Final Wcm With Revie of Literature

download Final Wcm With Revie of Literature

of 105

Transcript of Final Wcm With Revie of Literature

  • 7/30/2019 Final Wcm With Revie of Literature

    1/105

    PROJECT REPORT

    ON

    WORKING CAPITAL MANAGEMENT

    AT

    UTTARAKHAND JAL VIDYUT NIGAM LTD.

    In the partial fulfillment for the award of degree ofMASTER OF BUSINESS ADMINISTRATION (2012-14)

    Submitted To: Submitted By:

    Dr.Divya Negi Deepika Negi

    Lecturer GEU

    GRAPHIC ERA UNIVERSITY

    DEHRADUN-2480011

  • 7/30/2019 Final Wcm With Revie of Literature

    2/105

    PREFACE

    Vocational training is one of the most important parts in the

    M.B.A course. Since, learning theory and doing it practically aretwo aspects of study, every student of management course issupposed to undergo forty five days training in an organization.

    I was fortunate enough to get a chance to do my vocationaltraining in one of the esteemed organization of India UJVNL,Dehradun. I was posted in one by one department as the routineschedule of training department in UJVNL, which has beenfollowed:

    Training Department

    Finance Department

    Personal and Administration Department

    Quality control

    Production Department

    I have taken utmost care to prepare the report precisely andsolution- oriented rather than theoretical and so I hope that my

    work will be beneficial to the UJVNL.

    2

  • 7/30/2019 Final Wcm With Revie of Literature

    3/105

    ACKNOWLEDGEMENT

    I am very much thankful to the officers of theUJVNL, withoutwhose help and encouragement this project would have been

    impossible. I am highly obliged as the officers spared theirprecious time and share the information required for my project.I would like to show my deepest sense of gratitude to Mr. AshishMishra, (SM. Training); Mr. Ajay Garg, (DGM, QualityControl); Mr. Rajat Prabat, (C.M, P&A); Mr. Ram Arora, (SMManufacturing) whose guidance helped me in the completion ofthis project and I would also like to extent my sincere thanks toall the DGMs/CMs/SMs/DY.Managers & Managers and theemployees who gave me their valuable time for me.

    My special thanks in this regard goes to DR. DIVYA NEGI,ofGRAPHIC ERA UNIVERSITY, DEHRADUN. Who suggests and

    provides me the golden opportunity to make my project from thisdivision.

    Thank you,

    DEEPIKA NEGI

    (MBA-3rd Sem)

    3

  • 7/30/2019 Final Wcm With Revie of Literature

    4/105

    CERTIFICATE

    This is certify that Deepika Negi has successfully completedsummer training report on WORKING CAPITALMANAGEMENTAt UTTARAKHAND JAL VIDYUT NIGAM LTD.DEHRADUN.Under my guidance, which also forms partial fulfillment to MBADegree course. The produced report is genuine. I am fullysatisfied and appreciated the work done on the project.

    I wish good luck for the bright future of the candidate.

    DR.DIVYA NEGI

    Internal Guide

    GEU, DEHRADUN

    4

  • 7/30/2019 Final Wcm With Revie of Literature

    5/105

    DECLARATION

    I hereby declare that the project report on the financial support of

    UTTARAKHAND JAL VIDYUT NIGAM LTD.,DEHRADUN, has beensubmitted in partial fulfillment of the requirement for theMASTERS DEGREE IN BUSINESS ADMINISTRATION to GRAPHICERA UNIVERSITY, DEHRADUN is my original work and is notsubmitted for the award of any other degree, diploma fellowshipor other similar titles of prizes.

    DEEPIKA NEGIMBA-3rdSem

    (GRAPHIC ERA UNIVERSITYDEHRADUN)

    5

  • 7/30/2019 Final Wcm With Revie of Literature

    6/105

    COMPANY PROFILE

    Uttarakhand is renowned for its scenic beauty and rivers. India's two major rivers viz. Ganga and

    Yamuna start their journey from here. Besides these two rivers, Uttarakhand has a large network

    of rivers and canal which provides an immense scope for hydropower energy. One of the first

    hydro-power station in India was commissioned at Galogi in 1907. More power stations were

    subsequently developed over a period of time.

    12th February, 2001 - A new dawn in the Power Sector of Uttarakhand when UJVNL came into

    existence, with some promises to keep with the home state, to emerge as a Power Major and to

    make the state, so called "Urja Pradesh".

    Uttarakhand has a very high potential which is yet to be developed and to give impetus to power

    sector, Uttarakhand Jal Vidyut Nigam Limited (UJVNL) was formed. UJVNL is a wholly owned

    Corporation of the Government of Uttarakhand set up for managing hydro power generation at

    existing power stations and development, promotions of new hydro projects with the purpose of

    harnessing, the known, and yet to be known, hydro power resources of the State.

    Today, UJVNL operates hydropower plants ranging in capacity from 0.2 MW to 240 MW,

    totaling up to 1000 MW. Though the State is more or less sufficient in its energy generation to

    meet its own requirements, it is committed to develop its huge hydro power resources in an early

    and efficient manner for economic well-being and growth of the State and its people.

    6

  • 7/30/2019 Final Wcm With Revie of Literature

    7/105

    VISION , MISSION & VALUES

    Vision

    * To be an excellent & efficient organization on Strength of its Human Resources.

    * To be a significant player in the National Power Sector.

    * To induce adjacent infrastructure business that provides opportunities for growth.

    * To be the best corporate in Uttarakhand

    * To care for all.

    Mission

    *Contribution to improvement in the quality of life in Uttarakhand.

    Values

    *Creation of value for all stakeholders.*Result oriented with professional work culture.

    *Earn trust through fair business practices with all.

    *Growth balanced with environmental protection & enrichment.

    *Law abiding.

    7

  • 7/30/2019 Final Wcm With Revie of Literature

    8/105

    OBJECTIVES

    The main objects to be pursued by the Company for which it has been incorporated are as

    follows:-

    To establish takeover, operate and maintain Hydroelectric generating stations including

    mini & micro hydro electric generating station and tie-lines, substations and main

    transmission lines connected therewith.

    To carry on its activities within the State of Uttarakhand or elsewhere as may be found

    feasible.

    To make arrangements with any Company, Authority, Government or other persons or

    institutions for the operation and maintenance of any generating station owned by it

    (including transmission lines and other works connected therewith) on such terms and

    conditions as may be agreed upon between it and the Company.

    To take such measures as in the opinion of the Company, are calculated to advance the

    development of water power in the State of Uttarakhand and may carryout power and

    Hydro metric survey work and cause to be made such maps, plans, sections and estimate

    as are necessary for any of the said purpose.

    To carry out investigation and to prepare one or more schemes relating to the

    establishment or acquisition of generating stations, tie-lines, sub-stations and

    transmission lines for promoting the use of electricity within the State of Uttarakhand.

    To operate and maintain in the most efficient and economical manner the generating

    stations, tie-lines, sub-stations and main transmission lines, owned by the Company.

    To enter into agreement with any licensee licensed under the Indian Electricity Act, 1910

    or any other Act, Law of Regulation in force for the time being, or as modified from time

    to time or with any person for use of any transmission line, distribution line or main

    8

  • 7/30/2019 Final Wcm With Revie of Literature

    9/105

    transmission line of that licensee or person for such time and upon such terms as may be

    agreed.

    To enter into arrangement on such terms as my be agreed upon, for the sale of electricity

    generated by it to the State Electricity Company constituted for Uttarakhand or for the

    sale of electricity generated by it to any other state, body, person by itself with the

    consent of such person or persons duly authorized or licensed under prevalent Laws and

    Regulations or on its own account.

    To avail such rights, exercise such powers and functions and to perform such duties as

    are conferred upon or expected of the company under the provisions of such Laws,

    legislation and regulations as are in force from time to time.

    To do such other acts and things as are authorized to be done under the Electricity

    (Supply) Act, 1948, or any other Act, Laws or regulations in force or amended from time

    to time.

    9

  • 7/30/2019 Final Wcm With Revie of Literature

    10/105

    Genesis:

    UPSEB Unbundled :

    UPSEB Transfer Scheme14-01-2000

    Uttarakhand State Created:

    UP Reorganisation Act09-11-2000

    UJVN Ltd formed :

    1956 Companies Act12-02-2001

    UJVN Ltd Commenced Operations :Corporate Office in 2500 Sq ft Rented House.

    09-11-2001

    UJVN Ltd : took possessions of assets: 29-11-2000

    Had no Cash on : 09-11-2001

    Borrowed and Paid all employee dues and streamlined employee

    benefit :31-03-2002

    Sense of a new belongingness instilled in the people of UJVN

    Ltd :

    Nov 01- Mar 02

    10

  • 7/30/2019 Final Wcm With Revie of Literature

    11/105

    BRIEF HISTORY OF THE UJVNL

    The history of Uttarakhand Jal Vidyut Nigam Limited can be traced back to erstwhile U.P. State

    Electricity Board (In short UPSEB). The erstwhile U.P. State Electricity Board was trifurcatedpursuant to enactment of U.P. Electricity Reforms Act, 1999. U.P. State Electricity Reforms

    Transfer Scheme, 2000 was promulgated for execution of the trifurcation of erstwhile UPSEB

    into U.P. Power Corporation Ltd. (In short UPPCL), U.P. Jal Vidyut Nigam Ltd. (In short

    UPJVNL) and U.P. Rajya Vidyut Utpadan Nigam Ltd... By operation of the aforesaid Scheme all

    the Hydro Electric Projects earlier owned and operated by UPSEB were transferred to UPJVNL

    (a Govt. Company existing prior to the said trifurcation) in addition to other projects owned and

    operated by the UPJVNL previously.

