FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas...

46
FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council Project Completed for: U.S. Army Corps of Engineers and International Boundary and Water Commission Jim O’Brien FLO-2D Software, Inc.

Transcript of FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas...

Page 1: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

FLO-2D Model Development Rio Grande Canalization Project Reach

Presentation to:

New Mexico – Texas Water Commissionand

Paso del Norte Watershed CouncilProject Completed for:

U.S. Army Corps of Engineers andInternational Boundary and Water Commission

March 9, 2006 Jim O’BrienFLO-2D Software, Inc.

Page 2: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Project Purpose

The results of the FLO-2D model application will be used to support the development of the URGWOM model for the Rio Grande Canalization Project (RGCP) reach.

RGCP FLO-2D model will predict floodplain inundation, water surface elevation and levee inundation or overtopping associated with floodwave attenuation of return period flood events.

Page 3: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Project Components

• Hydrology Review

• Sediment Supply Review

• Field Data Collection Program

• FLO-2D Model Development

• Model Calibration and Application

Page 4: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Hydrologic Review

• Releases from Caballo Reservoir

• Design storm selection including point rainfall, distribution and depth-area reduction

• Application of the HEC-1 model including rainfall/runoff estimates, assumptions, selected parameters and results

Page 5: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Hydrology Review Results

• The combined probability of a 5,000 cfs release during the 100-yr flood is less than 1% on any given year. Used 2,350 cfs average irrigation release instead.

• The 100-yr, 24-hr general storm rainfall of 3.8 inches was verified with a frequency analysis of the Jornada Range and Hillsboro rain gage records.

• Parameter adjustments to the Corps 1996 RGCP HEC-1 rainfall runoff simulation resulted in higher tributary peak discharge that occurs further upstream.

Page 6: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Flood Hydrology

Two Possible Flood Scenarios

1. 5000 cfs release + 1996 Corps Study tributary flood inflows

2. Selected: 2,350 cfs release + revised 100-year 24-hr hydrology for tributary flood inflows ~ typical irrigation release

Page 7: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Return Period Flood Modeling

The various return period tributary flood inflows using the revised hydrology were simulated with the typical irrigation release of 2,350 cfs.

Return period floods were:

2-yr, 5-yr, 10-yr, 25-yr, 50-yr, 100-yr

Page 8: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Sediment Review Objective

Reviewed Corps’1996 Rio Grande Canalization Improvement Project, Volume 3, “Sedimentation Analysis from the Rio Grande Tributary Basins” and accompanying appendices

Page 9: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Only sediment supply to the RGCP reach

is the steep arroyo sediment Loading

Jim O’BrienTetra Tech, Inc.

Page 10: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Observations

• Upstream reservoirs and NRCS arroyo tributary retention dams have created a long term, historical sediment deficit in the river

• Channel incision in response to dredging

• Armoring of some reaches with local supply of coarse sediment from arroyos

Page 11: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Local Tributary Coarse Sediment Supply

Page 12: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Relatively high velocities over cobble/gravel bed

Page 13: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Two sources of coarse sediment: hillslope and tributary

Page 14: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Sediment Review Conclusions

• Evidence that there is a sediment deficit in the system

• Current tributary sediment supply may not sustain the existing channel morphology in response to future channel maintenance

Page 15: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Sediment Review Conclusions

• Corps study was an excellent approach to calculate the total RGCP sediment supply

• Corps study overestimated sediment yield for at least 7 of 20 study basins

• If sediment yield is overpredicted for the 20 study basins, the regressed relationship will overestimate the sediment yield for all basins

Page 16: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Sediment Review Conclusions (cont.)

• Most of the overestimated total load can be attributed to Colby adjustment factor based on wash load concentration and bed material size

• Selection of parameters, application of sediment transport equations and supercritical flow assumptions = overpredicted annual sediment yield

• Calibrate sediment total load computations to NRCS reservoir survey annual load

Page 17: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Sediment Yield from NRCS Reservoir Surveys

 Watershed NRCS Name

 Drainage Area

 Resurvey (yrs)

Average AnnualSediment Yield

Revised 2005 Average AnnualSediment Yield

Underwood Caballo #1 0.87 7.80 0.64 0.64

Wasson Caballo #2 1.30 13.10 1.31 0.20

South Salem Caballo #3 0.99 13.50 0.66 0.66

Apache ABM #1 3.42 7.20 0.87 0.87

Pena Blanca ABM #2 24.57 7.20 0.33 0.33

Mossman ABM #3 8.03 8.70 0.59 0.59

Bishop's Cap ABM #4 6.12 8.00 0.70 0.70

Fillmore Fillmore Arroyo #1 18.57 10.20 0.34 0.34

Salopek Fillmore Arroyo #2 0.72 10.20 0.35 0.35

Lower Fillmore Fillmore Arroyo #3 2.48 10.20 0.27 0.27

Tortugas #1 20.70 5.66 0.69 0.69

Tortugas #2 0.88 9.66 0.38 0.38

Dona Ana Doña Ana #1 6.90 14.80 0.66 0.77

North Fork Arroyo Doña Ana #2 2.20 13.00 0.15 0.15

Rodney Hatch Valley #5 2.10 9.10 1.55 0.91

Hatch Valley #5a Average 0.63 0.30

Hatch Valley #2 Std. Dev 0.38 0.31

Hatch Valley #3 0.51

Hatch Valley #6 0.19

AverageStd. Dev.

0.48

0.24

Page 18: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Sediment Yield Equation

• The equation for total sediment load QT

was of the form:

• QT = A1 + A2 Ab + A3 Log (Ab)

• where: A1, A2, and A3 are regression

coefficients and Ab is the basin area.

