FINAL MINUTES - Mackay Council · FINAL MINUTES WEDNESDAY 11 APRIL 2018 MIN/11.04.2018 FOLIO 49516...
Transcript of FINAL MINUTES - Mackay Council · FINAL MINUTES WEDNESDAY 11 APRIL 2018 MIN/11.04.2018 FOLIO 49516...
FINAL MINUTES
11 April 2018
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49511
Table of Contents
Folio Date Particulars
11.04.2018 Ordinary Meeting Minutes
11.04.2018 Office of the Mayor and CEO Monthly Report - April 2018
31.03.2018 Community and Client Services Monthly Report - March 2018
11.04.2018 Local and Subordinate Local Laws
Declaration of Potential Conflict of Interest
Nil.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49512
ORDINARY MEETING
MINUTES
1. ATTENDANCE:
His Worship the Mayor, Cr G R Williamson (Chairperson), Crs, A J Camm, M J Bella,
L G Bonaventura, K J Casey, J F Englert, R C Gee, F A Mann, K L May, A R Paton
and R D Walker were in attendance at the commencement of the meeting. Also present
was Mr C Doyle (Chief Executive Officer) and Mrs M Iliffe (Minute Secretary).
Cr Williamson acknowledged the Yuwibara people, the traditional owners of the land
on which we meet and paid his respects to their Elders past and present.
The meeting commenced at 10.00 am.
2. OPENING PRAYER:
Cr Camm led those present in Prayer.
3. ABSENT ON COUNCIL BUSINESS:
Nil
4. APOLOGIES:
Nil
5. CONDOLENCES:
The Mayor, on behalf of Council, expressed condolences to the family and friends of
Tate Adams who was a distinguished printmaker, teacher, gallerist and co-founder of
the Lyrebird Press. Tate Adams donated over 300 works, principally artists books, to
Artspace when it was opened in 2003. Artspace Mackay established the Tate Adams
Reading Room and Tate Adams Reading Pod to encourage the sharing of the significant
collection of artists' books.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49513
6. CONFLICT OF INTEREST:
Nil
7. CONFIRMATION OF MINUTES:
7.1 ORDINARY MEETING MINUTES - 28 MARCH 2018
THAT the Ordinary Meeting Minutes dated 28 March 2018 be adopted.
Moved Cr Camm Seconded Cr May
CARRIED
8. BUSINESS ARISING OUT OF MINUTES OF PREVIOUS MEETING:
Nil
9. MAYORAL MINUTES:
Nil
10. CONSIDERATION OF COMMITTEE REPORTS & RECOMMENDATIONS:
Nil
11. CORRESPONDENCE AND OFFICERS' REPORTS:
11.1 OFFICE OF THE MAYOR AND CEO MONTHLY REPORT -
APRIL 2018
Author Chief Executive Officer
Purpose
To provide Council with the Office of the Mayor and Chief Executive Officer's
Monthly Report for month of April 2018.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49514
Background/Discussion
All departments within MRC prepare a Monthly Review which identifies activities
undertaken and progress made during the specific month.
Consultation and Communication
The report contains input from relevant Programs across Council.
Resource Implications
As required to compile report, which is a routine task for multiple employees.
Risk Management Implications
Nil.
Conclusion
Council is kept informed of activities within the Office of the Mayor and Chief
Executive Officer and of major initiatives and projects across Council.
Officer's Recommendation
THAT the Office of the Mayor and Chief Executive Officers Monthly Report for
April 2018 be received.
The Chief Executive Officer (CEO) spoke to his report and provided an overview and
highlights of the Office of the Mayor and CEO Monthly Report for April 2018.
Cr Camm queried the status of the Northern Australia Alliance (NAA) and with
Council's commitment to the NAA, which was the setup of the Greater Whitsunday
Alliance (GW3) which has been fulfilled and therefore should the KPI around NAA be
removed and transfer this to the GW3 KPI's and their funding arrangement.
Cr May queried how is Council ensuring effective representation on NAA is being
undertaken and how are these being measures from GW3.
The Mayor advised Council can request the CEO of GW3 to provide a report to
Council. The Minutes of these meetings are published and at the April meeting he will
table this request.
Cr May queried in the overall performance of GW3 if there were any plans soon to
undertake an evaluation.
The CEO advised GW3 will be presenting to the Greater Whitsunday Council of
Mayors next week and then GW3 will present to Council shortly thereafter.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49515
Cr Bonaventura followed on from this query. He asked if Council is funding GW3 then
is it not Councils' responsibility to pursue GW3 to ensure progress is made in this area.
The Mayor advised GW3 have a KPI of their own to meet and when they are briefing
Council these questions can be put to them.
Cr Camm responded to Cr Bonaventura's comment advising Council is aware there are
political influences with the re-establishment of Regional Development Australia
(RDA) and what their role is and this has now lead to NAA's validity being questioned,
especially given a number of members of the NAA were seeking Federal Government
funding that was funding to RDA, and they were unsuccessful in that funding being
provided to NAA. It now appears that NAA is sitting in limbo and therefore the
question of where is Council's role and where is Council best invested over time.
The Mayor advised this needs to be undertaken by GW3 and suggested that when GW3
brief Council then these questions can be asked and then the GW3 Board can provide
the answers Councillors are seeking.
Cr Bonaventura advised he is happy to ask the questions of the GW3 Board when the
briefing is held but he is not happy for the responsibility to be removed from Council's
KPI's at this stage.
The Mayor agreed with Cr Bonaventura's request to not remove the NAA KPI from
Council's reporting at this stage.
Cr Bella queried, given the little progress other than through GW3 initiatives and
considering Council's investment in GW3, what progress and how is the progress
intended to be made.
The CEO advised the KPI in this report is around NAA and GW3 is only one (1) party
which can fill the gap and Council needs to work with GW3 and RDA to work out the
best way forward.
Cr Bella queried when the Sarina Field of Dreams contract is signed off for completion,
and the fact that there is a declarable weed found on this site, will there be provisions in
the sign off for continued care of the landscaping or will this be a cost to the ratepayer.
The CEO advised that all projects have formal sign off and Council will ensure sign off
is not completed until all obligations have been met as per the contract, and if they are
not met then something will be put in place to mitigate the risk to the ratepayers going
forward.
Cr Mann queried if the construction of the Mackay Skate and Wheeled Sports Plaza
commenced in mid-March 2018.
The CEO advised construction commenced in mid-March 2018 and due for completion
in August 2018.
Cr Paton congratulated the Council teams on the performance of the lost time injuries
(LTI's) frequency rate which is trending down. However, given the high number of
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49516
injuries in the Development Services Directorate has there been investigation on why
this is the case.
The CEO advised staff from Parks, Environment and Sustainability are part of the
Development Services Directorate and this is a reasonable risk area for Council. Every
incident, whether an injury or not, is investigated and there have been a number of
different types of injuries in the Parks area this year.
Cr Bonaventura followed on from Cr Paton's comments and advised he was not as
satisfied with the LIT's frequency rate. In 2016/17 Council was below 5 and this is
currently sitting at 7.2, this figure has been quite high through the majority of the year
and would like an explanation as to the contributing factors.
The CEO advised he appreciates Cr Bonaventura's view and last year the results
showed an exceptional performance, Council had reduced the number of LTI’s and
associated lost days considerably up to this year. There are 10 LTI's to date after 9
months, which is more than last year, and approximately 120 lost days. Each one of
these 10 are different types of incidents and very confident the reporting culture of the
organisation is very good. There is no pattern emerging with these incidents and safety
is something that is focused on and each incident is analysed.
Cr Bonaventura thanked the CEO for his explanation.
The Mayor advised the senior management team take safety extremely importantly and
focus on safety every day and the CEO is doing a very good job in this area as everyone
knows. However, one incident is still too many and need to continue the focus on
safety.
Cr Paton clarified his congratulations was for the figures trending in the right direction.
Cr May queried why the Blacksmith Street Turn-a-Round project of $45,578, which
had budget approval in 2012, was only completed in 2018.
The Director of Engineering and Commercial Infrastructure (DECI) advised the
original concept was developed for the project in 2012, however the construction then
need to await future budget process and approval.
Cr May advised when she looks at the Project Completed list and sees budget approval
year of 2012, then the report needs to be changed or the process needs to be quicker.
The CEO advised that when Council designs something they should be confident that
sometime in the near future the project will be approved. This process is being
reviewed to reduce the delay between design and completion of projects.
Cr Bonaventura queried given the lease has been executed for the Mackay Regional
Sports Precinct are there clauses in place to protect Council's asset in the future.
The CEO advised the lease is for 60 years, 20 x 20 x 20, and at year 50 both parties
meet to agree to what will occur at year 60. Therefore, Council of the day will know
what will be occurring with the asset at year 60.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49517
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Camm Seconded Cr Bonaventura
CARRIED
11.2 COMMUNITY AND CLIENT SERVICES MONTHLY REVIEW 1-31
MARCH 2018
Author Director Community and Client Services
Purpose
Attached is a copy of the Community and Client Services Monthly Review for the
month of March 2018.
Officer's Recommendation
THAT the Community and Client Services Monthly Review covering 1-31
March 2018 be received.
The Chief Executive Officer (CEO) spoke to this report and provided an overview and
highlights of the Community and Client Services Monthly Report for March 2018.
Cr Camm queried if the community engagement reporting can be reviewed to be more
forward facing from a community engagement point of view and for an understanding
of where it is appropriate for elected members to be involved.
The CEO advised this has been discussed at SLPT this week and will arrange for a
briefing to be held with Councillors to determine how Council can move forward with
different reporting options in this space.
Cr Camm commented that overall the reporting from this Directorate has significantly
improved and the input of some of the imagery and the description around the activity
informs the Councillors better.
Cr Mann queried what the number of Jubilee Community Centre (JCC) room hire
applications processed meant.
The CEO advised it is the total number of JCC room hires processed.
Cr May advised she would like to see the JCC room hire usage on a monthly basis
reported on, so there is a measure to compare on a year by year basis going forward.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49518
Cr Mann advised she feels the MRCLS 2017-18 Financial Year People Visits graph
does not make any sense but notes this will be changed for future reports.
Cr Mann queried what the "Hub" is in the graph for MRCLS New Members 2017-18
Financial Year.
The CEO advised the new members under the "Hub" represent school children who
have joined the library under the Young Peoples Service Library Program which is a
new initiative.
Cr Mann queried when the "Hub" was introduced.
The Director of Community and Client Services (DCCS) advised she would take that
query on notice and come back to the Councillors with the exact date.
Cr Camm commented on the query on the "Hub", as elected members they would like
to be made aware of new initiatives to be advocates out in the community.
The DCCS advised this is not a new initiative it is just a rebranding.
The CEO confirmed it is not a new initiative but the data is now starting to be captured
separately.
Cr Bonaventura advised the questions raised by Cr Camm and Cr Mann would be ideal
to be worked through at the Strategic Advisory Committee meeting and looks forward
to the commencement of this committee.
Cr Walker queried what the 14 emergency relief assistance packages entailed.
The DCCS advised the emergency relief assistance packages are a State Government
initiative, they provide some funding through the Sarina Neighbourhood Centre. The
packages are provided to residents who are experiencing hardship and may need some
assistance.
Cr Walker queried the level of interest for the youth ambassador program to Matsuura.
The DCCS advised there are six (6) registered for this program and staff have been
working with the schools to generate some interest and the deadline has been extended
twice now. There are four (4) high schools in the region who host their own trips to
Matsuura.
Cr Camm further expanded on this program in that there have been discussions around
engaging the schools to review an add on for a few days to Matsuura to their school
trips as it is important to maintain the relationship with Matsuura.
Cr May queried if there is an opportunity to enhance how the Council in Community is
reported as it is quite a significant initiative of this Council and there is a full day of
visiting a lot of places within the community and currently this reporting does not
capture it.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49519
The DCCS advised this would be reviewed for future reports.
Cr May queried if the Facebook interaction could be reported differently and show the
interaction on the different Council Facebook pages.
The DCCS advised this would be reviewed for future reports.
Cr May queried if the venue for the "Local Coastal Plans Lamberts Beach & Slade
Point" was correct.
The CEO advised that is not the correct venue.
Cr Mann queried if there was anything that could be done to assist with the MECC
attendances as Mackay is the last leg on the Queensland tour while Cains and
Townsville venues are closed for refurbishments currently.
The CEO advised the MECC Manager is continually negotiating to attract events to
Mackay.
The Mayor suggested Cr Mann take this off line and discuss it further with the DCCS.
Cr Bonaventura queried what was the emerging issue officers were responding to in
improving weed management at Council quarries.
The CEO advised this resulted from a request raised by Cr Bella where he reported a
single noxious weed growth in a pile of soil at a Council quarry. Local Laws crew
responded to the request and will continue to focus on this type of incidents at Council
quarries.
Cr Bonaventura queried if an education program is warranted to target overgrown
allotments given they make up two of the top six current active request categories.
The CEO advised an education process is warranted coming into the summer period as
it does not take long for the allotment to become overgrown.
Cr Bella advised the request he raised in relation to the noxious weed growth at the
Council quarry was undertaken quickly by the staff and to the satisfaction to the
residents of the area. Staff had previously inspected this site and there was no growth
showing how quickly they can appear, and he congratulated the staff for their quick
response.
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Mann Seconded Cr May
CARRIED
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49520
11.3 LOCAL AND SUBORDINATE LOCAL LAWS
File No Local Laws Review
Author Manager Governance & Safety
Purpose
To propose:
• Amendments to the following Subordinate Local Laws:
Subordinate Local Law No 1.1 (Alteration or Improvement to Local
Government Controlled Areas and Roads) 2011;
Subordinate Local Law No. 1.10 (Operation of Public Swimming Pools)
2011;
Subordinate Local Law No. 2 (Animal Management) 2011; and
• Repeal Local Law No. 2 (Meetings) 2008.
Background/Discussion
At Council's Ordinary Meeting of 26 July 2017 (Folio 45372), Council resolved to
proceed with amendments to:
Subordinate Local Law No 1.1 (Alteration or Improvement to Local
Government Controlled Areas and Roads) 2011;
Subordinate Local Law No. 1.10 (Operation of Public Swimming Pools)
2011;
Subordinate Local Law No. 2 (Animal Management) 2011;
And to repeal Local Law No 2 (Meetings) 2008.
The resolution included commencing the state interest and the public consultation
processes.
The Health & Regulatory Program briefed Council on the proposed amendments to
Subordinate Local Laws on 26 April 2017. Information on the proposed amendments
are detailed below.
Subordinate Local Law No 1.1 (Alteration or Improvement to Local Government
Controlled Areas and Roads) 2011
• Proposed amendments are to change the category activity from a category 2
to a category 1 activity.
• This amendment will allow Mackay Regional Council (MRC) to enforce the
removal and destruction of street trees by issuing a penalty infringement
notice rather than proceeding through the court system.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49521
Subordinate Local Law No. 1.10 (Operation of Public Swimming Pools) 2011
• The proposed amendments include the reference to the Building Act 1975 in
relation to swimming pools.
• This reference will allow MRC to better manage pool compliance under the
Subordinate Local Law.
Subordinate Local Law No. 2 (Animal Management) 2011
The proposed amendments include:
• the management of bee hives,
• the removal of the "designated town area" definition,
• the inclusion of the Shellgrit Creek Beach dog exclusion zone; and
• criteria amendments around keeping various types of animals.
Local Law 2 (Meetings) 2008
This Local Law is proposed to be repealed as it is no longer relevant. It was
developed and in place prior to the commencement of the Local Government Act
2009 (i.e. the Local Government Act 1993), and provisions contained within this
local law are now within the current Act.
Section 38 of the Local Government Act 2009 provides that Council must not make a
Local Law (including a Subordinate Local Law) that contains an anti-competitive
provision unless Council has complied with the procedures prescribed under a
regulation for the review of anti-competitive provisions.
Subordinate Local Law No. 2 (Animal Management) was identified to contain anti-
competitive provisions. MRC has complied with the procedures prescribed by the
regulation by undertaking a public interest test and further consultation between 18
December 2017 and 19 January 2018.
As part of MRC’s Local Law-Making process, Council is now able to resolve to make
the proposed amendments to the Subordinate Local Laws and to repeal Local Law No.
2 (Meetings) 2008.
Once the Council has made the resolution, MRC must then advise the public by
publishing a notice in the Government Gazette and Council’s website within one
month. MRC is also required to provide to the Minister for Local Government, Racing
and Multicultural Affairs a copy of the following within 14 days of the Notice being
published in the Gazette:
• Gazette Notice;
• Certified copy of the Subordinate Local Law referred to in the Notice.
The commencement of the new Subordinate Local Laws will take effect as at the date
the Notice is published in the Gazette.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49522
Consultation and Communication
According to the Local Law-Making Process which was adopted by Council on 6
March 2013, Council was required to formally consult with State agencies and the
general community.
State Interest Consultation
Consultation with the State agencies was only required for the repealing Local Law 2
(Meetings) 2008.
The consultation period was for a 6-week period (i.e. between 7 August 2017 and 18
September 2017) as per the Local Law-Making process. Correspondence was only
forwarded to the Department of Infrastructure Local Government & Planning for
comment.
It was considered that the Department was the only State agency which was required to
be consulted due to the content of the Local Law.
A submission was not received from the Department in relation to the repealing of this
Local Law.
Public Consultation
MRC was required to consult with the public for at least 21 days (consultation took
place between 5 August and 28 August 2017). MRC undertook the necessary
consultation by:
• Publishing a notice about the proposed Local Law in a newspaper circulated
generally in the local government’s area i.e. the Daily Mercury;
• Displaying the advertisement in a conspicuous place at the Local Government
public office; MRC’s Client Service Centre Gordon Street;
• Having a copy of the proposed Local Law and Subordinate Local Law available
for inspection or purchase at MRC’s office;
• Placing a copy of the advertisement on MRC’s website;
A second round of public consultation was required to take place in respect to the
Subordinate Local Law No. 2 (Animal Management) 2011 where anti-competitive
provisions were identified. This consultation took place between 18 December 2017
and 19 January 2018. Consultation was in accordance with the outlined process above
as well as consultation direct with identified stakeholders who may have had an interest
in the amendments to the Animal Management Subordinate Local Law.
These Stakeholders were the RSPCA Mackay and the CQ Beekeepers Association Inc.
MRC did not receive any submissions from the public in relation to the above Laws
from either consultation period.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49523
Resource Implications
Legal fees and advertising fees are budgeted accordingly. There are no other significant
resource implications.
Risk Management Implications
The risk associated with this activity is assessed as being low.
Conclusion
Council has now undertaken all the necessary steps pursuant the Local Law-Making
Process which was adopted by Council on 6 March 2013 and is now able to resolve to
adopt the proposed Amendments to the abovementioned Subordinate Local Laws and
to repeal Local Law No. 2 (Meetings) 2008.
With the adoption of these amended Subordinate Local Laws, Council will be able to
facilitate the changes to its regulatory powers to enforce the activities identified in the
Subordinate Local Laws and issue appropriate penalty infringement notices.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49524
Officer's Recommendation
THAT Council
(a) implement the recommendations of the Public Interest Test Report –Animal
Management (Amendment) Subordinate Local Law (No. 1) 2017; and
(b) make Local Law (Repealing) Local Law (No. 1) 2017 as advertised, but
amended by the omission of each reference to ‘2017’, and the insertion
instead of a reference to ‘2018’; and
(c) make Alteration or Improvement to Local Government Controlled Areas
and Roads (Amendment) Subordinate Local Law (No. 1) 2017 as
advertised, but amended by the omission of each reference to ‘2017’, and
the insertion instead of a reference to ‘2018’; and
(d) make Operation of Public Swimming Pools (Amendment) Subordinate
Local Law (No. 1) 2017 as advertised, but amended by the omission of each
reference to ‘2017’, and the insertion instead of a reference to ‘2018’; and
(e) make Animal Management (Amendment) Subordinate Local Law (No. 1)
2017 as advertised, but amended by the omission of each reference to
‘2017’, and the insertion instead of a reference to ‘2018’; and
(f) note that Animal Management (Amendment) Subordinate Local Law (No.
1) 2017 contains anti-competitive provisions; and
(g) adopt, pursuant to section 32 of the Local Government Act 2009, in the
form attached to this report to Council, consolidated versions of subordinate
local laws of Council as follows—
(i) Subordinate Local Law No. 1.1 (Alteration or Improvement to
Local Government Controlled Areas and Roads) 2011;
(ii) Subordinate Local Law No. 1.10 (Operation of Public Swimming
Pools) 2011;
(iii) Subordinate Local Law No. 2 (Animal Management) 2011.
Cr Walker sought further clarification on what the "anti-competitive provisions"
referred to in the Subordinate Local Law No. 2 (Animal Management) means.
The Director of Community and Client Services (DCCS) advised she would take this
query on notice and come back to the Councillors for a formal response.
The Executive Officer (EO) advised he understood it was in relation to commercial
activities for animals, including such things as commercial kennels.
Cr Camm wished to expand on this query, in relation to bee hives, and the local law
that is being proposed is not for commercial use of bee hives, only for a
hobbyist/domestic use.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49525
The Mayor advised with the proviso that the Councillors receive an explanation from
the DCCS about Cr Walker's query then he was happy for ask for the Motion to be
considered.
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Paton Seconded Cr Camm
CARRIED
11.4 LEASE OF LAND - JOINT LEASE - MACKAY CITY RUGBY
UNION FOOTBALL CLUB INC. AND MACKAY DISTRICT
JUNIOR RUGBY UNION INCORPORATED
File No 153955-118-SP
Author Manager Property Services
Purpose
To approve a new joint Trustee lease to Mackay City Rugby Union Football Club Inc.
and Mackay District Junior Rugby Union Incorporated for the area known as 'Quarry
Hill' being an area of approx. 5.9Ha being Lot 118 SP153955, 58 Hamilton Street,
North Mackay for a period of ten years.
Background/Discussion
Mackay Regional Council is the trustee of Crown (Reserves) Lot 118 on SP153955
situated at 58 Hamilton Street, North Mackay.
Historically this area was leased to Mackay and District Rugby Union (MDRU). The
lease for MDRU expired 31 December 2015. Council has had several meetings and has
attempted numerous times to assist MDRU with negotiating a new lease, with no
success.
Property Services was contacted in March 2018 by the newly elected President of
Mackay City Rugby Union Football Club (MCRU) to advise that MDRU no longer
wanted the responsibility of the lease and they, together with Mackay District Junior
Rugby Union (MDJRU) would like to reopen discussions with Council to establish a
joint lease.
Property Services instigated a meeting on site with the interested parties, with both
Clubs very keen to move forward with a joint lease. It should be noted that formal
notification has been received from MDRU on 19 March 2018 that they do not want to
be involved with the new lease.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49526
According to Section 236 (b) (ii) of the Local Government Regulation 2012, "a local
government may dispose of a valuable non-current asset other than by tender or auction
if - the valuable non-current asset is disposed of to a community organisation."
Therefore, Council is not required to re-tender this before leasing the property.
Consultation and Communication
Consultation has occurred between representatives of MCRU and MDJRU, Supervisor
Land Operations - Property Services, Manager Property Services, Director
Organisational Services and Council's Sport & Recreation Officers.
Resource Implications
All costs incurred in respect to the preparation and lodgement of the lease
documentation to be borne by the Lessees.
The lease will be a standard 'trustee' lease inclusive of peppercorn rental of $50.00 plus
GST per annum and other like conditions.
Risk Management Implications
Quarry Hill is known as the home of rugby union, should this lease not be approved,
both the community and region would not be able to benefit from the opportunities that
arise from such groups.
Conclusion
That the approval of the new joint lease to MCRU and MDJRU who have shown a
commitment to rugby union, the land and the local community is the most
advantageous outcome to Council.
The lease will be signed under delegation once finalised.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49527
Officer's Recommendation
THAT Council -
A. Resolves that an exemption applies under Section 236 (b) (ii) of the Local
Government Regulation 2012, "a local government may dispose of a
valuable non-current asset other than by tender or auction if - the valuable
non-current asset is disposed of to a community organisation."
B. AND THAT Council approve a new joint lease for a term of ten years to
Mackay City Rugby Union Football Club Inc and Mackay District Junior
Rugby Union Incorporated for the area known as "Quarry Hill" being an
area of approx. 5.9Ha being Lot 118 on SP153955, 58 Hamilton Street,
North Mackay, with such lease to be a standard 'trustee' lease inclusive of
peppercorn rental of $50.00 plus GST per annum and be subject to the
approval of the Department of Natural Resources and Mines.
