Finished) Construction Productivity 01132012
-
Upload
nguyen-ngoc-dung -
Category
Documents
-
view
373 -
download
14
Transcript of Finished) Construction Productivity 01132012
THE MANUAL OF
CONSTRUCTION PRODUCTIVITY MEASUREMENT
AND PERFORMANCE EVALUATION
CONSTRUCTION
INDUSTRY
INSTITUTE
Page | 1
CHAPTER 1
INSTRODUCTION
Productivity is one the most of frequently discussed topics in the construction
industry. The reason is that productivity translates directly into costs and ultimately in
to contractor profits made or lost on the job. In most projects, productivity is the most
difficult cost component to estimate. It is also the most difficult one to control [7, 14,
17]. Indeed, productivity can be affected by many things, both major and minor. Some
factors are within the control of the contractor may be unaware that adverse factors are
present.
Considering the importance of construction productivity to project cost and
schedule control, one would expected to find a large body of well-codified knowledge
describing how to recognize productivity problems and offering known, sure – to-
successful remedies. In reality, little such information exists on what affects
productivity and, more important, by how much [13]. The range of opinions on factors
is extensive. Some blame global issues such as the economy, union politics, or
government regulations. Others argue that the work ethic is the problem. However, a
growing majority of those closely associated with the construction industry look to the
project itself for the factors affecting productivity. The focus on the way in which
projects are planned, organized, and managed. Fortunately, the implication is that most
of the factors affecting productivity can be identified and controlled to the large
degree. One thing seems relatively certain: Before it can be improves, productivity
must be measured [13].
PURPOSE
The objective of this manual is to describe an approach to construction
productivity measurement that can be used by general and specialty contractors and
owners on small – to medium – sized commercial and industrial projects. Perform
evaluation, which is an extension of productivity measurement, is also discussed. The
concepts are equally applicable to contractors and owners who do not have
productivity measurement system or who need a simple , inexpensive measurement
approach. The approach emphasizes measurements for selected labor-intensive
construction activity at the screw level. The important factors considered I developing
the approach include the size and duration of project; the value of measuring a few
activities instead of the total effort; the relationship to other control systems that may
or may not be used; the need for little or no additional staff or overhead expense; the
need for easy – to – understand, timely, and accurate information; and, last, the needs
of the user.
APPLICATION
The approach described in this manual is not restricted to any particular project
size or type. Appropriate areas of application have been identified on commercial and
industrial project alike. Certain Activities on highway projects and maintenance or
outage work on process, petrochemical, and power plant can be measured using these
techniques. The techniques can be applied equally well to lump sum, unit price, or cost
reimbursable contracts and can be used by owners, contractors, and special
contractors.
Page | 2
This manual is unique in that is a comprehensive guide to measuring
construction productivity. It offer an encouraging and appealing approach to the
measurement task by stating from the outset that productivity measurement is simple,
effective and can be done for little overhead expense. The contractor who implements
the procedures presented in this manual will develop almost immediately an increased
awareness and sensitivity to productivity issues. By following up with corrective
action on the problem that surface, a contractor may easily save 10 percent or more on
the labor cost of the major construction activities that impact total project cost and
schedule.
DEFINITIONS
In this manual, the following terms and definitions are used:
Account – A record or identification scheme used to categorize information about
a specific work item or activity, an account represents a discrete part or category of the
work to be performed. For example, an account may contain the work-hours used in
the erection if formwork for elevated slabs.
Control account – a control account consist of a grouping of related accounts or
activities where each account has a unique degree of difficulty or level effort required.
For example, the account for wall, column, and slabs formwork may be grouped into a
single control account titled formwork.
Control budget – The base estimate of work-hour, quantities, and productivity for
an activity or account, the control budget is used for comparative purposes to evaluate
performance.
Earned value – This technique is used for calculating the percent complete of a
control account. It uses a weighted average approach in which the weight assigned to
each individual account in the control account is based on the initial work-hour
estimate for the account compared to the sum of the initial estimated work-hour for all
accounts included in the control account [5].
Forecasting – The process of projecting the total work-hour required to complete
an account or activity is called forecasting [3].
Performance evaluation – This process involves the comparison of the actual
progress and productivity to the control budget. It includes the comparison of quantity
installation rates and work-hour consumption rates. Forecasting is a part of
performance evaluation.
Performance factor – A measure of construction efficiency, it is the planed
productivity divided by the actual productivity. This ratio is sometimes called a PF
value or a rate ratio. A ratio greater than 1.0 signified better -than – planned
performance.
Productivity – The work-hour require per unit of work, productivity is the input
divided by the output and is calculated for a finite time interval. It is commonly called
the unit rate [17].
Productivity measurement – This process of quantifying the work-hour and
quantities associated with an activity or account provides the measurements used in
productivity calculations and performance evaluations [7].
Page | 3
BARRIER TO MONITORING PRODUCTIVITY
Many contractors do not measure or monitor construction productivity. The most
common reasons for not doing so are:
- I’ve never monitored productivity before.
- I don’t know how to measure productivity.
- Productivity control is a part of a cost control system, which is too complicated
to understand and too expensive to implement
- Productivity cannot be controlled.
- Productivity measurement will not tell me something about my project that o
don’t really know.
The first two reasons cited are really a reflection of past practices where
productivity measurement was not an absolute necessity. Keen competitions for
projects, high inflation rates, increased project complexity, and greater exposure to
unforeseen risks have changed this situation. Productivity measurement has emerged
as an inexpensive way to control one of the more important contractor risks,
specifically the craft work-hours.
Historically, the most widely publicized productivity measurement systems have
emerged from the heavy industrial and power plant construction sectors of the
industry. Here, productivity control has always been treated as subset of the cost
control system. Understandably, many contractors have been discouraged by apparent
complexity and the prohibitive expense of operating a large, complex cost control
system. Until now, the prevailing attitude seems to have been that productivity
measurement must be tied to these types of system [1]. In reality, however, the two
functions of productivity control and cost control can be separated, and, in doing so,
productivity measurement and control can be made simple, inexpensive, effective, and
timely. This manual is the first known comprehensive document that recognizes the
two functions as separable.
The last two challenges to productivity measurement can be considered together.
A growing body of knowledge says that productivity can be controlled [4]. This
assertion is supported by the conclusion that work ethic, labor union, and poorly
motivated workers are not the primary root causes of productivity problems. Studies
have consistently shown that that problems result from the way project are designed,
organized, planned, and managed, and that these conditions exist whether the project is
large or small, commercial or industrial, or union or merit shop [4,144]. The following
are a few of the more commonly reoccurring causes of poor productivity that are
within the exclusive control of the contractor:
- Crews are too large, especially at the beginning and end of and activity.
- Stockpile and storage areas are poorly organized.
- Materials are inadequately marked or not sorted fro easy retrieval.
- Delays result from waiting for tools and equipment.
- Housekeeping practices are poor.
- Inability to maintain continuity or momentum results because screws are
reassigned to different to work or locations.
- Work of one screw interferes with that of another.
- Sequencing and control of the work are poor.
- Material deliveries are untimely.
Page | 4
This list could easily be expanded, but the important point is that many of these
causes exist to varying degrees on all construction projects.
If these causes occur repeatedly, why aren’t they corrected? Actually, many of
them are subtle and appear gradually. Although, they may never be noticed, they are
still there. Often, by the time a problem is noticed, the damage has already been done.
In many other cases, corrective action is perceived to cost more than it would save.
What then is the role of productivity measurement and performance evaluation?
They should provide early warning signals, long before the problem is obvious. They
should answer the question: How serious is the problem? They should be the basis for
measuring the economic impact of alternatives and should be the basis measuring the
economic impact of alternatives and should provide an easy means for quantifying the
results.
ORGANIZATION OF THE MANUAL
This manual is organized into four main parts. The first part, which includes
chapter 2 and 3, describes the framework for productivity measurement. Chapter 2
explains the basic concepts of cost control, cost accounting, and productivity control.
Chapter 3 defines the system criteria and then develops the framework for productivity
measurement and control. Productivity accounts are presented, and the relationship to
other account and control system is described.
Part II of the manual explains the basic concepts of productivity measurement,
reporting, and devaluation. Chapter 4 describes how to measure work-hour and
quantities. Five methods of quantity measurement are described. Chapter 5 shows four
types of productivity calculations and graphically illustrates each. The advantages of
tabular and graphical output are described. Chapter 6 describes performance
evaluation, which is the process of comparing the productivity calculations with the
project estimate. Analytical and graphical forecasting techniques are illustrated.
More advanced concepts are addressed in part III. Rues of credit for complex tasks
and the earned value technique for control accounts are coveted in chapter 7. The
technique the forecasting using standard productivity curves is also detail. Chapter 8
addresses concepts that integrate productivity and schedule parameters.
Part IV presents several case studies and summarizes the results. Chapter 9
describes case studies of three contractors involved primarily in commercial and light
industrial construction. Their long – range objectives in measuring productivities are
describes along with lesions learned during the implementation process. The case
studies illustrate how productivity can be used to understand the factors that affect
productivity, to monitor and control important activities, and to develop labor units for
estimating. Chapter 10 summarizes the case study finding and conclusion.
USE OF THE MANUAL
The manual explains concepts in a general way, which means the techniques can
be applied regardless of the type of control system already in-place, nature of work,
sophistication of the contractors, and so forth. Part I explains the framework for
productivity measurement, and readers who have an understanding of productivity
control using a cost control system may wish to begin directly with chapter 3. For the
experienced user, chapter 2 and 3 describe the context in which measurements are
made. These two chapters will ease apprehension that contractor must implement a
cost control system to used the techniques; no significant changes in current modes if
Page | 5
operation are required. An experienced user should first concentrate on the basic
concepts in part II. As one becomes familiar with these, the first step beyond manual
tracking will probably be to computerize the process, which can be done relatively
easily on a spreadsheet program such as LOTUS 1-2-3 or on an integrated system like
framework II or SYMPHONY. After mastering the basic concepts on several projects,
the contractor may be ready to try some of the advance concepts in part III. The
experienced users may want to review part II before proceeding to part III, or may be
feel comfortable about implementing some of the advanced concepts from the outset.
All reader will find the case studies in part IV to be valuable, as they describe some
specific about implementation and details of lessons learned. The examples illustrate a
wide range of applications.
Page | 6
PART I - FRAMEWORK FOR PRODUCTIVITY CONTROL
An outgrowth of defense systems acquisition and large , cost reimburse
construction projects such as for nuclear power plants, refineries and coal gasification
facilities was the development of sophisticated cost control systems. These systems are
characterized by the breakdown of project expenditures according to code of accounts
Each account can be monitored for excessive costs, and these can be traced to the
source, e.g. , labor, construction equipment, construction materials, permanent plant
equipment, etc. [11].
Cost control systems have also been used to monitor labor productivity but
whether they are the most effective way of monitoring productivity questionable. This
section of the manual will develop the framework around which productivity can be
monitored in a simple and timely manner. Chapter shows that the cost control system
can be used for two purposes, and that the system is used affects the level of detail.
The most detailed form is needed for control purposes. The code of account structure
is designed to isolate problem areas. With this system, all project activities are tracked
in considerable detail, there is a feedback loop, and a support staff is needed. The
second form of the costing model is used only for accounting purposes. This simple
system, which supports the need to develop historical estimating data, concentrates on
accumulating costs at the end of the project. Many contractors use this type of model
because it is easy to understand and inexpensive to carry out. Unfortunately, the need
for controlling the rationale for simplifying the cost control system is then developed.
Chapter 3, the criteria for a productivity measurement and control system presented.
Using these criteria, the code of accounts for petrochemical facility and general
commercial construction are revised to be consistent productivity control needs. A
framework is developed in which productivity control operates separately from the
cost control system.
Page | 7
CHAPTER 2
FRAMEWORK FOR PRODUCTIVITY MEASUREMENT
AND PERFORMANCE EVALUATION
INTRODUCTION
A successful project is generally considered to be one that meets certain technical
objectives, is completed on or ahead of schedule, within the owner’s or contractor’s
budget, and results in a reasonable profit for the contractor. To ensure success, an
effective project control system must be implemented to provide managers and
superintendents with timely and accurate feedback on the consumption of resources.
Historically, this has meant the implementation of a cost control system. Prior to the
development of the productivity measurement system presented in Chapter 3, it is
worthwhile to review the differences in detail and usages of costing systems.
CHARACTERISTICS OF COSTING SYSTEMS
Usages
Costing system are designed to track and account for project costs. The reasons for
doing so are two-fold. First, the tracking function can be used during construction to
control project costs. Tracking highlights activities or areas that deviate significantly
from planned expenditures so that corrective action can be taken. How the system will
be used generally establishes the level of detail and degree of sophistication [11].
Costing system to Support Cost control
The more detailed and sophisticated systems are used to monitor and control cost
during construction. While these systems also support the estimating of future projects,
the requirement for considerable detail and sophistication arises to satisfy three
essential needs related to the control function: 1) to develop comparisons to project
estimates during construction, 2) to provide timely feedback, and 3) to isolate
particular problem areas where cost deviations are significant. Figure 1 shows the
overall cost control process. During construction, the contractor must account for costs
and work-hours and measure progress. Comparisons to the control budget are made
periodically, and corrective action is taken when required.
The framework for cost control is a standard code of accounts which defines how
costs will be categorized. Since costs and work-hours are used to estimate future work,
they must be consistently charged to each account from project to project [10]. Thus,
codes of accounts are typically standardized, and the accounts used for each project are
uniquely selected from the standard codes. The term “standard” should not be
misinterpreted, as there are no standards of practice. In reality, most contractors
develop their own standard codes that are uniquely tailored to their own mode of
operation.
Page | 8
Figure 1: Costing system to Support Cost Control
The hierarchical nature of cost codes is illustrated in Figure 2, which shows an
example of a code structure for a grass roots petrochemical facility [6]. Because the
emphasis is on isolating problem areas, the cost indicators allow for the charging of
expenditures to more narrowly defined areas such as direct costs, indirect costs,
subcontract costs, or home office costs. A four-digit activity code is divided into three
levels of detail. The first two digits define major activities or types of work and are
illustrated in Table 1. Table 2 shows the detailed subdivision of account 17xx, which is
aboveground non-racked piping. The cost classification code is used to further divide
the costs into direct labor, construction materials, construction equipment, and so
forth. In a comprehensive cost control system, numerous cost classification codes are
used.
Costing Systems to Support Estimating
The costing systems used only to support the estimating function are less
sophisticated and not as detailed as those required for cost control. Figure 3 illustrates
the reason. As can be seen, there are no comparisons to projects estimates, no variance
analyses, and no feedback loop. The main emphasis is on accumulating costs at the
end of the job, so timeliness is not an issue, and minimal or no support staff is needed.
Also, quantities or progress are often not measured but rather are summarized at
project completion. These data may be extracted from the project estimate or contract
documents.
Page | 9
The code of accounts need not be as detailed as that required for cost control two
reasons. First, it is not necessary to divide the project into areas since the code of
accounts is not being used to isolate problem areas. Second, a contractor would prefer
to have certain components of work grouped into a single account. An example would
be piping plus related scaffolding and material handling. Groupings that include
similar work plus the manual direct and indirect support effort facilitate the need to
develop accurate estimates in a relatively short period of time.
The net result is that only part of the code of accounts shown in Figure 2 is
needed. The applicable portion is shown in Figure 4, where the 16 digit code used for
cost control has been reduced to 10 digits. The number of possible entries for the cost
classification part of the code would be greatly reduced, from 50 or more to probably
four or five. The number of cost indicators would probably be reduced as well.
PRODUCTIVITY CONTROL
Historically, productivity measurement and control have been done almost
exclusively as a subset of the larger, more detailed cost control systems. The literature
abounds with articles and advertisements that show how to monitor costs and
productivity using the cost control system [3, 5, 15, 19].
Ironically, the fact that these two control systems are typically viewed as one is
probably a main reason why many contractors do not measure productivity. To these
contractors, cost control systems are too large and complicated, require a support staff
dedicated to measuring and quantifying site activities, and result in an intolerable
overhead expense [5]. Alternatively, these contractors rely on the much simpler
accounting-type systems such as the one shown in Figures 3 and 4. However, these
provide little in the way of control.
Fortunately, productivity measurement can be greatly simplified while still
providing control. If comparisons are to be made with the project estimate, then
productivity control must originate from the same code of accounts as does the cost
control system. Thereafter, productivity measurement and control can be done
separately from the cost control system. This separation allows the freedom necessary
to tailor the system to perform a specific function. The result is a system that is simple,
timely, and inexpensive» The remainder of the chapter develops this concept through
an explanation of the desired goals needed to achieve the cost-effectiveness of the
system.
