Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

download Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

of 67

Transcript of Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    1/67

    GEOTECHNICAL DESIGN REPORT

    ON

    PROPOSED TEMPORARY WORKS FOR TEMPODIVERSION

    FOR

    PROPOSED RECLAMATION AT TUAS FINGER O

    BCA Project Ref. Number: ?????

    h

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    2/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    TABLE OF CONTENT

    1. INTRODUCTION .....................................................................................1.1 Background.................................................................................................

    1.2 Design Codes ..............................................................................................

    2. GENERAL DESIGN CONSIDERATION .............................................2.1 Site Investigation Boreholes ........................................................................

    2.2 Assumed Soil Model...................................................................................2.3 Proposed Design Parameters .......................................................................

    2.4 Ground Water Table ...................................................................................

    2.5 Surcharge Load Condition...........................................................................

    3. LIMIT STATE EQUIBRIUM OF PROPOSED SHEETPILE WALL3.1 Stability against Piping Failure....................................................................

    3.2 Stability against Toe Failure ........................................................................

    4. GEOTECHNICAL DESIGN OF PROPOSED SHEETPILE WALL..4.1 Assumptions ...............................................................................................

    4.2 Results of FEM Analysis .............................................................................

    4.3 Risk Assessment to Surrounding Buildings................................................

    5. STRUCTURAL DESIGN OF PROPOSED SHEETPILE WALL........

    6. STRUCTURAL DESIGN OF STRUT AND WALER...........................6.1 Proposed Strut Spacing...............................................................................

    6.2 Strut and Waler Design...............................................................................7. OPEN CUT SLOPE..................................................................................

    8. PROPOSED INSTRUMENTATION PLAN..........................................

    APPENDIX

    A BOREHOLE LOGS IN VINICITY OF PROPOSED DRAIN

    B RESULTS OF SEEPAGE ANALYSIS OF PROPOSED SHEET

    TEMPORARY DRAIN BY SEEP/W

    C TOE STABILITY CALCULATION ON PROPOSED SHEETP

    D RESULTS OF FEM ANALYSIS OF PROPOSED SHEETPILE

    TEMPORARY DRAIN BY PLAXIS

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    3/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    LIST OF FIGURES

    Figure 1 Schematic Plan of Proposed Temporary Work on Temporary Dra

    Figure 2 Location Plan of Boreholes in vinicity of Proposed Temporary D

    Figure 3 Proposed Soil Model

    Figure 4 Schematic Sketch of Proposed Strutting System

    Figure 5 Results of Slope Stability Analysis of Proposed 1V: 2H Cut Slope

    Drain

    Figure 6 Plan View on Schematic Sketch on Interface between Sheetpile W

    Cut Slope

    LIST OF TABLES

    Table 1 Proposed Geotechnical Parameters for Temporary Works

    Table 2 Results of Toe Stability for Temporary Sheetpile Wall

    Table 3 Summary on FEM Results on Proposed Temporary Works for Te

    Table 4 Proposed Strut and Waler Members for Temporary Sheetpile Wa

    Table 5 Results of Open Cut Slope Analysis for the Outlet of Temporary

    Table 6 Proposed Instrumentation and Review Level

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    4/67

    STANDARD CERTIFICATION BY THE QUALIFIED PERSON

    WORKS

    1. In accordance with Regulation 9 of The Building Control Regulations

    Qualified Person for structural works appointed under section 8(1)(a) or

    Control Act, hereby submit the detailed structural plans and design calcul

    certify that they have been prepared in accordance with the provisions

    Regulations, the Building Control Act and any other written law peconstruction for the time being in force

    2. I further certify that these detailed structural plans and design calculations

    Project Ref No: .

    3. Total number of structural plans submitted : ___.and total number of pag

    in this book 1 ___

    __________________________________________ SE

    QUALIFIED PERSON FOR STRUCTURALSIGNATURE & STAMP

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    5/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    1. INTRODUCTION

    1.1 Background

    In this ST??? submission, this report describes the temporary work

    sheetpile wall for the drain diversion for the above-captioned projec

    about 5m deep by 4m wide and according to the construction stage

    Penta-Ocean Construction Co., Ltd, a 5m high sand surcharging wi

    awy from the edge of the temporary sheetpile wall once the drain

    However, the outlet of the drain facing the sea will be constructed by

    are no sand surcharging planned at this area as shown in Figure 1.