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Casey Seconded Cr Gee
CARRIED
11.5 MATERIAL CHANGE OF USE - EDUCATIONAL
ESTABLISHMENT (ANCILLARY CAR PARK) - LOT 902
MACKAY-BUCASIA DRIVE, MOUNT PLEASANT - LOT 902 ON
SP259166 - DA-2017-130
Application Number: DA-2017-130
Date Received: 19 December 2017
Action Officer: Dennis O'Riely
Applicant’s Details: Roman Catholic Trust Corporation Diocese
of Rockhampton for Catholic Education
c/- Justin Peel
PO Box 4499
MACKAY QLD 4740
Proposal: Education Establishment (Ancillary Cark
Park)
Site Address: Lot 902 Mackay-Bucasia Road, Mt Pleasant
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49528
Property Description: Lot 902 on SP259166
Owner’s Details: Gainbight Pty Ltd
Area: Lot 902: 2.498ha - Development Area:
1.137ha
Planning Scheme: Mackay Region Planning Scheme 2017
Planning Scheme Designations::
Zone:
Low Density Residential
Assessment Level: Impact
Submissions: 2 written submissions and 2 petitions
(containing 111 signatures)
Referral Agencies: Concurrence - Department of State
Development, Manufacturing, Infrastructure
and Planning
(Trigger: Planning Regulation 2017,
Schedule 10.9.4.2.4.1 State transport
corridors and future State transport corridors,
and Scheduled 10.9.4.1.1.1 Infrastructure -
State transport infrastructure)
Attachments: Attachment A:
Attachment B:
Attachment C:
Attachment D:
Attachment E:
Locality Plan
Proposal Plan
Referral Agency Response
Submitters Proposed
Amendments
Submitters Concerns -
Crispin Drive
Recommendation: Approved Subject to Conditions
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49529
ASSESSMENT OF APPLICATION
Purpose
The Material Change of Use application is for a school car park (defined in the
Mackay Region Planning Scheme as ancillary to an Education Establishment) for
Holy Spirit College, Mt Pleasant (refer to Attachment A – Locality Plan). The 247
space car park is proposed to be constructed on the balance land of Belmore Estate
residential estate, Lot 902 Mackay-Bucasia Road, Mt Pleasant.
The application is impact assessable and received two (2) properly made submissions
and two (2) properly made petitions (containing 83 and 28 signatures) against the
proposed development. The submissions raised concerns with connecting Tamron
Drive as a through-road to Baxter Drive and pedestrian and vehicle safety with more
traffic using Tamron Drive. The submitters have not raised any grounds that cannot
be appropriately conditioned or that would warrant the refusal of the development
application.
The submitters also requested that the proposal be amended to include a right-turn
egress from the car park to Tamron Drive to encourage vehicles to exit to the east via
Baxter Drive, rather than motorists driving west along Tamron Drive and causing
more congestion at the Tamron Drive/Pioneer Street roundabout near Northview
Primary School. In response to the submitters concerns, the applicant amended the
proposal to include the right-turn exit from the proposed car park.
The application is recommended for approval, subject to conditions.
Subject Site and Surrounds
The application has been made over the 2.498 ha parcel of land partially developed
for stage three (3) of Belmore Estate.
The car park will be located on 1.137ha of land purchased by the school from the
Belmore Estate developer Gainbight Pty Ltd (proposed lot 501), which is the balance
of stage three and is vacant.
The developer of Belmore Estate has applied to Council to endorse the survey plan for
part of stage three (3) of the estate, which creates nine (9) residential lots and the
balance development lot which is the subject of this development application. That
application is still under assessment at the time of writing this report. Currently all
infrastructure works for the new lots are completed, as is the construction of Tamron
Drive which will ultimately connect to Baxter Drive. Upon registration of the survey
plan for this part of stage three (3) the Tamron Drive road reserve will extend through
and connect to an unformed section of Baxter Drive. Tamron Drive is not currently
open to through vehicle traffic and this will not occur until the unformed section of
Baxter Drive is constructed by Council. This project is currently planned to be
delivered in 2018/2019 in conjunction with Holy Spirit College upgrading and
redesigning their existing car parking area.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49530
The development lot will be bounded by Tamron Drive along its northern boundary,
residential development to the west and Holy Spirit College to the south. There is an
existing 2m wide concrete footpath constructed along the Tamron Drive frontage of
the development site and a 1.8m high screen fence along the common boundary with
the residential lots located on the western boundary.
Proposal
The applicant proposes to construct a 247 space car park on the 1.137ha site for the
use of the adjacent Holy Spirit College (refer to Attachment B – Proposal Plan). The
car park will be used by staff and students of the campus, which includes Emmanuel
Catholic Primary School and Emmanuel Kindergarten. The applicant has advised that
the existing parking area to the east of the school will continue to be used for drop-off
and pick-up activities. The existing parking area will be redeveloped in the future to
account for the construction of the missing portion of Baxter Drive.
The development includes the provision of a 2m wide landscape strip along the
Tamron Drive frontage of the site. Access to the car park is proposed from both a
left-in entry from Baxter Drive (via an existing access along the northern boundary of
the school), and a left-in/left out and right-out access from Tamron Drive. The
2,883m2 balance area of the site adjoining the residential development is proposed to
remain vacant.
The proposal plans show new car parking and road reserve arrangement on the Baxter
Drive frontage of the college, however these changes do not form part of this
development application.
Background
Emmanuel Catholic School established in 1983 and now includes Emmanuel
Kindergarten and Holy Spirit College, with classes from kindergarten to year 12.
Holy Spirit College has an enrolment of 811 students and 105 full-time equivalent
staff. The college has onsite facilities that can cater for up to 1050 students and 130
full-time equivalent staff. In 2017 there were 55 students of driving age attending
Holy Spirit College, which is predicted to rise by 85 to 140 students due to changes to
the state-wide enrolment age. Emmanuel Catholic Primary School and Emmanuel
Kindergarten has an enrolment of 585 and 44 students respectively and are not
planned to change from their current levels. The existing facilities on the campus are
approved and built to accommodate up to an additional 25 staff and 239 students
compared to the current numbers. Northview Primary School, located adjacent to the
college campus and accessed from Pioneer Street has an enrolment of 380 students.
The proposed car park site is located in the area approved as part of stage three (3) of
Belmore Estate. Belmore Estate was formerly cane growing land and was approved
for 102 residential lots over three (3) stages (Council file reference DA-2006-268).
Stages one (1), two (2) and part of three (3) of the residential development have been
completed and the subject site is the balance lot of the subdivision. As part of the
recently completed stage of the estate, the extension of Tamron Drive to the Baxter
Drive road reserve has been completed, however the road is not open to through
vehicle traffic at this time. The road is scheduled to be opened to through traffic
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49531
when the existing Holy Spirit College car park and set down area in Baxter Drive is
reconfigured and Council constructs the missing extension to Baxter Drive.
There is an acknowledged traffic parking issue, especially around peak drop-off and
pick-up times at Holy Spirit College (and almost every other school). Further, school
staff and students have been parking informally on Council land for a number of
years. As part of a previous application to expand the school (in 2005) the parking
issue was raised and solutions investigated. Of the options put forward, the provision
of a second entry and exit from the school parking area was seen as a long-term
solution to the traffic issue. The solution involved the provision of a road connection
through what is now Belmore Estate to facilitate the second access/exit point.
The redesign of Holy Spirits existing car parking and drop-off/pick-up area and the
relocation and extension of Baxter Drive has been the subject of lengthy discussions
between Council and the Diocese. Negotiations have been required around land
exchanges to facilitate the new road and alignment, as well as the redesign of the car
parking area. The land exchanges (including road opening and closure) are almost
completed and it is anticipated that the Baxter Drive extension and Holy Spirit
College car park redevelopment will occur in the 2018/2019 financial year and be
delivered as a combined project between the parties. Detailed design of the works is
currently underway.
In relation to the current application, the developer met with Mackay Regional
Council planning staff on 11th September 2017 to discuss the proposed development
and outline the reasons for the need for the new parking area. The developer was
advised that subject to the proposal meeting the relevant Planning Scheme codes and
undergoing public notification, the expansion of the school on to the subject site is
supportable under the Planning Scheme.
PLANNING SCHEME ASSESSMENT
The proposed development has been assessed against the Mackay Region Planning
Scheme and is considered to be generally consistent with the intent of the scheme.
Strategic Framework
The Mackay Regional Planning Scheme Strategic Framework encourages social
facilities and community services, including education services to be planned and
appropriately located to support population growth in urban areas. The proposal will
assist in consolidating community activities within the existing urban area, and
provides the potential to cater for future population growth in the catchment area.
The development is considered to be consistent with the Strategic Framework in the
Mackay Region Planning Scheme.
The application has been assessed against the following Planning Scheme codes and
overlays:
• Low Density Residential Zone Code
• Community Activities Code
• General Development Requirements Code
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49532
• Healthy Waters Code
• Flood and Coastal Hazards Overlay Code
• Regional Infrastructure Overlay Code
The proposal generally complies with the intent of the above Codes. The alternative
outcomes to those nominated in the Planning Scheme are discussed below:-
Overlays
Flood and Coastal Hazards Overlay Code
The subject site is within the Flood and Coastal Hazards Overlay Code. The
proposed development does not include any buildings or habitable rooms and
therefore complies with the code. The development will be required to be filled so
that the car park has a storm event immunity of Q5, and be free draining to the lawful
point of discharge. It will also be conditioned that any filling of the site does not
cause ponding of storm water on adjacent sites.
Regional Infrastructure Overlay Code
The subject site is within the Regional Infrastructure Overlay Code because the site is
proximate to the Port of Mackay branch railway line. The overlay seeks to avoid
sensitive land uses establishing proximate to railway infrastructure. While the
proposed land use is defined as an Education Establishment and is defined as a
sensitive land use, the car park itself is not sensitive to noise impacts and will
therefore not be impacted by the operation of the railway. In addition, an acoustic
fence has been constructed by the developer of Belmore Estate along the northern side
of the Tamron Drive road reserve to reduce noise impacts from the operation of the
railway. The proposed car park complies with the intent of the code.
Zone Code
Low Density Residential Zone Code
The subject site is located in the Low Density Residential Zone. The purpose of the
zone is to provide for:-
a) a variety of low density dwelling types, including dwelling houses; and
b) community uses and small-scale services, facilities and infrastructure, to
support local residents.
The purpose of the zone code encourages community uses that service the local
population. The proposed development is included in the community activities
defined activity group in the Planning Scheme, and it is considered that the proposed
car park will improve the operation of the existing school and provide for the planned
increase in student enrolments and staff at the school. This additional parking area
will also help rectify the informal use of Council land for car parking as currently
occurs. The proposed car park location is a logical expansion of the existing school
facilities and is in an area of Belmore Estate that ensures that the car park will not
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49533
detrimentally impact the residential character of the area. Therefore, the proposal is
considered to comply with the intent of the Low Density Residential Zone Code.
Use Codes
Community Activities Code
PO7
Development integrates with the amenity and character of the local area.
The applicant is proposing a 2m wide landscaping strip along the entire Tamron Drive
frontage of the car park, which meets the minimum 2m wide landscaping requirement
in the acceptable outcome in the code. A condition will be imposed requiring that the
2 m wide landscaping strip be extended along the Tamron Drive frontage of the
vacant balance area to create continuity of the streetscape between the car park and
vacant balance land. The developer will be required to submit a landscaping plan for
approval at the time of operational works application.
General Development Requirements Code
PO25
Non-residential development maintains the visual and general amenity of adjoining
residential areas.
The development will be conditioned to ensure that the existing 1.8m high screen
fence along the western boundary between the car park and the residential
development be maintained to protect the amenity of future residents of Belmore
Estate. The portion of the site that abuts the residential lots is the balance area of the
site for which the school has not indicated a future use. Any proposal to use this
balance area will require a material change of use application to be lodged and the
potential impact of the future use will be assessed at that time and appropriate
treatments conditioned to ensure the amenity of the residential lots is maintained.
PO37
Landscaping visually softens and lowers the glare and heat generated by extensive
areas of hardstand.
The development will be conditioned so that the car park is provided with 1 shade tree
per every 6 car parks in accordance with the acceptable outcome in the code.
ADOPTED INFRASTRUCTURE CHARGES RESOLUTION
Infrastructure charges will apply to the development in accordance with Council’s
Adopted Infrastructure Charges Resolution 2014, as this application was lodged prior
to the commencement of the new Charges Resolution in February 2018.
The site is the balance lot of Belmore Estate and any credit available for the existing
lawful use of the site has been utilised in the previous stages of Belmore Estate by the
developer. The proposal does not include any buildings and therefore infrastructure
charges will not be levied on an additional gross floor area basis.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49534
The proposed development of an Education Establishment on the site attracts a
stormwater infrastructure charge of $8.50 per impervious square metre. The proposed
impervious area of the site is 8487m2 (site area of 1.137 ha minus balance area of
2883m2). The 8487m2 x $8.50/impervious m2 = $72,139.50.
INFRASTRUCTURE CONSIDERATIONS
The site has been connected to water and sewer services as part of the previous
development of Belmore Estate.
The applicant has undertaken a traffic impact analysis and submitted the report with
the development application. The analysis found that:
• the proposed car park is capable of accommodating the master planned transport
demands (i.e. active travel, car parking, traffic and bus demands) associated
with the school,
• The proposed layout of the new car park is consistent with the dimensional
requirements as set out in Council’s Planning Scheme and relevant Australian
Standards, and
• The analysis of the development indicates that the vehicle access and external
intersections are generally expected to operate within acceptable limits.
The proposal plan shows the western access to the car park as being capable of
accommodating a heavy rigid vehicle or a bus. Tamron Drive is not a designated bus
route and any bus servicing the school will have adequate access to the bus set-down
area in Baxter Drive. The development will be conditioned to require that the access
be amended to a frequent use medium rigid vehicle to discourage busses from
travelling west along Tamron Drive from the car park. The 40km per hour school
zone will be extended to the western boundary of the site to provide a slow traffic
environment for students and motorists in the area.
A condition is recommended that restricts the use from commencing prior to the
Baxter Drive extension to Tamron Drive being made to ensure vehicles exiting the car
park will have the option of travelling either east or west to Baxter Drive or Pioneer
Street as soon as it is operational. Alternatively, if the school wishes to use the car
park prior to the connection being made, a temporary access from the car park to
Baxter Drive must be provided to facilitate vehicle movements to the east. It is highly
likely that the School will want to construct the new parking area before the
redevelopment of their existing parking area is undertaken to ensure that there is
parking available for staff and students during the construction phase.
REFERRAL AGENCIES
The application was referred to the Department of State Development, Manufacturing,
Infrastructure and Planning for the following triggers:
• Planning Regulation 2017 (10.9.4.1.1.1) – Material change of use for an
education establishment.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49535
• Planning Regulation 2017 (10.9.4.2.4.1) – State transport corridors and future
State transport corridors – material change of use within 25m of a State-
controlled road.
The Department has approved the use with no conditions (refer to Attachment C –
Referral Agency Response).
SUBMISSIONS
The application was publicly notified in accordance with the requirements of the
Planning Act 2016, and as a result of this process, two (2) individually prepared
written submissions and two (2) petition submissions (containing 83 and 28
signatures) were received.
The submissions received, expressed opposition to the proposal. The principle
concerns raised from the submissions are summarised and discussed below..
1. Direction of traffic exiting car park
Submitters Concerns
Residents of Belmore Estate who have signed the petition, strongly believe that
vehicles entering the car park should not be forced to exit the area through Belmore
Estate as this would cause significant traffic congestion and safety issues at the
Tamron Drive/Pioneer Street roundabout.
Applicant’s Response:
GTA traffic Consultants have confirmed that the proposed right turn egress from the
new carpark onto Tamron Drive can be achieved with some minor reconfiguration of
the original concept plan to provide adequate sight distance to and from the east in
accordance with Austroads requirements. It is noted that the modification to the
perimeter car parking spaces will be completed as part of the detailed design phase
once the Tamron Drive retention system and drainage arrangements are finalised.
With confirmation that this option can now be achieved, Catholic Education commit
to providing this change, being the right-hand egress from the new carpark onto
Tamron Drive. Catholic Education’s commitment is in the spirit of being fair and
reasonable and working through concerns raised to achieve a positive outcome for all
parties.
Officers Comments:
The revised traffic study submitted by the applicant showed that by providing a
right-turn option from the car park, vehicles turning left and travelling west along
Tamron Drive from the car park would reduce by more than 50%.
The inclusion of the right-turn egress is supported because it will decrease
congestion at the Tamron Drive/Pioneer Street intersection and addresses the
concerns raised by submitters.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49536
2. Road Hierarchy
Submitters Concerns
Although the traffic report defines Tamron Drive as a ‘minor collector’ road, the
Mackay Region Planning Scheme 2017 Road Hierarchy maps define it as a local
street-access’, as defined within the Planning Scheme Engineering Design
Guidelines is to provide ‘direct access to properties, pedestrian movements and local
cycle movements. If the proposed car park approval were to be approved in its
current state, with all vehicles being directed to exit the area via Tamron Drive, the
‘local street – access’ definition would no longer meet this criteria.
Applicant’s Response:
Nil.
Officers Comments:
The classification of Tamron Drive in the location that fronts the proposed car park
was not identified in Council’s 2017 Mackay Region Planning Scheme road
hierarchy, because it was not constructed at the time. The existing constructed
section was shown as an access street in the Scheme hierarchy however this is a
known error. The road hierarchy for this street will be amended to reflect it's minor
collector status as part of a pending Planning Scheme amendment.
The entire length of Tamron Drive was identified in the road hierarchy of Council’s
2006 Mackay City Planning Scheme as a future major collector road connecting
Pioneer Street and Baxter Drive. The connection has been viewed as an important
connection to provide an additional road connection between Baxter Drive and
Pioneer Street. The conditions of the approval for Belmore Estate nominate Tamron
Drive as a designated minor collector street and the approved plan of development
shows the ultimate connection of Tamron Drive to Baxter Drive. A minor collector
road is of a sufficient design to cater for the expected future traffic. It should be
noted that Tamron Drive is not a designated bus route.
3. Tamron Drive connection to Baxter Drive
Submitters Concerns
The traffic study conducted by GTA Consultants shows that the existing vehicle
demand on Tamron Drive is 44 vehicles in the AM peak and 41 vehicles in the PM
peak. The master plan vehicle demand then increases to a staggering 299 vehicles in
the AM peak and 445 in the PM peak. Of course this would be taking into account
the Tamron Drive extension, which will be open to the public in the coming months,
however the proposed car park would only negatively contribute to this influx by
giving vehicles no other option but to exit the car park via Tamron Drive. Many
residents in Belmore Estate chose to purchase homes within the estate due to its
quiet surroundings and low levels of traffic. Whilst the Tamron Drive extension has
been approved to occur since the beginning of the estate, the residents would like to
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49537
ensure vehicles are not encouraged to utilise Tamron Drive as a thoroughfare or the
culs-de-sac in in the estate as U-turn facilities.
Applicant’s Response:
The proposed carpark associated with Tamron Drive is to be designated for staff and
students, which will be long term parking. The designated users exiting this carpark
will not be concentrated to the PM peak. Given the nature of the users, 75% of staff
will exit this carpark outside the identified peak periods, therefore, avoiding or not
contributing to the existing issues highlighted with the Tamron Drive and the Pioneer
Street roundabout.
Officers Comments:
The applicant’s traffic impact assessment expects 215 movements during the PM
peak hour to travel west along Tamron Drive when it is connected to Baxter Drive.
It is important to note that this connection, and the resulting traffic movements, will
occur regardless of whether this development application is approved because the
connection will occur with the reconfiguration of the Baxter Drive car park. The
traffic assessment has shown that Tamron Drive is capable of accommodating this
traffic.
4. Safety
Submitters Concerns:
Tamron Drive does not have designated roadside carparking, therefore vehicles
often park on the kerbside, restricting the road width to less than two lanes and
causing traffic to stop while oncoming traffic passes. This is evidenced on a daily
basis during the week and during school events at the entrance to the estate (Tamron
Drive/Pioneer Street) where vehicles attending Northview Primary School
dangerously park on the kerbside. Not only do these vehicles restrict the road to less
than two lanes, they also prevent traffic from having clear vision of oncoming traffic
and persons entering/exiting the parked vehicles around the bend.
This is already a significant safety risk and the residents of Belmore Estate are
deeply concerned that if the proposal were to proceed in its current state and
increase the volume of traffic in this location, the potential for an accident to occur
or someone be injured would also increase significantly.
Applicant’s Response:
Issues identified associated with the existing use of Tamron Drive, on street parking,
road width design and congestion to Pioneer Street roundabout are not the
responsibility of Catholic Education. This is existing infrastructure approved under a
separate development approval.
A review of the Queensland Government Crash Data from Queensland Roads for the
last available five-year period suggests that there is no existing crash history or
pattern along Tamron Drive or at the Pioneer Street/Tamron Drive intersection. The
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49538
new car park and associated vehicle access arrangements are not expected to create
safety concerns.
Officers Comments:
The development will be conditioned to extend the 40km per hour school zone
signage to reduce vehicle speeds through the area during school drop off and pick up
times. The school will be extended west along Tamron Drive in line with the
western boundary of the site.
For vehicles to be parked ‘legally’, all wheels are required to be on the road. If cars
observed by submitters are parked on the Tamron Drive footpath at the western
entrance to Belmore Estate, the cars are illegally parked. Tamron Drive is built as a
minor collector road, which allows vehicles to be parked on both sides of the road. It
is accepted that if cars are parked on both sides of Tamron Drive, the travel lane
available for vehicles will narrow, however it is considered that this will assist in
calming the traffic flow in the area.
In addition, as a result of receiving these submissions Council’s Technical Services
have undertaken to investigate if line marking and signage can be installed along the
western entrance to Belmore Estate along the bend in Tamron Drive to restrict cars
being parked in this location during school pickup/drop off times to provide better
visibility at the intersection.
These measures will improve the safety of pedestrians and motorists using the
Tamron Drive/Pioneer Street intersection, however it is important to note that these
traffic conditions currently exist and are not a result of this development application.
A major contributing factor to these issues at the Pioneer Street/Tamron Drive
intersection is that Northview Primary School has insufficient onsite car
parking/drop-off/pick-up area and it would be unreasonable to impose conditions
requiring this developer to undertake any works to improve the current situation.
5. Removal of left-turn lane from new set-down area on Baxter Drive
Submitters Concerns:
Consideration should be made to remove the left-turn highlighted in red on Figure 3
(refer to Attachment D – Submitters Proposed Amendments (shown in red box on
plan)) so vehicles must turn right onto Baxter Drive to exit the area. The potential
for congestion at this intersection would be minimal as Tamron Drive is not a major
thoroughfare road, therefore vehicles should not need to wait long before safely
crossing into the opposite lane.
Applicant’s Response:
The requested left-turn lane removal at the egress of the Holy Spirit College set-
down facility is not considered to be appropriate from a transport planning and traffic
engineering perspective. Such an amendment could be expected to reduce the
flexibility and robustness of the vehicles access arrangements, while also increasing
congestion within the set-down facility and the external road network. The left-turn
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49539
restriction is also very difficult to implement from a design perspective. As such,
this amendment has not been considered in the revised functional layout plan.
Officers Comments:
For the reasons outlined by the applicant above, it is recommended that the left-turn
on to Baxter Drive from the Baxter Drive car park remain in place. This left-turn is
part of the Baxter Drive car park upgrade and does not form part of this development
application.
6. Crispin Drive
Submitters Concerns:
There is a gate on the western side of the school which goes onto a Mackay Regional
Council easement (refer to Attachment E - Submitters Concerns - Crispin Drive).
There is almost 100 plus cars in this very small and narrow street which is very
dangerous. I fear that a student is going to be run over as it is not a designated
school zone with pickup/drop off facilities.
Applicant’s Response:
The traffic Impact Assessment did not consider pick-up activity in the vicinity of
Tolcher Street and Crispin Drive.
No amendments are required and this is also considered to be beyond the scope of
the current application as the application only related to the new Holy Spirit College
car park.
Officers Comments:
This complaint is not related to this development and has been passed on to Mackay
Police for further investigation.
The submissions have not raised issues that would warrant refusal of the application.
The major issue (provision of right turn out of the car park) has been agreed to by the
applicant and will be required as part of the construction of the car park.