Page | 10
Figure 2: Cost Account Coding Structure for Cost Control [6]
Project Number: Identifies the Project. (4 digits)
Cost Indicator: (Summary Indicators) One – digit numbers that represent broad
general categories such as direct labor, indirect costs, subcontract costs, or home office
cost. (1 digit)
Area: Designation is reserved for project numbers which relate to geographical
area, process unit, and so forth. (4 digits)
Activity: That part of the code of accounts used to describe a physical item of
work task to be performed. Example activities include piping, duct, backfill, roofing,
and so forth. Activities are the primary labor accounts. (4 digits)
Cost Clarification: Used to categorize the origin of project costs in terms of craft
labor, indirect labor, construction equipment, construction materials, permanent
material, permanent plant equipment, and so forth. (3 digits)
Page | 11
Table 1. List of Major Activity Accounts for the Model Plant Petrochemical
Facility [6]
Account No. Description
01XX Site Preparation/Demolition/Salvage/Removal for Relocation
02XX Site Improvements
03XX Underground Electrical
04XX Underground Piping
07XX Piling
08XX Concrete and Excavation
12XX Structural Steel
15XX Building Construction (Petroleum & Chemical Projects).
16XX Aboveground (Racked Outside Overhead) Piping
17XX Aboveground Non-racked Piping
18XX Aboveground Electrical
19XX Instrumentation
20XX Insulation
21XX Painting
23XX Paving
24XX Ducts
4XXX Major Equipment
Page | 12
Table 2. Detailed Subdivision for Aboveground Non-racked Piping Activities [6]
Account
Number Description
Unit of
Measure
17XX ABOVE GROUND NONRAKED PIPING
170X Material for aboveground non-racked piping -
1711 Prefab pipe outside shops Lump Sum
172X Spool Fabrication
1721 Spool fabrication - carbon steel 2 in- and under Linear Feet
1722 Spool fabrication - carbon steel 2 1/2 to 12 in. Linear Feet
1723 Spool fabrication - carbon steel 14 in. and above Linear Feet
1724 Spool fabrication - alloy 2 in, and under Linear Feet
1725 Spool fabrication - alloy 2 ½ to 12 in. Linear Feet
1726 Spool fabrication ~ alloy 14 in. and above Linear Feet
1727 Spool fabrication - other than carbon steel and alloy Linear Feet
1728 Hanger and support fabrication Lump Sum
173X Spool Erection and Field Run Pipe
1731 Spool erection - carbon steel and alloy 2 in. and under Linear Feet
1732 Spool erection - carbon steel and alloy 2 1/2 to 12 in Linear Feet
1733 Spool erection - carbon steel and alloy 14 in. and above Linear Feet
1734 Spool erection - other than carbon steel and alloy Linear Feet
1735 Field run pipe - 2 in. and under Linear Feet
1736 Field run pipe - above 2 in. Linear Feet
1737 Hangers and supports Linear Feet
1738 Testing x-ray, cleaning and pickling and stress relieving Lump Sum
1795 Sketching and material takeoff Lump Sum
1796 Piping materials Lump Sum
1797 Scaffolding Lump Sum
Page | 14
Figure 4. Cost Account Coding Structure for Estimating
Project Number Identifies the Project. (4 digits)
Cost Indicators (Summary Indicators) One-digit numbers that represent broad
general categories such as direct labor, indirect costs, subcontract costs, c hone office
costs. (1 digit)
Activity That part of the code of accounts used to describe a physical item of work
or work task to be performed. Example activities include piping, duct, backfill,
roofing, and so forth. Activities are the primary labor accounts. (4 digits)
Cost Classification Used to categorize the origin of project costs in terms of
craft labor, indirect labor, construction equipment, construction materials, permanent
material, permanent plant equipment, and so forth. (1 digit)
Denotes the unused portion of the cost code
Track Only Important Activities
It is recognized that, on any given project, most of the work-hours ^are consumed
by a small number of activities. If one controls these activities, he essentially controls
most of the project people resources. The problem inherent with cost control systems
is that they are designed to track all project expenditures. This means that the
contractor needs to measure the output over the total project before he can extract
information about the activities that are truly important. Additional overhead staffs are
often needed to operate the system and to interpret the results. Understandably,
contractors who are not ■ accustomed to measuring productivity are not eager to count
light fixtures, doors, ladders, handrails, valves, pipe hangers, and the thousands of
other minor items that must be installed, 3y tracking productivity separately, the
contractor can choose to monitor only those activities that he feels are important.
Simplify the Code of Accounts
To many contractors, codes of account structures like the ore illustrated in Figure
2 are overly complex. They require detailed narratives of what to include in each
account, and considerable tine may be needed to reconcile errors resulting from costs
being charged-to the wrong account, "When tracking is done separately from the cost
control system/ field personnel need to deal only with the four-digit labor accounts as
shown in Figure 5.
Page | 15
Tailor the Level of Detail
The level of detail in the code of accounts is typically established on the basis of
costs and does not always fully support the productivity control needs. Two examples
illustrate this point. The cost of 6-inch-KHameter stainless steel pipe is different from
that of 2 1/2-inch-diameter carbon steel pipe. In the cost control system, these
commodities are tracked separately. But, from the productivity measurement
viewpoint, the two may be nearly identical. Furthermore, a crew may install several
types of pipe in a single day, thus requiring that the quantities and work-hours be
reported by type. Thus, the costing system places an added burden on a reporting
system that contains more information than may be required for productivity control.
Figure 5. Codes for Productivity Measurement
Activity That part of the code of accounts used to describe a physical item of
work or work task to be performed. Example activities include piping, duct, backfill,
roofing, and so forth. Activities are the primary labor accounts and are thus the
productivity codes. (4 digits)
Denotes the unused portion of the cost code
In the second example, the unit cost difference of structural steel for commercial
multistory and structural steel for warehouse-type buildings may be sufficiently minor
to allow the two to be included in the same cost account. However, the units work-
hours for erection maybe very different. In this case, productivity control requires a
level of detail not available in the costing system. As illustrated in these two examples,
cost control and productivity measurement sometimes require different levels of detail.
Separate tracking allows the flexibility to meet the particular, needs at hand.
Simplify Units of Measure
The units of measure are established by a cost engineer or estimator for his own
particular need* Structural steel is purchased by the ton, so the measurement of
installed quantities is also by the ton. A foreman or superintendent can easily
determine how many pieces of structural steel have been erected and bolted, but to
convert these pieces to tons requires considerable time to study the drawings and to
make calculations. Likewise, an estimator determines the number of pipe hangers on
the basis of so many hangers per linear foot of pipe. Field personnel may know how
many hangers were installed, but, without measuring or studying the isometric
drawing, they will not readily know the footage. Thus, the units of measure used to
Page | 16
support estimating or cost control can sometimes place added burdens on field
personnel by requiring excessive measurement and quantification of the work.
Reduce the Amount of Data
Cost control systems handle sizeable amounts of data. The output generated is
typically in the form of summary statistics or numerical-data. Field supervisors who
would normally make use of productivity data have limited time or enthusiasm for
studying the numbers to make inferences about the progress of their work. Graphical
analyses enhance the ability to quickly interpret information, but, in some cost control
systems, the main emphasis is on generating numerical data, not graphs. The
timeliness of feedback is another concern. Consequently, some cost-control systems
provide information to field personnel in a form that is difficult to interpret, and which
may arrive too late to be of value.
SUMMARY
This chapter has shown that the level of detail in a costing system is related to how
the system is used. Many small- and medium-sized contractors want to collect only
historical estimating data. Their systems are simple and can be used with minimal
overhead expense. However, a system used for cost control purposes is far more
complex and expensive to operate.
Most contractors associate productivity measurement with cost control, but
productivity can be monitored and controlled separately from the cost control system,
and this means of measurement is recommended. Cost-control systems track
everything? Productivity control monitors only a few items controlling the work. The
level of detail needed for productivity control is not always the same as for cost
control. The units of measure are established by cost engineers and estimators, and
these often place unnecessary demands on field personnel for measuring and
quantifying their work. The feedback in cost control systems is sometimes in the form
of numerical data, whereas many field personnel having minimal experience with
measuring productivity prefer graphical output.
Page | 17
CHAPTER 3
CONCEPTUAL DESIGN OF THE PRODUCTIVITY
MEASUREMENT SYSTEM
The productivity measurement and performance evaluation system developed
herein for: 1- Small and medium-sized contractors who do not routinely measure
productivity and 2 - The larger and more sophisticated contractors who are
constructing projects for which the project budget prevents the use of a detailed and
expensive cost control system. Project can be commercial or industrial, or other types
which include labor-intensive activities. Maintenance and outage-type work are also
ideally suited for the productivity measurement system.
BASIS FOR SYSTEM DEVELOPMENT
Project Characteristics
On most commercial projects, the overhead expenses must be kept to a minimum.
The same situation prevails in the heavy industrial sector of the industry. The mega
projects of the 1970s are no longer being built, and shorter and smaller projects place
special demands on cost-control systems such as the one described in Chapter 2. The
structure of the code of accounts makes it difficult to reduce project overhead by
simply reducing the scope of the cost control system. While the support staff can be
trimmed, the need for some support will always exist. Activity durations today are
shorter then they have been in the past. Important controlling activities sometimes last
only 30-60 days. If effective control is to be exercised, feedback must occur quickly.
Even a two-week reporting cycle (most projects function on a monthly reporting cycle)
provides reporting probably too infrequently.
The need to reduce overhead means that quantity tracking must be provided by
those who are responsible for doing the work. Lower level supervisors are neither
accustomed to working with intricate cost codes like the one shown in Figure 2, nor
are they anxious to spend the time necessary to perform anything more than
elementary measurements. Unfortunately, these are the elements needed to drive the
cost control system.
Assumptions
The design of the productivity measurement system must consider the essential
features of cost control system as described in Chapter 2 and relate these to the
environment in which it must function. Therefore, the following assumptions are
presented as the basis for developing the productivity measurement system.
1. The productivity measurement system must be structured around the code of
accounts if comparisons to the project estimate are to be made. However, the tracking
and feedback can be done separately from the costing system.
2. A contractor’s code of account establishes the basis for deciding which activities to monitor. If the codes are too broad to support effective monitoring, the
system can still function as a stand-alone system. However, comparisons to project
estimates may not be possible.
3. Systems presently used by contractors to track or control costs are which
unaffected by the productivity measurement system.
Page | 18
4. The contractor is not required to install a cost control system in order to
measure and control productivity.
5. The productivity measurement system can operate independently from the
estimating or schedule control system. Productivity measurement can yield worthwhile
results, even if one do not have a work-hour, quantity or schedule estimate. However,
performance cannot be evaluated without these estimates.
6. Only direct labor accounts are of interest. The most cost-effective which
approaches to productivity control is to concentrate on the labor-intensive activities.
Such activities are a small percentage of the total number of activities, yet they have
the greatest effort on the project.
7. The focus of the measurement effort is at the crew level.
8. The system is implementable at the job site and able to be done manually.
However, if a microcomputer is available, it will facilitate this task.
System criteria
The assumptions listed provide guidance for developing the productivity
measurement system. The system should satisfy the following criteria:
1. Inexpensive - The system should be easy to implement, require little overhead
to operate, and have the capability to be manually driven
2. Simple – The data requirements should be minimal. Reporting should be done
by foremen using easy-to-comprehend units of measure; output should make liberal
use of graphics.
3. Flexibility – The system should be easily tailored to the operational needs and
objectives of the contractor. Rigid, inflexible systems, which require the contractor
instead, to adjust his mode of operation to the system, are undesirable.
4. Accuracy – The output must reflect what actually occurs at the site. The level of
detail should help to isolate problem areas.
5. Timeliness – Feedback must be given quickly so that corrective action can be
taken on short-duration activities. End-of-the-day feedback is possible, if it is
desirable, thus summaries can be produced weekly. Otherwise, feedback can be
provided at a frequency consistent with the scope and magnitude of the project.
6. Support Performance Evaluation – Labor comparisons to the project estimate
should be possible. This includes comparisons to the estimated work-hours, quantities,
unit rate, and planned duration for labor-intensive activities.
Page | 19
FRAMEWORK FOR PRODUCTIVITY MEASUREMENT
The above criteria have been used in developing the productivity measurement
system that is described throughout the remainder of this manual.
Reporting Requirements
The reporting system relies upon the input of two data items namely work-hours
and quantities (progress) for selected labor-intensive activities. The data collection and
analysis process are shown in Figure 6.
The foreman, on a daily basis, records the work-hours spent by a crew in
performing the particular task in question and the quantities installed or progress made
by the crew that day. Generally, the reporting of work-hours is done for payroll
purpose, so productivity measurement imposes no new work-hour reporting
requirement. The only possible change in reporting work-hours maybe reported
separately those work-hours spent on the activity being-monitored.
The reporting of quantities, or progress, is not routinely done by many contractors.
However, the knowledge of how much work has been done which is a fundamental
requirement for monitoring and control. The quantity-reporting scheme developed
herein, and described in detail in Chapter 4, is simple, is done for only a small number
of labor-intensive activities, is characterized be easy-to-use units of measure, and can
be easily and quickly summarized by the foreman at the end of the day.
As shown in Figure 6, productivity calculations are made using the reported work-
hours and quantities. These calculations can be done manually, but the most efficient
approach is to use a microcomputer. Input can be done by a clerk or time keeper.
Because the amount of data input is miniscule, the entire entry and analysis process
involves minimal effort and time. Feedback should be almost instantaneous, and
computer programmers, systems operators. Quantity surveyors or data entry personnel
are unnecessary.
Relationship to Other Accounting or Control Systems
Productivity measurement is designed to be a stand-alone system that is
implemented entirely at the job site. Nevertheless, it is related to several other control
and accounting systems. As shown in Figure 7, the productivity measurement system
utilizes information available from other systems but does not provide feedback to
these systems.
The selection of activities to monitor should be made according to the breakdown
of project activities established by the costing system. The reason for this is quite
simple work-hour reporting will be done this way for both payroll and cost-accounting
purposes. Productivity measurement then can rely on the same work-hour data that is
necessary if comparisons to the project estimate are needed. Where cost accounting
and monitoring systems are already in place, a definition already exists of the items
included in each account, and dual reporting would merely increase the confusion and
amount of paperwork.
Page | 22
Data from the cost accounting and control system are used to prepare project
estimates. Several important pieces of data from the estimate can be used to enhance
the productivity measurement system. These items are the estimated total work-hours
and quantities. The estimated unit rate can also be calculated. These parameters
provide important baselines for comparing current performance.
Although schedule control is generally viewed as separate from cost or
productivity control, productivity and quantity installation rates are an integral part of
predicting completion dates. Therefore, if available, the planned completion date or
estimated duration can be used to evaluate performance.
Selection of activities to monitor
The activities that should be monitored are the ones which affect the success of the
project. To maintain simplicity and minimize project overhead, only those activities
that affect the success of the project should be tracked, those that are labor-intensive.
The labor-intensive activities tend to have the longest durations and therefore are
critical form the schedule point of view.
Often, activities to monitor can be selected on the basis of experience. An
alternative approach is to calculate the total project work-hours and to divide this sum
by the number of line items or accounts. This calculation yields the average work-
hours per line item. Those items or accounts for which the estimated work-hours are
greater than this average can be designated as labor-intensive. This method usually
results in less than one-fourth of the line items or accounts being significant. This list
can be further modified at the prerogative of the manager.
Development of productivity codes
The project code of accounts is structured to support the cost control or accounting
function. However, productivity control is comparatively simple and narrower in
scope. Thus, productivity code structures for industrial and commercial construction
are discussed below.
Figure 5 shows how a 16-digit cost code used for the construction of
petrochemical facilities can be reduced to four digits. The four-digit activity code is
ideally suited for productivity control. This four-digit productivity code defines three
levels of detail. The broadest level, represented by the first two digits, denotes major
construction activities such as aboveground electrical, aboveground non-racked piping,
and so forth. Table 1 provides a complete listing of the 17 major activities. The third
and fourth digits further subdivide each major activity. Figure 8 illustrates the
productivity code for the erection of aboveground conduit. A fifth digit (not shown)
can be added at the user’s discretion to further define the conduit by size or type.
Figure 8. Structure of Productivity Measurement Codes for Industrial
Construction
18 1 2
SUBFEATURE LEVEL
1. Aboveground Conduit
FEATURE LEVEL
2. Electrical Raceways
MAJOR ACTIVITY OR FUNCTION LEVEL
2. Electrical Raceways
Page | 23
The structure of example of productivity measurement code for commercial
constructions is shown in figure 9 to be a five-digit code. The code number represents
structural formwork for concrete columns. The code structure is based upon the master
format published by the construction specifications institute (CSI) [12]. The major
activity or function level is denoted by the first two digits. Among the major activities
is concrete, masonry, metals, mechanical, and electrical work. The remaining three
levels further subdivide the major activities by size and type of work.
