FMEA for Manufacturing and Assembly Process

download FMEA for Manufacturing and Assembly Process

of 9

Transcript of FMEA for Manufacturing and Assembly Process

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    1/9

    International Conference on Technology and Business Management March 26-28. 2012

    501

    FMEA for Manufacturing and Assembly Process

    A. A. Nannikar

    D. N. Raut

    R. M. Chanmanwar

    S. B. Kamble

    [email protected], Mumbai

    D. B. [email protected]

    Siemens Ltd., Mumbai

    1. IntroductionFMEA is a systematic method of identifying and preventing system, product and process problems before they

    occur. It is focused on preventing problems, enhancing safety, and increasing customer satisfaction. Ideally,FMEAs are conducted in the product design or process development stages, although conducting an FMEA on

    existing products or processes may also yield benefits.FMEA is a tool that allows us to:

    Prevent System, Product and Process problems before they occur. Reduce costs by identifying system, product and process improvements early in the development cycle. Create more robust processes. Prioritize actions that decrease risk of failure. Evaluate the system, design, and processes from a new vantage point.

    FMEA is

    Description

    A procedure that examines each item in a system, considers how that item can fail and then determines how that

    failure will affect (or cascade through) the system.

    Acronyms

    FMEA: Failure Modes and Effects Analysis FMECA: Failure Modes and Effects and Criticality Analysis

    2. Review of LiteratureFailure Mode and Effects Analysis (FMEA) for ensuring that reliability is designed into typical semiconductor

    manufacturing equipment (Mario Villacourt 1992). The FMEA is taken during the design phase of the

    equipment life cycle to ensure that reliability requirements have been properly allocated and that a process for

    continuous improvement exists. The guide provides information and examples regarding the proper use of

    FMEA as it applies to semiconductor manufacturing equipment.

    This Executive Summary is designed in a what, why, when, how format to allow the reader a relatively quick

    overview of the main issues surrounding an FMEA which are contained in the main part of the Guidance

    Document itself (IMCA 2002). FMEA does not attempt to give comprehensive answers to the frequentlyanswered questions (FAQs), which are addressed in the main document.

    3. Purpose of FMEAThe purpose of performing an FMEA is to analyze the product's design characteristics relative to the planned

    manufacturing process and experiment design to ensure that the resultant product meets customer needs and

    expectations. When potential failure modes are identified, corrective action can be taken to eliminate them or to

    continually reduce a potential occurrence. The FMEA also documents the rationale for the chosen

    manufacturing process. It provides for an organized critical analysis of potential failure modes and the

    associated causes for the system being defined. The technique uses occurrence and detection probabilities in

    conjunction with severity criteria to develop a risk priority number (RPN) for ranking corrective action

    considerations.

    The FMEA can be performed as either a hardware or functional analysis. The hardware approach requiresparts identification from engineering drawings (schematics, bill of materials) and reliability performance data,

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    2/9

    International Conference on Technology and Business Management March 26-28. 2012

    502

    for example mean time between failures (MTBF), and is generally performed in a part-level fashion (bottom-

    up). However, it can be initiated at any level (component/assembly/subsystem) and progress in either direction

    (up or down).

    Typically, the functional approach is used when hardware items have not been uniquely identified or when

    system complexity requires analysis from the system level downward (top-down). This normally occurs during

    the design development stages of the equipment life cycle; however, any subsystem FMEA can be performed at

    any time. Although FMEA analyses vary from hardware to software, and from components (i.e., integratedcircuits, bearings) to system (i.e., stepper, furnace), the goal is always the same: to design reliability into the

    equipment.

    Thus, a functional analysis to FMEA on a subassembly is appropriate to use as a case study for the purposes of

    this guideline.

    When to perform FMEA

    Equipment Life CycleThe recommended method for performing an FMEA is dictated by the equipment life cycle. The early

    stages of the equipment life cycle represent the region where the greatest impact on equipment

    reliability can be made.

    Total QualityFMEA is recommended along with Process Analysis Technique, Design of Experiments and Fault TreeAnalysis, as a part of quality assurance that a company should use systematically for total quality

    control. All indicators from the total quality management perspective and from examination of the

    equipment life cycle tell us that the FMEA works best when conducted early in the planning stages of

    the design.