    Typical details of the sections in the QPs design is summarized as fo

    Proposed ERSS Proposed

    Platform

    Level

    (m CD)

    Final

    Formation

    level for

    Drain

    Diversion

    (m CD)

    Excavation

    Depth (m)

    Proposed

    Sheetpile

    toe

    CD)/Slop

    system

    Type 1 :FSP IV

    (S275) sheetpile

    wall with 1-

    level strut

    +6.0m +1.0m 5m -6m CD

    (12m

    penetratio

    length)

    Type 2: Open

    Cut slope at

    Drain Outlet

    +6.0m +1.0m 5m 1 V: 2H

    Note: ERSS Earth Retaining Stabilizing System

    * Assuming sand unit weight of 17 kN/m3for the sand surcharging

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    6/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    2. GENERAL DESIGN CONSIDERATION

    2.1 Site Investigation Boreholes

    There are no boreholes conducted at the proposed drain diversion

    boreholes TBH-35 and TBH-36 located in the vinicity as shown in Fi

    these 2 boreholes, the ground condition comprises of reclaimed sand

    the Jurong Formation. No Kallang Formation is found at these tw

    presents the two boreholes.

    2.2 Assumed Soil Model

    Based on the above nearby boreholes and the information that the arelocated within the exising sandkey, we inferred that the reclaim

    throughout the entire site for the proposed drain. The assumed soil m

    diversion is as depicted in below Figure 2.

    Reclaimed Sand

    (N=19 to 35)

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    7/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    2.3 Proposed Design Parameters

    The geotechnical design parameters proposed for the temporary w

    Table 1.

    2.4 Ground Water Table

    The groundwater table is assumed:-

    Seawater level : +3.0m CD (HWMS)

    2.5 Surcharge Load Condition

    Surcharge load of 10kPa was adopted behind the proposed sheetpile w

    3. LIMIT STATE EQUIBRIUM OF PROPOSED SHEETPIL

    3.1 Stability against Piping Failure

    The proposed 12m penetration length FSP IV sheetpile wall is checke

    stability due to piping. For an excavation depth of 5m, the embedded wall is therefore 7m.

    The factor of safety, FSpipingagainst piping is calculated using the follo

    FSpiping = Downward total weight of soil mass

    Average Upward Seepage pressure

    The average upward seepage force us is estimated using a seepage pr

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    8/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    3.2 Stability against Toe Failure

    The stability against toe failure is calculated using strength factor m

    parameters are used. The minimum factor of safety obtained using the

    summarized in Table 2. Appendix C presents the toe stability cal

    sheetpile wall.

    4. GEOTECHNICAL DESIGN OF PROPOSED SHEETPILE

    The design of the proposed Type 1: FSP IV sheetpile wall is carr

    program PLAXIS version 9 .The typical construction sequences for

    follows:-

    (i) Install FSP IV sheetpile wall to toe depth of 6m CD. Platform

    (ii) Excavate to +5.0m CD and then install strut @ +5.5m CD.

    (iii) Final excavation to formation level +1.0mCD.

    (iv) Construct a 150mm thick lean concrete at the formation level

    (v) Placement of +11.0m CD high sand surcharging at 11m

    sheetpile wall after the completion of the drain excavation to +

    4.1 Assumptions

    The assumptions made in the retaining wall analysis by PLAXISar

    i) 0.5m unplanned excavation is considered.

    ii) Drained parameter is used for Reclaimed sand.iii) Surcharge of 10 kPa is considered.

    iv) Preload to +11m CD is considered as surcharge in the FEM as

    weight of 17.5 kN/m3.

    v) 90%EI is considered for the FSP IV sheetpile wall

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    9/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    4.3 Risk Assessment to Surrounding Buildings

    There are no nearby structures within 2 times the excavation depth o

    work. Therefore, there is no impact assessment of the proposed

    surrounding ground and structures.

    5. STRUCTURAL DESIGN OF PROPOSED SHEETPILE W

    The ultimate bending moment capacity, Mc, of the FSP IV sheetpile w

    follows:-

    Mc= py . Zxx = 624 kNm

    Where, py= Yield stress of steel = 275 N/mm

    Zxx= Section Modulus of FSP IV sheetpile = 2270 cm3/

    From Table 2, the maximum unfactored bending moment of FSP IV s

    works is 154kNm. Using a load factor of 1.4, the ultimate bending m

    to be:-

    Mult= 1.4 x 154kNm = 216 kNm < Mc -----------

    6. STRUCTURAL DESIGN OF STRUT AND WALER

    6.1 Proposed Strut Spacing

    The proposed strut spacing for the temporary sheetpile wall is 5m

    schematic sketch:-

    5m

    Sh

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    10/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    6.2 Strut and Waler Design

    The steel strut is designed as compression member to resist the lat

    temporary retaining wall while the waler is designed as bending elem

    earth loads from the temporary retaining wall to the steel strut. Bo

    waler member are designed in accordance to BS 5950 : 2000 and

    design considerations are taken into the steel and waler design:-i) Increase of axial force arisng from 10 degree increase in tem

    accordance to TR26 : 2010 Technical Reference for Deep E

    SPRING Singapore.

    ii) Eccentricity of axial load at the connection. For waler of sing

    shall be about 10% of the overall dimension of the strut in the

    iii) Accidential impact load of 50 kN as in accordance to Reference for Deep Excavation published by SPRING Sing

    iv) One strut failure is also considered in the strutting design usi

    in accordance to TR26 : 2010.