Once the code structure has been established, it is necessary to develop the
various project accounts, which is accomplished by examining the complete code of
accounts and identifying likely labor-intensive accounts and identifying likely labor-
intensive activities. The non-labor-intensive accounts and others involving incidental
work can be deleted. The remaining accounts form the productivity measurement
codes. Representative codes are listed in appendices A and B for industrial and
commercial construction, respectively. The total number of accounts has been reduced
by a factor of more than four or five.
Unit of measure
The units of measure should be simple and easy to apply and should not burden
field personnel with unnecessary or time-consuming measurements. Convenient
counting schemes are desirable, and the units of measure must be selected so that
results are accurate.
In most instances, the same units used in the costing system can be used in the
productivity measurement system. However, there are exceptions. The following
partial list shows some of the accounts where the units of measure may be different:
Alternative Units of measure
Item of
work Cost Control Productivity measurement
Structural Steel Ton Piece, level, or tons
Pipe Hangers Linear feet Each
HVAC Duct Ton Linear feet
Sheet Piling Ton Linear feet
Column
Formwork
Square feet of
contract area
Linear feet, each, or square feet of
contract area
Obviously, the units in the costing system reflect how materials are purchased,
whereas, in the productivity system, they should relate to how components are
installed, units can vary from project to project.
Page | 24
Figure 8. Structure of Productivity Measurement Codes for Commercial
Construction
SUMMARY
This chapter has presented the framework for the productivity measurement
system that satisfies five criteria determined by the characteristics of the project and
the field supervisors who must rely upon the system. Crew level reporting is required
on a daily basis, and only labor –intensive activities are monitored. The productivity
measurement codes originate from the code of accounts designed for cost control
purposes, but the number of accounts is greatly reduced by eliminating non-labor-
intensive codes. In some instances, the units of measure have been changed to more
closely reflect how components are installed. Because the productivity measurement
system is not needed to provide feedback to other control systems, it is flexible and
can be tailored to suit particular project needs.
1 1 3
TYPE
1 Slab on grade
2 Elevated Slab
3 Colums4 Footers7 Beams
FEATURE LEVEL
1 Formwork
MAJOR ACTIVITY OR FUNCTION LEVEL03 Concrete
FEATURE LEVEL
1 Structural
03
Page | 25
PART II – BASIC CONCEPTS OFPRODUCTIVITY MEASUREMENT
AND PERFORMANCE EVALUATION
Productivity measurement and performance evaluation are two separate functions.
Productivity measurement involves the collection of information about various
activities. Specifically, production and the corresponding work-hours over o given
period of time are assigned to their respective activities or accounts, and these data can
be examined to determine if productivity is improving or declining.
Performance evaluation, on the other hand, involves a comparative analysis.
Work-hours, quantities, and productivity are evaluated against the planned values used
in the original project estimate. Activity durations can be projected and compared with
the planned or required completion dates of the activities.
Part II of this manual introduces the simplified concepts of productivity
measurement and performance evaluation. Chapter 4 describes five simple concepts of
measuring quantities and provides guidelines for selecting an appropriate measurement
method. The tracking of work-hours is also addressed. Chapter 5 shows how
productivity can be reported. Various calculations and formats are giving, and their
interpretations are illustrated. Principles of performance evaluation are given in
chapter 6, which also explains how to develop work-hour and productivity forecasts.
Page | 26
CHAPTER 4
MEASUREMENT OF QUANTITIES AND WORK-HOURS
INTRODUCTION
The tracking of work-hours alone is inadequate as a monitoring or control measure
because work-hours must be evaluated in the context of the amount of completed
physical work. It follows that effective project monitoring requires the measurement
of both the quantities and the work-hours needed to install these quantities (2, 13, 15,
16) The first part of this two-part chapter describes the basic principles of quantity
measurement (surveying), and the last part addresses the measurement of work-hours.
SIMPLICITY: THE CORNER STONE OF EFFECTIVE MEASUREMENT
Simplicity and effectiveness may at first seem to involve trade-offs, but, in reality,
the two features support each other. When concepts are simple, they are readily
understood. If a technique is simple, and therefore readily understood, it will be easy
to use, and its acceptance and application in a variety of situations will be more likely.
This simplicity encourages users to tailor the technique to their particular needs,
resulting in effective measurement.
Throughout this manual, simplicity has been integrated into the conceptual design
of the system. The most important advancement toward simplicity is the separation of
the productivity measurement system from the cost control system, making possible a
substantial reduction in the number a complexity of cost accounts and the use of
simple and convenient units of measure. These principles were described in Chapter 3
and were used to develop the productivity codes in Appendices A and B.
Freedom from the costing system also means that monitoring can be done the job
site without a need for support personnel. Feedback can be obtaining daily rather than
weekly or monthly. The conciseness of the data means it can be readily digested by the
project superintendent or foreman. Each these aspects are illustrated throughout the
remaining chapters in this manual
PRELIMINARY CONSIDERATIONS
When designing productivity control system for a Specific project, two
preliminary considerations must be made: the selection of the activities the will be
monitored and the level of detail in reporting.
Not all productivity codes are needed to establish effective project control; only
the codes important to the particular project should be used. While no conclusive rules
can be established, consideration should be given activities that are labor-intensive,
last long enough for corrective action be taken, and are interrelated with other
activities. If available, a CPM schedule can be used to identify activities with little or
no float time. Activities should be selected after considering the scope, complexity,
and duration of the work.
The level of detail relates to the scope of work for a particular activity and can
vary from project to project. Three illustrations of labor-intensive activities are given
below. The first involves pipe spool erection and field run pipe on a process facility,
and the second activity is structural steel erection on an office building. The last
Page | 27
activity is cable pulling on a refinery project. The following levels of detail selected
from Appendices A and B are possible:
1. Pipe spool erection on a process plant
17XX ABOVEGROUND NONRACKED PIPING
1730 Spool Erection and Field Run Pipe
1732 Spool Erection, 2 1/2 to 12 in.
1735 Field Run, 2 in. and under
2. Structural steel erection on an office building
05XXX METALS
05100 Structural Framing
05120 Structural Steel
05121 Multistory Type
05122 Warehouse Type
3. Cable pulling on a refinery project
18XX ABOVEGROUND ELECTRICAL
1830 Wire and Cable Installation
1831 Wire and Cable in Conduit
1832 Wire and Cable in Tray
As can be seen, several levels of detail can be used for each activity. The choice is
a matter of selecting the lowest level of detail that is consistent with the needed level
of control over the work. Obviously, not all activities will be monitored at the same
level of detail. Each of the three activities listed above will be used to illustrate
measurement concepts in subsequent discussions.
Page | 28
MEASURING THE AMOUNT OF WORK COMPLETED
How the amount of work completed is determined for a particular activity depends
upon the nature of the work and the particular control needs of the project. The
principal methods available for measuring quantities are
1. Units completed - Quantity surveys or physical measurement of work items are
involved in this method, which is best suited for situations where items can be easily
and quickly measured or counted, like cubic yards of excavation or number of ceiling
tiles in place.
2. Percent complete - A subjective evaluation is made by the foreman or
supervisor.
3. Level of effort - This method relies on predetermined rules to give appropriate
credit for partially completed work that must evolve through several stages. For
example, the stages of formwork are erection, alignment, tightening, stripping, and
cleaning. This method often used for bulk commodity items.
4. Incremental milestones - This variation of the level of effort method is used
where specific milestones can be identified, but quantities of output cannot be easily
measured. An example application is for equipment installation, alignment, and
testing.
5. Start/finish percentages - In this method, another variation of the level of
effort method, the only milestone or phases are starting and finishing.
Each of these methods is described in detail in subsequent paragraphs, and
examples illustrate the type of work for which each method is best suited.
Units Completed (Physical Measurement)
The simplest method of measuring output is to actually measure or count the units
of work completed. For example, one can physically measure how man feet of cable,
cubic yards of excavation, inches of weld, square feet of concrete block wall, or
number of plumbing fixtures which have been completed In a typical commercial or
industrial facility, there are numerous items or activities for which this simple but
effective method can be applied.
Several criteria exist for the proper application of the unit complete method.
These are summarized in Table 3. The scope of the work must be well defined and
relatively straightforward so that the number of output unit and their status can be
quickly ascertained. The units completed method is best applied where the work does
not include a mix of subtasks or where, if i does include a mix, these subtasks are few
in number and can be accomplished in a relatively short time frame.
For example, cable pulling is measured in terms of linear feet of cable pulled. The
scope of work is well defined, and the quantities installed can be quickly determined
from the pull ticket or pulling schedule. Cable pull is straightforward because the work
does not involve subtasks.
The placement of concrete for a slab on grade is a task which involves the subtasks
of placing, vibrating, and finishing- Although three subtasks are involved, all are
measured against cubic yards of concrete in place since the three are executed
simultaneously. The units completed method can be applied to concrete placement
because the quantity is readily measurable.
Page | 29
Table 3. Comparison of Various Methods of Quantity Measurement
Method Criteria Advantages Disadvantages
Units completed
Well-defined scope
Output determined quickly by counting or elementary math
Relatively few subtasks- Short duration for completing each unit of output Single craft or trade
Most detailed and accurate Does not rely on subjective opinions or evaluations Claimed output can be readily verified
Cost and accuracy of data
collection if misapplied
Percent complete
(Supervisor opinion)
Relatively minor tasks where reasonably accurate estimates can be made
Simple
Inexpensive
Quick
Can be very inaccurate and misleading
Level of Effort
Activities involving overlapping subtasks. Subtasks must be measurable or their status easily defined. Best suited where there is a large number of similar items, and the work will be ongoing for an extended period of time.
Greater detail and objectivity than simply estimating how work was done and less expensive than counting or measuring the units completed
More involved than simply estimating the percent complete
Incremental Milestone
Best suited where there are only a few item each subtask is difficult to measure, and the work may lost for an extended period of time
Easy to use
Simple to understand
Long periods may elapse before an intermediate milestone is reached
Start/ Finish
Percentages
Activity lacks intermediate milestone Activity of item of work should be of short duration
Work best for a large number of item
Simple
May be inaccurate, especially if there are few item of if the activity duration is length.
Page | 30
Another criterion for using the units completed method is that the time needed to
perform the completed installation of an individual unit of output should be relatively
short, say a day or less. Trench excavation and the hanging of doors would qualify,
whereas the testing of a piping system or the installation and alignment of equipment
probably would not. Also, work involving multiple crafts is often not well suited to the
units completed method because it can seldom be completed in a day.
The primary advantage of the units completed method is that, when properly
applied, it is the most accurate and therefore reliable method available. It is a
relatively objective method because it does not require a subjective opinion to
determine what has been completed. A third advantage of this method is that an audit
of the reported production is easily accommodated. The main problem with the units
completed method is the cost of data collection when the method is improperly
applied.
It is worth noting that pipe fabrication shops can use this method of measuring
output because there is commonality among many items. Since the fabrication shop is
responsible for a relatively narrow scope of work (bulk quantity items), the breadth of
the reporting system could be reduced without significant increases in manpower or
cost requirements.
Percent Complete (Supervisor Opinion) Method
A simple subjective approach is to ask the supervisor's opinion of the percentage
of the task which is completed. It is useful for relatively minor tasks, usually of short
duration, where development of a more complicated intermediate milestone or level of
effort formula is not justified. Painting, dewatering, architectural trimming, and
landscaping are candidates for this approach.
Level of Effort
A control system requiring the physical measurement of numerous items of work
would too burdensome and costly. One way to simplify the measurement process is to
assign a predetermined percent complete to a task on the basis of the completion of
various subtasks. The percentage is based upon the relative work-hours required to
complete each subtask.
To illustrate the level of effort method, the following example is considered in
which a contractor must install 1,708 small-bore pipe hangers. The following list of
subtasks involved shows the relative level of effort required for each. The relative
level of effort, or weighted completion status, is defined as rules of credit.
Subtask Unit of measure Rules of Credit
Fabricate each 0.40
Install each 0.50
Pre-service inspection each 0.10
Total task each 1.00
Page | 31
If, at sore point in time, 366 hangers have been fabricated, 185 installed, and 41
inspected, then the cumulative number of hangers completed is calculated as follows:
Cumulative Quantity (each) = 366 (0.40) + 185 (0.50) + 41 (0.10) (1)
= 243.0
The subtasks are selected so that the status can be easily determined by the
foreman, and no credit is given until the subtask is finished. The rules of credit remain
the same for all items of work within a given category or account. In this example,
they would be the same for all small-bore hangers, irrespective of the type or size of
hanger.
In another example, a contractor installs modular formwork for a reinforced
concrete basement wall. First, the outside form is erected, braced, and aligned. The
inside form is erected next. Thereafter, the two forms are braced, shored, and plumbed
as a unit. After the concrete placement, the form are stripped, cleaned, and oiled.
Example rules of credit for this task are given below·
Subtask Unit of Measure Rule of credit
Erect initial wall form ft2 0.90
Erect second wall form ft2 0.70
Final bracing and plumbing ft2 0.10
Strip and clean ft2 0.10
Total tasks ft2
The crew cannot take full credit for the work until after the forms have been
removed and cleaned. Notice that the sum of the rules does not add to l.00. This is
because the first = subtasks are applied to only half the total wall area.
A somewhat more detailed example involves the erection of piping isometrics.
Figure 10 shows the daily quantity report in which the Forman reports the status of
four isometrics. The rules of credit for pipe erection are presented below:
Page | 32
Daily quantity report
Pipe erection 163X and 173X
Foreman: Smith Page: 1 of 1
Date: Project: 8609
Office code: 2-0007
Status of work: List quantity installed and check appropriate column 1, 2, or 3.
(1) Erected Count pipe erected in place but not bolted/welded completely.
(2) End connections complete count pipe end connections completed bolted/welded
in place.
(3) Trimmed and complete Count Pipe completed and ready for test.
Isometric
drawing # Account #
Status of work Total
quantity
to be
installed
(ft)
Pipe
size
(in.)
Cumulative
quantity
installed to
date
(ft) (1) (2) (3)
A-267-30 Spool 1732 X 20 10 20
A-267-32 Spool 1732 X X 36 3 36
0-527-43 Field run
1735 X 231 1/2 200
0-527-43 Field run
1735 X X 231 1/2 147
0-819-02 Field run
1735 X X X 10 1-1/2 10
Figure 10: Daily quantity report
Page | 33
Subtask Unit of measure Rules of credit
Erected ft 0.30
Connections complete ft 0.50
Trimmed ft 0.20
Total task ft 1.00
Figure 10 shows that, for isometric drawing #A-267-30, the entire 20 feet have
been erected. The end connections on isometric #A-267-32 have been completed for
entire 36 feet. The last isometric, #0-819-02, has been entirely finished. However, for
the third isometric (drawing #0-527-43), 200 of 231 feet have been erected, but only
147 feet of the system have the connections completely bolted. The cumulative
footage is calculated as:
Cumulative quantity = 20 (0.30) + 36 (0.30 +0.50) + 200 (0.30) + 147 (0.50) +
10(0.30 + 0.50 + 0.20)
= 178.3 feet (2)
In the above example, the quantities for each of the subtasks are counted the same
way. This will not always be the case, as is illustrated by structural steel building:
Subtask Unit of measure Rules of credit
Erecting Individual pieces 0.50
Bolting (bolt-up) Individual pieces 0.25
Plumbing Pieces grouped by tier 0.15
Tightening (torque bolts) Pieces grouped by tier 0.10
Total task piece 1.00
In this example, output is measured by the number of pieces, i.e. , beams and
columns. Incidental pieces like gusset plates, tie rods, etc., are not counted. Plumbing
is done by tier, and as each tier is completed, the crew is credited for 15 percent of the
pieces associated with that particular tier. Likewise, tightening of high-strength bolts is
tracked according to the pieces per tier.
Importance of rules of credit
Rules of credit are used to specify the installation status of many commodity items
or components. The rules recognize partially completed work and provide an accurate
completion status without the added expense of detailed physical measurements. To
illustrate the influence of rules of credit on the accuracy of output measurements, the
situation represented in Figure 11 shows the cumulative work-hours per piece of
structural steel as a function of time. The task involved the structural steel erection of a
Page | 34
six-story building. As can be seen, when rules of credit are not applied, the manager
receives an overly optimistic view of the work. In this particular project, the last eight
work days were devoted exclusively to plumbing and tightening. Once all of the steel
was erected, the activity took almost 50 percent more time to finish, and the work-
hours per piece increased by about 40 percent. It should be obvious that, for some
items, progress and productivity cannot be accurately measured without the
application of rules of credit.
Fortunately, rules of credit are not complicated. Table 4 shows example rules for
various commodity items. In general, no more than three to five subtasks should be
considered. Each contractor develops a unique set of rules, which can remain
unchanged from project to project.