RESOURCES IMPLICATIONS
There are no resource implications for Council as a result of this recommendation,
except if either the applicant or submitters appeal Councils decision or conditions of
approval.
RISK MANAGEMENT IMPLICATIONS
Nil.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49540
CONSULTATION
External
The proposal was publicly notified as required by the Planning Act 2016. Details of
the submissions received are outlined earlier in this report.
Internal
The application was discussed with representatives from various Departments at the
Development Enquiries Meeting on 27 February 2018.
CONCLUSION
The proposal to provide 247 additional car parking spaces for the Holy Spirit College
will help alleviate traffic congestion at the existing school car parking area in Baxter
Drive and will assist in meeting the high demand for car parking spaces at the
campus. The expansion of the school on to the subject site which adjoins the campus,
is a logical expansion of the school’s facilities. The development will be provided
with landscaping along Tamron Drive and within the car park, and a screen fence will
be maintained between the development and adjoining residences. The development
will therefore not detrimentally impact upon the residential character of the area.
The connection of Tamron Drive to Baxter Drive and the resulting increase in traffic
through the Belmore Estate has been planned and approved since at least 2006. It is
recognised that the connection will represent an increase in the traffic through the
estate, particularly during school drop off and pick up times. However, it must be
noted that this road connection is not the subject of this development application and
will occur in any case under previously approved development applications which
complied with Council’s Planning Scheme. The developers have agreed to provide a
right-turn egress from the car park to encourage motorists to exit the car park via
Baxter Drive rather than travelling west to the Tamron Drive/Pioneer Street
roundabout, which is congested during school drop-off/pick-up times. The
applicant’s traffic impact assessment has demonstrated that the inclusion of the right-
turn exit will decrease vehicles from the car park travelling west by more than 50%.
The application is recommended for approval subject to conditions because it meets
the intent of the Mackay Region Planning Scheme.
PUBLIC PARTICIPATION
The Mayor welcomed the members of the public in the Public Gallery who had
registered to speak to this item on the agenda today and provided an explanation on
the procedure of public participation.
Fran Limmage
Ms Limmage advised she is a resident of Belmore Estate and is concerned with the
traffic flow that will be created on Tamron Drive because of this application. The
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49541
roundabout on Tamron Drive adjacent to the pickup/drop off area at Northview State
School is quite often blocked with cars wanting to enter this pickup/drop off area.
Currently there is congestion outside the Holy Spirit College along Baxter Drive but
has multiple exist off Baxter Drive. If the traffic is to travel along Tamron Drive
there is only one exit at the Pioneer Street roundabout which is already very
congested. She would like to Council to consider an exit that would allow vehicles to
travel back along Baxter Drive. The only access planned is via Tamron Drive and
currently there is no access to Tamron Drive from Baxter Drive.
Leslie Connolly
Ms Connolly advised she has the same concerns as Ms Limmage and when you try to
navigate through the Pioneer Street roundabout in the morning and afternoons the
vehicles from the stop, drop, go area block this. If there was an emergency the
emergency vehicles would not be able to transverse through the roundabout as it is a
gridlock. With the proposed increase in traffic from this application it will make the
situation even worse.
Justin Peel
Mr Peel advised he was attending today on behalf of the Diocese of Rockhampton for
Catholic Education (Diocese) in the event that there were some submitters that wished
to raise any concerns. The Diocese takes its position in the community very seriously
and considers the submissions seriously as part of the planning approval process. The
Diocese have invested a significant amount of money in purchasing the land for
carparking with the intention to improve the current traffic situation surrounding the
Holy Spirit College. Holy Spirit College raised traffic issues in 2005 and the issues
where investigated with Council's Technical Services department and the solutions
were to extend Tamron Drive, and Tamron Drive was approved for extension and
connection to Baxter Drive as part of a court order decision for Belmore Estate Stage
Three, but that decision encompassed stages one, two and three. As part of the
submission process the Diocese addressed the access and some of the points raised by
residents here today, a right turn egress was added to the carparking configuration to
allow vehicles to move east back on Tamron Drive to Baxter Drive and exit that way.
The Tamron Drive connection is an unrelated issue to this application, the traffic that
would have used Tamron Drive, regardless of the application, and would have entered
it anyway. The carpark will provide additional staff parking to improve the overall
traffic conditions in the area.
The Mayor acknowledged the residents for their attendance at today's Council
Meeting and thanked them for their input on this agenda item.
The Chief Executive Officer (CEO) advised the original Development Application
(DA) for the estate was approved in 2005 and this showed the road connecting
through between Pioneer Street and Baxter Drive as part of the original DA.
Cr May queried Council's intention in regarding the Baxter Drive to Tamron Drive
connection and the work required to be committed to enable this to occur.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49542
The Acting Director Development Services (A/DDS) advised there is an access from
Baxter Drive proposed into the carpark as part of this application and once the carpark
in under construction Council will need to consider the existing carpark and the
connection back to Baxter Drive. There is a layout proposed and will be finalised
once the approval is received and under construction.
Cr May queried where this might sit in Council's capital budget.
The CEO advised this project was currently listed to be considered in the 2018/19
budget discussions.
Officer's Recommendation
A. THAT Council approve the application for an Education Establishment
(ancillary car park) located at Lot 902 Mackay- Bucasia Road, Mt
Pleasant, described as Lot 902 on SP259166, subject to the following
conditions:
1. Plan of Development
The approved Educational Establishment (ancillary car park)
development must be completed and maintained generally in
accordance with the Plan of Development (identified in the Table
below) and supporting documentation which forms part of this
application, except as otherwise specified by any condition of this
approval.
Drawing Number Issue Prepared by Date
Q137920-04-03 P3 GTA Consultants 04/12/2017
2. Amended Plans Required
Prior to the lodgement of the operational works application the
approved plans of development must be amended to comply with
the following matters:
a) Landscaping in accordance with condition 11;
b) Access changes in accordance with condition 17;
3. Compliance with Conditions
All conditions must be complied with prior to the commencement of
the use on the subject site, unless specified in an individual
condition.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49543
4. Compliance with Council Standards
All design and construction for the development must be in
accordance with Council’s Policies, Engineering Design Guidelines,
Standard Drawings and Standard Construction Specifications.
5. Maintenance of Development
The approved development (including landscaping, car parking,
driveways and other external spaces) must be maintained in
accordance with the approved drawing(s) and/or documents, and
any relevant Council engineering or other approval required by the
conditions.
6. Conflict between plans and written conditions
Where a discrepancy or conflict exists between the written
condition(s) of the approval and the approved plans, the
requirements of the written condition(s) will prevail.
7. Notice of Intention to Commence the Use
Prior to the commencement of the use on the site, written notice
must be given to Council that the use (development and / or works)
fully complies with the decision notice issued in respect of the use
(please see attached notice for your completion).
8. Damage
The developer is responsible for the repair of any damage that is
caused to Council’s infrastructure as a result of the construction
works associated with the proposed development. The developer
must make any damage safe and then notify Council immediately.
Council will make the decision as to who will carry out the
rectification works and the timing for the completion of those
works.
9. Car Park Design
The car parking area must be constructed, sealed, line marked and
drained. The car parking must be designed in accordance with
AS/NZS2890.1:2004 Parking facilities Part 1: Off-street car parking
and AS/NZS2890.6:2009 Parking facilities Part 6: Off-street
parking for people with disabilities.
The car park must be lit in accordance with AS/NZS1680.2.1:2008
Interior and workplace lighting and AS/NZS1158.3.1:2005 Lighting
for roads and public spaces.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49544
Any car park lighting and other outdoor lighting, must comply with
AS 4282-1997 Control of the obtrusive effects of outdoor lighting.
Details of the car park design must be submitted for assessment as
part of the Operational Works application.
10. Car Park Kerbing
a) A 125mm high vertical concrete kerb must be provided
adjacent to the car parking area.
b) Car parking bays abutting footpaths and landscaping must be
provided with wheel stops.
11. Landscaping
Onsite landscaping must be provided in accordance with the
following:
a) A minimum 2m wide landscaping strip, with species suitable
for sight requirements, must be provided along the full
Tamron Drive frontage of the site, including in front of the
balance land.
b) shade trees must be provided in the car park area at a rate of 1
per 6 car parking spaces.
12. Landscape Plan Required
A detailed site and footpath landscaping plan must be prepared by a
qualified Landscape Designer and must be submitted with the
Operational Works application. The plan must show for all areas
identified on the approved plan of development the following:
a) Landscape specification of sufficient detail so that landscape
works are to be carried out;
b) Plant schedule detailing number of plants, species, pot size
and height at planting;
c) Details of soil and mulch types, including depths, areas of turf,
garden edges and paving finishes;
d) the details of the irrigation system needed at least for
establishment and backflow prevention device.
13. Completion of Landscaping
All of the landscaping works shown on the approved plan must be
completed before the commencement of the use on the site.
14. Use of Balance Area
The balance area has no approved use and is to be kept vacant.
Consequently, the balance area is not to form any part of the
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49545
operation of the developed area of the site unless approved by
Council via a future Material Change of Use application.
15. Visual Screen Fence
The existing 1.8m high visual screen fence between the site and the
adjoining residential properties to the west must be maintained. The
total cost of maintaining this fencing is to be met by the Developer.
16. Fencing
Any security fencing along the Tamron Drive frontage of the site
must be constructed of a visually appealing material other than plain
chain wire fencing. Minimum acceptable material is
coloured/powder coated chain wire fencing.
If fencing along the Tamron Drive frontage is proposed, the details
are to be included on the Landscaping Plan to be submitted with the
Operational Works application.
17. Car Park Access
Access to Tamron Street must be constructed generally accordance
with the GTA Consultants layout on drawing Q137920-04-03
rev.P3 and to have a minimum Asphalt wearing surface. Car park
Left turn exit lane must be restricted to a frequently use maximum
vehicle of a MRV; Tamron Drive is not an assigned bus route.
Details of the car park access are to be provided in the Operational
Works application.
18. Car Park Stormwater Immunity
The car park must have a Stormwater Immunity of Q5. The design
is to be included as part of the Operational Works application.
19. Speed Control in Car Parking Area
The driveway serving the car park, must feature a physical means of
speed control at the exit point near the front alignment.
20. External Road Signs
Provide a school zone combined sign R4-Q01A, R4-Q01B and R4-
Q01C on Tamron Drive at the western property boundary of Lot
902 on SP259166.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49546
21. Parking Signs and Pavement Markings
A sign/signs and pavement markings must be provided directing
drivers to the car parking.
22. Tamron Drive – Baxter Drive Connection
The car park use must not commence prior to Baxter Drive extended
to connect with Tamron Drive and being opened for through
vehicular traffic.
Alternatively, provide an internal temporary sealed connection to
Baxter Drive from the newly constructed Car Park. The temporary
connection is to be maintained for the full construction period of
Baxter Drive extension and the Baxter Drive car park fronting the
school. If a temporary connection is proposed, the details of its
location and formation must be included in the Operational Works
application.
23. Stormwater Drainage
Stormwater from the site shall be collected within the property
boundaries and discharged via an underground system to Council’s
stormwater system. The stormwater discharge points are the 3 stubs
in the stormwater pits located along Tamron Drive.
24. Ponding and Diversion of Stormwater
Ponding of stormwater resulting from the development must not
occur on adjacent sites and stormwater formerly flowing onto the
site must not be diverted onto other sites. The site shall be graded
so that it is free draining.
25. On-Site Detention
An assessment is to be undertaken of the developed (Carpark and
open space) stormwater flows against existing intended residential
use to determine if any on-site detention is required. If on-site
detention is required, a detailed design of the on-site detention
system must be submitted as part of the Operational Works
application.
A note with regards to the OSD maintenance requirements of the
development will be placed on Council’s Rates Database.
26. Site Based Stormwater Management Plan – High Risk
Council’s Stormwater Quality Risk Classification has classified this
development as ‘High Risk’ as defined Mackay City Council’s
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49547
Engineering Design Guidelines - Soil and Water Quality
Management – Planning Scheme Policy No.15.07.
The SBSMP must be submitted to Council for approval at the time
of submission of the Operational Works application. Assessment of
other components of the Operational Works Application cannot be
finalised until the SBSMP is approved first. If provided, Stormwater
Quality Improvement Devices must be located within the site and
must be of a private nature.
An assessment is to be undertaken of the developed (Carpark and
open space) MUSIC Modelling against existing intended residential
use to determine if additional stormwater treatment is required.
If additional stormwater treatment is required, the applicant must
either construct the additional treatment required or alternatively the
applicant may elect to make a contribution to Council towards the
regional treatment of stormwater quality under Council Policy
‘Voluntary Mechanism for Stormwater Quality Management. The
contribution must be agreed upon between the developer and
Council at the time of payment of the contribution, based on current
rates or policy as adopted by Council.
27. Kerb and Channelling and Underground Drainage
Kerb and channelling and underground drainage must be provided
in accordance with plans approved by Council. The system is to be
designed in accordance with Council’s Engineering Design
Guidelines.
B. THAT the applicant be provided with the following Assessment Manager
Advice:
1. Infrastructure Charges Notice
Pursuant to the Planning Act 2016 and the State Planning
Regulatory Provision (adopted charges) an Infrastructure Charges
Notice relates to this Development Permit, and accompanies this
notice.
2. Local Laws
The approved development must also comply with Council’s current
Local Laws under the Local Government Act 2009.
3. Hours of Work
It is the applicant/owner’s responsibility to ensure compliance with
Section 440R of the Environmental Protection Act 1994, which
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49548
prohibits any construction, building and earthworks activities likely
to cause audible noise (including the entry and departure of heavy
vehicles) between the hours of 6:30pm and 6:30am from Monday to
Saturday and at all times on Sundays or Public Holidays.
4. Dust Control
It is the applicant/owner’s responsibility to ensure compliance with
Section 319 General Environmental Duty of the Environmental
Protection Act 1994, which prohibits unlawful environmental
nuisance caused by dust, ash, fumes, light, odour or smoke beyond
the boundaries of the property during all stages of the development
including earthworks and construction.
5. Sedimentation Control
It is the applicant/owner’s responsibility to ensure compliance with
Chapter 8, Part 3C of the Environmental Protection Act 1994 to
prevent soil erosion and contamination of the stormwater drainage
system and waterways.
6. Noise During Construction and Noise in General
It is the applicant/owner’s responsibility to ensure compliance with
Chapter 8, Part 3B of the Environmental Protection Act 1994.
7. General Safety of Public During Construction
It is the principal contractor’s responsibility to ensure compliance
with Section 19 (2) Work Health and Safety Act 2011. Section 19
(2) states that a person conducting a business or undertaking must
ensure that the health and safety of other persons is not put at risk
from work carried out as part of the conduct of the business or
undertaking.
It is the responsibility of the person in control of the workplace to
ensure compliance with Section 20 (2) of the Work Health and
Safety Act 2011. Sections 20 (2) states that the person in control of
the workplace is obliged to ensure that the means of entering and
exiting the workplace and anything arising from the workplace are
without risks to the health and safety of any person.
8. Contaminated Land
It is strictly the applicant/owner’s responsibility to source
information regarding contaminated land from the Department of
Environment and Resource Management, Contaminated Land
Section as Council has not conducted detailed studies and does not
hold detailed information pertaining to contaminated land.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49549
9. Acid Sulphate Soils
If the proposed works trigger the State Planning Policy 2017 in
relation to Acid Sulfate Soils, a Site Based Acid Sulphate Soil
Management Plan must be prepared by a suitably qualified
professional and submitted to Council for approval as part of the
Operational Works application.
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Casey Seconded Cr May
Cr Casey advised he was on Council in 2005 when the original proposal for the estate
was approved and it was planned as a three stage development and the link from
Tamron Drive to Baxter Drive was always included in the proposal. He understands
the residents in Belmore Estate concerns but Council has no control over the
intersection at Pioneer Street, and this has nothing to do in relation to this application.
Cr Bonaventura advised he have visited the school many times during his six (6) years
on Council and the same issue is raised in relation to traffic congestion. The ability
for some of this traffic to come along Tamron Drive and exit via Baxter Street is an
advantage.
CARRIED
11.6 MATERIAL CHANGE OF USE - EXTRACTIVE INDUSTRY
(EXPANSION) - LOT 106 BOOMERANG ROAD AND LOT 696
BUSSEYS ROAD, PALMYRA QLD 4751 - DA-2017-122
Application Number: DA-2017-122
Date Received: 23 November 2017
Action Officer: Darryl Bibay
Applicant’s Details: Summit Construction Materials Pty Ltd
c/- Pointglen Developments
PO Box 8158s
MOUNT PLEASANT QLD 4740
Proposal: Extractive Industry (Expansion)
Site Address: Lot 106 Boomerang Road and Lot 696
Busseys Road, PALMYRA QLD 4751
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49550
Property Description: Lot 106 on SP262688 and Lot 696 on
K124900
Owner’s Details: Monique A Bussey-Jensen
Area: Lot 106 is 18.27ha
Lot 696 is 145.99ha
Planning Scheme: Mackay Region Planning Scheme 2017
Version 1.1
Planning Scheme Designations::
Zone:
Rural
Assessment Level: Impact
Submissions: Ten (10) submissions
- Nine (9) properly made
- One (1) not properly made
Referral Agencies: Concurrency- Department of Infrastructure,
Local Government and Planning
Attachments: Attachment A:
Attachment B:
Attachment C:
Locality Plan
Proposal Plan
Referral Agency Response
Recommendation: Approved Subject to Conditions
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49551
ASSESSMENT OF APPLICATION
Purpose
The Material Change of Use application is for Extractive Industry – Expansion at Lot
106 Boomerang Road and Lot 696 Busseys Road, PALMYRA QLD 4751. The
application is seeking approval for extraction of up to 1,000,000 tonnes of material
per year from the subject sites, which currently have approval for extraction of up to
100,000 tonnes per year. Extractive Industry in the rural zone triggers an impact
assessable application requiring the application to be publicly notified.
The application received nine properly made submissions and one not properly made,
all objecting to the proposal. The submissions have not raised any grounds that cannot
be appropriately conditioned.
The application is recommended for approval subject to conditions.
Subject Site and Surrounds
The subject sites are located at Lot 696 Busseys Road and Lot 106 Boomerang Road
Palmyra QLD 4751 described as Lot 106 on SP262688 and Lot 696 on K124900
(refer Attachment A – Locality Plans). The sites are zoned Rural and are
approximately 14km south west of the Mackay CBD and are strategically located near
upcoming large road infrastructure projects. The existing use of the Lot 106 is an
approved quarry. Lot 696 is generally vacant, though covered in vegetation with a
number of vehicle tracks traversing the property. Lot 696 also have approval for
extractive industry however operations have not commenced on this site.
The site is surrounded by rural properties and Extractive Industry uses. The nearest
rural residence is located 180m from the nearest subject lot boundary. The owner of
this residence is also the owner of the proposed quarry lots and has provided consent
to this application.
Background
On 20 October 2006 a Development Application was lodged for an Extractive
Industry over 3 lots for 3 separate quarry sites (DA-2006-386). The sites included the
two properties which are the subject of this application. The extractive industry was
proposed to be broken into stages with each quarry being completed prior to starting
the next. The application triggered referral to Department of Natural Resources and
Water, Department of Main Roads and the Environment Protection Agency. All three
concurrence agencies approved the development subject to conditions. The
application required impact assessment and there was one submission and a petition
(signed by 24 individuals affecting approximately 13 properties). Issues raised by the
submitters included traffic, amenity and road upgrades.
The Development Application was taken to Council’s Ordinary meeting on the 22 of
August 2007 for a decision with a recommendation that the development be approved
in part. The recommendation was to approve Quarry 1 (Lot 106) and Quarry 2 (Lot
696) but to refuse Quarry 3. The officer’s report concluded that Quarry 3 did not have
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49552
access from a sealed road and the proposal to commence Quarry 3 in 10 years’ time
was too long a period between the decision and commencement. The officer’s
recommendation was supported by Council and a Development Permit for Quarry 1
and Quarry 2 was issued.
The use commenced with the applicant extracting from Quarry 1 located on Lot 106.
The extraction for Quarry 1 has recently recommenced; however, no excavation
activity has occurred at the site of Quarry 2.
Pre-lodgement Advice
The applicant sought pre-lodgement advice from Mackay Regional Council on 30
August 2017. Council advised of the support for a Minor Change Application for
temporary increase in extraction and screening tonnage because it was considered the
changes to the existing Development Permit are minor in nature. Subsequent advice
from the Department of Infrastructure Local Government and Planning (DILGP)
indicated that the expansion constituted a new use and a new Material Change of Use
Development Permit is required for the proposed use.
Proposal
The applicant, Summit Construction Materials Pty Ltd, seeks development approval
for the extension of an existing quarry previously approved by Council on the subject
properties. The Busseys Road quarry currently operates in accordance with the
existing approval, DA-2006-386 and Environmental Authority EPPPR00896613 to
allow extraction and screening of materials up to 100,000t/year.
Approval is now sought to increase the permitted tonnage of materials extracted and
screened from the existing quarry to a maximum of 1,000,000 tonnes per year in line
with the Environmental Authority thresholds. This proposed increase will support
existing and future demand from the quarry including upcoming significant State
infrastructure projects, being the Mackay Ring Road Stage 1, and the Bowen Basin
Service Link (Walkerston Bypass Road).
This application seeks permission to extract without staging limitations, which is an
existing condition of DA-2006-386, specifically condition 9.
Condition 9
The proposed quarry will be staged in the following way:
a) Quarry 1 (Lot 676 on K124900) must cease a maximum of 5 years
from the date of commencement. Within 12 months of Quarry 1
ceasing operation, all rehabilitation works must be completed.
b) Quarry 2 must not commence until Quarry 1 has ceased. Once
commenced the use of Quarry 2 must cease a maximum of 5 years
after commencement. Within 12 months of Quarry 2 ceasing
operation, all rehabilitation works must be completed.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49553
The applicant has requested to be able to extract from Quarry 1 and Quarry 2 at the
same time because different material is available from each site, therefore the operator
would be able to supply two market segments simultaneously. There is no discussion
of this staging condition in the previous officer’s report and there does not appear to
be any amenity reason why the quarry could not operate from both pits at the same
time.
Essentially this application will supersede the approval granted under DA-2006-386
as it will approve a greater extraction amount and permit operation of both quarry
sites simultaneously.
The application also seeks to clear a section of vegetation located on site, mapped as
Category B on the regulated vegetation and Endangered Regional Ecosystems, and
outside of the current vegetation clearing approvals. It is proposed that an additional
2ha of regulated vegetation be cleared in accordance with the Vegetation
Management Plan. Assessment of the site for operational sustainability and safety has
identified the requirement and advantage to clear the identified 2ha. It is considered
that clearing this area of vegetation cannot be reasonably avoided, as this portion of
regulated vegetation is located on the high point of the proposed extraction zone.
Quarrying around high points is not practical, efficient and has obvious safety issues.
Built Form
Site offices and site facilities, plant laydown and storage and parking area are
proposed on Lot 106 and laydown, storage and maintenance facilities are proposed on
Lot 696 (refer to Attachment B – Proposal Plans).
Access, Egress, Parking and Traffic Impact Assessment
The proposed development does not propose to change existing approved access or
haulage routes from that approved under DA-2006-386, other than the construction of
an access into Lot 696 and an access between to the two sites. Constructed
improvements have previously been made as part of the existing quarry approvals and
include ancillary quarry structures and internal access.
Access to the site is via Boomerang Road to Bells Road. Road improvements were
undertaken in accordance with DA 2006-386. In particular:
• The existing intersection of Bells Road and Boomerang Road was upgraded to a
sealed standard; and
• Boomerang Road was upgraded to a sealed standard from the existing grid.
• Bells Road was upgraded (where necessary) between the intersection of
Homebush-Walkerston Road and the Intersection of Boomerang Road / Bells
Road.
Employees and visitors to the site will be able to park in the vicinity of the
administration building without risk of damage to vehicles.
Existing Plant and Equipment
Major plant and equipment used, or permitted to be used, on site generally includes
(but not limited to):
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49554
• Shipping container for on-site ‘office’ including workshop supplies;
• Portaloo facility, serviced by a licensed contractor who will lawfully dispose of
the effluent;
• Crushers / screener plants;
• Low loader and Service Trailers;
• Bulldozers;
• Excavators;
• Generators;
• Electric Compressor; and
• Off-road Haulage Trucks.
Hours of Operation
Hours of extraction and processing are 6 am to 6 pm Monday to Saturday, excluding
public holidays.