    The proposed strut and waler members are summarized in Table 4. Th

    the strut and waler are presented in Appendix E.

    7. OPEN CUT SLOPE

    The open cut slope for the outlet of the temporary drain will be const

    horizontal slope with a 150mm thick lean concrete lining (Grade 15)

    mesh. Weep holes are to be provided along the slope surface of the co

    We used a slope stability program SLIDE version 3 developed by

    the factor of safety for the proposed cut slope.

    Based on the modified Bishops method, the mimimum factor of safe

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    11/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    We propose the inclinometers and ground settlement markers locate

    proposed temporary work. For the open cut slope, we propose on

    markers. Table 6 summarizes the proposed review levels for the abov

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    12/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Figure 1 Schematic Plan of Proposed Temporary Work on Temporary Drain

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    13/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Figure 2 Location Plan of Boreholes in vinicity of Proposed Temporary Drain

    Boreholes TB

    TBH-36 in vi

    proposed Dra

    Proposed Drain

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    14/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Table 1 Proposed Geotechnical Parameters for Temporary Works

    Effective ShearStrengthGeological

    FormationSPT N-value

    BulkDensity(kN/m

    3)

    UndrainedShear

    Strength, cu(kPa) c',

    (kPa)'

    (deg)

    UnDeMo

    Reclaimed Sand 19-36 20 - 0 30

    JurongFormation(30

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    15/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Table 2 Results of Toe Stability for Temporary Sheetpile Wall

    Proposed

    Ground

    Level (m

    CD)

    Proposed Final

    Excavation level (m

    CD)

    Toe Pentration length

    from proposed

    ground level (m)

    Factor of safet

    Strength Facto

    Method

    +6.0 +1.0 12.0 1.8 > 1.0 (allo

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    16/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Table 3 Summary on FEM Results on Proposed Temporary Works

    Stage Condition Max. sheetpiledeflecton

    Max. bendingmoment

    AExcavation to FEL +1.0m (with0.5m unplanned excavation) fortemporary Drain

    16.5mm (RHS)16.0mm(LHS)

    132kNm/m (RHS132kNm/m (LHS

    B

    Sand surcharge placed behindRHS Sheetpile after completionof excavation for temporarydrain

    33.5mm (RHS) 132kNm/m

    Note: (i) RHS : Right Sand Side Sheetpile wall and LHS: Left Hand Side Sheetpile

    * Ultimate axial stress on 250mm thick concrete slab = 1.4 x 39x103/(250x1000) = 0.2

    BRC A-10 for the reinforcement for 250mm thick lean concrete

    Stage A: Excavation for the construction of temporary drain

    Stage B: Placement of Sand surcharging @ 11m behind the RHS sheetpile

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    17/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Table 4 Proposed Strut and Waler Members for Temporary Sheetp

    Member Type Steel section/Grade

    Steel Strut 1 H300, 94kg/m (S275) @ 5m c/c*

    Steel Waler 1 H400, 172kg/m (S275)

    * With splay member

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    18/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Table 5 Results of Open Cut Slope Analysis for the Outlet of Tempo

    Proposed SlopeLevel at Crest

    of SlopeLevel at Toe

    of SlopeMinimum fact

    1 vertical to 2horizontal with 150mmthick lean concrete

    (with BRC A8)**

    +6.0m CD +1.0m CD 1.96 > 1.5 (allow

    * Based on Modified Bishop Method

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    19/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    20/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Figure 5 Results of Slope Stability Analysis of Proposed 1V: 2H Cut Slo

    150mm thick lean concrete (Grade 15) w

    BRC A8 mesh. Weep hole to be provide1.5m c/c

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    21/67

    Geotechnical Design Report for Proposed Temporary Works

    On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One

    for Penta-Ocean Construction Co., Ltd

    Our Ref No: SNP 27-09R1

    Figure 6 Plan View on Schematic Sketch on Interface between Sheetpile

    1V: 2H

    concre

    1.5n c

    FSP IV sheetpile Wall

    Strut @ 5m c/c with splay

    member

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    22/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    23/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    24/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    25/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    26/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    27/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    28/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    29/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    30/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    31/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    32/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    33/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    34/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    35/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    36/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    37/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    38/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    39/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    40/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    41/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    42/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    43/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    44/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    45/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    46/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    47/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    48/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    49/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    50/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    51/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    52/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    53/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    54/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    55/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    56/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    57/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    58/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    59/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    60/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    61/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    62/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    63/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    64/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    65/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    66/67

  • 8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014

    67/67