0
DAY
Figure 11. Implication of not using rules of credit,
structural steel erection (Account 05121)
CU
MU
LA
TIV
E Q
UA
NT
ITIE
S (
PIE
CE
S)
10 20 300
200
400
600
800 WITHOUT RULES OF CREDIT
WITH RULES OF CREDIT
RULES OF CREDITSTRUCTURAL STEEL ERECTION
ERECTING 50%BOLTING 25%PLUMBING 15%TIGHTENING 10%
Page | 35
Criteria
The level of effort method should be used when the manner in which credit is
awarded for partially completed work can lead to misleading interpretation of
progress, productivity, and performance. From the previous examples, it should be
readily apparent that the level of effort method is best suited for those activities that
involve a number of overlapping subtasks. These subtasks may include more than one
craft, but, obviously, each subtask must be measurable. As illustrated by the structural
steel example, measurement concepts can be simplified. To be used effectively, the
status of subtasks must be easy to determine: e.g., a valve has been accepted; a cable,
terminated; or a piece of pipe, aligned. Finally, the level of effort method is well suited
for tasks where there is a large number of similar commodity items and for task that
may be in progress for an extended period of time.
Advantages and Disadvantages
The principle advantage of the level of effort method is that it allows one to obtain
greater objectivity and accuracy than by merely estimating the percent complete, yet it
is not as detailed (and, consequently, time-consuming and costly) as the units
completed method. The main disadvantage is that it can increase the complexity of the
reporting system for some items.
Incremental Milestone
The incremental milestone method of measurement is a variation of the level of
effort method and is characterized by the identification of a series of intermediate
milestones. A predetermined percent complete is associated with each milestone, as is
illustrated in Figure 12, with shows the sequence of installation of a major vessel in a
power plant. This method can be used when only a few items must be considered or
when the subtasks are difficult to measure and the task will take an extended period of
time to complete. In Figure 12, the subtasks are sequential rather than concurrent.
Start/Finish percentages
This method is applicable to task which lack readily definable intermediate
milestones or for which the effort in terms of work-hours required is very difficult to
estimate. It is best suited to short-duration tasks like valve installations. With the
start/finish method, one arbitrarily assigns a percent complete to the start of a task.
Zero is often used, but it can be 20 percent or even 50 percent. When the item is
complete, 100 percent completion is credited. No intermediate percentages are used
because subtasks cannot be identified.
Millwright or mechanical work is sometimes monitored in this way. For example,
alignment of a major fan and motor may take from a few hours to a few weeks,
depending upon the complexity. All one knows for certain is when the work starts and
when it is finished.
Other examples include flushing and cleaning, testing, and major rig operations.
To effectively use this method, the activities or items of work should be of relatively
short duration. Also, a large number of items will tend to reduce the inaccuracies
apparent in the approach.
Page | 36
Task or
commodity
Unit of
measure Rules of credit Description
Mechanical
equipment each
15% set
45% installed
40% accepted
On or near location in building
Bolted, welded, or released for grout
QC accepted after final alignment
and complete hookup
Pipe spool
or field run
pipe
spool or
feet
60% erected
30% welded/bolted
10% accepted
in place to rough line and grade with
fit-up lugs at all welds
all field welds/bolted completed and
accepted
tested and accepted by QC
Electrical
termination each
70% terminated
30% accepted
Terminations completed cable on
both ends and accepted by QC
Tested and accepted by QC
HVAC feet
40% erected
40% connected
20% accepted
In place on permanent hangers
All flanges connected and sealed
Testing and balancing completed;
installation accepted by QC
Pipe hanger
(small-bore) each
40% fabricated
50% installed
10% accepted
Shakeout; shop or field assembly
Attached to support and completely
secured to pipe
Accepted by QC
Masonry
(foundation
wall,
reinforced,
grouted)
square
feet of
wall
70% block
placement
20%grouting
10% paging
Placement of concrete masonry units
Placement of reinforcement and
grouting
Paging of the outside wall
Structural
steel (bolted
connections)
pieces
50% erection
25% bolting
15% plumbing
10% tightening of
bolts
Beam and columns in place
All bolts installed in joints and
connections
Each floor or tier plumbed and
aligned
Final tightening of bolts with impact
wrench
Page | 37
Figure 12. Large equipment installation – incremental milestone
Selection of an appropriate method
The selection of an appropriate method of measurement is relatively simple. For
instance, the incremental milestone and the start/finish percentages methods are
applied in situations where the subtasks are difficult to define or measure. Equipment
installation, alignment, and testing were cited as examples of tasks for which these
methods can be tracked more accurately using other methods. Thus, there are three
primary methods remaining from which to choose: the units completed, level of effort,
and percent completed methods.
In developing a measurement system, the overriding concern is that the system
works for the manager, and not that the manager works for the system. In selecting a
method, four criteria should be considered: Simplicity, degree of control needed,
project complexity, and project scope. The simplest method always be selected. It is
important that quantity measurements and, ultimately, productivity calculations reflect
what actually occurs on the project. The installation and calibration of instruments,
hanging of doors, and electrical terminations can be accomplished with little effort by
simply counting the units completed. On the other hand, it would be foolish to measure
the square footage of painted surface to determine progress. Estimating the percent
complete of painting provides equally useful information with much less effort.
The civil and bulk commodity items are usually labor-intensive and must be
closely monitored. Typically, these items require a significant number of work-hours,
involve the completion of several or more subtasks, utilize multiple crafts, and include
sub commodities of varying complexity. For example, an underground gravity flow
piping system contains pipe, catch basins, manholes, and valve boxes. Also, an
aboveground non racked piping system contains several sizes of pipes, valves, and
hangers. Actual measurement would be impractical and simple estimation of the
RECEIVED AT SITE
0%
50%
100%
SET
ALIGNED
INTERNALS INSTALLED
TESTED
ACCEPTED
Page | 38
percent complete would probably be inaccurate. Therefore, the level of effort method
is appropriate for many of the more important items.
Project complexity and scope are important considerations in selecting a method.
On small projects, or larger ones where the item in question is relatively minor, there
is little justification for establishing control measures based on the level of effort
method. Thus, instrument raceways might be tracked by the percent complete method
on a small job, whereas, on a larger one, the level of effort method may be used. If, on
the smaller job, the runs are straight and not particularly complex, for example, if clip
supports are used, then the units’ complete method can be easily applied.
The measurement methods and units of measure for the activities identified earlier
are:
1732 spool erection, 2 ½ to 12 in. (lin ft) level of effort
1735 field run pipe, 2 in and under (lin ft) level of effort
05121 multistory structural steel erection (piece) level of effort
1830 wire and cable in conduit and tray (lin ft) unit complete or start/finish
percentage
For pipe and steel erection, the level of effort method is chosen because each
involves several easy-to-define subtasks. Several days may elapse before a pipe
isometric is finished. The bolt tightening on structural steel may not occur until the end
of the task. Conversely, in cable pulling, each pull can normally be completed in a
single shift. The routing of cable from raceway to the termination or device will be
through short conduit runs that are already in place. The tracking of progress by
subtasks is not worth the effort. The unit of measure, linear feet, can be obtained from
the pull ticket. If the pulls are long and it is likely that many pulls will be incomplete at
the end of a shift, then the start/finish percentages method is suitable. If the conduit is
not installed and the cable must be coiled until later, then another approach, for
instance, the increment milestone method can be used.
Table 5 summarizes suggested methods of measurement for selected commercial
and industrial work.
REPORTING WORK-HOURS
Importance of Consistency
The reporting of work-hours is simpler than the measurement of quantities. All
that is needed is to assure that the work-hours are properly associated with the work
that is being performed. On a single project, the same coding system and level of detail
used to record quantities must be applied to the charging of work-hours as well. For
instance, if quantities of pipe are differentiated by size, then the work-hours must be
tracked in the same way. Thorough understanding of the productivity codes is
essential. If comparisons incorporated into the historical data file, then consistency is a
must. While the level of detail may vary from project to project, the definitions and
contents of the codes must be the same.
Page | 39
Reporting Work-hours to support Project Control
The total work-hours needed to construct a particular component can be divided
into seven categories. Figure 13 illustrates this concept for the spool erection and
installation of field run pipe. While this work normally is thought of as being mainly
part of the pipefitter craft, the figure shows that other workers also contribute to piping
activities. In some cost systems used primarily for estimating purpose, all of the work-
hours represented in.
Table 5. Suggested Methods of Quantity Measurement for Selected Items
Method of
Measurement General/Civil Mechanical Electrical
Units
Completed
Masonry partitions
excavation concrete
placement site
preparation piling
paving roofing siding
Plumbing fixture
pipe hangers
underground piping
shop fabrication of
bulk commodity
items insulation
Cable pulling
terminations lighting
fixtures underground
electrical
instrumentation
Percent
Complete
Painting backfill
architectural trim
landscaping and seeding
flooring scaffolding
special finishes
Plumbing systems
piping
Lighting systems
control wiring
Level of
effort
Structural steel concrete
formwork major
concrete pours masonry
systems
Piping isometrics
HVAC duct Cable tray conduit
Incremental
Milestone Cabinet and millwork
Equipment
installations
complex HVAC
systems
Control panels
transformers
Start/finish
percentages
Demolition salvage
major rigging operations
short duration activities
Flush, clean, and
tests of systems
short duration
millwright
alignment valve
installation
Start-up and testing
instrumentation
Page | 40
Figure 13. Distribution of work-hours for piping activities
Figure 13 are charged to the same account. This approach supports efficient and
accurate estimating. However, for productivity monitoring, the manager interested
mainly in the work-hours required for actual erection. Index productivity codes
presented in Appendices A and B have been intentionally simplified to track only
installation work-hours.
Figure 14 shows a foreman’s daily time sheet designed to efficiently record this
information. An example is shown for a nine-man electrician crew working a 10-hour
day. This forms that the crew worked 19 hours on pulling cable (account 1830), 12
hours on power hookups and terminations (account 1861), 33 hours on control
hookups and terminations (account 1862), and 16 hours on conduit (account 1821).
REPORTING FORMS
Work-hours reporting
The reporting of work-hours is straightforward because one can generally rely on
the existing payroll reporting system. Figure 14 exemplifies a typical reporting form.
In this case, the crew work-hours were charged to four productivity codes. The only
change to existing forms that may be need is a provision of space for recording the
productivity code.
Quantity Reporting
Many contractors are not accustomed to collecting quantity information, so new
forms must be developed. Quantity reporting forms should be simple easy to
understand and ensure accuracy of the information provided. Those activities
discussed throughout this chapter serve to illustrate the range of possibilities for
reporting forms.
The quantity reporting for cable pulling (account 1830) is very straightforward
because only the linear footage of the pull and whether the pull is finished need to be
reported. These data can easily be denoted on the payroll form, as shown in Figure 14.
A total of 19 hours was charged to pulling (account 1830). Of the two pulls made, the
first was completed (line 5), as denoted by the foreman, but the second was not.
PIPING ACTIVITIES WORK-HOUR DISTRIBUTION
warehousing 9%
construction equipment 2%
welder qualification 1%
scaffolding 13%
hangers 12%
erection 55%
tetsting 8%
Page | 41
Therefore, the crew credited with having pulled 175 linear feet, which is the length of
the first pull.
Quantity reporting for spool erection and field run pipe can be done on form such
as the one shown in Figure 10. This generic form can be used for racked and non-
racked pipe. All that is required of the foreman is to record the total quantity and pipe
size, as given on the isometric drawing, and to report the completion status and linear
footage. To minimize the chance for mistakes, the completion status is described on
the form.
Because the layout of structural steel is unique from project to project a generic
data collection form cannot be developed. However, all that is needed is a convenient
way for the foreman to report when a piece has been erected, bolted, or tightened and
when a floor has been plumbed. A graphical layout such as the one shown in Figure 15
is desirable. The foreman simply
Page | 42
DATE: 7-30-86
CRAFT:……Electrician……… BADGE NO
FOREMAN:……J. Barker……………… 173
(SIGNATURE)
SUPT: ……………………………..
(SIGNATURE)
START:…6:30….AM
PM STOP:…5:00… AM
PM
WO
RK
DE
SC
RIP
TIO
N
Lig
hti
ng l
ine
5,
Lin
e 5 L
UU
S
,175’-
Com
ple
ted
Ter
m &
Pan
el C
able
s L
ine
5
GIG
,LU
US
Ter
m
J.B
, L
ine
5 G
IG,
LU
US
Ter
m P
anel
s &
Dev
ices
, L
ine
5,
LU
US
, U
G
Conduit
for
Sta
r-w
hee
l L
ine
5
FI
Ter
m B
MI
Pan
el,
Lin
e 5 L
UU
S
Route
Cab
le &
25 P
in R
ecpt.
to
MCC FI Line 260’-
Inco
mple
te
Conduit
for
Dust
Contr
ol
Lin
e 5
,
LU
US
FOREMAN INSTRUCTOR
1. List Badge Numbers in
Numerical Order
2. Write in “Work Description”
columns in order. Do not skip
columns
3. Make sure description hours
equal total hours worked
4. Fill in Start &Stop Time
5. Sign Your Card
AC
CO
UN
T N
O
18
30
18
61
18
62
18
62
18
21
18
62
18
30
18
21
ANY INJURIES TODAY?
IF SO. EXPLAIN BELOW IN REMARK
BADGE
NO
NAME
CL
AS
S
DE
SC
RIP
TIO
N HOURS WORKED
REG
01
1.5
2.0
TOTAL REMARKS
(ABSENT LATE/EARLY START
STAYED LATE, INJURED, ECT)
75 G.Fisher S 10 10 < 10
76 D.Lewis S 10 10 < 10
173 J.Barker SF 10 10 < 1 2 2 1 1 1 1 1
174 C.Brooks S 10 10 < 5 3 2
478 D.Davis S 10 10 < 10
533 R.Lowes S 10 10 < - - - - - - - - Absent (Personal)
630 M.Balley S 10 10 < 6 4
660 S.Tanck II-1 0 0 < 1 3 3 3
661 J.Pierce S 10 10 < 2 3 5
<
TOTAL HOURS 80 80 < 12 12 8 18 7 7 7 9
Figure 14. Example of Foreman’s Daily Time Sheet
Page | 43
Marks the erected pieces and circles the joints that have been bolted or tightened.
The possibility of mistakes is greatly reduced because the form can be completed
quickly and easily.
SUMMARY
This chapter has presented five methods of measuring progress. The primary
methods are the units completed, percent complete, and the level of effort. Examples
of when each method can be used were cited. The measurement of work-hours was
also discussed, and a sample time sheet was given
Date FloorErection
Bolting
Tightening
Plumbing
Figure 15. Data Colletion Form for structural steel erection (Account 05121)
25'- 0" 25'- 0" 25'- 0" 26'- 0"
26
'- 0
"2
6'-
0"
26
'- 0
"2
6'-
0"
B C D E F
Page | 44
CHAPTER 5
REPORTING PRODUCTIVITY
The essential elements for calculating productivity were provided in the previous
chapter. Productivity is generally reported in two forms: productivity for the reporting
period and cumulative productivity to date. The length of the reporting period varies as
a function of the size, complexity, and duration of the work. Typical reporting periods
are daily, weekly, biweekly, monthly, or cumulatively, and generally, the larger and
more complex the reporting system, the longer the reporting period. The results which
can be displayed in tabular or graphical form can be used to analyze period variations
and short-term trends. This chapter illustrates the various calculations and presentation
formats and describes their value within a productivity measurement system
HOW PRODUCTIVITY MEASUREMENT SUPPORTS THE CONTROL
FUNCTION
For smaller to medium-sized projects, the need to analyze variations and short-
term trends in a timely manner is very important. If the proper method of measurement
has been selected, then daily variations in productivity should be the result of the
factors affecting productivity, and not the result of the type of data collection
procedure. Besides the importance of choosing the best data collection method for the
project, careful records must be kept because sloppy data collection only complicates
the interpretation process.
The goals of analysis and interpretation are quite simple. One aspect involves
relating changes in productivity to events cc conditions. The consequences of bad
weather, unusual congestion, high absenteeism, and other obvious factors can be
readily appreciated by most managers, but few can describe the effects in quantitative
terms. Also, less obvious factors can sometimes be isolated through productivity
measurement. The resulting knowledge of cause/effect relationships helps the manager
to formulate strategies for when to work, where to assign crews, and so forth. An
analysis of short-term trends can sometimes highlight problems that are not easily
recognizable by using conventional summary data. Therefore, productivity analyses
help to answer the question: Are we getting better or worse, and why?
PRODUCTIVITY CALCULATIONS
Productivity is defined as the work-hours per unit of work. Several different
calculations can be made depending upon the time frame that the data represents, i.e.,
whether productivity is reported daily, over some other period of time, or cumulatively
to date. The advantages, disadvantages, and uses of each approach, summarized in
Table 6, are described below
Page | 45
Table 6. Advantages, Disadvantages, and Users of the Forms of Productivity
Calculations
Approach Advantages Disadvantages Users
Daily
Immediate
feedback
Provides an order
of magnitude to a
particular problem
Support the
identification of
causes
Wide variation
possible which are
difficult to explain
Calculations done
daily
Draws attention to
problems that
occurred that day
Facilitates the
development of
strategies to prevent
reoccurrence
Period
Fewer calculations
Summaries needed
only periodically
Fluctuations in the
data not as great as
with daily
calculations
Lack of timeliness
of feedback.
