Total Quality Management – FMEA - Prof. Dr. D. Steude 1
FMEAFMEAFailure Mode and Effect AnalysisFailure Mode and Effect Analysis
Total Quality Management – FMEA - Prof. Dr. D. Steude 2
Development
• Development Center of the 1960s at the NASA space programs for quality assurance of the
• In the Consequence application v. a. in safety critical areas (such as aviation, nuclear technology)
• 1980 Recording as "Ausfalleffektanalyse" into the DIN 25448
• Since the end of the 1980s increased use in the automotive industry (first at Ford)
Definition
The failure modes and -analysis (FMEA, engl: Failure Modes and Effects Analysis) is
•a formalized, analytical method
•for systematic collection and avoid potential errors in the development of new products
•as well as in the planning of manufacturing and assembly processes.
The basic idea of the method:
Errors that are not made, must not be fixed!Errors that are not made, must not be fixed!
FMEA – Failure Mode and Effect Analysis
Quelle: Institut für Werkzeugmaschinen und Betriebstechnik Universität Karlsruhe (TH) Prof. H. Weule, Prof. D. Spath, Prof. J. Schmidt
Total Quality Management – FMEA - Prof. Dr. D. Steude 3 SS 2007
• With every new development in principle
• Introduction of new technologies, Materials and Processes
• Safety-related systems, components or procedures
• If potential failure serious and expensive consequences had the result
• In case of constructive or production changes to existing products
• In case of change of the working conditions of a product
• In so-called defective parts or Problemprozessen, i.e. if there is a high quality risk
• In the Business Risk Management Process
Range of application
Areas of use of the FMEA
4.3 Instrumente der Umsetzung
Quelle: Institut für Werkzeugmaschinen und Betriebstechnik Universität Karlsruhe (TH) Prof. H. Weule, Prof. D. Spath, Prof. J. Schmidt
Total Quality Management – FMEA - Prof. Dr. D. Steude 4
Considered Object
Basics of FMEA Time of the Responsibility for
Implementation
System-FMEA
Process FMEA
Design FMEA
Parent product or system
Product-concepts
after completion of the product
concept Development
Significant component
Construction Documents
after completion of the construction
documents Construction
Steps of the production
process
Manufacturing-plans
after completion of the manufacturing
plan
Production preparation, production
The FMEA can in all phases of the product lifecycle, From development to use, be used. In addition to the two "classic" FMEAs, the design and the process FMEA, is in the last time also increases the system-FMEA used.
Types of FMEA4.3 Instruments of implementation
Quelle: Institut für Werkzeugmaschinen und Betriebstechnik Universität Karlsruhe (TH) Prof. H. Weule, Prof. D. Spath, Prof. J. Schmidt
Total Quality Management – FMEA - Prof. Dr. D. Steude
5 SS 2007
Fehler, Ausfallvariante
Fahrzeug bleibt liegen
Motordefekt
Motorbrems-leistung zu
gering
Konstantdrossel-bremsleistung
fehlt
Drosselventilöffnet nicht
Ventil klemmt Durchmesser-maß nicht i.O.
Schleiffehler Werkzeug,Vorrichtung
Product Functional carrier
System Subsystem Assembly Component Characteristic property
Process step
Process parameters
Fahrzeug Motor Motorbrems-system
Konstantdrossel-bremssystem
Anordnung:Konstantdrossel
SchleifenVentil Ventil-durchmesser
Einstellung,Störgröße
Connection between the FMEA-types
Fehler-folge
Fehler-ursache
Fehler
System-FMEA 2
Fehler-folge
Fehler-ursache
Fehler
System-FMEA 1
Fehler-folge
Fehler-ursache
Fehler
Konstruktions-FMEA
Fehler-folge
Fehler-ursache
Fehler
Prozess-FMEA
Total Quality Management – FMEA - Prof. Dr. D. Steude
6 SS 2007
Planning and Preparation
Project selection
Appointment of a coordinator and team building
System analyse
Risk analysis
Risk Assessment
Risk minimization
Definition of measures
Agreement of the measures
Review of the measures (auditing)
Validation of the FMEA to the completed process
Risikobeurteilung: FMEA der VersorgungsketteFMEA – Failure Modes and Effects Analysis
Total Quality Management – FMEA - Prof. Dr. D. Steude
7 SS 2007
Systematisches Vorgehen
Das Produkt oder der Prozess werden in einer Top-Down-Vorgehensweise in einzelne Komponenten untergliedert.
