Final Presentation on Power Sector Edit-1
-
Upload
tariq-rashid -
Category
Documents
-
view
216 -
download
0
Transcript of Final Presentation on Power Sector Edit-1
-
8/2/2019 Final Presentation on Power Sector Edit-1
1/22
-
8/2/2019 Final Presentation on Power Sector Edit-1
2/22
Profile of the Country
*The Country : The Peoples Republic of Bangladesh
*Area (without offshore) : 1,47,570 Sq. Km.
*Population : 134 Million
*Per Capita Income : US$ 440
*GDP Growth Rate : 5.8% in 2009.
* Present Installed Capacity : 5166 MW Power
*BPDB : 2522 MW
*IPP : 1596 MW
*Access to electricity : 45%
*Demand : 4200 - 5500 MW
7.0% Average since 1990.
*APSCL : 6062 MW
*EGCB : 190 MW
*Present Available Generation : 3800 4200 MW
*Per capita generation : 175 kwh/ year (FY08)
*Rental : 252 MW
-
8/2/2019 Final Presentation on Power Sector Edit-1
3/22
-
8/2/2019 Final Presentation on Power Sector Edit-1
4/22
Present Structure of the Power Sector
BPDB
Generation EGCB
Single Buyer-
BPDBPGCB
BPDBNorth West
Zone
BPDBCentral Zone
BPDBSouth Zone
WZPDCWest Zone
DPDC DESCO REB/PBSs
A PSCL IPPS
Rental
Generation
-
8/2/2019 Final Presentation on Power Sector Edit-1
5/22
Power Utilities Charactererized by PoorFinances, Slow Pace of Reforms
Unviability of the power sector utilities due to
Inadequate cost recovery of operating andcapital costs from user charges
Considerable operational inefficiencies across the value chain, andespecially in the distribution and commercial segment.
Heavy subsidies and cross-subsidies builtinto the consumer tariffs
Inefficient operation of generation,transmission and distribution due to cost-plus approach of determining tariffs asagainst market based setting of tariffs
High T&Dlosses
LowCollection
efficiency
Poor Financial Healthof utilities
Unpaidsubsidies
Lowrevenue
-
8/2/2019 Final Presentation on Power Sector Edit-1
6/22
... the Unviability infusing long term
imbalance in this infrastructure sector
Infrastructure
GrowthaxPayers Users
ProvidingSubsidies
Lowering Input Costs
IncreasingTariffs
... this Sector riddled with structural problems. For an example, BPDB total costof supply is more than its average tariff Tk 2.60 per kWh where as DESCO buyselectricity from BPDB & PGCB (for wheeling charge) at Tk.2.67/kWh and sells
to customer at an average tariff 3.90 Tk. Per kWh
-
8/2/2019 Final Presentation on Power Sector Edit-1
7/22
Opportunities and Challenges
-
8/2/2019 Final Presentation on Power Sector Edit-1
8/22
Major Event in Reform Process
* National Energy Policy : January 1996
* Private Sector Power GenerationPolicy of Bangladesh
* Creation of PGCB (TransmissionCompany)
*
Creation of DESCO(Distribution Company for part of Dhaka)
* Creation of APSCL(Ashugonj Power Station Company)
* Creation of WAPDC (Distribution
Company)
*Regulatory Commission Act : March 2003* Creation DPDC
: 1996
: 1996
: 1996
: 2002
: 2003
: October 25, 2006
-
8/2/2019 Final Presentation on Power Sector Edit-1
9/22
Components of Reforms
*The principal components of the reform have been envisaged asfollowings:
- Segregation of power generation, transmission and distribution
function into separate services.
- Corporatization and commercialization of emerging power sectorentities.
- Effective regulation under Bangladesh Energy RegulatoryCommission (BERC).
- Private sector participation and private public partnership in powersector.
-
8/2/2019 Final Presentation on Power Sector Edit-1
10/22
Components of Reform (Contd.)
- Financial Restructuring and Recovery Plan of the sector.
- Introduction of cost reflective tariff for financial viability of theutilities and promoting efficient use of electricity.
- Development of demand side management (DSM) including energyefficiency measures to conserve energy.
- Development of alternative/ renewable energy resources.
- Capacity building and HRD for sector entities and corporatizedbodies.
-
8/2/2019 Final Presentation on Power Sector Edit-1
11/22
Challenges
Dependency on Gas as primary energy for the electricitygeneration.
Open Markets & Competition
Project Management & Technology.
Risk & Securitization
Reform and Restructuring.