Daily variations
hidden
Limited number of
data points on
which to base
conclusions
regarding trends.
Fails to support the
identification of
cause
Summaries for
upper-level
managers
Can be useful in
establishing short-
term goals
Moving Average
Daily feedback
Information not
grossly distorted by
one unusually good
or bad day
Calculations more
tedious
Analysis of short-
term trends
Cumulative
More closely
relates to cost and
profitability since
total values are
used
As work-hours and
quantity increase,
the slope changes
very slowly and by
small increments
Forecasting
probable out-come
Critiquing overall
progress.
Page | 46
Daily Productivity
The daily productivity or the unit rate is defined simply as:
Daily Productivity
( )
Both work-hours and quantities must be changed to the same account. In Figure
14, as an example, the electrician crew worked 80 total work-hours on that day, but
only 19 of these were charged to cable pulling. They completed one pull of 175 feet. In
this instance; the daily productivity for cable pulling is calculated only for completed
work as:
Daily Productivity
( )
)1830_(Code
Much information can be gained by studying the daily productivity of a crew.
Some causes of productivity decline can be readily identified, whereas others are some
subtle and require further investigation. To illustrate the usefulness of daily
productivity statistics, three examples are given using the activities developed in
Chapter 4.
Structural steel
Figure 16 shows a plot of the daily productivity of an ironworker crew erecting
structural steel on a six-story office building. Six days are of particular interest,
namely, days 4, 12, 15, 18, 21, and 24. The poor productivity on days 15 and 18 can be
explained by cold temperatures, 20’P and 12'F, respectively. On day 4, the weather
was bad, and the crew was sent hale after having worked for about 3 hours. With this
knowledge, the manager could better decide whether to work or send the crew home
on subsequent clays. Day 12 is more difficult to explain. The temperature was 27'F,
but the real problem may have been in the coordination of the work among the four
subtasks. Much of the effort was spent for plumbing, and few pieces of steel were
erected. On days 21 and 24, much of the work involved bolting
The role of daily productivity data is to focus attention and create awareness and
sensitivity. Later in this chapter, it will be shown how other data can be used in
conjunction with daily productivity to help isolate other productivity problems.
Pipe Erection
The daily productivity of a pipe erection crew installing six-inch-diameter pipe
spools (account 1732) is shown in Figure 17. The crew was working a 58-hour/week
schedule. During the first nine days, the daily crew productivity worsened at a steady
rate. Thereafter, erratic variations are observed. Given this information, a foreman or
superintendent should investigate the causes. Perhaps work assignments or
interferences with other crews· are the problems.
Cable Pulling
The analysis of cable pulling (account 1830) is similar to that of pipe erection. As
can be seen in Figure 18, steady increases in unit rates occurred after day 118.
Page | 47
0 5 10 15 20 25 30
0
2
4
6
8
DAY
WO
RK
HO
UR
S P
ER
PIE
CE
Difficulties in Plumbing Coordination
Bad Weather
Bolting Only
Figure 16. Unit Productivity for Structural Steel Erection
(Account 05121)
4 8 12 16 200
0
2
4
6
8
10
12
DAY
DA
ILY
WO
RK
HO
UR
S P
ER
LIN
EA
R F
OO
T
Figure 17. Unit Productivity for Pipe Erection (Account 1732)
Page | 48
Period Productivity
Calculating productivity for a given period of time is similar to calculating daily
productivity. Typical reporting periods are weekly, biweekly, and monthly. Only the
work-hours charged and the quantities installed during the period are consider. Period
productivity is calculated as follows:
Period Productivity
( )
Period productivity data are useful for upper- and middle level managers because
of their summary nature. For lower-level managers, the data can serve as a report card
and can help in establishing -short-term targets for example a goal may be to improve
productivity the next week by 10 percent compare with the previous week.
The limitations of period summaries are two-fold. First, if the duration of an
activity is short, then period productivity calculations do not provide adequate time for
problem evaluation and corrective action. Also, there are too few data points to
provide confidence in reaching conclusions. Period summaries are more appropriate
for longer duration activities. Second, period calculations tend to hide the effects of
various factors on productivity. For instance, the erratic character of the data in Figure
17 after day nine probably would not appear in weekly summaries.
14213212211210292
0.2
0.1
0.3
0.4
0.5
0
DAY
DA
ILY
WO
RK
HO
UR
S P
ER
LIN
EA
R F
OO
T
Figure 18. Unit Productivity for Cable Pulling (Account 1830)
Page | 49
Moving-average
Moving-average calculations are a compromise between daily and period
calculations. A time frame, n, is selected, and productivity over that period is
calculated using Equation 4. As the data for another day are collected, they are added
to the existing data, and the data from the oldest or least current day are deleted. Thus,
the calculation always includes the data from the previous n days. The advantage over
the simple period approach is that, because a new value is calculated each day, short-
term trend can be identified. The value of n is often selected to cover a work week
(n=5) that productivity from each day of the week is always included.
The value of the moving average is the early recognition of short-term trends.
These are often difficult to recognize using daily productivity data because it is subject
to considerable variability. Moving averages dampen the variability, as is shown in
Figure 19 which is the first 12 days of the structural steel erection example previously
discussed.
The data used in calculating the moving average in Figure 19 are summarized in
Table 7. By using a five-day moving average, it can be seen that the short-term
assessment is that productivity shows early signs of becoming worse. While the
upward trend in the last six days is small, it deserves careful monitoring. This trend is
not necessarily evident from studying the daily productivity data alone.
Page | 50
Table 7. Moving Average Calculations for Structural Steel Erection (Figure 19)
Day
Unit
Work-
hours
(1)
Work-hour
Total
(Last 5 days)
(2)
Unit
Quantities
(3)
Quantity
Total
(Last 5 days)
(4)
Unit
Productivity
(5)
Productivity
5-Day
Moving
Average (6)
1 38 38 18.5 18.5 2.027
2 40 78 30.6 41.9 1.307
3 56 134 39.1 88.2 1.432
4 20 154 6.0 94.2 3.333
5 56 210 53.3 147.5 1.051
6 56 228 35.5 164.5 1.578
7 56 244 27.8 161.7 2.014
8 40 228 28.5 151.1 1.404
9 54 262 48.3 193.4 1.118
10 46 252 21.6 161.7 2.130
11 41 237 47.1 173.3 0.870
12 53 234 19.6 165.1 2.704
5 10 15 20 25 30
DAY
0
0
1
2
3
4
WO
RK
HO
UR
S P
ER
PIE
CE
DAILY PRODUCTIVITY
5-DAY MOVING AVERAGE
Figure 19. Unit and Moving Average Productivity for the First
12 Days of Strutural Steel Erection (Account 05121)
Page | 51
Cumulative Productivity
Cumulative productivity is a compilation of all of the work-hours charged to an
account divided by the total quantities installed to date. It is calculated using the
following equation:
Cumulative Productivity
( )
The primary use of cumulative productivity calculations is to assess how the work
is progressing on the whole and to predict the' final productivity rate upon completion
of the activity, comparisons against the budgeted work-hours can be made in order to
evaluate potential profitability, figures 20 through 22 show the cumulative
productivity for the three example activities. The cumulative productivity curve for
structural steel in figure 20 shows that after the initial startup phase, the cumulative
productivity hovered at; just under 1.5 work-hours per piece until the last eight days.
Thereafter, the cumulative productivity declined by approximately 20 percent. Figures
21 and 22 clearly show steady losses in productivity for both cable pulling and pipe
erection.
As the work progresses, the number of work-hours and quantities will become
increasingly larger. Beyond, for example, ten reporting periods (days), even large
changes in daily product1vity will have a small effect on the cumulative productivity
calculation. Therefore, cumulative productivity calculations are of limited use in
detecting daily variations or short-term trends.
REPORTING FORMAT
The advantages of reporting productivity data in either graphical or tabular form
are described below.
Graphical Format
Graphical representations of productivity data are highly desirable because large
amounts of data can be quickly absorbed and understood. Graphs are especially
desirable for foremen and superintendents because the visual image allows them to
evaluate trends and make predictions without the need to manipulate data. Graphs also
create an element of confidence. Because they can be easily and quickly
comprehended, graphs support the criteria of simplicity, accuracy, and timeliness as
outlined in Chapter 3.
Graphical formats are especially suited for situations where updates to the data are
done on a daily basis. These include daily and cumulative productivity and moving
average calculations. A number of examples were presented earlier in this chapter.
Graphs are also well suited for comparing or reconciling two parameters, for example
productivity versus schedule considerations (see Chapter 8).
One limitation of graphics is that, if scales are improperly selected, it is more difficult
to put things into proper perspective. Graphs are not well suited to the presentation of
summary data.
Page | 52
0.7
0.9
1.1
1.3
1.5
1.7
91 101 111 121 131 141
DAY
CU
MU
LA
TIV
E W
OR
KH
OU
RS
PE
R L
INE
AR
FO
OT
Figure 21. Culmulative Productivity for Cable Pulling (Account 1830)
0.7
0.7
0.7
0.7
0.7
0.7
0.7 0.7 0.7 0.7 0.7 0.7
DAY
CU
MU
LA
TIV
E W
OR
KH
OU
RS
PE
R L
INE
AR
FO
OT
Figure 22. Culmulative Productivity for Large-Bore Pipe Erection (Account
1732)
Page | 53
Tabular Format
Tables of data are useful for summary statistics because there is little interpretation
required relative to the order of magnitude. Summary data on a weekly basis for a
crew installing small-bore pipe (account 1735) are given in Table 8. Summary data in
this form support the development of rules of thumb. For example, one can suppose
that it has been determined that the crew should be able to install 450 linear feet of
small-bore pipe per week. It can be seen that, after a slow start, the crew was able to
maintain this pace through week. 15. This is followed by six weeks of below-par
production. Weeks 15 through 17 are particular in revealing. The data show reduced
work-hours and output, but, at the same time; productivity decreased. This situation
suggests that the problem is related more to the nature of the work than to the number
of craftsmen assigned to the work. Over the last six weeks, the work-hours increased
significantly. The weekly output eventually increased, but it did so at the expense of
significant work-hour increases.
ANALYSIS OF WORK HOUR AND QUANTITY RATES
So far, this chapter has concentrated on studying the different forms of
productivity calculations. It follows, however, that, as suggested in Table 8; added
insight can be gained by individually reviewing the work-hour and quantity trends and
relating them to productivity trends.
Figures 23 and 24 show cumulative and daily work-hours and quantities,
respectively, for the small-bore pipe erection activity described at the beginning of the
chapter (account 1735). In figure 22, the productivity steadily worsened throughout the
activity duration. In Figure 23, both the cumulative and daily curves show that,
through weekday 15, the number of work-hours assigned to the work was very
consistent. Relative to the quantities", figure 24 shows a different picture. Four distinct
phases are seen; each with successively lower daily output. Only phase 4 can be
associated with the number of craftsmen assigned to the work.
The study of quantities helps to develop a sensitivity that can be applied to many
projects. For example, figure 25 shows the cumulative quantity curves for three similar
steel erection projects. Project A has been developed throughout this chapter. Project B
proceeded satisfactorily until a change in methods on day 13 forced the crew to
integrate its week with that of another. On Project C, the fact that steel deliveries
occurred very slowly from the beginning is clearly reflected.
Where the level of effort method of measurement is used, it is often possible to
review quantities installed for each subtask. Figure 26 illustrates the usefulness of this
type of analysis. The figure shows the cumulative pieces of steel that have been
erected, bolted, plumbed, and tightened. The completion rates should be reviewed
concurrently with the unit and cumulative productivity curves, shown in Figures 16
and 20, respectively. In figure 26, the relationship between plumbing and bolting is of
particular interest. The four-day delay in plumbing from day 15 through day 18
ultimately affected the bolting operation. The result of this breakdown in coordination
of the work is a loss of productivity, as shown by both figures 16 and 20.
Page | 54
Table 8. Typical Weekly Productivity Summary for Small-Bore Pipe (Account 1735)
Small - Bore Pipe (Account 1735)
Week
Quantity Work-hours Productivity
Weekly
lin ft
installed
(1)
Cumulative
fin ft
installed (2)
Weekly
Work-hours
(3)
Cumulative
Work-hours
(4)
Weekly
work-hours
lin ft
(5)
Cumulative
work-hour
lin ft
(6)
1 351 351 460 460 1.31 1.31
2 350 701 500 960 1.43 1.37
3 232 933 440 1400 1.9 1.5
4 587 1520 500 1900 0.85 1.25
5 438 1958 450 2350 1.03 1.2
6 453 2411 350 2700 0.77 1.12
7 532 2943 390 3090 0.73 1.05
8 557 3500 515 3605 0.92 1.03
9 500 4000 315 3920 0.63 0.98
10 453 4453 310 4230 0.68 0.95
11 450 4903 330 4560 0.73 0.93
12 532 5435 440 5000 0.83 0.92
13 326 5761 300 5300 0.92 0.92
14 467 6228 430 5730 0.92 0.92
15 449 6677 480 6210 1.07 0.93
16 334 7011 310 6520 0.93 0.93
17 255 7266 310 6830 1.22 0.94
18 418 7684 470 7300 1.12 0.95
19 377 8061 570 7870 1.51 0.98
20 243 8304 600 8470 2.47 1.02
21 262 8566 610 9080 2.33 1.06
22 513 9079 725 9805 1.41 1.08
23 521 9600 645 10450 1.24 1.09
Page | 55
0
400
800
1200
1500
2000
2400
0 4 8 12 16 20
DAY
Figure 23. Pipe Erection work-hours (Account 1732)
WO
RK
HO
UR
S
CUMULATIVE WORKHOURS
DAILY WORKHOURS
0
200
400
600
800
1000
1200
0 4 8 12 16 20
DAY
Figure 24. Pipe Erection Quantites (Account 1732)
QU
AN
TIT
ES
PHASE 1 PHASE 2 PHASE 3 PHASE 4
CUMULATIVE WORKHOURS
UNIT QUANTITY
Page | 56
SUMMARY
This chapter has demonstrated four important, methods of calculating productivity.
These calculations can be done apart from any knowledge of budgeted work-hours,
total quantities, or schedule considerations. Tabular and graphical formats were
illustrated. The use 'of work-hour and quantity rates in conjunction with productivity
curves to detect some of the cause of productivity losses was demonstrated. Each
graphical and tabular illustration showed how the information contained therein' could
provide insight to the manager relative to productivity. The emphasis throughout the
chapter has been on creating awareness and sensitivity.
0
200
400
600
800
0 10 20 30 40
DAY
Figure 25. Cumulative Quantity Curves for Three steel Erection Projects (Account 05121)
CU
MU
LA
TIV
E Q
UA
NT
ITIE
S (
PIE
CE
S) PROJECT A
PROJECT B
PROJECT C
0
200
400
600
800
0 5 10 15 20 25
DAY
Figure 26. Cumulative Quantities for the Subtasks in Structural Steel Erection
(Account 05121)
CU
MU
LA
TIV
E Q
UA
NT
ITIE
S
ERECT
BOLT
PLUMB
TIGHTEN
Page | 57
CHAPTER 6
PERFORMANCE EVALUATION
The analysis of daily productivity variations and short-term trends is very useful,
but Lt represents only a part of the overall control process. To strengthen perceptions
about productivity problems and to provide insight into potential profitability, it is
necessary to compare current productivity with the estimated or planned rates [91. The
process of making comparisons between actual and estimated productivity "is called
performance evaluation [181. As illustrated in Figure 7, the needed information for
comparative purposes includes the estimated work-hours, quantities, and productivity
(unit rate) from the project estimate and the planned duration or required completion
date from the project schedule. This chapter describes several ways of comparing
work-hours, quantities, and productivity using performance factors. Forecasting
techniques are also discussed.
CONTROL BUDGET
The control budget is the baseline against which comparisons are made. For
productivity control, a control budget is established for each activity which consists of
the total estimated work-hours, total quantities to be installed based on the quantity
take off, and the estimated productivity upon completion. If no estimate for the activity
is available, then the project manager can use realistic target values. Table 9 shows the
control budget for the pipe erection, structural steel, and cable pulling activities
presented in Chapter 4.
Performance Factors
The simplest form of performance evaluation is to compare the actual and planned
productivity values. This is done using a performance factor, which is a measure of
construction efficiency. The performance factor (PF) is calculated as follows:
Perform
( )
A performance factor is greater than unity indicates better-than-estimated
performance. Improvements in productivity are reflected by smaller productivity
values or reductions in the unit rate and larger or increasing PF values.
