract and instructions of the Engineer-in-charge.

The contractor/contractors shall take following insurance policies during the full contract period at his own cost:

a). In the case of construction works, without limiting the obligations and responsibilities under the contract, the contractor shall take insurance policy for the works and for all materials at site so that the value of the works executed and the materials at site up to date are sufficiently covered against risk of loss/damage to the extent as permissible under the law of insurance. The contractor shall arrange insurance in joint names of the company and the contractor. All premiums and other insurance charges of the said insurance policy shall be borne by the contractor.

The terms of the insurance policy shall be such that all insurance claims and compensations payable by the insurers, shall be paid to the Employer and the same shall be released to the contractor in installments as may be certified by the Engineer-in-charge for the purpose of rebuilding or replacement or repair of the works and/or

50

CONDITIONS OF CONTRACT

goods destroyed or damaged for which payment was received from the insurers. Policies and certificates for insurance shall be delivered by the contractor to the EIC for his approval before the starting date. Alterations to the terms of insurance shall not be made without the approval of EIC.

b). Where any company building or part thereof is used, rented or leased by the contractor for the purpose of storing or using materials of combustible nature, the contractor shall take separate insurance policy for the entire building and the policy shall be deposited with the company.

c) The contractor shall at all times during the tenure of the contract indemnify the company against all claims, damages or compensation under the provision of the Workmen's Compensation Act and shall take insurance policy covering all risk, claims, damages, or compensation payable under the Workmen's Compensation Act or under any other law relating thereto. d) The contractor shall ensure that the insurance policy/ policies is/are kept alive till full expiry of the contract by timely payment of premiums and it/they shall not be cancelled without the approval of the company and a provision is made to this effect in all policies, and similar insurance policies are also taken by his sub-contractors if any. The cost of premium shall be borne by the contractor and it shall be deemed to have been included in the tendered rate. e) In the event of contractor’s failure to effect or to keep in force the insurance referred to above or any other insurance which the contractor is required to effect under the terms of the contract, the company may effect and keep in force any such insurance and pay such premium/premiums as may be necessary for that purpose from time to time and recover the amount thus paid from any moneys due to the contractor.

THE CLAUSE 13(xviii) (A) SHALL BE APPLICABLE FOR WORKS OF ESTIMATED VALUE OF OVER Rs. 50 LAKHS. xviii) (B) Group Personal Accident Insurance –

The contractor shall directly pay the ex-gratia amount of Rs. 5.00 (Five ) lakhs to the same dependent family members of the deceased contractor’s worker ,who died in mine accident as certified by DGMS , to whome the statutory benefits under Employee Compensation Act , Provident Fund etc. have been paid , as per terms of contract or through Insurance Company by availing Group Personal Accident Insurance Policy for all its workers before commencement of the contract , which shall be renewed periodically to cover the entire duration of the contract. No reimbursement shall be made on this account by CIL/SECL. In order to comply with the above provision, contractor shall immediately on receipt of letter of

acceptance / work order shall obtain group personal accident insurance in respect of all the workmen

eggaged in mining activities for payment of Rs. 5.00 (Five ) lakhs in case of death in mine accident . A proof to such effect shall be produced to the satisfaction of the management before commencement of the work . However, the responsibility of payment of special relief / ex-gratia amount shall lie exclusively with the Contractor. If the contractor fails to disburse the special Relief /Ex-gratia within the due date, the subsidiary concerned may make payment to the eligible dependent as mentioned herein above. However, such amount shall be recovered from the Contractor from his dues eighter in the same and/ or other subsidiary of CIL.”

AS per Letter No. GM( c ) / SECL/BSP/2018-19/H/334 DT. 26.10.2018 ISSUED BY GM ( C ),SECL,BILASPUR)

xix) Setting Out: The contractor shall be responsible for the contract and proper setting out of the works and correctness of the position, reduced levels, dimensions and alignment of all parts of the work including marking out the correct lay out in reference to the permanent bench mark and reference points. Only one permanent bench mark and basic reference lines shall be marked and shown to the contractor as basic data.

51

CONDITIONS OF CONTRACT

The contractor shall have all necessary instruments, appliances and labour in connection therewith. If at any time during the progress of work any error is detected in respect of the position, levels, dimensions or alignment of any part of the work, the contractor on being required to do so by the Engineer-in-Charge or his representative shall at the expenses of the contractor rectify such errors to the satisfaction of Engineer-in-Charge unless such error is due to incorrect data supplied by the Engineer-in-Charge. xx) On receipt of Letter of Acceptance of Tender / Work Order the contractor shall forthwith Register and obtain License from the competent authority under the Contract Labour (Regulation & Abolition)Act 1970,the Contract Labour (Regulation & Abolition) Central Rules, 1971 and submit certified copies of the same to the Engineer-in-Charge and the Principal Employer. xxi) The contractor shall be registered under Goods and Services Tax (GST) and the GST Registration certificate with GSTIN (Form GST REG-25), as per GST Act & Rules should be submitted to the Engineer-in-Charge. xxii) The contractor shall, in connection with works, provide and maintain, at his own cost, all lights, security guards, fencing when and where necessary as required by the Engineer-in-Charge for the purpose of protection of the works, materials at site, safety of workmen and convenience of the public. xxiii) All materials (e.g. stone, moorum and other materials) obtained in the course of execution of the work during excavation and dismantling etc. shall be the property of the company and the same may be issued to the contractors, if required for use in the works at the rates to be fixed by the Engineer-in-Charge. xxiv) Unless otherwise specifically provided for, dewatering of excavation pits, working areas etc. shall be the contractor's responsibility and is to be carried out at his own cost as per instructions of EIC. The rates quoted by the contractor shall be deemed to include the dewatering costs.

xxv) Approval by the Nodal Officer/Engineer-in-Charge or his nominee: The contractor shall submit specifications and drawings showing the proposed temporary work to the Nodal Officer/Engineer-in-Charge or his nominee, who is to approve them if they comply with the specifications and drawings. The contractor shall be responsible for design of Temporary Works. The Nodal Officer/Engineer-in-charge or his nominee’s approval shall not alter the contractor’s responsibility for design of the Temporary Works.

14. Defects Liability Period:

In addition to the defect/s to be rectified by the contractor as per terms of the contract/ work order, the contractor shall be responsible to make good and remedy at his own expense the defect/s mentioned hereunder within such period as may be stipulated by the Engineer-in-Charge in writing:

a) Any defect/defects in the work detected by the Engineer-in-Charge within a period of 6 (six) months from the date of issue of Defect Liability certificate / completion certificate.

b) In the case of building works or other works of similar nature any defect in the work detected by the Engineer-in-Charge within a period of 6 (six) months from the date of issue of Defect Liability certificate/ completion certificate or before the expiry of one full monsoon period i.e. June to September whichever is later in point of time.

14.1 A programme shall be drawn by the contractor and the Engineer-in-Charge for carrying out the defects by the contractor detected within the defect liability period and if the contractor fails to adhere to this programme, the Engineer-in-Charge shall be at liberty to procure proper materials and carry out the rectifications in any manner considered advisable under the circumstances and the cost of such procurement of materials and rectification work shall be chargeable to the contractor and recoverable from any of the pending dues of the contractors.

52

CONDITIONS OF CONTRACT

The defect liability period can be extended by the company on getting request from the contractor only for valid reasons.

There will be no defect liability period for works like Grass Cutting, Jungle Cutting, Surface Dressing & any other work of similar nature to be decided by the Engineer-in-Charge.

15. Operating and Maintenance Manual:

If “as built” drawings and/or Operating and Maintenance Manual are required the contractor shall supply them by the dates as per instruction of the Engineer-in-charge.

If the contractor does not supply the drawings and/or Manual by the dates as stated above, or they do not receive the Nodal Officer or his nominee’s approval, the Nodal Officer or his nominee shall withhold the amount as stated in the agreement.

16. Settlement of Disputes.

It is incumbent upon the contractor to avoid litigation and disputes during the course of execution. However, if such disputes take place between the contractor and the department, effort shall be made first to settle the disputes at the company level. The contractor should make request in writing to the Engineer-in-charge for settlement of such disputes/ claims within 30 (thirty) days of arising of the cause of dispute/ claim failing which no disputes/ claims of the contractor shall be entertained by the company. Effort shall be made to resolve the dispute in two stages In first stage dispute shall be referred to Area GM or GM/HoD(C). If difference still persist the dispute shall be referred to a committee constituted by the owner. The committee shall have one member of the rank of Director of the company who shall be chairman of the committee. If differences still persist, the settlement of the dispute shall be resolved in the following manner: Disputes relating to the commercial contracts with Central Public Sector Enterprises / Govt. Departments (except Railways, Income Tax, Customs & Excise)/ State Public Sector Enterprises shall be referred by either party for Arbitration to the PMA (Permanent Machinery of Arbitration) in the department of Public Enterprises.

In case of parties other than Govt. Agencies, the redressal of the dispute may be sought through Arbitration (THE ARBITRATION AND CONCILIATION ACT, 1996 as amended by AMENDMENT ACT of 2015).

16A. Settlement of Disputes through Arbitration If the parties fail to resolve the disputes/differences by in house mechanism, then, depending on the position of the case, either the employer/owner or the contractor shall give notice to other party to refer the matter to arbitration instead of directly approaching Court. The contractor shall, however, be entitled to invoke arbitration clause only after exhausting the remedy available under the clause 16. In case of parties other than Govt. agencies, the redressal of disputes/differences shall be sought through Sole Arbitration as under.

Sole Arbitration:

In the event of any question, dispute or difference arising under these terms & conditions or any condition contained in this contract or interpretation of the terms of, or in connection with this Contract (except as to any matter the decision of which is specially provided for by these conditions), the same shall be referred to the sole arbitration of a person, appointed to be the arbitrator by the Competent Authority of CIL / CMD of Subsidiary Company (as the case may be). The award of the arbitrator shall be

53

CONDITIONS OF CONTRACT

final and binding on the parties of this Contract.

(a) In the event of the Arbitrator dying, neglecting or refusing to act or resigning or being unable to act for any reason, or his/her award being set aside by the court for any reason, it shall be lawful for the Competent Authority of CIL / CMD of Subsidiary Company (as the case may be) to appoint another arbitrator in place of the outgoing arbitrator in the manner aforesaid. (b) It is further a term of this contract that no person other than the person appointed by the Competent Authority of CIL / CMD of Subsidiary Company (as the case may be) as aforesaid should act as arbitrator and that, if for any reason that is not possible, the matter is not to be referred to Arbitration at all. Subject as aforesaid, Arbitration and Conciliation Act, 1996 as amended byAmendment Act of 2015, and the rules thereunder and any statutory modification thereof for the time being in force shall be deemed to apply to the Arbitration proceedings under this clause. The venue of arbitration shall be the place from which the contract is issued or such other place as the Competent Authority of CIL/ CMD of Subsidiary Company (as the case may be) at his discretion may determine. Applicable Law: The contracts shall be interpreted in accordance with the laws of the Union of India.