    That UPJVNL was erstwhile known and setup as UP Alparthak Evam Laghu Jal Vidyut Nigam

    Limited, a Government Company which was incorporated in 1985 to own establish and operate

    small, mini and micro hydel projects. Later on the name of the company was changed to UP

    Laghu Jal Vidyut Nigam Limited and ultimately to UP Jal Vidyut Nigam Limited in 1996.

    The State of U.P. was bifurcated by enforcement of U.P. Reorganization Act, 2000 (In short

    Reorganization Act) as a result thereof the State of Uttarakhand came into existence. The Govt.

    of India issued an order dated 05-11-01 u/s 63(4)(a) of the Reorganization Act whereby assets

    and liabilities between UPJVNL and UJVNL were divided. By operation of this order all the

    Hydro Power Assets of UPJVNL located in the State of Uttarakhand were transferred to UJVNL.

    Since then UJVNL is operating all these hydro power plants.

    Uttarakhand Jal Vidyut Nigam was formed on 9 Nov 2001 with it main motto of

    developing and harnessing the hydro potential of Uttarakhand State. The Nigam has 34 projects

    under operation with an aggregated capacity of more than 1400 MW and more than 14 projects

    are under different stages of implementation.

    11

  • 7/30/2019 Final Wcm With Revie of Literature

    12/105

    Board of Directors

    1. Shri Utpal Kumar Singh

    Chairman & Secretary (Energy), GoU

    7. Shri C.M. Vasudev

    Independent Director

    2. Shri R.P. Thapliyal

    Managing Director

    8. Shri S.C. Sen

    Independent Director

    3. Shri Alok Kumar Jain

    Prinicipal Secretary (Finance), GoU

    Non-Executive Director

    9. Shri B.C.K. MISHRA

    Director (Operations)

    4. Shri P.C Sharma

    Prinicipal Secretary (Ind. Dev.), GoU,

    Non-Executive Director

    10. Shri Jayant Kumar

    Director(Finance)

    5. Shri Nitesh Kumar Jha

    Additional Secretary (Energy), GoU

    Non-Executive Director

    11. Shri K.K. Singh

    Director(Projects)

    6. Dr. S. Ramesh

    Independent Director

    Top Management

    1. Shri Utpal Kumar Singh

    Chairman & Secretary (Energy), Gou

    8. Shri Chaturvedi

    General Manager (Yamuna Valley)

    2. Shri R.P. Thapliyal

    Managing Director

    9. Shri Purshottam Singh

    General Manager (Ganga Valley)

    3. Shri B.C.K. Mishra

    Director (Operations)

    10. Shri C P Madan

    General Manager (Accounts)

    4. Shri Jayant Kumar

    Director (Finance)

    11. Shri S.K Chopra

    General Manager (P & IR)

    5. Shri K.K. Singh

    Director(Projects)

    12. Shri Arvind Kumar

    General Manager (I/c) (SHP)

    6. Shri S.N. Verma 13. Shri Arun Sabharwal

    12

  • 7/30/2019 Final Wcm With Revie of Literature

    13/105

    Executive Director (E & M) Company Secretary

    7. Shri Sandeep Singhal

    Executive Director (Civil)

    Credentials

    Largest pre-1910 plant located at Galogi, Uttarakhand (Dehradun-Mussoorie Road).

    North India's first underground power house at Chibro.

    India's first tandem operation of Chibro-Khodri Power Station.

    India's first 220 KV two tier switchyard at Chibro Power station.

    Trifurcation of H.R.T. (Partly) of Khodri Power Station due to Inter-Thrust Zone.

    Replacement of runner chamber by N.S. Grout & Epoxy filling at Chilla Power Station for

    the first time in India.

    2000 engineer-years of hydropower O & M experience.

    International level Design & Research facilities at Irrigation Design Organization &

    Irrigation Research Institute at Roorkee.

    Maneri Bhali-II- Power Station of 4 units of 76 MW with Francis turbines along with a 220

    kV switchyard. Annual generation of 1566 GWh.

    Generation Targets For The Year 2009-10 as Fixed By CEA

    Generation (MU) Since Formation of UJVNL.

    Generation (MU) - LHPs (00-01 to 08-09)

    Generation (MU) - SHPs (00-01 to 08-09)

    13

    http://www.uttarakhandjalvidyut.com/Targets%20(09-10).xlshttp://www.uttarakhandjalvidyut.com/generation.htmhttp://www.uttarakhandjalvidyut.com/Monthly_Generation-%20LHPs%20(00-01%20to%2008-09).pdfhttp://www.uttarakhandjalvidyut.com/Monthly_Generation-%20SHPs%20(00-01%20to%2008-09).pdfhttp://www.uttarakhandjalvidyut.com/generation.htmhttp://www.uttarakhandjalvidyut.com/Monthly_Generation-%20LHPs%20(00-01%20to%2008-09).pdfhttp://www.uttarakhandjalvidyut.com/Monthly_Generation-%20SHPs%20(00-01%20to%2008-09).pdfhttp://www.uttarakhandjalvidyut.com/Targets%20(09-10).xls
  • 7/30/2019 Final Wcm With Revie of Literature

    14/105

    POWER PROJECTS IN INDIA

    14

  • 7/30/2019 Final Wcm With Revie of Literature

    15/105

    INTRODUCTION OF HYDRO POWER

    Hydro power is a non- polluting, renewable source of energy .It is perhaps the oldest renewable

    energy technique .Hydro power represents the use of water resources towards inflation free

    energy due to absence of fuel cost with mature technology characterized by highest primer

    moving efficiency and spectacular electricity efficiency.

    Small Hydro Projects are an important, appropriate and profitable that other energy supply

    options.

    Uttarakhand Jal Vidyut Nigam limited is primarily responsible for the Small Hydro

    development in Uttarakhand & is nodal agency to speed up this development.

    Formerly the small hydro projects were in Uttar Pradesh Laghu Jal Vidyut Nigam limited and

    thereafter transferred to UP Jal Vidyut Nigam but after formation of Uttarakhand these project

    15

  • 7/30/2019 Final Wcm With Revie of Literature

    16/105

    came under UJVNL, since then UJVNL (Uttarakhand Jal Vidyut Nigam Limited) has shown

    serious interest in development of these projects.

    Hydro Power Classification

    Hydro Power projects are generally classified in two parts ie. Small hydro projects and large

    hydro projects. In India hydro projects upto 25 MW are considered as small hydro Projects

    where above 25 MW are considered as large hydro projects

    The small hydro projects are further classified as follows

    Class Capacity in KW

    Micro Hydro Upto 100

    Micro Hydro 100-2000

    Small Hydro 2000 to 25000

    16

  • 7/30/2019 Final Wcm With Revie of Literature

    17/105

    Performance and Development of SHPs in Uttarakhand:

    Importance of SHPs

    Small hydro power

    Projects (SHPs) are

    an important,

    appropriate and

    profitable than other

    energy supply

    options and is a part

    of the full menu ofenergy options to be

    considered in

    meeting the needs of

    rural people more so in

    the remote and isolated

    locations in the hilly

    terrain of the state of

    Uttarakhand. SHPs

    compare well with the alternative energy supply options and have an important niche in the

    range of decentralized energy supply options. This niche is tightly demonstrated defined by

    the availability of adequate small-scale resource and as sufficiently concentrated density of

    demand, consisting of a need combined with purchasing power, to take advantage of a

    centralized, albeit small, power plant. SHPs have a great social bearing as it can provide rural

    people with electricity and create a sense of belonging to the modern world besides providing

    energy that can assist in securing the livelihoods of marginalized people. The SHPs are

    financially sustainable under the following conditions:-

    1. A high load factor

    2. A financially sustainable end-use.

    3. Costs are contained by good design and management.

    17

  • 7/30/2019 Final Wcm With Revie of Literature

    18/105

    There is a constraint in that costs of

    SHPs rise with the remoteness of the

    location but the cost of alternative

    options particularly diesel generator)

    may rise faster. SHPs in

    Uttarakhand in short will play an

    important role as growth engines for

    developing the economy of rural

    area which is isolated and remotely

    located.

    Uttarakhand has an estimated

    capacity of 1478 MW of SHP out of approximately estimated capacity of 20263 MW. The

    estimated capacity of small hydro projects of Uttarakhand is 7.3% of total estimated capacity of

    Hydro power in Uttarakhand and 10.23% of targeted contribution of Hydro in 10th Five Year

    Plan.

    Uttarakhand Jal Vidyut Nigam Ltd. is primarily responsible for the development of Small Hydro

    power project in the state of Uttarakhand and is a nodal agency for the speedy development ofthe same.

    In view of the above Government of Uttarakhand as well as Government of India are facilitating

    the development of small hydro projects in the state of Uttarakhand. The Small hydro projects

    have following distinct advantages:

    a. Hydro power involves a clean process of power generation.

    b. It is a renewable source of energy and contributes to the upliftment of the rural masses,

    especially projects located in remote and inaccessible areas.

    c. It is the most cost effective option for power supply because it does not suffer from the

    18

  • 7/30/2019 Final Wcm With Revie of Literature

    19/105

    limitation on account of fuel consumption.

    d. Most small hydro projects in Uttarakhand are being developed in remote and backward

    areas where substantial support for economic development is actually needed.

    e. Small hydro power contributes in solving the low voltage problem in the remote hilly

    areas and helping reducing the losses in transmission and distribution.

    f. In certain cases projects are helpful in providing drinking water and irrigation facilities.

    g. It helps in promoting the local industries in remote areas.

    h. The development of small hydro projects requires minimum rehabilitation and resettlement

    as well as environmental problems.

    i. Small hydro projects help in generating self employment in remote areas of the state.

    j. Small hydro power projects helps in providing stable electricity supply at remote areas

    where such facility by other source shall be much costlier and unreliable.

