First Floor Only
-
Upload
mathew-yoyakky -
Category
Documents
-
view
231 -
download
0
Transcript of First Floor Only
-
7/27/2019 First Floor Only
1/6
Firstfloor only
1 Podium Driveway & Car Parking
a Plain Cement Concrete: Supply, placing and
leveling of plain cement concrete 1:2:4 mix
100mm thk with trowel as base , cost including all
materials at site, all labor charges ,Transportation
,loading , unloading charges and other necessary
charges to complete the work as per drawingspecification and as instructed by PIC
188.24 Cum
SUB TOTAL
2 Basket Ball Court
A Steps Connecting to Basket ball court
a Crusher run: Supply, placing, leveling and
compaction with mechanical rammer for base to
100mm thick cost including all materials at site, all
labor charges and other necessary charges to
complete
0.47 Sqm
b Plain Cement Concrete: Supply, placing and
leveling of plain cement concrete 1:2:4 mix 50mm
thk, cost including all materials at site, all labor
charges and other necessary charges to complete
0.11 Cum
c Reinforced Cement Concrete : Supply, placing
and leveling of pre-mix cement concrete of grade
M20, cost including materials conveyance to site,
machine mixing, vibratory, centering, curing &
formwork, all labor charges and necessary
charges to complete. * For Steps
0.92 Cum
d Reinforcement: Supply and tying of steel
reinforcement including cutting and bending as per
Structural Engr's design cost including all
materials at site, necessary machineries, all labor
charges and other necessary charges to complete
0.05 Tons
3 Basket Ball Court
a Plain Cement Concrete: Supply, placing andleveling of plain cement concrete 1:2:4 mix 60mm
thk, with trowel as base , cost including all
materials at site, all labor charges,Transportation
,loading , unloading charges and other necessary
charges to complete the work as per drawing
specification and as instructed by PIC
3.29 Cum
b Reinforced Cement Concrete : Supply, placing
and leveling of pre-mix cement concrete of grade
M20, cost including materials conveyance to site,
machine mixing, vibratory, centering, curing &
formwork, all labor charges and necessary
charges ,Transportation , loading , unloading
charges to complete. * For retaining wall for
pedestal as per drawing specification and as
instructed by PIC
1.04 Cum
c Reinforcement: Supply and tying of steel
reinforcement including cutting and bending as per
Structural Engr's design cost including all
materials at site, necessary machineries, all labor
charges and other necessary charges
,Transportation ,loading , unloading charges to
complete as per drawing specification and as
instructed by PIC
0.03 Tons
d Vacuum dewatered Flooring : Providing and
laying 50mm thick Vacuum dewatered flooring
using 40mm thk. (1:2:4) concrete mix to proper
levels & slopes and finishing top with 10mm thk
cement mortar 1:3mix, cost including all materialsat site, all labor charges and other necessary
charges ,Transportation , loading , unloading
charges to complete as per drawing (LSCD 11.1
R2) specification and as instructed by PIC
54.86 Sqm
e Light wieght filling (cynder filling) : supply, placing,
leveling and compaction with mechanical rammer
for base including cost of all materials at site all
lbourcharges,transporation,loading,unloading
charges and other necessary charges to complete
the work as per drawing, specification and as
instructed by PIC
RO cum
4 Kid's Play Area
A Kid's Play Area
Landscaping work Rev-BOQ for Purva Grandbay, Kochi
Site Concepts Pvt Ltd. 1/6Rev-BOQ for Purva Grandbay, Kochi
-
7/27/2019 First Floor Only
2/6
Landscaping work Rev-BOQ for Purva Grandbay, Kochi
a Water proofing: Supplying and applying of
approved water proof membrane two coats as per
manufacturers direction and one productive layer
of cement sand screed 12mm thick cost including
all materials at site, all labor
charges,Transportation, loading , unloading and
other necessary charges to complete the work as
per the drawing,specification and as instructed by
PIC
Sqm
b Plain Cement Concrete: Supply, placing and
leveling of plain cement concrete 1:2:4 mix
125mm thk with trowel as base , cost including all
materials at site, all labor charges and other
necessary charges ,Transportation ,loading ,
unloading charges to complete the work as per
drawing specification and as instructed by PIC
21.53 Cum
d Light wieght filling (cynder filling) : supply, placing,
leveling and compaction with mechanical rammer
for base including cost of all materials at site all
lbourcharges,transporation,loading,unloading
charges and other necessary charges to complete
the work as per drawing, specification and as
