Final Presentation on Power Sector Edit-1

download Final Presentation on Power Sector Edit-1

of 22

Transcript of Final Presentation on Power Sector Edit-1

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    1/22

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    2/22

    Profile of the Country

    *The Country : The Peoples Republic of Bangladesh

    *Area (without offshore) : 1,47,570 Sq. Km.

    *Population : 134 Million

    *Per Capita Income : US$ 440

    *GDP Growth Rate : 5.8% in 2009.

    * Present Installed Capacity : 5166 MW Power

    *BPDB : 2522 MW

    *IPP : 1596 MW

    *Access to electricity : 45%

    *Demand : 4200 - 5500 MW

    7.0% Average since 1990.

    *APSCL : 6062 MW

    *EGCB : 190 MW

    *Present Available Generation : 3800 4200 MW

    *Per capita generation : 175 kwh/ year (FY08)

    *Rental : 252 MW

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    3/22

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    4/22

    Present Structure of the Power Sector

    BPDB

    Generation EGCB

    Single Buyer-

    BPDBPGCB

    BPDBNorth West

    Zone

    BPDBCentral Zone

    BPDBSouth Zone

    WZPDCWest Zone

    DPDC DESCO REB/PBSs

    A PSCL IPPS

    Rental

    Generation

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    5/22

    Power Utilities Charactererized by PoorFinances, Slow Pace of Reforms

    Unviability of the power sector utilities due to

    Inadequate cost recovery of operating andcapital costs from user charges

    Considerable operational inefficiencies across the value chain, andespecially in the distribution and commercial segment.

    Heavy subsidies and cross-subsidies builtinto the consumer tariffs

    Inefficient operation of generation,transmission and distribution due to cost-plus approach of determining tariffs asagainst market based setting of tariffs

    High T&Dlosses

    LowCollection

    efficiency

    Poor Financial Healthof utilities

    Unpaidsubsidies

    Lowrevenue

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    6/22

    ... the Unviability infusing long term

    imbalance in this infrastructure sector

    Infrastructure

    GrowthaxPayers Users

    ProvidingSubsidies

    Lowering Input Costs

    IncreasingTariffs

    ... this Sector riddled with structural problems. For an example, BPDB total costof supply is more than its average tariff Tk 2.60 per kWh where as DESCO buyselectricity from BPDB & PGCB (for wheeling charge) at Tk.2.67/kWh and sells

    to customer at an average tariff 3.90 Tk. Per kWh

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    7/22

    Opportunities and Challenges

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    8/22

    Major Event in Reform Process

    * National Energy Policy : January 1996

    * Private Sector Power GenerationPolicy of Bangladesh

    * Creation of PGCB (TransmissionCompany)

    *

    Creation of DESCO(Distribution Company for part of Dhaka)

    * Creation of APSCL(Ashugonj Power Station Company)

    * Creation of WAPDC (Distribution

    Company)

    *Regulatory Commission Act : March 2003* Creation DPDC

    : 1996

    : 1996

    : 1996

    : 2002

    : 2003

    : October 25, 2006

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    9/22

    Components of Reforms

    *The principal components of the reform have been envisaged asfollowings:

    - Segregation of power generation, transmission and distribution

    function into separate services.

    - Corporatization and commercialization of emerging power sectorentities.

    - Effective regulation under Bangladesh Energy RegulatoryCommission (BERC).

    - Private sector participation and private public partnership in powersector.

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    10/22

    Components of Reform (Contd.)

    - Financial Restructuring and Recovery Plan of the sector.

    - Introduction of cost reflective tariff for financial viability of theutilities and promoting efficient use of electricity.

    - Development of demand side management (DSM) including energyefficiency measures to conserve energy.

    - Development of alternative/ renewable energy resources.

    - Capacity building and HRD for sector entities and corporatizedbodies.

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    11/22

    Challenges

    Dependency on Gas as primary energy for the electricitygeneration.

    Open Markets & Competition

    Project Management & Technology.

    Risk & Securitization

    Reform and Restructuring.