    In Short we can say that SHPs are

    Simple to operate

    Non Polluting

    Minimum Maintenance

    Environment friendly

    Utilizes local resources

    Take less time in construction

    Can be used at places where grid is not possible.

    The viability can be improved by incorporating the benefits of Carbon Trading

    19

  • 7/30/2019 Final Wcm With Revie of Literature

    20/105

    Policy of UJVNL in the construction of Small Hydro Power Plants:

    The SHP Plant wing of UJVNL was christened with the purpose of:

    1. Improvement in civil design and relocation of project site.

    2. Design and maintenance of Electrical Equipments at Nigamss level.

    3. Monitoring of Daily Generation.

    4. Operations of project by Nigam that were earlier operated by contractors.

    5. Construction of new projects.

    6. Increasing generation by completing the incomplete project.

    7. Investigation & development of new projects.

    8. To avail the CDM benefits under the Kyoto Protocol to make SHPs more viable.

    UJVNL for early realization of the capacity in SHP would be focusing on the construction of the

    projects above 3 MW and accordingly the following policies has been adopted for theImplementation, operation & Maintenance of the SHP in the State:

    1. Construction of small hydro projects of 3 MW and larger capacities in general.

    2. Dry Leasing of all power stations up to 500 KW capacities to private entrepreneurs for

    operation & maintenance.

    3. Operation of Power Stations by Nigam's staff.

    20

  • 7/30/2019 Final Wcm With Revie of Literature

    21/105

    Performance of SHPs:Integrated efforts by UJVNL have steadily increased the generation of SHP after 9.11.2001 and

    details are given below

    Year 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 07-08 2008-09

    Up to

    nov

    Generation

    (in MU)25.6494 30.1242 40.9361 36.3510 40.1692 46.2272 42.8374 42.2933 32.4304

    21

  • 7/30/2019 Final Wcm With Revie of Literature

    22/105

    Future Plan of Capacity Addition :

    A total 86,600 kW capacity addition has been targeted as under:

    Project District Capacity(KW)Year of

    Completion

    1 Asiganga-I Uttarkashi 4500 2009-10

    2 Asiganga-II Uttarkashi 4500 2010-11

    3 Asiganga-III Uttarkashi7300(under

    revision)2010-11

    4 Dunao Pauri Garhwal 1500 2009-10

    5 Shobla-I Pithoragarh 8000 2010-11

    6 Tankul Pithoragarh 12000 2010-11

    7 Kaliganga-I Rudraprayag 4000 2009-10

    8 Kaliganga-II Rudraprayag 6000 2010-11

    9 Madhyamaheshwar Rudraprayag 10000 2009-10

    10 Kalidigad Uttarkashi 9000 2010-11

    11 Sonegad Uttarkashi 3000 2010-11

    12 Suringad II Pithoragarh 5000 2010-11

    13 Urgam II Chamoli 3800 2010-11

    14 Painagad Pithoragarh 4000 2010-11

    15 Pilangad II Uttarkashi 4000 2010-11 86,600

    The Setting up of SHPs in the state of Uttarakhand would help in the overall development of

    the state especially in the remote areas in the hills. It is a known fact that supplying improved

    energy services to people for the first time is difficult, supplying such services profitably to

    very poor people who live far away from roads and the electricity grid poses a particularly

    difficult challenge. Nevertheless, the access to electricity in the remote areas would generate

    livelihood and the impact can be spread to marginalized people and then to social activities.

    UJVNL is in the process of proposing new SHPs for CDM for earning Emission Reduction

    credits which will generate additional revenue for SHPs and make them financially viable. "It is

    easier to make the profitable social, than to make the social profitable" and UJVNL is aware

    that in planning SHP investments it is important to consider the plant for securing livelihood at

    an early stage and then to see how the impact can be spread to masses and for social activities.

    UJVNL is endeavoring to set up the SHPs so as bring about development in the remote areas of

    22

  • 7/30/2019 Final Wcm With Revie of Literature

    23/105

    Uttarakhand there by facilitating overall development of the state.

    STRATEGYFORFUTURECAPACITYADDITION:

    (a) Presently, UJVNL takes up the construction of the SHPs only after carrying out detailedsurvey(s), investigation(s) and engineering including cost optimization of various options. This

    requires collection of Hydrological and geological data besides synthesizing the same for

    arriving at a most economical engineering option. The entire work is outsourced to reputed

    agencies for timely completion besides maintaining the quality of work. Based on the past

    experience of the geology, metrology and the topography, safe designs have been adopted and

    where ever found necessary power channels have been replaced by tunnels.

    (b)Some of the other improvements in the process of development of SHPs are that: -

    I. Geological Surveys are being conducted in thorough manner so as to locate the

    power station at a safe place making it less prone to natural calamities.

    II. Power Channels are more prone to land slides/cloud bursting etc, therefore the water

    conductor system is being changed to tunnel as per site specific conditions.

    III. Machines of simple design are planned to be used for the power stations located in

    far off areas for their easy operation & maintenance.

    IV. Staff posted at these power stations is being given proper training in the operation &

    maintenance so as to minimize the break down time.

    POWER INDUSTRY

    Overview

    Power is a critical component of any economys infrastructure and without

    23

  • 7/30/2019 Final Wcm With Revie of Literature

    24/105

    its development, economic growth is severely hindered if not made

    impossible. It is an essential requirement of all facets of human life and is

    recognized as one of the basic human needs.

    An economys growth, development, ability to handle global competition is

    all dependent on the availability, reliability and quality of the power sector.

    The demand for power is growing exponentially and the scope of growth of

    this sector is immense.

    Global and Indian economy have decelerated, but power is one of the few

    commodities in short supply in India. So, despite the sluggishness in

    production and demand for manufactured products, India remains power

    hungry, both in terms of normal and peak power demand. Power is derived

    from various sources in India. These include thermal power, hydropower or

    hydroelectricity, solar power, biogas energy, wind power etc. The

    distribution of the power generated is undertaken by Rural Electrification

    Corporation for electricity power supply.

    As per the Constitution of India the power sector is mentioned in the

    Concurrent List and is under the purview of the Centre and the states. This

    sector is dominated primarily by Public Sector Undertakings. The state and

    Central Government account for 58% and 32% of the generation capacity

    respectively while the private sector accounts for a mere 10%. A major part

    of the transmission and distribution factors are handled by the state

    utilities. The private sector is slowly making its presence felt in the power

    sector in distribution and is making a foray into transmission. Power sector

    had been funded mainly through budgetary support and external

    borrowings were opened to private sector in 1991.

    Key players currently operating in the Indian power sector are National

    Thermal Power Corporation Limited, Nuclear Power Corporation of India

    Limited, North Eastern Electric Power Corporation Limited, Power Grid

    Corporation of India, Tata Power, etc.

    24

  • 7/30/2019 Final Wcm With Revie of Literature

    25/105

    Some Facts

    More than 64% of Indias total installed capacity is contributed by

    thermal power.

    Significant jump in unit size and steam parameters will result in higher

    efficiencies and better economics for the Indian power sector.

    Western region accounts for largest share (30.09%) of the installed power

    in India followed by Southern region with 27.76%.

    Unbalanced growth remains the cause of concern for the Indian power

    sector. Only about 56% of households have access to electricity, with the

    rural access being 44% and urban access about 82%.

    Southern region remains the dominant region in renewable energy

    source accounting for more than 57% of the total renewable energy

    installed capacity. India has installed power generation capacity of 1,41,079.84 MW as on

    January 31, 2008, which is about 100 times the installed capacity of

    1362 MW in the year 1947. Power generation has showcased a robust

    growth rate which is steadily improving year after year.

    There has been significant improvement in the growth in actual

    generation over the last few years. As compared to annual growth rate of

    about 3.1% at the end of 9th Plan and initial years of 10th Plan, the

    growth in generation during 2006-07 and 2007-08 was of the order of

    7.3% and 6.33% respectively.

    With the countrys power requirement expected to touch 8,00,000 MW by

    2031-32, India would need an investment of Rs6,00,000 crore. This

    25

  • 7/30/2019 Final Wcm With Revie of Literature

    26/105

    investment is possible only by attracting foreign direct investment and

    public-private participation in the power sector,

    At present, the energy shortage in the country was estimated at 10% and

    it touches 13% during peak seasons. There are states, where the energy

    shortage is 25%.

    This is a serious impediment in the way of industrial development and

    economic process. We need a crash project for capacity building and

    need to eliminate power shortage by 2012

    Outlook

    Over 78,000 MW of new generation capacity is planned in the next five

    years. A corresponding investment is required in Transmission and

    Distribution networks. Power costs need to be reduced from the current

    high of 8-10 cents/unit by a combination of lower AT & C losses,

    increased generation efficiencies and added low-cost generating capacity.

    Among the top issues facing power and utility companies in 2009 is the

    continued trend toward rising input costs (e.g., coal, natural gas) and

    increased construction risks, as the sector seeks to build out new

    infrastructure (both generation and transmission) to meet demand in

    environmentally responsible ways. When it comes to the fuel source,

    companies are experienced at managing price volatility. However, the

    credit crisis has created significant cash flow challenges for the hedging

    programs of many companies.