Contracts with Partnership firm/ Joint Venture/Consortium:

The Partnership firm /Joint Venture/Consortium is required to submit written consent of all the partners to above arbitration clause at the time of submission of bid. 17. E-way Bill : The e-way bill required in connection with supply of goods or services, if any, shall be

arranged by the supplier/vendor. However, the e-way bill will be arranged by CIL/Subsidiary if the

supplier/vendor is unregistered one or if provisions of the relevant Act and the rules made there

under specifically states that the e-way bill is required to be issued by recipient of goods.

18. In the event of recovery of any claim towards LD Charges, Penalty, fee, fine or any other charges

from the supplier/vendor, the same will be recovered along with the applicable GST and the

amount shall be adjusted with the payment to be made to the supplier/vendor against their

bill/invoice or any other dues. Further Earnest Money/Performance Security forfeited will be

inclusive of GST.

**************************************

ADDITIONAL TERMS AND CONDITIONS

The following additional terms and conditions are also acceptable to the Company. The tenderers are requested not to quote any further additional conditions in the tender. 1. Mobilization Advance i). No mobilization advance is payable for works whose estimated value is less than Rs.100.00 lakhs. ii). In the case of Turnkey work whose estimated value is more than Rs.100 lakhs a maximum of 10 % of the

54

CONDITIONS OF CONTRACT

total contract value of work will be paid as mobilization advance subject to submission of Bank Guarantee equal to 110% of the advance amount. The mobilization advance shall be paid in two installments.

iii). In case of other civil works valued more than Rs.100 lakhs mobilization advance will be paid upto 5% of the

contract value subject to submission of Bank Guarantee equal to 110% of the advance amount. The mobilization advance shall be paid in two installments.

iv). Mobilization advance will be given in instalments and subsequent instalments will be released after getting satisfactory Utilization Certificate from the contractor for the earlier instalments.

v). Interest on mobilisation advance will be charged at the rate of CIL’s borrowing rate under cash credit arrangement on the last date of bid submission and to be compounded quarterly.

vi). The mobilisation advance shall be recovered from the bills of the contractor from the second running on

account bill onwards @ 20% of the advance amount paid.

However, the full amount of mobilization advance with interest will be recovered maximum within 12 (twelve) months from the date of commencement of work or one half of the stipulated period of completion of work, whichever is less.

vii). The value of Bank Guarantee may be reduced to the extent such advance is recovered by the Company

subject to the conditions that the value of Bank Guarantee amount at any time is more than the recoverable outstanding advance. Bank Guarantee shall be irrevocable and from a Scheduled Bank acceptable to the Company.

viii). Part ‘Bank Guarantee’ (BGs) against the Mobilisation Advance shall be taken in as many numbers as the

proposed recovery instalments and shall be equivalent to 110% of the amount of each instalment.

ix). In case of “Machinery and Equipment advance”, insurance and hypothecation to the employer shall be ensured.

2. Application of Price Variation Clause. If the prices of materials (not being the materials supplied at fixed issue rates by the company) and wages of labour required for execution of the work increase or decrease, the contractor shall be compensated for such increase or recoveries will be made from the bills for such decrease as per provisions detailed hereafter: a) The amount of the contract shall accordingly be varied subject to the condition that such compensation for escalation/ de-escalation in price shall be available only for the work done during the stipulated period of the contract including such period for which the contract is validly extended under the provisions of the contract without any penal action. The Price Variation Clause shall not be applicable for works of capital nature, for which stipulated period of completion is six months or less. For regular maintenance/Service contract, price variation shall not be applicable where stipulated period of completion is twelve months or less. b) The base date for working out such escalation/de-escalation shall be the last date on which the bids (inclusive of price part) or revised price bids (inclusive of revised offer) were stipulated to be received. c) The compensation for escalation or recoveries to be made shall be worked out at quarterly intervals and shall be with respect to the cost of work done during the previous three months. The first such payment will be made at the end of three months after the month (excluding) in which the tender was accepted and thereafter at three months' interval.

d) Job specific modification in the formulae of price variation given in the following para(s) can be done with the approval of the CMD of the company

55

CONDITIONS OF CONTRACT

2.1 Escalation/ De-escalation for Labour: The amount paid to the contractor for the work done shall be adjusted for increase or decrease in the cost of labour and the cost shall be calculated quarterly in accordance with the following formula :

VL = W�

���×

����

��

Where : VL= Variation in labour cost i.e., increase or decrease in the amount in rupees to be paid or recovered.

W = Value of work done during the period under reckoning to which the escalation/de-escalation relates as indicated in clause-2.4 of the Additional Terms & Conditions of the contract.

A = Component of labour expressed as percentage of the total value of the

work adopted from the Table-1. Lo = Minimum wages for unskilled workers payable as per the Minimum Wages Act / Rules of the

State or Central Govt., whichever is more, applicable to the place of work as on the last date stipulated for receipt of the bids (inclusive of price part) or revised price bids whichever is later.

L = Revised minimum wages of unskilled worker corresponding to Lo during the period to which the

escalation/de-escalation relates.

2.2 Escalation /De-escalation on Materials: The amount to be paid to the contractor for the work done will be adjusted for increase or decrease in the cost of materials and the cost shall be calculated quarterly in accordance with the following formula :

Vm = W×

���×

��

Where :

Vm= Variation in the material cost i.e. increase or decrease in the amount in rupees to be paid or recovered.

W = Cost of work done during the period under reckoning to which the escalation / de-escalation relates

as indicated in clause-2.4 of the Additional Terms & Conditions of the contract. B = Component of material expressed as percentage of the total value of the work adopted from the

Table -1. M = Average All India Wholesale Price Index for all commodities for the period to which escalation/de-

escalation relates as published by the RBI Bulletin, Ministry of Industry & Commerce, Govt. of India.

Mo = All India Wholesale Price Index for all commodities as published by the RBI Bulletin, Ministry of

Industry & Commerce, Govt. of India, relating to the last date on which the bids (inclusive of price part) or revised price bids whichever is later were stipulated to be received.

2.3 Escalation/ De-escalation on POL : The amount to be paid to the contractor for the work done shall be adjusted for the increase or decrease in the cost of POL and the cost shall be calculated quarterly in accordance with the formula given below :

Vf = W�

���×

����

��

56

CONDITIONS OF CONTRACT

Where : Vf = Variation in the cost of fuel, oil and lubricants increase or decrease in the rupees to be paid or

recovered.

W = Value of work done during the period under reckoning to which the escalation/ de-escalation relates as indicated in clause 2.4 of the Additional terms & Conditions of the contract.

C =Component of POL expressed as percentage of the total cost of the work taken from Table -1.

F = Average Index Number for wholesale price for the group of `Fuel, Power, Light & Lubricants' as

published by the Economic Adviser, Ministry of Industry, Govt. of India for the period to which the escalation/de-escalation relates.

Fo = Index number of wholesale price for the group, Fuel, Power, light & lubricants as published by the

Economic Adviser, Ministry of Industry, Govt. of India prevalent on the last date of receipt of bids (inclusive of Price Part) or revised price bids whichever is later.

2.4 While calculating the value of "W" the following may be noted : The cost on which the escalation will be payable shall be reckoned as 85 % of the cost of work as per the bills to which escalation relates, and from this amount the value of materials supplied or services rendered at the prescribed charges under the relevant provisions of the contract, and proposed to be recovered in the particular bill, shall be deducted before the amount of compensation for escalation or de-escalation is worked out. In the case of materials brought to site for which any secured advance is included in the bill, the full value of such materials as assessed by the Engineer-in-Charge (and not the reduced amount for which secured advance has been paid) shall be included in the cost of work done for operation of this clause. Similarly, when such materials are incorporated in the work and the secured advance is deducted from the bill, the full assessed value of the materials originally considered for operation of this clause should be deducted from the cost of the work shown in the bill, running or final. Further the cost of work shall not include any work for which payment is made at prevailing market rates.

2.5 In the event the price of materials and/ or wages of labour required for execution of the work decreases, there shall be downward adjustment of the cost of work so that such price of materials and/or wages of labour shall be deductible from the cost of work under this contract and in this regard the formulae herein before stated under this clause shall mutatis/mutandis apply. No such adjustment for the increase / decrease in material price and/ or wages of labour before mentioned would be made in case of contracts related to capital works, in which the stipulated period of completion of the work is six (6) months or less. However for Maintenance works any adjustment for the increase or decrease in material price or wages of labour would be made only when the stipulated period of completion of the work is more than twelve (12) months.

2.6 Application of Price Variation Clause during extended period of Contracts. The Price Variation Clause as stated above will be applied for extended time frame of a contract by following the principle stated as under:

i) Normally, if and when it is understood that a contract is not going to be completed within the scheduled time period, the contract is kept operative by extending the time of completion provisionally. During this provisional extended period the operation of the Price Variation Clause will remain suspended. ii) If and when it is decided at the end of the successful completion of the work that the delay was due to causes not attributable to the contractor, then the Price Variation Clause will be revived and applied as if the scheduled date of completion has been shifted to the approved extended date. iii) If it is decided at the end of successful completion of the work that the delay was due to the fault of the contractor then the Price Variation Clause will not be revived and no further payment will be made to the contractor on this account. Additionally the Clause related to Compensation for delay will be applied.

57

CONDITIONS OF CONTRACT

No payment will be made by applying “FROZEN INDICES “under any circumstances.

Table – 1

Value of A, B & C in the escalation formula in the additional terms & conditions for Civil Works : Sl Particulars A% (Labour

Component) B% (Material Component)

C% (POL Component)

1 For building works 25 75 Nil

2 For Road works 15 80 05

3 For external sewerage, External water supply and external electrification

10 90 Nil

4 For external water supply, external sanitary and external electrification (through labourrate contract)

75 25 Nil

5 For steel structural works 15 85 Nil

6 For steel structural works with Deptt. free supply of rolled steel sections(through labour rate contract)

75 25 Nil

7 For Coal Handling Plant Civil Works

25 75 Nil

8 For under-ground civil works such as Incline Drivage, Shaft Sinking etc.

35 65 Nil.

9 For only labour oriented works of maintenance nature.

100 Nil Nil

For all other works not listed above, the component of labour, material and POL of the total cost of work shall be as specifically indicated in the tender document.

SAFETY CODE. 1. Suitable scaffolds should be provided for workmen for all works that cannot safely be done from the ground, or

from solid construction except such short period work as can be done safely from ladders. When a ladder is used, an extra mazdoor shall be engaged for holding the ladder and if the ladder is used for carrying materials as well suitable footholds and hand-hold shall be provided on the ladder and the ladder shall be given an inclination not steeper that ¼ to 1 ( ¼ horizontal and 1 vertical).

2. Scaffolding of staging more than 3.6 m (12ft). above the ground or floor, swung or suspended from an overhead

support or erected with stationary support shall have a guard rail properly attached or bolted, braced and

58

otherwise secured at least 90 cm (3ft) high above the floor or platform of such scaffolding or staging and extending along the entire length of the outside and ends thereof with only such opening as may be necessary for the delivery of materials. Such scaffolding or staging shall be so fastened as to prevent it from swaying from the building or structure.

