Final rept 'Containment Sump Check Valves Weld Overlay ...c-,.;.' v 0054-o01o1-001-11o Revision 1...
Transcript of Final rept 'Containment Sump Check Valves Weld Overlay ...c-,.;.' v 0054-o01o1-001-11o Revision 1...
-
i!
; i \l
|
)
ATTACHMENT
Consumers Power CompanyPalisades PlantDocket 50-255
WELD OVERLAY REPAIRS OF CONTAINMENT SUMP CHECK VALVESFOLLOW-UP INFORMATION
July 15, 1994
:
>
;
i
i
|.
9407250324 940715PDR ADOCK 05000255P pop ,
-
.
c- ,
.; .' v.
0054-o01o1-001-11oRevision 1
VECTRA 0054.00101.001.110 '
.
FINAL REPORT
CONTAINMENT SUMP CHECK VALVES ''
WELD OVERLAY REPAIRIMPLEMENTATION EVALUATION
PALISADES NUCLEAR PLANT
Prepared for: ;
Consumers Power Company (
,
Prepared by:
VECTRA
,
Reviewed by: Issued by:
~
.
Carl H. Froehlich, P.E. Dale L. Jor/sEngineering Manager Project M4 nager
_
Date: 14 ZIy I'IfY 't
|
|
-
1
REVISION CONTROL SHEET.c ,.
TITLE: Final Report - Containment Sump DOC. FILE NO.: 0054.00101.001.110Check Valves Weld Overlay RepairIrT.plementation Evaluation -Palisades Nuclear Plant
Carl H. Froehlich / Staff Engineer CMMlNAME/ TITLE INITIALS
James W. Axline / Staff Engineer On File
NAME/ TITLE INITIALS
James A. Brown / Staff Engineer [-INAME/ TITLE INITIALS
NAME/ TITLE INITIALS
AFFECTED DDC. PREPARED ACCURACY CRITERIAPAGE(S) REV. BY/DATE CHECK BY/DATE CHECK BY/DATE REMARKS
iii - v 0 On File On File On File issued for use.
1 - 38 0 " " *
CA/J /4/g4 T/ft/g 7/#9/p Corrected typo.715 117 & 18 1 incorporated CPCo comment.
;
21 - 23 1 |"
25 & 28 1 W Corrected typo.
;
I
|
!
PAGE 1 OF 1 i
- ii - |
-
, .~ -
-,
,0
' ' V |,
~ " ' ~ '#~ ' '' ' ' ' 'VECTRA Revision 0
TABLE OF CONTENTS |
Enae
LIST OF TABLES iv
LIST OF FIGURES v ,l
1.0 INTRODUCTION 1
2.0 OVERLAY IMPLEMENTATION REQUIREMENTS 6,
l2.1 ASME Section XI Repair Program 6 12.2 Overlay Material and Application Requirements 6 '2.3 Original Pipe Surface Liquid Penetrant Examination 72.4 Original Pipe Surface Repair / Seal Layer PT Examination 82.5 Minimum 2 Layer Thickness 8 l2.6 Ferrite Content 92.7 NDE Access 9 ,2.8 Overlay Design 9 l2.9 Repaired Weldment/ Component and System Evaluation 10 |2.10 Pressure Testing 102.11 Preservice Examinations 102.12 Piping System Support Examination and Other 11
Applicable Requirements I2.13 Code Case Documentation 11
3.0 AS-BUILT OVERLAY GEOMETRY 14 ']
4.0 VOLUMETRIC UT INDICATIONS EVALUATION 17
5.0 OVERLAY WELDMENT AND SYSTEM AFFECTS 25
5.1 Weidment Evaluation 25 !5.2 System Evaluation 28
6.0 SUMMARY AND CONCLUSIONS 35
7.0 REFERENCES 36'
,
-
j- .
-
.: y: -
I
- iv - 0054-00101-001-110VECTRA Revision O;
i
|
LIST OF TABLES
Number M Paae
2.6-1 CK-ES3166 and CK-ES3181 Minimum Ferrite 12Content Measurements
3.0-1 As-Built Weld Overlay Repair Thicknesses 15
3.0-2 As-Built Weld Overlay Repair Widths 15
3.0-3 As-Built Weld Overlay Repair Axial Shrinkages 16
4.0-1 Allowable Volumetric Preservice Examination 24Planar Flaws
l
1
|
-
.
j T..
-v- 0054-00101-001-110yRevision 0
LIST OF FIGURES
Number Titic Paga
1.0-1 General Layout of Containment Sump Check Valves 2
1.0-2 CK-ES3166 Check Valve-to-Tee Pre-Weld Overlay 3Repair Indication Roll-Out Map
1.0-3 CK-ES3181 Check Valve-to-Tee Pre-Weld Overlay 4Repair Indication Roll-Out Map
1.0-4 CK-ES3166 and CK-ES3181 Check Valve-to-Tee 5Pre-Weld Overlay Repair Cross-Section
2.8-1 Weld Overlay Repair Design Dimensions 13
3.0-1 As-Built Weld Overlay Repair Thickness Measurement 10Locations
4.0-1 CK-ES3166 Check Valve-to-Tee Post-Weld Overlay 21Repair Indication Roll-Out Map
4.0-2 CK-ES3181 Check Valve-to-Tee Post-Weld Overlay 22Repair Indication Roll-Out Map
4.0-3 Surface and Subsurface Planar Flaws 23
5.1-1 Typical Post-Overlay Axial Residual Stress Conditions 30 ||
5.1-2 Carbon vs. Ferrite Content Affects on IGSCC Resistance 31 ||
5.1-3 Boat Sample Metallographs 32 |
5.2-1 CK-ES3166 Piping System Layout 33
5.2-2 CK-ES3181 Piping System Layout 34
. _ _
-
9
V'.c .
-1- 0054-00101-001-110VECTRA neyision o
1.0 INTRODUCTION
A leak leading to the shutdown of Consumer Power Company's iCPCo)
Palisades Nuclear Plant (PNP) was identified in a check valve (CK-ES3166)
in the auxiliary building west engineering safeguards room on February 17,
1994. Subsequent nondestructive examinations also identified indications
in another check valve (CK-ES3181) and additional indications in valve
CK-ES3166. In the Reference 1 system diagram, these valves are part of
the Engineering Safeguard System (ESS ; Safety injection, Containment
Spray, and Shutdown Cooling Systems). The generallocation of these
valves is shown in Figure 1.0-1. As shown in Figures 1.0-2 through 1.0-4,
the identified indications are located in the downstream end of the check
valves which are each welded to a 24" x 24" x 14" tee fitting.