    Some power and utility companies looking to address the dual challenges

    of rising costs and tight credit markets are exploring constructionstrategies that embrace

    multiple potential power sources (coal, gas,nuclear, alternative energies), but which offer

    flexibility to change

    26

  • 7/30/2019 Final Wcm With Revie of Literature

    27/105

    As per data released by Central Electricity Authority, New Delhi the total installed capapcity in

    india is 159398.49 MW along with captive installed capacity of 19509 MW which are connect to

    National Grid system as on 31th March, 2010.

    The targeted capacity addition during 11th plan for various installed capacity sector is as

    under:

    Type/Sector Central State Private State Total

    Thermal 24840 11552 23301 59693

    27

  • 7/30/2019 Final Wcm With Revie of Literature

    28/105

    Hydro 8654 3491 3482 15627

    Nuclear 3380 0 0 3380

    Total 36874 15043 26783 78700

    India is hurrying up to enhance its installed capacity to meet out the power demand in the

    country. Even in this kind of scenario the power shortage is taking its toll on consumers

    consumptions as well as Industrial growth. The power shortage in various region will show the

    precarious condition of gap between power generation and consumption.

    Region Power shortage

    Energy Shortage (MU) Peak power Shortage (MW)

    Northern -29,570 -11.6 -5,720 -15.4

    Western -35,401 -13.7 -7,023 -17.7

    Southern -14,032 -6.4 -3,129 -9.7

    Eastern -3,910 -4.4 -836 -6.3

    North-Eastern -1,036 -11.1 -315 -17.9

    This power shortage is only going to increase in term of energy as well as peak power demand

    and supply.

    28

  • 7/30/2019 Final Wcm With Revie of Literature

    29/105

    Chibro Power Plant (4x60MW)

    The Power Station is a Run-of-Riverscheme with an underground power plant.

    The underground power plant was the first

    station in the north India and wascommissioned in the year 1975. The power

    station draws water from Ichari dam located

    on the river Tons, one of the major tributary

    of river Yamuna.

    The Chibro power station is a unique

    engineering marvel in the country and wasthe first experience in carrying out

    tunneling in the Himalayan Thrust Zones,

    which is a challenge due to varied rock structure and strength and throws up unexpected

    challenges in the tunneling effort. The water from Ichari dam is fed into the power stationthrough a 6.2 km long Head Race Tunnel (HRT) and the power plant comprising 4 units of 60

    MW each with Francis turbines of 84,000 HP output is housed in a rock cavern with the major

    challenge of maintaining fresh air and safety measures due to constraint in space. The PowerStation's Design Energy is 750 MU with a design head of 110 m.

    The power plant has shown significant improvements since 2000 and the generation has gone upin spite of restriction imposed by Irrigation Department on the discharge in the tunnel and low

    hydrology in the year 2004-05.

    There has been a restriction imposed by

    the Irrigation Department in limiting thedischarge in the HRT to 200 Cumecs asagainst the earlier capacity of 225

    Cumecs. The plants downtime has

    reduced and the availability has

    improved significantly.

    The increase in the efficiency and

    availability has been possible due to thenumber of maintenance and safety

    measures under taken which were

    pending since long time. The APDP alsoprovided funds for the modernization in

    a limited way mainly for installation of

    (i) Static Excitation System

    (ii) Microprocessor based governors and

    (iii) SF6 Breakers

    (iv) Major overhauling of Unit-2

    (v) Modernization of Communication System

    (vi) Tandem control System

    29

  • 7/30/2019 Final Wcm With Revie of Literature

    30/105

    The major maintenance works undertaken in the plant that have been responsible for improved

    performance are:-

    i) Repairing of MIV.

    ii) Monitoring of head loss.

    iii) Reduction in the Break down losses.

    UJVNL proposes to carry out the M&U of the power station which is estimated to cost Rs.

    201.25 crore. The major M&U works proposed are:-

    i) Modernization of Trash Rack cleaning equipment at Ichari dam.

    ii) Modernisation of Communication, Test & Control, Protection & Instrumentation, fireProtection equipment, switchyard equipment, hydro mechanical equipment etc.

    iii) Improvement in efficiencies of Turbines and generators.

    iv) Replacement of old 220kV oil filled cables with new XLPE cables

    v) Replacement of Stators' cores

    vi) Fire fighting system

    vii) Fresh Air Ventilation System

    The M&U works would enhance the life of power plant by another 20-25 years besidesimprovement in efficiency of turbines and generators. The post M&U generation is expected to

    increase to 850 MU and the works are expected to be completed by 2011-12.

    Year 2004-05 2005-06 2006-07 2007-082008-09

    (Upto Nov-08)

    Generation(MU) 637.90 804.94 756.17 755.08 724.19

    30

  • 7/30/2019 Final Wcm With Revie of Literature

    31/105

    31

  • 7/30/2019 Final Wcm With Revie of Literature

    32/105

    Ramganga Power Plant (3X66 MW)

    The power plant is a Reservoir based scheme on river Ramganga located near the famous Jim

    Corbet Park in district Pauri Garwhal and utilizes the water dammed up for irrigation purpose.The project was commissioned in 1975. The water in the irrigation channel is regulated by UP

    Irrigation and the generation is dependent on the rain in the catchment area as also on the

    drawal of water for irrigation purpose in the command area of the canal. The surface power

    house is located at the toe of the dam and houses 3 units of 66 MW each with Francis turbines of

    92400 HP. The Power Station's Design Energy is 311 MU with a design head of 84.4 m.

    The Ramganga power station is

    a medium head scheme with a

    design discharge of 285 cum.

    The project has unique

    challenges in operation due to

    restriction imposed on the

    release of water in the water

    conductor system by UP

    irrigation which is dependent on

    the demand of water in the command area of the canal based on the irrigation requirement. The

    generation in the plant takes place after the monsoon season when the demand for irrigation

    picks up.

    The generation from the plant is dependent on the drawal of water for irrigation in the

    downstream of the plant and rainfall in the catchment area.

    The repair of the downstream channel is with UP- Irrigation Department. UJVNL has taken up

    the repairs of the under water parts of the plant.

    UJVNL proposes to carry out the M&U of the power station which is estimated to cost Rs. 36.95

    crore. The major M&U works proposed are:-

    32

  • 7/30/2019 Final Wcm With Revie of Literature

    33/105

    i) Provision of Micro-processor based Governors, Static excitation equipments, On-line

    monitoring equipment and Replacement of Generator winding with F Class insulation.

    ii) Modernization of Communication, Test & Control, Protection & Instrumentation, switchyard

    equipment, hydro mechanical equipment, etc.

    iii) Repair of civil structures and MIV

    iv) Improvement in the efficiency of Generators and Turbines

    The generation after the completion of M&U works would increase to 315 MU and the works

    are expected to be completed by 2010-11.

    Year 2004-05 2005-06 2006-07 2007-082008-09

    (Upto Nov-08)

    Generation(MU) 211.88 333.29 154.17 279.06 118.66

    33

  • 7/30/2019 Final Wcm With Revie of Literature

    34/105

    Chilla Power Plant (4x36MW)

    The power station is a Run-of-River scheme on river Ganga located upstream of the holy cityof Hardwar and was commissioned in 1980-1981.There are 4 Kaplan vertical shaft turbines,

    Maximum operating head 32.5m Annual generation of the present design is about 725 MU

    which may increase to about 1076 MU due to the enhanced hydrological regulation in upper

    basins owing to commissioning of Tehri Project as well as upgrading works per current

    modern practice. For these reasons the time is being considered appropriate to undertake

    upgrading works so as to ensure the secure and reliable operation of the power station for

    the next 20-25 years.

    UJVNL proposes to carry out the M&U of the power station which is estimated to cost Rs.

    250.00 crore. The objective of the M&U program is to rehabilitate and upgrade the project

    to ensure dependable future generation and increase the station output to the highesteconomic level, keeping in view the following:

    i) Rehabilitate and modernize the Chilla power station.

    ii) Increase the Plant output, preferably by increasing the unit discharge and output.

    34

  • 7/30/2019 Final Wcm With Revie of Literature

    35/105

    iii) Provide hydraulic equipment that will be more resistant against erosion.

    iv) Provide new turbine runner with an improved cavitations behavior.

    v) Provide automatic trash rack cleaning machine.

    The generation after the completion of M&U works would increase to 1076 MU and the

    works are expected to be completed by 2011-12.

    Year 2004-05 2005-06 2006-07 2007-082008-09

    (Upto Nov-08)Generation(MU) 745.78 659.23 740.51 825.97 563.62

    35

  • 7/30/2019 Final Wcm With Revie of Literature

    36/105

    Khodri Power Plant (4x30MW)

    The Power Station is located on the downstream of the Chibro Power station and was

    commissioned in the year 1984. Thepower station draws water through

    a 6 km long and 7.5 diameter

    tunnel directly from the collection

    gallery of the Chibro power station.

    The surface Power House

    comprising 4 units of 30 MW each

    with Francis turbines of 43,600 HP

    output is located on the banks of

    Yamuna and the outlet of the water

    from the power station is in river Yamuna upstream of the Dakpathar Barrage. The Power

    Station's Design Energy is 345 MU with a design head of 57.9 m.

    The operation of Chibro power station and the Khodri power station is another engineering

    marvel. The tandem control scheme between Chibro and Khodri Power Stations is in operation

    since January, 1984 and is the first of its kind in the country which optimizes the utilization of

    water for generation besides maintaining the safety of both the plants in case of outages.

    The plants downtime has reduced and the availability has improved significantly. The

    improvements have been possible due to the number of maintenance and safety measures under

    taken which were pending since a long time. The APDP also provided funds for the

    modernization in a limited way mainly for installation of

    (i) Static Excitation System

    (ii) Dry Type Auxiliary Transformers and

    (iii) SF6 Breakers .