3. Working platforms, gangways and stairways should be so constructed that they should not sag unduly or

unequally, and if the height of the platform or the gangway or the stairway is more than 3.6 m (12ft) above ground level, they should be closely boarded, should have adequate width and should be suitably fastened as described in (2) above.

4. Every opening in the floor of a building or in a working platform shall be provided with suitable means to prevent

the fall of person or materials by providing suitable fencing or railing whose minimum height shall be 90 cm (3ft). 5. Safety means of access shall be provided to all working platforms and other working places. Every ladder shall

be securely fixed. No portable single ladder shall be over 9 m (30ft) in length while the width between side rails in rung ladder shall in no case be less than 20 cm (11 ½”) for ladder upto and including 3 m (10ft) in length. For longer ladders, this width should be increased at least ¼” for additional 30 cm (1ft.) of length. Uniform step spacing of not more than 30 cm shall be kept. Adequate precautions shall be taken to prevent danger from electrical equipment. No materials on any of the sites or work shall be so stacked or placed as to cause danger or inconvenience to any person or the public. The contractor shall provide all necessary fencing and lights to protect the public from accident and shall be bound to bear the expenses of defence of every suit, action or other proceedings at law that may be brought by any person for injury sustained owing to neglect of the above precautions and to pay any damages and cost which may be awarded in any such suit; action or proceedings to any such person or which may, with the consent of the contractor, be paid to compensate any claim by any such person.

6. Excavation and Trenching : All trenches 1.2 m (4ft) or more in depth, shall at all times be supplied with at least

one ladder for each 30 m. (100 ft.) in length or fraction thereof. Ladder shall extend from bottom of the trench to at least 90 cm (3ft) above the surface of the ground. The side of the trenches which are 1.5 m (5ft) or more in depth shall be stepped back to give suitable slope or securely held by timber bracing, so as to avoid the danger of sides collapsing. The excavated materials shall not be placed within 1.5 m (5ft) of the edges of the trench or half of the depth of the trench whichever is more. Cutting shall be done from top to bottom. Under no circumstances, undermining or undercutting shall be done.

7. Demolition : before any demolition work is commenced and also during the progress of the work,

i. All roads and open areas adjacent to the work site shall either be closed or suitably protected.

ii. No electric cable or apparatus which is liable to be a source of danger or a cable or apparatus used by the

operator shall remain electrically charged.

iii. All practical steps shall be taken to prevent danger to persons employed from risk of fire or explosion or flooding. No floor, roof or other part of the building shall be so overloaded with debris or materials as to render it unsafe.

8. All necessary personal safety equipment as considered adequate by the Engineer-in-Charge should be kept available for the use of the person employed on the site and maintained in a condition suitable for immediate use, and the contractor should take adequate steps to ensure proper use of equipment by those concerned:- The following safety equipment shall invariably be provided.

i) Workers employed on mixing asphaltic materials, cement and lime mortars shall be provided with protective footwear and protective goggles.

ii) Those engaged in white washing and mixing or stacking of cement bags or any material which is injurious to the eyes, shall be provided with protective goggles.

iii) Those engaged in welding works shall be provided with welder’s protective eye-shields.

59

iv) Stone breaker shall be provided with protective goggles and protective clothing and seated at sufficiently safe intervals.

v) When workers are employed in sewers and manholes, which are in active use, the contractors shall ensure that the manhole covers are opened and ventilated at least for an hour before the workers are allowed to get into the manholes, and the manholes so opened shall be cordoned off with suitable railing and provided with warming signals or boards to prevent accident to the public. In addition, the contractor shall ensure that the following safety measures are adhered to:-

a) Entry for workers into the line shall not be allowed except under supervision of the Engineering Assistant or any other higher officer.

b) At least 5 to 6 manholes upstream and downstream should be kept open for at least 2 to 3 hours before any man is allowed to enter into the manhole for working inside.

c) Before entry, presence of Toxic gases should be tested by inserting wet lead acetate paper which changes colour in the presence of such gases and gives indication of their presence.

d) Presence of Oxygen should be verified by lowering a detector lamp into the manhole. In case, no Oxygen is found inside the sewer line, workers should be sent only with Oxygen kit.

e) Safety belt with rope should be provided to the workers. While working inside the manholes, such rope should be handled by two men standing outside to enable him to be pulled out during emergency.

f) The area should be barricaded or condoned of by suitable means to avoid mishaps of any kind. Proper warming signs should be displayed for the safety of the public whenever cleaning works are undertaken during night or day.

g) No smoking or open flames shall be allowed near the blocked manhole being cleaned.

h) The malba obtained on account of cleaning of blocked manholes and sewer lines should be immediately removed to avoid accidents on account of slippery nature of the malba.

i) Workers should not be allowed to work inside the manhole continuously. He should be given rest intermittently. The Engineer-in-Charge may decide the time up to which a worker may be allowed to work continuously inside the manhole.

j) Gas masks with Oxygen Cylinder should be kept at site for use in emergency.

k) Air-blowers should be used for flow of fresh air through the manholes. Whenever called for, portable air blowers are recommended for ventilating the manholes. The Motors for these shall be vapour proof and of totally enclosed type. Non sparking gas engines also could be used but they should be placed at least 2 meters away from the opening and on the leeward side protected from wind so that they will not be a source of friction on any inflammable gas that might be present.

l) The workers engaged for cleaning the manholes / sewers should be properly trained before allowing to work in the manhole.

m) The workers shall be provided with Gumboots or non-sparking shoes bump helmets and gloves non sparking tools safety lights and gas masks and portable air blowers ( when necessary). They must be supplied with barrier cream for anointing the limbs before working inside the sewer lines.

n) Workmen descending a manhole shall try each ladder stop or rung carefully before putting his full weight on it to guard against insecure fastening due to corrosion of the rung fixed to manhole well.

o) If a man has received a physical injury, he should be brought out of the sewer immediately and adequate medical aid should be provided to him.

60

p) The extents to which these precautions are to be taken depend on individual situation but the

decision of the Engineer-in-Charge regarding the steps to be taken in this regard in an individual case will be final.

vi) The Contractor shall not employ men and women below the age of 18 years on the work of painting with products containing lead in any form. Wherever men above the age of 18 are employed on the work of lead painting, the following precaution should be taken:-

a) No paint containing lead or lead products shall be used except in the form of paste or readymade paint.

b) Suitable face masks should be supplied for use by the workers when paint is applied in the form of spray or a surface having lead paint is dry rubbed and scrapped.

c) Overalls shall be supplied by the contractors to the workmen and adequate facilities shall be provided to enable the working painters to wash during and on the cessation of work.

d) Measures shall be taken, wherever practicable, to prevent danger arising out of from dust caused by dry rubbing down and scraping.

e) Adequate facilities shall be provided to enable working painters to wash during and on cessation of work.

f) Overall shall be worn by working painters during the whole of working period.

g) Suitable arrangement shall be made to prevent clothing put off during working hours being spoiled by painting materials.

9. When the work is done near any place where there is risk of drowning, all necessary equipments should be

provided and kept ready for use and all necessary steps taken for prompt rescue of any person in danger and adequate provision, should be made for prompt first aid treatment of all injuries likely to be obtained during the course of the work.

10. Use of hoisting machines and tackle including their attachments, anchorage and supports shall conform to

the following standards or conditions:-

i) (a) These shall be of good mechanical construction, sound materials and adequate strength and free from patent defects and shall be kept repaired and in good working order. (b) Every rope used in hoisting or lowering materials or as a means of suspension shall be of durable quality and adequate strength, and free from patent defects.

ii) Every crane driver or hoisting appliance operator, shall be properly qualified and no person under the age of 21 years should be in charge of any hoisting machine including any scaffolding winch or give signals to operator.

iii) In case of every hoisting machine and of every chain ring hook, shackle swivel and pulley block used in hoisting or as means of suspension, the safe working load shall be ascertained by adequate means. Every hoisting machine and all gear referred to above shall be plainly marked with the safe working load. In case of a hoisting machine having a variable safe working load each safe working load and the condition under which it is applicable shall be clearly indicated. No part of any machine or any gear referred to above in this paragraph shall be loaded beyond the safe working load except for the purpose of testing.

61

iv) In case of departmental machines, the safe working load shall be notified by the Electrical Engineer-in-Charge. As regards contractor’s machines the contractors shall notify the safe working load of the machine to the Engineer-in-Charge whenever he brings any mach8inery to site of work and get it verified by the Electrical Engineer concerned.

12. Motors, gearing, transmission, electric wiring and other dangerous parts of hoisting appliances should be

provided with efficient safeguards. Hoisting appliances should be provided with such means as will reduce to the minimum the risk of accidental descent of the load. Adequate precautions should be taken to reduce to the minimum the risk of any part of a suspended load becoming accidentally displaced. When workers are employed on electrical installations which are already energized, insulating mats, wearing apparel, such as gloves, sleeves and boots as may be necessary should be provided. The worker should not wear any rings, watches and carry keys or other materials which are good conductors of electricity.

13. All scaffolds, ladders and other safety devices mentioned or described herein shall be maintained in safe

condition and no scaffold, ladder or equipment shall be altered or removed while it is in use. Adequate washing facilities should be provided at or near places of work.

14. These safety provisions should be brought to the notice of all concerned by display on a notice board at a

prominent place at work spot. The person responsible for compliance of the safety code shall be named therein by the contractor.

15. To ensure effective enforcement of the rules and regulations relating to safety precautions the arrangements

made by the contractor shall be open to inspection by the Labour Officer or Engineer-in-Charge of the department or their representatives.

16. Notwithstanding the above clauses from (1) to (15), there is nothing in these to exempt the contractor from the

operations of any other Act or Rule in force in the Republic of India.

TECHNICAL SPECIFICATIONS

Technical Specifications to be followed Civil Engineering Works

Latest CPWD specification shall be adopted. Presently CPWD specifications 2009 Vol. I & II is in vogue which may be followed. These specifications cover all type of Building Works. The specifications are available as a printed document issued by CPWD and also in soft copy in .pdf format on CPWD website. Electrical Engineering Works

62

Latest CPWD specification shall be adopted. Presently the following are in vogue:

Part No. Description Year of Issue

I Internal 2013

III Lifts And Escalators 2003

V Wet Riser And Sprinklers System 2006

VI Heating, Ventilation And Air Conditioning Works

2005

Roads and Bridges

Standard Specifications issued by Ministry of Road Transport & Highway may be followed. Presently MORT&H Specifications on roads and bridges 2013 is available. These specifications cover exhaustively various roads and bridge works.

eTender Portal User Agreement

In order to create a user account and use the eTender portal you must read and accept this eTender portal User Agreement. A. UNDERTAKINGS TO BE FURNISHED ONLINE BY THE BIDDER I DO HEREBY UNDERTAKE 1. That all the information being submitted by me/us is genuine, authentic, true and valid on the date of

63

submission of tender and if any information is found to be false at any stage of tendering or contract period, I/We will be liable to the following penal actions apart from other penal actions prescribed elsewhere in the tender document.

a. Cancellation of my/our bid/contract (as the case may be) b. Forfeiture of EMD c. Punitive action as per tender document

2. That I/we accept all terms and condition of NIT, including General Terms and Condition and Special/Additional Terms and Condition as stated there in the tender document as available on the website.