instructed by PIC
RO cum
5 Veiwing deck
A Paving
a Crusher run: Supply, placing, leveling and
compaction with mechanical rammer for base to
470mm thick cost including all materials at site, all
labor charges and other necessary charges to
complete
2.41 Sqm
b Plain Cement Concrete: Supply, placing and
leveling of plain cement concrete 1:2:4 mix
150mm thk, cost including all materials at site, all
labor charges and other necessary charges to
complete
0.77 Cum
c Reinforced Cement Concrete : Supply, placing
and leveling of pre-mix cement concrete of gradeM20, cost including materials conveyance to site,
machine mixing, vibratory, centering, curing &
formwork, all labor charges and necessary
charges to complete. * For retaining wall
0.53 Cum
d Reinforcement: Supply and tying of steel
reinforcement including cutting and bending as per
Structural Engr's design cost including all
materials at site, necessary machineries, all labor
charges and other necessary charges to complete
0.02 Tons
e Light wieght filling (cynder filling) : supply, placing,
leveling and compaction with mechanical rammer
for base including cost of all materials at site all
lbourcharges,transporation,loading,unloading
charges and other necessary charges to complete
the work as per drawing, specification and as
instructed by PIC (aprox high 500 mm )
3.50 cum
6 Water feature
A Water Feature
a Plain Cement Concrete: Supply, placing and
leveling of plain cement concrete 1:2:4 mix
100mm thk, cost including all materials at site, all
labor charges and other necessary charges to
complete
0.57 Cum
b Reinforced Cement Concrete : Supply, placing
and leveling of pre-mix cement concrete of gradeM20, cost including materials conveyance to site,
machine mixing, vibratory, centering, curing &
formwork, all labor charges and necessary
charges to complete. * For retaining wall
1.02 Cum
c Reinforcement: Supply and tying of steel
reinforcement including cutting and bending as per
Structural Engr's design cost including all
materials at site, necessary machineries, all labor
charges and other necessary charges to complete
0.08 Tons
Site Concepts Pvt Ltd. 2/6Rev-BOQ for Purva Grandbay, Kochi
-
7/27/2019 First Floor Only
3/6
Landscaping work Rev-BOQ for Purva Grandbay, Kochi
d Water proofing: Supplying and applying of
approved water proof membrane two coats as per
manufacturers direction and one productive layer
of cement sand screed 12mm thick cost including
all materials at site, all labor charges and other
necessary charges to complete
10.12 Sqm
7 Planter Box (3 nos)
a Reinforced Cement Concrete : Supply, placing
and leveling of pre-mix cement concrete of grade
M20, cost including materials conveyance to site,
machine mixing, vibratory, centering, curing &
formwork, all labor charges and necessary
charges to complete. * For Planter walls
1.34 Cum
b Reinforcement: Supply and tying of steel
reinforcement including cutting and bending as per
Structural Engr's design cost including all
materials at site, necessary machineries, all labor
charges and other necessary charges to complete
0.04 Tons
c Water proofing: Supplying and applying of
approved water proof membrane two coats as per
manufacturers direction and one productive layer
of cement sand screed 12mm thick cost including
all materials at site, all labor charges and othernecessary charges to complete
7.43 Sqm
d Plastering: Plastering for side walls in cement
mortar 1:6mix 12mm thick sponge finish for walls
cost including all material to site, all labor charges
and other necessary charges to complete
5.54 Sqm
8 Planter Boxes (2 nos)
a Reinforced Cement Concrete: Supply, placing
and leveling of pre-mix cement concrete of grade
M20, cost including materials conveyance to site,
machine mixing, vibratory, centering, curing &
formwork, all labor charges and necessary
charges to complete. * For Planter walls
1.05 Cum
b Reinforcement: Supply and tying of steelreinforcement including cutting and bending as per
Structural Engr's design cost including all
materials at site, necessary machineries, all labor
charges and other necessary charges to complete
0.03 Tons
c Water proofing: Supplying and applying of
approved water proof membrane two coats as per
manufacturers direction and one productive layer
of cement sand screed 12mm thick cost including
all materials at site, all labor charges and other
necessary charges to complete
9.48 Sqm
d Plastering: Plastering for wall surfaces in cement
mortar 1:6mix 12mm thick; finish for wall cost
including all material to site, all labor charges and
other necessary charges to complete.