    36

  • 7/30/2019 Final Wcm With Revie of Literature

    37/105

    The major maintenance works undertaken in the plant that has been responsible for improved

    performance are:-

    i) Repair of underwater parts.

    ii) Epoxy Textolite wedges and packers were provided in the stator punching.

    iii) Replacement of old governors with Micro-processor based Governors

    UJVNL proposes to carry out the M&U of the power station which is estimated to cost Rs.

    120.00 crore. The major M&U works proposed are:-

    i) Provision of On-line monitoring equipment.

    ii) Digital display of parameters in control room.

    iii) Modernization of Communication, Test & Control, Protection, Instrumentation and fire

    protection of generators

    iv) Improvement in the efficiency of generators and Turbines.

    v) Fire fighting system

    The M&U works besides enhancing the life of plant by another 25 years would also increase the

    generation to 400 MU. The works are expected to be completed by 2011-12.

    Year 2004-05 2005-06 2006-07 2007-082008-09

    (Upto Nov-08)

    Generation(MU) 305.14 378.82 356.18 354.66 325.21

    37

  • 7/30/2019 Final Wcm With Revie of Literature

    38/105

    38

  • 7/30/2019 Final Wcm With Revie of Literature

    39/105

    Maneri Bhali Stage-II (4x76 MW)

    Maneri Bhali Hydroelectric Project Stage-II envisaged the utilization of the 285 m drop

    available in river Bhagirathi between the tail waters of Tiloth Power Station (Maneri BhaliStage-I Project) and the head waters of Tehri Dam. The diversion structure is situated near the

    township of Uttarkashi at about 152 km from Rishikesh, the nearest railhead, and is designed to

    divert 142 cumecs of water into a head race tunnel of diameter 6.0 m and length 16 km to

    generate 1566 Million Units of electricity annually through a power house of 4x76 MW at

    Dharasu. This project has been commissioned in 2008 & is the second power project of UJVNL

    on river Bhagirathi.

    River Bhagirathi a major tributary to River Ganga originates from Gangotri in the glacial

    Himalayas and meets river Alaknanda at Deoprayag to form Ganga which ultimately meets the

    ocean in the Bay of Bengal.

    SOME RECORDS IN THE NAME OF MB-II:

    Largest unit and plant capacity (4X76 MW) in UJVNL.

    Highest head (285 m gross) amongst the large power stations in UJVNL.

    Longest water conductor system (16 km. dia 6.0 m HRT) and highest surge tank (172m)

    in UJVNL.

    39

  • 7/30/2019 Final Wcm With Revie of Literature

    40/105

    Sedimentation chamber designed to allow smallest size of silt particle (below 150

    microns) in to the water conductor system.

    HVOF coating on turbine underwater parts being provided for preventing erosion, for the

    first time in the region.

    First power station in UJVNL to use single-phase generator transformer.

    First power station to use cyclonic strainers in cooling water system.

    First power station to use Nitrogen based fire protection system for main transformers in

    the region to use this system.

    Year 2007-082008-09

    (Upto Nov-08)

    Generation(MU) 77.02 853.99

    40

  • 7/30/2019 Final Wcm With Revie of Literature

    41/105

    LITERATURE REVIEW

    Introduction

    With the boat of success steaming ahead in the global markets, India has already become the

    most privileged destination for Outsourcing and capital Management. The word which one

    would simply lisp in the beginning of this century has become the most pronounced and sought

    after term.

    Generating revenues, fostering employments, elevating the living standards, an eternal inventory

    of opportunities simply showcase a phenomenon which is no less than the renaissance for our

    Indian markets. Many researchers have talked about Capital Management in their works,

    highlighted its capability as money making sector, showcased its doom of high employee

    turnover, sketched out its strengths, weaknesses, opportunities and threats, and also chalked out

    its dynamics of HR.

    Other researchers have extensively worked on various perceived attitudes of employees like their

    satisfaction, motivation, its influence on their tenure, their loyalty, commitment etc. This chapter

    unfolds all the relevant literature about the capital Management in Uttarakhnad Jal Vidyut

    theories and research works of employee motivation and satisfaction, and collaborates thefindings to tackle the problem of attrition in this sector.

    We live in an age of outsourcing, clearly designates that outsourcing has now become an

    acknowledged, accepted and established business strategy [38]. One of the most familiar forms

    of outsourcing is capital ,. Budget , in Uttarakhand Jal Vidyut Nigam ltd. i.e., transferring the

    operational ownership of one or more of the firms business processes to an external supplier

    that, in turn, administers the processes according to some predefined metrics is working capital

    management or Outsourcing thus refers to the rearrangement of entire business functions to

    some other service providers, primarily in low cost locations. The service provider may be either

    self-owned or a third party.

    41

  • 7/30/2019 Final Wcm With Revie of Literature

    42/105

    Some of the general services provided by the Uttarakhand Jal Vidyut Nigam ltd. Capital

    Management , Cash flow Analysis, Reconciliation, Data Entry, Payroll Processing, QuickBooks

    Accounting, Financial Statement Preparation and Accounting Services. Some of the web based

    services include live online sales and order entry, E-commerce transaction support, Live online

    enquiry handling, Web Design/Development. Here it is vital to note that capital management

    may comprise both IT management and business operations. Business operations include

    relocating or transferring functions such as payroll, accounting, billing or even real estate

    management to a third party. Invariably all these business processes depend on IT but they are

    unlike hard-core IT operations such as data center activities or network administration. An

    imperative facet of business process outsourcing is its capacity to free corporate executives from

    some of their day-to-day process management responsibilities and duties. Capital Management

    involves business process management and outsourcing. Business process management utilizes

    technology aimed at revamping the process, trimming down unnecessary steps, and eliminating

    redundancies. On the other hand outsourcing uses proficiency and resources of dedicated

    external service providers to execute many of these fundamental yet non-core activities. carries

    out both the functions at the same time, thereby speeding implementation and ascertaining that

    the intended benefits really hit the bottom line.

    CHAPTER-III

    RESEARCH

    METHODOLOGY

    42

  • 7/30/2019 Final Wcm With Revie of Literature

    43/105

    RESEARCH METHODOLOGY

    When we talk of Research Methodology, we not only talk of the research methods but also

    consider the logic behind the methods we use in the context of our research study and explain

    why we are using a particular method or technique and why we are not using so that research

    results are capable of being evaluated either by research himself or by others.

    As the title of the project suggests the project is about the study of the working capital

    management in the company. So my objective is that to know that how the working capital

    should be maintained in the company & which method is used in this.

    SAMPLE SIZE

    The sample size refers to the no. of employees selected from the company to constitute a sample.

    The sample size used for study includes two companies.

    METHOD OF SAMPLING

    The process employed for the sample was Cluster Sampling.

    Sample Size: 2

    Method of Sampling: Cluster

    Area of work: Working capital management

    Method of Data collection: Secondary

    Tools: Annual report, Balance sheet, Internal sources.

    43

  • 7/30/2019 Final Wcm With Revie of Literature

    44/105

    SOURCES OF DATA COLLECTION

    SECONDARY DATA

    Secondary data are those which have already been collected by someone else and have already

    been passed through the statistical process.

    Acc. to Dessel-Data collected by other persons

    All the data has been collected from internal source that includes:-

    a) Magazines

    b) Books

    c) Websites

    d) Reports

    e) Files

    f) Staff

    DATA COLLECTION METHOD

    The data was collected by me from both the sources for my training project report. In case of

    secondary ways of data collection of magazines and books of UJVNL were used.

    44

  • 7/30/2019 Final Wcm With Revie of Literature

    45/105

    WORKING CAPITAL

    Working capital in short may be said as the capital required in meeting the short tem needs . The

    requirement of working capital differs from firm to firm. The firm may require large amount of

    working capital or may be less, it depends on the kind of work done by the particular

    organization.

    CLASSIFICATION OR KINDS OF WORKING CAPITAL

    Kinds of working capital

    On the basis

    of conceptOn the basis

    of time

    Gross

    working

    capital

    Net

    working

    capital

    Permanent

    or fixed

    working

    capital

    Temporary

    or variable

    working

    capital

    Regular working

    capital

    Reserve

    working capital

    Seasonal

    working capital

    Special

    working capital

    45

  • 7/30/2019 Final Wcm With Revie of Literature

    46/105

    GROSS WORKING CAPITAL: Total current assets

    1. Gross working capital: - Gross working capital refers to the firms investment in

    current assets. Current assets are the assets which can be converted into cash within an

    accounting year and include cash, short term securities, debtors, (account receivable or

    book debts) bills receivable and stock (inventory).

    NET WORKING CAPITAL: Change in current assets and current liabilities

    Thus

    Working capital= current assets- current liabilities

    Net working capital: - Net working capital refers to the difference between current

    assets and current liabilities. Current liabilities are those claims of outsider which are

    expected to mature for payment within an accounting year and include creditors (account

    payable), bills payable, and outstanding expenses. Net working capital can be positive. Or

    negative. A positive net working capital will arise when current assets exceed current

    liabilities. A negative net working capital occurs when current liabilities s are in excess of

    current assets.

    The two concepts of working capital gross and net-are not exclusive rather, they have equal

    significance from the management viewpoint.

    Permanent or fixed working capital: It is the minimum amount which is required to ensure

    effective utilization of fixed facilities and maintaining the circulation of current assets. For

    example every firm has to maintain a minimum level of raw material, work-in-progress, finished

    goods and cash balance. This minimum level of current asset is called permanent or fixed

    working capital as this part of capital is permanently blocked in current asset.

