MBA CPM & CE-QS Stake Holder Analysis of Delhi Metro Phase - III Group Members A13559014072 SABRINATH K A13559014073 VIVEK RADADIA A13559014078 SATYANARAYANA B A13559014073 RAUNAQ SINGH - PUNEET SOBTI

Transcript of Final presentation d 3

Page 1: Final presentation d 3

MBA CPM & CE-QS

Stake Holder Analysis of Delhi Metro Phase -III

Group Members A13559014072 SABRINATH KA13559014073 VIVEK RADADIAA13559014078 SATYANARAYANA BA13559014073 RAUNAQ SINGH - PUNEET SOBTI

Page 2: Final presentation d 3

Introduction Began Operation-24 Dec 2002Delhi Metro planned in phases for over 20 years Each of the 4 phases has a target of five years. Completed Phase I (65 km) in 2006 Completed Phase II (125 km) in 2011Current Total Length 193.2 kmConstruction on Phase-III began on Scheduled completion Time of Phase-III & Phase IV are 2016 & 2021 respectively with the network spanning 413 by then

Page 3: Final presentation d 3

Project Specifics of Phase-III

• Total Length 167.277kms• Number of stations -104 (28 U.G 41km )• Green Building Stations• Ring Lines system to interconnect existing

lines• Communication Based Train Control • Expected Ridership of 18,56,426 in 2016

Page 4: Final presentation d 3

Objectives• Identification of stakeholders and their impact• Evaluation of stakeholder influence during

project preparation • Methods & Approach adopted for Public

Consultation • Methods & strategy used for Land Acquisition• Learn the strategies adopted for relocation &

rehabilitation of PAPs for Delhi MRTS Projects

Page 5: Final presentation d 3

DMRC

Gov. of UP

MEDIA

CISF

DMC

DDA

GOI

Archeology Department

PAP’S

Contractors

Indian Railways

MoUD

Bombardier Transportation

SIEMENS

Employees

Samsung-HCC

AFCON

L &TPratibhaJ K Infra

MBL Infra

ITC CEM

Central Pollution Board

NGO

Phase-III 2016???

RITES-JICA-Gov of Delhi

MIND MAP

PWD

GRC

Page 6: Final presentation d 3

Stakeholder’s Involved• JICA• DMRC• Bombardier Transportation• RITES• CISF• DDA• Govt of India• Govt of Delhi• Media• Department of Archeology

• Delhi Municipal Corporation

• Bombardier Transportation

• General Public• Traffic Police

Department• ITC CEM • MBL Infra• HCC• PWD

Page 7: Final presentation d 3

List of Internal Stakeholders

DMRC ITC CEM Ltd MBL Infra Bombardier Transportation SIEMENS HCC RITES Employees of DMRC Grievance Redressal Comiitee

• J K Kumar Infraproject • Arvind Techno Engineers

Pvt Ltd• Sam(India) Built Well Pvt

Ltd• ITC CEM • Pratibha JV• Afcon• RITES

Page 8: Final presentation d 3

List of External Stakeholders

• General Public• Media• Traffic Police Department• Government Bodies• Department of Archeology• Ministry of Environment

Page 9: Final presentation d 3

Stakeholder Map

Importance to Success

Stak

ehol

der

Inte

rest

s/Ex

pect

ation

s

Page 10: Final presentation d 3

Ref. No.

Stakeholder

001 002 003 004 005 006 007 008 009 010 011 012 013 014 015

001 DMRC

002 JICA +

003 Govt of Delhi

+ N

004 Contractor

+ U +

005 Govt of India

+ + + U

006 DDA + U + U N

007 Municipal

+ U + U N +

008 Archeological

+ U + U + M M

009 General public

+ U + U N U U U

010 CISF + U + U + U U U M

011 Bombardiert

+ U + M + U U U U U

012 Media m U M U M N M + + U U

013 Indian Railway

m U M U M U U U U U + N

014 Govt of UP

+ U + U + U U N N U U M

015

Page 11: Final presentation d 3

Strategic Engagement Plan

Page 12: Final presentation d 3

WHAT SUCCESS LOOKS

LIKE FOR

THE PROJET TEAMTHE ORGANIZATION /MINISTER

THE COMMUNITY/OTHER STAKEHOLDERS

SUCCESSFUL EXECUTION OF METRO RAIL PROJECTSWITH OUT ANY ACCIDENTS AND DELAYS

GOOD TRANSPORT FACILITY,SATISFACTION FOR PUBLIC.GREAT RETURNS,DEVELOPMENT

CNCAP TRANSPORT WITH GREAT AMENITY WHICH WAS NEED AND ULTIMATE SOLUTION

INFORM CONSULT INVOLVE COLLABORATE EMPOWER

STAKEHOLDERS STAKEHOLDERS STAKEHOLDERS STAKEHOLDERS STAKEHOLDERS

JICA JICA GOVT OF INDIAGOI,GOD,DMC,LISF,PAP'S,RITES,MEDIA , GOI,GOD,PAP'S

RITES INDIAN RAILWAYS GOVT OF DELHI CEMENTS, RITES

CONTRACTOR RITES GOVT OF UPBOMBARDIER TRANSPORT CONTRACTORS

CENTRAL POLLUTION BOARD

CENTRAL POLLUTION BOARD

JICA,INDIAN RAILWAYS,RITES,NGOS MOUD,DMC,PWD,DDA INDIAN RAILWAYS

INDIAN RAILWAYS,,NGO'S

ARCHEOLOGY DEPARTMENT

ARCHEOLOGY DEPARTMENT

ARCHEOLOGY DEPATRMENT CEMENTS

CISF,TRAFFIC POLICE DEPARTMENT,DDA

PAP's

TOOLS TOOLS TOOLS TOOLS

WEB SITE ,MEETINNGS,LETT

ERS

MEETINGS,DMRC WEB SITE, SPECIAL COMMITEE LETTERS

MEETINGS,REPORTS,NEWSPAPERS ,

ADVERTISEMENTS,LETTERS,DMRC WEB SITES

DMRC WEB SITES,OFFICIAL

LETTERS,REPORTS,MEETINGS

MEETINGS,OFFICIAL LETTERS,DMRC WEB

SITE

Page 13: Final presentation d 3

Engagement Evaluation Strategy

Page 14: Final presentation d 3

References

• Delhi Metro Wikipedia Page

http://en.wikipedia.org/wiki/Delhi_metro#Phase_III

• DMRC Official Website

http://www.delhimetrorail.com/

• RITES Report on Social Impact Assessment of Delhi Metro – Phase III SOCIAL PA

http://www.delhimetrorail.com/projectsupdate/SIA-REports-2.pdf