As discussed in the Reference 2 evaluation report, "use as-is", spool piece
replacement, and weld overlay repair alternatives were considered for the
repair of the check valve-to-tee weldments. In early March, a weld overlay
repair meeting the requirements of American Society of Mechanical
Engineers (ASME) Boiler and Pressure Vessel Code (BPVC) Case N-504-1
(Reference 3) was selected as the repair alternative.
This report presents an evaluation of the implemented weld overlay repairs.
._ _
-
.
*
; y.
-2- 0054-00101-001-110VECTRA Revision o
SAFETYINJECTION
&REFUELINGWATERTANK
(1) TO HP & LP SAFETY INJECTION &CONTAINMENT SPRAY PUMPS
V Vl
CONTAINMENT_
SUMP_
1(1)
4 __ (1)A :
_L3181 CONTAINMENT
4 f >< || T-' PENETRATIONS'4, N a' >4 !! -
3166
24' x 24' x 14*TEE V i
(1)
,
Figure 1.0-1
GENERAL LAYOUT OF CONTAINMENT SUMPCHECK VALVES
(Reference 1)
-
,
1,
; : v.
-3- 0054-00101-001-110VECTRA Revision o
|
1
A l8.7 k WELD
- >/ REPAIRS(#)C /*,,excL, 2.2' @'/_b#7* @__. __ @ M VALVE
J.W L i@ @) n@ I/ On4 i,,
bh |_t i i i in i in jCo- lis l (32.75 1 [43.37s1 181.2s-| 175.s-| g
@ |36 l 14s.51 [W.Fj TEE|37.37s1 146.251 | 77.7-|
(3166 RAW.WPG) |48.s1
NOTES:
1. Detected leakage occurred at Indication No. 8.2. All indications were detected during volumetric UT.3. Indications 1,8, and 9 were also detected during
radiographic examination.|
4. Original construction repairs of valve body.
Figure 1.0-2,
|CK-ES3166 CHECK VALVE-TO-TEE |
PRE-WELD OVERLAY REPAIR INDICATION ROLL-OUT MAP(Reference 4)
,
;
_ _ - _\
-
: : ,
-4- 0054-00101-001-110VECTRA Revision o
A
J.*K%@
v i nA |
(if I45 2'DE)y VALVE
@ i =s .@ @' y || i @ t
$ / yI il I ! I i | |0" |6.8751 148.375j 159.51 |68.875 75.751 y
|0.751 |7.751 |70.751 TEE
(3181 FLAW.WPG)
NOTE: All indications were detected during volumetric UT.
Figure 1.0-3
CK-ES3181 CHECK VALVE-TO-TEEPRE-WFLD OVERLAY REPAIR INDICATION ROLL-OUT MAP
(Reference 4)
l1
- _ _ _ _-_
-
,. .- y
~5' 54' ' '' ' ~ ' 'VECTRA Revision 0
VALVE * - . TEE
f. WELDREGION *C'
REGION *B'__
REGION *A'
!
l ! |!j- . . . . t ,
! l
'
_.
m'
FLOWs
>
PEG 40NS WPO)
Figure 1.0-4
CK ES3166 AND CK-ES3181 CHECK VALVE-TO-TEEPRE-WELD OVERLAY REPAIR CROSS SECTION
(Reference 4)
- - - - - . - -
-
. . _ . _ _ _
|
; ; Y|
'.
1
!
-6- 0054-00101-001-110 iVECTRA Revision o
!
2.0 OVERLAY IMPLEMENTATION REQUIREMENTS:
The weld overlay repairs applied to the CK-ES3166 and CK-ES3181 check
valve-to-tee weldments were implemented in accordance with thes
following requirements of Code Case N-504-1 (Reference 3).
2.1 ASME Section XI Reoair Proaram.
Code Case N-504-1 Paragraph (a) requires the implementation of weld
overlay repairs in accordance with a Repair Program satisfying the
requirements of ASME BPVC Section XI, Subsection IWA-4000.
Accordingly, the Reference 5 Repair Program was prepared to detail
currently applicable and original construction codes; flaw removal methods;
gensral weld overlay repair application, design, implementation
documentation, and permanent record requirements; nondestructive
examination (NDE) and system pressure testing requirements; and form ;
NIS-2 documentation requirements.
2.2 Overlav Material and Acolication Reauirements
Code Case N 504-1 Paragraph (b) requires that weld overlay repair filler
metal have a maximum carbon content of 0.035%, be applied 360*
circumferentially around a weldment, and be deposited in accordance with
a qualified welding procedure specification. Accordingly, the Reference 6
application and examination procedure was used to control theo
I implementation of weld overlay repairs on the CK-ES3166 and CK-ES3181
i check valve-to-tee weldments.
4
l
it I
- . _ _ _ - , , - - - . - - - --_, _ _ _ -
-
.'' y,
-7- 0054-00101-001-110VECTRA Revision 0
|
As required by the Reference 7 purchase order, all filler metals used during
machine Gas Tungsten Arc Welding (GTAW) for the application of the joverlays or manual GTAW or Shielded Metal Arc Welding (SMAW) for
original pipe surface or overlay repairs were permitted a maximum carbon
content of 0.030%. The Reference 6 procedure also required the
following: !
a. Application of overlays using parallel, overlapping,360
circumferential beads around a weldment.
b. The use of ASME BPVC Section IX qualified welders, welding
operators, and welding procedure specifications,
c. Overlay application with water inside the weldments,
d. A maximum allowable "interpass" temperature of 212 F.
e. A maximum heat input of 28 Kjoules/ inch for at least the first two
design (structural) layers of an overlay.
2.3 Oriainal Pioe Surface Liauld Penetrant Examination
Code Case N-504-1 Paragraph (c) requires that the original pipe surface be
examined by the liquid penetrant (PT) examination technique with a
maximum indication acceptance criteria of 1/16" before application of a
weld overlay repair. The Code Case goes on to require the repair of
unacceptable indications by either excavation / repair welding or the
application of one or more " seal" layers that are not to be included in the1'
weld overlay repair design thickness.
|
-
e
4 ,
'$ k. Y
-8- 0054-00101-001-110VECTRA Revision o i
The leaking flaw discovered in the CK-ES3166 check valve-to-tee
weldment was excavated and repair welded prior to overlay application.'
Due to other PT indications in the weld overlay repair areas on the original
pipo surface of both weldments that exceeded a zero tolerance size
acceptance criteria required by the Reference 6 application and
examination procedure, a seal layer was applied to each weldment. The
seallayer covered the excavation repair in the CK-ES3166 weldment.
As shown in Section 3.0, the seal layer thicknesses have not been
included in the weld overlay repair design (structural) thicknesses.
