BRAYS BAYOU + BRIDGEFall 2015 Concept Presentation
Presented by:
Julianne Crawford, Avi Gori, Kasia Nikiel
![Page 2: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/2.jpg)
Project Description + Goals
➔ Design Brays Bayou channel modifications
➔ Reconstruct of Greenbriar Bridge between Braeswood & Main
➔ Consider of additional stormwater flow from 7200 Main
➔ Coordinate with 7200 Main development for other features
➔ Protect Meyerland area from future flooding
![Page 3: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/3.jpg)
Brays Bayou between Fannin St. and Greenbriar St.
![Page 4: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/4.jpg)
Greenbriar Bridge
![Page 5: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/5.jpg)
Background Research + Modeling
![Page 6: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/6.jpg)
Project Brays➔ Funded by US Army Corps and HCFCD➔ Comprehensive re-design of Brays Bayou
◆ Channel Modifications◆ Bridge Replacement/Renovation◆ New Detention Area
➔ Aimed at mitigating riverine flooding throughout Brays Bayou Watershed ➔ Status:
◆ Upper Reach: Completed◆ Middle Reach: In Progress◆ Lower Reach: In Progress
➔ Scheduled to be completed in 2021
![Page 7: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/7.jpg)
Project Brays Proposed Improvements
![Page 8: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/8.jpg)
100-year Floodplain (TSARP Model - 2004)
![Page 9: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/9.jpg)
100-year Floodplain (Current Conditions - 2010)
![Page 10: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/10.jpg)
100-year Floodplain (Post Project Brays - 2021)
![Page 11: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/11.jpg)
100-year Floodplain (TSARP) at Site Location
![Page 12: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/12.jpg)
100-year Floodplain (Post Project Brays) at Site Location
![Page 13: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/13.jpg)
Bridge - Current Conditions
![Page 14: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/14.jpg)
Concept Design
![Page 15: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/15.jpg)
OPTION 1: Widen the Channel
![Page 16: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/16.jpg)
HEC-RAS Geometry for Greenbriar Section
Main Street
Greenbriar Street
Fannin Street
![Page 17: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/17.jpg)
Cross Section Comparison - Downstream (RS 56478)
Current 100-yr Level (44.07 ft)
PPB 100-yr Level (43.47 ft)
PPB Geometry
Current Geometry
![Page 18: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/18.jpg)
OPTION 1: Widen the Channel -- BRIDGE
![Page 19: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/19.jpg)
OPTION 2: Retaining Wall
![Page 20: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/20.jpg)
HEC-RAS Geometry for Greenbriar Section
Main Street
Greenbriar Street
Fannin Street
![Page 21: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/21.jpg)
Cross Section Comparison - Upstream (RS 59882)
Current 100-yr Level (45.70 ft)
PPB 100-yr Level (44.96 ft)
PPB Geometry
Current Geometry
![Page 22: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/22.jpg)
OPTION 2: Retaining Walls -- BRIDGE
![Page 23: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/23.jpg)
Existing Plan View of Bridge Deck
![Page 24: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/24.jpg)
87.0’
Bridge Tie-Ins With Existing Roads
87.0’
5% Grade 4.35’
![Page 25: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/25.jpg)
Proposal
![Page 26: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/26.jpg)
Modified Scenario
➔ Retaining walls and some
widening on both banks
from Main to Greenbriar
➔ Retaining walls and
substantial widening on the
right bank from Greenbriar
to Fannin
![Page 27: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/27.jpg)
Modified HEC-RAS Geometry Examples (Upstream - RS 58740 )
Modified Geometry
PPB Geometry
![Page 28: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/28.jpg)
Modified HEC-RAS Geometry Examples (Downstream - RS 57958)
Modified Geometry
PPB Geometry
![Page 29: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/29.jpg)
Modified Scenario Results - RS 59882
Modified Geometry
PPB Geometry
Modified 100-yr LevelPPB 100-yr Level
44.71 ft 44.96 ft
![Page 30: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/30.jpg)
Modified Scenario Results - RS 56478
Modified Geometry
PPB Geometry
Modified 100-yr LevelPPB 100-yr Level
43.47 ft 43.37 ft
![Page 31: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/31.jpg)
Proposed Bridge Cross-Section
![Page 32: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/32.jpg)
Proposed Plan View of Widened Bridge Deck
![Page 33: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/33.jpg)
Impact of Proposed Modifications
➔ Modifications along the Main to Fannin portion of the channel should not have
drastic adverse effects on downstream sections.
➔ According to the 100-year floodplains, both current and post project brays, the
areas downstream of our site already face a much lower inundation hazard
than the middle and upper reaches.
![Page 34: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/34.jpg)
Moving Forward
![Page 35: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/35.jpg)
Brays Bayou
➔ Finalize channel modifications for Main to Fannin segment
➔ Add additional cross sections to existing HEC-RAS geometry
➔ Perform unsteady state HEC-RAS analysis
➔ Incorporate additional flow from hotel if necessary
![Page 36: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/36.jpg)
Proposed HEC-RAS Geometry Modification
![Page 37: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/37.jpg)
Bridge
➔ Finalize aesthetic design with 7200 Main St. group
➔ Determine appropriate foundations
➔ Superstructure/Substructure design of the bridge
![Page 38: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/38.jpg)
Meyerland
![Page 39: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/39.jpg)
May 2015 Storm - Comparison of Flooding to Current 100-year Floodplain
![Page 40: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/40.jpg)
May 2015 Storm - Damage Reports in Meyerland
![Page 41: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/41.jpg)
100-year Floodplain (Post Project Brays) at Meyerland
![Page 42: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/42.jpg)
![Page 43: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/43.jpg)
Appendix
![Page 44: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/44.jpg)
Channel Profile
Fannin Greenbriar Main
Direction of Flow
![Page 45: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/45.jpg)
Construction
![Page 46: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/46.jpg)
Green Space
➔ Finalize design for green space with hotel
➔ Ensure that all trails are integrated smoothly
![Page 47: Final fall senior design presentation](https://reader031.fdocuments.us/reader031/viewer/2022030306/58ce8a1f1a28ab210a8b76a1/html5/thumbnails/47.jpg)
Meyerland 100-yr Floodplain - Current Conditions v. Post Project Brays