FINAL ENVIRONMENTAL IMPACT ASSESSMENT &...
Transcript of FINAL ENVIRONMENTAL IMPACT ASSESSMENT &...
FINAL ENVIRONMENTAL IMPACT ASSESSMENT & ENVIRONMENTAL MANAGEMENT PLAN
For
PROPOSED EXPANSION OF PAPER PRODUCTION WITH CAPACITY FROM 300 TPD TO 600 TPD ALONG WITH CPP OF
14.00 MW
At
Muktsar – Malout Road, P.O.: Village Rupana, Dist.: Sri Muktsar Sahib, Punjab – 152032.
Land/Plot Area: 18.43 Ha. (1,84,341 m2) Production Capacity: 300 TPD to 600 TPD
[ToR Letter No: IA-J-11011/196/2014-IA.II(I) dated 16/04/2019]
[Study Period: 1st December 2018 to 28th February 2019]
[Schedule 5 (i) Category “A” as per EIA Notification 2006 and its amendment thereof]
Applicant Consultant
SATIA INDUSTRIES LTD. ECO CHEM SALES & SERVICES
Muktsar – Malout Road, P.O.: Village Rupana, Dist.: Sri Muktsar Sahib, Punjab – 152032.
E-mail: [email protected]
Tel No: +01633 – 262001, 262215 263585.
Office Floor, Ashoka Pavilion “A”, New Civil Road, Surat, Gujarat – 395001. (QCI/NABET ACCREDITED NO.
NABET/EIA/1720/ SA 085) E-mail: [email protected]
Tel No: +912612231630
July – 2019
Doc. No.: 2018_ECSS_EIAI1_1800028
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat i 2018_ECSS_EIAI1_1800028
UNDERTAKING BY PROJECT PROPONENT
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat ii 2018_ECSS_EIAI1_1800028
UNDERTAKING BY CONSULTANT
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat iii 2018_ECSS_EIAI1_1800028
EXECUTIVE SUMMARY
1. Project Name and Location (Village, Dist, State, Industrial Estate (if applicable))
Name: M/s. Satia Industries Limited, Village-Rupana
Dist - Sri Muktsar Sahib – 152026, Punjab.
Location: Survey No.: (New) R43//18,19/1,21,22,23.R61//26/1/1,1/1.R79//5/1,5/2,6,7.R78//1,2.
(Old) 26/1/1, 26/2/2, 13, 61/18, 23, 22, 19/1, 20, 21, 11/1, 10, 1, 5/1, 5/2, 6/1, 6/2, 15, 16, 25,
24, 17, 14, 7/1, 7/2, 4, 60/3, 8/1, 8/2, 60/13, 18, 19, 20, 16, 25/2, 2/2, 1, 2, 3, 10, 79/9, 8, 13/1,
13/2,
2. Products & Capacities. If expansion proposal, then existing products with capacities and reference to early EC.
Existing capacity 300 TPD and 30 MW CPP, Proposed additional Capacity 300 TPD and 14 MW CPP, Total production capacity will be 600 TPD and 44 MW CPP.
The existing unit of Satia Industries Limited has been obtained Environment Clearance wide No.F.No.J-11011/196/2014-IA-II(I) dated: 29th May,2018.
The company has been obtained Consent to Establish and Operate from State Pollution Control Board, Punjab. Satia has obtained Consent to Operate vide no. TOA/Fresh/MKS/2018/7687794 Date of issue: 09/07/2018 & Date of expiry: 31/03/2023 & CTOW/Fresh/MKS/2018/7687650 Date of issue: 09/07/2018 & Date of expiry: 31/03/2023.
3. Requirement of Land, Raw Material, Water, Power, Fuel with Source of supply (Quantitative)
Land Requirement: Total land area acquired for the proposed expansion project is 9.53 Acres (38568 m2) with 36.02 acres (145773 m2) land of existing plant (300TPD). Total area after expansion (600TPD) will be 45.55 Acres, (184341m2) which is already in possession of SIL.
Raw material:
Requirements of Raw Materials
S.No Name of Raw Materials Existing
(TPD) Proposed
(TPD) Total (TPD)
1. Imp. Waste Paper 0.000 35.300 35.300
2 Imp. Wood Pulp 0.000 32.600 32.600
3 Paper Additives 7.579 4.421 12.000
4 Soap Stone 65.650 52.350 118.000
5 Wheat Straw, Sarkanda, Bagasse
533.000 105.000 638.000
6 Wood Chips 150.000 205.600 355.600
7 Caustic 130.450 52.350 182.800
8 Liquid Oxygen 6.120 000 6.120
9 Chlorine Dioxide 3.400 4.600 8.000
10 Oxy Bleach Booster 000 4.400 4.40
11 Lime 95.200 32.200 127.400
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat iv 2018_ECSS_EIAI1_1800028
S.No Name of Raw Materials Existing
(TPD) Proposed
(TPD) Total (TPD)
Total 991.4 528.8 1520.3
Water: The total water requirement after expansion will increase from 16,500 to 24,000 KLD and it will be met from Arniwala Canal available near the site.
Power: Total Power Requirement after proposed expansion will be 44 MW is being/will be sourced from in house CPP.
Fuel:
S.