    What does it contain?

    An FMEA covering the complete system (which may include FMEAs of various subsystem manufacturers)

    should encompass those FMEAs by a review and an analysis of the interfaces between the subsystems. An

    FMEA should contain a practical test programme and the results from those tests.

    Who carries out an FMEA?

    An FMEA team should be well knowledge of the each system. They are specialist having discipline in each

    system required in design process. For example, machinery systems, electrical systems, DP control systems and

    other control systems.

    4. Process ImprovementFMEA is done in any equipment. In this process, to identify the possible failure modes and find the effect of this

    failure to the equipment. To prevent this failure, possible changes in design and improvement can be made. This

    identification of potential failure mode leads to a recommendation of effective reliability program.

    Mainly failure mode can be set according to the FMEAs Risk Priority Number (RPN) system. A concentrated

    effort can be placed on the higher RPN items based on the Pareto analysis obtained from the analysis. As the

    equipment proceeds through the life cycle phases, the FMEA analysis becomes more detailed and should be

    continued. The FMEA consist of following steps:

    FMEA Prerequisites Functional Block Diagram Failure mode analysis and preparation of work sheets Team Review Corrective action

    R.R. -Review Requirements

    R.F.D. - Review FRACAS Data

    G.S.D.- Get System Description

    F.B.D.- Functional Block Diagram

    D.F.M. - Dtermine Failure Mode

    C.P.- Changes Proposed?

    C.A.R.- Corrective Action Required

    N.C.R.- No Change RequiredR.E.- Reliable Equipment

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    3/9

    International Conference on Technology and Business Management March 26-28. 2012

    503

    Figure 1 Steps of FMEA

    5. FMEA ProcessesFMEA Pre-requisites

    Review specifications such as the statement of work (SOW) and the system requirement document(SRD).

    Collect all available information that describes the subassembly to be analyzed. Systems engineeringcan provide system configuration

    Compile information on earlier/similar designs from in-house/customer users such as data flowdiagrams and reliability performance data from the company's failure reporting, analysis and corrective

    action system (FRACAS).

    The above information should provide enough design detail to organize the equipment configuration to the

    level required for analysis.

    Functional Block Diagram

    This diagram shows how different parts are interact to each other to verify the critical path. It is easy to

    understand relations of the parts.

    The recommended way to analyze the system is to break it down to different levels (i.e., system, subsystem,

    subassemblies, and field replaceable units). Review schematics and other engineering drawings of the system

    being analyzed to show how different subsystems, assemblies or parts interface with one another by their critical

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    4/9

    International Conference on Technology and Business Management March 26-28. 2012

    504

    support systems such as power, plumbing, actuation signals, data flow, etc. to understand the normal functional

    flow requirements.

    Failure Mode Analysis and Preparation of Work Sheets

    Determine the Potential Failure ModeAnswer of asking simply question determines the failure. Thats the simple question is What can go

    wrong? Subassembly examples of failure modes Assembly examples of failure modes Manufacturing/Process examples of failure modes Component examples of failure modes

    The Reliability Analysis Centre (RAC) has developed a document designed solely to address

    component failure mechanisms and failure mode distributions for numerous part types including

    semiconductors, mechanical and electromechanical components.

    Determine the Potential Effects of the Failure ModeThe potential effects for each failure mode need to be identified both locally (subassembly) and

    globally (system). Customer satisfaction is key in determining the effect of failure mode. Safety

    criticality is also determined at this time based on Environmental Safety and Health (ES & H) levels.Based on this information, a severity ranking is used to determine the criticality of the failure mode on

    the subassembly to the end effect.

    Determine the Potential Cause of the FailureMost probable causes associated with potential failure modes. As a minimum, examine its relation to:

    Preventive maintenance operation Failure to operate at a prescribed time Intermittent Operation Degraded output or operational capability Design causes

    Determine Current Controls/Fault DetectionMany organizations have design criteria that help prevent the causes of failure modes through their

    design guidelines. Checking of drawings prior to release, and prescribed design reviews are paramount

    to determining compliance with design guidelines.

    Detection methods are - Local hardware concurrent with operation, downstream or at a higher level,

    Built-in test (BIT), Application software exception handling, Time-out, Visual methods, Alarms.