2.4 Orlainal Pioe Surface Repair / Seal Laver PT Examination,
Code Case N-504-1 Paragraph (d) requires that any excavation repairs or
seal layers applied over the original pipe surface also be examined by the
PT examination technique with a maximum indication acceptance criteria*
of 1/16". The seal layers applied to the CK-ES3166 and CK-ES3181
weldments were PT examined and found acceptable per a zero tolerance
size acceptance criteria required by the Reference 6 application and
examination procedure (References 8 and 9).
2.5 Minimum 2 Laver Thickness j|
|
Code Case N-504-1 Paragraph (e) requires that a weld overlay repair be
constructed of a minimum of two layers. Section 3.0 presents the seal
layer, design (structural) weld overlay repair, and total overlay thicknesses i
for the CK-ES3166 and CK ES3181 weldments.
,
__!
-
4
: Y..
!
-9- 0054-00101-001-110yRevision 0 ;
2.6 Ferrite Content I
Code Case N-504-1 Paragraph (e) also requires that the first layeri
considered to be part of the design (structural) weld overlay repair '
thickness shall have a minimum ferrite content of 7.5 FN without requiring - ;further evaluation. As shown in Table 2.6-1, all ferrite content I
measurements for the first two design (structural) layers of the CK-ES3166
and CK-ES3181 overlays exceeded 7.5 FN.,
2.7 NDE Access
Code Case N-504-1 Paragraph (f) requires that an overlay's geometryI
provide access for PT and volumetric ultrasonic (UT) examination. The
weld overlay repairs applied to the CK-ES3166 and CK-ES3181 check
valve-to-tee weldments permit access for PT and volumetric UT as
illustrated by the NDE results reported through-out this evaluation report.
2.8 Overlav Desian,
The Reference 4 calculation package presents the design of the weld
overlay repairs for the CK-ES3166 and CK-ES3181 check valve-to-tee
weldments. The overlays were designed in accordance with Paragraph (f)
of ASME BPVC Case N-504-1 (Reference 3) and Paragraph IWB 3640 of
ASME BPVC Section XI (Reference 10). Figure 2.8-1 presents the design
weld overlay repair geometries..
4 . , -__ -, , - - - ,,
-
-. -
*
.- y.
~' ~ 54~ ' '~ . ' . ' 'VECTRA~
Revision O,
2.9 Reoaired Weldment/Comoonent and System Evaluation
Code Case N-504-1 Paragraph (g) requires an evaluation of a repaired
weldment/ component and the repair's affect on other weldments and
components within the repaired weldment/ component's piping system.
For the CK-ES3166 and CK-ES3181 check valve-to-tee weld overisy
repairs, an evaluation of these concerns is presented in Section 5.0.
2.10 Pressure Testino
Code Case N-504-1 Paragraph (h) requires that a completed overlay be
pressure tested in accordance with ASME BPVC Section XI, Subsection
IWA-5000. As required by the Reference 5 Repair Program, the
CK-ES3166 overlay applied over the leaking flaw discussed in Section 1.0 '
was hydrostatically tested. In addition, even though it was applied over
indications that did not penetrate the pressure boundary, the CK-ES3181 -
overlay was also hydrostatically tested.
P
2.11 Preservice Examinations
Code Case N-504-1 Paragraphs (i) and (j) require that a completed overlay
be examined using PT techniques and the overlay and the outer 25% of
the original pipe wall be examined using volumetric UT techniques prior to
being placed in service. The weld overlay repairs applied to the
CK-ES3166 and CK-ES3181 check valve-to-tee weldments were examined
using PT and volumetric UT techniques. All PT indications were evaluated
by PNP personnel and found to meet the acceptance standards of ASME
BPVC Section XI Table IWB-3514-2 (References 11 through 14). All UT
indications are addressed in Section 4.0.
.
-
. y-.
- 11 - 0054-00101-001-110. VECTRA Revision 0
2.12 Pinina System Sucoort Examination and Other Acolicable Recuirements
Code Case N-504-1 Paragraph (k) requires a VT-3 examination of piping
system restraints, supports, and snubbers affected by the weld overlay
repair activities. To provide access for the application of the CK-ES3166
check valve-to-tee overlay, a spring hanger had to be removed. This
hanger received a VT-3 examination after reinstallation.
Code Case N-504-1 Paragraph (1) states that the requirements of ASME
BPVC Sections IWA-4000, IWB-4000, IWC-4000, and IWD-4000 shall
also be met during overlay application. Because the ESS is currently
treated as an ASME Class 2 system not subject to IWD-4000, the
applicable requirements of Sections IWA-4000, IWB-4000, and IWC-4000
were met.
2.13 Code Case Documentation
Code Case N-504-1 Paragraph (m) requires weld overlay repairs applied in
accordance with N-504-1 be documented on an NIS-2 form. As required
by the Reference 5 Repair Program, the CK-ES3166 and CK-ES3181 check
valve-to-tee weld overlay repairs have been duly documented.
|
-
. -. . _ _ _ _ _ __ . _. . .
'
; :. y
,
-12- 0055 00101 001 110VECTRA Revision o
,
Table 2.6-1
CK-ES3166 AND CK-ES3181MINIMUM FERRITE CONTENT MEASUREMENTS
(References 15 and 16)
CK ES3166 CK-ES3181
First Valve Side 12.5 FN 12.5 FNDesignLayer Tee Side 12.5 FN 10 FN
Second Valve Side 12.5 FN 12.5 FN|Design
Layer Tee Side 12.5 FN 12.5 FN|
|
|
l
|
,
d
.I
v-- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ . _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _
-
_ _ _
''
y..
. -13- 0054-00101-001-110VEC, IRARevision 0
i WELD
!A l B
M == M 45 min.| NOTE 2 , | (tyP-),
=f S. t-'
. -K - ------- - _____ 7,
'. / )_
<
. (V T.WPG)
!