    Temporary or variable working capital: It is the amount of working capital which is required

    to meet the seasonal demand and some exigencies. Variable working capital can be further be

    classified as

    Seasonal working capital: the capital required to meet the seasonal needs of the

    enterprises is called as seasonal working capital.

    46

  • 7/30/2019 Final Wcm With Revie of Literature

    47/105

    Special working capital: That part of working capital which is required to meet special

    exigencies such as launching of extensive marketing campaigns for conducting research

    etc.

    OPERATING CYCLE OF WORKING CAPITAL

    Sufficient working capital is necessary to sustain sales activity. Technically this is

    referred to as a operating/ cash cycle. It can be said to be at the heart of the need of

    working capital.

    Cash/operating cycle is the length of time necessary to complete following

    event.

    Convert cash into raw material.

    Raw material into goods in process.

    Goods in process into finished goods.

    Finished goods into debtors through credit sales, and debtor into cash.

    The cycle is a continuous process

    47

    CASH

    FINISHED

    GOODS

    DEBTORS

    RAW

    MATERIAL

    WORK INPROGRESS

    SALES

  • 7/30/2019 Final Wcm With Revie of Literature

    48/105

    OPERATING CYCLE

    The Working Capital cycle or Cash Conversion cycle as it is also called is usually expressed in

    terms of the number of days. This figure is the average time that it takes to turn investment in

    books into cash and profit. Payback expresses the number of days required to recoup the original

    investment on a single title. In the organizations Balance Sheet there will be the costs of paper,

    titles still under development, and author advances of books already and not yet published. In

    addition there will be the cost of stocks of unsold books, Accounts Receivable, and Accounts

    Payable.

    Determinants of working capital

    The requirements of working capital generally vary from industry to industry, concern to

    concern and time to time. Comparing the production cycle of UJVNL with any of the FMCG

    Company we will notice that, UJVNL takes considerably longer period to manufacture a

    turbine while in FMCG companies like HLL or P&G takes few minutes to manufacture their

    product. Working capital in these companies can be even negative as they take credit from

    suppliers and sell their products on cash. So current liabilities are higher due to which figure

    of working capital can be negative. The various factor which influence the amount ofworking capital required by a business enterprises, may be grouped under two heads.

    1) Internal factor: - The factor which are within the control and competence of

    management. These may include the risk taking attitude of management, turn over of

    receivable and inventories terms of purchase and sale s and credit rating etc.

    2) External factor: - these may include the nature of business, volume of production and

    sales and business cycle.

    PERMANENT AND TEMPORARY WORKING CAPITAL

    The operating cycle thus crates the need for current assets (working capital).however this need

    does not come to an end after the cycle is completed. It continues to exist. Thus the distinction

    betweenpermanentand temporary working capital should be known.

    48

  • 7/30/2019 Final Wcm With Revie of Literature

    49/105

    Business keeps on going even after the realization of cash from customers, which creates the

    need for regular supply of working capital. However the magnitude of Working capital required

    is not constant, but fluctuating. To carry on business, a certain minimum level of Working capital

    is necessary on a continuous and uninterrupted basis. For all practical purpose, this requirement

    has to be met permanently as with other fixed assets. This requirement is referred to as

    Permanent or fixed Working capital.

    Any amount over or above the permanent level of Working capital is temporary, fluctuating or

    variable Working capital. This portion of the required Working capital is needed to meet

    fluctuation in demand consequent upon changes in production and sales as a result of seasonal

    changes. The basic distinction between these two is:

    0

    5

    10

    15

    20

    25

    30

    Area 2

    5

    PERMANENT WO RKING CAPITAAL

    TEMPORARY WORKING

    CAPITAL

    FINANCING OF WORKING CAPITAL

    The various sources for the financing of working capital are as follows:

    Sources of Working capital

    49

  • 7/30/2019 Final Wcm With Revie of Literature

    50/105

    Permanent or fixed Temporary or variable

    1. Shares

    2. Debentures

    3. Public deposits

    4. Ploughing back of profits

    5. Loans from Financial institutions.

    CALCULATION OF WORKING CAPITAL

    Working capital is the excess of current assets over current liabilities. Information regarding

    current assets and current liabilities is available from the balance sheet. Working capital should

    be sufficient to meet routine requirement of the business.

    The two concepts of working capital are current assets and current liabilities. They have a

    bearing on the cash operating cycle. In order to calculate the working capital the working capital

    needs, what is required is the holding period of various types of inventories, the credit collection

    period and credit payment period. Working capital also depends on the budgeted level of activity

    in terms of production/sales. The calculation of working capital is based on the assumption that

    the production/sales is carried on evenly throughout the year and all costs accrue similarly. As

    the working capital requirements are related to the cost excluding and not to the sale price.

    Working capital is computed with reference to cash cost. The cash cost approach is

    comprehensive and superior to the operating cycle approach based on holding period of debtors

    and inventories and payment of creditors.

    The computation of working capital can be summarized as follows:(I) Estimation of current asset :

    a) Minimum desired cash and bank balances

    b) Inventories

    Raw material

    Work-in-progress

    50

    1. Commercial banks

    2. Indigenous bankers

    3. Trade creditors

    4. Installment credit

    5. Advances

    6. Accounts Receivables-

    Credit/Factoring

    7. Accrued expenses

    8. Commercial papers

  • 7/30/2019 Final Wcm With Revie of Literature

    51/105

    Finished goods

    c) Debtors*

    Total current assets

    (II) Estimation of current liabilities :

    a) Creditors**

    b) Wages

    c) Overheads

    Total current liabilities

    (III) Net working capital (I-II)

    Add: margin for contingency

    (IV) Net working capital required

    * If payment is received in advance, the item would be listed in current liabilities.

    ** If advance payment is to be made to creditors, the item would appear under current

    asset. The same would be treated for advance payment of wages and overheads.

    IMPORTANCE OR ADVANTAGES OF WORKING CAPITAL

    Working capital is the blood and nerve centre of a business. Just as circulation of blood is

    essential in the human body for maintaining life, working capital is very essential to maintain the

    smooth running of a business. No business can run successfully without an adequate amount of

    working capital. The main advantages of maintaining adequate amount of working capital are as

    follows:

    Solvency of the business.

    Goodwill

    Easy loans

    Cash discounts

    Regular supply of raw materials

    51

  • 7/30/2019 Final Wcm With Revie of Literature

    52/105

    Regular payment of salaries, wages and other day-to-day commitments.

    Exploitation of favorable market conditions.

    Ability to face crisis

    Quick and regular return on investments

    High morale.

    WORKING CAPITAL MANAGEMENT

    Working Capital is the money used to make goods and attract sales. The less Working Capital

    used to attract sales, the higher is likely to be the return on investment. Working Capital

    management is about the commercial and financial aspects of Inventory, credit, purchasing,

    marketing, and royalty and investment policy. The higher the profit margin, the lower is likely to

    be the level of Working Capital tied up in creating and selling titles. The faster that we create and

    sell the books the higher is likely to be the return on investment. Thus when we have been using

    the word investment in the chapter on pricing, we have been discussing Working Capital.

    AFFECT OF BUSINESS TRANSACTIONS ON WORKING CAPITAL

    In preparing a statement of changes in financial position, on working capital basis, it is convient

    to classify business transactions into three categories:

    1. Transactions Affecting only Current Asset or Current liabilities Accounts: These

    transactions produce changes in working capital accounts but do not change the account of

    working capitals. For example, the purchase of merchandise increases inventory and accounts

    payable but has no effect on working capital; it may therefore be ignored in preparing the

    statement of changes in financial positions. Similarly, paying accounts payable affects cash, so

    this transaction would be reflected in cash basis statement of changes in financial position.

    However, the transaction has no effect on working capital since a current asset (cash) and a

    current liability (accounts payable) decrease by the same amount. Hence, the transaction would

    not be reflected as a source or use in a working capital basis statement of changes in financial

    position. Other transactions like collection of receivables, short-term borrowing, purchase of

    52

  • 7/30/2019 Final Wcm With Revie of Literature

    53/105

    short-term government securities also fall in this category of transactions. Thus, when funds are

    defined as working capital, there is no need to show the details of the more or less continous

    movement of resources between current liabilities and current assets which results from the

    manufacture and sale of goods and the collection of receivables from customers. Indeed, the

    focus is on the usually more significant flows affecting non-current assets (i.e. long term

    investments) and permanent capital, the name given to the sum of long-term liabilities and

    owners equity.

    Thus the funds statement, i.e. Statement of Chances in Financial Position based on changes in

    working capital position, is a better and useful tool for highlighting the changes that have taken

    place in the financial operations between two balance sheet dates.

    2. Transactions Affecting Current Asset or Current Liability Account and a Non-Working

    Capital (Non-current) Account: These transactions bring about either an increase or a decrease

    in the amount of working capital. The issue of long-term bonds, for example, increases current

    assets and increases loan on bonds, a non-working capital account; therefore the issue of bonds

    is a source of working capital. Similarly when the bonds approach maturity they are transferred

    to the current liability classification in the balance sheet. This causes a reduction (a use) of

    working capital. If changes in non-working capital accounts are analyzed, these events are

    brought to light, and their effect on working capital will be reported in the statement of changes

    in financial position.3. Transactions affecting only Non-current Accounts: These transactions have no direct effect

    on the amount of working capital. The entry to record depreciation is an example of such a

    transaction. Other transaction in this category, such as issue of share capital in exchange for plant

    assets, are called exchanged transactions involving only non-current accounts and are viewed as

    both a source and a use of working capital, but do not change the amount of working capital.

    Alternatively, such exchange transactions may not be considered in preparing a statement of

    changes in financial position on working capital basis.