    After the detection by previous method, determining the recovery method is another part. Recovery

    methods are- Retry, Re-load and retry, Alternate path or redundancy, Degraded, Repair and restart.

    Determining the Risk Priority Number (RPN)RPN is the indicator for the determining proper corrective action on the failure modes. It is calculated

    by multiplying the severity, occurrence and detection ranking levels resulting in a scale from 1 to 1000.RPN = Severity Occurrence Detection

    The small RPN is always better than the high RPN. A Pareto analysis is based on the RPN. In this all

    the possible failure modes, effects and causes are determined. High RPN is gives idea for corrective

    action on failure mode.

    The engineering team generates the RPN and focused to the solution of failure modes. After findingsolution, improvements can be made.

    Rating Scale Example:

    If Severity = 10, indicates that the effect is very serious and is worse than Severity = 1.

    If Occurrence = 10, indicates that the likelihood of occurrence is very high and is worse than

    Occurrence = 1.

    If Detection = 10, indicates that the failure is not likely to be detected before it reaches the end user is

    worse than Detection =1.

    An RPM is comparable to other RPMs in the same analysis, but an RPM is not comparable to RPNs

    in another analysis. Because similar RPNs can result in several different ways and represents different

    types of risk.

    Preparation of FMEA WorksheetsAction takes tasks recommended for the purpose of reducing any or all of the rankings. Only designrevision can be bringing about the revision in the severity ranking.

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    5/9

    International Conference on Technology and Business Management March 26-28. 2012

    505

    Actions All critical or significant characteristics must have recommended actions associated

    with them

    Recommended actions should be focused on design, and directed toward mitigatingthe cause of failure, or eliminating the failure mode

    If recommended actions cannot mitigate or eliminate the potential for failure,recommended actions must force characteristics to be forwarded to process FMEAfor process mitigation

    All recommended actions must have a person assigned responsibility for completionof the action

    Responsibility should be a name, not a title Person listed as responsible for an action must also be listed as a team member There must be a completion date accompanying each recommended action Unless the failure mode has been eliminated, severity should not change Occurrence may or may not be lowered based upon the results of actions Detection may or may not be lowered based upon the results of actions If severity, occurrence or detection ratings are not improved, additional

    recommended actions must to be defined.

    WorksheetTable 1 Work Sheet of FMEA

    SourceBook of Quality and Reliability Management by Lalit Wankhede

    DescriptionItem/Function Name or concise statement of function performed by the equipment.

    Potential Failure Mode- A answer of asking simply question determines the failure.

    Potential Local Effect(s) of Failure subassembly consideration.

    SEV Severity ranking.

    Class - A safety critical failure mode.

    Potential Cause(s)/ Mechanism(s) of Failure - Most probable causes associated with

    potential failure modes.

    Occur- Occurrence ranking based on the probability of failure.

    Current Design Controls- methods of prevention and detection.

    Detect- Detection ranking based on the probability of detection.

    RPN- Risk Priority Number.

    Recommended Actions Action recommended to reduce the possibility of occurrence of thefailure mode, reduce the severity (based on a design change) if failure mode occurs, or

    improve the detection capability should the failure mode occur.

    Response and Target Complete Date- This area lists the person responsible for evaluation

    of the recommended actions. Besides ownership, it provides for accountability by assigning a

    completion date.

    Actions Taken Following completion of a recommended action, the FMEA provides for

    closure of the potential failure mode.

    SEVFollowing recommended corrective action.

    OCCFollowing recommended corrective action.

    DETFollowing recommended corrective action.

    RPNFollowing recommended corrective action.

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    6/9

    International Conference on Technology and Business Management March 26-28. 2012

    506

    6. Team ReviewThe engineering team suggested comments and review the worksheet to consider the failure modes based upon

    RPNs. Engineering team determines potential problems, identify possible changes in design, data fill in the

    worksheet etc. are updated. The worksheets need to reflect the changes until final design of equipment. When

    the design is finalized, the worksheets are then distributed to the users, design engineering, technical support and

    manufacturing. The worksheets may also provide information to other engineering areas.

    Team members for FMEA Process engineer Manufacturing supervisor Operators Quality Safety Product engineer Customers Suppliers

    7. Corrective ActionDesign Engineering

    Design engineering uses the completed FMEA worksheets to identify and correct potential design relatedproblems. This is where the FMEA becomes the basis for continuous improvement.