3. That I/we accept the Integrity Pact as given in the tender document (if applicable).

4. That I/we, am/are giving my/our consent for e-payment and submitting/ shall submit the mandate

form for e-Payment in the format as prescribed in the document in case, the work is awarded to us. 5. That I/we do authorize CIL/Subsidiary for seeking information/clarification from my Bankers having

reference in this bid. 6. That I/we will upload original/certified photo/scanned of all the relevant documents as prescribed in

the tender document in support of the information and data furnished by me/us online. 7. I/We confirm that I/We have not been banned or de-listed by any Govt. or Quasi Govt. agencies or

PSUs. In case We are banned or delisted this information shall be specifically informed to the tender issuing authority.

8. That I/We accept all the undertakings as specified elsewhere in the tender document.

9. That this online agreement will be a part of my bid and if the work is awarded to me/us, this will be a

part of our agreement with CIL/Subsidiary Company.

B. TERMS AND CONDITIONS OF E-TENDER SERVICES AGREEMENT COPYRIGHT NOTICE : Copyright̩̉2013, Coal India Limited, India. All rights reserved. YOU MAY NOT MODIFY, COPY, REPRODUCE,REPUBLISH, UPLOAD, POST, TRANSMIT, OR DISTRIBUTE, IN ANY MANNER, THE MATERIALON THE SITE, INCLUDING TEXT, GRAPHICS, CODE AND/OR SOFTWARE. You may print and download portions of material from the different areas of the website solely for your own non-commercial use provided that you agree that you shall not change or delete any copyright or proprietary materials from the site.

https://coalindiatenders.nic.in is an e-procurement portal of Coal India Limited/its Subsidiary. THIS E-TENDER PORTAL AND RELATED SERVICES SUBJECT TO YOUR COMPLIANCE WITH THE USER'S

TERMS AND CONDITIONS SET FORTH BELOW :

PLEASE READ THE FOLLOWING INFORMATION CAREFULLY. YOU MAY NOT COMPLETE YOURREGISTRATION AND USE THE E-TENDER PORTAL WITHOUT AGREEING TO COMPLY WITH ALL OFTHE TERMS AND CONDITIONS SET FORTH BELOW.

BY REGISTERING THE USER NAME AND PASSWORD, YOU AGREE TO ABIDE BY ALL THE TERMSAND CONDITIONS SET FORTH BELOW :

64

Bidder Registration, Password and Security :

Upon successful completion of Registration online, User ID and Password will be registered. You can login, only by giving valid User ID and Password and then signing with your valid Digital Signature Certificate.

The Online registration/enrollment of bidder on the portal should be done in the name of the bidder. The person whose DSC is attached to the Registered Bidder should be either the bidder himself Or, duly authorized by the Bidder.

User ID and password are strictly personal to each Authorised User and non-transferable. The User shall ensure that its Authorised Users do not divulge or disclose their user ID or password to third parties. In the event that the Authorised User comes to know that the User ID/Password has been/ might have been divulged, disclosed or discovered by any third party, user or its authorized user shall immediately modify the password using "Change Password" option. CIL/subsidiary will have no responsibility or obligation in this regard.

At the time of enrollment in the e-Tendering portal of CIL/its Subsidiaries, the Bidders should ensure that the status of DSC is active on this site. The activation of newly issued DSC may take 24 hrs or more. Hence Bidders who are obtaining new DSC should register at least 24 hrs before the submission of Bid.

By registering in this portal you forthwith assume the responsibility for maintaining the confidentiality of the Password and account, and for all activities that occur under your Password or Account. You also agree to (a).immediately notify by e-mail to Application Administrator/Nodal officer, of any unauthorized use of your Password or Account or any other breach of security, and (b) ensure that you log-out from your account at the end of each session. CIL/its Subsidiaries shall not be liable for any loss or damage caused to you due to your failure to comply with the foregoing.

Registered user can modify or update some of the information in their profile as and when required at their own discretion. However some information such as "User ID" are protected against changes by Bidder after enrollment and some other information such as "Bidder Name" etc. are protected against changes by Bidder after bid submission.

Modification of software :

With consent of Project Advisory Committee, e-procurement of CIL, the Administrator of e-Tender portal, reserves the right to modify, add, delete and/or change the contents , classification and presentation of the information on the market place at any time as it may in its absolute discretion find to be expedient and without giving any notice. It is the users responsibility to refer to the terms and/or any change or addition to the same while accessing the site.

Coal India Limited reserves right to interrupt/suspend the availability of the e-Tender system without any notice to the users.

System Requirements :

It is the users responsibility to comply with the system requirements : hardware, software, Internet connectivity at user premises to access the eTender portal as mentioned in the home page in the link "Resources Required". Under any circumstances, CIL shall not be liable to the Users for any direct/indirect loss incurred by them or damages caused to them arising out of the following:

(a). Incorrect use of the e-Tender System, or ;

(b). Internet Connectivity failures in respect of the equipments used by the Users or by the Internet

65

Service Providers, or ;

(c). Inability of the Bidder to submit their bid due to any DSC related problems, hardware, software or any other factor which are personal/ special/local to the Bidder.

Contents of Tender Information :

Tenders shall be published by the authorized Tender Inviting Authorities of the respective Tendering entities of CIL/subsidiary. In case of any clarifications arising out of the tenders, the users have to contact the respective Tender Inviting Authority.

Bid Submission Acknowledgement :

The User should complete all the processes and steps required for Bid submission. The successful Bid submission can be ascertained once acknowledgement is given by the system through Bid Submission number i.e. Bid ID, after completion of all the processes and steps. Coal India Limited is not responsible for incomplete bid submission by users. Users may also note that the incomplete bids will not be saved by the system and so the same will not be available to the Tender Inviting Authority for processing. The acknowledgment is the only confirmation of submission of bid, which the bidder can show as a proof of participating in the tender. Other than this acknowledgement, no proof will be considered as a confirmation to the submission of a bid. If the bidder fails to produce this acknowledgement required for verification in case of dispute, his claim for submission of bid may not be considered.

Upload files :

The bidders have to ensure that the files being uploaded by them are free from all kinds of viruses and contain only the relevant information as stated by the Tender Inviting Authorities for the particular tender. It is not obligatory on the part of CIL/subsidiary to read each and every document uploaded by the Bidder. If any bidder/Company has uploaded/attached irrelevant data, bogus or fabricated certificates towards his qualification requirements to the respective tender then their User account will be liable for termination permanently or temporarily by CIL/subsidiary without any prior notice.

User Conduct :

You agree that all information, data, text, software, photographs, graphics, messages or other materials ("Content"), whether publicly posted or privately transmitted, are the sole responsibility of the person from which such Content is originated. This means that you are entirely responsible for all Content that you upload, post, email or otherwise transmit via the eTender portal.

CIL/subsidiary does not control the Content posted via the e-Tender portal and, as such, does not guarantee the accuracy, integrity or quality of such Content. Hence under no circumstances, CIL/subsidiary is liable in any manner for any Content, including, but not limited to, for any errors or omissions in any Content, or for any loss or damage of any kind incurred as a result of the use of any Content posted, e-mailed or otherwise transmitted via the Site.

Amendments to a tender published :

You agree that the CIL/ Subsidiary companies reserves the right to re-tender /cancel a tender or extend the closing date or amend the details of tender at any time by publishing corrigendum as applicable.

Special Admonitions For International Use :

Recognizing the global nature of the Internet, you agree to comply with all local rules regarding online content and acceptable Content. Specifically, you agree to comply with all applicable laws regarding the transmission of technical data to and from India or the country in which you reside.

Links :

66

The Site may provide, links to other World Wide Web sites or resources. Because CIL/subsidiary has no control over such sites and resources, you acknowledge and agree that the CIL/Subsidiary is not responsible for the availability of such external sites or resources, and does not endorse and is not responsible or liable for any Content, advertising, products, or other materials on or available from such sites or resources. You further acknowledge and agree that the CIL/subsidiary shall not be responsible or liable, directly or indirectly, for any damage or loss caused or alleged to be caused by or in connection with use of or reliance on any such Content, Goods or Services available on or through any such site or resources.

Miscellaneous :

This Agreement shall all be governed and construed in accordance with the laws of India & applicable to agreements made and to be performed in India. The e-Tender portal's failure to insist upon or enforce strict performance of any provision of this Agreement shall not be construed as a waiver of any provision or right. Neither the course of conduct between the parties nor trade practice shall act to modify any provision of this Agreement. CIL/subsidiary may assign its rights and duties under this Agreement to any party at any time without notice to you. Any rights not expressly granted herein are reserved.

Governing Law :

Terms shall be governed by, and construed in accordance with, Indian law. The parties agree that the principal civil court of the place where the registered office of Coal India/Subsidiary Company is situated shall have non-exclusive jurisdiction to entertain any dispute with Coal India/Subsidiary company. In case of dispute being with a regional Institute of CMPDIL, the principal Civil Court where the said regional Institute is situated shall be place of suing. CIL/subsidiary reserves the right to initiate any legal action against those bidders violating all or any of the above mentioned terms & conditions of e-Tender services agreement.

Modification of terms of Agreement :

CIL/its Subsidiaries reserves the right to add to or change/modify the terms of this Agreement. Changes could be made by us after the first posting to the Site and you will be deemed to have accepted any change if you continue to access the Site after that time. CIL/its Subsidiaries reserves the right to modify, suspend/cancel, or discontinue any or all services/ make modifications and alterations in any or all of the content, at any time without prior notice.

Policy and Security :

General Policy :

CIL/its Subsidiaries is committed to protecting the privacy of our e-Tender site visitors. CIL/subsidiary does not collect any personal or business information unless you provide it to us voluntarily when conducting an online enrolment, bid submission etc. or any other transaction on the Site.

Information Collected :

When you choose to provide personal or business information to us to conduct an online transaction, we use it only for the purpose of conducting the specific online transaction that you requested. The

67

information is also used for the purpose of vendor searches. For each online transaction, we require only a minimum amount of personal and business information required to process your transaction. When you visit our portal to browse, read pages, or download information, we automatically collect and store only the following information:

The Internet domain and IP address from which you access our portal;

The date and time you access our portal;

The pages you visit This information would help us to make our site more useful to visitors and to learn about the number of visitors to our site and the types of technology our visitors use. We do not give, share, sell or transfer any personal information to a third party unless required to do so by law. If you do not want any personal or business information to be collected, please do not submit it to us ; however, without this required information we will be unable to process your online bid submission or any other online transaction. Review, update and correction of any personal or business information can be done directly on the Site.

