Flex cable feasibility study : Context / Objectives
description
Transcript of Flex cable feasibility study : Context / Objectives
MISTRAL & ASTRAL SensorsFlex feasibility study
Gilles CLAUS (on behalf of PICSEL-ALICE team of IPHC-Strasbourg)
IPHC [email protected] 2 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
Goal of this study Based on STAR-PXL flex cable (proven technology) Estimate minimum achievable cable width Calculate voltage drop along the power bus Calculate material budget
Design decisions for evaluation Cable length for 9 chips ( 15 mm x 30 mm ) 9 x 30 mm = 270 mm Cable width 15 mm + Bonding area ? mm (pads, bonding wire loop, decoupling capacitors) Cable design done on FR4 by C.Illinger
GND & VDD traces 7 mm width – 30 µm Aluminium
Flex cable feasibility study : Context / Objectives
270 mm
> 15
mm
IPHC [email protected] 3 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
Minimum cable width : Study done by M.Goffe & IPHC µTechnique Team (M.Imhoff & Co)
50 µm thick sensors Wedge bonding Minimum bonding pads distance : Chip Flex
500 µm Loop too short 800 µm Acceptable value for bonding reliability
Result ~ 1 mm Cable width ~ 16 mm Better result achievable ?
Flex cable feasibility study : Minimum cable width
500 µm
500 µm
800 µm
IPHC [email protected] 4 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
One segment
ΔU / segment 2 ΔU / segment 1
9 x I 2 x I I8 x I
ΔU / segment 9
Chip No 9 Chip No 3 Chip No 2 Chip No 1
Calculation hypothesis
Common GND & VDD traces for analogue & digital Aluminium traces : 7 mm width – 30 µm thick – ρ Al = 26.10-9 ohm.m Sensors : 15 x 30 mm² - Power supply = 1,8 V MISTRAL : Pd = 200 mW/cm² I = 0,5 A/Chip - ASTRAL : Pd = 85 mW/cm² I = 0,21 A/Chip
Voltage drop MUST be <= 200 mV
Distance between two sensors = “One segment” ρ Al = 26.10-9 ohm.m – Trace 7 mm width - 30 µm thick R = 3,7 m ohm
Total voltage drop ΔV1 = R x I, ΔV2 = R x 2 x I … ΔV9 = R x 9 x I Arithmetic serie Voltage drop = Sum of the serie = 9 x ( ΔV1 + ΔV9) / 2 = 9 x (RI + 9RI) / 2 = 45 x R x I Chip
MISTRAL (Pd = 200 mW/cm² I = 0,5 A/Chip)
ΔV = 45 x R x I Chip = 45 x 0,0037 x 0,5 = 83 mV Total (Vdd, gnd) = 166 mV
ASTRAL (Pd = 85 mW/cm² I = 0,21 A/Chip)
ΔV = 45 x R x I Chip = 45 x 0,0037 x 0,21 = 35 mV Total (Vdd, gnd) = 70 mV
Flex cable feasibility study : Voltage drop
IPHC [email protected] 5 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
Remark
Voltage drop calculation done in DC
This true ONLY if there is enough decoupling capacitors / chip on the flex
If it’s not the case There is an AC component I power bus = I dc + I ac
At which freauency ?
Clock and harmonics Input 40 MHz – Serializer 600 MHz – 1,2 GHz (1,2 Gb/s – 2,4 Gb/s) AC component if unbalanced currents (should be minimized with differential architecture - LVDS)
At frames frequency : T r.o = 20,8 µs F = 100 KHz No risk with skin effect BUT Low frequency requires high capacity value
What’s about skin effect ?
Gianluca’s Talk yesterday Aluminium 12 µm @ 50 MHz < 1 / 2 Trace thickness (35 µs)
Which effect is more critical : Traces inductance / Skin effect ?
Is there simulations ?
Chip current profile ?
Flex cable feasibility study : Voltage drop
IPHC [email protected] 6 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
Radiation length
Kapton flex 50 µm Xo = 34,2 cm X = 0,0146 % Xo
2 x Aluminium 30 µm X0 = 8,897 cm X = 2 x 0,037 % Xo = 0,074 % Xo
2 x Adhesive 25 µm Xo = 33,8 cm X = 2 x 0,0074 % Xo = 0,0148 % Xo
Total X = 0,1 % Xo
Total thickness = 160 µm
Al 30 µmAdhesive 25 µm
Kapton 50 µm
Adhesive 25 µm
Al 30 µm
Flex cable feasibility study : Material budget
IPHC [email protected] 7 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
Flex
Does it makes sense to continue this study ?
Now it’s a design in a CAD tools Nothing has been produced
Is there manpower to pursue this study ?
Power distribution – Voltage drop
Definition of minimum decoupling capacitors value / chip
Skin effect / Traces inductance
Chip current profile
Flex cable feasibility study : Conclusion
IPHC [email protected] 8 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
Backup
IPHC [email protected] 9 / 7ALICE ITS upgrade - Mini week 10-12 March 2014
IPHC [email protected] 10 / 7ALICE ITS upgrade - Mini week 10-12 March 2014