Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
-
Upload
mypenta2008 -
Category
Documents
-
view
217 -
download
0
Transcript of Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
1/67
GEOTECHNICAL DESIGN REPORT
ON
PROPOSED TEMPORARY WORKS FOR TEMPODIVERSION
FOR
PROPOSED RECLAMATION AT TUAS FINGER O
BCA Project Ref. Number: ?????
h
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
2/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
TABLE OF CONTENT
1. INTRODUCTION .....................................................................................1.1 Background.................................................................................................
1.2 Design Codes ..............................................................................................
2. GENERAL DESIGN CONSIDERATION .............................................2.1 Site Investigation Boreholes ........................................................................
2.2 Assumed Soil Model...................................................................................2.3 Proposed Design Parameters .......................................................................
2.4 Ground Water Table ...................................................................................
2.5 Surcharge Load Condition...........................................................................
3. LIMIT STATE EQUIBRIUM OF PROPOSED SHEETPILE WALL3.1 Stability against Piping Failure....................................................................
3.2 Stability against Toe Failure ........................................................................
4. GEOTECHNICAL DESIGN OF PROPOSED SHEETPILE WALL..4.1 Assumptions ...............................................................................................
4.2 Results of FEM Analysis .............................................................................
4.3 Risk Assessment to Surrounding Buildings................................................
5. STRUCTURAL DESIGN OF PROPOSED SHEETPILE WALL........
6. STRUCTURAL DESIGN OF STRUT AND WALER...........................6.1 Proposed Strut Spacing...............................................................................
6.2 Strut and Waler Design...............................................................................7. OPEN CUT SLOPE..................................................................................
8. PROPOSED INSTRUMENTATION PLAN..........................................
APPENDIX
A BOREHOLE LOGS IN VINICITY OF PROPOSED DRAIN
B RESULTS OF SEEPAGE ANALYSIS OF PROPOSED SHEET
TEMPORARY DRAIN BY SEEP/W
C TOE STABILITY CALCULATION ON PROPOSED SHEETP
D RESULTS OF FEM ANALYSIS OF PROPOSED SHEETPILE
TEMPORARY DRAIN BY PLAXIS
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
3/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
LIST OF FIGURES
Figure 1 Schematic Plan of Proposed Temporary Work on Temporary Dra
Figure 2 Location Plan of Boreholes in vinicity of Proposed Temporary D
Figure 3 Proposed Soil Model
Figure 4 Schematic Sketch of Proposed Strutting System
Figure 5 Results of Slope Stability Analysis of Proposed 1V: 2H Cut Slope
Drain
Figure 6 Plan View on Schematic Sketch on Interface between Sheetpile W
Cut Slope
LIST OF TABLES
Table 1 Proposed Geotechnical Parameters for Temporary Works
Table 2 Results of Toe Stability for Temporary Sheetpile Wall
Table 3 Summary on FEM Results on Proposed Temporary Works for Te
Table 4 Proposed Strut and Waler Members for Temporary Sheetpile Wa
Table 5 Results of Open Cut Slope Analysis for the Outlet of Temporary
Table 6 Proposed Instrumentation and Review Level
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
4/67
STANDARD CERTIFICATION BY THE QUALIFIED PERSON
WORKS
1. In accordance with Regulation 9 of The Building Control Regulations
Qualified Person for structural works appointed under section 8(1)(a) or
Control Act, hereby submit the detailed structural plans and design calcul
certify that they have been prepared in accordance with the provisions
Regulations, the Building Control Act and any other written law peconstruction for the time being in force
2. I further certify that these detailed structural plans and design calculations
Project Ref No: .
3. Total number of structural plans submitted : ___.and total number of pag
in this book 1 ___
__________________________________________ SE
QUALIFIED PERSON FOR STRUCTURALSIGNATURE & STAMP
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
5/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
1. INTRODUCTION
1.1 Background
In this ST??? submission, this report describes the temporary work
sheetpile wall for the drain diversion for the above-captioned projec
about 5m deep by 4m wide and according to the construction stage
Penta-Ocean Construction Co., Ltd, a 5m high sand surcharging wi
awy from the edge of the temporary sheetpile wall once the drain
However, the outlet of the drain facing the sea will be constructed by
are no sand surcharging planned at this area as shown in Figure 1.