No. Fuel
Quantity, TPD Source
Existing Proposed Total
1. Rice Husk 500 400 900 Local Suppliers
2. Black Liquor 400 300 700 In-House
4. Process Description in brief, specifically indicating the gaseous emission, liquid effluent and solid/hazardous wastes. Materials balance shall be presented. Process description is given in Chapter 2 as Section No. 2.6. Gaseous Emission Satia Industries Limited has 01 boiler of 50 TPH capacity and 02 boilers of 75 TPH capacity each. Moreover, SIL has two Recovery boilers of 25 and 50 TPH capacity. Whereas the Chemical recovery Boiler is run through the Black Liquor, the other boilers run on rice husk as well as biogas generated from UASB digester. The steam requirement for the proposed expansion plant shall be met from the proposed 75 TPH boiler, which will run on rice husk and biogas generated from UASB digester. The other 50 TPH recovery boiler will be kept as standby. The significant pollutants identified due to flue gas emissions are/will be PM, NOx and SO2. There is/will be No Process Gas Emission.
Liquid Effluent
After expansion Total industrial Waste water generation will be 21,412 KLD (Existing- 14,575 KLD, Proposed- 6,837 KLD)
Domestic waste water will be 87 KLD (Existing- 60 KLD, Proposed - 27 KLD). Solid and Hazardous Waste After proposed expansion
ETP Sludge from ETP -17.00 TPD
Lime Sludge from Causticizing - 227.30 TPD
Fly Ash from Boiler House-115.00 TPD 5. Measures for mitigating the impact on the environment and mode of discharge or disposal.
Satia Industries Limited Adequately designed sewerage treatment plant for domestic effluent. Total industrial effluent will be treated in modified ETP. Water consumed in CPP will be optimized to maximum possible COCs to reduce overall water consumption. Evaporation losses from the CPP will be minimized by energy efficient coolers/condensers and evaporators. Sewage will not be allowed to release in the river/canal water. Domestic sewage is/will be treated in the septic tank/soak pit.
Hazardous is/will be disposed as per hazardous waste rules 2016 and fly ash is/will be disposed for brick manufacturing and land filling in an eco-friendly manner.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat v 2018_ECSS_EIAI1_1800028
Flue Gas: Satia Industries Limited is being /will be provided the Electro Static Precipitator (ESP) and adequate stack height for controlling Flue gas Emission from the Source of Air pollution.
6. Capital Cost of the Project, Estimated time of completion.
The total project cost after expansion is Rs 500 Crores.
The project will take approximately 18 months after all the statutory clearances from SPCB for site clearance and power plant clearance are received.
7. Site selected for the project- Natural of land – Agricultural (Single/double crop), barren, Govt/Private land, status of is acquisition, nearby (in 2-3 km) water body, population, with in 10 km other industries, forest, Eco-sensitive zones, accessibility.(Note –in case of industrial estate this information may not be necessary)
The land for the expansion is already in the possession of project proponent as expansion to be executed in the existing premises.
The existing project site is well connected by road to State Highway No. 41 & 16 (4.55 km & 0.27 km).
Majority of the raw materials are available from the nearby areas.
Easy availability of manpower for the expansion project. In addition to the above, the following factors within the study area (10 km) have also been considered:
There is no National Park or Wild Life Sanctuary.
There are no metropolitan cities.
There are no ecologically sensitive areas. 8. Baseline environmental data – Air quality, Surface and Ground water quality, Soil characteristic, Flora and Fauna, Socio-Economic condition of the nearby population.
Ambient Air Quality Monitoring
Sr. No.
Criteria Pollutants
Unit Maximum Value
Minimum Value
98th Percentile
Value
Prescribed Standard
1. PM10 µg/m3 88.6 62.5 88.4 100
2. PM2.5 µg/m3 48.3 32.8 48.0 60
3. SO2 µg/m3 16.7 9.6 16.6 80
4. NOX µg/m3 21.5 14.2 21.5 80
All the results of ambient air quality parameters have been found well within the limit as per NAAQS. Based on comparison study of results for tested parameters with NAAQS, it is interpreted that ambient air quality of studied locations is good. This interpretation relates to the sampling carried out and results found for particular locations and study period.
Noise Monitoring
Sr. No.
Parameter Unit Maximum Value Minimum Value Prescribed Standard
1. Leq (Day) dB(A) 77.4 49.8 -
2. Leq(Night) dB(A) 72.1 42.8 -
Based on noise level data obtained during the survey for residential area and industrial area, it is interpreted that noise levels are within the standard norms prescribed by MoEF & CC. Looking towards the increase in noise generating sources it is suggested that there is need to apply noise reducing devices at noise generating sources and generate public awareness.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat vi 2018_ECSS_EIAI1_1800028
Soil Quality and Characteristics
Sr. No.
Parameter Unit Maximum Value Minimum Value
1. pH - 7.44 7.12
2. Electrical Conductivity dS/m 0.48 0.35
3. Sodium meq/100gm 1.2 0.8
4. Potassium meq/100gm 0.5 0.3
5. Phosphorous mg/100gm 16.3 13.6
6. Total Nitrogen % 0.074 0.052
Based on soil analysis data it is concluded that soils are normal from salinity point of view as SAR is <2.0 and ESP is < 15%. The soils are having medium in nitrogen, low in phosphorus and potassium. The levels of total Fe, Cu, Cr, B and Zn are within the safe limits. However, for successful greenbelt development liberal quantity of organic manure is recommended. Soils of studied locations are suitable for plantation as well as for agricultural purpose.
Ground Water
Sr. No.