14.04 Sqm
9 Planter Boxes
a Reinforced Cement Concrete: Supply, placing
and leveling of pre-mix cement concrete of grade
M20, cost including materials conveyance to site,
machine mixing, vibratory, centering, curing &
formwork, all labor charges Transportation
,loading , unloading and necessary charges to
complete. * For Planter walls as per drawing
,specification and instructed PICbut exculding
cost of reinforcement steel
24.26 Cum
b Reinforcement: Supply and tying of steel
reinforcement including cutting and bending as per
Structural Engr's design cost including all
materials at site, necessary machineries, all labor
charges ,Transportation ,loading , unloading
charges and other necessary charges to
complete as per drawing specification and as
instructed by PIC
0.73 Tons
c Water proofing: Supplying and applying of
approved water proof membrane two coats as per
manufacturers direction and one productive layer
of cement sand screed 12mm thick cost including
all materials at site, all labor
charges,Transportation, loading , unloading and
other necessary charges to complete as per the
drawing,specification and as instructed by PIC
161.70 Sqm
Site Concepts Pvt Ltd. 3/6Rev-BOQ for Purva Grandbay, Kochi
-
7/27/2019 First Floor Only
4/6
Landscaping work Rev-BOQ for Purva Grandbay, Kochi
d Plastering: Plastering for wall surfaces in cement
mortar 1:6mix 12mm thick; finish for wall cost
including all material to site, all labor charges
Transportation ,loading , unloading and other
necessary charges to complete the work as per
drawing,specification and as instruced by PIC
323.40 Sqm
SUB TOTAL
TOTAL FIRST FLOOR
GRANITE AND TILING WORK
1 Feature Steps
a Granite work (Black Granite): Supply and fixing
of Black Granite as per dig on cement mortar
1:3mix cost including all materials to site, all labor
charges ,Transportat ion , loading , unloading
chargesand other necessary charges to complete
the work as per drawing (LSCD 3.1 R2 )
specification and as instructed by PIC
i) Cut to size x 20mm thick antique finish with
sandwich edge for step threads
49.12 Sqm 42.36
ii) Cut to size x 20mm thick antique finish for step
landing
60.31 Sqm
b Granite work (Black Granite): Supply and fixing
of Black Granite as per dig on cement mortar
1:3mix cost including all materials to site, all labor
charges ,Transportat ion , loading , unloading
chargesand other necessary charges to complete
the work as per drawing (LSCD 3.1 R2 )
specification and as instructed by PIC
i) 150 x L x 20mm thick polished finish for step
risers
21.18 Sqm
2 Basket Ball Court
A Steps Connecting to Basket ball court
a Granite work (Black granite): Supply and fixing
of Black granite as per dig on cement mortar
1:3mix cost including all materials to site, all laborcharges and other necessary charges to complete
i) 300 x L x 20mm thk antique finish with sandwich
edge for step tread
3.15 Sqm
b Granite work(Grey granite): Supply and fixing of
Grey granite as per dig on cement mortar 1:3mix
cost including all materials to site, all labor
charges and other necessary charges to complete
i) 150x L x 20mm thk polished finish for step riser 1.58 Sqm
3 Kid's Play Area
a Granite work (Sadarahalli Grey granite): Supply
and fixing of Sadarahalli grey granite as per drg
on cement mortar 1:3mix and applying of
impregnable clear colour sealer two coats onecoat before installation and one coatafter
installation with necessary pointing work, cost
including all materials to site, all labor
charges,Transportation ,loading , unloading and
all other necessary charges to complete the work
as per drawing,specification and as instruced by
PICi) 250 x L x 40mm thk flamed finish for banding 3.11 Sqm
4 Veiwing deck
a Granite work (Royal Brown granite): Supply
and fixing of Royal Brown granite as per dig on
cement mortar 1:3mix cost including all materials
to site, all labor charges and other necessary
charges to complete
i) Cut to size x 20mm thk antique finish for paving 5.94 Sqm