Typical details of the sections in the QPs design is summarized as fo
Proposed ERSS Proposed
Platform
Level
(m CD)
Final
Formation
level for
Drain
Diversion
(m CD)
Excavation
Depth (m)
Proposed
Sheetpile
toe
CD)/Slop
system
Type 1 :FSP IV
(S275) sheetpile
wall with 1-
level strut
+6.0m +1.0m 5m -6m CD
(12m
penetratio
length)
Type 2: Open
Cut slope at
Drain Outlet
+6.0m +1.0m 5m 1 V: 2H
Note: ERSS Earth Retaining Stabilizing System
* Assuming sand unit weight of 17 kN/m3for the sand surcharging
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
6/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
2. GENERAL DESIGN CONSIDERATION
2.1 Site Investigation Boreholes
There are no boreholes conducted at the proposed drain diversion
boreholes TBH-35 and TBH-36 located in the vinicity as shown in Fi
these 2 boreholes, the ground condition comprises of reclaimed sand
the Jurong Formation. No Kallang Formation is found at these tw
presents the two boreholes.
2.2 Assumed Soil Model
Based on the above nearby boreholes and the information that the arelocated within the exising sandkey, we inferred that the reclaim
throughout the entire site for the proposed drain. The assumed soil m
diversion is as depicted in below Figure 2.
Reclaimed Sand
(N=19 to 35)
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
7/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
2.3 Proposed Design Parameters
The geotechnical design parameters proposed for the temporary w
Table 1.
2.4 Ground Water Table
The groundwater table is assumed:-
Seawater level : +3.0m CD (HWMS)
2.5 Surcharge Load Condition
Surcharge load of 10kPa was adopted behind the proposed sheetpile w
3. LIMIT STATE EQUIBRIUM OF PROPOSED SHEETPIL
3.1 Stability against Piping Failure
The proposed 12m penetration length FSP IV sheetpile wall is checke
stability due to piping. For an excavation depth of 5m, the embedded wall is therefore 7m.
The factor of safety, FSpipingagainst piping is calculated using the follo
FSpiping = Downward total weight of soil mass
Average Upward Seepage pressure
The average upward seepage force us is estimated using a seepage pr
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
8/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
3.2 Stability against Toe Failure
The stability against toe failure is calculated using strength factor m
parameters are used. The minimum factor of safety obtained using the
summarized in Table 2. Appendix C presents the toe stability cal
sheetpile wall.
4. GEOTECHNICAL DESIGN OF PROPOSED SHEETPILE
The design of the proposed Type 1: FSP IV sheetpile wall is carr
program PLAXIS version 9 .The typical construction sequences for
follows:-
(i) Install FSP IV sheetpile wall to toe depth of 6m CD. Platform
(ii) Excavate to +5.0m CD and then install strut @ +5.5m CD.
(iii) Final excavation to formation level +1.0mCD.
(iv) Construct a 150mm thick lean concrete at the formation level
(v) Placement of +11.0m CD high sand surcharging at 11m
sheetpile wall after the completion of the drain excavation to +
4.1 Assumptions
The assumptions made in the retaining wall analysis by PLAXISar
i) 0.5m unplanned excavation is considered.
ii) Drained parameter is used for Reclaimed sand.iii) Surcharge of 10 kPa is considered.
iv) Preload to +11m CD is considered as surcharge in the FEM as
weight of 17.5 kN/m3.
v) 90%EI is considered for the FSP IV sheetpile wall
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
9/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
4.3 Risk Assessment to Surrounding Buildings
There are no nearby structures within 2 times the excavation depth o
work. Therefore, there is no impact assessment of the proposed
surrounding ground and structures.
5. STRUCTURAL DESIGN OF PROPOSED SHEETPILE W
The ultimate bending moment capacity, Mc, of the FSP IV sheetpile w
follows:-
Mc= py . Zxx = 624 kNm
Where, py= Yield stress of steel = 275 N/mm
Zxx= Section Modulus of FSP IV sheetpile = 2270 cm3/
From Table 2, the maximum unfactored bending moment of FSP IV s
works is 154kNm. Using a load factor of 1.4, the ultimate bending m
to be:-
Mult= 1.4 x 154kNm = 216 kNm < Mc -----------
6. STRUCTURAL DESIGN OF STRUT AND WALER
6.1 Proposed Strut Spacing
The proposed strut spacing for the temporary sheetpile wall is 5m
schematic sketch:-
5m
Sh
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
10/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
6.2 Strut and Waler Design
The steel strut is designed as compression member to resist the lat
temporary retaining wall while the waler is designed as bending elem
earth loads from the temporary retaining wall to the steel strut. Bo
waler member are designed in accordance to BS 5950 : 2000 and
design considerations are taken into the steel and waler design:-i) Increase of axial force arisng from 10 degree increase in tem
accordance to TR26 : 2010 Technical Reference for Deep E
SPRING Singapore.
ii) Eccentricity of axial load at the connection. For waler of sing
shall be about 10% of the overall dimension of the strut in the
iii) Accidential impact load of 50 kN as in accordance to Reference for Deep Excavation published by SPRING Sing
iv) One strut failure is also considered in the strutting design usi
in accordance to TR26 : 2010.