MACKAY ISAAC WHITSUNDAY REGIONAL PLAN
The subject site is located outside of the regional plan Urban Footprint and within the
Regional Landscape and Rural Production area. The proposal is a consistent use in
the Rural Production area.
PLANNING SCHEME ASSESSMENT
The proposed development has been assessed against Council’s Mackay Region
Planning Scheme 2017 and is considered generally consistent with the intent of the
Scheme.
The application has been assessed against the strategic framework and the following
codes.
• Rural Zone Code
• Extractive Industry Code
• General Development Requirements Code
• Agricultural Land Overlay Code
• Bushfire Hazard Overlay Code
• Biodiversity Overlay Code
• Landscape Character & Image Corridors Overlay Code
• Landslide Hazard Overlay Code
Strategic Framework
The proposed extension to an existing quarry at Busseys Road is considered
consistent with the Strategic Framework of the Mackay Region Planning Scheme
2017. Notwithstanding the existing approved quarry at the subject site, the proposal
specifically aligns with the Strategic Framework.
The proposal is appropriate development which will facilitate supply of materials
required for planned regional and local transport infrastructure upgrades. The existing
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49555
quarry is appropriately located adjacent to identified quarry resources, and will ensure
the regions environmental, economic, and social vision is supported and enhanced.
• Natural Resource Management
3.6.4 Element – Extractive resources
Protecting extractive resources in the region
1) Key resource areas are protected from encroachment by
incompatible development.
2) The impacts of hard rock extractive industries, such as drilling,
blasting and crushing are mitigated to retain the amenity of nearby
properties.
3) Transportation and haulage routes associated with extractive
resources are protected.
The subject site is more than 50m away from the residential area and is buffered
with vegetation from the sensitive uses from impacts of extractive resource
areas and high impact activities. Haulage routes have been conditioned by
DILGP.
• Strong Economy –
3.9.7 Element - Extractive resource industries and high impact activities
Supporting extractive resources and high impact activities
1) The economic viability and function of extractive industries is
protected.
2) Key resource areas and high impact activity areas are buffered from
sensitive uses.
3) The haulage routes of extractive industries are connected to the
appropriate road hierarchy and provide buffers along such routes to
mitigate impacts on sensitive uses.
4) The health, wellbeing, amenity and safety of communities are
protected from the impacts of air, noise and odour emissions, and
from the impacts of hazardous materials.
The diversity of economic activities is supported through appropriate land uses,
minimising land use conflicts, protection from incompatible development and
protecting economic infrastructure. The extractive industries are supported uses
within the Rural Zone. It is recognized that extraction must be carefully managed
to ensure there are no detrimental impacts to any nearby sensitive land uses,
downstream properties or existing agricultural uses through the impact on
amenity or dispersal of hazardous material.
The extractive industry operations provide construction materials to the
community which support the infrastructure necessary to maintain strong social
structure.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49556
The development and, in this case, expansion of extractive industries is supported by
the Strategic Framework and Scheme as a whole as these materials are acknowledged
as valuable resources for the region. When impacts from the proposed extraction
activities can be minimized or removed, extractive industries are supported by the
Scheme.
Overlays
The subject site is affected by the following Overlays:
• Agricultural Land Overlay
• Bushfire Hazard Overlay
• Biodiversity Overlay
• Landscape Character & Image Corridors Overlay
• Landslide Hazard Overlay
An assessment against the Overlays follows:
• Agricultural Land Overlay Code
“The purpose of the code will be achieved through the following overall
outcomes:
a) development that fragments, alienates or diminishes the productive
capacity of agricultural land for agricultural purposes is avoided; and
b) agricultural activities on agricultural land is protected and promoted;
and
c) the full productive capacity of agricultural land for agricultural purposes
is not compromised by the location of sensitive land uses that will prevent
or constrain current or future farming operations.”
A portion of Lot 696 is mapped as agricultural land class A and B in the Mackay
Region Planning Scheme. However, the current use of the property has been for
grazing and there is no evidence of cane production on the property in recent history.
The mapped agricultural land will be removed from potential agricultural production
for the duration of the quarrying activities but will be required to be rehabilitated at
the cessation of quarrying. At this time the land should be once again suitable for
grazing.
It is considered that there is a general non-compliance with the Code due to the loss of
agricultural land from potential production during the quarrying activities. It would
be potentially possible to restrict the quarrying activities from the agricultural land;
however, this would not seem practical to protect an isolated portion of the site for
agricultural use, when the majority of the site that is not regulated vegetation will be
quarried. It is considered appropriate to approve the proposed use on the mapped
agricultural land.
• Bushfire Hazard Overlay Code
“The purpose of the code will be achieved through the following overall
outcomes:
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49557
(a) development in bushfire hazard areas is located and designed so that:
(i) damage from bushfire events is minimised; and
(ii) it avoids areas with a very high, high and medium risk bushfire
hazard; and
(iii) accessibility and equipment is provided for fire fighting vehicles; and
(iv) safe evacuation during bushfire events can be facilitated;”
The subject site is mapped Medium Bushfire Risk in the Mackay Region Planning
Scheme, generally because Lot 696 is heavily vegetated.
The proposed plan of development on Lot 106 shows proposed offices and site
facilities, plant laydown and storage and parking area (Drawing No 0288-C02 rev B)
and on Lot 696 laydown, storage and maintenance facilities (Drawing No 0288-C01
rev B). The applicant has not addressed the Bushfire Hazard Overlay Code in their
Planning Assessment Report; there are however, general provisions which relate to
Fire Control in their Environmental Management Plan. To ensure safety of people
and property are maintained in the event of a bushfire, a relevant condition is
recommended which requires water storage for firefighting purposes.
• Biodiversity Overlay Code
“The purpose of the code will be achieved through the following overall
outcomes:
a) the ecological integrity and functionality of environmentally significant
vegetation and wildlife habitat areas, waterways and wetlands is
maintained by ensuring that development:
i. retains elements of ecological importance; and
ii. effectively mitigates potential environmental, amenity, hydrologic
and access impacts; and
b) where relevant, the ecological integrity and functionality of
environmentally significant vegetation and wildlife habitat areas,
waterways and wetlands is improved through rehabilitation measures and
enhancing regional ecological connectivity.”
Lot 696 is mapped as Environmentally Significant Vegetation and as containing a
Waterway. However, only 2ha of isolated Environmentally Significant Vegetation
shall be disturbed by the development. In addition, the loss of vegetation has been
accepted and conditioned by DILGP as part of their concurrence agency response.
Therefore, the loss of vegetation is considered acceptable.
The impact on the waterway has not been identified by the applicant in their
assessment of the Overlay. The code states that development avoids being located
within 50m of a waterway. It is therefore proposed to include a condition that the
development may not occur within 50m of the mapped waterway.
As part of the submissions received in relation to the application, concerns have been
raised about the existence of weed species on the site, and in particular sicklepod.
The Department of Agriculture and Fisheries Factsheet states:
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49558
“These species can invade and completely dominate pastures and other
disturbed areas such as roadsides, fence lines, creek banks and disturbed areas.
They have the potential to become major weeds of many crops within a matter
of two or three growing seasons.
Sicklepod and sennas are unpalatable to domestic stock. However, cattle and
horses will eat mature seed, which can pass through the animal and germinate
in dung. This is the most common manner of seed spread from one property to
another.
Seed reserves of 2000 seeds/m2 of soil have been recorded in dense stands of
sicklepod. These large reserves may germinate at any time of the year under
favourable conditions. Once a seed population develops in the soil, sicklepod
can remain a problem for many years. Seed can remain viable for up to 10
years.
Legal requirements
All three sicklepods are restricted invasive plants under the Biosecurity Act
2014. They must not be given away, sold, or released into the environment
without a permit. The Act requires everyone to take all reasonable and practical
steps to minimise the risks associated with invasive plants and animals under
their control. This is called a general biosecurity obligation (GBO). This fact
sheet gives examples of how you can meet your GBO.
At a local level, each local government must have a biosecurity plan that covers
invasive plants and animals in its area. This plan may include actions to be
taken on certain species. Some of these actions may be required under local
laws. Contact your local government for more information.
Sicklepod has the potential to become a major weed across much of Queensland and
although its current range is extensive, the weed is only in the early stages of its
invasion. The economic impact of this weed could become significant.
Council’s local law officers have recommended the following control measures
placed on the development and included in the applicants Environmental Management
Plan.
• Regular spraying of invasive biosecurity matter to be conducted with
appropriate chemical
• No top soil (150mm depth) to be removed from site
• Any contaminated material to be stockpiled on site and treated
• All roadways, laneways and water courses to be kept weed free
• Create and maintain a 10m weed free buffer zone around perimeter of property
• Create a clean down area for machinery. This area to be bunded and monitored
for invasive biosecurity matter. If found must be treated immediately.
• All equipment must be cleaned before leaving site.
The applicants Environment Management Plan already contains a section that
addresses Weed Management in general; however, the imposition of this condition
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49559
will reinforce the importance of on-site management of invasive weeds and other
biosecurity matters.
In relation to Councils obligations under the Biosecurity Act 2014, Council has a
biosecurity plan (Mackay Regional Council Biosecurity Plan: 2017-2021). The
purpose of the plan is for Council to have an effective and efficient want to control
invasive biosecurity matter while educating landholders in the importance of
managing pests in their own properties. The plan also helps Council to priorities
where they should be targeting their resources/species to control.
It is considered that with the imposition of these conditions, the development will be
generally compliant with the requirements of the Biodiversity Overlay Code.
• Landscape Character & Image Corridors Overlay Code
“The purpose of the code will be achieved through the following overall
outcomes:
a) development in landscape character areas is sensitively located and
designed so that landscape character attributes are maintained; and
b) development adjacent to image corridors enhances the region’s visual
amenity by providing high quality built form and landscaping outcomes.”
The vegetated North and West part of Lot 696 is covered by the Landscape Character
overlay. No works or vegetation removal is proposed within that area and so the
overlay is considered to be complied with.
• Landslide Hazard Overlay Code
“The purpose of the code will be achieved through the following overall
outcomes:
a) development on steep land is avoided or located and designed so that the
level of landslide hazard risk is minimised; and
b) development does not result in increased landslide hazard risk for
adjoining and nearby sites; and
c) reconfigured lots on steep land provide a usable and accessible building
envelope.”
Both lots contain land that is identified as having a slope of greater than 15%, which
is the trigger for assessment under this Overlay. In relation to Lot 696, no extraction
is proposed in the areas indicated as having steep slopes. On Lot 106, the area
indicated as having steep slopes is currently being quarried. It is considered that the
proposal complies with the overall intent of the code.
A detailed assessment has been undertaken against the following codes:
• Rural Zone Code
• General Development Requirement Code
• Extractive Industry Code
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49560
Only the areas of non-compliance and provisions requiring management of conflicts
are discussed below.
• Rural Zone Code
The purpose of the code will be achieved through the following overall outcomes:
“(iii) the zone also accommodates intensive rural activities, extractive industry
(and complementary activities) and other activities requiring a location
outside urban areas due to the amount of land required, the significance
of impacts generated and/or other reasons, if the development does not:
a) diminish the productive capacity of land for rural activities; and
b) result in adverse impacts on the environment or sensitive land uses;
and
c) result in visually obtrusive development that detrimentally impacts
on the rural amenity and landscape character of the area;”
The local government purpose of the zone code is to provide for a range of rural
activities, residential uses that support rural activities and intensive rural activities and
other uses that cannot be located in urban areas. The zone also contains undeveloped
land providing ecological and habitat value.
The proposed development is for an identified use within the purpose of the code and
is not in conflict with Agricultural land uses or supporting farming infrastructure.
Some environmental constraints have been identified onsite and assessed above
against the biodiversity overlay; however, the alternative solutions proposed and
recommended conditions are considered to address those issues.
Therefore, it is considered that the proposal complies with the overall outcomes of the
Rural Zone Code.
• General Development Requirement Code
“The purpose of the code will be achieved through the following overall
outcomes:
a) development is efficiently serviced by utility and access infrastructure;
and
b) the integrity and efficiency of existing utility and access infrastructure
systems is maintained; and
c) development provides adequate on-site vehicular access and adequate
parking and servicing facilities for vehicles and parking facilities for
bicycles; and
d) development maintains the amenity of the surrounding area; and
e) sensitive land uses in close proximity to activities generating amenity
impacts are located and designed to mitigate the impacts; and
f) development is protected from inundation by floodwaters, and does not
exacerbate flood impacts on other properties in the surrounding area;
and
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49561
g) earthworks maintain public safety, environment quality and a high level of
visual amenity; and
h) landscaping enhances the tropical character, visual amenity,
environmental quality and microclimate of sites and streetscapes; and
i) works in public streets enhance the pedestrian amenity, visual amenity
and general usability of streets; and
j) development is designed to reduce opportunities for antisocial and
criminal behaviour.”
The purpose of the General development requirements code is to provide general
requirements regarding infrastructure, amenity, safety and environmental standards
for assessable development. An assessment against the infrastructure requirements is
detailed below:
• Stormwater management will be in accordance with the Stormwater
Management Plan.
• Any waste generated will be incidental and will be disposed of off-site by the
contractors.
• The access track will be formed and drained to provide all-weather access to the
haulage trucks.
• There is adequate area to permit car parking on-site without impacting adjoining
residences. It is recommended that Council condition the car parking area, with
the provision of signage directing the people to the designated area ensures
safety for employees and visitors on site.
• The proposed quarry will operate in accordance with the Environmental
Management Plan to ensure compliance with the Environmental Protection
(Air) Policy 2008.
• The proposed quarry will be conditioned to operate in accordance with the
applicants Environmental Assessment Plan and Environmental Management
Plan relating to noise and in particular the ‘Actual Operation’ scenario in the
Noise Impact Assessment report by Live It Acoustics.
On the basis of the above and the proposed conditions, it is considered that there are
no conflicts with the General Development Requirements Code.
• Extractive Industry Code
“The purpose of the code will be achieved through the following overall
outcomes:
a) extractive industries fulfil a demonstrated need; and
b) extractive industries are located, designed and operated to maintain
public safety, general amenity and landscape character of the
surrounding area; and
c) external haulage routes operate efficiently but do not compromise:
(i) the amenity of areas containing concentrations of sensitive land
uses; and
(ii) the condition of the roads; and
d) a high standard of water quality is achieved within and downstream of the
subject site through the implementation of appropriate water management
techniques; and
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49562
e) rehabilitation works during and upon cessation of the extractive industry
use results in the previous environmental attributes and usability of the
land being restored and/or improved.”
It is considered that the proposed development complies with most of the acceptable
outcomes of the Extractive Industry Code and are discussed in detail elsewhere in this
report. In summary, conditions are proposed which address amenity of existing
residents, environmental impacts shall be contained to the site or otherwise mitigated,
roadworks necessitated by the development have been included in the conditions and
haulage routes have been conditioned by DILGP.
The main areas of non-compliance identified are the proximity of works to the
northern adjoining neighbours which have dwelling houses on the properties. It is
recommended that no works are to occur within 400m of the existing dwellings in
accordance with AO2.1(b) of the code.
Also, a condition requiring rehabilitation of the site at the cessation of the activity has
been proposed in accordance with AO8.1 and AO8.2 of the code.
ADOPTED INFRASTRUCTURE CHARGES REGIME
Infrastructure Charges are not applicable to the development as there is no gross floor
area or impervious area proposed as part of the operations.
INFRASTRUCTURE CONSIDERATIONS
Water & Sewer
The subject site is not connected to Council’s reticulated water or sewer services.
Onsite facilities will be provided by the operator as required by relevant Workplace
Health & Safety legislation.
Roadworks
The applicant is proposing a new access location off Boomerang Road to Lot 696 and
also an internal connection between the two quarry locations crossing Boomerang
Road is proposed.
The increased truck movements on Boomerang Road will result in an increase in
incremental maintenance required to the haul routes. A condition will be applied to
any approval for the applicant to identify additional road maintenance or upgrades
required due to the haulage operations, and to undertake those works.
This information will need to be detailed in the Operational Works application.
Stormwater
It is agreed in principle that stormwater runoff can be managed onsite in accordance
with the applicants Environmental Management Plan. However, it has been
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49563
conditioned that stormwater runoff from the site shall create no worsening to
downstream properties.
REFERRAL AGENCIES
The development application was referred to the Department of State Development,
Manufacturing, Infrastructure and Planning (DSDMIP) for the following provisions of
the Planning Regulation 2017:
• Planning Regulation Schedule 10 Part 3 Division 4 Table 3 .1 Clearing
Native Vegetation
• Planning Regulation Schedule 10 Part 5 Division 4 Table 2.1
Environmentally relevant activity
• Planning Regulation Schedule 10 Part 9 Division 4 Table 1.1
Infrastructure - state transport infrastructure
The State has approved the use subject to conditions (refer Attachment C – Referral
Agency Response).
SUBMISSIONS
The application was publicly notified in accordance with the requirements of the
Planning Act 2017, and as a result of this process, nine (9) individually prepared
properly made written submission and one (1) not properly made written submission
was received.
The submissions received, expressed opposition to the proposal. The principle
concerns raised from the submissions are summarised and discussed below.
1. Traffic impacts;
• Road Impacts & Capacity
• Safety
2. Infrastructure provision;
3. Noise and vibration;
4. Dust / air quality;
5. Stormwater Quantity and Quality;
6. Groundwater;
7. Visual amenity;
8. Biosecurity / Pest Management;
9. Flora and Fauna;
10. Public notification issues;
11. Planning scheme conflicts.
1. Traffic Impacts – Road Impacts & Capacity
In summary, the submitters had the following concerns with regards to Traffic Impacts:
• Poor current state of the road and the impact the added traffic will have.
• Additional heavy vehicles will impact on the existing school bus pickup point.
• Existing road is a single lane.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49564
• Single lane bridge at Rocky Creek crossing is already dangerous.
Applicant’s Response:
Road Impacts & Capacity
A Road Impact Assessment (RIA) has been prepared by SLR Consulting. The RIA
involved the following tasks:
- Inspection of the public road network in the vicinity of the site.
- Collation of data from road authorities describing the existing road conditions and
survey of peak hour traffic volumes to supplement the data held by road authorities.
- Forecast the additional traffic demands likely to be generated by the activities
associated with the project.
- Forecast future design traffic volumes, both including and excluding project traffic
demands.
- Undertake swept path assessments for the study intersections.
- Identification of the project’s potential impact on the State-controlled road
pavement and associated rehabilitation and maintenance contribution.
SLR Consulting determined a contribution payable as a result of increased traffic
generated by the increased traffic demand, to satisfy any additional maintenance
requirements on the existing roadway. Assessment of turning paths and stopping
distances were also undertaken, which determined that the results were within allowable
limits. Furthermore the report did not identify any intersection upgrades required, and
determined that:
“The assessment establishes that the provision of channelised lanes is not required to
provide an appropriate level of safety at the study intersections”
The submissions received appear to be concerned with increased traffic intensity as a
result of the increased extraction limits. As part of the current approval, the existing pit
has been supplying the Mackay Ring Road project for a number of months. Traffic
intensity is generally related to the demand from the specific construction project being
supplied, which is a result of the required timeframe to complete the project.
Increase of the maximum annual extraction limit is not expected to have an increase on
the maximum number of vehicle movements per day, however will allow the upcoming
road infrastructure projects with the construction material quantities required for these
projects. Additionally, it should be noted that the increased extraction limit is sought to
be able to supply other construction projects as they occur within the region.
Some submissions query the need for the increased extraction limit, when there are other
quarries within the region with larger extraction limits. Bussey’s Pit is ideally suited to
the Mackay Ring Road, Walkerston Bypass projects, Industrial projects as well as other
future projects located south of the river. Requiring construction materials to be sourced
from more distant quarries adds stress to the road network and increases road
maintenance impacts and decreases amenity for other parts of the community.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49565
Safety Impacts
As detailed above, Stopping Sight Distances, vehicle swept paths & need analysis for
upgrade to Bells Road / Walkerston Homebush Road Intersection and Busseys Road /
Bells Road Intersection was undertaken. The report determined that there was no
requirement to alter these intersections as a result of this DA. Additionally it should be
noted that the one-way bridge over Sandy Creek is currently being upgraded by MRC
with completion anticipated by June 30, 2018.
Also please refer to Road Impact Assessment Mackay Busseys Quarry report dated 21
November 2017 prepared by SLR Consulting. The potential issues raised by submitters
have been addressed within the SLR report.
Officers Comments:
Road impacts are a significant issue in any extractive industry application due to the
additional traffic generation and the applicant has been required to assess and provide
reports on the likely impact on the local roads that will be utilised.
It is recommended to that the proposed access locations off Boomerang Road must be
constructed to accommodate swept paths from the largest design vehicle and the location
must achieve minimum sight requirements. Further, it is recommended to condition to
erect speed signs to mitigate speed in the area.
Conditions will be imposed on any approval that requires the applicant to undertake any
upgrading required to ensure traffic safety on the haul roads under the control of Council.
In relation to Rocky Creek bridge, Council is undertaking upgrade works to commence
imminently, with anticipated completion by 30 June 2018.
In relation to the issue raised about the school bus pick up point; if the approved haulage
route contains a school bus route there should be signage in place already to indicate the
use of the road as a bus route and indicate the location of pickup points. Councils’
Technical Services program will investigate the location of bus routes and pick up points
and arrange for the necessary signage to be installed if not already existing.
2. Infrastructure Provision
In summary, the submitters had the following concerns:
• No infrastructure is available to the site.
Applicant’s Response:
Portable water and sewerage currently service the existing quarry and will continue to do
so. Summit Construction Materials successfully manages numerous operations in this
manner with no issues. This practice is consistent with many quarries due to their
remoteness from infrastructure.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49566
Officers Comments:
Due to the location of the proposed quarry, the provision of portable water and sewerage
facilities is acceptable and consistent with accepted practice.
3. Noise and Vibration
In summary, the submitters had the following concerns in relation to noise:
• The submitters are concerned with elevated noise levels due to increase operation
• The development will cause added noise to a quiet residential farming area.
Applicant’s Response:
Noise Impacts have been assessed in the Environmental Assessment Plan (EAP) and is
summarised below:
A noise impact assessment has been prepared by Live It Acoustics. The report included
monitoring of background noise levels, and modelled alternate scenarios to establish
likely impacts to sensitive receptors. The report determined the most affected sensitive
receptor to be Lot 15 (32) Busseys Road, however;
“Provided Pointglen Developments Pty Ltd undertakes excavation and processing
activities on the Bussey Quarry (Western and Eastern sites) in accordance with the
proposed 'actual' operating scenario, the proposed development will comply with the
established noise criterion.”
Live It Acoustics Noise Impact Assessment is included in Attachment 3 for reference
As no blasting is proposed as part of the application it is not anticipated that vibration
will be a concern, due to the distance between the extraction sites and residences.
The Department of Environment and Science have issued the attached Environmental
Authority, which comprehensively conditions the development to ensure the environment
and community amenity is protected from noise and vibration issues. Refer also initial
application and further State Information Request responses, as forwarded to Council.
Officers Comments:
The potential for noise impact on surrounding sensitive places has been assessed by the
State and conditioned in the Environmental Authority issued by Department of
Environment and Heritage Protection. It is also proposed to include a condition on any
approval that requires the quarry operations to be in accordance with the applicants
Environmental Assessment Plan and Environmental Management Plan relating to noise
and in particular the ‘Actual Operation’ scenario in the Noise Impact Assessment report
by Live It Acoustics.
4. Dust / Air Quality
In summary, the submitters had the following concerns in relation to dust:
• Concern that the increase will add additional dust from the increased traffic and
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49567
impact on dirt road access not designed to carry large vehicles.
Applicant’s Response:
Please refer to Environmental Management Plan Section 18.6, which details management
procedures proposed for the works.
The Department of Environment and Science have issued the attached Environmental
Authority, which comprehensively conditions the development to ensure the environment
and community amenity is protected from dust and air quality issues. Refer also initial
application and further State Information Request responses, as forwarded to Council.
The excavations are proposed to be undertaken by Summit Construction Materials, whom
operate numerous extraction sites across the region within close proximity to nearby
residents, and are experienced in managing dust effects.
Air quality impacts have addressed in the EAP included in Attachment 2. A summary is
below:
The closest nearby sensitive receptor is located at Lot 15 (32) Busseys Road, which is
approximately 220m to the north-east of the eastern extraction area. This residence is the
land owner of the subject properties and gives their consent to the application.
Furthermore, the eastern pit is a well-established pit as part of the current approval which
currently operates effectively in the area.