Numerical Comparisons
Typical numerical comparisons are made on a period and cumulative basis. Table
10 shows an example of a performance evaluation report in which actual work-hours,
quantities, and unit rates are compared to the control budget. The period calculations
are a summary of the previous five days.
Page | 58
Table 9. Example of an Initial Control Budget
Activity Description Account Units
Estimated
Work-
hours
(1)
Quantities
to be
installed
(2)
Planned
Unit Rate
(3)
Aboveground Non-racked
Piping, Spool Erection, 2
1/2 to 12 in
1732 lin ft 1,350 1,069 1.27
Aboveground Non-racked
Piping, Field Run, 2 in. and
Under
1735 lin ft 10,200 10,000 1.02
Structural Steel Erection,
Multistory Type 5121 pieces 963 642 1.5
Wire and Cable Pulling in
Conduit and Tray 1830 lin ft 6,228 69,202 0.09
Page | 59
Table 10. Example Performance Evaluation Report
Account Activity Units of
Measure
Work-hours Quantities
Budgeted
Unit Rate
Performance
Factor Total
Forecasted
Work-hours Budget Period To Date Percent Budget Period
To
Date Percent Period
To
Date
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
1732 Piping lin ft 1,350 658 1,824 135 1,063 197 917 86 1 0 1 2,114
1735 Piping lin ft 10,200 450 2,350 23 10,000 438 1,95
8 20 1 1 1 12,002
5121 Structural
Steel piece 963 228 782 81 642 158 517 81 1 1 1 971
1830 Cable lin ft 6,228 730 1,060 17 69,202 9,612 14,3
27 21 0 1 1 5,020
Column (4) = Column (3) : Column (1) x 100
Column (8) = Column (7) : Column (5) x 100
Column (10) = Column (9) : [Column (2) : Column (6)]
Column (11) = Column (9) : [Column (3) : Column (7)]
Column (12) = Column (3) x Column (5) : Column (7)
Page | 60
In this example, the large-bore piping work (account 1732) is preceded very
ineffectively. Progress during the previous week was especially poor. Eighty-six
percent of the quantities had been installed, but there was a significant overrun in
work-hours. The small-bore piping (account.1735) was projected to overrun. Steel
erection proceeded as had been planned. The cable pulling productivity was about 20
percent better than the budgeted but only 21 percent of the cable had been pulled.
Column (8) of Table 10 shows the percentage of budgeted quantities that were
installed. This is the true representation of the percent complete of an activity. It has
been observed that some contractors use the percentage of work-hours as a measure of
percent complete. For this approach to be correct, the budgeted unit rate and the
quantity takeoff must be accurate, and the actual unit rate must equal the budgeted unit
rate. The large-bore piping activity in Table 10 illustrates the danger in relying on the
consumed work-hours for ·this purpose.
Graphical Analyses of the PF
It is often helpful to review a graphical plot of the to-date performance factors.
Figure 27 show a graphical plot of cumulative performance factors that is typical for
many industrial construction activities. At the outset, performance is usually worse
than expected because the crews are not yet familiar with the work, because of
overstaffing in anticipation of an accelerated pace of work, or for other reasons. Before
long, performance improves and is actually better than planned. This trend may remain
until near the end of the activity, when congestion and difficulties with the final
completion of systems cause productivity to decline. The shape of the curve is
important because it represents an expectation. The shape varies with the type of work
(and the level of detail used in tracking the work.
Figure 28 show the cumulative performance factors for the first 13 days of the
large-bore piping activity and can be compared with Figure 27. Essentially, from the
beginning, the work as performed at below-par performance and the trend continued to
work. In this instance, the unit rate as probably underestimated, since planned
performance as never achieved. Because the PFs did not stabilize, below-par
productivity may also be a problem.
Figure 29, which give the cumulative PF values for cable pulling, show instability
that is the opposite of the piping activity. However, the PF trended toward a PF of 1.0,
so the activity may have proceeded as planned. Although a degree of instability is
expected at the outset, the PF values should eventually stabilize. If not changes in
methods or requirements, increasingly difficult work, or increased congestion are
among the possible causes. Dramatic or sharp changes in PF values may result for a
variety of reasons, but these should be relatively easy to identify.
Page | 61
FORECASTING
Numerical Approach
A second dimension of performance evaluation is forecasting the total work-hours
used in completing an activity. The ability to forecast is valuable for projecting work-
hour variances and assessing cost impacts. The simplest method of forecasting is to
divide the to-date work-hours by the per-cent complete of the activity. The following
equation can be used:
Work hour forecast at activity completion
( )
Column 12 in Table 10 shows the work-hour-s forecasts using this equation.
Sometimes it is helpful to have additional information related to forecasts. Table 11
shows a sample forecast report that provides relative and actual variances.
Graphical Approach
The numerical approach to forecasting using Equation 7 assumes that the
productivity will remain constant until the activity is completed. This approach is
subject to err-or if the cumulative productivity changes appreciably. A simpler and
often more accurate approach is to manually forecast using graphs.
Graphical forecasts can combine to-date trends, knowledge of what lies ahead, and
intuition of a manager who has had similar experiences on other projects. Also, the
manager must under-stand what has occurred on the activity until that point in time.
To forecast using graphs, a learning curve plot is needed. A learning curve is simply
the cumulative unit productivity. On they-axis plotted against the cumulative
quantities on the x-axis. Figures 30 through 32 illustrate productivity forecasts for
large-bore pipe erection, structural steel, and cable pulling, respectively. As can be
seen, some subjectivity is involved. These productivity forecasts can be compared with
those in Table 10 and with the actual productivity at completion as follows:
10 20 300 40 50 60 70 80 90 100
1.0
PERCENT COMPLETE
Figure 27. Plots of Typical Cumulative Performance Factors for Many
Industrial Construction Activities
CU
MU
LA
TIV
E P
ER
FO
RM
AN
CE
FA
CT
OR
S
Page | 62
Activity Unit
Calculated
Forecast
(Table 10)
Graphical Forecast
(Figures 30-32) Actual
Large-bore pipe
erection work-hours/lin ft 1.99 2.25 2.23
Structural steel work-hours/piece 1.51 1.41 1.73
Cable pulling work-hours/lin ft 0.074 0.088 0.103
Table 11. Example Forecast Report
Account Activity
Work-hours Percent
Completed Budgete
d To Date Forecast Overrun Variance
(1) (2) (3) (4) (5) (6)
1732 Piping 1350 1824 2114 764 1.57 86
5121 Structural
steel 963 782 971 8 1.01 81
1830 Cable 6228 1060 5000 -1208 0.81 21
0
CUMULATIVE QUANTITIES (LINEAR FOOT)
Figure 30. Productivity Forecasr for Pipe Erection (Account 1732)
CU
MU
LA
TIV
E P
RO
DU
CT
IVIT
Y
300 15000
0.75
1.5
2.25
3.00
600 900 1200
ES
TIM
AT
E 1
,063 L
F
FORECAST: 2.25 WH/LF
Page | 63
This comparison shows that the graphical forecast can be more accurate than the
analytical ones. The projected work-hours to complete can be readily calculated from
the productivity forecast.
RELIABILITY OF ESTIMATES
In preparing the project estimate, managers and estimators make the best use of
available data. Unfortunately, the time available for preparing the estimate is usually
200 10000
1.25
1.5
1.75
2.00
400 600 800
ES
TIM
AT
E642
PC
S
FORECAST: 1.41 WH/PC
0
CUMULATIVE QUANTITIES (PIECE)
Figure 31. Productivity Forecasr for Structural Steel (Account 05121)
CU
MU
LA
TIV
E P
RO
DU
CT
IVIT
Y
0
CUMULATIVE QUANTITIES (LINEAR FOOT)
Figure 32. Productivity Forecasr for Cable Pulling (Account 1830)
CU
MU
LA
TIV
E P
RO
DU
CT
IVIT
Y
14,000
.050
.075
1.00
.125
ES
TIM
AT
E6
92
02
LF
FORECAST: 0.088 WH/LF
28,000 42,000 56,000 70,000 84,400
1.75
2.00
Page | 64
limited, and the information may be incomplete. As a result, quantity takeoffs may be
in error, or, in some cases, a work task may be completely overlooked. Productivity
data is subject to wide variation, so the assumptions made in the estimating phase will
seldom exactly coincide with reality. Accordingly, the estimate should not be
considered a document without fault, and, when variances develop during the control
phase of a project, analysis of results should always consider estimating errors as a
possible reason.
To illustrate, it is assumed that the work-hours for .a given activity are projected to
overrun. Some of the possible explanations for the overrun are listed below.
- The total quantity of work may have been underestimated, requiring more labor
and material than budgeted.
- The estimated work-hours per unit of work may have been unrealistically low.
- Crew productivity may have been lower than what should reasonably be
expected for a variety of reasons.
Next, it is assumed that the projected work-hours for another activity are expected
to be right on target. This does not necessarily mean that everything was correct. In
fact, either of the following could be the situation:
- A low quantity estimate may be offset by better-than-budgeted productivity.
- Worse-than-budgeted productivity may be compensated for by fewer quantities
than budgeted.
Thus, productivity control is much more than simp11 watching for negative total
variances with and among activities or amounts. The status of an account is the
composite status of a number of parts, and each of those parts should be watched, even
if productivity appears favorable.
SUMMARY
This chapter has illustrated simple analytical and graphical techniques for
comparing actual performance to the control budget and for making work-hour
forecasts. Minimal information is required, and the output is in a concise and easy-to-
understand form.
Page | 65
PART III – ADVANCED CONCEPTS OF PRODUCTIVITY
MEASUREMENT AND PERFORMANCE EVALUATION
Chapters 4 through 6 covered the basic concepts that must be mastered en order to
effectively measure productivity. Persons who have previous experience with cost-
control systems will be familiar with most of these. However, there is much more to be
gained from productivity measurement and performance evaluation than can be
provided by the basic concepts. Therefore, Part III presents advanced concepts that can
be applied by the more experienced user,
Cumulative productivity changes as activities progress. Chapter 7 begins with a
presentation of standard productivity performance curves and shows how they can be
used to improve the accuracy of work-hour forecasts. Comparison of the shape of an
actual cumulative performance curve to the shape of the standard curve is also useful.
The earned value concept, a method for calculating the percent complete of a control
account, is described. The chapter concludes by describing five indices that may
suggest the cause of productivity problems.
Chapter 8 shows how productivity data and schedule information can be
integrated; The emphasis is on graphical presentations and indices that permit a very
quick assessment of overall performance.
Page | 66
CHAPTER 7
ADVANCED MEASUREMENT AND FORECASTING CONCEPTS
Chapter 4 through 6 presented the basic concepts of productivity measurement,
analysis, and forecasting which can be effectively applied to many construction
activities. However, situations occasionally arise where details several modifications
and extensions that will allow one to measure complex construction activities and to
more accurately forecast the total work-hours using standard productivity curves. The
earned value technique for monitoring control accounts is also described.
Measuring complex construction activities
Chapter 4 described how the level of effort method could be used to measure the
quantities (progress) for activities involving subtasks. The method is particularly well
suited to measuring bulk commodity items. However, the level of effort method can
also be used to monitor complex, one-off-a-kind items, as is illustrated by the example
for the erection of an absorber tower on a process plant.
For this work, it is estimated that 520 tons of structural steel are involved. Table
12 shows the status of the work at an early stage of completion. Different units of
measure are used for the various subtasks. Several items, such as shakeout, plumb, and
punch-list, are associated with the entire absorber tower and cannot be conveniently
related to a particular tier or bay. These subtasks are measured on the basis of percent
complete. Girts and sag rods are measured according to the number of bays finished.
The columns, beams, braces, and connections are measured by the piece. The overall
progress of the erection operation is determined by multiplying the percent complete
of each subtask by the respective rule of credit. The table shows that the work is 15.6
percent complete. The equivalent tonnage erected is 15.6 percent of the 520 tons, or
80.5 tons.
Forecasting using standard productivity performance curves
A characteristic problem with construction productivity is that it is continually
changing. This variability can result in significant analysis and forecasting
inaccuracies when using the linear approach defined by Equation 7 in chapter 6. The
need to develop accurate forecasts is particularly acute during the early stages of an
activity.
To overcome the problem of variations in cumulative unit rates, some contractors
have developed standard productivity performance curves for key commodity items.
The curves reflect the contractor’s expectations, on the basic of his experience, of how
productivity performance should change during the installation process. An example
of a standard productivity performance curve for small-bore pipe installation (account
1735) is shown in Figure 33.
Table 12. Quantities for the Erection of a 520-Ton Absorber Tower
Subtask Units of
Measure
Rule of
Credit
Total
Quantity
Quan-
tity to
Date
Percent
Comp-
lete
Relative
Percent
Complete
Total
Equiv-
alent
Tons
Equiv-
alent Tons
to Date
(1) (2) (3) (4) (5) (6) (7)
Run
foundation EA 0.02 200 200 100.0 2.0 10.4 10.4
Page | 67
bolts
Shim % 0.02 100 100 100.0 2.0 10.4 10.4
Shake out % 0.05 100 100 100.0 5.0 26 26.0
Columns EA 0.06 84 74 88.1 5.3 31.2 27.5
Beams EA 0.1 859 52
Cross braces EA 0.11 837 57.2
Girts & sag
rods BAY 0.2 38 104
Plum & align % 0.09 100 5 5.0 0.5 46.8 2.3
Connections EA 0.3 2977 74 2.5 0.7 156 3.9
Punch-list % 0.03 100 15.6 0.0
TOTAL
CONTROL TON 1 520 520 0.0
Column (4) = Column (3) x Column (2) x 100
Column (5) = Column (4) x Column (1)
Column (6) = Column (1) x total estimate quantity, ie. in this case, 520 tons
Column (7) = Column (4) x Column (6) : 100
0
PERCENT COMPLETE
Figure 33. Standard Productivity Performance Curve
for Pipe Erection (Account 1735)
CU
MU
LA
TIV
E P
ER
FO
RM
AN
CE
FA
CT
OR
20 1000.7
40 60 80
0.8
0.9
1.0
1.1
1.2
1.3
Page | 68
The use of the standard productivity performance curve is illustrated by the small-
bore piping (account 1975) example shown in Table 10. The installation is 20 percent
complete. From the performance evaluation report (Table 10), the to-date productivity
is calculated as:
To-date Productivity
(account 1735) =
2,350
1,958
= 1.20 work-hours/lin ft
This compares to the budgeted unit rate at completion of 1.02 work-hours/lin ft,
which would indicate an 18 percent overrun. However, from the standard productivity
performance curve (Figure 33), it is expected that the unit rate should be higher at 20
percent complete than it will be at completion. To calculate the forecasted work-hours
using the standard curve, the date from Table 10 are substituted into the following
equation to yield forecast work-hours.
Forecast
Work-hours =
Actual
Unit
Rate
X
Expected
Performance
Factor
X
Current
Quantity
Estimate
=
=
1.20 x (0.93) x (10,000) = 11,160 work-hours
This forecast is 842 work-hours less than the 12,002 work-hours calculated in
Table 10. The resulting forecast unit rate at completion is 1.12 work-hours/lin ft.
The standard productivity performance curve can be applied also when quantity
estimates are revised. This situation is demonstrated in Table 13, which is a typical
productivity report for a pipe-filter crew installing small-bore pipe. The work-hour
forecast in column 5 is calculated using Equation 9.
Sometimes it is useful to compare actual performance to the standard productivity
performance curve. A comparison of the actual performance factor (PF) values in
Table 13, column 10 with values in Figure 33 is shown in Figure 34. In this
comparison, the crew never performed as well as expected for extended periods of
time, even though the performance factor was greater than 1.0 for half of the time.
Thus, where unit rates are known to vary appreciably, the performance factor should
always be compared with the standard productivity performance curve.
MONITORING PROGRESS USING CONTROL ACCOUNTS
Many times it is advantageous to monitor constructions progress by grouping
similar activities into a single larger category called a control account. For example,
small-bore (account 1735) and large-bore (account 1732) piping can be combined into
an aboveground non-racked piping control account (account 1730). Similarly, wall
forms (account 03117), and elevated slab forms (account 03112) can be combined into
one category, the structural formwork control account (account 03110).