Das systematische Vorgehen wird dabei durch die Verwendung eines Formblattes unterstützt.
Risikoanalyse, -bewertung und -minimierung
Der Ablauf der FMEA gliedert sich in Risikoanalyse, Risikobewertung und Risikominimierung. Letztere muss solange wiederholt werden, bis die Risikoprioritätszahl unter einem definierten Grenzwert liegt.
Risikoanalyse
Risikobewertung
Risikominimierung
Festlegung von Maßnahmen
Einführung der Maßnahmen
Überprüfung der Maßnahmen
Risiko ?
Ende
Risiko ?
Fehlermöglichkeits- und -einflußanalyse
Methodische Grundsätze4.3 Instrumente der Umsetzung
Total Quality Management – FMEA - Prof. Dr. D. Steude
8 SS 2007
Avoid,
decrease
laminate
Even bear
Renunciation
•An incentive•Risk-sharing•Risk compensation• insurance
Reduction of the risk probability
Reserves-educationR
isk
pot
ent
ial
Risiko-Management – die StrategieFMEA – Risk management4.3 Instrumente der Umsetzung
Total Quality Management – FMEA - Prof. Dr. D. Steude
9 SS 2007
preventive use
To fully exploit its benefits, the FMEA should already be used to run the beginning of the product life?.
FMEA-Team
development
Quality Assurance
attempt
distribution
(Customer)
planning
production
Interdisciplinary, creative teamwork
EntwicklungBeschaf-fung
Prozeß-planung
KundeFertigung
0,10 €1 €
100 €
10 €
Des
ign
FM
EA
Pro
cess
FM
EA
FehlerentdeckungFehlerverhütung
zune
hmen
de F
ehle
rkos
ten
In the preparation of FMEA employees from different departments of a company are involved.
In order to maintain continuity, certain functional areas at least 2 different types of FMEA participate.
Methodological Principles4.3 Instruments for implementing
Total Quality Management – FMEA - Prof. Dr. D. Steude
10 SS 2007
Fehlermöglichkeits- und -einflußanalyse Teil-Name Teil-Nummer
Firma (Stempel, Warenzeichen)
Konstruktions-FMEA Prozeß-FMEA System-FMEA Modell/System/Fertigung Techn. Änderungsstand
Bestätigung durch betroffene Abteilung
Name/Abt./Lieferant Name/Abt./Lieferant Erstellt durch (Name/Abt.) Datum Überarbeitet
IST-ZUSTAND VERBESSERTER ZUSTAND
Systeme/ Merkmale Potentielle Fehler
Potentielle Fehlerfolgen D
Potentielle Fehlerursachen
Vorgesehene Prüfmaßnahmen
Auftreten
Bedeutung
Entdeckung
Risiko-prioritäts-
zahl (RPZ)
Empfohlene Abstellmaßnahme
Verantwort-lichkeit
Getroffene Maßnahmen
Auftreten
Bedeutung
Entdeckung
Risiko-prioritäts-
zahl (RPZ)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17)
Risk analyse Risk minimizationRisk? Evaluated?
Maintenance
FMEA form VDA4.3 Instruments for implementing
Total Quality Management – FMEA - Prof. Dr. D. Steude
11 SS 2007
Spalte 1: Systems / features
in Design FMEA: component name (eg valve)
in Process FMEA: Process Name: (eg, drilling)
Valve - switch - pipe
- Ausfall (evtl. auch sicherheitskritisch)- Geräusche- Nacharbeit notwendig- Montage erschwert
Spalte 3: Potential failure effects
Description of the consequences of the error for internal (in process FMEA) and external customers (in Design FMEA)
It is assumed that the error occurred.
Cracked - Swaps - Obstruction - short - corrosion - fatigue - wear
Spalte 4: documentation obligations
Are affected by the potential consequences of errors or mistakes legal provisions in this column is a "D" stated
Noise Control Act offends against the Federal Emissions?
A list of all possible errors of the observation unit
Important : Make any subjective review! First, minor errors can prove on closer inspection to be quite critical.
Can serve as the basis of previous experience FMEA s or customer service information like parts.