The next closest nearby receptor is located 280m away immediately north of the western
extraction site boundary. This represents the minimum distance from the sensitive
receptor and it is noted that the quarry will generally progress in a south-westerly
direction as extraction increases into the future. There are no known sensitive receptors in
this direction as the current land use in this area is sugar cane & cattle grazing property.
The site is benefited by the large portion of land which is currently mapped as regulated
vegetation within the north-western portion of the property. As such no extraction is
permitted within this area, which will act as a buffer to protect northern properties from
the prevailing south-easterly winds. The impacts to northern residents can therefore be
considered as minor, provided that appropriate mitigation measures are implemented and
adopted in accordance with the quarry operator’s EMP.
Officers Comments:
As discussed above, it is considered that dust impacts can be effectively managed by the
operator via the methods outlined in their Environmental Management Plan. Further,
dust issues have been appropriately conditioned within the Environmental Authority.
5. Stormwater Quantity and Quality
In summary, the submitters had the following concerns relating to Stormwater Quantity
and Quality:
• Only general stormwater plans have been provided and they are not adequate.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49568
Applicant’s Response:
Stormwater Quality & Quantity has been addressed in the Site Based Stormwater
Management Plan (SBSWMP). Sedimentation basins have been sized in accordance with
IECA Best Practice Erosion and Sediment Control Guidelines. The SBSWMP outlines
discharge criteria required to be achieved in order to comply with DES requirements.
As per the SBSWMP, disturbance on the site will be staged to minimise sediment runoff.
There will be no Stormwater flooding issues as a result of the development, as detailed in
the EAP Section 3.4
Officers Comments:
As discussed above, it is considered that stormwater quality and quantity can be
appropriately conditioned and a detailed assessment undertaken as part of an Operational
Works application.
6. Groundwater
In summary, the submitters had the following concerns relating to impact on
groundwater:
• Impact on existing residents bores.
Applicant’s Response:
Due to the elevation of the proposed site, interference with groundwater is not expected.
Fuels, Oils & chemicals will be stored in accordance with the attached Environmental
Authority (Attachment 4) and as per the EMP to effectively mitigate risk of
contamination of groundwater as a result of the works.
Summit Construction Materials successfully operates numerous quarries including
Busseys pit as per the current approval with no contamination issues to date.
Officers Comments:
It is considered that groundwater will not be detrimentally impacted by the development.
7. Visual Amenity
In summary, the submitters had the following concerns relating to impact on amenity
The change of the development permit application could negatively impact the quality
and character of our property and surrounding areas and the way it functions. The
change of license will add additional noise, dust from the increased traffic and impact on
the dirt road access not designed to carry large vehicles.
Applicant’s Response:
The proposed increase in intensity will not impact visual amenity, since the proposed use
is visually identical with the existing quarry approval over the site.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49569
The amenity of sensitive receptors in relation to noise, vibration and air are addressed
elsewhere in this response.
Officers Comments:
It is proposed to condition a buffer between the extraction activities and nearby sensitive
receptors.
8. Biosecurity / Pest Management
In summary, the submitters had the following concerns:
• The lot is riddled with a noxious weed called picky bush, parthenium weed, stink
weed, thorn trees, rag weed, sickle pod and no management has been done to date.
• Sicklepod can produce up to 8000 seed’s per year and the seed is viable for up to
20 years.
Applicant’s Response:
The proposed intensity of use does not increase the risk of sicklepod spreading, since
quarrying activities can already occur over the site in accordance with the existing
approval.
The existing quarry has comprehensive procedures to manage the spread of noxious
weeds, including sicklepod. Please refer to EMP Section 18.10 (Attachment 5) for
information on management procedures to mitigate any potential issues.
Standard procedures which will be implemented include stripping of all vegetation to a
sufficient depth within the proposed work extent and stockpiling clear of the work area to
ensure that seeds are not spread as a result of the construction works. Topsoil which has
not been in contact with Sickle Pod or other noxious weeds will be selected for use in
order to provide a growing media which does not contain these noxious weeds. Further,
the site will be monitored to manage any Invasive plants which may germinate on site
during the operation.
Officers Comments:
It is proposed to include a biosecurity condition which will address the issue of weed
control onsite.
9. Flora and Fauna
In summary, the submitters had the following concerns
• The development affects the flora and fauna
Applicant’s Response:
The site includes mapped Regulated Category B endangered regional ecosystem.
Vegetation and essential habitat was assessed by the State under the State Development
Assessment Provisions - State Code 16.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49570
The proposed development was found to comply with the requirements of State codes.
The Referral Agency Response conditions provided to Council include protection of
almost all of the mapped remnant vegetation. Additionally, the State has conditioned a
substantial buffer to the protected remnant vegetation ensuring further protection of the
ecosystem from accidental encroachment.
A small isolated section of Remnant Vegetation will be cleared for operational purposes.
The existing quarry operation is permitted to clear this vegetation under the State’s self-
assessable clearing code “Managing clearing for an extractive industry” regardless of the
outcome of this approval.
Officers Comments:
As discussed above in the assessment of the Biodiversity Overlay, it is considered that
this have been effectively conditioned by the Department as part of the Environmental
Authority.
10. Legislation Compliance (Public notification issues)
In summary, the submitters had the following concerns
• Inadequate signage location
• Incorrect description of ‘Development’ Proposed
• Incorrect signage letter sizing
• Invalid application as an Operational Works was not applied for.
Applicant’s Response:
The public notification undertaken for these works satisfies the requirements set out in
the Planning Act, in particular:
- Council have been provided with photographic evidence showing 4 signs were
placed at all subject road boundaries. The photographs show the signs were clearly
visible from the adjoining roads.
- The description in the public notification is appropriate and accurately describes the
proposed use being applied for. A submitter has noted the use description should
include Operational Works. However, the requirement for an Operational Works
application is superfluous to the Material Change of Use. Any planning scheme
requirement for further applications only applies to other requirements, such as
landscaping works or access.
- Signage lettering is correctly sized. Any inconsistency, perceived or otherwise,
would be inconsequential, as demonstrated by the submissions received.
Officers Comments:
Council confirms that it is considered the public notification was adequately undertaken,
as evidenced by the number of submissions received and through the evidence provided
in the notice of compliance of the public notification. The Operational Works component
of the development can be applied for separately as is standard practice.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49571
11. Planning Scheme Conflicts
In summary, the submitters had the following concerns
• Non-compliance with the extractive industry code
Applicant’s Response:
The proposed increase in intensity of quarry use is consistent with the existing
approved quarry operation and the planning scheme intent. Also:
1. The subject site is zoned Rural and contained within the Hinterland Locality.
Adjoining properties are zoned Rural.
• Extractive industry uses are supported by the overall outcomes of the
Rural Zone Code.
• The increased extraction rates will not significantly alter the existing
approved operation of the quarry.
2. The proposed use is protected by the Planning Schemes Desired Environmental
Outcomes. In particular:
• Biodiversity and Habitat/Natural Features are preserved through the
protection of the sites remnant vegetation.
• Economic Development: The proposed use will improve the economic
viability of Mackay by locally providing much needed material for
significant infrastructure projects.
• Amenity and Community Well-being: Impacts from the proposed increase
in intensity have been examined thoroughly and are discussed elsewhere in
this response. Furthermore, the State has assessed the environmental
impacts of the increased intensity and conditioned the approval for noise,
dust, etc. The proposal will not compromise the intent of this DEO, as
demonstrated elsewhere.
Officers Comments:
As discussed above as part of the planning scheme assessment, Extractive Industry is
supported in rural areas and it is not considered there are any conflicts with the
applicable codes.
RESOURCES IMPLICATIONS
Nil.
RISK MANAGEMENT IMPLICATIONS
Nil, with the exception of potential costs involved if an appeal is lodged.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49572
CONSULTATION
External
The application was publicly notified in accordance with the Planning Act 2017 and it
has been determined the requirements of the Act has been satisfied in this respect.
Internal
The application was discussed with representatives from various Departments at the
Development Enquiries meeting on 13 March 2018.
CONCLUSION
Quarrying activities have been previously approved on these sites and this application
proposes an increase in the permissible extraction from 100,000 tonnes per year to
1,000,000 tonnes per year.
It is considered that the proposed development is generally consistent with the intent
of the relevant assessment codes and the Planning Scheme in general. Conditions are
proposed to be applied to ensure any impacts are ameliorated or prevented. Further, it
is not considered that the submission received have raised any issues that would
warrant refusal of the application.
The application is recommended for approval, subject to reasonable and relevant
conditions.
Officer's Recommendation
A. THAT Council approve the Material Change of Use - Extractive Industry
(Expansion) for a Quarry up to 1,000,000 tonnes per year at Lot 106
Boomerang Road and Lot 696 Busseys Road, PALMYRA QLD 4751 in
accordance with the following conditions:
1. Plan of Development
The approved Extractive Industry development must be completed
and maintained generally in accordance with the Plan of
Development (identified in the Table below) and supporting
documentation which forms part of this application, except as
otherwise specified by any condition of this approval.
Project
Drawing
Title
Drawing
Number
Revision Prepared by Date
Bussey
Quarry
5021-00
Plan of
Development
0288-
C00
B Pointglen
Developments
02/11/2017
Bussey
Quarry
5021-00
Western
Layout
0288-
C01
B Pointglen
Developments
02/11/2017
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49573
Project
Drawing
Title
Drawing
Number
Revision Prepared by Date
Bussey
Quarry
5021-00
Eastern
Layout
0288-
C02
B Pointglen
Developments
02/11/2017
2. Compliance with Conditions
All conditions must be complied with prior to the commencement of
the use on the subject site, unless specified in an individual
condition.
3. Maintenance of Development
The approved development (including landscaping, car parking,
driveways and other external spaces) must be maintained in
accordance with the approved drawing(s) and/or documents, and
any relevant Council engineering or other approval required by the
conditions.
4. Compliance with Council Standards
All design and construction for the development must be in
accordance with Council’s Policies, Engineering Design Guidelines,
Standard Drawings and Standard Construction Specifications.
5. Damage
The developer is responsible for the repair of any damage that is
caused to Council’s infrastructure as a result of the construction
works associated with the proposed development. The developer
must make any damage safe and then notify Council immediately.
Council will make the decision as to who will carry out the
rectification works and the timing for the completion of those
works.
6. Extraction Limits
The maximum extraction amount approved is 1,000,000 tonne per
year.
7. Blasting
Extraction by blasting is not permitted.
8. Conflict between plans and written conditions
Where a discrepancy or conflict exists between the written
condition(s) of the approval and the approved plans, the
requirements of the written condition(s) will prevail.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49574
9. Notice of Intention to Commence the Use
Prior to the commencement of the use on the site, written notice
must be given to Council that the use fully complies with the
decision notice issued in respect of the use (please see attached
notice for your completion and return to
10. Hours of Operation
The use may operate only between the hours of 6am to 6pm
Monday to Saturday, excluding public holidays.
11. Dust Control
Dust suppression measures must be undertaken to ensure that dust
does not cause a nuisance to surrounding areas and residents.
All roads/storage areas/external stockpiles/vacant or grazed areas
must be maintained to avoid dust nuisance to any adjacent dwelling
to the satisfaction of the Council.
12. Settlement Ponds
Any settlement ponds to be used for retention of discharged water
must be maintained to ensure that offensive or noxious odours do
not emanate from the site, causing an environmental nuisance.
13. Environmental Management Plan
Operation of the Extractive Industry must be in accordance with the
Environmental Management Plan prepared by Summit Construction
Material Pty Ltd, Project: Bussey Quarry, Job No: 5021-0, Revision
1. Where there are inconsistencies between these conditions and the
Management Plan, the conditions shall prevail.
14. Weed Management
In accordance with the QLD “Biosecurity Act 2014” every person
or organisation has a General Biosecurity Obligation to take all
reasonable and practical measures to prevent or minimise the
biosecurity risk.
Weed management must be undertaken onsite in consultation with
Council’s Pest Management Officer and include:
a) Regular spraying of invasive biosecurity matter to be
conducted with appropriate chemical
b) No top soil (up to 150mm deep) to be removed from site
c) Any contaminated material to be stockpiled on site and treated
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49575
d) All roadways, laneways and water courses to be kept weed
free
e) Create and maintain a 10m weed free buffer zone around the
perimeter of the site
f) Create a clean down area for machinery. This area is to be
bunded and monitored for invasive biosecurity matter. If
found it must be treated immediately.
g) All equipment must be cleaned before leaving site.
15. Fuel Storage
Any storage of fuel onsite is to be in accordance with AS1940-
2004-Storage and Handling of Flammable and Combustible Liquids.
16. Works for Mitigating Increment Road Degradation
The applicant shall undertake a road impact assessment of Local
Government controlled roads and intersections, including
Boomerang Road, Bells Road, Walkerton-Homebush Road and
Stockroute Road. The report will be subject to Council approval
and must determine the incremental maintenance requirements as a
result of the predicted increase in traffic volume and impact. The
applicant shall undertake the necessary road works to mitigate the
incremental degradation.
Advice Note:
Council may be prepared to enter into an Infrastructure Agreement
in relation to the works required due to accelerated maintenance
caused by the haulage activities.
17. Access
The proposed access locations off Boomerang Road must be
constructed to accommodate swept paths from the largest design
vehicle and the location must achieve minimum sight requirements.
Access details including adequate traffic control measures should be
provided in the Road Impact Assessment study. This study must be
provided to Council for approval prior to commencement of works.
18. Stormwater Drainage
Stormwater from the site shall be controlled within the property
boundaries and discharged via the existing drainage paths, generally
in accordance with the approved plans. No worsening of
stormwater runoff in terms of quantity, quality and nuisance runoff
(frequent flow causing erosion or unusable wet areas) is to occur at
the discharge point or subsequent downstream properties.
Stormwater detention and stormwater treatment must be provided
appropriately to ameliorate any issues.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49576
19. Ponding and Diversion of Stormwater
Ponding of stormwater resulting from the development must not
occur on adjacent sites and stormwater formerly flowing onto the
site must not be diverted onto other sites. The site shall be graded
so that it is free draining.
During the operational phase of the quarry, the runoff from
upstream must not be mixed with the quarry operation area to ensure
the quality of runoff downstream of the quarry satisfies the water
quality objects of the State Planning Policy.
20. Site Based Stormwater Management Plan
Stormwater Quality Best Management Practices (SQBMP) must be
developed and implemented in accordance with Mackay City
Council’s Engineering Design Guidelines – Soil and Water Quality
Management – Planning Scheme Policy No.15.07. As a minimum,
erosion and sediment control must be undertaken.
21. Speed Signs
Provide speed signs to mitigate speed in the area.
22. Site security
Prior to the commencement of the use, the site must be secured to
ensure no unauthorised entry to the satisfaction of Council.
• Security gates shall be installed at all access points.
• Security fencing must be provided around the proposed
development in accordance with the relevant Australian
Standard.
• Signs will be erected on both road frontages at the gate
locations as required.
23. Safety and Warning Signage
A safety and warning sign/signs must be provided, which
communicates information about the facility-related safety issues
and discourage unauthorised access. All signs must:
a) be satisfactorily visible, legible;
b) maintained at all times; &
c) located on the security fence.
24. Minimum Car Parking Spaces
The car parking area must be constructed, and drained for a
minimum of 10 car parking spaces including 1 car parking spaces
for people with disabilities. The carparking must be delineated in
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49577
some form and signs posted to direct people to the designated
parking area.
25. Provision of Water for Fire-fighting Purposes
Provide an adequate and accessible water supply system for fire-
fighting purposes on site. A minimum of 25,000 litre water storage
is required.
26. Concentration of Flow
Concentration of flow resulting from the proposed development
must not have any adverse impacts on downstream properties and
drainage infrastructure.
27. Site Rehabilitation
Rehabilitation works during, and at the cessation of the extractive
industry use, are provided in accordance with a rehabilitation
management plan which must be provided to Council for approval
prior to the commencement of the use.
The rehabilitation management plan must detail:
a) progressive / staged rehabilitation works; and
b) clean-up works (including areas of possible soil or water
contamination); and
c) works required to ensure landform and soil profiles are stable
and in a usable condition; and
d) revegetation using native plant species; and
e) monitoring for all aspects of the operations impacting on the
environment.
28. Limit of Use
No works associated with the Extractive Industry including but not
limited to operation of machinery, stock piling and extraction are to
occur:
a) within 400m of a sensitive landuse located on Lot 14 on
RP749091 and Lot 15 on RP749091.
b) Within the buffer of the identified waterway onsite.
29. Noise Impacts during operations
The noise generated by the quarry operations must not create
adverse impact to any sensitive land uses. The operation of the
quarry must be in accordance with the applicants Environmental
Assessment Plan and Environmental Management Plan relating to
noise and in particular the ‘Actual Operation’ scenario in the Noise
Impact Assessment report by Live It Acoustics.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49578
B. THAT the applicant be provided with the following Assessment Manager
Advice:
1. Local Laws
The approved development must also comply with Council’s current
Local Laws under the Local Government Act 2009.
2. Dust Control
It is the applicant/owner’s responsibility to ensure compliance with
Section 319 General Environmental Duty of the Environmental
Protection Act 1994, which prohibits unlawful environmental
nuisance caused by dust, ash, fumes, light, odour or smoke beyond
the boundaries of the property during all stages of the development
including earthworks and construction.
3. Sedimentation Control
It is the applicant/owner’s responsibility to ensure compliance with
Chapter 8, Part 3C of the Environmental Protection Act 1994 to
prevent soil erosion and contamination of the stormwater drainage
system and waterways.
4. Noise During Construction and Noise in General
It is the applicant/owner’s responsibility to ensure compliance with
Chapter 8, Part 3B of the Environmental Protection Act 1994.
5. General Safety of Public During Construction
It is the principal contractor’s responsibility to ensure compliance
with Section 19 (2) of the Work Health and Safety Act 2011. Section
19 (2) states that a person conducting a business or undertaking
must ensure that the health and safety of other persons is not put at
risk from work carried out as part of the conduct of the business or
undertaking.
It is the responsibility of the person in control of the workplace to
ensure compliance with Section 20 (2) of the Work Health and
Safety Act 2011. Sections 20 (2) states that the person in control of
the workplace is obliged to ensure that the means of entering and
exiting the workplace and anything arising from the workplace are
without risks to the health and safety of any person.
6. Acid Sulphate Soils
If the proposed works trigger the SPP 2/02 Planning and Managing
Development in Acid Sulphate Soils, a Site Based Acid Sulphate
Soil Management Plan must be prepared by a suitably qualified
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49579
professional and submitted to Council for approval as part of the
Operational Works application.
7. Further Approvals Required
Operational Works Development Permit – Public/Private
Infrastructure
• Stormwater Quantity and Quality Mitigation Devices
• External Roadworks
Minor Works Permit
• Rural Access
PUBLIC PARTICIPATION
The Mayor welcomed the members of the public in the Public Gallery who had
registered to speak to this item on the agenda today and provided an explanation on
the procedure of public participation.
Tony Bugeja
Mr Bugeja queried if it was deemed appropriate that every submitter to an application
receive a registered solicitors letter from the developer if the submitters are only
following Council's requirements for submissions. His property is downstream from
this application and will be effected by waterflow from the application which runs in
between the creek. He has a licenced pumping station pumping water in flood times
out of the creek into a dam. Any contaminated water that flows down the creek will
be pumped and placed into his dam and then reticulated over his farm. Any seeds that
come down the creek will be spread all over his farm. He believes once ground has
been disturbed then sicklepod will explode along with giant rats tail grass, rag weed
and log wood which are all present on the application property. He believes there are
not enough sediments traps and they are not big enough to control the amount of
water that will come through the applicant's property.
Sam Camilleri
Mr Camilleri advised that SJPC Camilleri Family Trust have recently finalised the
leasing of Lot 100, the adjoining property to the application. The property has been
for the past 100 years camping and watering reserve where neighbouring graziers of
the day have open public access to the lagoon for watering stock in drought. The
Department of Environment when the property was offered for lease strongly advised
the trust it was for grazing and grazing only. He is concerned that any contaminated
substance escapes from the applicant's property into the water course his cattle will
have access to this water. He is concerned that the assurance of this not occurring
cannot be guaranteed. He is also concerned with the potential spread of noxious
weeds onto his property and opposes the application.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49580
Patricia Julien
Ms Julien advised she lives approximately 5 km north north west of the development
application site and is concerned about the impact of dust. There is no background
baseline monitoring of dust required in this application and would like to see
continuous dust monitoring to ensure the quarry is following the dust standards. She
would also like to see ambient monitoring in the interest of public health.
Michael McEachern
Mr McEachern advised his property borders the development application property and
is concerned that the reports submitted by the applicant were done inhouse rather than
by external independent firms. He is also concerned with the presence of sicklepod
on the property and the material taken off the property will be used on the ring road
which goes through the dress circle of Mackay's cane farms. This could be a very
serious issue for cane farmers if sicklepod is spread. He is concerned with the amount
of dust his property will be forced to endure as a result of this application as he is less
than 200m from the proposed site and one (1) km of his boundary faces the quarry. If
Boomerang Road was fully bitumen and the cattle grid was moved to the end of
Boomerang Road this would assist with reducing the dust levels.
Vic Vassallo
Mr Vassallo advised as the applicant his company does take submitters concerns very
seriously and wanted to respond to some comments made today. He advised the
reports were not prepared inhouse, they were prepared by consultants and engineers
including Cardno and others as well including RPS. The development is a
requirement for an economic area that is growing, Mackay is a growth area and
Mackay needs construction material. Dust and traffic impacts need to be considered
with every quarry application and unfortunately these are not the major concerns
being raised for this applicantion. One of the major concerns is sicklepod which is a
noxious weed. Noxious weeds are abundant and widespread from Carmila through to
Bowen, there are not many properties in Mackay that do not have sicklepod. The
development of the quarry will improve the spread of sicklepod and noxious weeds
through the stripping of the top soil and stockpiling it, sediments ponds and a
management system for biosecurity.
The Mayor acknowledged the residents for their attendance at today's Council
Meeting and thanked them for their input on this agenda item.
Cr Paton queried once the quarry is finished will the site be rehabilitated.
The Acting Director Development Services (A/DDS) advised there is an existing
Environmentally Relevant Activity (ERA) standard for quarries and includes
rehabilitation of the site when the quarry is completed.
Cr Paton was more concerned with the topography of the land at the completion of the
quarry and if it would be another farm dam or useful land.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49581
A/DDS advised the ERA conditions do not relate to if there is a dam or not only that it
must be useable and if there is an area where there is a dam, it controls how that dam
works.
Cr Bonaventura queried the conditions around dust control and if the conditions are
applicable to Council's road reserve.
A/DDS advised the condition is about all activity as a result of the quarry that dust
must be managed. There is also a road degradation condition that refers to all of the
roads as part of this application.
Cr Walker queried what was in the Environment Management Plan (EMP) if as it
states in the officer's comments that the dust impacts being controlled through it.
A/DDS advised there are a number of comments in the EMP including dust and
deferred to the Manager of Development Assessment (MDA) for further comment.
The MDA advised the EMP will address all of the issues including if there is being
dust generated requiring the staff on site to have a water truck spray the haulage areas
or stockpiles to ensure the dust level is maintained if they identify this as an issue.
Also within the EMP if there are complaints received, they address these and record
the information as to time and location of dust nuisance.
The Mayor queried the MDA if he thought the EMP would address Cr Walker's
query.
The MDA advised if the EMP was implemented then yes, Cr Walker's query would
be addressed. The State Government also have conditions in relation to the dust
nuisance legislation and strict requirements around dust generation.
Cr Bella queried if there is any conditioning on where the water that will be used to
suppress the dust will be sourced from. Is that water from a quarantined source, is it
from an area that has infestations, or is it going to be sourced from on-site. This water
will be sprayed over stockpiles and if there is no conditioning on where this water is
going to be accessed from then he is concerned that the EMP is short-sighted and
limited and totally ineffective.
A/DDS advised the water sourcing is up to the operator, but there are two sediment
dams that will be part of this application and part of the weed control Council's pest
management officer will be involved in the weed control.
Cr Bella commented that all that needs to occur is if water is accessed from an area on
site where there is weed and then sprayed on stockpiles this will spread the weeds.
He believes the water needs to be accessed from a quarantined site and not from on
site.
