Florida Product Approval System 2008 Rule 9B-72 Changes
description
Transcript of Florida Product Approval System 2008 Rule 9B-72 Changes
Florida Product Approval Florida Product Approval SystemSystem
2008 Rule 9B-72 Changes2008 Rule 9B-72 Changes
Florida Building Commission Florida Building Commission Florida Department of Community AffairsFlorida Department of Community Affairs
2555 Shumard Oak Blvd | Tallahassee, FL 32399-2100 | (850) 487-1824
www.floridabuilding.org
Florida Product Approval SystemFlorida Product Approval SystemDepartment of Community Affairs Product Approval Department of Community Affairs Product Approval
TeamTeam
Recent Product Approval Recent Product Approval ChangesChanges
Ted Berman and Associates, LLCTed Berman and Associates, LLC
THEODORE BERMAN, P.E.THEODORE BERMAN, P.E.Product Approval System AdministratorProduct Approval System Administrator
SIMON SEGAL, P.E.SIMON SEGAL, P.E.Assistant Engineer, Assistant Engineer, Product Application Product Application ReviewReview
JESSICA HUPPERTAdministrative Officer
VERDA LA RUEVERDA LA RUEProduct Approval, Product Approval, Process Support Process Support SpecialistSpecialist
Recent Product Approval Recent Product Approval ChangesChanges
Florida Building Code 2007Florida Building Code 2007
• The 2007 Florida Building Code is now available online.
•http://www2.iccsafe.org/states/Florida2007FinalDraft/• The Effective Date for 2007 Code is October 1, 2008
Recent Product Approval Recent Product Approval ChangesChanges
Florida Building Code 2007Florida Building Code 2007
There are three ways to have your product comply with the new code
• Self-Affirmation of existing application
• Revision of existing application• New application
Recent Product Approval Recent Product Approval ChangesChanges
Self–Affirmation FBC 2007Self–Affirmation FBC 2007
Application Self Affirmation Upon review of the new Code, if the standards and restrictions in the new Code applicable to your product have not changed, you can “self-affirm” that your product complies with applicable standards of the new Code. Please contact the Product Approval Administrator Ted Berman And Associates before initiating a self-affirmation Self Affirmations cost $50.
Recent Product Approval Recent Product Approval ChangesChanges
Revision FBC 2007Revision FBC 2007
Application Revision:• If the standards or restrictions pertaining to your product in the 2007 Code have changed, then a product revision application must be submitted.• New evidence such as a test report or an evaluation report demonstrating compliance must also be submitted.•Revisions cost $300.
Recent Product Approval Recent Product Approval ChangesChanges
Revision FBC 2007Revision FBC 2007
IMPORTANTIF THERE ARE MULTIPLE PRODUCTS WITHIN THE SAME APPLICATION (FL#), THEN EVIDENCE FOR ALL THE PRODUCTS MUST BE SUBMITTED. THE ENTIRE PRODUCT LINE MUST ALSO COMPLY WITH THE NEW STATE PRODUCT APPROVAL RULE AND ALL THE REQUIREMENTS THEREIN
Recent Product Approval Recent Product Approval ChangesChanges
New Application ProcessNew Application Process
Changes made to the new application Changes made to the new application process include:process include:
There is now There is now ONE COMPLETION DEADLINEONE COMPLETION DEADLINE No more recommendation for Conditional Approval or No more recommendation for Conditional Approval or
Deferral by the Administrator.Deferral by the Administrator. Applicants work at their own pace to complete Applicants work at their own pace to complete
applications by the posted deadline date. applications by the posted deadline date. Early submittals will have more correction time if needed.Early submittals will have more correction time if needed. Once validated, Ted Berman and Associates, LLC review Once validated, Ted Berman and Associates, LLC review
the application and email the applicant notifying them of the application and email the applicant notifying them of any discrepancies.any discrepancies.
Only those applications that are complete and reviewed Only those applications that are complete and reviewed by the Deadline are recommended to the Product by the Deadline are recommended to the Product Oversight Committee (POC) and be listed on the meeting Oversight Committee (POC) and be listed on the meeting agendaagenda
Recent Product Approval Recent Product Approval ChangesChanges
New Application ProcessNew Application Process
Before submittal, verify the following:Before submittal, verify the following: Verify that the product is Florida Building Code CompliantVerify that the product is Florida Building Code Compliant Manufacturer’s name on the BCIS matches the name on Manufacturer’s name on the BCIS matches the name on
the Certification Agency Certificate.the Certification Agency Certificate. Model size and performance is an exact match with Model size and performance is an exact match with
uploaded Certification Agency Certificate.uploaded Certification Agency Certificate. Installation Documents are attached.Installation Documents are attached. On Limitations of use for each model define: use within On Limitations of use for each model define: use within
HVHZ or outside HVHZ; impact, design rating, missile level HVHZ or outside HVHZ; impact, design rating, missile level and any other pertinent information.and any other pertinent information.
