Final Project in Construction Management
Final Presentation
![Page 2: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/2.jpg)
Winter Semester 2013/14Advisor: Ziv Hendel
Submitted by: Paula Barmaimon 941104093
![Page 3: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/3.jpg)
LocationRechov Nisim Aloni, Tel Aviv
![Page 4: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/4.jpg)
13500 m²
Rechov Nisim Aloni, Tel Aviv
![Page 5: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/5.jpg)
Site Layout
Site offices
Parking Parking
Baranovich
Storage Area
Eating area
Toilets
10 m
45 m45 m
Concrete pumpCheck the crane model
![Page 6: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/6.jpg)
Site preparation
Earthworks
Parking
Structural Works
Finishing works
Schedule
Development
![Page 7: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/7.jpg)
Crews
Baranovich team
Formwork walls, external &
internal
Steel
Slab
![Page 8: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/8.jpg)
Schedule
Walls formwork placingWalls steel placingSlab formwork placingConcrete casting
Concrete setting
Slab steel placing
![Page 9: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/9.jpg)
![Page 10: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/10.jpg)
Day 1-4
![Page 11: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/11.jpg)
Day 1-4
![Page 12: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/12.jpg)
Day 5-7
![Page 13: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/13.jpg)
Day 5-7
![Page 14: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/14.jpg)
Day 8
![Page 15: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/15.jpg)
Day 8
![Page 16: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/16.jpg)
Day 9-12
![Page 17: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/17.jpg)
Crews
Baranovich team
Formwork walls, external &
internal
Steel
Slab
![Page 18: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/18.jpg)
Baranovich system1. Clean2. Place the stones
3. Place the fuga
4. Place isolation
5. Place steel mesh
• Used in high rise building with many typical floors• Shortens the duration of exterior cladding• Casts external walls and stones at the same time
![Page 19: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/19.jpg)
Baranovich system• Scaffolding needed for workers to place it• At least 4 anchores/stone• Must be cleaned extremely well
![Page 20: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/20.jpg)
Slab team – PERI Skydeck system
![Page 21: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/21.jpg)
Advantages• Removal is possible after 1 day• Light components • Easy to clean• Fewer slab props- saves time and space
![Page 22: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/22.jpg)
Total workers needed for
concrete works20 workers
![Page 23: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/23.jpg)
Cost Analysis CIP CONCRETE
![Page 24: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/24.jpg)
CIP concrete• Quantity
• Cost
![Page 25: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/25.jpg)
Steel
Density of steel 7850 kg/m3
![Page 26: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/26.jpg)
Cost of steel
![Page 27: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/27.jpg)
Steel in beams
![Page 28: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/28.jpg)
Steel
![Page 29: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/29.jpg)
Formwork
![Page 30: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/30.jpg)
Total Cost
![Page 31: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/31.jpg)
Summary for Concrete Works
Total Cost of Project 300,000,000 concrete works ~ 16% of total proyect
The total duration of the proyect is 36 months. The total duration of concrete works is 19 months.Concrete works must be completed in 2 weeks/floorPeri Skydeck must be used to achieve this rate.
The crew size for this purpose is 20 workers .
![Page 32: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/32.jpg)
Project Manager
2 Site Engineer
2 Head Foreman
Concrete Foreman
Steel Foreman
Parking Foreman
Finishing Foreman
Development
Foreman
Secretaries Guard
MEP Manager BOQ Buying Coordinators
MANAGEMENT CREW
![Page 33: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/33.jpg)
Overheads
![Page 34: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/34.jpg)
![Page 35: Final project in Construction Management - Technion Institute of Technology](https://reader034.fdocuments.us/reader034/viewer/2022042906/58a8cb901a28ab53138b6141/html5/thumbnails/35.jpg)
THANK YOU!!