Flooding Mitigation and Drainage renewal, Glenbrook, NSW

1
Drainage Renewal 19 Brook Rd, Glenbrook AWP 2011/12 (completed on June 2012) Project Cost: $ 114,250 Pipeline: - 525mm 66.5 lin meters Pit: - 4 Headwall: - 1 Detention Basin with Grated inlet pit: - 1 Kerb & Gutter: - 57 lin meters Driveway restoration: - 3 Turf restoration: - 70m 2 Pavement restoration: - 40m 2 February 2012 February 2012 June 2012 June 2012 June 2012 February 2012

Transcript of Flooding Mitigation and Drainage renewal, Glenbrook, NSW

Page 1: Flooding Mitigation and Drainage renewal, Glenbrook, NSW

Drainage Renewal – 19 Brook Rd, Glenbrook

AWP – 2011/12 (completed on June 2012)

Project Cost: $ 114,250

Pipeline: - 525mm – 66.5 lin meters

Pit: - 4

Headwall: - 1

Detention Basin with Grated inlet pit: - 1

Kerb & Gutter: - 57 lin meters

Driveway restoration: - 3

Turf restoration: - 70m2

Pavement restoration: - 40m2

February 2012 February 2012

March 2012 June 2012

June 2012

June 2012

February 2012