A/DDS advised this is not part of the conditions but this could be included if it is
Councils' wish.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49582
Cr Casey advised he is concerned with the degradation of the road surface along
Boomerang Road and Bells Road. His major concern is the intersection at Bells Road
and the Walkerston-Homebush Road as Council has previously approved a quarry on
Walkerston-Homebush Road and the trucks will be travelling along this route. Trucks
going through this intersection are swinging into the other lane to navigate the
intersection and it is a very dangerous situation. When the cane is high the sight lines
are impossible to have a safe entry and exit from Bells Road. Will there be any
conditions to upgrade this intersection or the sight lines.
The Mayor advised there were no conditions to upgrade.
A/DDS advised there is an existing approval over both sites that conditions in the past
to update the intersections for the specifically designed vehicles and was considered
in the previous application. There is a condition in place in this application for the
vehicles to access to the quarry but not the intersection.
Cr Casey advised he understands that but this application multiples this by 10 and that
is the problem and the trucks will be using this route for the next two (2) years.
Cr Bonaventura followed on from Cr Casey's query, at what point does Council
require upgrade of the road. It may have been conditioned for those size vehicles
under previous applications but those vehicles were not as often as they will be as a
result of this application.
The Mayor queried if officers have done any research on the road requirements.
A/DDS advised the applicant had submitted a road impact assessment report and it
did not identify the need for an upgrade.
Cr Bonaventura queried if Council has done any research not just the applicant.
MDA advised Council's Engineering Department have undertaken an impact
assessment and this concurs with the conclusions in the applicants reports that no
additional works are required for the number of movements.
Cr Camm queried the trigger point for potential upgrade of the roads and the threshold
and if Council's Engineering Department's assessment does not warrant an upgrade
can that determination once an approval is granted be changed, amended or reviewed
based upon compliance measures, safety interaction or monitoring of the road.
MDA advised the conditions would need to be reviewed and assessment of the
impacts before the applicant is requested to address the matter.
Cr May advised it was the Councillors observation during their inspection of the site
that the vehicles are not turning within the road as it is, she is curious to understand
how putting more trucks on the road does not warrant an upgrade.
MDA advised the traffic impact assessment bases its designs on the Australian
Standards in terms of movements, each individual driver of the vehicle operates
independently.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49583
Cr Bella advised he has concerns in relation to the traffic impact from the increase in
number of movements and if the road does start to deteriorate in any way it is the very
nature of drivers of heavy machinery to try and find the best path. If there is any road
degradation the drivers will deviate from the norm and if there are no conditions to
make sure the road is maintained there is potential for issues. The very nature of
truck and dog movements, it is not the loaded vehicle that causes issues it is more
likely the unloaded vehicle coming back at speed as there is a tendency on uneven
roads for the empty dog to jump around the road and become quite intimidating for
any driving coming in the other direction. Are there any conditions in place to ensure
the maintenance of the road is continually monitored and not moving into an area of
greater risk for the residents who are using this road for their activities.
A/DDS advised condition 16 does relate to works to mitigating increment road
degradation, subject to Council approval, which is an ongoing requirement of what
works are required in relation to road degradation.
Cr Bonaventura queried in relation to the repairs and degradation there are several
quarries using these roads, how does Council confirm which trucks created the
damage in assessing who is responsible for the repairs.
A/DDS advised it will be determined by the vehicles using the road and which quarry
they are working out of. Similar conditions are placed on other quarries.
Cr Bonaventura advised he is unsure how Council can specify how the damage was
caused from trucks from this applicant or a different quarry.
The Mayor advised if all quarries are conditioned the same and Council is aware of
how many movements there are per quarry per day, the upgrade of the road should be
easily proportioned.
Cr Paton advised there appears to be a number of issues that Councillors would like
further investigation undertaken and if a briefing to Councillors was requested what
timeframe would be required by Officers to gather all of this information.
The Mayor advised if Cr Paton wanted additional information the report would need
to lay on the table pending further information and sought clarification from the CEO
if further investigation was required in relation to traffic management, traffic flow,
dust suppression and water use as a vector for weeds and recondition how long would
officers need.
The CEO advised based on the discussions taking place, then officers would need to
investigate these concerns and could take up to four (4) weeks before they are ready
to bring the report back to Council for consideration.
The Mayor advised if Councillors are of a mind to amend the Officers
Recommendation then there needs to be a justification.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49584
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Camm Seconded Cr Gee
<RIGHT CLICK> DECISION
Cr Camm advised she would reserve her right of reply.
Cr Bella advised he did not support the Motion. He understands the comments about
development and economic activity but he fails to see why certain businesses, certain
current activities are going to be facing a far greater cost of operation due to this
development. The geography of this quarry is perfect however, situationally there are
some serious questions. He feels the maintenance of the road is a significant risk.
Just because there is pest infestation throughout the region, it does not mean all areas
of the region are infested. It also does not mean quarantine protocols should not be
adopted. He is concerned the biosecurity plan will not control the risk of weed
infestation spread. The wash down facility is only for machines working on site it is
not for trucks and trucks can spread the weeds through the animal dung on the
roadside from animals from this property.
Cr Paton advised he would like to raise a Procedural Motion based on concerns raised
so far by the Councillors.
Procedural Motion
THAT the report lay on the table pending a briefing to Council on the final
topography of the land and the rehabilitation, traffic management plan and
noxious weed control.
Moved Cr Paton
LOST
Crs Camm, Englert, Gee, Mann, May, Walker and Williamson
recorded their vote against the Procedural Motion.
Cr May advised she was speaking in favour of the Motion. In relation to a comment
Cr Bella raised in his argument, the competitive nature of the quarrying business is
not a matter for a planning decision and Council cannot base their decision on this.
Cr Bella wished to raise a Point of Order.
The Mayor asked Cr Bella what his Point of Order was in relation to.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49585
Cr Bella advised he did not make any comment with regard to the competitive nature
of quarrying.
The Mayor advised a Councillor cannot interrupt another Councillor with a Point of
Order unless it is on very specific procedural grounds.
Cr Bella advised that what Cr May was saying was an incorrect statement.
The Mayor advised Cr Bella that that was not a Point of Order and asked Cr May to
continue.
Cr May advised she believes the application has been conditioned appropriately,
meets all of the planning requirements and by putting some safe measures in place
where Council can address issues should they arise in the future. In relation to the
biosecurity, this quarry is currently in operation and if there was to be an outbreak of
weeds being transported from the site this would be occurring now. She believes
Council have applied the planning instruments available and conditioned, along with
the State Government, the application appropriately to meet the requirements.
The Mayor clarified for the Councillors what a Point of Order is under the current
Standing Orders - a Point of Order is "A Councillor may ask the Chairperson to
decide a point of order where it is believed that another Councillor has failed to
comply with proper procedure or is in contravention of these Standing Orders or the
Act or is beyond the jurisdictional power of the local government." The Standing
Orders state that "A point of order cannot be used as a means of contradicting a
statement made by a Councillor speaking about a matter".
Cr Casey advised he was not in favour of the Motion due to his concerns with the
road safety of the intersection of Bells Road and the Walkerston-Homebush Road.
Cr Bonaventura advised he was not in favour of the Motion due to road safety. He
advised during his recent inspection of the site he agrees it is an excellent site for a
quarry, however is slightly concerned in relation to the noxious weeds but believes
this could be controlled. The intersection and safety is Council's responsibility and
believes there should be a condition to improve this intersection that will see one
million tonnes per year travel through it.
The Mayor asked Cr Camm if she wished to exercise her right of reply.
Cr Camm advised Councillors had received correspondence from Nina Sandral to
draw Councillors attention to the road safety that has been discussed today,
particularly in relation to school children and the bus routes. She advised it is her
intention to work with the Office of the Mayor and CEO to contact the relevant
stakeholders to discuss the safety of the rural bus routes. In relation to the role of
submitters and applicants she advised she does not condone bullying tactics on any
level and confirmed she had received a copy of the correspondence that was sent to
submitters. She believes Councillors role is clear under the Local Government Act in
assessing development applications and it is to determine a planning scheme that
defines land use. For this reason and Council Officers expertise and their independent
review of this application along with various State Government departments she will
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49586
be voting in favour of this Motion. Over the next 2-3 years during the construction of
the Mackay Ring Road is going to cause massive impacts to the community but it is
doing this to get more trucks off the roads and by passing our region to result in better
public safety.
The Mayor put the original Motion for voting as follows now the debate was
finalised.
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Camm Seconded Cr Gee
CARRIED
Crs Bella, Bonaventura and Casey recorded their vote against the Motion.
11.7 MATERIAL CHANGE OF USE FOR AN EXTRACTIVE INDUSTRY
- FARM WORKS (DAM) AND TEMPORARY QUARRY FOR THE
REMOVAL OF UP TO 200,000 TONNES OF MATERIAL
(TEMPORARY USE 12 MONTHS) - 92 GLENDARAGH ROAD,
GLENELLA QLD 4740 (LOT 5 ON SP241649) - DA-2017-119
Application Number: DA-2017-119
Date Received: 28 November 2017
Action Officer: Shane Kleve
Applicant’s Details: Vella's Civil Construction
c/- Cardno (QLD) Pty Ltd
PO Box 759
MACKAY QLD 4740
Proposal: Material Change of Use - Extractive Industry
- Farm Works (dam) and temporary quarry
for the removal of up to 200,000 tonnes of
material (temporary use 12 months)
Site Address: 92 Glendaragh Road, Glenella
Property Description: Lot 5 on SP241649
Owner’s Details: G.W. Galletly Pty Ltd
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49587
Area: 30.06Ha
Planning Scheme: Mackay Region Planning Scheme 2017
Planning Scheme Designations:
Zone:
Rural
Assessment Level: Impact
Submissions: Four (4) submissions
Referral Agencies: Concurrence - Department of State
Development, Manufacturing, Infrastructure
and Planning (DSDMIP)
Attachments: Attachment A:
Attachment B:
Attachment C:
Attachment D:
Locality Plan
Proposal Plan
Referral Agency Response
Environmental Authority
Recommendation: Approved Subject to Conditions
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49588
ASSESSMENT OF APPLICATION
Purpose
This development application to Mackay Regional Council seeks a Development
Permit for a Material Change of Use for Extractive Industry - Farm Works (dam) and
temporary quarry for the removal of up to 200,000 tonnes of material (temporary use
12 months) at 92 Glendaragh Road, Glenella (refer to Attachment A – Locality Plan).
Submissions have been received and the submitters have raised issues of a planning
and environmental nature relating to the proposed use. The submissions have not
raised any grounds that cannot be appropriately conditioned or that warrant refusal of
the application.
The application is recommended for approval subject to conditions.
Subject Site and Surrounds
The subject site is approximately 10km north-west of the Mackay CBD and has a total
area of 30.06ha. The subject site comprises undulating to hilly terrain. The south-
eastern section of the lot ranges in height of approximately RL 11.7m to 30m AHD.
The site is predominantly used for grazing. Other features include farm sheds, cane
railway and remnant vegetation. The site has frontage to Glendaragh Road, from
which it gains access via a bitumen sealed driveway that extends approximately 12m
into the subject site. An unformed road reserve crosses the site, as detailed in the
Locality Plan. There are no reticulated water or sewer services available to the
property, however electricity is available to the site. There are easements across the
subject site, for access and electricity infrastructure.
The surrounding area is made up of other rural zoned land, including a permanent
quarry (Deguara’s Quarry) to the north, rural uses and Jane Creek to the south, rural
uses and dwellings to the west, and cane railway, dwelling and rural uses to the east.
Two dwellings are located approximately 700m to the south and one residence is
located more than 450m to the north-east. Residences to the west are shielded by the
hill immediately adjoining the quarry site.
Proposal
The proposed activity involves a temporary quarry for the removal of up to 200,000
tonnes of material (temporary use 12 months), and farm works (dam) (refer to
Attachment B – Proposal Plan). The proposed development requires a Material
Change of Use for Extractive Industry to enable the extracted material to be removed
from the site. It is noted that the construction of the farm works (dam) would not
trigger a material change of use if the extracted material was being retained on site
and used as part of the dam construction. The material change of use for the
extractive industry is triggered solely because the applicant intends to use the
extracted material offsite.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49589
The proposed activity involves excavation works for the export material from the site
for use on the Mackay Ring Road. The works are temporary, and the applicant has
indicated that they are expected to take up to 200,000 tonnes over a period not
exceeding 12 months. The proposed hours of operation are 6am to 6pm Monday to
Saturday, excluding public holidays.
The extraction and removal will be by mechanical means, including an excavator and
a rotation of haul trucks for removal of the spoil material. No blasting is proposed.
The area of works is approximately 1.5ha, and the extraction site ranges in height
from approximately RL 11.7m (base of excavation) to 30m AHD (top of batter). The
topsoil will be stockpiled and re-spread following completion of the use. It is
proposed that the completed site will be at an approximate height no lower than RL
11.7m AHD (base of dam). A water truck will be available for dust management.
The site has an existing access via Glendaragh Road, which will remain, and no
changes are proposed to this access point. No formal parking is proposed; however,
any cars will be accommodated on site in the proximity of the area of works. No
visitors are anticipated to the site.
MACKAY ISAAC WHITSUNDAY REGIONAL PLAN
The subject site is located outside of the regional plan Urban Footprint and within the
Regional Landscape and Rural Production area.
The regional plan states;
“4.4 Planning and managing agricultural land
Land suitable for agricultural production is identified, protected and managed
to provide for profitable and sustainable use of the resource. Use and
management programs build resilience to, or mitigate, the potential impacts of
climate change.”
It is considered that the farm work (dam) and construction of a temporary quarry will
be an asset to the future use of the site for agricultural purposes.
PLANNING SCHEME ASSESSMENT
The proposed development has been assessed against Council’s Mackay Region
Planning Scheme and is considered generally consistent with the intent of the
Scheme.
Strategic Framework
The strategic intent for the various parts of the Council area are outlined in the
Strategic Framework. The subject site is zoned Rural and contains agricultural land,
with the relevant elements below:
“The rural areas are protected from the impacts of urban growth and managed
to sustain their role in providing the natural resource base, maintaining the
landscape function and ecosystem services, and supporting agricultural
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49590
industries. Rural land is subject to sustainable agricultural practices and
catchment management that controls soil erosion and stream bank stability,
protects riparian vegetation and limits the movement of chemical residues and
nutrients from farms into the aquatic environment.”
“Agricultural land is protected from incompatible uses to prevent loss and
fragmentation of land for agricultural production. Agricultural land is a key
component of the resilience and diverse economic base of the Mackay region,
which includes local food supply and sugar cane production as a dominant
agricultural use.”
The proposed extractive industry is consistent with what is expected in the rural areas.
Further, while the extraction activities will impact on an area of agricultural land it is
considered that the resulting farm dam will facilitate continued and hopefully
improved agricultural opportunities on the site at the completion of the works.
Overall it is considered that the application is consistent with the intent of the
Strategic Framework.
Assessment Benchmarks
The application has been assessed against the following assessment benchmarks of
the Planning Scheme:
• Rural Zone Code
• Extractive Industry Code
• General Development Requirements Code
• Acid Sulphate Soils Overlay Code
• Agricultural Land Overlay Code
• Biodiversity Overlay Code
• Bushfire Hazard Overlay Code
• Landscape Character and Image Corridors Overlay Code
• Landslide Hazard Overlay Code
• Flood and Coastal Hazards Overlay Code
• Regional Infrastructure Corridor Overlay Code
A detailed assessment has been undertaken against the following codes:
• Rural Zone Code
• Extractive Industry Code
• General Development Requirements Code
Only the areas of non-compliance and provisions requiring management of conflicts
are discussed below.
Rural Zone Code
The proposal generally complies with the intent of the Rural Zone Code, except for
the Amenity provision PO12.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49591
The specific outcome for PO12 states:
“Development does not generate unreasonable levels of noise, odour, dust, air
emission, light or vibration impacts that affect:
(a) adjoining and nearby sites within a residential zone; and
(a) adjoining or nearby site containing an existing sensitive land use.”
There are no acceptable/probable solutions this provision.
The proposal adjoins a sensitive use, a dwelling approximately 450m to the northeast.
Amenity is partly ensured by limiting extraction methods to mechanical extraction
only (no blasting), hours of operation and regular use of water trucks; however, the
proposal does not include a Noise Impact Assessment. In the circumstance that the
quarry was proposed to be a permanent operation in the area it would be appropriate
to condition the provision of a noise impact assessment to demonstrate that the
operations would not create impact on sensitive land uses. However, with proposal
being a temporary approval and the nearest sensitive land use being 450m to the north
north east, it is considered that there is unlikely to be an impact from the operations.
It is noted that DSDMIP requested a noise impact assessment as part of their
assessment and the applicant responded by outlining the nature of the extraction
activity and its temporary nature. The applicant requested that any noise monitoring
be undertaken on a complaint basis due to the location of the activity and the
surrounding primarily rural land uses. DSDMIP accepted this response and did not
require the noise impact assessment to be undertaken. It is considered that this risk
based approach should also be taken by Council in the setting of conditions. A
condition in relation to noise generated by the activity has been included in the
proposed conditions to reinforce the requirement not to cause an environmental
nuisance and that noise monitoring and amendments to operations will be required if
complaints about noise are received and noise exceeds the limits legislated in the
Environmental Protection (Noise) Policy 2008.
It is considered that dust impacts can be effectively managed through the
recommended dust conditions and mitigation methods.
Extractive Industry Code
The proposal generally complies with the intent of the Extractive Industry Code,
except for the Utility Infrastructure and Services provisions: PO1, PO2, and the
Rehabilitation Works provision PO8.
The specific outcome for PO1 states:
“The extractive industry fulfils a demonstrated need for the resource in
development projects in the region.”
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49592
The acceptable/probable solution for AO1 states:
“The need for an extractive industry is demonstrated through a report which
details the: (a) type of resource to be extracted and the nature of its use in
development projects in the region; and
(b) proposed rate of extraction; and
(c) market demand for the resource.”
The applicant has not prepared a needs report in this instance. It is considered that the
proposal is considered acceptable, as the proposal is short term (temporary use up to
12 months) and the extraction fulfils a need for fill material that is located in close
proximity of the Mackay Ring Road. The proximity of the material will reduce
haulage impacts and costs.
The specific outcome for PO2 states:
“The extractive industry is located and operated to maintain public safety and
minimise potential noise, dust, vibration and visual amenity impacts on nearby
publicly accessible areas and sensitive land uses.”
The acceptable/probable solutions for AO2.2 states:
“Extractive industry operation areas are not located within 40 metres of any
boundary.”
The proposed quarry is set back 10m from the boundary of the adjoining temporarily
closed road and 30m from neighbouring properties. The proposal is considered
acceptable, as the nearest dwelling/sensitive use is approximately 450m to the
northeast, and no publicly accessible area is within close proximity of the quarry site.
Conditions are proposed to be applied to address dust impacts, with conditions
proposed to ensure that potential noise impacts will be addressed on a complaint basis
if any are received, which is consistent with the approach taken by DSDMIP.
The specific outcome for PO8 states:
“Rehabilitation works during, and at the cessation of the extractive industry
use, restore the environmental values and/or useability of the subject site.”
The acceptable/probably solutions for AO8.3 states:
“A bond for the performance of rehabilitation works is provided.”
The applicant is not proposing to provide a performance bond. This is considered
acceptable, as the proposal is short term (temporary use up to 12 months) and the site
will be used as a farm dam when the quarry use has ceased. Further, a rehabilitation
condition has been imposed, ensuring the subject site, other than the farm dam, is
rehabilitated to allow agricultural uses to recommence post operation.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49593
General Development Requirements Code
The proposal generally complies with the intent of the General Development
Requirements Code, except for the Amenity provision PO18.
The specific outcome for PO18 states:
“The acoustic amenity, privacy and liveability of residential areas and sensitive
land uses is maintained by ensuring that:
(a) noise generating development in close proximity to existing and/or future
sensitive land uses is located, designed and operated to minimise acoustic
impacts on the sensitive land use; and
(b) sensitive land uses in close proximity to existing and/or future noise
generating uses are located and designed to ensure minimal acoustic
impacts on the sensitive land use.
The acceptable/probable solutions for AO18.1 states:
“Development is located, designed and operated to achieve the following noise
levels when measured from:
• for proposed sensitive land uses: habitable rooms (assuming open
windows) nearest the noise source; and
• for proposed noise generating development:
- within the nearest habitable room (assuming open windows) of
adjoining / nearby sensitive land uses; and
- 2 metres beyond the boundary of the site and 1.5 metres above
ground level, here the adjoining site is undeveloped and in a
residential zone or intended to accommodate a sensitive land use;
(a) background (L90) + 5dB(A) for variable noise between the hours of
7:00 am to 10:00 pm; and
(b) background (L90) + 3dB(A) for variable noise between the hours of
10:00 pm and 7:00 am; and
(c) background (L90) for continuous noise sources (measured at the
facade of the sensitive use between 7:00 am and 10:00 pm and
within habitable rooms assuming open windows from 10:00 pm –
7:00 am); and
(d) maximum limit LAmax 45dB(A); and
(e) the acoustic quality objectives (internal noise criterion) for the
particular use identified in the Environmental Protection (Noise)
Policy 2008 or, if not listed, the internal sound level design criterion
contained in Australian Standard AS/NZS2107 Acoustics –
Recommended design sound levels and reverberation times for
building interiors.”
The proposal does not include an acoustic impact assessment. The applicant states
that the use is temporary, and that noise impact will be managed through maintaining
a vegetated buffer area to adjoining dwellings, hours of operation will be restricted
and that no blasting is to occur.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49594
DSDMIP requested a noise impact assessment from the applicant as part of their
assessment of the environmentally relevant activity component of the application.
The applicant has requested that noise issues be addressed only if complaints are
received due to the location and temporary nature of the operation. This has been
accepted by DSDMIP and it is considered that this approach should also be taken by
Council due to the location and temporary nature of the use. A condition in relation
to noise generated by the activity has been included in the proposed conditions to
reinforce the requirement not to cause an environmental nuisance and that noise
monitoring and amendments to operations will be required if complaints in relation to
noise are received and noise exceeds the limits legislated in the Environmental
Protection (Noise) Policy 2008.
Overlays
The subject site is affected by the following Overlays:
Acid Sulphate Soils Overlay Code
It is considered that the proposal complies with the Acid Sulphate Soils Overlay Code
as the proposed suite of conditions includes a requirement for the applicant to provide
a Site Based Acid Sulphate Soil Management Plan if disturbance of acid sulfate soils
is likely.
Agricultural Land Overlay Code
It is considered that the proposal is generally compliant with the Agricultural Land
Overlay Code. The majority of the subject site is mapped with Agricultural Land
Classification (ALC) A and B in the Mackay Region Planning Scheme. The area to be
developed is approximately 2ha and this is also mainly on land mapped as agricultural
land. However, the farm dam will be used to support agricultural uses on the site
once the quarry use has ceased, and the land outside the dam will be rehabilitated for
agricultural uses after the extraction activity has ceased.
Biodiversity Overlay Code
It is considered that the proposal generally complies with the Biodiversity Overlay
Code, based on the location of the works and the applicants proposed Management
Plans for the operation of the extractive industry.
Bushfire Hazard Overlay Code
It is considered that the proposal complies with the Bushfire Hazard Overlay Code, or
where compliance has not been demonstrated it is not relevant to the activity. The
subject site is mapped in part with high and very high bushfire hazard, however, only
a very small proportion of the high bushfire mapped area encroaches in to the
development area and other than demountable site offices and amenities, there will be
no built infrastructure that could be impacted during a bushfire event.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49595
Landscape Character and Image Corridors Overlay Code
It is considered that the proposal complies with the Landscape Character and Image
Corridors Overlay Code. The location of the extraction operation is outside of the
remnant vegetation on the site and it has been conditioned that rehabilitation work is
to be undertaken upon completion of the work on site.
Landslide Hazard Overlay Code
It is considered that the proposal complies with the Landslide Hazard Overlay Code
as the extraction site is located on land with a gradient less than 15%.
Flood and Coastal Hazards Overlay Code
It is considered that the proposal complies with the Flood and Coastal Hazards
Overlay Code. Only a very small part of the operation area is impacted by the overlay
mapping, and the use by its nature would not be effected should the site be flooded
during its operation as a quarry other than the requirement to pump out the extraction
area to allow extraction to recommence.
Regional Infrastructure Corridor Overlay Code
It is considered that the proposal complies with the Regional Infrastructure Corridor
Overlay Code. The site is mapped as containing a cane railway and a powerline
easement.
The powerline that was covered by the easement has been removed from the property
and it is likely that the easement itself will be in the process of being extinguished as
it is no longer necessary.
