Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load...

29
1 Flexible Operation Integrating thermal power with Renewable Energy & Challenges Y M Babu Technical Services, Noida

Transcript of Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load...

Page 1: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

1

Flexible Operation

Integrating thermal power with Renewable Energy &

Challenges

Y M Babu

Technical Services, Noida

Page 2: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

2

Why Flexible Operation?

Limitations with Renewable generation has called for flexible operation:

Intermittent and variable

Season and Weather dependent

Location and time of day dependent

Does not match the load demand curve

Wind generation is unpredictable

Solar generation is predictable but non controllable

30th Nov 2018

Page 3: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

3

Integration of Renewable Energy in Grid

Balancing by conventional energy sources (large part of which isthermal) is required.

Greater the penetration of RE in grid, greater is the requirementof balancing.

30th Nov 2018

Page 4: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

4

Expectation from Thermal plants

Backing down and cyclic loading

Frequent start/stops may be required

Higher ramping rates during loading and unloading

But base load conventional plants are

not designed for such cyclic loading.

30th Nov 2018

Page 5: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

5

Start-up of Steam turbines (BHEL make)

30th Nov 2018

Start type Outage hours Mean HP Rotor

temperature

(deg C)

Start-up time

(Rolling to full

load in min.

approx)

Cold Start 190 hr 150 deg C 255

Warm Start 48 hr 380 deg C 155

Hot Start 8 hr 500 deg C 55

Normal Mode : 2000-2200 starts

Slow Mode : 8000 starts

Fast Mode : 800 starts

Page 6: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Effect of Load Cycling on Power Plant Components

6

Creep – Slow and continuous deformation of materials due to high temperature exposure even at constant load

Thermal Fatigue – Failure of metal when subjected to repeated or fluctuating stresses due to thermal cycling of components

Components affected – HP/IP rotors, Blades, Casings, Valves, Header, Y-Piece, T-piece, MS/HRH Pipelines and pressure parts.

30th Nov 2018

Page 7: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

7

Life Expenditure of Components

30th Nov 2018

Operating Steam

Pressure

Life Time Consumption

Creep Damage

Stress

Fatigue Damage

Creep Rupture Strength

Mechanical Stress Thermal StressType of

Material

Operating

Stress

Operating Steam

temperature

Steam Pressure

inside a thick –

walled

component

Physical properties of a

material

Geometrical

Dimensions of a thick

walled components

Temperature

Difference inside a

thick –walled

component

Page 8: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

8

Life Expenditure Computation

The consumed life of a component is the sum of the life consumed by Creep & Low Cycle Fatigue

MINER SUM MC IS INDICATOR OF THE LIFE EXPENDED DUE TO CREEP

&

MINER SUM MF IS INDICATOR OF THE LIFE EXPENDED DUE TO LOW CYCLE FATIGUE

30th Nov 2018

Page 9: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

9

Life Expenditure Computation

30th Nov 2018

FOR STATIONARY COMPONENTS :

M = MC + MF = 1 WARNING POINT

FOR ROTATING COMPONENTS :

M = M C + MF = 0.5 WARNING POINT

Approaching the Warning Point of Effective Miner Sumindicates that the life of the component has reached its limit.

Page 10: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

10

Impact of Cycling on Equipment and Operation

Critical components are subjected to thermal stresses which are cyclic in nature

Higher fatigue rates leading to shorter life of components

Advanced ageing of Generator insulation system due to increased thermal stresses

Efficiency degradation at part loads

More wear and tear of components

Damage to equipment if not replaced/attended in time

Shorter inspection periods

Increased fuel cost due to frequent start-ups

Increased O&M cost

30th Nov 2018

Page 11: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

11

Other Operational Risks

Ventilation in HP and LP Turbine

at lower loads

Droplet erosion of LP blades

Excitation of LP blades due to ventilation

Frequent start/stop of major auxiliaries

(PA/FD/ID fans, BFP) reduces their reliability.

Increased risk for pre-fatigued components.

Drop in efficiency & high Auxiliary Power Consumption (APC) at partial loads

30th Nov 2018

Page 12: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Age of Thermal Power Plants In India(in Years)

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

0-5 years 6-10 years 10-15 years 15-20 years 20-25 years > 25years

43357 MW

22610 MW

8359 MW 7780 MW5630 MW

> 25years, 29549 MW

MW

CA

PA

CIT

Y

AGE GROUP

Number of Sets

30th Nov 2018

Page 13: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

13

Assumed Load Demand Curve on Thermal Machines

30th Nov 2018

0

20

40

60

80

100

120

40%

80%

100%

80%

2% / min 3% / min

Page 14: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

14

Impact Assessment of Load Cycling

Impact of cyclic operation on BHEL supplied equipment withassumed load curve has been investigated.