Parameter Unit Maximum Value
Minimum Value
Desirable Limit
Permissible Limit
1. pH - 7.94 7.04 6.5-8.5 No
Relaxation
2. TDS mg/L 2254 218 500 2000
3. TSS mg/L < 2 < 2 - -
4. Total Hardness mg/L 1200 112 200 600
5. Chloride mg/L 875 40 250 1000
6. Total Alkalinity mg/L 580 122 200 600
7. Fluoride mg/L 0.7 0.11 1.0 1.5
8. Iron mg/L 0.42 < 0.10 0.3 No
Relaxation
Based on comparison study of test results with drinking water norms, it is interpreted that water qualities of most of the studied locations meet with the drinking water standards as per IS 10500: 2012 except Goniana village. Ground water sample collected from project site, Rupana, Sotha, chak Gilijiwala,Barkandi,Muktsar and Bhangchiri can be used in drinking as well as in other domestic and irrigation purpose. Ground water sample collected from Goniana village should not be used in drinking as it contains TDS, Total Hardness, Chloride and Iron more than prescribed limit but it can be used in other domestic purpose as well as in irrigation also. These interpretations are based on comparison study with standard for tested parameters only as per IS 10500: 2012.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat vii 2018_ECSS_EIAI1_1800028
Surface Water
Sr. No.
Parameter Unit Maximum Value
Minimum Value
Desirable Limit
Permissible Limit
1. pH - 7.75 7.23 6.5-8.5 No Relaxation
2. TDS mg/L 214 168 500 2000
3. DO mg/L 5.1 4.9 - -
4. COD mg/L 16 10 - -
5. BOD mg/L 6 < 4.0 - -
River water qualities for the samples collected from different surface water bodies are contaminated with organic matter and microbes. Total coliforms have been reported in all sample, it indicated towards the faecal pollution in surface water bodies. Results of other tested parameters meet with the drinking water norms. Based on comparison study with drinking water norms it is concluded that these water sources can be used for irrigation purpose and it can also be used in drinking after conventional treatment followed by disinfection.
Ecology and Biodiversity
Dominant trees observed in the study region were Amaltas, Gulmohar, Shisham and kali shirish. There was no reserved forest recorded during the survey in the study region. Area is devoid of dense forest as a result no schedule -1 wild life was observed during the survey. Common mammal of the study region was Blue bull, Squirrel, Common mongoose and rabbit were seen. Although the soil of study region is clay loam, which favors the plant growth but looking to the density of plant it may also be suggested to improve the quality of environment as well as ecology and bio diversity by planting more trees. Due to lack of natural habitat, less numbers of wild mammals were observed. Number of species and density of wild mammals can be increased by promoting/ facilitating the growth of bushes. There was no endangered species observed during primary survey.
Socio Economic
During the primary survey it was observed that almost pakka road facility is available in all villages within 10 km radius. Literacy rate of the study region is from 48.44 to 67.33%. When compared to other places, these villages exhibit lower rate of literacy thus there is need to promote education among more and more people. Almost all the villages have more than 50% people as non-workers. It indicates that the problem of unemployment can be solved by providing proper training and education. There is also need to establish more industries so that maximum number of employment can be generated. Basic amenities like Education facilities Health care facilities, water supply, electric power supply, mode of transportation etc. are available in all villages.
9. Identification of hazardous in handling, processing and storage of hazardous material and safety system provided to mitigate the risk. After identifying hazards in handling processing and storage of hazardous material both Qualitative
and Quantitative risk has been analyzed. Mitigation measures like periodical training on fire drill and
using SCBA, conducting emergency response drill on yearly basis, training drivers for transportation
of hazardous goods, providing fire extinguishers etc is given in Chapter no: 7
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat viii 2018_ECSS_EIAI1_1800028
10. Likely impact of the project on Air, Water, Land, Flora-fauna nearby population. Impacts on Air:
Impacts: During Transportation, Storage and Handling, and During Plant Operation Phase PM, SO2 and NOx will be generated.
Mitigation measures: we are/will be using PUC Certified vehicle and fully covered by the tarpaulin for controlling Dusting, Regular water sprinkling will be done on roads to avoid dust generation from handling. Highly efficient four fields ESP is being/will be provided to reduce the particulate matter emissions from the boiler. Adequate stack height is being/will be provided for adequate dispersal of pollutants. Ash is being/will be transported by closed bulkers/full body trucks duly covered after loading to potential users. Moreover, from air modeling study, it has been proved that the air emission from the proposed project will not increase in significant manner. Additional greenbelt will be developed in and around the project premises area, around the storage yards and along the roads to minimize the fugitive dust generation.
Impacts on Water:
Impacts: Water is being/will be obtained from Arniwala Canal; hence no impact on ground water is envisaged. After proposed expansion Total 21412 KLD industrial effluent and 87 KLD Domestic effluents will be generated.
Mitigation measures: Total industrial waste water is/will be treated in ETP and partly treated water will be reused in manufacturing process. The final effluent is discharged into the plantation area where eucalyptus plantation is developed to consume the total quantity of effluent into the plantation area and domestic waste water is/will be treated in septic tank/soak pit.
Impacts on Land: The proposed expansion will be carried out in already acquired is 9.53 Acres (38568 m2) adjoining land. Impacts on Flora-fauna:
Impacts: Fugitive emission from vehicle movement will form a layer in leaves thus reducing the gaseous exchange process. This ultimately affects the growth of plants. Also, common animals found in the study region may get affected by the dust and gaseous emission from transportation activity.
Mitigation measures: Vehicles with valid PUC Certificate will only be allowed within the premises. Vehicles are being/will be strictly instructed to follow traffic rules and speed limits. Traffic violators will be penalized. Green belt will be encouraged to mitigate the emission level. Plantation will be carried out on approach roads and nearby vicinity. Budget of Rs. 20-30 Lakhs is allotted for green belt development and maintenance.
There are the some likely impacts on Air, Water, Land and Flora-fauna and we have provided mitigation measures for the same. Hence, No major impacts will be occurred in nearby population.