    WORKING CAPITAL ANALYSIS OR MEASURING THE WORKING CAPITAL

    The working capital is a means to run the business smooth and profitably, and not an end. Thus,

    concept of working capital has its own importance in a going concern. A going concern, usually,

    has a positive balance of working capital i.e., the excess of current assets over current liabilities,

    but sometimes the uses of working capital may be more than the sources resulting into a negative

    53

  • 7/30/2019 Final Wcm With Revie of Literature

    54/105

    value of working capital. This negative balance is generally offset soon by gains in the following

    periods. A study of changes in the uses and sources of working capital is necessary to evaluate

    the efficiency with which the working capital is employed in the business. This involves the need

    of working capital analysis.

    The analysis of working capital can be conducted through a number of devices, such as:

    1. Ratio analysis

    2. Funds flow analysis

    3. Budgeting

    Ratio Analysis: A ratio is a simple arithmetical expression of the relationship of one number to

    another. The technique of ratio analysis can be employed for measuring shot-term liquidity or

    working capital position of the firm. The following ratios can be calculated for this purpose:

    Current ratio

    Acid test ratio

    Absolute liquid ratio or cash position ratio

    Inventory turnover ratio

    Receivables turnover ratio

    Payables turnover ratio

    Working capital turnover ratio

    Working capital leverages

    Ratio of current liabilities to tangible net worth

    Asset Usage

    The assessment of asset usage is important as it helps us to understand the overall level of

    efficiency at which a business is performing.

    The basic equations for this section are:

    Total Asset Turnover =Turnover

    Total Assets

    54

  • 7/30/2019 Final Wcm With Revie of Literature

    55/105

    Stock Turnover =Average Stocks

    Credit Sales/365

    Debtors Turnover =Average Debtors

    Credit Sales/365

    Creditors Turnover =Average Creditors

    Credit Sales/365

    The assessment of asset usage is important as it helps us to understand the overall level of

    efficiency at which a business is performing.

    55

  • 7/30/2019 Final Wcm With Revie of Literature

    56/105

    DIFFERENCE BETWEEN CASH FLOW AND FUND FLOW STATEMENT

    BASIS OF

    DIFFERENCE

    CASH FLOW STATEMENT FUNDS FLOW STATEMENT

    MEANING It is a statement of changes in

    the financial position of business

    due to the inflow and outflow of

    cash.

    It is a statement of changes in the

    financial position of business due to

    the inflow and outflow of funds.

    PLANNING

    PERIOD

    Statement of cash flow is

    required for short range

    planning.

    Funds flow statement is required for

    long range planning.

    RELIABILTY Plans for more immediate future

    can rely upon information

    supplied by cash flow statement.

    Plans for more immediate future

    cannot rely upon information

    supplied by funds flow statement.

    TREATMENT OF

    CURRENT ASSETS

    It does not treat all current assets

    as cash.

    It treats all current assets at par with

    funds, although debts are collected

    within months and stock is sold

    within 6 months.

    TREATMENT OF

    CURRENT

    LIABILITIES

    Increase in bank overdraft and

    increase in outstanding expenses

    are treated separately.

    Increase in outstanding expenses is

    treated as increase in overdraft.

    CASH/FUNDS

    FROM OPERATION

    While making cash flow

    statement cash from operation is

    calculated.

    While making funds flow statement

    funds from operation is calculated.

    BASIS Prepared on cash basis. Prepared on accrual basis.

    Working capital budget:

    A budget is a financial and/or quantitative expression of business plans and policies to be

    pursued in the future period of time. Working capital budget, as a part of total budgeting process

    of a business, is prepared estimating future long-term and short-term working capital needs and

    the sources to finance them, and then comparing the budgeted figures with the actual performance

    for calculating variances, if any, so that corrective actions may be taken in the future. The objective of

    working capital budget is to ensure the availability of funds as and when needed, and to ensure effective

    utilization of these resources. The successful implementation of working capital budget involves the

    56

  • 7/30/2019 Final Wcm With Revie of Literature

    57/105

    preparing of separate budgets for various elements of working capital, such as cash, inventories and

    receivables, etc.

    Working Capital Management (Debt vs. Equity)

    Working capital is the money you will need to keep your business going until you can cover your

    operating costs out of revenue. As a small business owner, it will be wise to have enough

    working capital on hand to cover items such as the following during the first few months that

    you are in business:

    Replacing inventory and raw materials: you will need to fund the purchase of inventory

    out of working capital until you start to see cash from sales, which could take months.

    Paying employees: even the most loyal worker wants to get paid on time, regardless of

    how much or how little cash your firm earns during its first months.

    Paying yourself: unless you have made other arrangements, you will need to withdraw

    some money to support yourself.

    Debt payments: if you have borrowed money to get started, you probably have to begin

    repaying it right away. Missing your first loan payments will not do your credit rating any

    good.

    An emergency fund: you need some cash on hand to cover unforeseen shortfalls that may

    result from any number of factors such as delays in getting your space ready, a slowpaying client, or slow business.

    Debt vs. Equity Assessments

    It is essential that you assess the relative merits of each form of funding for your specific

    business.

    57

  • 7/30/2019 Final Wcm With Revie of Literature

    58/105

    DEBT EQUITY

    Take on Creditors Take on Partners

    Low Expected Return High Expected Return

    Smaller Funding Amounts Larger Funding Amount

    Periodic Payments No Short-Term Payments

    Maturity Date Open-Ended Exit Date

    More Restrictions Less Restrictions

    ADVANTAGES OF USING DEBT

    DISADVANTAGES OF USING DEBT

    Debt is not an ownership interest in the

    business. Creditors generally do not have

    voting power.

    Unpaid debt is a liability of the business. If it is

    not paid then the creditors can legally claim the

    assets of the firm. This action can result in

    liquidation or reorganization.

    The payment of interest on debt is considered a

    cost of doing business and is fully tax

    deductible.

    Your business must earn at least enough money

    to cover for the interest expense, otherwise you

    may not be able to pay you interest which may

    lead to default (financial distress).

    The creditors will only be concerned that the

    business will be able to generate cash flow to

    cover interest expenses.

    ADVANTAGES OF USING EQUITY DISADVANTAGES OF USING EQUITY

    Unlike obligation of debt, your business will not

    have any contractual obligation to pay for

    equity dividend.

    Equity is an ownership of the business. So an

    equity partner will have a direct say about your

    business.

    Equity financing also allows your business to

    obtain funds without incurring debt, or without

    58

  • 7/30/2019 Final Wcm With Revie of Literature

    59/105

    having to repay a specific amount of money at a

    particular time.

    Making more efficient use of Working Capital

    The table below lists items, which influence Working Capital levels favorably and adversely

    Items that reduce Working Capital

    levels for publishers

    Items that increase Working

    Capital levels for publishers

    - Increased profit margins - Lower profit margins

    - Customers who pay promptly

    - Advance payments by customers

    - Long print runs except where all the

    books are required on publication e.g.School and university textbooks

    - Inventory which is sold and paid for

    quickly by customers after publication

    - Lower Inventory levels by reducing

    print quantities and working with

    printers who will deliver quickly and

    produce low print runs economically

    - Slow authors who deliver late and

    whose manuscripts require substantial

    editing

    - Holding paper stock unless market

    conditions demand and the savings

    are large

    - Slow schedules for the development

    of new titles

    - Successful promotion that speeds up

    the rate of sale

    - Making advance payments to

    printers

    - Seasonal sales except where the

    publishers prints only for the season

    - Licensing (but problematic in young

    economies)

    - Paying suppliers on completion with

    credit

    - Authors who deliver manuscripts on

    disk ready for computer make-up

    - Incentives to staff , authors , suppliers,

    customers , sales staff and agents to

    59

  • 7/30/2019 Final Wcm With Revie of Literature

    60/105

    speed up the rate of sale and of

    developing new books, delivering

    manuscripts on schedule

    Measures to Improve Working capital management

    The essence of effective Working capital management is proper cash flow forecasting. This

    should take into account the impact of unforeseen events, market cycles, loss of a prime

    customer and actions by competitors. The effect of unforeseen demands of Working capital

    should be factored in.

    It pays to have contingency plans to tide over unexpected events. While market-leaders can

    manage uncertainty better, even other companies must have risk-management procedures. These

    must be based on objective and realistic view of the role of Working capital

    Addressing the issue of Working capital on a corporate-wide basis has certain advantages. Cash

    generated at one location can well be utilized at another. For this to happen, information access,

    efficient banking channels, good linkages between production and billing, internal systems to

    move cash and good treasury practices should be in place.

    An innovative approach, combining operational and financial skills and an all-encompassing

    view of the companys operations will help in identifying and implementing strategies that

    generate short-term cash. This can be achieved by having the right set of executives who are

    responsible for setting targets and performance levels. They are then held accountable for

    delivering, encouraged to be enterprising and to act as change agents.

    Effective dispute management procedures in relation to customers will go along way in freeing

    up cash otherwise locked in due to disputes. It will also improve customer service and free up

    time for legitimate activities like sales, order entry and cash collection. Overall, efficiency will

    increase due to reduced operating costs.

    Collaborating with your customers instead of being focused only on own operations will also

    yield good results. If feasible, helping them to plan their inventory requirements efficiently to

    match your production with their consumption will help reduce inventory levels. This can be

    done with suppliers also.

    60

  • 7/30/2019 Final Wcm With Revie of Literature

    61/105

    Working capital management is an important yardstick to measure a company operational

    and financial efficiency. This aspect must form part of the companys strategic and

    operational thinking. Efforts should constantly be made to improve the Working capital

    position. This will yield greater efficiencies and improve customer satisfaction

    61

  • 7/30/2019 Final Wcm With Revie of Literature

    62/105

    Structure of Working Capital of UJVNL

    The analysis of structure of working capital enables management of an enterprise to know as

    to how the working capital is being administered. It also furnishes valuable information to

    the short term creditors and others regarding the strength of working capital of the

    undertaking.