Testing standards and year of standard as certified by Testing standards and year of standard as certified by Certification Agency. If testing standards are not adopted Certification Agency. If testing standards are not adopted in the version of the Florida Building Code, an equivalency in the version of the Florida Building Code, an equivalency of standards will be required.of standards will be required.
Recent Product Approval Recent Product Approval ChangesChanges
Product Approval MethodsProduct Approval Methods
Four Methods for State ApprovalFour Methods for State Approval Certification MethodCertification Method Test ReportTest Report Evaluation Report from an Evaluation EntityEvaluation Report from an Evaluation Entity Evaluation Report from a Florida licensed Evaluation Report from a Florida licensed
Architect or a Florida Professional EngineerArchitect or a Florida Professional Engineer
Recent Product Approval Recent Product Approval ChangesChanges
RULE 9B – 72 changesRULE 9B – 72 changes
9B – 72.0109B – 72.010(31)(31)(f)For shutters:(f)For shutters:
Shutters subcategory has been expanded to add fabric Shutters subcategory has been expanded to add fabric storm panel.storm panel.
9B – 72.0709B – 72.070(1)(g)Demonstration of Compliance:(1)(g)Demonstration of Compliance:
Products required to demonstrate compliance using referenced testing standard(s) and Products required to demonstrate compliance using referenced testing standard(s) and also requiring rational analysis that falls outside the scope of the agency certificate also requiring rational analysis that falls outside the scope of the agency certificate designating product certification, must demonstrate compliance using an evaluation designating product certification, must demonstrate compliance using an evaluation report from an approved evaluation entity.report from an approved evaluation entity.
ValidationsValidations
9B-72.080 Product Validation9B-72.080 Product ValidationTwo Types of ValidationTwo Types of Validation
Administrative ValidationAdministrative Validation Technical ValidationTechnical Validation
NOTE:The validation process has been added to Certification Mark or Listing method on the Florida State Product Approval System
Administrative ValidationAdministrative Validation
Applicable to:Applicable to: A certification mark or listing from an A certification mark or listing from an
approved certification agencyapproved certification agency An evaluation report from a Florida An evaluation report from a Florida
Registered Architect or Licensed Engineer Registered Architect or Licensed Engineer independent from the manufacturerindependent from the manufacturer
An evaluation report from an approved An evaluation report from an approved evaluation entity (i.e. ICC)evaluation entity (i.e. ICC)
Recent Product Approval Changes
Administrative Validation Administrative Validation CriteriaCriteria
Criteria consists of:Criteria consists of: Verification of certification, certification agency Verification of certification, certification agency
status, product description, testing standards status, product description, testing standards per Florida Building Code and compliance per Florida Building Code and compliance documentation with the current code.documentation with the current code.
Verification of installation instructions, Verification of installation instructions, anchorage requirements and product anchorage requirements and product performance under certification.performance under certification.
Verification of any limits of use included as Verification of any limits of use included as certified and use of rational analysis within certified and use of rational analysis within the scope of certificationthe scope of certification
Administrative ValidationAdministrative ValidationChecklistChecklist
Administrative ValidationAdministrative ValidationChecklistChecklist
Administrative ValidationAdministrative ValidationOverviewOverview1a.
Certification: Certificate, Mark
Or Listing
1c.Evaluation report from evaluation
entity ie. ICC
1d.Evaluation
report from an architect or
engineer
EVALUATIONREPORT
3rd PARTY
ADMINVALIDATION
Technical ValidationTechnical Validation
Applicable to:Applicable to: A test report from an approved testing A test report from an approved testing
laboratorylaboratory An evaluation repot from an approved An evaluation repot from an approved
evaluation entity that is not an evaluation entity that is not an independent third party from the independent third party from the manufacturermanufacturer
Recent Product Approval Changes
Technical Validation Technical Validation CriteriaCriteria
In addition to criteria for In addition to criteria for Administrative Validation, Technical Administrative Validation, Technical validation includes:validation includes: Determination that the evaluator has Determination that the evaluator has
complied with acceptable standards of complied with acceptable standards of engineering principles.engineering principles.