11. Emergency preparedness plan in case of natural or in plant emergencies. On- Site and Off- Site emergency plan has been prepared for existing unit and same shall be modified
for proposed expansion.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat ix 2018_ECSS_EIAI1_1800028
Details regarding safety committee along with their roles and responsibilities, mutual aids
arrangements, roles and responsibilities of stake holders including stake holders, etc are given in
Chapter: 7.
12. Issues raised during public hearing (if applicable) and response given. Issues are raised in Public hearing and its response is incorporated in EIA/EMP Report after conducting Public hearing.
13. CSR/CER Plan with proposed expenditure.
The company has proposed a detailed CER Plan. Under this plan, the proponent has allocated a budget of Rs. 3.75 Crores i.e. 0.75 % of the total cost of Rs. 500 Crores to be spent within a period of 5 years.
14. Occupational Health Measures
Personnel protective equipment such as safety shoes, safety goggles, hand gloves, gum boots, safety helmet, and breathing apparatus set kit will be given to all workers and staff. Additional PPEs will be readily available at the workplace.
Medical surveillance for the workers working in risk zone is/will be carried out regularly.
Safety awareness programs will be conducted. 15. Post Project Monitoring Plan
Post project environmental monitoring is/will be done as per MoEFCC/CPCB/PPCB guidelines by following recommended/standard method approved by MoEFCC/CPCB. Budget of Rs. 15.00 lakh/annum has been allocated for monitoring of Air, Surface Water, Ground water & Soil environment.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat x 2018_ECSS_EIAI1_1800028
TOR COMPLIANCE
A. Additional TOR Reply Citation
1. A Note on pulp washing system capable of handling wood pulp shall be included.
Details are incorporated in EIA/EMP report. Section 2.6 Chapter 2 Page No.21
2.
Manufacturing process details for the existing and proposed plant shall be included. Chapter on pulping & Bleaching shall include: no black liquor spillage in the area of pulp mill; no use of elemental chlorine for bleaching mill; installation of hypo preparation plant; no use of potcher washing and use of counter current or horizontal belt washers. Chapter on chemical recovery shall include: no spillage of foam in chemical recovery plant, no discharge of foul condensate generated from MEE directly to ETP; control of suspended particulate matter emissions from the stack of fluidized bed recovery boiler and ESP in lime kiln.
Details of Manufacturing Process and Chemical recovery plant are incorporated in EIA/EMP report.
Section 2.6 Chapter 2 Page No.21 Section 10.2.3 Chapter 10 Page No.192
3.
Studies shall be conducted and a chapter shall be included to show that soda pulping process can be employed for Eucalyptus/Casuarina to produce low kappa (bleachable) grade of pulp.
Details are incorporated in EIA/EMP report. Section 2.6 Chapter 2 Page No.21
4.
Commitment that only elemental chlorine-free technology will be used for the manufacture of paper and existing plant without chemical recovery plant will be closed within 2 years of issue of environment clearance.
Company is already having elemental Chlorine-free technology for bleaching of pulp and Chemical recovery plant is already existing
Section 2.6 Chapter 2. Page No.21
5.
A Commitment that no extra chlorine base bleaching chemicals (more than being used now) will be employed and AOx will remain within limits as per CREP for used based mills. Plan for reduction of water consumption.
Agreed & Complied Plan for reduction of water consumption has been given in EIA/EMP Report
Section 10.2.3 Chapter 10 Page No.192
B. Generic TOR in respect of Industry Sector
1. Executive Summary Complied
Page No.iii
2. Introduction
i. Details of the EIA consultant including NABET accreditation
Complied Annexure XIV Page No.232
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xi 2018_ECSS_EIAI1_1800028
ii. Information about the project proponent
Satia Industries Limited (SIL) has been
promoted by Dr. Ajay Satia in the year
1984, who toiled hard during initial period
of militancy in Punjab and made this
Project viable and model unit with his hard
work, sincerity and excellent team building
spirit now having three paper machines at
Muktsar – Malout Road, PO : Village
Rupana, Dist: Sri Muktsar Sahib, Punjab –
152032, which is manufacturing 300 TPD
of eco-friendly paper using agricultural
residues (Wheat Straw, Sarkanda,
Baggasse, Cotton Sticks), Wood Base
(Wood, Veneer & Bamboo Chips) as raw
material.
With the entry of second generation of the
family Shree Chirag Satia, Executive
Director entering the family business, SIL
intends to increase its present production
capacity from 300 TPD to 600 TPD by
expanding its project and 14.0 MW CPP.
---
iii. Importance and Benefits of the project
Details are incorporated In EIA/EMP Report.
Section 2.2 Chapter 2 Page No.10
3. Project description
i. Cost of project and time of completion
The total investment of Rs.500.00 Crores is proposed for the expansion of the project. Time Completion Schedule is incorporated in EIA/EMP report.
Section 2.11 Chapter 2 Page No.35
ii. Products with capacities for the proposed project
Details of products with capacities are incorporated In EIA/EMP Report.
Section 2.5.2 Chapter 2 Page No.20
iii.
If expansion project, details of the existing products with capacities and whether adequate land is available for expansion, reference of earlier EC if any.
Land document is attached in EIA/EMP report.
Annexure: IV Page No.222
iv. List of raw materials required and their source along with mode of transportation.
Details or required raw materials are incorporated In EIA/EMP Report.
Section 2.5.1 Chapter 2 Page No.19
v. Other chemicals and materials required with quantities and storage capacities
Chemicals and materials required with quantities are incorporated In EIA/EMP Report.