Page | 69
Table 13. Productivity Report for Small-bore pipe (Account 1735) – Showing Revised Quantity Estimates
Week
Quantiy Work-hours Productivity
Initial Budget: 10,000 linear feet (lf) Initial Budget: 10,200 work-hours Initial Budget: 1.02 work-hours/linear feet (wh/lf)
Takeoff lf Install
Cumulative %
Complete
Work-hours
Expended
Work-hours
Forecast
% Complete
Actual wh/lf
Expected Performance
Factor
Forecast wh/lf
Actual Performance
Factor
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
1 10,000 351 3.5 460 10484 0.04 1.31 0.8 1.05 0.78
2 701 7.0 960 11504 0.08 1.37 0.84 1.15 0.74
3 9,800 933 9.5 1400 12647 0.11 1.50 0.86 1.29 0.68
4 1,520 15.5 1900 11025 0.17 1.25 0.9 1.13 0.82
5 1,958 20.0 2350 10939 0.21 1.20 0.93 1.12 0.85
6 2,411 24.6 2700 10645 0.25 1.12 0.97 1.09 0.91
7 2,943 30.0 3090 10290 0.30 1.05 1 1.05 0.97
8 3,500 35.7 3605 10397 0.35 1.03 1.03 1.06 0.99
9 4,000 40.8 3920 10276 0.38 0.98 1.07 1.05 1.04
10 4,453 45.4 4230 10054 0.42 0.95 1.08 1.03 1.07
11 9,600 4,903 51.1 4560 9911 0.46 0.93 1.11 1.03 1.10
12 5,435 56.6 5000 9980 0.50 0.92 1.13 1.04 1.11
13 5,761 60.0 5300 9980 0.53 0.92 1.13 1.04 1.11
14 6,228 64.9 5730 10157 0.56 0.92 1.15 1.06 1.11
15 6,677 69.6 6210 10268 0.60 0.93 1.15 1.07 1.10
16 7,011 73.0 6520 10267 0.64 0.93 1.15 1.07 1.10
17 7,266 75.7 6830 10378 0.66 0.94 1.15 1.08 1.09
18 7,684 80.0 7300 10488 0.70 0.95 1.15 1.09 1.07
19 8,061 84.0 7870 10497 0.75 0.98 1.12 1.09 1.04
20 8,304 86.5 8470 10869 0.78 1.02 1.11 1.13 1.00
21 8,566 89.2 9080 11092 0.82 1.06 1.09 1.16 0.96
22 9,079 94.6 9805 10990 0.89 1.08 1.06 1.14 0.94
23 9,600 9,600 100.0 10450 10450 1.00 1.09 1 1.09 0.94
Page | 70
Column (3) = Column (2) : Column (1) x 100
Column (5) = Column (1) x Column (9)
Column (6) = Column (4) : Column (5)
Column (8) Determined from standard productivity performance curve
Column (9) = Column (7) x Column (8)
Column (10) = 1.02 : Column (7)
Column (7) = Column (4) : Column (2)
In the above example, the relationship between the control account and the
individual activities is defined by the framework of the productivity codes or the code
of accounts. Fortunately, the measurement concepts developed here do not require
such a rigorous formulation. In fact, the control account need not be a recognizable
code selected from the code of account. For instance, a commercial contractor may be
interested primarily in the timely construction of floor space so that other trades can
begin erecting partitions, fixtures, etc. The floor area control account may be defined
as followed:
0
PERCENT COMPLETE
20 100
0.7
40 60 80
0.8
0.9
1.0
1.1
1.2
0.6
EXPECTED PERFORMANCE
ACTUAL PERFORMANCE
Page | 71
Floor Area (Control account)
05121 Structural steel erection
05210 Web joist
05300 Metal decking
03312 Concrete elevated slabs
As can be seen, a contractor can readily adapt the productivity measurement to fit
his own special needs.
The use of control accounts often makes it easier to evaluate progress because a
single broad-scope account is studied rather than a collection of several narrow-scope
accounts. However, the difficulty in using this approach arises because the effort
required for each of the various narrow-scope accounts is not the same. For instance,
in Table 9, the budgeted quantities, work-hours, and unit rates for small- and large-
bore pipe differ greatly. For this reason, the narrow-scope accounts cannot be
combined without appropriate adjustments. Fortunately, the earned value concept can
be used to eliminate this problem in order to facilitate the combination of narrow-
scope accounts to form a single control account.
THE EARNED VALUE CONCEPT
The earned value concept is a technique for calculating the percent complete of a
control account. It is a weighted-average technique in which each account is assigned a
weight that accounts for the degree of difficulty of that part of the work and the
estimated quantities to be installed. With the earned value concept, each account is
assigned a fixed amount of resources that can be earned. The resources earned can be
either work-hours or dollars, since these are the only two types of resources to which
the many units of measure in a project (cubic yards, linear feet, each, ect.) can be
converted. If the resources are work-hours, then the total work-hours that can be
earned are calculated as follows:
Total Earnable
Work-hours
(each Account)
= Initial Estimated
Unit Rate
x Current Quantity
Estimate
Figure 35 illustrates the concept using the data from Table 9 for small- and large-
bore pipe. Using the initial estimate, the maximum work-hours that can be earned in
completing the piping control account is 11,550.
Page | 72
As the work is accomplished, work-hours in each account are earned at the unit
rate specified in this initial control estimate. The quantities installed are converted to
earned work-hours by using Equation 11, and the sum of the earned work-hours
represents the earned work-hours for the control account. The following equations are
used to determine these values:
Earned Value
(Work-hours)
for the
Control Account
= ∑ Initial Estimated
Unit Rate X
Quantities Installed
to Date (11)
Percent
Complete of
the Control
Account
= Earned Work-hours to Date
x 100 (12)
Initial Estimated
Unit Rate x
Current Quantity
Estimate
Prior to the start of an account, nothing is earned; when it is complete, 100 percent
of the work-hour has been earned. No more than 100 percent can ever be earned. The
percentage of the work-hours earned also represents the percent complete of the
control account.
The earned value technique is demonstrated by the following example using the
small- and large-bore piping data in Table 9. The budgeted unit rates are 1.02 and 1.27
work-hours/lin ft, respectively. Table 14 shows how the percent complete for the
control account (1730) is calculated using the initial estimate, the current quantity
estimate, unit rate, and the quantities installed to date.
A second sample shows how revised quantity estimates affect the earned value and
percent complete calculations. Here, the estimated quantities for small-bore piping are
revised downward from the original 10,000 lin ft (Table 9) to 9,600 lin ft. the
estimated quantity of large-bore pipe remains the same. The change for small-bore
piping is reflected in the productivity report (Table 13) after week 11. Table 15 shows
the quantities to date and the percent complete calculation.
Several points relative to the earned value concept are important. The total work-
hours that can be earned in an account changes only if the current forecasted quantities
change, as is illustrated in Table 15, Column 3. The total is revised upward or
downward according to the initial estimated unit rate, which never changes (The initial
Figure 35. Illustration of Earned Work-hours for Piping Control Account
SMALLBORE PILEACCOUNT
(1735)
TOTALWORKHOURS
TO BEEARNED
10,200
LARGEBORE PILEACCOUNT
(1732)
PILECONTROLACCOUNT
(1730)
TOTALWORKHOURS
TO BEEARNED
1,350
TOTALWORKHOURS
TO BEEARNED,CONTROLACCOUNT
11,550
PE
RC
EN
T
0
40
20
60
80
100
ACCOUNT/WORK HOUR EQUIVALENTS
Page | 73
estimated unit rate should not be confused with the forecasted or actual unit rate).
Since the initial estimated unit rate is always used, it provides a permanent datum from
which to measure performance. Thus, the work-hours earned in installing a given
quantity of materials are independent from the actual work-hours used. The quantities
to date are determined using rules of credit and are actual contract quantities, as
opposed to purchased quantities, which may include allowances for waste. Quantities
do not change if work must be redone because of interior quantity or a design change.
Table 14. Calculation of Percent Complete Using Earned Work-hours, Example 1
Account
Initial Unit
Rate
Estimate
Current
Quantity
Estimate
Total
Work-hours
to be earned
Quantities
to Date
Earned
Work-
hours
to Date
Percent
Complete
(1) (2) (3) (4) (5) (6)
1732 1.27 1,063 1,350 197 250 18.5
1735 1.02 10,000 10,200 701 715 7
1730
(control) 11,550
956 8.4
Column (3) = Column (1) x Column (2)
Column (5) = Column (1) x Column (4)
Column (6) = Column (5) : Column (3) x 100
Table 15. Calculation of Percent Complete Using Earned Work-hours, Example 2
Account
Initial Unit
Rate
Estimate
Current
Quantity
Estimate
Total
Work-hours
to be earned
Quantities
to Date
Earned
Work-
hours
to Date
Percent
Complete
(1) (2) (3) (4) (5) (6)
1732 1.27 1,063 1,350 957 1,215 90
1735 1.02 9,600 9.792 4,903 5,001 51.1
1730
(control) 11,142
6,216 55.8
Column (3) = Column (1) x Column (2)
Column (5) = Column (1) x Column (4)
Column (6) = Column (5) : Column (3) x 100
Page | 74
USE OF INDICES AND PARAMETERS
Productivity and performance information can be supplemented with indices and
parameters that facilitate quick review of an activity, account, or control account. Such
indices relate the magnitude of a reported value to an established reference value of the
same item. When they are used, a par performance of 1.0 is recommended, with an
index greater than 1.0 meaning better-than-par and an index lower than 1.0 meaning
below-par performance.
Indices Related to Labor Productivity and Costs
Performance factors for an activity or account were described in Chapter 6. This
concept can be extended to control accounts using the earned value concept. It is
defined as follow:
for a Control Account Earned Work hours to Date for the Control Account
Actual Work hours to Date for the Control Account 13)
The performance factor for the control account is independent of the budgeted
quantities or forecasted unit rates. It is dependent only upon what was installed, the
work-hours charges to do the work, and the initial unit rate that was expected to have
been achieved. When the PF is greater than 1.0, more work-hours have been earned
than have actually been charged. Table 16 presents a typical earned work-hours report.
Labor cost can be affected by the crew composition and size. The composite wage
index (CWI) relates the budgeted composite labor wage rates for the crew to the actual
wage rates. It is based on the total crew in the following way:
Composite Wage Index (CWI) Budgeted Crew Costs Per our
Actual Crew Costs Per our (14)
The index is affected by the crew size and composition and by individual wage
rates. It is also affected by shift differential and overtime pay, but it is not affected by
the number of hours worked per day or week. For example, work was planned using
an eight-person crew, with an average wage rate per craftsperson of $17.92 per hour,
which equals a budgeted hourly crew cost per hour of $143.36. For this example, the
following cost and work-hour summary is determined for the first three weeks of
work:
Week
Total Crew
Hours
Worked
Total Labor
costs
1 45 6,603.08
2 42 6,018.80
3 38 6,152.58
Total 125 18,774.46
Page | 75
Table 16. Typical Earned Work-hour Report
Account
Initial
Unit Rate
Estimate
Current
Quantity
Estimate
Total
Work-
hours to be
earned
Quant-
ities to
Date
Actual
Work-
hours to
Date
Earned
Work-
hours to
Date
Percent
Complete
Perfor-
mance
Factor
Percent
Com-plete
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1732 1.27 1,063 1,350 957 1,597 1,215 90.0 0.76 90
1735 1.02 9,600 9.792 4,903 4,560 5,001 51.5 1.10 51.1
1730
(control) 11,142
6,157 6,216 56.8 1.01 55.8
Column (3) = Column (1) x Column (2)
Column (6) = Column (1) x Column (4)
Column (7) = Column (6) : Column (3) x 100
Column (8) = Column (6) : Column (5)
The actual crew cost per hour can be calculated as follow:
Actual Crew Cost Per our Total Labor Costs
Total Crew ours Worked (15)
18,774.46
125
= $150.2
The composite wage index (CWI) can then be calculated by using Equation (14):
An index of less than 1.0 reflects the combined influence of overtime pay, crew
size and composition, individual wages, and the average crew size, the index is also
affected by absenteeism.
A labor budget performance index, which combined the performance factor and
the composite wage index, is sometimes calculated:
Labor Budget Performance Index (LBPI) Performance Factor Composite Wage Index(16)
This index gives a clearer picture of labor cost trends.
Indices Related to Estimating Accuracy
Obviously, the accuracy of a quantity estimate can have considerable influence on
the work-hours required to complete the work. An inaccurate estimate can actually
hinder the analysis of other indices and parameters. The estimating quantity variance
factor (EQVF) is intended to catalogue variances between the actual and estimated
quantity of work. It is calculated as follows:
EQVF Initial Estimated Quantity Revised Estimate Quantity
Revised Quantity Estimate (17)
A positive EQVF indicates that fewer quantities will be installed than were
initially estimated. A negative EQVF means that the initial quantity estimate was low.
Page | 76
A variance factor for a control account can be calculated also in the following
way:
EQVF for Control Account ∑ ( EQVF Total Earned Work hours)
Total Earned Work hours for Control Account (18)
Typical estimating quantity variance factors are shown in Table 16.
SUMMARY
This chapter has described how advanced concepts can be used to improve the
accuracy of analysis and forecasting technique. Complex construction activities can be
monitored using the level of effort method. If different units of measure are used for
the various subtasks, then the estimated quantities must be used. Standard
productivities curve allow one to reply on prior knowledge of how productivity varies
in order to improve forecasts. Performance factors can also be compared to standard
curves. Quantity estimates are needed in order to use standard productivity curve. The
earned value concept has been described as a technique for calculating the percent
complete of a control account. Several indices have been presented which can help in
isolating the cause of productivity problems.
Page | 77
CHAPTER 8
PRODUCTIVITY AND SCHEDULE PERFORMANCE
Satisfactory productivity performance and schedule performance do not always
occur simultaneously. Productivity can be good, but the work may be behind schedule.
Likewise, schedules are often met at the expense of significant productivity losses.
Thus, to have a more complete picture of project performance, productivity and
schedule performance must be viewed together. This chapter illustrates how these two
aspects can be integrated. The type of scheduling system used is irrelevant. It can be in
the form of a bar chart, a CPM schedule, a required activity completion date, or simply
an allocation of a certain number of working days.
ESTABLISHING PLANNED PROGRESS
The progress of an activity is measured on the basis of the percentage of the total
quantities that have been installed. To evaluate schedule performance, a planned
progress curve is needed which shows the scheduled cumulative percentage of the
quantities installed versus time. The simplest progress curve assumes that the same
number of quantities will be installed each day or week. This assumption yields a
straight line curve from 0 to 100 percent, with the project finishing at the required
time. Throughout this manual, however, cumulative unit rate curves have been shown
to be typically nonlinear. Therefore, one would expect the planned progress curve also
to be nonlinear.
Planned progress curves can be drawn subjectively or they can be developed from
a standard productivity performance curve such as the one shown in Figure 33. The
following example illustrates how they can be developed using a standard productivity
performance curve.
The control budget data for structural steel erection can be determined from Table 9:
Estimated quantities 642 pieces
Estimated work-hours 963 work-hours
Estimated unit rate 1.50 work-hours/piece
To complete the steel erection, the plan is to work eight hours a day, five days per
week, using a maximum crew size of eight. Five ironworkers will be hired for the first
week to perform shakeout and to erect the first and second floor columns. Three more
Page | 78
crew members will be hired beginning the second week, bringing the crew to the
required size. When the progress of the work reaches 85 percent, which roughly
coincides with the completion of the erection subtask, the crew will be reduced to four
ironworkers and will remain at four until the work is completed. The planned manning
level is shown in Figure 36, and Figure 37 shows the standard productivity
performance curve for structural steel erection.
Figure 36. Planned manning level, structural Steel erection ( Account 05121)
At the outset, the performance factor is expected to be considerably below (par.
From Figure 37, the expected PF value is 0.70. The output and percent complete for
the first day can be calculated:
Cumulative First Day Output = 0.4x 0.70 / 1.50 = 18.67 pieces
Percent Complete = 18.67 x 100 / 642 = 2.9 percent
The following day, the expected performance factor is 0.73, which yields:
Cumulative Second Day Output = 80 x 0.73 / 1.50 = 38.83 pieces
Percent Complete = 38.93 x 100 /642 = 6.1 percent
Output for subsequent days is calculated by repeating the procedure until all
estimated quantities are installed. Table 17 summarizes the calculations for this
example, and Figure 38 shows the planned progress curve as a function of the
10 20 30 40 50 60 70 80 90 100
1
2
3
4
5
6
7
8
PERCENT COMPLETE
CR
EW
SIZ
E
Page | 79
percentage of time. The curve has the characteristic S-shape. For instance, when 20
percent of the time has elapsed, one would expect that 14 percent of the work would
be done. At the 80 percent milestone, about 90 percent of the work should be
completed. As can be seen in Table 17, the projected duration is 19 working days.
A second example is for the small-bore piping operation (account 1735). The
standard productivity performance curve shown in Figure 33 is used. The cumulative
percent complete calculations are shown in Table 18 and Figure 39. As in the
previous example, expected progress is less at the beginning and end of the activity.
The slowest progress shown in Figure 39 occurs during the first 25 percent of time.
