Flooding Mitigation and Drainage renewal, Glenbrook, NSW
1
Drainage Renewal – 19 Brook Rd, Glenbrook AWP – 2011/12 (completed on June 2012) Project Cost: $ 114,250 Pipeline: - 525mm – 66.5 lin meters Pit: - 4 Headwall: - 1 Detention Basin with Grated inlet pit: - 1 Kerb & Gutter: - 57 lin meters Driveway restoration: - 3 Turf restoration: - 70m 2 Pavement restoration: - 40m 2 February 2012 February 2012 June 2012 June 2012 June 2012 February 2012
-
Upload
mainur-rahman -
Category
Documents
-
view
75 -
download
0
Transcript of Flooding Mitigation and Drainage renewal, Glenbrook, NSW
Drainage Renewal – 19 Brook Rd, Glenbrook
AWP – 2011/12 (completed on June 2012)
Project Cost: $ 114,250
Pipeline: - 525mm – 66.5 lin meters
Pit: - 4
Headwall: - 1
Detention Basin with Grated inlet pit: - 1
Kerb & Gutter: - 57 lin meters
Driveway restoration: - 3
Turf restoration: - 70m2
Pavement restoration: - 40m2
February 2012 February 2012
March 2012 June 2012
June 2012
June 2012
February 2012