Flight Departures during Taxiway C Construction
5
FLIGHT DEPARTURES DURING TAXIWAY C CONSTRUCTION San Diego International Airport
description
Flight Departures during Taxiway C Construction . San Diego International Airport . Phase 1. Start October 28,2009 = 78 Days of Construction. Phase 2. Start January 7,2010 = 66 Days of Construction. Phase 3. Start Feb 22, 2010 = 78 Days of Construction. Questions and Answers. - PowerPoint PPT Presentation
Transcript of Flight Departures during Taxiway C Construction
![Page 1: Flight Departures during Taxiway C Construction](https://reader034.fdocuments.us/reader034/viewer/2022051317/56816352550346895dd3f16b/html5/thumbnails/1.jpg)
FLIGHT DEPARTURES DURING TAXIWAY C CONSTRUCTION
San Diego International Airport
![Page 2: Flight Departures during Taxiway C Construction](https://reader034.fdocuments.us/reader034/viewer/2022051317/56816352550346895dd3f16b/html5/thumbnails/2.jpg)
Phase 1
Start October 28,2009 = 78 Days of Construction
![Page 3: Flight Departures during Taxiway C Construction](https://reader034.fdocuments.us/reader034/viewer/2022051317/56816352550346895dd3f16b/html5/thumbnails/3.jpg)
Phase 2
Start January 7,2010 = 66 Days of Construction
![Page 4: Flight Departures during Taxiway C Construction](https://reader034.fdocuments.us/reader034/viewer/2022051317/56816352550346895dd3f16b/html5/thumbnails/4.jpg)
Phase 3
Start Feb 22, 2010 = 78 Days of Construction
![Page 5: Flight Departures during Taxiway C Construction](https://reader034.fdocuments.us/reader034/viewer/2022051317/56816352550346895dd3f16b/html5/thumbnails/5.jpg)
QUESTIONS AND ANSWERS