WELD OVERLAY REPAIR DIMENSIONSVALVE
NO.t,(1) A B
CK-ES3166 0.20" 4.6" 2.0"
CK-ES$181 0.19" 4.4" 2.0"
NOTFJ:
(1) t, = minimum design thickness.(2) Final contour based upon volumetric UT examination requirements.
i
Figure 2.8-1 |
WELD OVERLAY REPAIR DESIGN DIMENSIONS(Reference 4)
,
i
e
w
-
: Y ||
|
- 14 - 0054-00101-001-110Revision 0
l
1
3.0 AS-BUILT OVERLAY GEOMETRY |l|
Per the requirements of the Reference 6 application and examination
procedure, Weld Overlay Data Sheets (References 17 and 18) were used
to document the following weld overlay repair information for the CK-
ES3166 and CK-ES3181 check valve-to-tee weldments: ;l!
a. The original pipe wall, seal layer, design (structural) weld overlayi
repair, and total weld overlay repair thicknesses (Table 3.0-1).
b. The final shoulder-to-shoulder width of the overlay (Table 3.0-2). ,I
c. The first and second design (structural) layer ferrite content i
measurements (Table 2.6-1),
Id. The weld overlay axial shrinkage (Table 3.0-3).
l
The thicknesses shown in Table 3.0-1 were measured as shown in Figure
3.0-1. ll
i
A comparison of the design (structural) overlay thicknesses presented in l:
Table 3.0-1 and the shoulder-to-shoulder overlay widths presented in Table
3.0-2 with the design weld overlay repair geometries presented in Figure
2.8-1 shows that the as-built geometries conservatively meet the design
geometries. Therefore, the as-built weld overlay repairs meet the
requirements of Paragraph (g) of ASME BPVC Case N-504-1 (Reference 3)
and Paragraph IWB-3640 of ASME BPVC Section XI (Reference 10). |
|
- - - _ _ - - - _ _ - - _ _ _ . - - - - _ - _ - - - . _ _
-
.
.' y*,-
- 15 - 0054-00101-001-110VECTRA Revision 3
Table 3.0-1
AS-BUILT WELD OVERLAY REPAIR THICKNESSES(References 17 and 18)
CK-ES3166 CK-ES3181
Avg. Original Pipe Wall 0.70" O.73"Thickness (A)
,
Avg. Pipe Wall + Seal 0.79" 0.80"Layer Thickness (B)
Avg. Seal Layer 0.09" 0.07"Thickness (C = B - A)
Avg. Pipe Wall + Total 1.54" 1.64"Overlay Thickness (D)
Avg. Total Overlay 0.84" 0.91"Thickness (E = D - A)
Avg. Design (Structural) 0.75" O.84"Overlay Thickness(F = D - 8)
Table 3.0-2
AS-BUILT WELD OVERLAY REPAIR WIDTHS(References 17 and 18)
CK-ES3166 CK-ES3181
Avg. Shoulder-to- 6.7" 6.6"Shoulder OverlayWidth '
_.
* Dimensions A + B in Figure 2.8-1.
_ _ - _ _ _ _ _ _ . _ _ _ _ .
-
'*
y /.
-16- 0054-00101-001-110VECTRA Revision o
Table 3.0-3
AS-BUILT WELD OVERLAY REPAIR AXIAL SHRINKAGES(References 17 and 18)
AVG. WITNESS MARK-TO-CK-ES3166 CK-ES3181WITNESS MARK DISTANCE
Before Overlay (A) 9.55" 9.38"
After Overlay (B) 9.33" 9.05"
Avg. Overlay Shrinkage 0.22" 0.33"(C = B - A)
_
( WELDSEAL LAYER THICKNESS
_ MEASUREMENTS
h = 2.25' _,i ;
L | | -= r ,=& -- ' . jo
x , .,.
. _.
|,
NN ' BOUNDARY MARKS (
WTTNESS MARKS (twow.m1 m
Figure 3.0-1
AS-BUILT WELD OVERLAY REPAIRTHICKNESS MEASUREMENT LOCATIONS
-
.
.
| * y.
- 17 - 0054-00101-001-110VECTRA seyision i
4.0 VOLUMETRIC UT INDICATIONS EVALUATION
Figures 4.0-1 and 4.0-2 present the post-weld overlay repair volumetric UT
results for the CK-ES3166 and CK-ES3181 check valve-to-tee weldments.
The Reference 4 calculation package for the check valve overlay designs
used the original pipe wall thicknesses (t) determined by ultrasonic '
thickness measurements associated with the characterization of the
original pipe wall indications shown in Figures 1.0-2 and 1.0-3 at/near the
centerline of the valve-to-tee butt weld where the average cross-sectional
applied stresses are the greatest. These thicknesses are as follows: '
CK-ES3166: t = 0.61 "
CK-ES3181: t = 0.58" '
These pipe wall thicknesses differ from the ultrasonically measured
pre-weld overlay repair original pipe wall thicknesses shown in Table 3.0-1
because, as shown in Figure 3.0-1, these latter thicknesses were
measured near the end of the overlay on the tee.
As discussed in the Reference 4 calculation package, the low applied 4
primary stresses acting on the check valve-to-tee weldments permit a
maximum allowable flaw depth (a)-to-thickness (t) ratio (a/t) for an
assumed 360 long flaw of 0.75 per the source equations used to derive
Table IWB-3641-1 in ASME BPVC Section XI (Reference 10). Accordingly, 1
based upon an assumed flaw depth of 100% of the original pipe wall
thickness, the overlay design thicknesses, t , were determined as follows:o>
-
1
1 .
*; .
- 18 - 0054-00101-001-110VECTRA sevision ,
CK-ES3166: t, 0.61" / 3 = 0.20"=
CK-ES3181: t = 0.58" / 3 = 0.19"o
Based upon the average pipe wall plus total overlay thicknesses presented
in Table 3.0-1, the following maximum allowable 360 long flaw depths
would be permitted in each weldment:
CK-ES3166: a ,,. 0.75 * 1.54" = 1.16"=mCK-ES3181: a ,,. 0.75 * 1.64" = 1.23"=m
Therefore, the original pipe wall plus seal layer thicknesses presented in
Table 3.0-1 are easily bounded by these maximum allowable 360 long
flaw depths.
The minimum remaining ligament thicknesses (t, per Figure 4.0-3) required
over all circumferentialindications assumed to have a 360 length and any
axial indications greater than 1.5" in length are as follows:
CK-ES3166: t, 0.25 * 1.54" = 0.38"=
CK-ES3181: t, 0.25 * 1.64" = 0.41 "=
As shown in Figure 4.0-1, all of the CK-ES3166 volumetric UT indications
have remaining ligament thicknesses greater than 0.38", therefore, the as-
built geometry of the CK-ES3166 overlay is acceptable per Code Case
N-504-1 (Reference 3) requirements. However, as shown in i;igure 4.0-2,
CK-ES3181 volumetric UT Indication No's. 4 and 6 have remaining
ligament thicknesses less than 0.41", therefore, the as-built condition of
the CK-ES3181 overlay requires further evaluation.
-
- . . - - _ -.
; .'* y
(
~'*~ 54~ ' '~ .' ' 'VECTRA Revision 0 '
Per Paragraph (i) of Code Case N-504-1, indications observed during
preservice examinations shall meet the acceptance standards of Table
IWB-3514-2. All of the indications presented in Figures 4.0-1 and 4.0 2
have " negligible" depths reported from the preservice volumetric UT
examinations. For this evaluation, the indication depths, a,, will be
assumed to be 1/32"(0.0325").