Section 2.5.1 Chapter 2 Page No.19
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xii 2018_ECSS_EIAI1_1800028
vi. Details of emissions, effluents, hazardous waste generation and their management
Details are incorporated in EIA/EMP report. Section 2.8 Chapter 2 Page No.30
Vii.
Requirement of water, power, with source of supply, status of approval, water balance diagram, man-power requirement (regular and contract).
Total Water Requirement After Proposed Expansion will 24,000 KLD its source from Arniwala Canal available near the site.
Total power requirement After proposed expansion will be 44 MW (Existing 30MW and Proposed 14 MW) and its source is being/will be obtained from In-house CPP.
Water balance diagram are incorporated in EIA/EMP report.
Presently there are 1100 numbers of employees. There will be additional 500 numbers of employees, thus total 1600 numbers of employees after proposed expansion.
Annexure V Page No.223 Section 2.4.3 Chapter 2 Page No.18 Section 2.8.2 Chapter 2 Page No.31 Section 2.4.2 Chapter 2 Page No.18
Viii
The project proponent shall furnish the requisite documents from the competent authority in support of drawl of ground water and surface water and supply of electricity.
Source of surface water from Arniwala Canal available near the site.
No ground water used.
Source of electricity is being/will be obtained from In-house CPP.
Annexure: V Page No.223
ix.
Process description along with major equipments and machineries, process flow sheet (quantative) from raw material to products to be provided
Details are incorporated In EIA/EMP Report.
Section 2.6 Chapter 2 Page No.21
x. Hazard identification and details of proposed safety systems
Details are incorporated In EIA/EMP Report.
Section 7.6.1 Chapter 7 Page No.156
xi. Expansion/modernization proposals:
a.
Copy of all Environmental Clearance(s) including Amendments thereto obtained for the project from MoEF&CC/SEIAA shall be attached as annexure. A certified copy of the latest Monitoring Report of the Regional Office of Ministry of Environment and Forests as per circular dated 30t May, 2012 on the status of compliance of conditions stipulated in all the existing environmental clearances including Amendments shall be provided. In addition, status of compliance of Consent to
The existing unit of Satia Industries Limited
has been obtained Environment Clearance
wide No.F.No.J-11011/196/2014-IA-II(I)
dated: 29th May,2018.
Compliance to EC conditions have been attached. Monitoring Report of Regional office attached as Compliance of Consent to operate for ongoing/existing operation of the project from PPCB has been attached with the EIA-EMP report.
Annexure: II Page No.220 Annexure: III Page No.221
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xiii 2018_ECSS_EIAI1_1800028
operate for ongoing/existing operation of the project from SPCB shall be attached with the EIA-EMP report.
b.
In case the existing project has not obtained the environmental clearance, reason for not taking EC under the provisions for EIA Notifications 1994 and/or EIA Notifications 2006 shall be provided. Copies of Consent to Establish/No Objection Certificate and Consent to operate (in case of units operating prior to EIA Notifications 2006, CTE and CTO of FY 2005-2006) obtained from the SPCB shall be submitted. Further compliance report to the conditions of consents from the SPCB shall be submitted.
Not Applicable ---
4. Site Details:
i.
Location of the project site covering village, Taluka/Tehsil, District and State, Justification for selecting the site, whether other sites were considered.
M/s SATIA INDUSTRIES LIMITED is located at Muktsar –Malout Road, PO : Village Rupana, Dist: Sri Muktsar Sahib, Punjab – 152032
---
ii.
A toposheet of the study area of radius of 10km and site location on 1:50,000/1:25,000 scale on an A3/A2 sheet. (including all eco-sensitive areas and environmentally sensitive places)
Study Area Map of radius of 10 km is incorporated EIA/EMP report.
Chapter 3 Page No.37
iii. Co-ordinates (lat-long) of all four corners of the site..
Corner Latitude Longitude
A 30°25'11.10"N 74°31'19.16"E
B 30°25'24.87"N 74°31'18.11"E
C 30°25'16.49"N 74°30'54.78"E
D 30°25'06.74"N 74°31'0.93"E
---
iv. Google map-Earth downloaded of the project site.
Google map-Earth images are incorporated in EIA/EMP reports.
Section 2.3.2 Fig.2.2 Chapter 2 Page No.13
v.
Layout maps indicating existing unit as well as proposed unit indicating storage area, plant area, greenbelt area, utilities etc. If located within an industrial area/estate/complex, layout of industrial area and location of unit within the industrial area/estate.
Layout is attached in EIA/EMP report. Section 2.4 Fig 2.4 Chapter 2 Page No.17
vi.
Photographs of the proposed and existing (if applicable) plant site. If existing, show photographs of plantation/greenbelt, in particular.
Complied Chapter 2 Fig 2.1 Section 2.3 Page No.12
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xiv 2018_ECSS_EIAI1_1800028
vii.
Land use break-up of total land of the project site (identified and acquired), government/private - agricultural, forest, wasteland, water bodies, settlements, etc shall be included. (not required for industrial area)
Details are incorporated In EIA/EMP Report.
Section 2.4.1 Chapter 2 Page No.16
1viii.
A list of major industries with name and type within study area (10 km radius) shall be incorporated. Land use details of the study area.
Details are incorporated In EIA/EMP Report.
Figure 3.1 Chapter 3 Page No.37
ix. Geological features and Geo-hydrological status of the study area shall be included.
Geological features and Geo-hydrological status of the Study area are incorporated in EIA/EMP Report.
Section 3.7-3.8 Chapter 3 Page No.59
x.
Details of Drainage of the project upto 5km radius of study area. If the site is within 1km radius of any major river, peak and lean season river discharge as well as flood occurrence frequency based on peak rainfall data of the past 30 years. Details of Flood Level of the project site and maximum Flood Level of the river shall also be provided. (mega green field projects)
Drainage map is attached in EIA/EMP report.