    Technical Support

    From the FMEA worksheets, the engineering team can suggest a statistically based preventive maintenance

    schedule based on the frequency and type of failure. A spares provisioning list can also be generated from the

    worksheet.

    Manufacturing

    From the FMEA worksheets, the team could suggest a process be changed to optimize installations, acceptance

    testing, etc. This is done because the sensitivities of the design are known and documented. The selection of

    suppliers can be optimized as well. FMEA can be a way to communicate design deficiencies in the

    manufacturing of the equipment.

    8. Ranking Criteria for FMEASeverity Ranking Criteria

    Calculating the severity levels provides for a classification ranking that encompasses safety, production

    continuity, scrap loss, etc. It determines how affect the potential failure mode to the customers. Only applies to

    the effect and is assigned with regard to any other rating.

    Table 2 Severity Ranking Criteria

    Effect Rank Criteria

    None 1 No effect

    Very Slight 2 Negligible effect on Performance. Some users may notice.

    Slight 3 Slight effect on performance. Non vital faults will be noticed by many users.

    Minor 4 Minor effect on performance. User is slightly dissatisfied.

    Moderate 5 Reduced performance with gradual performance degradation. User dissatisfied.

    Severe 6 Degraded performance, but safe and usable. User dissatisfied.

    High Severity 7 Very poor performance. Very dissatisfied user.

    Very High Severity 8 Inoperable but safe.

    Extreme Severity 9 Probable failure with hazardous effects. Compliance with regulation is unlikely.

    Maximum Severity 10 Unpredictable failure with hazardous effects almost certain. Non-compliant with regulations.

    SourceBook of Quality and Reliability Management by Lalit Wankhede.

    Environmental, Safety and Health Severity CodeThe Environmental Safety and Health (ES&H) severity code is a qualitative means of representing the

    worst case incident that could result from an equipment or process failure or for lack of a contingencyplan for such an incident.

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    7/9

    International Conference on Technology and Business Management March 26-28. 2012

    507

    Occurrence Ranking Criteria

    The probability that a failure will occur during the expected life of the system can be described in potential

    occurrences per unit time.

    Table 3 Occurrence Ranking Criteria

    Occurrence Rank Criteria

    Extremely Unlikely 1 Less than 0.01 per thousand

    Remote Likelihood 2 0.1 per thousand rate of occurrence

    Very Low Likelihood 3 0.5 per thousand rate of occurrence

    Low Likelihood 4 1 per thousand rate of occurrence

    Moderately Low Likelihood 5 2 per thousand rate of occurrence

    Medium Likelihood 6 5 per thousand rate of occurrence

    Moderately High Likelihood 7 10 per thousand rate of occurrence

    Very High Severity 8 20 per thousand rate of occurrence

    Extreme Severity 9 50 per thousand rate of occurrence

    Maximum Severity 10 100 per thousand rate of occurrence

    SourceBook of Quality and Reliability Management by Lalit Wankhede

    Detection Ranking Criteria

    This section provides a ranking based on an assessment of the probability that the failure mode will be detected

    given the controls that are in place. The probability of detection is ranked in reverse order.

    Table 4Detection Ranking Criteria

    Detection Rank Criteria

    Extremely Likely 1 Can be corrected prior to prototype/ Controls will almost certainly detect

    Very High Likelihood 2 Can be corrected prior to design release/Very High probability of detection

    High Likelihood 3 Likely to be corrected/High probability of detection

    Moderately High Likelihood 4 Design controls are moderately effective

    Medium Likelihood 5 Design controls have an even chance of working

    Moderately Low Likelihood 6 Design controls may miss the problem

    Low Likelihood 7 Design controls are likely to miss the problem

    Very Low Likelihood 8 Design controls have a poor chance of detection

    Very Low Likelihood 9 Unproven, unreliable design/poor chance for detection

    Extremely Unlikely 10 No design technique available/Controls will not detect

    SourceBook of Quality and Reliability Management by Lalit Wankhede

    9. Case StudyPerform FMEA on a Pressure Cooker

    Figure 2 Pressure Cooker

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    8/9

    International Conference on Technology and Business Management March 26-28. 2012

    508

    Pressure Cooker Safety Features

    Safety valve relieves pressure before it reaches dangerous levels. Thermostat opens circuit through heating coil when the temperature rises above 250 C.