Therefore, referring to Figures 4.0-2 and 4.0-3, CK-ES3181 Indication
No's. 4 and 6 are assumed to have the following flaw depth (a)-to-length
(t) aspect ratios:
Indication No. 4: a,/ t = 0.0325" / 1.00" = 0.033
Indication No. 6: a,/ t = 0.0325" / 12.0" = 0.003
Assuming the maximum allowable 360 long flaw depth (t, = 0.41"),
Indication No's. 4 and 6 would be determined to be surface or subsurface
flaws per ASME BPVC Section XI (Reference 10) Table IWB-3514-2 and
Figure 4.0-3 as follows:
Indication No. 4: d = a /2
= 0.0325" / 2 = 0.016"
Soo = t,4 ,0.40" > 0.4d = 0.006"=
So t, - (Soo + a)=
0.41" - (0.40" + 0.0325")=
= - 0.0225" < 0.4d = 0.006"
/. Indication No. 4 is a surface flaw.
. ,
=-
-
, . - _ _ .
.
.- / ,,
- 20 - 0054 00101-001-110 iVECTRA sevision o )
l
Indication No. 6: d = a /2
= 0.0325" / 2 = 0.016"
Soo = t,.
= 0.25" > 0.4d = 0.006"
S,o = t, - (S o + a)o= 0.41 " - (0.25" + 0.0325")
= 0.1275" > 0.4d = 0.006"/. Indication No. 6 is a subsurface flaw.
Table 4.0-1 presents allowable volumetric preservice examination planar
flaw depth (a)-to-thickness (t) ratios for a 0.41" nominal wall thickness by
interpolating Table IWB-3514-2 values. Per Table 4.0-1, the aspect ratio
(a,/t = 0.033) for surface Indication No. 4 conservatively permits an alt
ratio of 9.4%. Therefore, Indication No. 4 has an allowable flaw depth of
0.094 * 0.41 " = 0.039 " which is greater than the assumed 1/32" (a i,
= 0.0325") flaw depth. Also, per Table 4.0-1, the aspect ratio (a/t
= 0.003) for subsurface Indication No. 6 conservatively permits an a/t
ratio of 9.3%. Therefore, Indication No. 6 has an allowable flaw depth of,
2 * 0.093 * 0.41" = 0.076" which is greater than the assumed 1/32" (a
= 0.0325") flaw depth. Therefore, all the CK-ES3181 volumetric UT
preservice examination indications meet the acceptance standards of Code
Case N-504-1 Paragraph (g).
._. _
-
.
; : \,
- 21 - 0054-00101-001-110VECTRA Revision i
-@4
. . . . . . . . . . . . . . . . . . . ........... .................... -- -
3.o= -@4@ @-
A
| 1.5' 4...--g8*~~~~-~~--' ' - - -'. . . . . . ....1.01.. . ._- .-................-....---......
I ,Y Y 2 08 _v v _
A._ i &
__J .__ _ .. ........_ VALVE .. . ...-.. _ {
_ _ . .
1.25' k 1.3'
f ff fi
TEE
I 66.0"| | r .0'l |7.5'l 1**
pieswonwpo) 157.0'i [11,0'j.
^'LENGTH DEPTH COMMENT
O. L GAME T
1.5* Lack of Bond |1 1.4*'"
2 0.2* 0.75" Pinhole |"*
3 0.2* O.75* Pinhole'"
4 8' *" 0.40' Lack of Bond5 0.6* O.55*"*
* Remaining ligament (t,) per Figure 4.0-3.* * Does not correspond to 0" position in Figure 1.0-2.
l*** Negligible depth. ]
Figure 4.0-1
CK-ES3166 CHECK VALVE-TO-TEEPOST-WELD OVERLAY REPAIR INDICATION ROLL-OUT MAP l
(References 19 and 20) l
- __
-
: .- ,
- 22 - 0054-00101-001-110VECTRA R evisio n 3
|
'@ \ | 1
l
2.75'
_-.._...-.. ___.-. ___......_. .......s..___. ____ _. ____.-..____.l @ 02F ii_ WOR - y
I A A A- -
}-------- VALVE -- ---- [---- -- l------ I ----------------------------. .--0.75'
j |A =1.3*
// //// ///f~
hTEE
I I I| iI4 i.75' | | 21.0*l [8.5'] @ **
maiwonwo: 146.5'l 46.0*j [gp
' ^'LENGTH DEPTH COMMENTNO. IG ME T
1 6' '" 0.55"
2 4.5* "* 0.50'3 0.10* "* 0.60*
4 1.00* *" 0.40'
5 3.25" "* 1.25'
6 12.0" *** 0.25** Remaining ligament (t,) per Figure 4.0-3.** Does not correspond to 0" position in Figure 1.0-3.*** Negligible depth.
Figure 4.0-2
CK-ES3181 CHECK VALVE-TO-TEJPOST-WELD OVERLAY REPAIR INDICATION ROLL-OUT MAP
(Reference 21)
-
.
* r,- .
- 23 - 0054-00101-001-110VECTRARevision i
oUTSIDE DIAMETER (00)
_g INSIDE DtAMETER (10)-
: A s . . . . . ... .. :4A%~
. n[- ' . ; b.[f* kf' "'. ^
-
: : ,y
- 24 - 0054-00101-001-110yRevision 0
Table 4.0-1
ALLOWABLE VOLUMETRIC PRESERVICE EXAMINATION PLANAR FLAWS
Nominal Wall Thickness (inches)
Aspect 0.312''' O .41 "" 1.0"'Ratio
surface Subsurface Surface Subsurface Surface Subsurface(all)Flaw alt Flaw att Flaw alt Flaw alt Flaw alt Flaw alt
(%) (%) (%) (%) (%) (%)
0.00 9.4 9.4Y 9.3 9.3Y 8.5 8.5Y
0.05 9.6 9.6Y 9.5 9.5Y 8.6 8.6Y
0.10 9.8 9.8Y 9.7 9.7Y 8.8 8.8Y
NOTES:
1. a (surface flaw) = 2d (subsurface flaw) = flaw depth.2. t = flaw length.3. t = nominal wall thickness.4. S = flaw edge-to-surface distance.5. If S < 0.4d, corresponding flaw is considered a surface flaw.
If S .;>_. 0.4d, corresponding flaw is considered a subsurface flaw.6. Y = S/a. If Y > 1.0, use Y = 1.0.7. From Reference 10, Table IWB-3514-2.8. Interpolated from 0.312" and 1.0" values.