The cane railway is not located in the area of the extraction and Mackay Sugar have
advised that they have no concerns with the proposed activity, based on the plans
contained in the application material.
INFRASTRUCTURE CONSIDERATIONS
Water & Sewer
The subject site is not connected to Council’s reticulated water or sewer services. On-
site facilities will be provided by the operator as required by relevant Workplace
Health & Safety legislation and employee requirements.
Stormwater
The applicant has stated that stormwater quality will be managed within the quarry /
dam, functioning as a sedimentation pond. Overland flow is to be diverted away from
the dam site, ensuring no runoff into the dam during construction. Water collection is
expected to be minimal during the extraction / construction period, which will be
pumped out as required once the sediment has settled.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49596
Council maintains erosion and sediment control conditions to comply with the
planning scheme, in addition to the stormwater quality conditions in the
Environmental Authority (EA0001187) by the Department of Environment and
Heritage Protection. The Aurecon Environmental Assessment and Management Plan
requires that the developed stormwater runoff will be returned to pre-developed flow.
Roadworks
The development will be accessed from the existing access point via Glendaragh
Road. The applicant has submitted a Traffic Impact Assessment (31 January 2018,
Aurecon), which recommends a temporary traffic management plan to control ingress
and egress from the site rather than proposing any physical works at the intersection.
It is recommended that a temporary traffic management plan as proposed by the
applicant be conditioned as satisfactory based on the temporary use, and on the
condition the traffic management plan is completed by a qualified person and
approved by Council. This will encourage the temporary use. The intersection safety
will be controlled by the traffic management plan.
Further, it is recommended that a condition be imposed for the works for mitigating
incremental road degradation. The applicant shall undertake a road impact assessment
of Local Government controlled roads that form part of the haulage route, such as
Glendaragh Road and determine the incremental maintenance requirements as a result
of the predicted increase in traffic volume and impact. The Road Impact Assessment
must be submitted to Council for approval. The applicant shall undertake the
necessary road works to mitigate the incremental degradation.
Dust suppression is detailed in the Environmental Assessment and Management Plan
by Aurecon and is conditioned in the Environmental Authority Permit. It is
recommended that Council condition these aspects of the development accordingly.
REFERRAL AGENCIES
The application was referred to the Department of State Development, Manufacturing,
Infrastructure and Planning (DSDMIP), as a concurrence agency, for the following
triggers:
• Planning Regulation 2017, Schedule 10, Part 9, Division 4, Subdivision 1:
Infrastructure – State Transport Infrastructure.
• Planning Regulation 2017, Schedule 10, Part 5, Division 4: Environmentally
Relevant Activity (ERA) 16.
The application was also referred to Powerlink, acting as an advice agency, for the
following trigger:
• Powerlink Easement in proposed area
The DSDMIP and Powerlink have approved the use subject to conditions (refer to
Attachment C – Referral Agency Responses).
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49597
ADOPTED INFRASTRUCTURE CHARGES REGIME
Infrastructure Charges are not applicable to the development as there is no gross floor
area or impervious area proposed as part of the operations.
SUBMISSIONS
The application was publicly notified in accordance with the requirements of the
Planning Act 2016, and as a result of this process, four (4) submissions were received.
The submissions received, expressed concern about the proposal. The principle
concerns raised from the submissions are summarised under the following headings
and discussed below.
1. Dust;
2. Traffic Impacts;
3. Noise;
4. Impacts on the Surrounding Environment;
5. Infrastructure Provision;
6. Dam;
7. Approval Period and size of extraction area;
8. Planning Scheme Intent and Need of Quarry;
9. Legislation Compliance; and
10. Conflict of Interest.
1. Dust
In summary, the submitters had the following concerns in relation to dust: -
• Concern of increase in dust in existing nearby dwellings.
• Dust can have a detrimental impact on health in humans, wildlife, livestock,
vegetation.
Applicant’s Response:
“A Water truck will be maintained at the site to manage dust as required. Complaint
management procedures have been detailed in the common material.”
Officer’s Comments:
It is considered that dust impacts can be effectively managed through the
recommended conditions. A detailed description of the potential airborne dust
generation and greenhouse gas emission impacts and the proposed mitigation
measures for dust/air quality control is included in section 3.3 Air Quality of the
Environmental Assessment and Management Plan prepared by Aurecon dated 31
January 2018. The mitigation measures outlined in the Management Plan have been
recommended to be conditioned.
2. Traffic Impacts
In summary, the submitters had the following concerns with regards to Traffic
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49598
Impacts:-
• Speed limit to be reduced as a result of the extra heavy traffic along
Glendaragh Road
• Temporarily closed road and provision of access to neighbouring Lot 4 on
RP910713
• Traffic dangers on the Bruce Highway
• Tramline concerns
Applicant’s Response:
“It is proposed that a traffic management plan be put into place for management of
trucks along Glendaragh Road – a defined KRA transport route. The traffic plan will
take speed management into consideration.”
“The road reserve is not misrepresented in the application. Furthermore, the
application does not prevent use of the road.”
“Bruce Highway: The application has been referred to the DTMR via SARA, who
has provided a Concurrence Response approving the development application.”
“The excavation and dam will not impact on the safety or use of the tramline. Refer
to comments below:
• The dam is exempt development being for agricultural purposes. However, the
dam is mentioned in the development application for completeness and is
relevant to determine rehabilitation works required at the completion of the
project. Should the dam overtop, flows will not be greater than pre-
development flows as there is no increase in impervious area. The approximate
volume of the dam will be 24ML.
• The dam will only have a small effect on surface flows in the immediate vicinity
of the dam.”
Officer’s Comments:
The Traffic Impact Assessment by Aurecon dated 31 January 2018 recommends to
retain the existing property access, and to adopt a Traffic Management Plan with
associated controls in place, such as reduced speed signage, warning signs, UHF, and
manned traffic control. It is recommended that a condition to this effect be imposed.
Lot 4 on RP910713 has legal access through an easement via Larkins Road
(Easement G on RP 910713, specifying that Easement G is for Right of Way
purposes). As such, there will be no change to the current access arrangements for
the surrounding properties.
As mentioned above, the application was referred to Department of Main Roads via
SARA. A response was received approving the application with conditions.
Advice has been received from Mackay Sugar Limited, who advised that from a cane
railway point of view, the proposal does not present concerns.
In summary, it is considered that the traffic impact concerns can be appropriately
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49599
conditioned.
3. Noise
In summary, the submitters had the following concerns in relation to noise: -
• The development will cause added noise to the nearby residents, livestock and
wildlife.
Applicant’s Response:
No response received regarding noise.
Officers Comments:
The proposed quarry is situated south/southwest from the nearest residence,
approximately 450m away. Prevailing winds in the area tend to come from the
south/southeast, i.e. towards the residence, and operation hours of 6am to 6pm
Monday to Saturday has potential to increase the noise levels in the area. The
Environmental Authority (refer to Attachment D – Environmental Authority)
conditions noise impacts, based on not causing environmental nuisance to any
sensitive place. DSDMIP has accepted the applicants request for noise monitoring to
be required only if complaints are received by the relevant State department. It is
considered that due to the location of the activity and its temporary nature, that
Council should follow the State in leaving noise issues to be addressed as and when
complaints are received. A condition in relation to noise generated by the activity has
been included in the proposed conditions to reinforce the requirement not to cause an
environmental nuisance and that noise monitoring and amendments to operations
will be required if complaints are received and noise exceeds the limits legislated in
the Environmental Protection (Noise) Policy 2008.
4. Impacts on the Surrounding Environment
In summary, the submitters had the following concerns in relation to impact on the
surrounding environment: -
• Impacts to the Jane Creek ecosystem
• Impacts to the local flora and fauna
• Spread of noxious weeds
Applicant’s Response:
“It is not expected that there will be any significant intermittent or residual impact
on Jane Creek or the wider reef catchment. Refer to comments below:
• The dam is exempt development being for agricultural purposes. However, the
dam is mentioned in the development application for completeness and is
relevant to determine rehabilitation works required at the completion of the
project. Should the dam overtop, flows will not be greater than pre-
development flows as there is no increase in impervious area. The approximate
volume of the dam will be 24ML.
• The dam will only have a small effect on surface flows in the immediate vicinity
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49600
of the dam.”
“The subject site is not designated as an essential habitat area or regulated
vegetation. Therefore, there is no implication on the development beyond the general
environmental duty of care.”
“Prevention of potential weed spread can be conditioned as relevant.”
Officers Comments:
The application has been assessed by the Department of Environment and Heritage
Protection and an Environmental Authority has been issued, which sets out
legislative requirements and conditions that the applicant must comply with. Further,
it is recommended that a condition be imposed to require rehabilitation of the site at
the completion of the approved extraction via a rehabilitation plan.
Council’s local law officers have recommended that if noxious or invasive weeds or
other biosecurity risk is identified on the site, the following control measures be
conditioned on the development and included in the Environmental Management
Plan.
• Regular spraying of invasive biosecurity matter to be conducted with
appropriate chemical
• No top soil (150mm depth) to be removed from site
• Any contaminated material to be stockpiled on site and treated
• All roadways, laneways and water courses to be kept weed free
• Create and maintain a 10m weed free buffer zone around perimeter of property
• Create a clean down area for machinery. This area to be bunded and monitored
for invasive biosecurity matter. If found must be treated immediately.
• All equipment must be cleaned before leaving site.
5. Infrastructure Provision
In summary, the submitters had the following concerns about infrastructure
provision: -
• No infrastructure is available to the site.
Applicant’s Response:
No response was received by the application regarding infrastructure provision
Officers Comments:
Due to the remote nature of some extractive industries it is not unusual that they do
not have access to reticulated infrastructure.
6. Dam
In summary, the submitters had the following concerns about the proposed Dam: -
• What is the size of the Dam
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49601
• The location of the Dam
• Dam’s effect on Bore
• Environmental impacts as a result of the Dam
Applicant’s Response:
“The dam is exempt development being for agricultural purposes. However, the dam
is mentioned in the development application for completeness and is relevant to
determine rehabilitation works required at the completion of the project. Should the
dam overtop, flows will not be greater than pre-development flows as there is no
increase in impervious area. The approximate volume of the dam will be 24ML.”
“Agriculture is not regarded as a sensitive land use. The extraction site is beyond the
required separation distances to sensitive uses (e.g. dwelling houses) specified in the
Planning Scheme for extractive industries not involving blasting.”
“The proposed dam will decrease runoff, as it does not introduce any impervious
areas, but instead will capture a proportion of the natural flow into the dam. The
diversion drains will be designed and approved through a sediment and erosion
control plan, to be prepared as part of the subsequent Operational Works detailed
design requirements”
“The dam will only have a small effect on surface flows in the immediate vicinity of
the dam.”
Officers Comments:
It is noted that the construction of the farm works (dam) would not trigger a material
change of use if the extracted material was being retained on site and used as part of
the dam construction. The material change of use for the extractive industry is
triggered solely because the applicant intends to use the extracted material offsite.
7. Approval Period and Size of Extraction Area
In summary, the submitters had the following concerns about the life of the
approval: -
• Is it a temporary quarry?
• An approval allows for the entire site to be used
Applicant’s Response:
“Approval is sought in accordance with the proposed plan of development, which is
specific to the area of the property where the work is proposed.”
Officers Comments:
It is recommended that conditions be imposed specifying clearly that the use is
temporary only, up to 12 months, and up to 200,000 tonnes of material can be
extracted. Further, it is recommended that a condition specifies that only the area
clearly outlined on the plan of development can be extracted. Such restrictions are in
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49602
place in the environmental authority as well as the recommended approval
conditions. No extraction will take place outside this mapped area.
8. Planning Scheme Intent and Need for Quarry
The submitters had concerns about planning scheme intent and the need of the
proposal.
Applicant’s Response:
“The Town Planning Report by Cardno addresses the planning scheme intent and
concludes that the proposed extractive industry and farm dam is a consistent use.
Refer to Section 6 of the report for discussion.”
“The development proposal is considered to be consistent with the Planning Scheme.
Accordingly, it is not relevant to consider need.”
Officers Comments:
The proposed use is consistent with the intent of the Mackay Region Planning
Scheme. The applicant has not prepared a needs report in this instance. The proposal
is considered acceptable, as the proposal is short term (temporary use up to 12
months). The extraction fulfils a Queensland Government need for clean fill in close
proximity of the Mackay Ring Road.
9. Legislation Compliance
In summary, the submitters had the following concerns: -
• Public Notification was not undertaken in accordance with the legislative
requirements as the dates on the notices were inconsistent.
• Incorrect description of proposed activity
• Incorrect referral process
• Invalid application as an Operational Works was not applied for.
Applicant’s Response:
“Public notification has been carried out in accordance with the requirements of the
Planning Act and associated DA Rules.”
“The application has been confirmed as being properly made by the Mackay
Regional Council as the Assessment Manager.”
“The application has been properly referred to the State for assessment of State
Codes.”
Officers Comments:
Council is satisfied that the public notification was adequately undertaken, as
evidenced by the number of submissions received. The description of the proposed
activity is correct in accordance with the Mackay Region Planning Scheme. The
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49603
State has responded as a Concurrence Agency to the application, and as such it is
considered that the correct referral process has been undertaken. The Operational
Works component of the development can be applied for separately as is standard
practice, however, it is considered that an operational works application is not
applicable in this instance.
10. Conflict of Interest
The submitters had concerns about conflict of interest with Aurecon and Stage 1 of
the Ring Road project.
Applicant’s Response:
“Aurecon have been engaged to provide technical reporting only, and it is not their
scope to address town planning matters.”
Officers Comments:
Council officers are satisfied that the report from Aurecon is independent of Stage 1
of the Ring Road project.
It is considered that the submissions have not raised any issues of sufficient concern
to warrant refusal of the application.
RESOURCES IMPLICATIONS
Nil.
RISK MANAGEMENT IMPLICATIONS
Nil, other than if an appeal is lodged by the applicant or submitters in response to the
approval or its conditions.
CONSULTATION
External
The application was publicly notified in accordance with the Planning Act 2016 and it
has been determined the requirements of the Act has been satisfied in this respect.
Internal
The application has been tabled at Council’s internal development enquiries meeting
where the proposal was considered appropriate rural development in this rural
locality.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49604
CONCLUSION
This proposal for an Extractive Industry - Farm Works (dam) and temporary quarry
for the removal of up to 200,000 tonnes of material (temporary use 12 months) is
recommended for approval, as it is considered that any conflicts with the Planning
Scheme are not sufficient to warrant refusal of the application.
The proposed extractive industry will fulfil a need that exists for quarry material for
stage 1 of the Mackay Ring Road project, and therefore it is considered that there is a
need for the proposed development. The nature of the use means that it must be
located where appropriate quarry material exists.
The concerns raised by submitters, particularly in relation to dust, noise, traffic and
impacts on the surrounding environment can be appropriately conditioned. It is
important to note that the farm dam aspect of the proposal does not require an
approval from Council and the proposed quarry is temporary only and has been
conditioned to cease in 12 months from the commencement of the use or when 200,00
tonnes of material has been extracted, whichever comes first. Any extension of this
time period, or extraction limit, will require a separate application to Council.
The application is recommended for approval, subject to conditions.
Officer's Recommendation
A. THAT Council approve this an Extractive Industry - Farm Works (dam)
and temporary quarry for the removal of up to 200,000 tonnes of material
(temporary use 12 months) at 92 Glendaragh Road, Glenella, QLD 4740
in accordance with the following Assessment Manager conditions and
Assessment Manager Advice:
1. Plan of Development
The approved Extractive Industry development must be completed
and maintained generally in accordance with the Plan of
Development (identified in the Table below) and supporting
documentation which forms part of this application, except as
otherwise specified by any condition of this approval.
Project
Drawing
Number
Revision Prepared by Date
Lot 5 SP241649
92 Glendaragh Road
0001 C Aurecon 26.02.18
Lot 5 SP241649
92 Glendaragh Road
0004 C Aurecon 26.02.18
Lot 5 SP241649
92 Glendaragh Road
0005 C Aurecon 26.02.18
Lot 5 SP241649
92 Glendaragh Road
0006 B Aurecon 26.02.18
Lot 5 SP241649
92 Glendaragh Road
0007 B Aurecon 26.02.18
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49605
Project
Drawing
Number
Revision Prepared by Date
Lot 5 SP241649
92 Glendaragh Road
0008 B Aurecon 26.02.18
2. Compliance with Conditions
All conditions must be complied with prior to the commencement of
the use on the subject site, unless specified in an individual
condition.
3. Maintenance of Development
The approved development (including landscaping, car parking,
driveways and other external spaces) must be maintained in
accordance with the approved drawing(s) and/or documents, and
any relevant Council engineering or other approval required by the
conditions.
4. Blasting
Extraction by blasting is not permitted.
5. Conflict between plans and written conditions
Where a discrepancy or conflict exists between the written
condition(s) of the approval and the approved plans, the
requirements of the written condition(s) will prevail.
6. Notice of Intention to Commence the Use
Prior to the commencement of the use on the site, written notice
must be given to Council that the use fully complies with the
decision notice issued in respect of the use (please see attached
notice for your completion and return to
7. Temporary Approval
This approval will lapse at the sooner of:
a) 12 months from the date of the commencement of the use.
OR
b) Maximum extraction of 200,000 tonnes is reached.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49606
8. Hours of Operation
The use may operate only between the hours of 6am to 6pm
Monday to Saturday, excluding public holidays. Extractive activities
must not be conducted on public holidays.
9. Settlement Ponds
Any settlement ponds to be used for retention of discharged water
must be maintained to ensure that offensive or noxious odours do
not emanate from the site, causing an environmental nuisance.
10. Dust Control
All roads/storage areas/external stockpiles/vacant or grazed areas
must be maintained to avoid dust nuisance to surrounding areas,
including any adjacent dwelling or sensitive land uses to the
satisfaction of the Council.
The mitigation measures listed in the Environmental Assessment
and Management Plan by Aurecon dated 31 January 2018 must be
strictly adhered to. These include, but are not limited to:
• Utilise fuel efficient vehicles
• Avoid idling vehicles where possible
• Turn off vehicles when not in use
• No burning of wastes on site
• Landscaping and rehabilitation of site will occur as soon as
possible following staged extractive activities
• Dust generating areas will be watered down on a regular basis
• Minimise or cease earthworks in periods of high winds
• All vehicles will observe speed limits
• All trucks transporting material to and from the site will cover
their loads
• Regular observations of site conditions to occur to determine
if dust is an issue and mitigation measures will be applied as
appropriate
• Record all dust complaints on Incident Notification Report
• Confine traffic to designated tracks and haul roads
• Avoid stockpiling extracted material
• Limit topsoil stockpile heights and regularly water down to
prevent dust emissions (until natural topsoil stockpile
regrowth grass cover is established.
• If requested by DEHP, conduct dust monitoring to investigate
a complaint
• Any material (i.e. dirt) spilt or tracked into external roads will
be cleaned up and removed.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49607
11. Environmental Management Plan
Operation of the Extractive Industry must be in accordance with the
Environmental Assessment and Management Plan prepared by
Aurecon dated 31 January 2018. Where there are inconsistencies
between these conditions and the Management Plan, the conditions
shall prevail.
12. Weed Management
In accordance with the QLD “Biosecurity Act 2014” every person
or organisation has a General Biosecurity Obligation to take all
reasonable and practical measures to prevent or minimise the
biosecurity risk.
Weed management must be undertaken onsite in consultation with
Council’s Pest Management Officer and include an initial joint
inspection of the site with the operator and Councils Pest
Management Officer to investigate the proposed quarry location to
identify the possible presence of weeds or other Biosecurity risk. If
any risk is identified the following requirements must be
implemented:
a) Regular spraying of invasive biosecurity matter to be
conducted with appropriate chemical
b) No top soil (up to 150mm deep) to be removed from site
c) Any contaminated material to be stockpiled on site and treated
d) All roadways, laneways and water courses to be kept weed
free
e) Create and maintain a 10m weed free buffer zone around the
perimeter of the site
f) Create a clean down area for machinery. This area is to be
bunded and monitored for invasive biosecurity matter. If
found it must be treated immediately.
g) All equipment must be cleaned before leaving site.
13. Fuel Storage
Any storage of fuel onsite is to be in accordance with AS1940-
2004-Storage and Handling of Flammable and Combustible Liquids.
14. Site security
Prior to the commencement of the use, the site must be secured to
ensure no unauthorised entry to the satisfaction of Council.
15. Extraction Limits
The maximum extraction amount approved is 200,000 tonnes.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49608
16. Compliance with Council Standards
All design and construction for the development must be in
accordance with Council’s Policies, Engineering Design Guidelines,
Standard Drawings and Standard Construction Specifications.
17. Damage
The developer is responsible for the repair of any damage that is
caused to Council’s infrastructure as a result of the construction
works associated with the proposed development. The developer
must make any damage safe and then notify Council immediately.
Council will make the decision as to who will carry out the
rectification works and the timing for the completion of those
works.
18. Access
The existing access must be utilized for ingress and egress from the
site.
19. Traffic Management Plan
A Traffic Management Plan must be prepared by a Registered
Professional Engineer of Queensland (RPEQ) with competency in
traffic engineering and submitted to Council for Approval. This
report must include the incremental traffic generation due to the
proposed quarry operation.
The approved Traffic Management Plan must be implemented at all
times during the operation of the approved use.
20. Works for Mitigating Incremental Road Degradation
The applicant shall undertake a road impact assessment of Local
Government controlled roads that form part of the haulage route,
such as Glendaragh Road, and determine the incremental
degradation and maintenance requirements as a result of the
predicted increase in traffic volume and impact. The Road Impact
Assessment must be submitted to Council for approval. The
applicant shall undertake the necessary road works to mitigate the
incremental degradation.
Advice Note:
Council may be prepared to enter into an Infrastructure Agreement
in relation to the works required due to accelerated maintenance
caused by the haulage activities.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49609
21. Stormwater Drainage
Stormwater from the site shall be controlled within the property
boundaries and discharged via the existing drainage paths, generally
in accordance with the approved plans and Sections 3.5 and 3.7 of
the Environmental Assessment and Management Plan prepared by
Aurecon (dated 31 January 2018, Reference 501663).
No worsening of stormwater runoff in terms of quantity, quality and
nuisance runoff (frequent flow causing erosion or unusable wet
areas) must occur at the discharge point or subsequent downstream
properties. Stormwater detention and stormwater treatment must be
provided appropriately to ameliorate any issues.
22. Ponding and Diversion of Stormwater
Ponding of stormwater resulting from the development must not
occur on adjacent sites and stormwater formerly flowing onto the
site must not be diverted onto other sites. The site shall be graded
so that it is free draining.
During the operational phase of the quarry, the runoff from
upstream (north of the site) must not be mixed with the quarry
operation area to ensure the quality of runoff downstream of the
quarry satisfy the water quality objects of the State Planning Policy.
23. Site Based Stormwater Management Plan
Stormwater Quality Best Management Practices (SQBMP) must be
developed and implemented in accordance with Sections 3.5 and 3.7
of the Environmental Assessment and Management Plan prepared
by Aurecon (dated 31 January 2018, Reference 501663).
24. Water Supply/Sewage Treatment
Potable water supply and sewage treatment are to be supplied to
site, if required, in accordance with the relevant codes and
guidelines.
25. Site Rehabilitation
At the completion of the approved extraction activity and
commencement of use of the farm dams, rehabilitation of the
construction area must be undertaken generally in accordance with
Section 3.12 of the Environmental Assessment and Management
Plan prepared by Aurecon (dated 31 January 2018, Reference
501663) and to the satisfaction of Council and include but not be
limited to
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49610
a) Clean-up works including area of possible soil contamination
by fuels or weeds etc.
b) Landform and soil profiles which approximate those which
were pre-existing on the site (excluding the dam areas and
associated stormwater infrastructure).
c) Monitoring for all aspects of the operations for 12months
d) Providing a stable and sustainable land form upon the
cessation of operations
e) The disturbed areas are to be suitable for the future land use.
26. Noise Impacts during Operations
Noise generated by the quarry operations must not create an
environmental nuisance to any sensitive place or land use as defined
in the Environmental Protection Act 1994 and Environmental
Protection (Noise) Policy 2008.
Should complaints be received about noise generated by the
operation of the approved use the applicant must undertake noise
monitoring to assess the noise generated by the activity. If the noise
levels exceed the level permitted by the Environmental Protection
(Noise) Policy 2008, the operator of the quarry must amend the
operations or equipment used on site to ensure the noise levels are
not exceeded.