Use of Cookies :

When you choose to enter into an online transaction, we use cookies to save the information that you input while progressing through the transaction. A cookie is a very small amount of data that is sent from our server to your computers hard drive. By enabling this feature, the cookie will remember the data entered by you and next time when you visit this site, the data stored in the cookie will be available in future.

Security :

The Site has security measures in place to protect against the loss, misuse and alteration of information under our control.

eMail / SMS Notifications :

The GePNIC eProcurement Server has functionality of automatically sending eMail / SMS alerts at various events as per the bidders preference. There is no manual intervention while sending these pre-defined eMail / SMS alerts. All events for which eMails / SMS being sent is also available to users on the Dash Board / the user login of the Bidder. Although all efforts will be made to ensure timely delivery of eMail / SMS, due to dependency in various other external factors, the delivery of eMail / SMS may not be assured and bidders are requested to check the portal on a periodic basis for any such events. Non receipt of eMail / SMS cannot be quoted as a reason for failure of service as this is an added facility being provided to users.

Annexure-I

FORMAT FOR LETTER OF BID

(To be uploaded by the Bidder on his Letter Head during submission of bid online)

To : The General Manager (Civil)/HoD South Eastern Coalfields Limited Bilaspur (C.G.), PIN-495006

68

Sub : BID for the Work _________________________________

NIT No. : …………………………………………………….dated………………...

Tender Id No : …………………………………………………………………………. Dear Sir, This has reference to above referred bid. I/we have read and examined the conditions of contract, Scope of Work, technical specifications, BOQ and other documents carefully. I /We am/are pleased to submit our bid for the above work. I/We hereby unconditionally accept the bid conditions and bid documents in its entirety for the above work and agree to abide by and fulfill all terms and conditions and specifications as contained in the bid document. I/we here by submit all the documents as required to meet the eligibility criteria as per provision of the bid notice/document. I/We hereby confirm that this bid complies with the Bid validity, Bid security and other documents as required by the Bidding documents.

If any information furnished by me/us towards eligibility criteria of this bid is found to be incorrect at any time, penal action as deemed fit may be taken against me/us for which I/We shall have no claim against CIL/Subsidiary.

Until a formal agreement is prepared and executed, this bid and your subsequent Letter of Acceptance/Work Order shall constitute a binding contract between us and South Eastern Coalfields Limited (SECL).

Should this bid be accepted, we agree to furnish Performance Security within 28 days of issue of letter of acceptance and commence the work within 10 days of issue of letter of acceptance. In case of our failure to abide by the said provision, South Eastern Coalfields Limited shall, without prejudice to any other right or remedy, be at liberty to cancel the letter of acceptance/ award and to forfeit the Earnest Money and also debar us from participating in future tenders for a minimum period 12 months.

Yours faithfully,

Signature of Bidder

(In case of JV, signature of all partners)

Annexure-II

PROFORMA FOR UNDERTAKING

(To be uploaded by the Bidder on his Letter Head during submission of bid online)

I / We, ..................................................................................., Proprietor/Partner/Legal Attorney/Director/ Accredited Representative of M/S. .................................., solemnly declare that:

69

1. I/We am/are submitting Bid for the work……......................................................against Bid Notice No. ......................... Dated………………… and I/we offer to execute the work in accordance with all the terms, conditions and provisions of the bid.

2. Myself/Our Partners/Directors don’t has/have any relative as employee of South Eastern Coalfields

Limited.

* (If so, furnish the name, designation & place of posting of employee of SECL and name of the

bidder/partners/directors, who are relative of the employee of SECL)

3. All information furnished by us in respect of fulfillment of eligibility criteria and qualification information of this Bid is complete, correct and true.

4. All copy of documents, credentials and documents submitted along with this Bid are genuine, authentic, true and valid.

5. I/ We hereby authorize department to seek references / clarifications from our Bankers.

6. I/We will submit GST Registration Certificate with GSTIN (Form GST REG-25), whenever I/We are

liable for GST Registration as per GST Act & Rules.

(applicable for GST Unregistered bidders)

7. We hereby undertake that we shall register and obtain license from the competent authority under the contract labour (Regulation & Abolition Act) as relevant, if applicable.

8. *I/We hereby confirm that we have registration with CMPF Authorities. We shall make necessary payments as required under law.

OR *I/We hereby undertake that we shall take appropriate steps for registration as relevant under

CMPF authorities, if applicable. We shall make necessary payments as required under law.

* Delete whichever is not applicable.

9. ** I/We have not been banned or delisted by any Govt., or Quasi Govt. Agencies or PSUs.

(In case of JV, all partners are covered) OR

**I / We ………………..have been banned by the organization named “_____________” for a period of………………… year/s, effective from ………………. to……………………..…..

[ in case of JV, name(s) of the JV Partner(s) ]

** Delete whichever is not applicable.

10. If any information and document submitted is found to be false/ incorrect at any time, department may cancel my/our Bid and action as deemed fit may be taken against me/us, including termination of the contract, forfeiture of all dues including Earnest Money and banning/ delisting of our firm and all partners of the firm etc.

11. (a). I/We are not engaging and will not engage any child labour in any of the activities for which

I/We are participating in the tender.

(b). If it is reported and proved that child labour is engaged by me/us, then I/We will be penalized 10% of the contract value and will be blacklisted.

70

Signature of the Bidder

(In case of JV signature of all partners of JV) Dated..........................

Annexure-III

MANDATE FORM FOR ELECTRONIC FUND TRANSFER / INTERNET BANKING PAYMENT.

1. Name of the Bidder :………………………………………………………………… 2. Address of the Bidder : …………………………………………………………………. ………………………………………………………………….

71

City………………………. Pin Code…………………………. E-mail Id ……………………………………………………… Permanent Account Number ………………………………….. 3. Particulars of Bank:

Bank Name Branch Name

Branch Place Branch City

Pin Code Branch Code

MICR No.

( Digital Code number appearing on the MICR Band of the cheque supplied by the Bank. Please attach Xerox copy of a cheque of your Bank for ensuring accuracy of the Bank Name, Branch Name and Code Number.

RTGS CODE

Account Type Savings Current Cash Credit

Account Number(as appearing in the Cheque Book.

4. Date from which the mandate should be effective. I hereby declare that the particulars given above are correct and complete. If any transaction is delayed or not effected for reasons of incomplete or incorrect information. I shall not hold Company responsible. I also undertake to advise any change in the particulars of my account to facilitate updation of records for purpose of credit of amount through SBI Net / RTGS transfer/NEFT. I agree to discharge responsibility expected of me as a participant under the scheme. Any bank charges levied by the bank for such e-transfer shall be borne by us. Place : Date : Signature of the Party / Authorised Signatory ------------------------------------------------------------------------------------------------------------------------ Certified that particulars furnished above are correct as per our records. Banker’s Stamp Date :

Signature of the Authorised official from the Bank)

Annexure-IV

PROFORMA FOR EXECUTION OF AGREEMENT.

STAMP PAPER

(of appropriate value as per Stamp Act)

This agreement is made on ………………. day of …………….. between ( Name of Company ) having its registered office at ……………………………………………… (hereinafter called the ‘COMPANY’ which expression shall,

72

unless repugnant to the subject or context, include its successors and assignees) of the one part and ( Name of the Contractor ) carrying on business as a ( partnership/ proprietorship/ Ltd. Co. etc. ) firm under the name and style ………………………………………………… (hereinafter called the ‘said Contractor’ which expression shall, unless the context requires otherwise include them and their respective heirs, executors, administrators and legal representatives) of the other part.

Whereas the Company invited tenders for the work of “……………………………………… ……………………..” and

whereas the said Contractor/ Firm submitted tender for the said work and deposited a sum of Rs………………….. as Earnest Money and whereas the tender of the said contract has been accepted by the Company for execution of the said work.

NOW THIS AGREEMENT WITNESSETH AS FOLLOWS:

1) In this agreement words and expressions shall have the same meaning as are respectively assigned to them in the tender papers hereinafter referred to.

2) The following documents which are annexed to this agreement should be deemed to form and be read and construed as part of this agreement viz.

i) Annexure-A Tender Notice (Page .. to ..) ii) Schedule –A General Terms & Conditions, Special Conditions,

General Technical Specification and Safety Code (Page ……. to ………) iii) Schedule-B The probable Quantities and Amount (Page …….. to ……..…)

iv) Schedule-C Negotiation letters (Page …….. to ……..…)

iv) Schedule-D Letter of Acceptance/Work Order (Page ……... to ………...)

v) Schedule-E Drawings (Page …….. to ………...)

3) In consideration for the payment of the sum of Rs……………( W/O Value; both in words and figures ) or such other sum as may be arrived at under the clause of the specification relating to Payment by items measurements at unit prices by the Company, the said Contractor shall, subject to the terms & condition contained herein execute and complete the work as described and to the extent of probable quantities as indicated in Schedule B with such variations by way of alteration, addition to or reduction from the said works. 4) The company has received a sum of Rs............ towards Performance Security Deposit (1st part of Security Deposit) in the form of Demand Draft / Certified Cheque/ B.G./ other form (details to be furnished) . 5) The said contractor hereby covenants with the company that the company shall deduct at 5% of R/A Bills as Retention Money (2nd part of Security Deposit ) to make the total Security as 11.25% (Eleven point two five

percent) of contract value, as per the terms & condition of the tender/ contract. IN WITNESS WHEREOF THE parties herein have set their hands and seals the date and year above written.

1 Partner. Signature 2 Partner Signature On behalf of M/S………………………………..

73

The Contractor, as one of the constituted attorney, In the presence of – 1. Name ____________________________ Signature

Address :

Occupation : Signed by Sri ……….on behalf of Signature ( Name of Company) in presence of -

1. Name : Signature 2. Address: .

Annexure-V

PROFORMA OF BANK GURANTEE FOR PERFORMANCE SECURITY (On Non-Judicial Stamp paper of appropriate value as per provision of the Stamp Act applicable in the concerned state)

[Applicable for PSD amount of Rs.5.00 Lakh and more]

To ………………………….. …………………………..

74

Re: Bank Guarantee in respect of Contract No…………………….….,Dated……………. Between …………….. (Name of the company) and ………………………………. (Name of the Contractor)

WHEREAS

…………………………………………….. (Name and address of the Contractor) (herein after called “the Contractor”) has entered into a contract made as per letter of acceptance……………………………….dated.…………………….(herein after called the said contract) with ………… (name of the Company) (hereinafter called “the Company”) to execute ……………………………………………………………………………………………… (name of the contract and brief description of work) on the terms and conditions contained in the said contract.

It has been agreed that the Contractor shall furnish a Performance Security in the shape of Bank

Guarantee from a Schedule bank for a sum of Rs………………………………. as security for due compliance and performance of the terms and conditions of the said contract.