INDICES RELATED TO THE SCHEDULE
One, of the simplest forms of schedule evaluation is to compare wnat was actually
done with what was planned. This evaluation can be represented by a schedule
performance index. The index is calculated as shown:
Schedule Performance Index (SPI)
Scheduled Quantities to Date (19)
Figure 37. Standard productivity performance curve for structural Steel erection
( Account 05121)
20 40 60 80 100
0.7
0.8
0.9
1.0
1.1
0
CU
MU
LA
TIV
E P
ER
FO
RM
AN
CE
FA
CT
OR
PERCENT COMPLETE
Page | 80
0
PERCENT TIME
Figure 38. Planned Progress Curve for Structural Steel
Erection (Account 05121)
20 10040 60 800
PE
RC
EN
T C
OM
PL
ET
E
20
40
60
80
100
0
PE
RC
EN
T C
OM
PL
ET
E
20
40
60
80
100
0
PERCENT TIME
Figure 39. Planned Progress for Small-Bore Piping
(Account 1735)
20 10040 60 80
Page | 81
Table 17: Planned progress calculations for structural Steel erection ( Account 05121)
Estimate
642 pieces
Assumption
8 Crew members
963 work-hours 8-hours workday
1.5 work-hours/piece 5 days per week
Day Daily work-
hours
Cumulative
work hours
Expected
cumulative
performance
factor
(figure 37)
Expected
Cumulative
unit rate
Cumulative
daily
output
Cumulative
percent
complete
(1) (2) (3) (4) (5) (6) (7)
1 40 40 0.7 2.14 18.67 2.9
2 40 80 0.73 2.05 38.39 6.1
3 40 120 0.81 1.85 64.8 10.1
4 40 160 0.85 1.76 90.67 14.1
5 40 200 0.89 1.69 118.67 18.5
6 64 264 0.92 1.63 161.92 25.2
7 64 328 0.95 1.58 207.73 32.4
8 64 392 0.97 1.55 253.49 39.5
9 64 456 0.99 1.52 300.96 46.9
10 64 520 1.01 1.49 350.13 54.5
11 64 584 1.01 1.49 393.23 61.3
12 64 648 1.02 1.47 440.64 68.6
13 64 712 1.02 1.47 484.16 75.4
14 64 776 1.02 1.47 527.68 82.2
15 64 840 1.03 1.46 576.8 89.8
16 32 872 1.02 1.47 592.96 92.4
17 32 904 1.02 1.47 614.72 95.8
18 32 936 1.01 1.49 630.24 98.2
19 32 968 1.01 1.49 651.79 100
Column (5) = Estimated unit rate + column (4)
Column (6) = Column (3) x Column (4) + Estimated unit rate
Column (7) = [Column (6) + Estimated quantity ] x 100%
Page | 82
Table 18: Planned progress calculations for Small-bore pip ( Account 1735)
Estimate
10000 lin ft
Assumption
12 Crew members
10200 work-hours 8-hours workday
1.02 work-hours/lin ft 5 days per week
Day Daily work-
hours
Cumulative
work hours
Expected
cumulative
performance
factor
(figure 33)
Expected
Cumulative
unit rate
Cumulative
daily
output
Cumulative
percent
complete
(1) (2) (3) (4) (5) (6) (7)
1 200 200 0.70 1.46 137.25 1.4
2 400 600 0.73 1.4 429.41 4.3
3 400 1000 0.77 1.32 754.90 7.5
4 400 1400 0.82 1.24 1125.49 11.3
5 480 1880 0.86 1.19 1585.10 15.9
6 480 2360 0.90 1.13 2082.35 20.8
7 480 2840 0.94 1.09 2617.25 26.2
8 480 3320 0.97 1.05 3157.25 31.6
9 480 3800 1.00 1.02 3725.49 37.3
10 480 4280 1.04 0.98 4363.92 43.6
11 480 4760 1.07 0.95 4993.33 49.9
12 480 5240 1.10 0.93 5650.98 56.5
13 480 5720 1.12 0.91 6280.78 62.8
14 480 6200 1.14 0.89 6929.41 69.3
15 480 6680 1.15 0.89 7531.37 75.3
16 480 7160 1.14 0.89 8162.40 81.6
17 480 7640 1.13 0.9 8463.92 84.6
18 480 8120 1.11 0.92 8836.47 88.4
19 480 8600 1.09 0.94 9190.20 911.9
20 480 9080 1.07 0.95 9525.10 95.3
21 480 9560 1.04 0.98 9747.45 97.5
22 320 9880 1.02 1 9880.00 98.8
23 320 10200 1.01 1.01 10100.00 100
Column (5) = Estimated unit rate + column (4)
Column (6) = Column (3) x Column (4) + Estimated unit rate
Column (7) = [Column (6) + Estimated quantity ] x 100%
Page | 83
Similarly, the schedule performance index for a control account can be expressed as:
S for a Control Account
Scheduled Work hours to Date ( )
An SPI greater than 1.0 indicates that the work is ahead of schedule. The work is
behind schedule if the index is less than 1.0.
INTEGRATING PRODUCTIVITY AND SCHEDULE PERFORMANCE
Productivity and schedule performance are closely related, and it is advantageous
to study the two simultaneously. For an activity, this can be easily done graphically
by plotting the performance factor (Equation 6) against the schedule performance
index (Equation 19). For a control account, Equations 13 and 20 are used.
Figure 40 shows how to interpret the results. Data points in the first quadrant
indicate that both productivity and schedule performance are better than planned. If
both are worse than planned, then the data point will be in the third quadrant. Figure
40 includes possible reasons why a data point will fall in a particular quadrant.
Figure 41 shows the schedule and productivity performance history for the
structural steel operation. For this example, the work began ahead of schedule, and
productivity was better than planned. However, beginning with day 7, there was a
steady and pronounced deterioration in the schedule. Productivity remained at the
planned level through day 17. Thereafter, a continued loss in productivity occurred.
Figure 42 shows a similar curve for the small-bcre piping operation. While the
progress was ahead of schedule for the first three weeks, productivity was
considerably worse than planned by the end of the period. This was followed by a
seven-week period in which the work remained ahead of schedule and productivity
performance steadily improved. After week 10, both schedule and productivity levels
deteriorated.
MONITORING OVERALL PROJECT PERFORMANCE
Thus far, the concepts described have been applied to the evaluation of activities
or control accounts. Yet, these concepts can be extended for the monitoring of the
performance of the overall project or a portion thereof. In doing so, it is unnecessary
to monitor all project activities.
The following example illustrates the performance monitoring of a total project.
While the work may involve thousands of activities, only a few accounts have been
Page | 84
isolated as being the controlling or significant items of work. These items can be
combined into a relatively small number of control accounts, shown by Figure 43 in
bar chart format. The columns in figure 43 are explained by Table 19. Control of
these nine control accounts should result in the control of the overall project.
Figure 40. Schedule performance index Venus performance factor
possible weather delays
undermanding of the work
later than planned start
overly optimistic schedule
0.5 1.0 2.0 3.0 4.00.0 5.0
SCHEDULE
PREFORMANCE INDEX(SPI)
AHEAD OF SCHEDULE, BETTER
THAN ESTIMATED PRODUCTIVITY
BEHIND SCHEDULE, BETTER THAN
PLANNED PRODUCTIVITY
2.0
3.0
4.0
5.0
0.5
0.0
BEHIND SCHEDULE LOWER THAN
PLANNED PRODUCTIVITY
AHEAD OF SCHEDULE,WORSE
THAN ESTIMATED PRODUCTIVITY
earlier than planned start
poor productivity offset by fewer than plan quantities
over manning
low productivity estimates
saving in work-hours
overly optimistic schedule
fewer quantities than estimated
very favorable working conditions
PERFORMANCE FACTOR (PF)
many possible causes including
inaccurate estimatea
later than planed start
dfficult and disoranized work, etc
Page | 85
Figure 41: Project performance for structural Steel erection (Account 05121)
Figure 42: Project performance for Small-Bore Piping (Account 1735)
START OF
ACTIVITY
0.90.8 1.00 1.10 1.20
0.9
1.00
1.10
1.00
1.20
1.30
1.40
PERFORMANCE FACTOR
DAY 17
DAY 6
DAY 7
SC
HE
DU
LE
D P
ER
FO
RM
AN
CE
IN
DE
X
ACTIVITY
COMPLETION
0.90.8 1.00 1.10 1.20
1.0
1.1
1.2
1.3
1.4
1.5
PERFORMANCE FACTOR
SC
HE
DU
LE
D P
ER
FO
RM
AN
CE
IN
DE
X
WEEK3
WEEK10
START OF ACTIVITY
ACTIVITY COMPLETION
Page | 86
30 60 85 90 95100
15 45 85100
35 55 75 90 9510015
50 65 75 85 9510030155
50 65 80 90 971003520103
30 50 75 90 97100155
30 50 75 90 97100155
15 40 75100
15 40 75100
86 92 9710044 54 65 7619 24 29 353 6 11 151
S: SCHEDULE PROGRESSA: ACTUAL PROGRESS
PROGRESS OF PRODUCTIVTY REPORTING
Figure 43. Progress Chart Based on Earned Value Concepts
PROJECT:
CUSTOMER:
ControlAccount
COSTCODE
SCHEDULE
MONTHS
EARTHWORK
S
A
FOUNDATION
STRUCTURAL STEEL
EQUIPMENT SETTING
PIPING
ELECTRICAL
INSTRUMENTATION
INSULATION
PAINTING
TOTAL CONSTRUCTION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
S
A
S
A
S
A
S
A
S
A
S
A
S
A
S
A
S
A
Earned Value
REL.WEIGHT
IWHRS
PERCENTCOMPLETE
I
EARNEDWHRS
ACTUALWHRS
EXPENDED
PerformanceFactor
Sch.
Perf.
Index
(1) (2) (3) (4) (5) (6) (7)
TO DATE (-/-/-) PF Trends
MONTHS
3 6 9 12 15
10,000 32
25,000 82
30,000 102
25,000 82
95,000 322
50,000 172
40,000 142
12,500 42
12,500 41
300,000 1002
Page | 87
Figure 43 shows the planned monthly progress for each control account. Column 1 contains the
maximum earned work-hours. This column will change only if the quantities are revised. The relative
weight in column 2 indicates the degree of difficulty of each control account relative to the total. Because
these weights are determined by the earned work-hours and the percent complete calculations are
determined by rules of credit and earned work-hours in individual accounts, an accurate assessment of
percent complete should be possible.
Figure 44 provides a- progress schedule prepared at the end of the eighth month. It shows late
completion of the earthwork, foundation, structural steel, and equipment setting subtasks. The piping and
electrical work are shown to be ahead of schedule. This progress is reflected by the schedule
performance index (SPI), which, when an activity is completed, becomes 1.0. The SPI cannot be
calculated for an activity that begins early, as is the case for the electrical work. Overall, the work in this
example is ahead of schedule (SPI = 1.05) because of the influence of the piping and electrical work,
which have the largest relative weights. Using the earned work-hours, the percent complete can be
calculated as 30.3 percent. If the actual work-hours were used, the percent complete would be 32
percent, or about 6 percent higher than the actual amount. Productivity is better than planned on the
earthwork, structural steel, and piping. However, overall productivity is lower than planned, since the
actual work-hours are more than the earned work-hours.
USE OF EARLY AND LATE START DATES
If the scheduling system used provides early and late start times, these times can be combined
graphically with quantity arc progress information to produce commodity curves. An example is shown
in Figure 45 for small-bore pipe on a power plant project. The planned progress based on early and late
start dates yields an envelope in which actual progress must fall if the project schedule is to be
maintained. As can be seen in Figure 45, schedule slippage occurred, and a recovery plan was
successfully initiated. The small-bore pipe is currently progressing according to the late-start schedule.
SUMMARY
This chapter has described how schedule and productivity performance can be viewed
simultaneously to better understand how the job is progressing. To access actual progress, there must be
a plan. A planned progress curve was developed using a standard productivity curve and a variable
manning level. This was also used to determine the activity duration. Overall monitoring of an activity or
control account was done graphically. The performance factor was plotted against a schedule
performance index. The concepts of earned value were then used to show how the progress and
productivity of a total project effort can be monitored.
Table 19. Definition of Terms in Figures 43 and 44
Earned Value Work-hours - Indicates the estimated work-hours required to complete this control
account. This number remains unchanged unless the quantities are revised.
Relative Weight - Defines the relative value of this control account compared to the total construction
effort for this project. It is determined on the basis of the distribution of earned work-hours.
Percent Complete - Indicates the physical measurement of work completed in the specific control
account.
Earned Work-hours to Date - Defines the work-hour that should have been spent for the equivalent
work progress. It is determined by multiplying the quantities installed times the budgeted unit rate.
Actual Work-hours Expended - Indicates the actual work-hours expended to date. It is usually
obtained from the time sheet.
Performance Factor - Indicates the relative productivity as compared to the pre-established budget
(1.0 being the budgeted productivity). Anything less than 1.0 indicates the expenditure of more work-
hours to accomplish equivalent units of work than originally budgeted.
Schedule Performance Index - A comparison of actual earned work-hours to the planned earned
work-hours. An index greater than 1.0 indicates that the work is ahead of schedule.
Page | 88
1983 1984
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL
ACT. MONTH 32 559 761 818 909 587 837 300 787 1339 600 104 148 146 321
SCHED. MONTH 480 730 940 880 860 810 760 760 700 650 440 200 140 120 120 120 100 100 90
ACT. CUM. 582 1141 1902 2720 3629 4216 5063 5353 6140 7474 8079 8183 8331 8477 8798
SCHED. CUM. 1030 1760 2700 3580 4440 5250 6010 6770 7470 8120 8560 8760 8900 9020 9140 9200 9360 9460 9550
J F M A M J J A S O N D J F M A M J J A S O N D4.0
13.6
23.2
32.8
42.4
52.0
61.6
71.2
80.8
90.4
100
1983 1984
PE
RC
EN
T C
OM
PL
ET
E
BASE ON EARLY START
SMALL BORE-PILE
BASE ON LATE START
BASE ON ACTUAL
Page | 89
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
S
A
S
A
S
A
S
A
S
A
S
A
S
A
S
A
S
A
Earned Value
REL.WEIGHT
IWHRS
PERCENTCOMPLETE
I
EARNEDWHRS
ACTUALWHRS
EXPENDED
PerformanceFactor
Sch.
Perf.
Index
(1) (2) (3) (4) (5) (6) (7)
TO DATE (-/-/-) PF Trends
MONTHS
3 6 9 12 15
10,000 32
25,000 82
30,000 102
25,000 82
95,000 322
50,000 172
40,000 142
12,500 42
12,500 41
300,000 1002
30 60 85 90 95100
15 45 85100
35 55 75 90 9510015
50 65 75 85 9510030155
50 65 80 90 971003520103
30 50 75 90 97100155
30 50 75 90 97100155
15 40 75100
15 40 75100
86 92 9710044 54 65 7619 24 29 353 6 11 151
S: SCHEDULE PROGRESSA: ACTUAL PROGRESS
PROGRESS OF PRODUCTIVTY REPORTING
Figure 44. Progress Report Showing Status as of the Eight Month
95 9880
96 10050
50 85
6020
15
3
18 306
PROJECT:
CUSTOMER:
ControlAccount
COSTCODE
SCHEDULE
MONTHS
EARTHWORK
S
A
FOUNDATION
STRUCTURAL STEEL
EQUIPMENT SETTING
PIPING
ELECTRICAL
INSTRUMENTATION
INSULATION
PAINTING
TOTAL CONSTRUCTION
Page | 90
PART IV - LESSONS LEARNED AND FINDINGS
Chapters 9 and 10 cover the case studies. The goal of the case studies was to test the basic
concepts presented in Part II and report any needed modification. None were found to be
necessary. Mother goal was to describe experiences with implementing the measurement
system. Generally, these experiences were positive.
In Chapter 9, profiles of the three contractors are presented, and the 13 activities that
were studied are described. The diverse backgrounds and interests of the contractors and the
range of conditions and project types encountered in the case study activities add to the
credibility of the results. The chapter documents examples of haw productivity measurement
can be used to develop labor units for estimating, to understand factors that affect
productivity, and to monitor and control important activities. These examples show the
versatility of productivity measurement. Several situations are shown where labor units for
estimating can be developed. In these situations, summarizing work-hours and quantities at
project completion would have been inappropriate. For another activity, work-hours rather
than quantities were recorded for each subtask. In other examples, the effects of various
disruptions on productivity are shown. The disruptions documented include quality problems,
drawing errors, bad weather, crew reassignments, equipment breakdown, and several others.
The case study data are, also used to forecast the work-hours and workdays needed to
complete several activities. Earned value calculations are used on another activity to show
that there were difficulties in maintaining momentum. Performance factor curves were used to
isolate activities with the greatest opportunity f0c improvement and, to compare actual
productivity to expectations.
The case study findings are summarized in Chapter 10. These are organized according to
the six system criteria stated in Chapter 3. Other relevant findings are' also presented.