-
: | w.
- 25 - 005 & o0101-001-110VECTRA |Revision 1 '|||
5.0 OVERLAY WELDMENT AND SYSTEM AFFECTS |
|Code Case N-504-1 (Reference 3) Paragraph (g) requires an evaluation of a!
repaired weldment/ component and the repair's affect on other Weldments ||
and components within the repaired weldment/ component's piping system. I
For a repaired weldment/ component, this evaluation shall consider the
affects of waterbacking as it affects residual stress produced by the
overlay in combination with other applied system loads. The evaluation
shall also address increases in piping system loads caused by overlay
stiffness, deadweight, and axial shrinkage affects.
5.1 Weldment Evaluation
The Reference 22 report presents an evaluation of the effectiveness of a
Code Case N-504-1 weld overlay repair relative to proposed root causes
affecting the structural and service integrity of the CK-ES3166 and
CK-ES3181 containment sump suction check valves. After determining
that high or even moderate cyclic load magnitudes do not occur at the
check valve-to-tee weldments, the overlay effectiveness evaluation
document presents the following potential root causes for the indications
discovered in the check valves:
a. Intergranular Corrosion (IGC).
b. Intergranular Stress Corrosion Cracking (IGSCC).
c. Original construction casting or welding flaws.
As discussed in Sections 2.2 and 2.6, the overlays applied to the check
valve-to-tee weldments utilized the following implementation parameters:
|
_ _ _ _ - _ - _ _ _ - - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _
-
-.
.'Q
- 2e - 0054 00101 001.,,oVECTRA Revision 0
a. Filler metals having maximum carbon contents of 0.035% and
as-deposited ferrite contents greater than 7.5 FN.
b. Machine GTAW techniques to apply parallel, overlapping,360*
circumferential beads around a weldment with waterbacking,
c. A maximum allowable "interpass" temperature of 212 F.
d. A maximum heat input of 28 Kjoules/ inch for at least the first two
design (structural) layers of an overlay.
The overlay application, waterbacking, and heat input parameters
described above have been shown to produce a typical axial through-wall
residual stress pattern acting to mitigate circumferentially oriented,
stress-driven flaws as shown in Figure 5.1-1 (Reference 23). However, in
order to provide defense-in-depth against corrosion-driven cracking, the
cast-in-place, as-deposited weld overlay filler metal must provide the
ultimate barrier to arrest corrosion- and stress corrosion-driven cracking.
As shown in Figure 5.1-2 (Reference 24), weldments with a maximum
carbon content of 0.035% and a ferrite content of 7.5 FN (7.5%) are
inherently resistant to aggressive failure mechanisms such as IGSCC. The
actual measured first and second layer ferrite contents for the check valve
overlays exceeded 7.5 FN thereby further increasing their anticipated
resistance to corrosion cracking.
The inherent resistance of low carbon /high ferrite content overlays is
particularly important in the presence of through-wall flaws as found in the
CK-ES3166 check valve-to-tee weldment. In these cases, beneficial under-
-
'.
.. ,< y
- 27 - 0054-00101-001-110VECTRA nevision 0
the overlay residual stress patterns are of little/no help in mitigating stress
corrosion cracking because the overlay has yield level tensile residual
stress through its complete thickness (see Figure 5.1-1). As shown in
Figure 5.1-3 (Reference 25), overlays applied over through-wall flaws
utilizing filler metals meeting the requirements of Code Case N-504-1 have
been shown to resist IGSCC in actual plant service. The buat sample
shown in Figure 5.1-3 was extracted from an overlay that had been in
service for one fuel cycle at Quad Cities Unit 2. During overlay
application, a steam blow-out was encountered requiring excavation and
weld repair. The preservice volumetric UT examination of this overlay
confirmed that the steam blow-out was sealed just below the overlay-to-
original pipe surface interface. Nevertheless, at the next refueling outage,
a follow-up volumetric UT examination suggested that the steam b|ow-out
had grown approximately half way through the overlay thickness.
However, as shown in Figure 5.1-3, the follow-up UT inspection had
incorrectly determined the remaining ligament depth because the steam
blow-out is clearly arrested at the weld repair-to-original pipe surface
interface even after one fuel cycle of operation.
The maximum interpass and heat input parameters utilized also help to
inhibit further sensitization of the original weldment surface, The
Reference 26 pipe replacement study provides recommended welding
parameters for the application of corrosion-resistant cladding (CRC) to
avoid / reduce sensitization of exposed base rnetal. This study suggests a
maximum interpass temperature of 250 F and a maximum heat input of 25
Kjoules/ inch. The maximum 212 F interpass temperature used to apply the
check valve overlays is clearly bounded by the EPRI-recommended value
and a maximum 28 Kjoule/ inch heat input on a waterbacked surface
-
.. ;.. 7
- 28 - 0054-00101-001-110VECTRA neyision i
is judged to be equivalent to the EPRI-recommended value on a non-
waterbacked surface.
Therefore, the weld overlay repairs applied to the CK-ES3166 and
CK-ES3181 check valve-to-tee weldments conservatively re-establish the
original ASME BPVC structural factors of safety while providing a
corrosion-resistant barrier against unacceptably deep crack propagation for
the balance-of-plant life witnout creating new highly sensitized potential
leakage paths.
5.2 System Evaluation
Rigorous evaluations of sustained stresses resulting from weld overlay
repair axial shrinkage have been performed for nuclear plants around the
world on piping systems with many overlays having axial shrinkages
comparable to those reported in Table 3.0-3. Such evaluations typically
result in weld overlay shrinkage (WOS) stresses, in unrepaired weldments
away from rigid anchors / supports, of under 1,000 psi. WOS stresses have
combined with other piping system stresses to create yield level stress
magnitudes in weldments adjacent to rigid r -hors only in cases involving
short runs of piping with multiple overlays. |
As discussed in NUREG-0313 (Reference 27), the mcgnitude of sustained|
stresses acting on stress-imoroved, austenitic stainless steel, Boiling Water
Reactor (BWR) primary recirculation system piping weldments is important
in determining their expected resistance to IGSCC. However, the Safety
injection, Containment Spray, and Shutdown Cooling piping weldments of
the PNP ESS have not been stress-improved because IGSCC had not been
-
.- . . -.- - . _ ,_ . - . . . . _
.
;: : ,
- 29 - 0054-00101-001-110VECTRA noyision o
established as a degradation system in the past. Therefore. there is no
current reason for performing a sustained stress evaluation of the ESS.
piping weldments because there are no stress-improved weldments.