B. THAT the applicant be provided with the following Assessment Manager
Advice:
1. Infrastructure Charges Notice
The approved use does not include any additional gross floor area or
impervious areas. Accordingly, no Infrastructure Charge will be
levied.
2. Local Laws
The approved development must also comply with Council’s current
Local Laws under the Local Government Act 2009.
3. Dust Control
It is the applicant/owner’s responsibility to ensure compliance with
Section 319 General Environmental Duty of the Environmental
Protection Act 1994, which prohibits unlawful environmental
nuisance caused by dust, ash, fumes, light, odour or smoke beyond
the boundaries of the property during all stages of the development
including earthworks and construction.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49611
4. Sedimentation Control
It is the applicant/owner’s responsibility to ensure compliance with
Chapter 8, Part 3C of the Environmental Protection Act 1994 to
prevent soil erosion and contamination of the stormwater drainage
system and waterways.
5. Noise During Construction and Noise in General
It is the applicant/owner’s responsibility to ensure compliance with
Chapter 8, Part 3B of the Environmental Protection Act 1994.
6. General Safety of Public During Construction
It is the principal contractor’s responsibility to ensure compliance
with Section 19 (2) of the Work Health and Safety Act 2011. Section
19 (2) states that a person conducting a business or undertaking
must ensure that the health and safety of other persons is not put at
risk from work carried out as part of the conduct of the business or
undertaking.
It is the responsibility of the person in control of the workplace to
ensure compliance with Section 20 (2) of the Work Health and
Safety Act 2011. Sections 20 (2) states that the person in control of
the workplace is obliged to ensure that the means of entering and
exiting the workplace and anything arising from the workplace are
without risks to the health and safety of any person.
7. Acid Sulphate Soils
If the proposed works trigger the State Planning Policy 2017 in
relation to Acid Sulfate Soils, a Site Based Acid Sulphate Soil
Management Plan must be prepared by a suitably qualified
professional and submitted to Council for approval as part of the
Operational Works application.
PUBLIC PARTICIPATION
The Mayor welcomed the members of the public in the Public Gallery who had
registered to speak to this item on the agenda today and provided an explanation on
the procedure of public participation.
Anne Agius
Advised there are a number of oversights in this report and she would like to address
them today.
1) Road Access
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49612
The Noonan farm is made up of two lots, the home on lot 4 and cattle and sugar land
on lot 6. The quarry application on lot 5 restricts road access from Glendaragh Road
to the Noonan home and land on lot 4. The access route from Glendaragh Road is not
a gazetted road but for the past 50 years it is the track used by farmers. Access from
Glendaragh Road is the only access the Noonan farm can legally bring in truck loads
over 10 tonnes as there is a 10 tonne truck limit on Richmond Road making access
through Larkin Road illegal.
2) Gates
The application states the it does not prevent use of the road but there will be fencing
and locked security gates 24/7. How are the Noonan's to access their farm and home
and conduct normal agricultural activates through locked security gates.
She advised the Noonan's have lodged an application to have the legal access to their
farm reopened, there is currently an application before the DNRM to left the
temporary closure of the gazetted road into lot 4.
She is also concerned with public safety as there will be haulout drivers, loco crews
and farmers will have to pass within 40 meters of the site and encounter trucks
leaving the site at a rate of 18 trucks per hour.
Julie Weir
Ms Weir advised she would like to raise several errors she feels are in the application.
The size of the dam when requested on 23 February 2018 from the applicant was
stated as the average depth of 2.5 with a total volume of 2.4 megalitres (size of one
Olympic pool). The Planning Department of Council in April 2018 shows the quarry
hole of 10 Olympic pools which is a significant difference. This application is based
on their report and is incorrect and this should be alarming to Councillors. The quarry
maybe temporary for 12 months but the dam left at the completion is left forever. This
quarry and the resulting dam is within 80 metres of Jane Creek that feeds the
Gooseponds. If Council approve the Material Change of Use today for Lot 5 it is not
just for one site it is for the entire 30 hectares of Lot 5 opening up all that land to
future quarrying. An application for extension to this temporary quarry needs only go
to the Council Planning Department and does not have to be approved by Councillors.
Joe Noonan
Mr Noonan advised if the application was approved today then a structure will be
built along the very floodplain that carried the flood that devastated Glenella in 2008.
The proposed dam and quarry in the application is right on the edge of the floodplain.
When this dam overflows there is no buffer, if the water from the dam is not used
regularly then there is no buffer capacity exposing the lower lying residential areas to
potential flooding over and above the normal flood events.
Ursula Noonan
Ms Noonan wanted to raise the issue of noise. The Department of Infrastructure
requested a Noise Impact Statement but this was rejected by the applicant who wants
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49613
to address noise issues only if they are complaints. There will only be three (3) hours
during the day that will be noise free and that will occur for six (6) days per week.
The applicant also does not have to pay a bond under the Extractive Industry Code,
they don’t have to put any permanent infrastructure to cope with additional traffic or a
needs assessment to justify the need for another quarry because this is a temporary
project. She also stated that the map on page 256 of the Agenda is incorrect as it
includes Noonan land in the site works.
Marie McCusker
Ms McCusker advised her home overlooks the proposed site for the quarry and is
concerned with the intersection between Glendaragh Road and the Bruce Highway.
She currently sees risk taking behaviour occurring at this intersection now and with
the increased traffic flow as a result of this application this will multiply. She advised
she supports everything the previous speakers have raised and if you are aware that in
the next 2-3 years there is going to be an increased onus on managing risks then why
is this not done proactively. This quarry is proposed in a beautiful pristine area that is
less then 2km from Glenella, how does this fit in with Council's future regional plan.
The Mayor acknowledged the residents for their attendance at today's Council
Meeting and thanked them for their input on this agenda item.
The Chief Executive Officer (CEO) advised that Ms Noonan is correct that the area
on the map contained within the report is incorrect, and had been already identified as
incorrect and a revised plan has been circulated to the Councillors already and will be
corrected when the Minutes of the Meeting are circulated with the correct map be
included.
The Mayor asked the Councillors to first address the recommendation by the Officer's
and if amendments are requested or alternative motions raised they would be
addressed at the appropriate stage and called for questions from the Councillors.
Cr May queried in relation to the traffic management plan and entering and exiting the
site how can she be assured that there will be traffic control officers there every time a
truck enters or leaves the site. How does Council ensure the safety of the users of
Glendarah Road if the traffic management plan is not being adhered to?
A/DDS advised the traffic management plans are compiled by companies that do this
on a professional basis and they are all about safety. These companies are liable for
all safety issues and if there is a recommendation from the traffic management plan to
have traffic controllers on site at any stage and they are not there it would be up to the
traffic controllers and the operator to be liable for not adhering to the traffic
management plan.
The Mayor queried further from Cr May's query is he needs clarification on the exit
and entry to Glendarah Road, the traffic control over the hill leading up to that exit
and entry point and the exit and entry point to the Bruce Highway. Has this all been
taken into account in terms of the traffic management, particularly the number of
movements expected on the site to extract 200,000 tonnes over four months.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49614
A/DDS advised the traffic management plan needs to be compiled and it is a
condition in the report and that all of those issues would have to be reviewed.
The Mayor queried if all Council has conditioned is that there will be a traffic
management plan.
A/DDS advised yes that was correct.
Cr May queried how can Council be assured that the adjoining landowners, who were
given verbal agreement, will be given access to the locked gate.
A/DDS advised that the management plan would need Council approval so it could be
included in the traffic management plan.
Cr May queried the extension of time, this application is temporary for 12 months,
given the issue has been raised around whether this would come back to Council for
approval can the procedure be clarified.
A/DDS advised the applicant has 12 months from the start of operations and if an
extension is requested a report would need to be prepared for formal Council
consideration and approval.
Cr May queried is there going to be any rehabilitation of the site if the dam is being
created and if vegetation is removed will this be reinstated at the end of the quarrying.
A/DDS advised there is an Environmental Relevant Activity (ERA) report that deals
with site rehabilitation and condition 25 deals with site rehabilitation.
Cr Camm queried if the dam could be constructed now without Council approval if
the applicant was moving no fill off site.
The CEO advised for the size of the dam being requested they would not be required
to obtain Council approval.
Cr Camm queried if that was applicable to this location.
The CEO advised that was correct.
Cr Mann queried in relation to the reactive complaints based issues, is there any
ability for Council officers to check regularly on progress of the application rather
than wait for complaints based activity.
A/DDS advised the complaints would be forwarded to the Local Laws officers for
their investigation, there are also audits carried out throughout the process of material
change of use applications to ensure the conditions are being adhered to.
Cr Bonaventura sought clarification as he understood it was not Council who would
be investigating the complaints in relation to the ERA and it would need to go through
a State Government department.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49615
The Mayor asked Cr Mann what her query was in relation to.
Cr Mann advised they were in relation to general conditions of the application.
Cr Bella queried in relation to the traffic management plan and the traffic controllers
of the control of flow on the vehicles leaving and entering the site or is it on the
control of flow on the normal residential traffic or is it on both.
The Mayor advised the traffic management plan has yet to be formalised and
Councillors have all these valid questions around the traffic management plan but the
A/DDS has stated that the condition is that there will be a traffic management plan.
He advised there is a fair degree of concern from Councillors about what the traffic
management plan may be made up of.
A/DDS advised the traffic management plan would need to consider all of the
concerns and provide direction as to what goes into the traffic management plan
which is subject to Council approval.
The Mayor queried if Councillors will get an ability to input into the traffic
management plan.
The CEO advised the traffic management plan is a condition that there must be one
that Council officers must approve but it does not come back to elected members.
Cr Bella advised any traffic management plan would need to take into consideration
the inconvenience to the traffic that is currently using these roads. He is extremely
concerned about the topography of the land obscuring view and must include access
to the current road users.
Cr Walker advised he is concerned with how the road access will work, the hours of
operation will be early morning or late evening for haulout equipment and how will
the access be guaranteed if there are locked gates.
A/DDS advised there is a condition for locked gates but if Councillors would like the
gates moved then the conditions would need to be amended accordingly.
Cr Walker queried if there were separate access would this be lockable.
The CEO advised that part of the traffic management plan would be to provide
everyone with access to the gazetted road, and assumed that there would be a locked
gate for workplace health and safety of the site.
Cr Walker queried if that was the case then would the haulout operator be provided
with a key to the gate to gain access at 3 am, if that is the case then he does not see
this being feasible.
The CEO advised that will be the details in the traffic management plan.
Cr Walker queried where the water will be released to if the dam is to be pumped out.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49616
A/DDS advised the dam's exit point goes into Jane Creek.
Cr Bella queried if it would not be more prudent to condition the fencing of the actual
quarrying site and the gates there rather than the gates on the access road.
A/DDS advised the fencing of the quarry site would depend on the various things and
would need to be investigated.
Cr Mann queried if the State raised any concerns with the sediment run off into Jane
Creek and did they review the site.
The Mayor advised the State had no concerns and were happy to sign off on the
application.
Cr Bonaventura requested additional information about the rural zoning code and
Amenity provision PO12 as listed in the agenda on page 234.
A/DDS advised this is how the planning scheme is written and the specific outcome
on the left-hand column that this is a requirement, sometimes in the right-hand
column acceptable outcomes are listed but in this instance the planning scheme does
not have any detail in the right-hand column.
Cr Camm advised that contained on page 234 Cr Bonaventura mentioned it advises if
the quarry was to become an ongoing operation with approval then there are
management conditions in relation to noise, dust, etc.
Cr Bonaventura commented that Council is not voting for an ongoing operation today
but rather a temporary one.
Cr Camm advised in the report it refers to what conditions would need to be
addressed should the quarry become an ongoing operation.
A/DDS advised because the application is for a temporary quarry there are conditions
not required if it was a permanent ongoing operation.
Cr Bonaventura advised following on from where Cr Camm mentioned in the agenda
it states "It is noted that DSDMIP requested a noise impact assessment as part of their
assessment and the applicant responded by outlining the nature of the extraction
activity and its temporary nature." A noise monitoring request was recommended and
it was not taken up by the applicant and he would like to know why.
A/DDS advised it was up to the applicant to decide what information they provide
with their application.
Cr Bonaventura queried why the bond was not considered for this application.
A/DDS advised it was a new provision of the planning scheme that was adopted last
year in case it was necessary to use it. Council has not used a bond in any quarry
situation so far and to be consistent it was felt that a bond not be requested for this
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49617
application. Even though there is not a bond there are other tools to ensure the site is
appropriately rehabilitated.
Cr Bonaventura advised he does not believe the site complies with the landscape
character and image corridors overlay. When you look at the site from the Bruce
Highway you see vista he wants for Mackay and the proposed site for the quarry dam
at this location is acceptable. There is a quarry site around the corner which is not
visible from the road and it is not an issue.
Cr Bella advised in the handout provided to Councillors there are photos of a quarry
that was supposed to be temporary and was to be rehabilitated and is not, is this
correct and if so, would it not be the conditioning of a bond a way to ensure the
rehabilitation is carried out.
The Mayor advised the issue of possible bonds was only introduced as part of the
recently adopted planning scheme.
Cr Bella advised there is a quarry in a nearby area that was supposed to be
rehabilitated and wasn’t under the mechanisms the A/DDS stated and if it is the case
that the quarry was to be rehabilitated and it hasn't then the mechanisms are not
effective and it may be better to consider a bond for this particular development.
The Mayor requested clarification from the A/DDS if the nearby quarry was to be
rehabilitated and has not been.
Cr Camm raised a Point of Order.
The Mayor asked Cr Camm what was her Point of Order.
Cr Camm advised this request was not pertinent to the report.
The Mayor advised it was a question raised by a Councillor and would like the
A/DDS to answer it.
A/DDS advised the original application for the nearby quarry had separate
applications after they were considered by Council and as part of those applications
have agreed to extend or change the conditions. The bond would not apply if they
applicant is operating under their current development application.
Council Resolution
THAT the Officer's Recommendation be adopted.
Moved Cr Camm Seconded Cr Mann
Cr Camm advised this assessment has been made against the Mackay Region
Planning Scheme and cannot urge Councillors enough that there is a half-billion-
dollar infrastructure project occurring in our region. It has taken 10 years of advocacy
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49618
by former Councils to fight for the Mackay Ring Road and this application in relation
to the Ring Road are pertinent and important. Councillors are bound under the
legislation to approve applications on planning grounds that have been technically
assessed. This application has been recommended by Officers for approval and this is
the reason why she is voting in favour of the Motion.
Cr Bonaventura advised he was voting against the Motion on planning grounds. The
proposal conflicts with the overall outcomes of the rural zone. In this proposal the
ridge line forms the amenity of the surrounding area, reducing noise generation and
improves the visual amenity. The site is visible from the Bruce Highway and he
believes an excellent part of what Council should endeavour to protect as part of the
rural zone code. He believes the application is in conflict with the extractive industry
code overall in its outcomes and performance outcomes. He understands quarries are
essential but it is Councillors role to ensure they are located in areas that are suitable.
In this instance he does not believe this application has demonstrated that the 200,000
tonnes cannot be sourced elsewhere. He believes this application also has not shown
how it will prevent noise generation from the operation or creating adverse impacts on
the surrounding land users. He believes this proposal conflicts with the general
development requirement code. The main point is safety and this application has not
demonstrated that conflicts between vehicles hauling quarry materials and other users
of the existing access track for farming and cane haulage activities can be
satisfactorily addressed. This proposal is entering onto a road network Council
controls and he believes this is an unacceptable safety risk and the application should
be refused as it conflicts with Councils' general development code in the planning
scheme. There is a conflict with the biodiversity overlay code, the risk here is there
are two important overlays in the vicinity of the proposed site, remnant vegetation that
is location approximately 80m to the north and then there is Jane Creek, which is
protected as high ecological value to protect and filter water as it makes its way to the
great barrier reef approximately 80m to the south.
Cr Mann advised she was in favour of the Motion as the environmental and planning
issues raised have been addressed by the conditions imposed on the application and
the State has approved the application. The traffic management plan will need to be
approved by Council Officers and is confident it will address all the issues raised here
today as safety is paramount. Based on planning grounds she will be voting in favour
of the Motion.
Cr Bella advised he is not in favour of the Motion and he believes quarrying should be
done in geographically appropriate areas in situationally appropriate areas and on
biosecurity grounds. If this was something that was planned for many years then why
is Council inundated with these types of applications with no forward looking as to
where the appropriate place for quarries would be. He has serious concerns in
relation to the traffic in the area and he does not believe and does not wish to approve
something before he has seen what the plan is and how it could control all possible
variables. He believes it is problematic for current users and there are so many
potential conflicts that could make it very difficult for the operation of the farming
region surrounding this site. He would like to see going into the future that Council
starts looking into a preferred quarrying plan or scheme so that Council is not placed
in a similar situation in the future.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49619
Cr May advised she is was not in favour of the Motion because she is not satisfied
with the traffic management plan and there are some really serious issues with this
application in relation to the truck movements entering and existing the site. She is
not comfortable is approving the application by saying this will be addressed in a
traffic management plan in this case. The current users of the road need to have been
given access and the environmental concerns and rehabilitation of the site where the
remnant vegetation has been destroyed to allow this quarry is of concern as is the run
off of the site into Jane Creek. She does not believe the demonstration of need for this
particular site has been given and therefore even on a temporary basis has been met.
There are a number of quarries already existing in this area that could accommodate
the need for the Ring Road and she will not support this application.
Cr Walker advised he will not be supporting the Motion as he has concerns with the
interaction both on the access road between haulouts, trains, trucks and the normal
traffic going in and out of the local farms. The accessibility on the Glendaragh Road
is another issue and he believes it is dangerous with the slope of the landscape and the
hills. He believes the construction of a dam on the floodplain of Jane Creek is an
environmentally sensitive location.
Cr Casey advised he would not be supporting the Motion as he has similar concerns to
those raised by Cr May. Councillors are being asked to vote on an application
without the full information and he is very concerned with the safety on Glendaragh
Road. He advised if the traffic management plan was available for Councillors to
consider this may have eased some of his concerns.
Cr Gee advised he would not be supporting the Motion as Jane Creek as a waterway is
valued through the whole area and to approve a temporary activity that could
potentially have such long-term impacts to the area is not something he is willing to
support.
The Mayor asked Cr Camm if she wished to exercise her right of reply.
Cr Camm advised the Mackay Region Planning Scheme is very clear around where
quarrying activities can occur, quarry activities are impact assessible and the State
Planning Legislation is very clear that it can occur in the rural code but it does need to
be assessed. The impacts of this quarry in comparison to other quarries currently
operating does not differ. This quarry is in close proximity to the construction of the
ring road and it is not Council's decision to make an assessment on whether this
quarry is commercially viable. If the fill does not come from this quarry it will come
from other quarries around the region. She is protective of farmers in the region and
she will not vote against where a farmer can install a dam on their property. She
urged all Councillors who spoke against the Motion to consider the real, relevant and
technical planning grounds you have argued against this application.
LOST
Crs Bella, Bonaventura, Casey, Gee, May, Walker and Williamson
recorded their vote against the Motion.
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49620
FURTHER it was noted by those voting against the Officer's Recommendation and
refusing the application that the following are associated reasoning and concerns -:
1. The proposal is in conflict with the Overall Outcomes and Performance
Outcomes of the Rural Zone Code as the applicant has not demonstrated that
the proposal will not adversely impact on the amenity of the surrounding area
through noise generation or impact on the visual amenity of the area. Further,
the application has not demonstrated that the activity will not adversely
impact on the ecological integrity of habitat areas and corridors connecting
areas of ecologically important areas.
2. The proposal is in conflict with the Extractive Industry Code Overall
Outcomes and Performance Outcomes as the applicant has not demonstrated
that there is a demonstrated need for the material that cannot be filled by other
existing quarries. Further, it has not been demonstrated that the noise
generated from the operations will not cause adverse impacts at surrounding
sensitive land uses.
3. The proposal conflicts with the General Development Requirements Code as
the application has not demonstrated that the acoustic amenity of surrounding
sensitive land uses will be maintained. Also, the proposal has not
demonstrated that conflicts between vehicles hauling quarry material and
other users of the existing access track for farming and cane haulage activities
can be satisfactorily addressed. Further, access/exit into the site is not safe as
haulage vehicles exiting the property are required to utilise both traffic lanes,
therefore impacting on the safety and efficiency of the road network.
4. The proposal is in conflict with the Biodiversity Overlay Code as the proposal
does not include the rehabilitation and enhancement of ecological
connectivity between the area of environmentally significant vegetation and
the watercourse.
12. RECEIPT OF PETITIONS:
Nil
13. TENDERS:
Nil
14. CONSIDERATION OF NOTIFIED MOTIONS:
Nil
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49621
15. PUBLIC PARTICIPATION:
Ms Bobby Barker, on behalf of the Kidney Support Network which is a small
Queensland charity, wanted to bring to the Council's attention the work they do for the
Mackay region residents. They have volunteers who transport patients to hospital
visits, man their charity shops and provide administration support. If there is anything
Council could do to support this network would be appreciated.
Ms Liza Williams, on behalf of the Kidney Support Network, queried if there was any
support and education that could be provided in preparing grant applications as they
have not had much success with grant funding so far.
The Mayor advised that the Director of Community and Client Services could meet
with the Kidney Support Network regarding what Council could do to assist them.
16. LATE BUSINESS:
Cr Mann reminded Councillors on Friday 20 April Council Character and Heritage
Advisory Committee will hold part of their meeting at the Bluewater Quay and will
include the unveiling of two (2) story boards which will commemorate the 100th
anniversary of the 1918 cyclone.
Cr Mann advised the cyclone survivors bus tours on Saturday 21 April will tour some
of the houses that survived the 1918 cyclone and local historian, Berenice Wright will
be on the tours to provide some insight into what occurred at that time.
Cr Mann presented to the Mayor a certificate of appreciation from Anglicare in
recognition of Councils' support to the low cost food assist centre that has been
operating from the old Retravision building for approximately 12 months. It was only a
trial period but this has now been extended due to the success in providing low cost
food for the marginalise residents of the region and free food parcels to residents in
need.
The Mayor explained that Anglicare advised on their last count on the free food parcels
they were delivering was approximately 400 per week.
Cr Bonaventura advised on Saturday 14 April 2018 the Italian Street Festival will be
held in Wood Street and invited everyone to attend if they were able to.
LEAVE OF ABSENCE - CR MAY
THAT Cr May be granted leave of absence for the Ordinary Council Meeting on
Tuesday 24 April 2018.
Moved Cr Mann Seconded Cr Camm
CARRIED
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49622
17. CONFIDENTIAL REPORTS:
Nil
18. MEETING CLOSURE:
The meeting closed at 1.03 pm.
19. FOR INFORMATION ONLY:
Nil
Confirmed on Tuesday 24 April 2018
………………………………………
MAYOR
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49623
APPENDIX / ATTACHMENTS
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49624
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49625
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49626
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49627
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49628
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49629
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49630
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49631
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49632
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49633
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49634
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49635
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49636
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49637
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49638
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49639
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49640
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49641
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49642
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49643
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49644
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49645
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49646
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49647
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49648
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49649
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49650
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49651
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49652
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49653
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49654
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49655
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49656
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49657
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49658
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49659
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49660
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49661
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49662
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49663
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49664
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49665
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49666
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49667
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49668
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49669
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49670
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49671
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49672
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49673
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49674
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49675
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49676
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49677
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49678
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49679
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49680
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49681
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49682
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49683
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49684
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49685
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49686
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49687
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49688
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49689
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49690
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49691
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49692
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49693
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49694
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49695
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49696
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49697
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49698
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49699
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49700
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49701
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49702
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49703
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49704
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49705
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49706
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49707
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49708
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49709
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49710
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49711
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49712
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49713
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49714
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49715
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49716
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49717
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49718
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49719
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49720
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49721
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49722
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49723
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49724
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49725
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49726
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49727
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49728
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49729
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49730
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49731
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49732
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49733
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49734
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49735
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49736
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49737
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49738
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49739
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49740
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49741
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49742
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49743
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49744
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49745
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49746
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49747
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49748
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49749
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49750
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49751
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49752
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49753
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49754
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49755
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49756
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49757
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49758
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49759
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49760
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49761
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49762
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49763
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49764
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49765
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49766
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49767
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49768
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49769
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49770
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49771
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49772
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49773
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49774
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49775
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49776
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49777
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49778
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49779
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49780
FINAL MINUTES WEDNESDAY 11 APRIL 2018
MIN/11.04.2018 FOLIO 49781