Page 19: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Sediment Load Adjustment

Sediment yield per unit area was plotted as f(basin area). A decreasing power function could be applied to adjust the sediment yield equation as function of the basin area. The derived adjustment equation was:

Fa = 5.69 * Ab (-0.3739)

where: Fa is the adjustment factor

Table 4. Page 8 Report

Page 20: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Recommendation

• Use the Dona County DTM to estimate the sediment yield in all the detention basins…might have to create an as-built surface to compare with.

Page 21: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Field Data Collection ProgramJune-July 2004 RGCP

Channel Cross Section Survey

• Surveyed 145 Cross Sections

• Monumented and verified with control

• Surveyed levee to levee in most cases

• Water surfaces for calibrations at moderate flows (< 2,000 cfs less than bankfull)

Page 22: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Cross Section Locations with 250 ft Grid System

Page 23: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

CROSS SECTIONS DTM VS GROUND SURVEY

Reference elevation for the bridge rating curve was different in the data base

Page 24: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

FLO-2D Model Development

• DTM Points/Images

• Establish FLO-2D Finitie Difference Grid System

• Channel Components

• Model DetailsInfiltration and EvaporationLevees and Hydraulic Structures

• Model Calibration

• Flood Results

Page 25: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Data BaseDTM PointsImagesChannel Cross Section SurveysCalibration Data – Inflow and Outflow

Discharge

All together – this comprises one of the best major river data bases ever assembled. The only difficulty was that there is so damn much of it.

Page 26: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

DTM Points

• Dona Ana County DTM • The DTM data base was selectively edited

along the floodplain• Compiled individual DTM images into 12

files• Each of the 12 files was imported into the

GDS and a grid system was overlaid• 12 grid systems were generated using

both high and low filters

Page 27: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

FLO-2D Grid System

Page 28: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Basic ‘Riada’ (Big Flood) Results

• Area of Inundation

• Flood hydrographs every 250 ft of channel

• Flood wave attenuation

• Levee deficiency and overtopping

Page 29: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Area of Inundation Maps

Maps in Report

Page 30: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Maximum Areas of Inundation

Table 4. Predicted Areas of Inundation

5,000 cfs Release – Original Flood

Hydrology(acres)

2,350 cfs Release – Revised Flood

Hydrology(acres)

Inflow Flood Volume (af-ft) 163,937 100,207

Maximum Wetted Floodplain 6100 6089

Maximum Wetted Channel Surface Area

3835 3761

Total Maximum Inundated Area 9935 9850

Page 31: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

2004 Water Surface Elevation Calibration Results

• Difference between measured and predicted water surface elevation ranged from -0.49 to +0.49 ft

• Average difference is 0.03 ft

Page 32: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Flood Hydrographs 2004 Calibration Results

Haydon Gage

Page 33: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

2004 Calibration Results

Leasburg Gage

Page 34: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

2004 Calibration Results

Mesilla Gage

Page 35: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

2004 Calibration Results

Anthony Gage

Page 36: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

100-yr Peak Discharge (cfs) vs River Mile

0

5000

10000

15000

20000

25000

0 20 40 60 80 100 120

River Miles Below Caballo Dam

Disch

arge (

cfs)

100-yr Flood 1996 HEC-2 Q (cfs)

FLO-2D Results - Original Hydrology

FLO-2D Results - Revised Hydrology

Floodwave Attenuation

Page 37: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Levee Freeboard Deficiency

Page 38: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Diversion Dam and Wasteway Operation During Flooding

SKIP THIS…unless people have questions

Page 39: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Diversion Dam Operation During Flooding

EBID – Percha and Leasburg diversion dams are weirs - no significant change. Open up the by-pass gates and close diversions (8-hour lead time). Want to avoid having the irrigation system inundated.

Mesilla diversion dam has gates (12-18 hr lead time) to open the gates. Shut down the canal diversion.

Biggest concern is flooding into the irrigation facilities at the diversion.

Page 40: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Diversion Dam Operation During Flooding

American Diversion Dam – IBWC

Wait until flood arrives. 6 gates are automatically control, 7 gates are manually controlled. Open all gates. Basically have a capacity of 12,000 cfs. Shut canal diversions.

Page 41: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Diversion Dam Operation During Flooding

All diversion dams are assumed to be broad crested weirs and open during flooding. The rating curve for passing the flood downstream was estimated using the broadcrested weir equation and a 2.85 coefficient for some loss of efficiency with gate structures.

Page 42: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Wasteway Operation During Flooding

Wasteways and drains are affected by backwater during flooding and can cause local flooding. All wasteways have gates (box culvert slide gates) and an effort is made to close all gates during flooding. Water in drains can flood because water continues to flow during flooding. Some watersheds drain into wasteways and deliver flood inflows from tributaries.

Page 43: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Wasteway Operation During Flooding

Assumed that all wasteways without flood inflows have closed gates. Levees would have to be overtopped to initiate flooding at wasteway locations. Additional detail can added to the model as local flooding is investigated. There is no operational policy other than to close the gates.

Page 44: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Remaining Issue: Additional roadway or other embankment details

Corps agreed that this additional detail is beyond the scope of work and that more detail can be added based on local flood studies and levee improvements.

Page 45: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

Potential future benefits

• Flood risk and hazard assessment• Flood mitigation – raise levees• Local flood details – levee elevations,

wasteways, urban flooding• Revise flood hydrology• River operations• River maintenance response• River restoration response

Page 46: FLO-2D Model Development Rio Grande Canalization Project Reach Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council.

The End