Spalte 2:potential error
Risk Analysis4.3 Instrumente der Umsetzung
Total Quality Management – FMEA - Prof. Dr. D. Steude
12 SS 2007
Spalte 6: Proposed test measures
Spalte 5: Potential Causes
Collection of all possible sources of error that can lead to the observed error
Possible classification of the causes of errors :
- Design-related errors
- Production-related error
- Due to assembly errors
a) Avoid activities (V) (= Verhütungsmaßnahmen): Measures that either prevent the occurrence of the fault or error cause?
Reducing the probability of occurrence (risk A number is decreased)
b discovering measures (E)) (test measures): measures, a discovery of the error allow? Increase the probability of
detection (risk number E is small)
c) impact limiting measures (A): measures, not prevent the occurrence of a failure, but reduce its impact
or even prevent it? Reduce the significance of the fault (figure B risk is smaller)
It is recommended to focus on existing inspection measures for similar structures or to the planned tests and new developments in
- Design? changes (V) - process changes (V)
- Sampling tests (E) - improve? Testability (E)
- Redundant function? design (A) - Warning devices (A)
- Dimensioning - false material
- Form-/Lagetolerenzen - surface structure
- Incorrect installation - incorrect setting
risk Analysis4.3 Instruments for implementing
Total Quality Management – FMEA - Prof. Dr. D. Steude
13 SS 2007
Column 7: probability of occurrence
Assessment of probability of occurrence of any cause in the light of recent prevention measures (see column 6)
It is believed that the cause of the error and error can not be detected before the product reaches the customer.
The significance of the error flows with not included in the assessment.
Auftretenswahrscheinlichkeit Häufigkeit Bewertungspunkte
unwahrscheinlich
Es ist unwahrscheinlich, daß ein Fehler auftritt.
0
1
sehr gering
Konstruktion entspricht generell früheren Entwürfen, für die sehr geringe Fehlerzahlen bekannt sind.
1/10000 1/5000
2 3
gering
Konstruktion entspricht generell früheren Entwürfen, bei denen gelegentlich Fehler auftraten.
1/2000 1/1000 1/200
4 5 6
mäßig
Konstruktion entspricht generell früheren Entwürfen, bei denen immer wieder Schwierigkeiten auftraten.
1/100 1/50
7 8
hoch
Es ist nahezu sicher, daß Fehler in größerem Maße auftreten.
1/10 1/2
9 10
risk Assessment4.3 Instruments of implementation
Total Quality Management – FMEA - Prof. Dr. D. Steude
14 SS 2007
Column 8: the error means
Evaluation of the effect of the error on the client, taking into account the recent impact limitation measures
The valuation is independent of the occurrence and detection probability.
Principle have the same error Follow the same rating
Bedeutung des Fehlers (Auswirkung auf den Kunden) Bewertungspunkte
keine Auswirkung
Es ist unwahrscheinlich, daß der Fehler eine wahrnehmbareAuswirkung auf das System hat.
1
unbedeutend
Der Kunde wird nur geringfügig belästigt. Er wird nur eine geringeBeeinträchtigungen des Systems bemerken.
23
mittelschwer
Der Kunde ist unzufrieden. Er fühlt sich durch den Fehler belästigtoder ist verärgert.
456
schwer
Der Kunde ist über den Fehler verärgert, jedoch ist dieSystemsicherheit nicht betroffen.
78
äußerst schwerwiegend
Fehler führt zum Ausfall des Systems. Sicherheit und/oderEinhaltung gesetzlicher Vorschriften ist beeinträchtigt.
910
risk Assessment4.3Instruments for implementing
Total Quality Management – FMEA - Prof. Dr. D. Steude
15 SS 2007
Column 9: Probability of Detection
Assessment of the likelihood for the discovery of the error, before the product is delivered, regardless of the occurrence and the significance of the error
The previous inspection measures must be considered in the assessment.
Wahrscheinlichkeit der Entdeckung Häufigkeit Bewertungspunkte
hoch
Funktioneller Fehler, der bei den nachfolgenden Arbeitsgängen bemerkt wird
> 99,99 %
1
mäßig
Augenscheinliches Fehlermerkmal. Automatische 100 % Prüfung eines einfachen Merkmals (z.B. Bohrung vorhanden)
> 99,7 %
2-5
gering
Leicht zu erkennendes Fehlermerkmal. Automatische 100 % Prüfung eines meßbaren Merkmals (z.B. Durchmesser).