If WOS stresses were to be determined in the ESS piping weldments, they <
would be expected to be less (and in most cases, much less) than 1,000
psi. As shown in Figures 5.2-1 and 5.2 2, only one overlay was applied to
each containment sump piping system and each system has both large
vertical and horizontal distances from its associated containment
penetration to the first anchor or support that would be affected by overlay'
axial shrinkage. The configurations of piping shown in Figures 5.2-1 and
5.2-2 result in very flexible systems which easily accommodate small
amounts of overlay axial shrinkage.
, , . - . . _ - . _ _ _ - _ _ - _ _ - _ - _ _ _ -
-
.
,. ; .' y
- 30 - 0054 00101-001-110VECTRA Revision o
___.. ....m..........
:. e* % \'a v
,--- g/ /me,
3.-* *----
*.y,ss ._ , !_* ;.. ..
, . . ..a e' i. | ~- ,-,.. i
\ v....
I
1|
V/////MA\ \\%1.
, ma - u.
Inside Surface Axial Residual Stress
we.n muam
.
"'. . .*.u.
, . *. . ., , . . . . ... . . . ..
2 .. . .*j T** \, M,.*E* \u- -s
y* e.
""''*"**,u- .
. .. ... *. Ju. .
|. - ... .. 2 .. . . . *.e*...
F.W.B IEat .emunn
Axial Throuch-Wall Residual Stresa
Figure 5.1-1
TYPICAL POST-OVERLAY AXIAL RESIDUAL STRESS CONDITIONS(Reference 23)
_ _ _ . _
-
li
*I,
*
.e ,e , y1
VECTRA- 31 - 0054-00101-001-110
>
Rev..ision 0 !)
:!
O to
CLOEED SYMSOL - ICSCC|
OPE N $vMSOL NO OGSCC |
M LFFsLLED$v SOL iGSCC - AT LE AST ONE 5 AMPLESTREN C 4 FA URESCROSS HA TCME D SYMSOL MINOR ENvsRONME NT AL eNF LUENCE
0 00 - CF3CF8veELD(D
CF3 F URNACE0 07 - h 5 $ @ CF85EN$1T12ED
I1
0 06 - $ $ ]a1
0 a* - 6 YV 9 0 e2i'C sitiO*FmaaJ
'
$ > 1000*F /4Sn!u
ON - O As s.E LDED Aa . Lis Aa . snt,
7 Sit LLif t MARD5URF ACED
* * 'o >
> > 0 10 02 - U8 o ]ao
O I0O > ;00i - o ;
ii i l I I I I I i i l i l i Ig
O 2 4 e a 10 s2 is is is 20 22 as as 2e 20 1
F E RRITE t%)
I
Figure 5.1-2 |1
CARBON VS. FERRITE CONTENT AFFECTS ON IGSCC RESISTANCE I(Reference 24)
!
1
.
I
|
!
|1
1
-
. . - _ . .. . . - . . - .- - . . _ _ . . . - .
-
|i
: .'- y.
l::
) 32 - oosooo,o1001 3,oVECTRA Revision o i.
#.1
'd1
,, ..
t-
|. ;- . I<
;1
?gbOfs. [ ,'
.$; gr ,v., .. '-. . . , .
3. .-.r,-..%,
; '... .x.
g-<- v.
.
11.25X Maanification'
D :-6; ' t. O' ' ,,, tp ty;y) j|g.,; { ,'
- .. $,
gr % z. ,s.
' , , ,.f,k, .h. ,'
., g-; .. x .-.
;w . . .
..
, . .: -.
f . ,,-
.
..
:' ,
.
. .
<
!
150X Maanification
Figure 5.1-3 i
BOAT SAMPLE METALLOGRAPHS(Reference 25)
|
. . . _ . .. . _ . _ _ . . _ _ _ _ _.. _ . _ __ ,._.._ _ _-
-
.
,
|
|
.Y |*.' .: *
VECTRA~ ~ 54~ ' '~ ' ' ' '
Revision 0
Iv
A ROCANCHOR
d| n=3'J
15' - 6" CK-ES3166 CHECK VALVE.TO-TEE WELDMENT (TYP.)
_
th I % !
L = 2' i'p...
ELEVATION ," 2,= =
, = 9' -, w ;
= 4' = 46', _
CONTAINMENTPENETRATION (TYP.)
~*_
= {' 7,4. .
N Wu
mas "" ) PLAN VIEWr
Figure 5.2-1 >
CK-ES3166 PIPING SYSTEM LAYOUT !,
(Reference 28)
9
r - -. - , . - - _ _ - - -_
-
. . _ .
i
* V.* *.
~ 34 - 54- 0101-001-110VECTRARevision 0
I$NsItt$'$TTP> 0 - *< c=Ta>>~r"-
[ELEVATION
,
=67 :,CONTAINWENT #
PENETRATION (TYP.)
ren/' :>4N
a
PLAN VIEW = 20'
r = 3' ,
OOA
,
l
Figure 5.2-2 |
CK-ES3181 PIPING SYSTEM LAYOQT(Reference 29)
|
l
|I
|
,
. _ _ _ . . _ . _ _ _ _ _ _ _ . _ _ _ _ . .
-
.._ ._. _
1
|| | 3
|'- 35 - 0054-00101-001-110
VECTRA neyision o
6.0 SUMMARY AND CONCLUSIONS
This report presents an evaluation of wald overlay repairs applied to the
containment sump check valve to-tee weldments at the Palisades Nuclear
Plant relative to the requirements of ASME BPVC Case N-5041'
(Reference 3). These weldments are on the downstream side of check
valves CK-ES3166 and CK-ES3181 and contain indications attributed to
either IGC, IGSCC, or original construction casting or welding flaws
(Reference 22).
The as-built check valve-to-tee weld overlay repairs meet the requirements
of Code Case N-504-1 and ASME BPVC Section XI (Reference 10),
Paragraph IWB-3640 for each of the potential degradation mechanisms
identified above. This report also illustrates that pre-overlay volumetric UT
indications confined within the CK ES3166 and CK-ES3181 original pipe
wall thicknesses of 0.70" and 0.73", respectively, must grow to depths
greater than 1.16" and 1.23", respectively, with a corresponding length of
360* to exceed the allowable flaw acceptance criteria of ASME BPVC
Section XI, Paragraph IWB-3640.
The weld overlay repairs applied to the check valve to-tee weldments
conservatively re establish the original ASME BPVC structural factors of
safety whilo providing a corrosion-resistant barrier against unacceptably
deep crack propagation for the balance of-plant life without creating new
highly sensitized potentialleakage paths.
_. _ _ _ _ - _ _ _ .