    Impediment of supporting infrastructure, such as:

    Gas exploration; gas pipe networks; coal Development;

    M i T d M t it

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    12/22

    Moving Towards Maturity

    Stage 5Stage 4Stage 3Stage 2Stage 1

    IndependentPower Plants

    Transmission

    Transmission

    Transmission

    Vertically

    Integrated

    Utilities

    Generation

    Transmission

    Distribution

    Multiple

    players

    Independent

    Power Plants

    Generation

    Multiple

    players

    Captive Power

    Plants

    Independent

    Power Plants

    State owned

    generation

    Multiple

    players

    DistributionCompanies

    Open Access

    Customers

    Multiple

    players

    Captive Power

    Plants

    Independent

    Power Plants

    generation

    Multiple

    players

    Distribution

    Companies

    Open Access

    Customers

    Power Pools/

    Power

    Exchanges/

    OTC

    Distribution

    Companies

    Vertically

    IntegratedUtilities

    Generation

    Transmission

    Distribution

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    13/22

    Ultimate Structure of

    Electricity Market

    *Single Buyer Model at present

    - Single Buyer purchases all the power from generators

    - Sells power to different Distribution companies

    *Multi-buyer and competitive Pool may be adopted when the marketbecomes matured and stable

    *Wholesale Real Time Power Trading

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    14/22

    Key Issues in Investment

    Demand supply gap

    Health of the power sector

    Historical track record in private investments

    Export possibility

    Scale of opportunities

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    15/22

    Success Factor for Private Investments

    Appropriateness of purchase tariff to recover cost of capital.

    Financial health of purchaser.

    Generation integrated with distribution

    Adequacy of payment security mechanisms

    Maturity and depth of domestic financial markets/ institutions toraise finances.

    Alternative markets availability to the IPPs for sale of power in case

    of default by the monopoly buyer.

    Could be in the form of direct third party sales to large industrialconsumers.

    Trading markets/ entities as demand aggregates for sale to alternatebuyers.

    Credit enhancement mechanisms like Letter of Credit, escrow coverand Government Guarantees required as an alternate payment securitymeasure to mitigate payment risks.

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    16/22

    IPP Financing: Basics

    As standalone, green-fieldassets, sponsors do not have accessto internally-generated cash flows.

    Must raise all of their capital from external sources.

    Use project companies to finance illiquid assets with long, butusually limited lives.

    For maturity matching reasons, requires long-term debt.

    Use of long term debt forces capital providers to make long-termassessment of project, industry, and sovereign risks.

    Cash flow based financing.

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    17/22

    Transparent procurement Tariff structure Must be sufficient to meet projects operating costs, debt service, return on equity, and return of equity.

    Creditors rights and the efficiency of legal enforcement Common law vs. civil law Strong vs. weak enforcement

    Government: Sovereign vs. Commercial Entity

    Waiver of sovereign immunity

    Concession agreement Off- take agreement/Input supply agreement

    Penalty for non-performance, LDs

    Termination payments

    Credit enhancements

    Direct agreement Lenders step-in rights

    Assignment of project agreements

    Repatriation of loan proceeds Currency convertibility Currency depreciation risk

    Lenders Concerns: General

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    18/22

    Local Financing Limitations forIPP Projects

    Long term financing needs of infrastructure projects are notbeing meet by commercial banks because of:

    Size of projects

    Single borrower limits

    Industry Concentration

    Limited total market capacity Unavailability of long term funds (maturity mismatch)

    Unwillingness to lend at fixed interest rates

    The ability of banks to extend term credit (beyond about fiveyears) is extremely limited, constrained by dependence uponshort-term deposits. Even in the most developed economies, theability of the banking sector to provide project financing isfacilitated only by the banks access to long term debt in thecapital markets and substantial capital

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    19/22

    IPP Financing: Basics

    As standalone, greenfieldassets, sponsors do not have accessto internally-generated cash flows.

    Must raise all of their capital from external sources.

    Use project companies to finance illiquid assets with long, butusually limited lives.

    For maturity matching reasons, requires long-term debt.

    Use of long term debt forces capital providers to make long-termassessment of project, industry, and sovereign risks.

    Cash flow based financing.

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    20/22

    0

    200

    400

    600

    800

    1000

    1200

    2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

    FiguresinU

    S$Million

    Foreign

    Local

    Total

    Investments Required in the Generation & Transmision During Planning

    http://tariq_presentation/PSMP-2005.xlshttp://tariq_presentation/PSMP-2005.xlshttp://tariq_presentation/PSMP-2005.xls
  • 8/2/2019 Final Presentation on Power Sector Edit-1

    21/22

    Conclusion

    * 18,000 MW new capacity will be required upto 2025 as per PSMP.

    *The investment (Capital Cost) requirement for generation &Transmission is estimated at 12.035 Billion US$ for base casescenario. Higher economic growth is expected and consequentlyinvestment requirement will be much more. The investmentopportunities in Bangladesh Power Sector are promising forBangladesh Power Sector are promising for Private Sector.

  • 8/2/2019 Final Presentation on Power Sector Edit-1

    22/22