> 98 %
6-8
sehr gering
Nicht leicht zu erkennendes Fehlermerkmal. Visuelle oder manuelle 100 % Prüfung
> 90 %
9
unwahrscheinlich
Das Merkmal wird nicht geprüft, bzw. kann nicht geprüft werden. Verdeckter Fehler, der nicht erkannt wird.
< 90 %
10
risk Assessment4.3 Instruments for implementing
Total Quality Management – FMEA - Prof. Dr. D. Steude
16 SS 2007
Mit der Risikoprioritätszahl wird ein Maß für das Risiko festgelegt. Je höher die RPZ, desto höher das Risiko.
Die RPZ ergibt sich aus der Multiplikation der jeweiligen Bewertungspunkte für Auftreten (A), Bedeutung (B) und Entdeckung (E) der Fehlers:
RPZ = A * B * E
Diese Berechnung ist für alle Fehlerursachen durchzuführen.
Die Risikoprioritätszahlen geben einen Anhaltspunkt für die Reihenfolge der anschließend durchzuführenden Verbesserungsmaßnahmen im Rahmen der Risikominimierung. Fehlerursachen mit einer hohen RPZ sollten zuerst betrachtet werden.
Darüber hinaus sollten unabhängig von der RPZ auch die Einzelbewertungen betrachtet werden:
hohe "A"-Werte: Fehler treten häufig auf. Solche Fehler müssen vorrangig beseitigt werden.
hohe "B"-Werte: Die zu erwartende Verärgerung des Kunden ist besonders groß. Es sollte über eine konzeptionelle Änderung nachgedacht werden.
hohe "E"-Werte: weisen auf konzeptionelle Schwachstellen hin
In der Praxis werden oft nur Fehlerursachen mit einer RPZ größer als 125 oder Einzelbewertungen größer als 8 als besonders kritisch angesehen. Aufgrund der Subjektivität der Risikoprioritätszahlen ist von dieser
Vorgehensweise aber abzuraten! Unter dem Gesichtspunkt einer Null-Fehler-Strategie stellt jeder Fehler eine Beeinträchtigung der Produktqualität dar und sollte deshalb vermieden werden.
Spalte 10: Risikoprioritätszahlen (RPZ)
Risikobewertung4.3 Instrumente der Umsetzung
Total Quality Management – FMEA - Prof. Dr. D. Steude
17 SS 2007
Basic Approaches:
Avoiding the error cause
Reducing the probability of occurrence
Reduction in the importance of the error
Increase the probability of detection
Column 11: Recommended Remedial
Review of measures :
Basically: Fault avoidance measures are preferable to missing rent nationwide!
i.e. Quality is produced not merely achieved!
Error condition Nationwide measures are costly and do not lead to quality improvements. • You should only be used as an emergency or temporary basis.
The best way is to avoid the cause of the error by design and / or manufacturing engineering changes. good method: Poka-Yoke, i.e. avoid inadvertent error ("idiots security") installation of an incorrect part is as avoided by design produced distinctiveness
minimizing risk4.3 Instruments for implementing
Quelle: Institut für Werkzeugmaschinen und Betriebstechnik Universität Karlsruhe (TH) Prof. H. Weule, Prof. D. Spath, Prof. J. Schmidt
Total Quality Management – FMEA - Prof. Dr. D. Steude
18 SS 2007
For any corrective action has to be a responsible employee or department to be entered.
In addition, a date for the launch is set.
Column 12: Responsibility
Registration of the final measures imposed, which do not necessarily correspond with the recommended corrective actions listed in column 11 .
Column 14-17: Assessing the Effects
A new risk assessment provides information on the effectiveness of the measures.
This regard are the same criteria as for columns 7-10.
The method of minimizing risk must be repeated until the risk of error is minimized to the requirements accordingly.
The method of minimizing risk must be repeated until the risk of error is minimized to the requirements accordingly.
Column 13: Measures introduced
Minimizing Risk4.3 Instruments for implementing
Quelle: Institut für Werkzeugmaschinen und Betriebstechnik Universität Karlsruhe (TH) Prof. H. Weule, Prof. D. Spath, Prof. J. Schmidt