-
-
.... .-., .,
;
VECTRA~ *~ 5#~ ' '~ ' ~ ' '
n, i ioni
s
7.0 REFERENCES
1. Consumers Power Company Palisades Nuclear Plant Drawing No.M204, " System Diagram - Safety injection, Containment Spray, &Shutdown Cooling System", Sheet No. A, Revision 5.
2. Sargent & Lundy Document No. CMED-058599, " Check Valve LeakRoot Cause, Engineering Analysis, and Repair / ReplacementOptiors", Revision O.
3. American Society of Mechanical Engineers (ASME) Boiler andPressure Vessel Code (BPVC) Case N-504-1, " Alternative Rules forRepair of Class 1, 2, and 3 Austenitic Stainless Steel Piping -Section XI, Division 1", Approval date: August 9,1993
4. VECTRA Document No. 0054-00101-001-200, " Calculation -Package - Containment Sump Check Valves Weld Overlay RepairDesign - Palisades Nuclear Plant", Revision O.
5. VECTRA Document No. 0054-00101-001-100, "ASME Section XIRepair Program - Weld Overlay Repairs to Austenitic Stainless SteelPiping Weldments and Components - Palisades Nuclear Plant",Revision O.
6. VECTRA Document No. 0054-00101001-101, " Procedure forApplication and Examination of Weld Overlay Repairs to AusteniticStainless Steel Piping Systems - Palisades Nuclear Plant",Revision O.
7. Consumers Power Company Purchase Order No. MM0027247.
I8. Consumers Power Company Nondestructive Testing Services Liquid
Penetrant Examination Report, i xaminer: D. Hecksel, Dated:3/11/94, Sheet No. DLH-1, 2 pages (CK-ES3166).
9. Consumers Power Company Nondestructive Testing Services LiquidPenetrant Examination Report, Examiner: D. Hecksel, Dated:3/12/94, Sheet No. DLH-1, 2 pages (CK-ES3181). ;
10. ASME BPVC Section XI, " Rules for Inservice Inspection of Nuclear-Power Plant Components",1992 Edition with 1992 Addenda.
.
-
**' *, .,_
t
~ 37 - #54-M101-@1-110VECTRA Revision 0
11. Consumers Power Company Nondestructive Testing Services Liquit.Penetrant Examination Report, Examiner: D. Hecksel, Dated:3/21/94, Sheet No. DLH-1, 3 pages (CK-ES3166).
12. Consumers Power Company Nondestructive Testing Services Liquid .Penetrant Examination Report, Examiner: T. Carpenter, Dated:3/22/94, Sheet No. TBC-01,1 page (CK-ES3181).
13. Consumers Power Company Nondestructive Testing Services LiquidPenetrant Examination Report, Examiner: D. Hecksel, Dated:3/22/94, Sheet No. DLH-1,1 page (CK-ES3181).
.
14. Consumers Power Company Nondestructive Testing ServicesSupplementary Sketch, Examiner: D. Hecksel, Dated: 3/22/94,Sheet No. DLH-1,1 page (CK-ES3181).
15. PCI Energy Services Delta Ferrite Measurement Report, W.O.24410749, Dated: 3/25/94, 2 pages (CK-ES3166). !
16. PCI Energy Services Delta Ferrite Measurement Report, W.O.24410748, Dated: 3/25/94, 2 pages (CK-ES3181).
17. Weld Overlay Data Sheet, W. O. 24410770.2, Dated: 3/24/94,,
1 page (CK-ES3166). '
18. Weld Overlay Data Sheet, W. O. 24410771.0, Dated: 3/24/94, |1 page (CK-ES3181). I
19. Virginia Corporation Ultrasonic Examination Indication Record,Examiner: Y. Merey, Dated: 3/21/94, page 5 of 5, with VirginiaCorporation Ultrasonic Examination Record - Profile / Plotting,Examiner: Y. Merey, Dated: 3/21/94, 2 pages (CK-ES3166).
- 1
20. Virginia Corporation Ultrasonic Examination Indication Record, !Examiner: Y. Merey, Dated: 3/22/94, page 1 of 2, with VirginiaCorporation Ultrasonic Examination Record - Profile / Plotting,
'
Examiner: Y. Merey, Dated: 3/22/94, page 2 of 2 (CK-ES3166).
21. Virginia Corporation Ultrasonic Examination Indication Record,Examiner: Y. Merey, Dated: 3/22/94, page 6 of 6, with Virginia 1Corporation Ultrasonic Examination Record - Profile / Plotting,Examiner: Y. Merey, Dated: 3/22/94, 2 pages (CK-ES3181).
l
!
!
-
-
Ss Y f
- 38 - 0054 00101-001-110i VECTRA Revision 0
22. Sargent & Lundy Document No. CMED-058617, " Evaluation of theEffectiveness of Code Case N-504-1 Repair for Proposed RootCauses for Containment Sump Suction Check Valves", Revision O.
23. Kulat, S. D., Pitcairn, D. R., and Sobon, L. J., " ExperimentalVerification of Analytically Determined Weld Overlay Residual StressDistributions", Transactions of the 8th International Conference onStructural Mechanics in Reactor Technology (SMiRT), Brussels, iBelgium, August 19-23, 1985, Volume D, pages 231-235.
24. Hughes, N. R., Clarke, W. L., and Delwiche, D. E., "IntergranularStress-Corrosion Cracking Resistance of Austenitic Stainless SteelCastings", Stainless Steel Castings, ASTM STP 756, AmericanSociety of Testing and Materials,1982, pages 26-47.
25. Froehlich, C H., Axtine, J. W., Do, H. O., and Holland, D. G., " FieldVerification of the Effectiveness of the Induction Heating Stressimprovement Process and Weld Overlay Repair Techniques on BWRAustenitic Stainless Steel Recirculation System Piping Weldments",12th Smirt Post Conference Seminar No. 2, Assuring StructuralIntegrity of Steel Reactor Pressure Boundary Components, Session 3- Resolution ofIntegrity issues on Operating Plants, Paris, France,August 23-24, 1993.
26. Electric Power Research Institute (EPRI) Document No. NP-2033-LD,"BWR Large-Diameter Pipe Repair / Replacement Study", Volume 2,Final Report, September 1981.
27. United States Nuclear Regulatory Commission (USNRC) DocumentNo. NUREG-0313, " Technical Report on Material Selection andProcessing Guidelines for BWR Coolant Pressure Boundary Piping",Revision 2, published January 1987.
28. Bechtel Drawing No. 03319. " Stress isometric - Safety injection,Containment Spray, and Shutdown Cooling System", Sheet 4 of 8,Revision 4.
29. Bechtel Drawing No. 03319, " Stress isometric - Safety injection,Containment Spray, and Shutdown Cooling System", Sheet 1 of 8,Revision 4. I