The proposed strut and waler members are summarized in Table 4. Th
the strut and waler are presented in Appendix E.
7. OPEN CUT SLOPE
The open cut slope for the outlet of the temporary drain will be const
horizontal slope with a 150mm thick lean concrete lining (Grade 15)
mesh. Weep holes are to be provided along the slope surface of the co
We used a slope stability program SLIDE version 3 developed by
the factor of safety for the proposed cut slope.
Based on the modified Bishops method, the mimimum factor of safe
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
11/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
We propose the inclinometers and ground settlement markers locate
proposed temporary work. For the open cut slope, we propose on
markers. Table 6 summarizes the proposed review levels for the abov
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
12/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Figure 1 Schematic Plan of Proposed Temporary Work on Temporary Drain
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
13/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Figure 2 Location Plan of Boreholes in vinicity of Proposed Temporary Drain
Boreholes TB
TBH-36 in vi
proposed Dra
Proposed Drain
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
14/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Table 1 Proposed Geotechnical Parameters for Temporary Works
Effective ShearStrengthGeological
FormationSPT N-value
BulkDensity(kN/m
3)
UndrainedShear
Strength, cu(kPa) c',
(kPa)'
(deg)
UnDeMo
Reclaimed Sand 19-36 20 - 0 30
JurongFormation(30
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
15/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Table 2 Results of Toe Stability for Temporary Sheetpile Wall
Proposed
Ground
Level (m
CD)
Proposed Final
Excavation level (m
CD)
Toe Pentration length
from proposed
ground level (m)
Factor of safet
Strength Facto
Method
+6.0 +1.0 12.0 1.8 > 1.0 (allo
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
16/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Table 3 Summary on FEM Results on Proposed Temporary Works
Stage Condition Max. sheetpiledeflecton
Max. bendingmoment
AExcavation to FEL +1.0m (with0.5m unplanned excavation) fortemporary Drain
16.5mm (RHS)16.0mm(LHS)
132kNm/m (RHS132kNm/m (LHS
B
Sand surcharge placed behindRHS Sheetpile after completionof excavation for temporarydrain
33.5mm (RHS) 132kNm/m
Note: (i) RHS : Right Sand Side Sheetpile wall and LHS: Left Hand Side Sheetpile
* Ultimate axial stress on 250mm thick concrete slab = 1.4 x 39x103/(250x1000) = 0.2
BRC A-10 for the reinforcement for 250mm thick lean concrete
Stage A: Excavation for the construction of temporary drain
Stage B: Placement of Sand surcharging @ 11m behind the RHS sheetpile
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
17/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Table 4 Proposed Strut and Waler Members for Temporary Sheetp
Member Type Steel section/Grade
Steel Strut 1 H300, 94kg/m (S275) @ 5m c/c*
Steel Waler 1 H400, 172kg/m (S275)
* With splay member
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
18/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Table 5 Results of Open Cut Slope Analysis for the Outlet of Tempo
Proposed SlopeLevel at Crest
of SlopeLevel at Toe
of SlopeMinimum fact
1 vertical to 2horizontal with 150mmthick lean concrete
(with BRC A8)**
+6.0m CD +1.0m CD 1.96 > 1.5 (allow
* Based on Modified Bishop Method
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
19/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
20/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Figure 5 Results of Slope Stability Analysis of Proposed 1V: 2H Cut Slo
150mm thick lean concrete (Grade 15) w
BRC A8 mesh. Weep hole to be provide1.5m c/c
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
21/67
Geotechnical Design Report for Proposed Temporary Works
On Temporary Drain Diversion for Proposed Reclamation at Tuas Finger One
for Penta-Ocean Construction Co., Ltd
Our Ref No: SNP 27-09R1
Figure 6 Plan View on Schematic Sketch on Interface between Sheetpile
1V: 2H
concre
1.5n c
FSP IV sheetpile Wall
Strut @ 5m c/c with splay
member
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
22/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
23/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
24/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
25/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
26/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
27/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
28/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
29/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
30/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
31/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
32/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
33/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
34/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
35/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
36/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
37/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
38/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
39/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
40/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
41/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
42/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
43/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
44/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
45/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
46/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
47/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
48/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
49/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
50/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
51/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
52/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
53/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
54/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
55/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
56/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
57/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
58/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
59/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
60/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
61/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
62/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
63/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
64/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
65/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
66/67
-
8/11/2019 Finger 1 Project_ERSS Report for Temporary Drain Diversion_24 Sep 2014
67/67