We………………………………………….. (name of the Bank) having its branch/Office at……..………………….. have, at the request of the Contractor, agreed to furnish this bank Guarantee by way of Performance Security. NOW, THEREFORE, we the………………………………….. Bank (herein after called The Bank) hereby, unconditionally and irrevocably, guarantees and affirms as follows :

The Bank do hereby irrevocably guarantees and unconditionally agree with the Company that if the contractor shall in any way fail to observe or perform the terms and conditions of the said contract or shall commit any breach of its obligation there under, the Bank shall on its mere first written demand, and without any objection, demur and without any reference to the contractor, pay to the company the said sum of …………………………………………………………..……… or such portion as shall then remain due with interest without requiring the Company to have recourse to any legal remedy that may be available to it to compel the Bank to pay the sum, or failing on the company to compel such payment by the contractor.

Any such demand shall be conclusive as regards the liability of the Contractor to the company and as

regards the amount payable by the Bank under this Guarantee. The Bank shall not be entitled to withhold payment on the ground that the Contractor has disputed its liability to pay or has disputed the quantum of the amount or that any arbitration proceeding or legal proceeding is pending between the company and the Contractor regarding the claim.

The Bank further agree that the Guarantee shall come into force from the date hereof and shall remain in

force and effect till the period that will be taken for the performance of the said Contract which is likely to be ……………………………….. day of …………….………….. but if the period of Contract is extended either pursuant to the provisions in the said contract or by mutual agreement between the contractor and the company, the Bank shall renew the period of the Bank Guarantee failing which it shall pay to the company the said sum of ………………….…. or such lesser amount of the said sum of …………… as may be due to the company and as the company may demand.

This Guarantee shall remain in force until the dues of the company in respect of the said sum of

………………………………………..….and interest are fully satisfied and the Company certifies that the Contract has been fully carried out by the Contractor and discharged the guarantee.

The Bank further agrees with the company that the company shall have the fullest liberty without consent

of the Bank and without affecting in any way the obligations hereunder to vary any of the terms and conditions of the said contract or to extend time for performance of the said contract from time to time or to postpone for any time or from time to time any of the powers exercisable by the Company against the contractor and to forebear to enforce any of the terms and conditions relating to the said Contract and the Bank shall not be relieved from its liability by reason of such failure or extension being granted to the Contractor or to any forbearance, act or omissions on the part of the company or any indulgence by the Company to the Contractor or any other matter or thing whatsoever which under the law relating to sureties would but for this provision have the effect or relieving or discharging the Guarantor.

The Bank further agrees that in case this Guarantee is required for a longer period and it is not extended

by the Bank beyond the period specified above, the Bank shall pay to the company the said sum of ……………….……… or such lesser sum as may then be deemed to the Company and as the Company may require.

75

Notwithstanding anything contained herein the liability of the Bank under this Guarantee is restricted to

Rs………..……. The guarantee shall remain in force till the day ……*…….. of ……*..……. and unless the guarantee is renewed or claim is preferred against the bank on or before the said date all rights of the Company under this guarantee shall cease and the Bank shall be relieved and discharged from all liabilities hereunder except as provided in the preceding Clause.

* The date of guarantee shall cover a period of minimum one year or 90 days beyond the date of completion whichever is more.

Any notice by way of request, demand or otherwise hereunder maybe sent by post/e-mail/Fax addressed to the bank branch/operative branch, which shall be deemed to be a sufficient demand notice. Bank shall effect payment thereof forthwith.

This guarantee will not be discharged due to the change in the constitution of the Bank or the Contractor. The Bank has under its constitution power to give this Guarantee and Sri……………………. who has signed it on behalf of the Bank has authority to do so. “The Bank Guarantee as referred above shall be operative at our branch at………………………... payable at…………………………. The Contact details of the Bank issuing BG and the local operating Branch of the Bank at Bilaspur (C.G.) are as under :

Particulars Issuing Bank Local Operating Branch at Bilaspur

Branch Code

Postal Address

Telephone No.

FAX No.

Email Id

Signed and sealed this………..day of……………..at…………

SIGNED, SEALED AND DELIVERED For and on behalf of the Bank by : (Signature) (Name) (Designation) (Code number) (address) Under jurisdiction of Bilaspur court only.

Note :

(i) The Bank Guarantee issued by a scheduled bank shall be operative at its branch situated at Bilaspur (Chhattisgarh State) or if the issuing bank does not have any branch at Bilaspur then Bank Guarantee shall be operative at any of its Kolkata Branch.

(ii). The Bank Guarantee (BG) issued by the issuing Bank on behalf of contractor in favour of “South

Eastern Coalfields Limited” shall be in paper form as well as issued under “Structured Financial

Messaging System (SFMS)”.

The details of beneficiary for issue of Bank Guarantee (BG) under SFMS platform is furnished below:

A. State Bank of India as advising Bank of SECL:

76

1. Name of the Beneficiary

and his details.

i Name South Eastern Coalfields Limited

(SECL)

ii Area SECL - HQ. Bilaspur

iii Name of Bank State Bank of India

iv Bank Account No. 30285470636

v Department Civil

2. Beneficiary Bank,

Branch and address.

i Name of Bank State Bank of India

ii Bank Branch name SME SBI Branch

iii Branch code 4177

iv Beneficiary Bank Branch

IFSC

SBIN0004177

v Beneficiary Bank Address SBI, Galaxy Height, Vyapar Vihar

Bilaspur, PIN-495001,

Chhattisgarh

B. ICICI Bank as advising Bank of SECL:

1. Name of the Beneficiary

and his details.

i Name SECL 14265

ii Area SECL – HQ. Bilaspur

iii Name of Bank ICICI Bank

iv Bank Account No. 028205003346

v Department Civil

2. Beneficiary Bank,

Branch and address.

i Name of Bank ICICI Bank

ii Bank Branch name Vyapar Vihar, Bilaspur,

Chhattisgarh

iii Branch code 0282

iv Beneficiary Bank Branch

IFSC

ICIC0000282

v Beneficiary Bank Address ICICI Bank Ltd. , Surya Chambers,

Plot No. A/09, Vyapar Vihar,

Bilaspur, Chhattisgarh, PIN-

495001

Annexure-VI

PROFORMA OF JOINT VENTURE AGREEMENT

(On Non-Judicial Stamp paper of appropriate value as per provision of the Stamp Act applicable in the concerned state)

This Joint Venture agreement is made on this ……………………..day of…………………………………..

77

AMONGST/BETWEEN M/s………………………………………, having its registered Office at ………………………... Represented by Shri…………………………….(Name and Designation) of M/s………………...Who has power of Attorney to enter into Joint Venture with…………………………………...andSign all documents/ agreements on behalf of M/s……………… (hereinafter referred to as”……………….”)

AND

M/s………………………………………, having its registered Office at ………………………... Represented by Shri…………………………….(Name and Designation) of M/s………………...who has power of Attorney to enter into Joint Venture with…………………………………...andSign all documents/agreements on behalf of M/s……………… (hereinafter referred to as”……………….”).

AND

M/s………………………………………, having its registered Office at ………………………... Represented by Shri…………………………….(Name and Designation) of M/s………………...who has power of Attorney to enter into Joint Venture with…………………………………...andSign all documents/agreements on behalf of M/s……………… (hereinafter referred to as”……………….”). The expressions M/s …………………..and M/s…………………and M/s ………..shall, wherever the context admits, mean and include their respective legal representatives, successors-in-interest and assigns and shall collectively be referred to as “Joint Venture /Parties” and individually as “Joint Venture Partner/Party”. WHEREAS M/s……………….and M/s………………agreed to form a Joint Venture in order to join their forces to obtain best results from the combinations of their individual resources of technical and management skill, finance and equipment for the benefit of the project and in order to submit the Bid for the work of “………………………………….............................................…………………………………………………………………………………………………” (Hereinafter referred to as “Project”) under……………………..(Name of Company) (hereinafter referred to as “the principle Employer”). The Parties hereby enter into this Joint Venture Agreement (hereinafter referred to as “Joint Venture agreement”) to jointly prepare and submit the Bid for the Project and in the event of securing the Project from the Employer, to execute the Project in accordance with the Contract terms and conditions, to the satisfaction of the Principal Employer. NOW THEREFORE, the parties, in consideration of the mutual premises contained herein, agree as follows: 1) FORMATION AND TERMINATION OF THE JOINT VENTURE.

The parties under this Agreement have decided to form a Joint Venture to submit the Bid for the above Project and execute the Contract with the Principal Employer for the Project, if qualified and awarded.

a) The name and style of the Joint Venture shall be “………………………………..”

(hereinafter called the “Joint Venture ”)

b) The Head Office of the Joint Venture shall be located at………………………. and the site office will be located at the site of the Project. All communication regarding the project will be made to…………………… Telephone Nos…………………………..

c) Neither of the parties of the Joint Venture shall be allowed to sign, pledge, sell or otherwise dispose all or part of its respective interests in the Joint Venture to any party including the existing partner of the Joint Venture.

d) The terms of the Joint Venture shall begin as on the date first set forth above and shall terminate on the

earliest of the following dates. i) The Joint Venture fails to obtain qualification from the Employer. ii) The Contract for the Project is not awarded to the Joint Venture. iii) The Employer cancels the Project.

78

iv) The Project is completed including defects liability period to the satisfaction of the Employer and all the parties complete any and all duties, liabilities and responsibilities under or in connection with the Contract and the Joint Venture agreement.

2) LEAD PARTNER.

M/s…………………………. shall be the Lead Partner of the Joint Venture and is In-charge for performing the contract management. M/s…………………. shall be attorney of the parties duly authorized to incur liabilities and receive instructions for and on behalf of any and all partners in the Joint Venture and also all the partners of the Joint Venture shall be jointly and severally liable during the bidding process and for the execution of the contract as per contract terms with the employer in accordance with the power of attorney annexed.All Joint Venture partners M/s…………………..; M/s…………….& M/s………………………….. nominate and authorize Shri………………. ( name and designation) of M/s……………………………… to sign all letters, correspondence, papers & certificates and to submit the Pre-qualification Application / Bid documents for and on behalf of the Joint Venture.

3) REPRESENTATIVE OF THE PARTNERS OF THE JOINT VENTURE. Each constituent party of the Joint Venture appoints the following personnel as the representative of the relevant party with full power of attorney from the Board of Directors of the concerned company, or from the partners of the entity, or from the proprietor. JV Partner Name Position in the respective Company M/s…………… ………………….. …………………………………….. M/s………….. ………………….. ……………………………………..

M/s………….. ………………….. …………………………………….. 4) PARTICIPATION SHARE & WORK RESPONSIBILITIES.

4.1 The parties agree that their respective participation share (hereinafter called ‘Participation Share’) in the Joint Venture shall be as follows: M/s………………………………….. : ……..…..% (…………..per cent) M/s………………………………….. : ……..…..% (…………..per cent) and M/s………………………………….. : ……..…..% (…………..per cent) 4.2 The Parties shall share the rights and obligations, risk, cost and expenses, working capitals, profits or losses or others arising out of or in relation to execution of the Project in proportion to their share of participation in the Joint Venture except as otherwise agreed. 4.3 The parties shall jointly execute the works under the Project as an integrated entity and allocate responsibilities as regards division of work between themselves by organizing the adequate resources for successful completion of the Project. However all parties shall remain jointly and severally responsible for the satisfactory execution of the Project in accordance with the Contract terms and conditions.