Lower load upto 55% of rated and a ramp down rate of 2%/minand ramp up rate of 3%/ min. has been established.

Studies are being conducted to assess the impact on componentlife with loads as low as 40% of the rated load.

It is assumed that main steam and HRH temperatures are keptconstant and Unit is operated in sliding pressure mode.

30th Nov 2018

Page 15: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Cyclic Operation - Findings

Preliminary studies indicate that load backing from 100%-55%load at a ramp rate of 2%-3% per minute will not have significantimpact on life consumption of Turbine, Boiler, Generator & ESP.

However this mode of operation will have additional cost interms of lower efficiency at part loads.

20

Backing down below 55% load and/or increase in ramp rates willhave effect on the fatigue life of the equipment.

Backing down below 55% load will also have other negativeimpacts on the equipment as discussed earlier and need furtherinvestigation in detail.

30th Nov 2018

Page 16: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

16

Mitigating the Effect of Cycling

Additional Condition monitoring systems/ Sensors

Improved design of Boiler and Turbine to allow faster ramping and increased number of cycles

Adaptation of Control System

Older plants may require RLA to assess the cycling impact on already fatigued components.

Replacement of fatigued/ worn-out components

Shorter inspection period

30th Nov 2018

Page 17: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

17

Condition Monitoring for Flexible operation

Complete operation data is available.

Scheduling of RLA.

Continuous online consumption of life expenditure.

Detection of highly stressed parts for inspection.

Exploring the margins available for optimization of operating modes.

Online monitoring of Generator components as early warning system.

30th Nov 2018

Page 18: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

18

Condition Monitoring Systems

Turbine Stress Controller (TSC)

Boiler Stress Monitoring System (BOSMON)

Blade Vibration Monitoring System (BVMS)

Stator End Winding Vibration Monitoring

Rotor Flux Monitoring

Partial Discharge Monitoring

Additional sensors for health monitoring

30th Nov 2018

Page 19: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Primary frequency control by regulating turbine extraction

Frequency control technique, allowing for fast response even though boiler response is slow

Reducing the flow through extractions helps in raising the load as steam is forced through turbines

Feed forward command given to boiler master for increasing boiler load for further sustaining the load increase.

Load increase up to 7% is achievable on case to case basis

19 30th Nov 2018

Page 20: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Model based Predictive Control (MPC)

20

Existing PID Controller

Philosophy

MPC Philosophy

30th Nov 2018

Page 21: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Model based Predictive Control (MPC)

Advanced type controller primarily for steam temperature control for both SH & RH:

Consists of predictor & controller

Predictor creates models based on past operating data and then predicts the parameters in future course

Based on the prediction, the controller regulates the spray control valves.

Continuous communication between MPC & DCS.

Automatic updation of models.

21 30th Nov 2018

Page 22: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Model based Predictive Control (MPC)

22

During training of MPC

Switching scheme for MPC

30th Nov 2018

Conventional

PID Control

MPC Software

runs in

Workstation

Inputs to PID Controller

Inputs to MPC Software

PID Selection from HMI Station

Relevant DPU in MAX DCS

PID Output to DESH

spray control valve

Page 23: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Model based Predictive Control (MPC)

23

During running of MPC

Switching scheme for MPC

30th Nov 2018

Conventional

PID Control

MPC Software

runs in

Workstation

Inputs to PID Controller

Inputs to MPC Software

Selection from HMI Station

Relevant DPU in MAX DCS

MPC Output to DESH

spray control valve

Page 24: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Online Coal Analyzer

24 30th Nov 2018

Key Aspects

Coal Flow Measurement

Sieve AnalysisCoal & Ash

Characterisation

Experiments with different loading rates are being conducted.

The online coal analyser is under development stage.

Page 25: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Online Coal Analyzer (Contd.)

Coal flow & fineness through each pipe can be measured

Better control over air/ fuel ratio

Better control over fineness

Better control over burner performance

Combustion and temperature profiles within the furnace can be improved.

Slagging & fouling issues can be reduced

25 30th Nov 2018

Page 26: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Flame Scanners

Key requirements:

Reliability for detecting flame of coals with low VM.

Reliability at low load operation.

Reliability for fuel flexible operation.

26 30th Nov 2018

Page 27: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

Flue Gas Temperature Control

Minimum flue gas temperature to be achieved using SCAPH to meet air heating requirements.

Avoid acid corrosion in APH baskets and downstream equipment.

27 30th Nov 2018

Page 28: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

28

Renewables integration – Overall impact

Thus increased penetration of renewables will lead to

Increased cost due to cycling resulting in higher tariff from conventional sources

Reduced equipment life and thus earlier replacement of plants

30th Nov 2018

Page 29: Flexible Operation€¦ · Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated. Lower load upto 55% of rated and a ramp down rate of

29