ii) 100 x L x 20mm thk antique finish for external
cladding
0.58 Sqm
5 Water feature
a Granite work (Black Granite): Supply and fixing
of Black Granite as per dig on cement mortar
1:3mix and applying of impregnable clear color
sealer two coats one coat before installation and
one coat after installation cost including all
materials to site, all labor charges and other
necessary charges to complete
Site Concepts Pvt Ltd. 4/6Rev-BOQ for Purva Grandbay, Kochi
-
7/27/2019 First Floor Only
5/6
Landscaping work Rev-BOQ for Purva Grandbay, Kochi
i) 200 x L x 40mm thk polished finish both edge
chamfered for coping (without clear color sealer)
2.60 Sqm
ii) Cut to size x 20mm thk polished finish for
internal cladding
3.51 Sqm
iii) Cut to size x 20mm thk polished finish for
external cladding (without clear color sealer)
1.83 Sqm
6 Planter Boxes (3nos)
a Granite work (Black Granite): Supply and fixing
of Black Granite as per dig on cement mortar
1:3mix, cost including all materials to site, all labor
charges and other necessary charges to complete
i) 200 x L x 20mm thk polished finish with
sandwich & both edge for coping
1.99 Sqm
7 Stepping stones
a Stepping stonework (Grey granite): Supply and
fixing of 50mm thk Grey granite stepping stone as
per dig on 50mm sand bed cost including all
materials to site, all labour charges and other
necessary charges to complete
i) 1200 x 450 x 50mm thk antique finish with grassjoints for stepping stones
4.86 Sqm
8 Planter Boxes (2 nos)
a Granite work (Black granite): Supply and fixing
of Black granite as per dig on cement mortar
1:3mix cost including all materials to site, all labor
charges and other necessary charges to complete
i) 200 x L x 40mm thk polished finish with
sandwich & both edge chamfered for coping
2.34 Sqm
9 Planter Boxes
a Granite work (Black granite): Supply and fixing
of Black granite as per dig on cement mortar
1:3mix and applying of impregnable clear colour
sealer two coats one coat before installation and
one coatafter installation with necessary pointing
work cost including all materials to site, all labor
charges Transportation ,loading , unloading and
other necessary charges to complete the work as
per drawing,specification and as instruced by PIC
i) 200 x L x 20mm thk polished finish with
sandwich edge for coping
53.90 Sqm
TOTAL 1ST FLOOR
GRAND TOTAL (Total Civil and granite work)
Site Concepts Pvt Ltd. 5/6Rev-BOQ for Purva Grandbay, Kochi
-
7/27/2019 First Floor Only
6/6
No. Description of work Quantity Unit Rate Amount Remarks
1 Basket Ball Court
a
Synthetic paint finish: Providing synthetic paint
finish over basketball court area color: Blue, cost
including all materials to site, necessary
machineries, all labor charges and other
necessary charges ,Transportation ,loading ,
unloading charges to complete as per drawing
(LSCD 11.1 R2) specification and as instructedby PIC
54.86 Sqm
i Ditto but red color Sqm
ii50 mm wide court white marker (dashed line as
per drg no LSCD11.1 R2Sqm
2 Planter Box (3 nos)
a
Painting: Painting for plastered surface in
textured finish, color: match to building color, one
base coat and two finishing coats cost including all
materials at site, all labor charges and other
necessary charges to complete
- Sqm
3 Planter Boxes (2 nos)
a
Painting: Painting for external plastered surface
in textured paint finish, color: match to building
color, one base coat and one finishing coat costincluding all materials at site, all labor charges and
7.02 Sqm
4 Planter Boxes
a
Painting: Painting for external plastered surface
in textured paint finish, color: match to building
color, one base coat and one finishing coat cost
including all materials at site, all labor charges
Transportation ,loading , unloading and other
necessary charges to complete the work as per
drawing,specification and as instruced by PIC
151.95 Sqm
TOTAL -
Landscaping work Rev-BOQ for Purva Grandbay, Kochi
First floor and fifth floor
Site Concepts Pvt Ltd. 1/6Rev-BOQ for Purva Grandbay, Kochi