5) JOINT AND SEVERAL LIABILITIES.

All partner of Joint Venture shall be liable jointly and severally during the Pre-qualification and Bidding process; and in the event the contract is awarded, during the execution of the Contract, in accordance with Contract terms.

6) WORKING CAPITAL

Each party shall contribute working capital for equipment, labour and material or any expenses incurred for execution of the Project or any other investment required in connection with the execution of the project proportionate to the participation ratio.

79

7) BID SECURITY:

Bid Security, Performance Security and other securities shall be paid by the Joint Venture except as otherwise agreed.

8) PERSONNEL & EQUIPMENT

Team of Managers / Engineers of all the partners of the Joint Venture will form part of the core management structure and assist in execution of the project. The list of Personnel and equipment proposed to be engaged for the project by each Party will be decided by the management committee.

9) NON PERFORMANCE OF RESPONSIBILITY BY ANY PARTY OF JOINT VENTURE .

a) As between themselves, each Party shall be fully responsible for the fulfillment of all obligations arising

out of its scope of the work for the Project to be clarified subject to the Agreement between the Parties and shall hold harmless and indemnified against any damage arising from its default ornon-fulfillment of such obligations.

b) If any Party fails to perform its obligations described in this Agreement during the execution of the Project

and to cure such breach within the period designated by the non-defaulting party, then the other party shall have the right to take up work, the interest and responsibilities of the defaulting party at the cost of the defaulting party.

c) Stepping into the shoes of the existing partner of Joint Venture with all the liabilities of the existing

partner from the beginning of the contract with the prior approval on Northern Company.

d) Notwithstanding demarcation or allotment of work of between/amongst Joint Venture partners, Joint Venture shall be liable for non-performance of the whole contract irrespective of their demarcation or share of work.

e) In case bid being accepted by Company, the payments under the contract shall only be made to the Joint

Venture and not to the individual partners.

10) BANK A/C.

Separate Bank A/c. shall be opened in the name of the Joint Venture in a scheduled or Nationalized Bank in India asper mutual Agreement and all payments due to the Joint Venture shall be received only in that account, which shall be operated jointly by the representative of the Parties hereto. The financial obligations of the Joint Venture shall be discharged through the said Joint Venture Bank Account only and also all the payments received or paid by company to the Joint Venture shall be through that account alone.

11) LIMIT OF JOINT VENTURE ACTIVITIES. The Joint Venture activities are limited to the bidding and in case of award, to the performance of the Contract for the Project according to the conditions of the Contract with the Employer.

12) TAXES. Each Party shall be responsible for its own taxes, duties and other levies to be imposed on each party in connection with the Project. The taxes, duties and other levies imposed on the Joint Venture in connection with the Project shall be paid from the account of the Joint Venture.

13) EXCLUSIVITY

The Parties hereto agree and undertake that they shall not directly or indirectly either individually or with other party or parties take part in the Bid for the said Project. Each Party further guarantee to the other party hereto that this undertaking shall also apply to its subsidiaries and companies under its direct or indirect control.

80

14) MISCELLANEOUS:

a. Neither party of the Joint Venture shall assign, pledge, sell or otherwise dispose all or part of its respective interests in the Joint Venture to all third party without the Agreement of the other party in writing.

b. Subject to the above clause, the terms and conditions of this agreement shall be binding upon the parties, the Directors, Officers, Employees, Successors, Assigns and Representatives.

15) APPLICABLE LAW

This agreement shall be interpreted under laws and regulations of India.

IN WITNESS Whereof the Parties hereto have hereunder set their respective hands and seals the day, month, year first above written. For …………………………………….. For…………………………….. For…………………………….. Signature _____________________ Signature _______________ Signature _______________ (Name & Address) (Name & Address) (Name & Address) (Official Seal ) (Official Seal) (Official Seal) Place ………………………………….. Place……………………….. Place……………………….. Date …………………………………… Date ………………………………. Date ………………………………. Witness Witness Witness Signature …………………………….. Signature ………………………… Signature ………………………… (Name & Address) (Name & Address) (Name & Address)

Annexure-VII

Pre Contract Integrity Pact

General:

81

This pre-bid pre-contract Agreement ( hereinafter called the Integrity Pact) is made on…….day of the month of…..2014, between, on one hand, South Eastern Coalfields Limited (hereinafter called the “BUYER” which expression shall mean and include, unless the context otherwise requires, his successors in office and assigns ) of the First Part and M/s ……… ……. ……… ……. ……… ……. (hereinafter called the “BIDDER/ Seller” which expression shall mean and include, unless the context otherwise requires, his successors and permitted assigns) of the Second Part. WHEREAS the BUYER proposes to award, under laid down organizational procedure, Contracts “……………………………………………………………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………………………………………………………” (Name of the WORK) and the BIDDER/ Seller is willing to offer/ has offered the work and WHEREAS the BIDER is a private company/public company/Government undertaking/ partnership./ registered export agency, constituted in accordance with the relevant law in the matter and the buyer is a PSU. NOW, THEREFORE, To avoid all forms of corruption by following a system that is fair, transparent and free from any influence/ prejudiced dealings prior to, during and subsequent to the currency of the contract to be entered into with a view to:- Enabling the BUYER to obtain the desired said work at a competitive price in conformity with the defined specifications by avoiding the high cost and the distortionary impact of corruption on public procurement, and Enabling BIDDERS to abstain from bribing or indulging in any corrupt practice in order to secure the contract by providing assurance to them that their competitor will also abstain from bribing and other corrupt practices and the BUYER will commit to prevent corruption, in any form, by its officials by following transparent procedures. The parties hereto hereby agree to enter into this Integrity Pact and agree as follows:

Commitments of the BUYER

1.1 The BUYER undertakes that no official of the BUYER, connected directly or indirectly with the contract, will

demand, take a promise for or accept, directly or through intermediaries, any bribe, consideration, gift reward, favour or any material or immaterial benefit or any other advantage from the BIDDER, either for themselves or for any person, organization or third party related to the contract in exchange for an advantage in the bidding process, bid evaluation, contracting implementation process related to the contract.

1.2 The BUYER will, during the pre-contract stage, treat all BIDDERS alike, and will provide to all BIDDERs the

same information and will not provide any such information to any particular BIDDER which could afford an advantage to that particular BIDDER in comparison to other BIDDERs.

1.3 All the officials of the BUYER will report to the appropriate Government office any attempted or completed

breaches of the above commitments as well as any substantial suspicion of such a breach. 2. In case any such preceding misconduct on the part of such official(s) is reported by the BIDDER to the BUYER

with full and verifiable facts and the same is prima facie found to be correct by the BUYER, necessary disciplinary proceedings, or any other action as deemed fit, including criminal proceedings may be initiated by the BUYER and such a person shall be debarred from further dealing related to the contract process. In such a case while an enquiry is being conducted by the BUYER the proceedings under the contract would not be stalled.

Commitments of BIDDERs

3. The BIDDER omits itself to take all measures necessary to prevent corrupt practices, unfair means and illegal activities during any stage of its bid or during any pre-contract or post contract stage in order to secure the contract or in furtherance to secure it and in particular commit itself to the following.

3.1 The BIDDER will not offer, directly or through intermediaries, any bribe, gift, consideration, reward, favour, any material or immaterial benefit or other advantage, commission, fees, brokerage or inducement to any

82

official of the BUYER, connected directly or indirectly with the bidding process, or to any person, organization or third party related to the contract in exchange for any advantage in the bidding, evaluation, contracting and implementation of the contract.

3.2 The BIDDER further undertakes that it has not given,. Offered or promised to give, directly or indirectly any bribe, gift , consideration, reward, favour, any material or immaterial benefit or other advantage, commission, fees, brokerage or inducement to any official of the BUYER or otherwise in procuring the Contract or forbearing to do or having done any act in relation to the obtaining or execution of the contract or any other contract with the Government for showing or forbearing to show favour or disfavour to any person in relation to the contract or any other contract with the Government.

3.3* Foreign BIDDERs shall disclose the name and address of agents and representatives in India and Indian BIDDERs shall disclose their foreign principals or associates.

3.4* BIDDERs shall disclose the payment to be made by them to agents/ brokers or any other intermediary, in connection with this bid/contract.

3.5* The BIDDER further confirms and declare to the BUYER that the BIDDER is the original manufacturer/ integrator/ authorized Government sponsored export entity of the defence stores and has not engaged any individual or firm or company whether Indian or foreign to intercede, facilitate or in any way to recommend to the BUYER or any of its functionaries, whether officially or unofficially to the award of the contract to the BIDDER, not has any amount been paid, promised or intended to be paid to any such individual, firm or company in respect of any such intercession, facilitation or recommendation.

3.6 The BIDDER, either while presenting the bid or during pre-contract negotiations or before signing the contract, shall disclose any payments he has made, is committed to or intends to make to officials of the BUYER or their family members, agents, brokers or any other intermediaries in connection with the contract and the details of services agreed upon for such payments.

3.7 THE BIDDER will not collude with other parties interested in the contract to impair the transparency, fairness and progress of the bidding process, bid evaluation, contracting and implementation of the contract.

3.8 The BIDDER will not accept any advantage in exchange for any corrupt practice, unfair means and illegal activities.

3.9 The BIDDER shall not use improperly, for purposes of completion or personal gain, or pass on to others, any information provided by the BUYER as part of the business relationship, regarding plans, technical proposals and business details, including information contained in any electronic data carrier. The BIDDER also undertakes to exercise due and adequate care lest any such information is divulged.

3.10 The BIDDER commits to refrain from giving any complaint directly or through any other manner without supporting it with full and verifiable facts.

3.11 The BIDDER shall not instigate or cause to instigate any third person to commit any of the actions mentioned above.

3.12 If the BIDDER or any employees of the BIDDER or any person acting on behalf of the BIDDER, either directly or indirectly, is a relative of any of the officers of the BUYER, or alternatively, if any relative of an officer of the BUYER has financial interest/ stake in the BIDDER’s firm, the same shall be disclosed by the BIDDER at the time of filing of tender.

The term “relative” for this purpose would be as defined in Section 6 of the Companies Act 1956.

3.13 The Bidder shall not lend to or borrow any money from or enter in to any monetary dealings or transactions, directly or indirectly, with any employee of the BUYER.

3.14 Bidder shall not approach the Courts while representing the matters to IEMs and he/ she will await their decision in the matter.

3.15 In case of sub-contracting, the Principal contractor shall take the responsibility of the adoption of Integrity Pact by the sub-contractor.

83

3.16 Bidders will no pass any information provided by Principal as part of business relationship to others and will not commit any offence under PC/IPC Act.

3.17 Bidders will disclose any transgressions with any other Company that may impinge on the anti corruption principle.

3.18 Bidders will not enter into any undisclosed agreement or understanding with other bidders with respect to prices, specifications, certifications, subsidiary contracts.

