Fire Detection and Suppression Chapter 4 Fire Pumps.
-
Upload
roxanne-barber -
Category
Documents
-
view
242 -
download
3
Transcript of Fire Detection and Suppression Chapter 4 Fire Pumps.
Fire Detection and Suppression
Chapter 4
Fire Pumps
Fire Pumps4-2
Fire Pump Functions
• The main function of a fire pump is to increase the pressure of the water that flows through it.— Inadequate or nonexistent municipal water
supply system
— Sprinkler systems and standpipe systems
Fire Pumps4-3
Common Fire Pump Types
• Split-case pumps (see Fig. 4.2 in manual) — Horizontal: not self-priming
(Continued)
Fire Pumps4-4
Common Fire Pump Types
— Horizontal: not self-priming
(Continued)
Fire Pumps4-5
Common Fire Pump Types— Single-stage and multiple-stage
— Maintenance– Packing gland
– Wear rings
Fire Pumps4-6
Common Fire Pump Types
• Split-case pumps (cont.)— Vertically mounted
Fire Pumps4-7
Common Fire Pump Types• Vertical shaft turbine pumps
(Continued)
Fire Pumps4-8
Common Fire Pump Types— Pressurized water source
Fire Pumps4-9
Pump Drivers
• Engines or motors used to turn the pump
• Power requirements
• Types— Electric motors
– Required power
(Continued)
Fire Pumps4-10
Pump Drivers– Mounting
(Continued)
Fire Pumps4-11
Pump Drivers– Mounting (cont.)
– Maintenance(Continued)
Fire Pumps4-12
Pump Drivers
• Types (cont.)— Diesel engine drivers
– Engine power
– Gear drives
– Engine requirements
– Cooling system
– Fuel storage
– Maintenance(Continued)
Fire Pumps4-13
Pump Drivers
• Types (cont.)— Steam turbines
– Horizontal and vertical shaft
– Limited feasibility
Fire Pumps4-14
Pump Controllers
• Govern pump operation
• Controllers for electricmotor-driven pumps— Switches
— Multiple pumpsconnected in parallel
— Manual shutdown
(Continued)
Fire Pumps4-15
Pump Controllers (cont.)• Diesel engine controllers
— Main function is to close the circuit between the storage batteries and the engine starter motor.
— Alarm and signal devices
(Continued)
Fire Pumps4-16
Pump Controllers (cont.)
— Pressure recording device
— Manual shutdown
— Weekly startup
Fire Pumps4-17
Pump Installation Components and Accessories
• Pipe and fittings— Materials
— Valves
— Standards– Suction piping: NFPA 24, Standard for the Installation
of Private Fire Service Mains and Their Appurtenances
– Discharge piping: NFPA 24 and NFPA 13, Standard for the Installation of Sprinkler Systems
— Sizing (Continued)
Fire Pumps4-18
Pump Installation Components and Accessories (cont.)
• Relief valves— Prevent pressures that are high enough to
damage system piping or fittings
— Required only if pressure at churn is high enough to damage system components
— Sizing
(Continued)
Fire Pumps4-19
Pump Installation Components and Accessories (cont.)
• Circulation relief valve: provides enough water flow into and out of the pump to prevent the pump from overheating when operating at churn against a closed system
• Test equipment— Test manifold
— GPM metering device(Continued)
Fire Pumps4-20
Pump Installation Components and Accessories (cont.)
• Pressure maintenance pumps— Prevent false starts due to fluctuations in
pressure of water supply to pump
— Small-capacity, high-pressure pumps that maintain constant pressure on system
(Continued)
Fire Pumps4-21
Pump Installation Components and Accessories (cont.)
• Gauges— Horizontal split-case pumps and vertical shaft
pumps – One gauge near discharge port
– One gauge near intake
— Vertical turbine pump: single gauge on discharge side
(Continued)
Fire Pumps4-22
Pump Installation Components and Accessories (cont.)
• Component arrangement— Typical arrangement
(Continued)
Fire Pumps4-23
Pump Installation Components and Accessories (cont.)
— Additional bypass line
(Continued)
Fire Pumps4-24
Pump Installation Components and Accessories (cont.)
— Horizontal-shaft pump installation (See Fig. 4.23 in manual)
— Vertical-shaft pump installation (See Fig. 4.24 in manual)
• Standard performance specifications: NFPA 20, Standard for the Installation of Centrifugal Fire Pumps
Fire Pumps4-25
Testing, Inspection, and Maintenance
• Testing fire pumps— Piping: hydrostatic testing
— Acceptance testing– Certified shop test curves
– Standard performance points:1. Maximum of 140 percent of rated pressure at 0 gpm.
2. Minimum of 100 percent of rated pressure at 100 percent of rated flow.
3. A minimum of 65 percent of rated pressure at 150 percent of rated flow.
(Continued)
Fire Pumps4-26
Testing, Inspection, and Maintenance
• Equipment needed for pump tests— One section of 2 1/2-inch or larger hose for each
hose connection on the test header
— One Underwriters playpipe for each hoseline
— Method for safely securing playpipes
— Pitot tube and gauge
— Method of measuring pump speed
— Voltmeter and ammeter(Continued)
Fire Pumps4-27
Testing, Inspection, and Maintenance
• Conversion of velocity pressure to gpm:
Q=(29.83)(Cd)(D2)(√P)Where:
Q=Flow in gpm
Cd=Coefficient of discharge
D=Discharge orifice diameter
P=Nozzle pressure(Continued)
Fire Pumps4-28
Testing, Inspection, and Maintenance (cont.)
• Acceptance test on an electric horizontal split-case pump
Step 1: Calculate the expected pitot pressure for 100 percent and 150 percent of the rated flow.
Step 2: Connect all the hoselines and nozzles.
Step 3: Close the indicating control valve that separates the pump from the fire system.
(Continued)
Fire Pumps4-29
Testing, Inspection, and Maintenance
• Acceptance test on an electric horizontal split-case pump (cont.):
Step 4: Connect the ammeter and voltmeter to the test leads in the controller or at any other appropriate location.
Step 5: If using a handheld revolution counter to measure pump speed, remove end plate of motor for access to shaft.
(Continued)
Fire Pumps4-30
Testing, Inspection, and Maintenance
• Acceptance test on an electric horizontal split-case pump (cont.):
Step 6: If end of shaft is not accessible, use a strobe-type tachometer.
Step 7: Start the pump.
Step 8: Open the control valve in the line leading to the test header and open the hose valves for the first gpm measurement.
(Continued)
Fire Pumps4-31
Testing, Inspection, and Maintenance
• Acceptance test on an electric horizontal split-case pump (cont.):
Step 9: Open and adjust sufficient lines to exact required pitot pressures for 100 percent of rated flow.
Step 10: When all readings are complete and recorded, open and adjust additional hoselines to the exact required pitot pressures for 150 percent of the rated flow.
(Continued)
Fire Pumps4-32
Testing, Inspection, and Maintenance
• Acceptance test on an electric horizontal split-case pump (cont.):— Repetitions
– Manually controlled
– Automatically controlled
– Electrically driven pump
(Continued)
Fire Pumps4-33
Testing, Inspection, and Maintenance
• Acceptance test on an electric horizontal split-case pump (cont.):— Evaluating data
– Performance curves
– Pump speed
– Voltage and current for electrically driven pump
• Acceptance test on a vertical shaft electric pump
• Acceptance test on a diesel driven pump