Engineering verification that the Engineering verification that the evaluation complies with the Code.evaluation complies with the Code.
Copy of the application complying with all Copy of the application complying with all aspects of rule 61G15-36 F.A.C. must be aspects of rule 61G15-36 F.A.C. must be filed with the Commission.filed with the Commission.
Technical ValidationTechnical ValidationChecklistChecklist
Technical ValidationTechnical ValidationChecklistChecklist
Technical ValidationTechnical ValidationOverviewOverview
1d.Evaluation
report from an architect or
engineer
EVALUATIONREPORT
IN HOUSE
TECHNICALVALIDATION
1b.Test
report
Installation InstructionsInstallation Instructions
Installation instructions also Installation instructions also require validation:require validation:
If prepared by company engineers then If prepared by company engineers then technical validation is requiredtechnical validation is required
If prepared by independent engineers If prepared by independent engineers then administration validation is requiredthen administration validation is required
Recent Product Approval Recent Product Approval ChangesChanges
Installation InstructionsInstallation Instructions
Installation instructions criteria:Installation instructions criteria: Determination that the evaluator has complied with Determination that the evaluator has complied with acceptable standards of engineering principles.acceptable standards of engineering principles. Engineering verification that the evaluation complies Engineering verification that the evaluation complies with the Code.with the Code. Copy of the application complying with all aspects of Copy of the application complying with all aspects of rule 61G15-36 F.A.C. must be filed with the Commission.rule 61G15-36 F.A.C. must be filed with the Commission.Exception:Exception:
Technical Validation is not required if the installation Technical Validation is not required if the installation instructions including attachments are verified by instructions including attachments are verified by the product certification agency or the product the product certification agency or the product evaluation agency.evaluation agency.
WindowsWindows
Installation instructions requirements Installation instructions requirements for windows must contain the following:for windows must contain the following:
Type, and grade of anchor, and/or Type, and grade of anchor, and/or manufacturer’s anchor specifications, manufacturer’s anchor specifications, including minimal nominal size, minimum including minimal nominal size, minimum penetration into substrate and minimum edge penetration into substrate and minimum edge distances.distances.
Type, physical dimensions, material and grade Type, physical dimensions, material and grade of any accessory item or strap, if applicable.of any accessory item or strap, if applicable.
Spacing of anchors, shims, accessory items Spacing of anchors, shims, accessory items and straps. and straps.
Illustrated diagrams of the attachment of the Illustrated diagrams of the attachment of the product structure. product structure.
RULE 9B – 72 OptionalRULE 9B – 72 OptionalState Approval with updatesState Approval with updates
INSTALLATION INSTRUCTIONS
3rd PARTY
IN HOUSE
TECHNICALVALIDATION
ADMINVALIDATION
REVIEW BY CERT AGENCY
Validation EntitiesValidation Entities
All approved Validation Entities All approved Validation Entities must retain documentation of must retain documentation of the product applicationthe product application
Testing Labs are not allowed to Testing Labs are not allowed to conduct validationsconduct validations
Quality Assurance ExpirationQuality Assurance Expiration
For all the methods of compliance, For all the methods of compliance, including the certification Mark or Listing including the certification Mark or Listing Method, a new field is added to collect the Method, a new field is added to collect the Expiration Date of the Quality Assurance Expiration Date of the Quality Assurance Entity Contract on Page 3 of the applicationEntity Contract on Page 3 of the application
An email is sent to the Manufacturer with a An email is sent to the Manufacturer with a copy to DCA when the Expiration Date has copy to DCA when the Expiration Date has elapsed.elapsed.
Search criteria on the Product Search Search criteria on the Product Search webpage allows searching for expired webpage allows searching for expired Quality Assurance Entity Contracts.Quality Assurance Entity Contracts.