Impediment of supporting infrastructure, such as:
Gas exploration; gas pipe networks; coal Development;
M i T d M t it
-
8/2/2019 Final Presentation on Power Sector Edit-1
12/22
Moving Towards Maturity
Stage 5Stage 4Stage 3Stage 2Stage 1
IndependentPower Plants
Transmission
Transmission
Transmission
Vertically
Integrated
Utilities
Generation
Transmission
Distribution
Multiple
players
Independent
Power Plants
Generation
Multiple
players
Captive Power
Plants
Independent
Power Plants
State owned
generation
Multiple
players
DistributionCompanies
Open Access
Customers
Multiple
players
Captive Power
Plants
Independent
Power Plants
generation
Multiple
players
Distribution
Companies
Open Access
Customers
Power Pools/
Power
Exchanges/
OTC
Distribution
Companies
Vertically
IntegratedUtilities
Generation
Transmission
Distribution
-
8/2/2019 Final Presentation on Power Sector Edit-1
13/22
Ultimate Structure of
Electricity Market
*Single Buyer Model at present
- Single Buyer purchases all the power from generators
- Sells power to different Distribution companies
*Multi-buyer and competitive Pool may be adopted when the marketbecomes matured and stable
*Wholesale Real Time Power Trading
-
8/2/2019 Final Presentation on Power Sector Edit-1
14/22
Key Issues in Investment
Demand supply gap
Health of the power sector
Historical track record in private investments
Export possibility
Scale of opportunities
-
8/2/2019 Final Presentation on Power Sector Edit-1
15/22
Success Factor for Private Investments
Appropriateness of purchase tariff to recover cost of capital.
Financial health of purchaser.
Generation integrated with distribution
Adequacy of payment security mechanisms
Maturity and depth of domestic financial markets/ institutions toraise finances.
Alternative markets availability to the IPPs for sale of power in case
of default by the monopoly buyer.
Could be in the form of direct third party sales to large industrialconsumers.
Trading markets/ entities as demand aggregates for sale to alternatebuyers.
Credit enhancement mechanisms like Letter of Credit, escrow coverand Government Guarantees required as an alternate payment securitymeasure to mitigate payment risks.
-
8/2/2019 Final Presentation on Power Sector Edit-1
16/22
IPP Financing: Basics
As standalone, green-fieldassets, sponsors do not have accessto internally-generated cash flows.
Must raise all of their capital from external sources.
Use project companies to finance illiquid assets with long, butusually limited lives.
For maturity matching reasons, requires long-term debt.
Use of long term debt forces capital providers to make long-termassessment of project, industry, and sovereign risks.
Cash flow based financing.
-
8/2/2019 Final Presentation on Power Sector Edit-1
17/22
Transparent procurement Tariff structure Must be sufficient to meet projects operating costs, debt service, return on equity, and return of equity.
Creditors rights and the efficiency of legal enforcement Common law vs. civil law Strong vs. weak enforcement
Government: Sovereign vs. Commercial Entity
Waiver of sovereign immunity
Concession agreement Off- take agreement/Input supply agreement
Penalty for non-performance, LDs
Termination payments
Credit enhancements
Direct agreement Lenders step-in rights
Assignment of project agreements
Repatriation of loan proceeds Currency convertibility Currency depreciation risk
Lenders Concerns: General
-
8/2/2019 Final Presentation on Power Sector Edit-1
18/22
Local Financing Limitations forIPP Projects
Long term financing needs of infrastructure projects are notbeing meet by commercial banks because of:
Size of projects
Single borrower limits
Industry Concentration
Limited total market capacity Unavailability of long term funds (maturity mismatch)
Unwillingness to lend at fixed interest rates
The ability of banks to extend term credit (beyond about fiveyears) is extremely limited, constrained by dependence uponshort-term deposits. Even in the most developed economies, theability of the banking sector to provide project financing isfacilitated only by the banks access to long term debt in thecapital markets and substantial capital
-
8/2/2019 Final Presentation on Power Sector Edit-1
19/22
IPP Financing: Basics
As standalone, greenfieldassets, sponsors do not have accessto internally-generated cash flows.
Must raise all of their capital from external sources.
Use project companies to finance illiquid assets with long, butusually limited lives.
For maturity matching reasons, requires long-term debt.
Use of long term debt forces capital providers to make long-termassessment of project, industry, and sovereign risks.
Cash flow based financing.
-
8/2/2019 Final Presentation on Power Sector Edit-1
20/22
0
200
400
600
800
1000
1200
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
FiguresinU
S$Million
Foreign
Local
Total
Investments Required in the Generation & Transmision During Planning
http://tariq_presentation/PSMP-2005.xlshttp://tariq_presentation/PSMP-2005.xlshttp://tariq_presentation/PSMP-2005.xls -
8/2/2019 Final Presentation on Power Sector Edit-1
21/22
Conclusion
* 18,000 MW new capacity will be required upto 2025 as per PSMP.
*The investment (Capital Cost) requirement for generation &Transmission is estimated at 12.035 Billion US$ for base casescenario. Higher economic growth is expected and consequentlyinvestment requirement will be much more. The investmentopportunities in Bangladesh Power Sector are promising forBangladesh Power Sector are promising for Private Sector.
-
8/2/2019 Final Presentation on Power Sector Edit-1
22/22