Section 3.6.2 Chapter 3 Page No.58
xi.
Status of acquisition of land. If acquisition is not complete, stage of the acquisition process and expected time of complete possession of the land.
Land already Acquired ---
xii. R&R details in respect of land in line with state Government policy.
Not Applicable ---
5. Forest and Wildlife related issues
Not Applicable
---
i.
Permission and approval for the use of forest land (forestry clearance), if any, and recommendations of the State Forest Department. (if applicable)
ii.
Land use map based on High resolution satellite imagery (GPS) of the proposed site delineating the forestland (in case of projects involving forest land more than 40 ha).
iii.
Status of Application submitted for obtaining the stage I forestry clearance along with latest status shall be submitted.
iv. The projects to be located within 10
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xv 2018_ECSS_EIAI1_1800028
km of the National Parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-a-vis the project location and there commendations or comments of the Chief Wildlife Warden-thereon.
v.
Wildlife Conservation Plan duly authenticated by the Chief Wildlife Warden of the State Government for conservation of Schedule I fauna, if any exists in the study area.
vi.
Copy of application submitted for clearance under the Wildlife (Protection) Act, 1972, to the Standing Committee of the National Board for Wildlife.
6. Environmental Status
i.
Determination of atmospheric inversion level at the project site and site specific micro- meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall.
Month
Temperature (oC)
Relative Humidity
(%)
Wind Speed (km/hr)
Min.
Max.
Min.
Max.
Min.
Max.
Dec'18
3.4 26.2
23.0
97.0 0.1
12.3
Jan'19
4.1 22.1
21.0
96.0 0.1
19.0
Feb'19
5.8 23.1
33.0
98.0 0.1
21.0
Table 3.3 Section 3.3 Chapter 3 Page No.42
ii.
AAQ data (except monsoon) at 8 locations for PM10, PM2.5, SO2, NOX, CO and other parameters relevant to the project shall be collected. The monitoring stations shall be based CPCB guidelines and take into account the pre-dominant wind direction, population zone and sensitive receptors including reserved forests.
We have selected 8 locations for AAQ data. Details are incorporated in EIA/EMP report.
Table 3.4 Section 3.4.1 Page No.48
iii.
Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given in the NAQQM Notification of Nov. 2009 along with – min., max., average and 98% values for each of the AAQ parameters from data of all AAQ stations should be provided as an annexure to the EIA Report.
Details of Raw data of all AAQ measurement for 12 weeks of all stations are given in EIA/EMP report.
Table 3.6-3.8 Section 3.4 Chapter 3 Page No.50
iv. Surface water quality of nearby Details of surface water locations are Table 3.19
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xvi 2018_ECSS_EIAI1_1800028
River (60m upstream and downstream) and other surface drains at eight locations as per CPCB/MoEFCC guidelines.
incorporated in EIA/EMP report. Section 3.11.7 Chapter 3 Page No.72
v. Whether the site falls near to polluted stretch of river identified by the CPCB/MoEF&CC.
No ----
vi. Ground water monitoring at minimum at 8 locations shall be included.
Details of Ground water locations are incorporated in EIA/EMP report.
Table 3.17 Section 3.11.4 Chapter 3 Page No.69
vii. Noise levels monitoring at 8 locations within the study area.
Details of Noise level Monitoring locations are incorporated in EIA/EMP report.
Table 3.9 Section 3.5.1 Chapter 3 Page No.53
viii.
Soil characteristics as per CPCB guidelines.
Result of Soil Analysis are incorporated in EIA/EMP report.
Table 3.16 Section 3.10 Chapter 3 Page No.65
ix.
Traffic study of the area, type of vehicles, frequency of vehicles for transportation of materials, additional traffic due to proposed project, parking arrangement etc.
Details of Traffic Study Of the area are incorporated in EIA/EMP report.
Section 3.9 Chapter 3 Page No.63
x.
Detailed description of flora and fauna (terrestrial and aquatic) existing in the study area shall be given with special reference to rare, endemic and endangered species. If Schedule-I fauna are found within the study area, a Wildlife Conservation Plan shall be prepared and furnished.
Details of EB Studies are incorporated in EIA/EMP report.
Section 3.12 Chapter 3 Page No.78
xi. Socio-economic status of the study area.
During the primary survey it was observed that almost pakka road facility is available in all villages within 10 km radius. Literacy rate of the study region is from 48.44 to 67.33%. When compared to other places, these villages exhibit lower rate of literacy thus there is need to promote education among more and more people. Almost all the villages have more than 50% people as non-workers. It indicates that the problem of unemployment can be solved by providing proper training and education. There is also need to establish more industries so that maximum number of employment can be generated. Basic amenities like Education facilities Health care facilities, water supply,
Section 3.13 Chapter 3 Page No.83
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xvii 2018_ECSS_EIAI1_1800028
electric power supply, mode of transportation etc. are available in all villages.
7. Impact Assessment and Environment Management Plan
i.
Assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. In case the project is located on a hilly terrain, the AQIP Modelling shall be done using inputs of the specific terrain characteristics for determining the potential impacts of the project on the AAQ. Cumulative impact of all sources of emissions (including transportation) on the AAQ of the area shall be well assessed. Details of the model used and the input data used for modeling shall also be provided. The air quality contours shall be plotted on a location map showing the location of project site, habitation near, sensitive receptors, if any.
Details of Air Modelling are incorporated in EIA/EMP report.
Section 4.2.2 Chapter 4 Page No.108
ii.