BCIS HomepageBCIS Homepage
New order of compliance method
BCIS HomepageBCIS Homepage
New validation for certification method
BCIS HomepageBCIS Homepage
New QA contract expiration date
BCIS HomepageBCIS Homepage
New evaluation by third party/rational analysis criteria
Florida Building Code 2007Florida Building Code 2007
Important Code Changes Products to be Labeled:
Exterior Windows and Glass Doors Garage Doors, Skylights
Recent Product Approval Recent Product Approval ChangesChanges
Skylights(1714.5.2.1.1), Exterior Skylights(1714.5.2.1.1), Exterior Windows And Glass Doors(1714.5)Windows And Glass Doors(1714.5)
Skylights, Exterior Windows and Glass Doors Required Labels:
Permanent Label Temporary Label
Recent Product Approval Recent Product Approval ChangesChanges
Skylights(1714.5.2.1.1), Exterior Skylights(1714.5.2.1.1), Exterior Windows And Glass Doors(1714.5)Windows And Glass Doors(1714.5)
Permanent Label: Permanent label is a label that cannot be
removed without noticeable damage: It is limited to one design pressure rating
per reference standard per label. Permanent label shall identify: the manufacturer performance characteristics Product’s model/series number Approved product certification agency, testing lab,
evaluation entity or Miami-Dade Product Approval to indicate compliance with the relevant standards
Recent Product Approval Recent Product Approval ChangesChanges
Skylights(1714.5.2.1.1), Exterior Skylights(1714.5.2.1.1), Exterior Windows And Glass Doors(1714.5)Windows And Glass Doors(1714.5)
Temporary Supplemental Label: Temporary Label has to be printed and
supplied by the manufacturer and shall identify:
the manufacturer products model/series number, positive and negative design pressure rating, products maximum size, glazing thickness, indicate impact rated if applicable, Florida Product Approval number or Miami-Dade Product
Approval number if applicable, and applicable test standard.
The supplemental label is limited to one design pressure rating per reference standard per label.
Recent Product Approval Recent Product Approval ChangesChanges
Skylights(1714.5.2.1.1), Exterior Skylights(1714.5.2.1.1), Exterior Windows And Glass Doors(1714.5)Windows And Glass Doors(1714.5)
NOTE:PERMANENT LABEL SHALL BECOME THE DEFAULT IF THE TEMPORARY LABEL IS MISSING OR NO LONGER LEGIBLE
Recent Product Approval Recent Product Approval ChangesChanges
1714.5.3.4 Garage Door Labeling1714.5.3.4 Garage Door Labeling
Garage Door Permanent Label shall identify the manufacturer, garage door model/series number, the positive and negative design pressure rating, indicate impact rated if applicable, the installation instruction drawing reference number, Fl. Product Approval number or Miami-Dade Product
Approval if applicable, and the applicable test standards. Label may also contain in a checklist format required
garage door components for an approved garage door assembly.
1714.8 Impact-1714.8 Impact-Resistant CoveringsResistant Coverings
• 1714.8.3 Location of Label:• Accordion: Bottom of locking bar or center mate facing exterior
• Permanent Label is required.• 1714.8.2 Following information to be included on the label:
• Product approval name and address• Methods of approval e.g. FBC, Miami-Dade (M-D), TDI Evaluation and ICC-ES• Applicable standards• For FBA and M-D, the FL # or the NOA #
1714.8 Impact-1714.8 Impact-Resistant CoveringsResistant Coverings
• 1714.8.3 Location of Label:• Rollup: On the bottom of the hood facing the exterior or on the bottom slat facing the exterior or outside• Bahama Awning or Colonial Hinged: On the bottom, placed on the back of the shutter.• Panels: For metal and plastic panels the label may be embossed or printed spaced not more than every three lineal feet on each panel. The label shall be applied by the holder of the product approval and shall face the exterior. • Framed products: The label shall be on the side or bottom facing the exterior.• Labels on all other products shall face the exterior.
1714.8 Impact-1714.8 Impact-Resistant CoveringsResistant Coverings
• 1714.8.4 Installation:• In accordance with manufacturer’s instructions, which shall be provided and be available to inspectors.• Opening protection components including fasteners evaluated by an approved authority may be interchangeable if they provide equal or greater structural performance and durability
F.A.Q.’sF.A.Q.’s
I have a new product that meets 2004 and 2007 codes, which code do I apply for?
Apply for 2004 and self-affirm for 2007
The person with authorized signature on the application no longer works for us? What do I do?
If you are going to self-affirm, you can first submit an editorial revision. If you are going to revise anyway, you can change the authorized signature with the revision
F.A.Q.’sF.A.Q.’s
I lost my username and password?Contact Department of Community
Affairs with an email from either the email registered with the application or from the President or Vice-President of the Company
The page loads with an error? What do I do?Norton / Symantec Firewalls do not like
your Product to be approved. Turn the Firewalls off.
F.A.Q.’sF.A.Q.’s
I am submitted an entity application but I need to change something, can I do it?
If the status of your entity application is “pending accreditation”, you can still make changes to your application.
Mo MadaniMo MadaniDepartment of Community Affairs Department of Community Affairs Codes and StandardsCodes and [email protected]@dca.state.fl.us850.921.2247 (p) | 850.414.8436 850.921.2247 (p) | 850.414.8436 (f)(f)