    The structure of working capital can also be analyzed by measuring the change the

    proportion of cash, receivable, inventory and other items to the total current assets in course

    of time.

    This analysis points out the components which have over grown and where unduly high fund

    has been tied up. This analysis may be carried further to each component of current assets to

    study the changes in its sub-divisions.

    Investment in working capital is generally considered as dead investment as it, does not

    contribute towards companys profit generating capacity but are also required, so it should be

    done in such a way that it does not create any side-effects like blockage of money. In

    comparison to working capital, investments should be more in fixed assets which are

    productive and contribute towards firms profit.

    62

  • 7/30/2019 Final Wcm With Revie of Literature

    63/105

    WORKING CAPITAL PATTERN OF UJVNL

    (In 000)

    CURRENT ASSET 2006-07 2005-06 2004-05

    Inventory 2149406 1847956 1341899

    Sundry debtors 286070 208516 443147

    Cash & bank

    balance 486460 353395 163062

    Other C.A. 1709 5558 2185

    Loans & advances 890016 940652 631468

    TOTAL C.A. 3813661 3356077 2581761

    CURRENT

    LIABILITIES

    Current liabilities 2381169 2247006 2059717

    Provision 849097 783313 973431

    TOTAL 3230266 3030319 3033148

    WORKING CAPITAL 583395 325758 (451387)

    TURNOVER 14525.49 10336.4

    W.C. CONVERSION

    PERIOD (in days) 151 173

    63

  • 7/30/2019 Final Wcm With Revie of Literature

    64/105

    (Working Capital = Total current assets Total current liabilities)

    64

  • 7/30/2019 Final Wcm With Revie of Literature

    65/105

    Working capital pattern of BIL of last 2

    years

    -451387

    325758

    583395

    -600000

    -400000

    -200000

    0

    200000

    400000

    600000

    800000

    2004-05 2005-06 2006-07

    65

  • 7/30/2019 Final Wcm With Revie of Literature

    66/105

    SHAREHOLDING PATTERN

    Category No. of shares held %age of share

    holding

    2004-05 2005-06 2004-05 2005-06

    A. Promoters Holding1. Promoters

    - Indian 750 750 0.00 0.00

    - Foreign 1217321

    9

    1217321

    9

    50.96 50.96

    2. Persons acting in concert - - - -

    Sub Total 1217396

    9

    1217396

    9

    50.96 50.96

    B. Non-Promoters Holding 1171619

    4

    1171619

    4

    49.04 49.04

    3. Institutional Investor

    a. Mutual Funds and UTI 861938 653796 3.61 2.74

    b. Banks, Financial institutions, insurance

    companies (Central/State Govt. Institutions/

    Non-Govt. Institutions)

    4137370 3263233 17.32 13.66

    c. Foreign Institutional Investors (FIIs) 1402489 2977656 5.87 12.46

    Sub Total 6401797 6894685 26.80 28.86

    4. Others

    a. Private Corporate bodies 338934 235253 1.42 0.98b. Indian Public 4851195 4467818 20.30 18.70

    c. NRIs/OCBs 120388 114148 0.50 0.48

    d. Any Other 3880 4290 0.02 0.02

    Sub Total 5314397 4821509 22.24 20.18

    GRAND TOTAL 2389016

    3

    2389016

    3

    100.00 100.00

    66

  • 7/30/2019 Final Wcm With Revie of Literature

    67/105

    PIE CHART SHOWING SHAREHOLDING PATTERN OF

    BILFOR THE YEAR 2005-06

    0

    50.96

    2.7413.66

    12.46

    0.98

    18.7

    0.48 0.02

    Indian Promoters Foreign Promoters

    Mutual funds & UTI Banks

    FIIs Private corporate bodies

    Indian Public NRIs/OCBs

    Other

    67

  • 7/30/2019 Final Wcm With Revie of Literature

    68/105

    PIE CHART SHOWING SHARE HOLDING PATTERN OF BIL

    FOR THE YEAR 2004-05

    0

    50.96

    3.6117.32

    5.87

    20.3

    0.5 0.02

    1.42

    Indian Promoters Foreign Promoters

    Mutual funds & UTI Banks

    FIIs Private corporate bodies

    Indian Public NRIs/OCBs

    Other

    68

  • 7/30/2019 Final Wcm With Revie of Literature

    69/105

  • 7/30/2019 Final Wcm With Revie of Literature

    70/105

    WORKING CAPITAL FOR THE YEAR 2005-06

    G/L PARTICULARS AMOUNT TOTAL

    CURRENT ASSETS

    CLOSING STOCK

    20500

    1 INVENTORY FO 2386279.87

    20500

    2 INVENTORY HSD 1319357.44

    20500

    3 INVENTORY LDO 775863.92

    20500

    4 INVENTORY ENGG.STR 3090080.1620600

    0 INVENTORY INGREDIENT 29191221.91

    20600

    1 INVENTORY PACKING 20387586.5

    20600

    2 INVENTORY CBBS,CLSG 2245570.54

    20700

    3 INVENTORY FG BISCUITS 5614899.25

    20701

    3 INVENTORY WIP- GOOT 151412.2520701

    9 CLOSING STOCK INV FG 552790.21

    A/C RECEIVABLE

    21000

    0 ACCOUNTS RECEIVABLE DOMESTIC 12048.89

    CASH IN HAND 21100

    2 CASH IN HAND-DEL BR 0

    21104

    3 CASH IN HAND-UA 34476

    CASH AT BANK 21305

    2

    CITI BANK DELHI MAIN

    70

  • 7/30/2019 Final Wcm With Revie of Literature

    71/105

    OF UJVNL INDUSTRIES LTD. Pantnagar (Uttarakhand)

    G/L PARTICULARS AMOUNT TOTAL

    CURRENT ASSETS

    CLOSING STOCK205001 INVENTORY FO 1250901.87

    205002 INVENTORY HSD 1737552.76

    205003 INVENTORY LDO 1322501.12205004 INVENTORY ENGG.STR 6571934.32

    206000 INVENTORY INGREDIENT 84432770.4

    206001 INVENTORY PACKING 16249728.09206002 INVENTORY CBBS,CLSG 2444207.44

    207003 INVENTORY FG BISCUITS 19911752.57

    207013 INVENTORY WIP- GOOT 132982.7

    207019 CLOSING STOCK INV FG 166906.11

    209000 LOOSE TOOLS 905051.8

    A/C RECEIVABLE 210000 ACCOUNTS RECEIVABLE DOMESTIC 4896050.28

    CASH IN HAND 211002 CASH IN HAND-DEL BR 0

    211043 CASH IN HAND-UA 15917

    PREPAID EXPENSES 220002 PREPAID EXPENSES MISC 14446.68

    220003 PREPAID INSURANCE 59052220004 PREPAID LEASE RENTAL 0220006 PREPAID MEDICAL INSUR. 0

    220009 PREPAID RATES & TAXES 0

    220041 PREPAID GROUP INSUR 5515220039 ADVANCE STAFF TRAVEL DOM 54417

    WIP

    202000 CWIP 0

    202001 AUC- D&M(CWIP) 5369271.68

    TOTAL CURRENT ASSETS 145540958.8

    CURRENT LIABILITIES

    BILLS PAYABLE

    111000 ACC PAYABLE DOMESTIC 45606390.3111001 ACC PAYABLE EXPORT 0

    111002 ACC PAYABLE ONE VD 51391

    111003 ACC PAYABLE STATUT 525202

    71

  • 7/30/2019 Final Wcm With Revie of Literature

    72/105

    111004 ACC PAYABLE EMPL 2030111005 ACC PAYABLE SSI 135300

    111007 ACC PAYABLE AW VENDOR 0

    104143 DEPOSIT PAYABLE VENDR 275000104127 DEPOSIT PAYABLE CUST OTH 150000

    104118 C.S.T PAYABLE 4154.89

    104165 WORK CONT TAX PAYABLE 28377104201 APMC CLEARING A/C 0

    104202 GR/IR-CLEARING-PRO 2721309.9

    104203 FREIGHT CLEARING (MM) 12046697.98

    ACCRUED & O/S EXPENSES

    104016 ACC MISC EXPENSES 8076499.86104017 ACC ONWARD FREIGH 669362.71

    104023 ACCR PRIMARY FREIGHT 26697238.71

    104025 ACCR SALARIES & WAGES 614091104033 ACCR LOADING 81934

    104220 ACCR TAX SERVICE 0104207 TDS CONTRACTOR S 194 C 517762104209 TDS RENT SEC 1941 21004

    104210 TDS- PROF.FEES 194 J 729

    104218 TCS CUST SCRAP SALE 6646.51

    104244 VAT PAYABLE 86142.02104245 VAT INPUT CREDIT RM 0

    104246 VAT INPUT CREDIT CG 0

    104152 MISC RECOVERY 0

    CREDITORS

    104050 CO CONTR GPF LIA A/C 71111104053 CO CONTR ESI LIA A/C 33200

    104154 RET. PAYABLE VENDOR 8426606.06

    104064 EMPL CONTR ESIC 12256

    104128 STALE CHJEQE /AC 70946.07104067 EMPL CONTR GPF 62697

    104124 ENTRY TAX 102750.37104125 TDS INT DEP SEC 194 A 0

    104126 AACO DEP PAYABLE CUSTM 0

    PROVISIONS 110002 PROV FOR BONUS 9