Water Quality modeling-in case, if the effluent is proposed to be discharged in to the local drain, then Water Quality Modeling study should be conducted for the drain water taking into consideration the upstream and downstream quality of water of the drain.
Not Applicable -
iii.
Impact of the transport of the raw materials and end products on the surrounding environment shall be assessed and provided. In this regard, options for transport of raw materials and finished products and wastes (large quantities) by rail or rail-cum road transport or conveyor-cum-rail transport shall be examined.
Total 151 trucks/day will be required for transportation of raw material and finished products. Impacts on transportation has been described in EIA/EMP report.
Chapter 4 Section 4.2.2 Page No.108
iv.
A note on treatment of wastewater from different plant operations, extent recycled and reused for different purposes shall be included. Complete scheme of effluent treatment. Characteristics of untreated and treated effluent to meet the prescribed standards of discharge under E(P) Rules.
Details of Effluent treatment plant and characteristic of treated effluent is incorporated in EIA/EMP report.
Section 10.2.3 Chapter 10 Page No.192
v. Details of stack emission and Details of stack emission are incorporated Section 2.8.1
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xviii 2018_ECSS_EIAI1_1800028
action plan for control of emissions to meet standards.
in EIA/EMP report. Chapter 2 Page No.30
vi. Measure for fugitive emission control
Mitigation measures for fugitive emission control are incorporated in EIA/EMP report.
Section 10.2.2 Chapter 10 Page No.189
vii.
Details of hazardous waste generation and their storage, utilization and disposal. Copies of MOU regarding utilization of solid and hazardous waste shall also be included. EMP shall include the concept of waste-minimization, recycle/reuse/recover techniques, Energy conservation, and natural resources conservation.
Details of hazardous waste generation and their storage, utilization and disposal are incorporated in EIA/EMP report. Details of
Section 2.8.3 Table 2.11 Chapter 2 Page No.34
viii.
Proper utilization of fly ash shall be ensured as per Fly Ash Notification, 2009. A detailed plan of action shall be provided.
fly ash is/will be disposed for brick manufacturing and land filling in an eco-friendly manner.
Annexure VI Page No.224
ix.
Action plan for the green belt development plan is 33% area i.e. land with not less than 1,500 trees per ha. Giving details of species, width of plantation, planning schedule etc. shall be included. The green belt shall be around the project boundary and a scheme for greening of the roads used for the project shall also be incorporated.
Action plan for greenbelt development is incorporated in EIA/EMP report.
Section 10.2.4 Chapter 10 Page No.198
x.
Action plan for rainwater harvesting measures at plant site shall be submitted to harvest rainwater from the roof tops and storm water drains to recharge the ground water and also to use for the various activities at the project site to conserve fresh and reduce the water requirement from other sources.
Details are incorporated in EIA/EMP report. Section 10.5.1 Chapter 10 Page No.207
xi.
Total capital cost and recurring cost/annum for environmental pollution control measures shall be included.
Details Of EMS are incorporated in EIA/EMP report.
Section 10.6 Chapter 10 Page No.209
xii. Action plan for post-project environmental monitoring shall be submitted.
Details of post Project Monitoring are incorporated in EIA/EMP report.
Section 6.3 Chapter 6 Page No.133
xiii.
Onsite and Offsite Disaster (natural and man-made) Preparedness and Emergency management Plan including Risk Assessment and
Onsite and offsite Emergency plans are incorporated in EIA/EMP report.
Section 7.7 & 7.8 Chapter 7 Page No.169
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xix 2018_ECSS_EIAI1_1800028
damage control. Disaster Management plan should be linked with District Disaster Management Plan.
8. Occupational health
i.
Details of existing Occupational & Safety Hazards. What are the exposure levels of above mentioned hazards and whether they are within Permissible Exposure Level (PEL). If these are not within PEL, what measures the company has adopted to keep them within PEL so that health of the workers can be preserved.
Management plan for occupational health & safety are incorporated in EIA/EMP report.
Section 7.4.8 Chapter 7 Page No.151
ii.
Details of exposure specific health status evaluation of worker. If the worker‟s health is being evaluated by pre designed format, chest x-rays, Audiometry, Spirometery, Vision testing (Far & Near vision, color vision and any other ocular defect) ECG, during pre- placement and periodical examinations give the details of the same. Details regarding last month analyzed data of abovementioned parameters as per age, sex, duration of exposure and departmental wise.
Details of periodical medical examination are incorporated in EIA/EMP report.
Section 7.4.7 Chapter 7 Page No.151
iii. Annual report of health status of workers with special reference to Occupational Health and Safety.
Annexure IX Page No.227
iv. Plan and fund allocation to ensure the occupational health & safety of all contract and casual workers.
Rs 3.00 lakhs has been Allotted for Occupation health and Safety.
--
9. Corporate Environment Policy
i.
Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.
The company has a well-developed Environment Policy.
Annexure XII Page No.230
ii.
Does the Environment Policy prescribe for standard operating process/procedures to bring into focus any infringement/deviation/violation of the environmental or forest norms/conditions? If so, it may be detailed in EIA.
iii.
What is the hierarchical system or Administrative order of the company to deal with the environmental issues and for ensuring compliance with the environment clearance conditions?
The company has developed a Hierarchal system for dealing withthe environmental issues and for ensuring compliance with the EC conditions. Details are incorporated in EIA/EMP report.
Section 10.7 Figure 10.8 Chapter 10 Page No.210
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xx 2018_ECSS_EIAI1_1800028
Details of this system may be given.
iv.
Does the company have system of reporting of non-compliances/violations of environmental norms to the Board of Directors of the company and/or shareholders or stakeholders at large? This reporting mechanism shall be detailed in the EIA report.
