Flow Chart– Internal NCR No ZGC QAQC RESPONSIBILITIES START Report, Prepare Reviewed & Approved to Issue? (Yes) ZGC Stamp, Date, Signed ,Recipient Decision Registers, Distributed to Subcontractor Submit Corrective/Preventive Action (Within 6 days) Checked & Received Copies for Recipients Decision Reviewed & Released with Status Code –Open or Closed for Subcontractor Necessary Action Registers, Distribution END ZGC Project Manager ZGC Document Controller ZGC Project Manager/QAQC ZGC Document Controller/ Sub Contractor’s PM ZGC Project Manager/QAQC ZGC /Document Controller ZGC Project Manager Any Related Cost, Lost Time? If yes – Fill - ZGC-QA-FM0007- Rev00 –Quality Violation Notice QVN Sub Contractor’s PM

description

p

Transcript of Flow Chart-3. Internal NCR

Page 1: Flow Chart-3. Internal NCR

Flow Chart– Internal NCR

No

ZGC QAQC

RESPONSIBILITIESSTART

Report, Prepare

Reviewed & Approved to Issue?

(Yes)

ZGC Stamp, Date, Signed ,Recipient Decision

Registers, Distributed to Subcontractor

Submit Corrective/Preventive Action

(Within 6 days)

Checked & Received

Copies for Recipients Decision

Reviewed & Released with Status Code –Open or Closed for

Subcontractor Necessary Action

Registers, Distribution

END

ZGC Project Manager

ZGC Document Controller

ZGC ProjectManager/QAQC

ZGC Document Controller/

Sub Contractor’s PM

ZGC Project Manager/QAQC

ZGC /Document Controller

ZGC Project Manager

Any Related Cost, Lost Time? If yes – Fill - ZGC-QA-FM0007-Rev00 –Quality Violation

Notice QVNSub Contractor’s PM