    Scope of FMEA for Pressure Cooker

    Resolution - The analysis will be restricted to the four major subsystems (electrical system, safetyvalve, thermostat, and pressure gage).

    Focus SafetyBlock Diagram of Pressure Cooker

    Figure 3Block Diagram Pressure Cooker

    Table 5 FMEA is shown in Table

    ComponentFailure

    Mode

    Effects on

    other

    Components

    Effects on

    whole

    System

    Consequence

    Category

    Failure

    Likelihood

    Detection

    Method

    Compensating

    Provisions

    Pressure

    relief valve

    Jammed

    open

    Increased gas

    flow and

    thermostat

    operation

    Loss of hot

    water, more

    cold water

    input and

    gas

    I - SafeReasonably

    probable

    Observe at

    pressure

    relief valve

    Shut off water

    supply, reseal or

    replace relief

    valve

    Jammed

    closedNone None I - Safe Probable

    Manual

    testing

    No conseq.

    unless combined

    with other

    failure modes

    Gas valveJammed

    open

    Burner

    continues to

    operate,

    pressure relief

    valve opens

    Water temp.

    and pressure

    increase;

    water turns

    to steam

    III - CriticalReasonably

    probable

    Water at

    faucet too

    hot;

    pressure

    relief valve

    open (obs.)

    Open hot water

    faucet to relieve

    pres., shut off

    gas; pressure

    relief valve

    compensates

  • 7/22/2019 FMEA for Manufacturing and Assembly Process

    9/9

    International Conference on Technology and Business Management March 26-28. 2012

    509

    Jammed

    closed

    Burner ceases

    to operate

    System fails

    to produce

    hot water

    I - Safe Remote

    Observe at

    faucet

    (cold

    water)

    Thermostat

    Fails to

    react to

    temp.

    rise

    Burner

    continues to

    operate,

    pressure relief

    valve opens

    Water temp.

    rises; water

    turns to

    steam

    III - Critical Remote

    Water at

    faucet too

    hot

    Open hot waterfaucet to relieve

    pressure;

    pressure relief

    valve

    compensates

    Fails to

    react to

    temp.

    drop

    Burner fails to

    function

    Water

    temperature

    too low

    I - Safe Remote

    Observe at

    faucet

    (cold

    water)

    10.ConclusionThe failure modes included in the FMEA are the failures anticipated at the design stage. As such, they could be

    compared with Failure Reporting, Analysis and Corrective Action System (FRACAS) results once actual

    failures are observed during test, production and operation. Take appropriate steps to avoid either possibility.

    11.References1. B.G. Dale and P. Shaw, Failure Mode and Effects Analysis in the U.K. Motor Industry: A State-of-Art

    Study, Quality and Reliability Engineering International,Vol. 6, 184, 1990.2. Mario Villacourt, Failure Mode and Effects Analysis (FMEA), Technology Transfer #92020963B-

    ENG SEMATECH September 30, 1992.3. Texas Instruments Inc. Semiconductor Group, FMEA Process, June 1991 Ciraolo, Michael,

    Software Factories: Japan, Tech Monitoring by SRI International,April 1991, pp. 15.4. Matzumura, K., Improving Equipment Design Through TPM, The Second Annual Total Productive

    Maintenance Conference: TPM Achieving World Class Equipment Management, 1991.

    5. Lalit Wankhede Quality and reliability management.6. BSI Standard, BS 5760-5:1991: 'Reliability of Systems, Equipment andComponents', Part 5: 'Guide to

    Failure Modes, Effects and Criticality Analysis(FMEA and FMECA).7. IEC Standard, IEC 60812: 'Analysis Techniques for System Reliability Procedure for Failure Mode

    and Effects Analysis (FMEA).

    8. CEI/IEC812 Analysis techniques for system reliability - Procedure for failure modes and effectsanalysis (FMEA).

    9. IMO MSC Resolution 36(63) Annex 4 Procedures for Failure Mode and Effects Analysis (HSCCode).

    10. Analysis techniques for system reliability - Procedure for failure modes and effects analysis (FMEA) -CEI/IEC 812:1985.