4. Previous Transgression:

4.1 The BIDDER declares that no previous transgression occurred in the last three years immediately before signing of this Integrity Pact, with any other company in any country in respect of any corrupt practices envisaged hereunder or with any Public Sector Enterprise in India or any Government Department in India that could justify BIDDER’s exclusion from the tender process.

4.2 The BIDDER agrees that if it makes incorrect statement on this subject, BIDDER can be disqualified from the

tender process or the contract, if already awarded, can be terminated for such reason. 5. Earnest Money Deposit (EMD)

As mentioned in the Tender Document 6. Sanctions for Violations:

6.1 Any breach of the aforesaid provisions by the BIDDER or any one employed by it or acting on its behalf ( whether with or without the knowledge of the BIDDER) shall entitle the BUYER to take all or any one of the following actions, wherever required.

(i) To immediately call off the pre contract negotiations without assigning any reason or giving any compensation to the BIDDER. However, the proceedings with the other BIDDER(s) would continue.

(ii) The Earnest Money Deposit (in pre-contract stage) and / or Security Deposit/ Performance Bond (after the contract is signed) shall stand forfeited either fully or partly, as decided by the BUYER and the BUYER shall not be required to assign any reason therefore.

(iii) To immediately cancel the contract, if already signed, without giving any compensation to the BIDDER.

(iv) To recover all sums already paid by the BUYER, and in case of an Indian BIDDER with interest thereon at 2% higher than the prevailing Prime Lending Rate of State Bank of India, while in case of a BIDDER from a country other than India with interest thereon at 2% higher than the LIBOR . If any outstanding payment is due to the BIDDER from the BUYER in connection with any other contract for any other stores, such outstanding payment could also be utilized to recover the aforesaid sum and interest.

(v) To encash the advance bank guarantee and performance bond/ warranty bond, if furnished by the BIDDER, in order to recover the payments, already made by the BUYER, along with interest.

(vi) To cancel all or any other Contracts with the BIDDER. The BIDDER shall be liable to pay compensation for any loss or damage to the BUYER resulting from such cancellation/ rescission and the BUYER shall be entitled to deduct the amount so payable from the money(s) due to the BIDDER.

(vii) To debar the BIDDER from participating in future bidding processes of the Government of India for a minimum period of five years, which may be further extended at the discretion of the BUYER.

(viii) To recover all sums paid in violation of this Pact by BIDDER(s) to any middleman or agent or broker with a view to securing the contract.

(ix) In case where irrevocable Letters of Credit have been received in respect of any contract signed by the BUYER with the BIDDER, the same shall not be opened.

(x) Forfeiture of Performance Bond in case of a decision by the BUYER to forfeit the same without assigning any reason for imposing sanction for violation of this Pact.

6.2 The BUYER will be entitled to take all or any of the actions mentioned at para 6.1(i) to (x) of this Pact also on the Commission by the BIDDER or any one employed by it or acting on its behalf ( whether with or without the knowledge of the BIDDER), of an offence as defined in Chapter IX of the Indian Penal code , 1860 or Prevention of Corruption Act, 1988 or any other statute enacted for prevention of corruption.

84

6.3 The decision of the BUYER to the effect that a breach of the provisions of this Pact has been committed by the BIDDER shall be final and conclusive on the BIDDER. However, the BIDDER can approach the Independent Monitor(s) appointed for the purposes in this Pact.

7. Independent Monitors:

7.1 The BUYER has appointed Independent Monitors (hereinafter referred to as Monitors) for this Pact in

consultation with the Central Vigilance Commission (Names and Address of the Monitors to be given). 7.2 The task of the Monitors shall be to review independently and objectively, whether and to what extent

the parties comply with the obligations under this Pact. 7.3 The Monitors shall not be subject to instructions by the representatives of the parties and perform their

functions neutrally and independently. 7.4 Both the parties accept that the Monitors have the right to access all the documents relating to the

project/ procurement, including minutes of meetings. 7.5 As soon as the Monitor notices, or has reason to believe, a violation of this Pact, he will so inform the

Authority designated by the BUYER. 7.6 The BIDDER(s) accepts that the Monitor has the right to access without restriction to all Project

documentation of the BUYER including that provided by the BIDDER. The BIDDER will also grant the Monitor, upon his request and demonstration of a valid interest, unrestricted and unconditional access to his project documentation. The same is applicable to Subcontractors. The Monitor shall be under contractual obligation to treat the information and documents of the BIDDER/ Subcontractor(s) without confidentiality.

7.7 The BUYER will provide to the Monitor sufficient information about all meetings among the parties related to the Project provided such meetings could have an impact on the contractual relations between the parties. The parties will offer to the Monitor the option to participate in such meetings.

7.8 The Monitor will submit a written report to the designated Authority of BUYER/ Secretary in the Department/ within 8 to 10 weeks from the date of refernce or intimation to him by the BUYER/ BIDDER and, should the occasion arise, submit proposals for correcting problematic situations.

8. Facilitation of Investigation In case of any allegation of violation of any provisions of this Pact or payment of commission, the BUYER or its agencies shall be entitled to examine all the documents including the Books of Accounts of the BIDDER and the BIDDER shall provide necessary information and documents in English and shall extend all possible help for the purpose of such examination. 9. Law and Place of Jurisdiction This Pact is subject to Indian Law. The place of performance and jurisdiction is the seat of the BUYER. 10. Other Legal Actions The actions stipulated in this integrity Pact are without prejudice to any other legal action that may follow in accordance with the provisions of the extant law in force relating to any civil or criminal proceedings. 11. Validity 11.1 The validity of this Integrity Pact shall be from date of its signing and extend upto 5 years or the complete

execution of the contract to the satisfaction of both the BUYER and the BIDDER./ Seller, including warranty period, whichever is later. In case, BIDDER is unsuccessful, this Integrity Pact shall expire after six months from the date of the signing of the contract.

85

11.2 Should one or several provisions of this Pact turn out to be invalid; the remainder of this Pact shall remain valid. In this case, the parties will strive to come to an agreement to their original intensions.

12. The parties hereby sign this Integrity Pact at on BUYER BIDDER Name of the Officer CHIEF EXECUTIVE OFFICER

Designation Deptt./MINISTRY/PSU Witness Witness 1. 1.

2. 2.

* Provisions of these clauses would need to be amended/ deleted in line with the policy of the BUYER in regard to involvement of India agents of foreign suppliers.

Annexure-VIII

PROFORMA FOR WRITTEN CONSENT FOR ARBITRATION CLAUSE

(Applicable for Partnership Firm & Joint Venture)

86

We, all the Partners of M/s ………………………………………………………………………… (Partnership Firm/ Joint

Venture), do hereby give our written consent for acceptance of the following Arbitration Clause of the

NIT for the Work “……………………………………………………………………………………………………………………………………”

tendered by SECL, vide NIT No. ………………………………………………………………………………… dated ………………..

and Tender Id …………………………….. :

A. Settlement of Disputes.

It is incumbent upon the contractor to avoid litigation and disputes during the course of execution. However, if such disputes take place between the contractor and the department, effort shall be made first to settle the disputes at the company level. The contractor should make request in writing to the Engineer-in-charge for settlement of such disputes/ claims within 30 (thirty) days of arising of the cause of dispute/ claim failing which no disputes/ claims of the contractor shall be entertained by the company. Effort shall be made to resolve the dispute in two stages In first stage dispute shall be referred to Area GM or GM/HoD(C). If difference still persist the dispute shall be referred to a committee constituted by the owner. The committee shall have one member of the rank of Director of the company who shall be chairman of the committee. If differences still persist, the settlement of the dispute shall be resolved in the following manner: Disputes relating to the commercial contracts with Central Public Sector Enterprises / Govt. Departments (except Railways, Income Tax, Customs & Excise)/ State Public Sector Enterprises shall be referred by either party for Arbitration to the PMA (Permanent Machinery of Arbitration) in the department of Public Enterprises. In case of parties other than Govt. Agencies, the redressal of the dispute may be sought through Arbitration (THE ARBITRATION AND CONCILIATION ACT, 1996 as amended by AMENDMENT ACT of 2015).

B. Settlement of Disputes through Arbitration

If the parties fail to resolve the disputes/differences by in house mechanism, then, depending on the position of the case, either the employer/owner or the contractor shall give notice to other party to refer the matter to arbitration instead of directly approaching Court. The contractor shall, however, be entitled to invoke arbitration clause only after exhausting the remedy available under the clause 16. In case of parties other than Govt. agencies, the redressal of disputes/differences shall be sought through Sole Arbitration as under.

Sole Arbitration:

In the event of any question, dispute or difference arising under these terms & conditions or any condition contained in this contract or interpretation of the terms of, or in connection with this Contract (except as to any matter the decision of which is specially provided for by these conditions), the same shall be referred to the sole arbitration of a person, appointed to be the arbitrator by the Competent Authority of CIL / CMD of Subsidiary Company (as the case may be). The award of the arbitrator shall be final and binding on the parties of this Contract. (a) In the event of the Arbitrator dying, neglecting or refusing to act or resigning or being unable to act for any reason, or his/her award being set aside by the court for any reason, it shall be lawful for

87

the Competent Authority of CIL / CMD of Subsidiary Company (as the case may be) to appoint another arbitrator in place of the outgoing arbitrator in the manner aforesaid. (b) It is further a term of this contract that no person other than the person appointed by the Competent Authority of CIL / CMD of Subsidiary Company (as the case may be) as aforesaid should act as arbitrator and that, if for any reason that is not possible, the matter is not to be referred to Arbitration at all. Subject as aforesaid, Arbitration and Conciliation Act, 1996 as amended byAmendment Act of 2015, and the rules thereunder and any statutory modification thereof for the time being in force shall be deemed to apply to the Arbitration proceedings under this clause. The venue of arbitration shall be the place from which the contract is issued or such other place as the Competent Authority of CIL/ CMD of Subsidiary Company (as the case may be) at his discretion may determine. Applicable Law: The contracts shall be interpreted in accordance with the laws of the Union of India.

Signature of Partners of Partnership Firm/ Joint Venture :

1. Name of Partner : Signature :

2. Name of Partner : Signature :

3. Name of Partner : Signature :

4. Name of Partner : Signature :

5. Name of Partner : Signature :

6. ……………………………………………………………………………………

7. …………………………………………………………………………………..

Note : This CONSENT has to be signed by each Partner of Partnership Firm/ Joint Venture

Annexure-IX

PROFORMA OF MEMORANDUM (To be a Part of Contract Agreement)

88

TENDER FOR WORK

I/We hereby tender for the execution for the SOUTH EASTERN COALFIELDS LIMITED (SECL) of the work

specified in the underwritten MEMORANDUM at rates specified in the Price-bid within a period of --------

--------------------- Days as per Work Order and subject to the annexed conditions of Contract and with

such materials as are provided for by and in all other respects in accordance with such conditions so far

as applicable.

MEMORANDUM

1 Name of Work

2 Agreement Value of Work

3 Performance Security Deposit (PSD)

4 Additional Performance Security Deposit

5 Percentage to be deducted from Bills towards Retention Money

6 Scheduled Date of Commencement of Work

7 Scheduled Date of Completion of Work