The company has developed a Hierarchal system for reporting of non-compliances / violations of environmental norms to the higher management. Details are incorporated in EIA/EMP report.
Figure 10.8 Section 10.7 Chapter 10 Page No.210
10.
Details regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.
The necessary infrastructure facilities like drinking water and sanitation has been already provided to the construction workers and truck drivers within the project site.
-
11.
Corporate Environment Policy(CER)
i.
To address the public hearing issues,an amount as specified under ministry‟s Office Memorandum vide F.No.22-65/2017-IA.III dated 1st may 2018 amounting of RS………crores,shall be earnmarked by the project proponent,towards Corporate Environment Responsibility(CER).Distinct CER projects shall be carved out based on PWD schedule of rates for each distinct Item and schedule for time bound action plan shall be prepared.These CER projects as indicated by the project proponent shall be implemented long with main project.Implementation of such program shall be ensured by constituting a Committee comprising of the project proponent,representatives of village Panchyat & District Administration.Action taken report in this regard shall be submitted to the Ministry' Regional office.No free distribution/donations and or free campus shall be included in the above CER budget.
The company also proposes to carry out social welfare activities for the welfare of local community. The company has proposed a detailed CER Plan. Under this plan, the proponent has allocated a budget of Rs. 3.75 Crores i.e. 0.75 % of the total cost of Rs. 500 Crores to be spent within a period of 5 years. Details of CER are incorporated in EIA/EMP report.
Table 10.9 Section 10.8 Page No.210
12.
Any litigation pending against the project and/or any direction/order passed by any Court of Law against the project, if so, details thereof shall also be included. Has the unit received any notice under
Not Applicable -
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxi 2018_ECSS_EIAI1_1800028
the Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air and Water Acts? If so, details thereof and compliance/ATR to the notice(s) and present status of the case.
13.
A tabular chart with index for point wise compliance of above TORs.
Complied Page No.X
14.
The TORs prescribed shall be valid for a period of three years for submission of the EIA-EMP reports along with Public Hearing Proceedings (wherever stipulated).
Noted --
The following general points shall be noted:
i. All documents shall be properly indexed, page numbered.
Agreed & Complied --
ii. Period/date of data collection shall be clearly indicated.
Agreed & Complied --
iii. Authenticated English translation of all material in Regional languages shall be provided.
Agreed & Complied --
iv.
The letter/application for environmental clearance shall quote the MOEF file No. and also attach a copy of the letter.
Agreed --
v.
The copy of the letter received from the Ministry shall be also attached as an annexure to the final EIA-EMP Report.
Agreed & Complied --
vi.
The index of the final EIA-EMP report must indicate the specific chapter and page no. the EIA-EMP Report.
Complied --
vii.
While preparing the EIA Report, the instructions for the proponents and instructions for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I) dated 4th August, 2009, which are available on the website of this Ministry shall also be followed.
Complied
--
viii.
The consultants involved in the preparation of EIA-EMP report after accreditation with Quality Council of India (QCI)/National Accreditation Board of Education and Training (NABET) would need to include a certificate in this regard in the EIA- EMP reports prepared by them and data provided by other organization/Laboratories including their status of approvals etc. Name of Consultant and the Accreditation
Complied
Annexure.XIV Page No.232
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxii 2018_ECSS_EIAI1_1800028
details shall be posted on the EIA-EMP Reports as well as on the cover of the Hard Copy of the Presentation material for EC presentation.
ix.
TOR‟s prescribed by the Expert Appraisal Committee (Industry) shall be considered for the preparation of EIA-EMP report for the project in addition to all the relevant information as per the „Generic Structure of EIA‟ given in Appendix III and IIIA in the EIA Notification, 2006. Where the documents provided are in a language other than English, an English translation shall be provided.The draft EIA-EMP Report shall be submitted to the State Pollution Control Board of the concerned State for conduct of Public Hearing. The SPCB shall conduct the Public Hearing/Public consultation, district-wise, as per the provisions of EIA Notifications, 2006. The Public Hearing shall be chaired by an Officer not below the rank of Additional District Magistrate. The issues raised in the Public Hearing and during the consultation process and the commitments made by the project proponent on the same shall be included separately in EIA-EMP Report in a separate chapter and summarized in a tabular chart with financial budget (capital and revenue) along with time-schedule of implementation for complying with the commitments made. The final EIA Report shall be submitted to the Ministry for obtaining Environment clearance.
Complied Public hearing held on 04/07/2019. Issues raised and addressed during public hearing/consultation are incorporated in EIA report.
Section 7.1 Table 7.1 Page No.143
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxiii 2018_ECSS_EIAI1_1800028
CONTENTS
LIST OF TABLES .................................................................................................................... xxxiii
LIST OF FIGURES ................................................................................................................ xxxviii
CHAPTER 1...................................................................................................................................... 1
INTRODUCTION ............................................................................................................................. 1
1.0 PRELUDE .............................................................................................................................................. 1
1.1 PURPOSE OF THE REPORT ................................................................................................................. 1
1.2 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT ..................................................... 2
1.2.1 Identification of the project ................................................................................................................... 2
1.2.2 Identification of the Project Proponent ................................................................................................. 2
1.3 BRIEF DESCRIPTION OF PROJECT .................................................................................................... 2
1.3.1 Nature, Size and Location of the Project ................................................................................................ 2
1.3.2 Importance to the Country and Region .................................................................................................. 4
1.4 REGULATORY FRAMEWORK AND ENVIRONMENTAL CLEARANCE ......................................... 6
1.5 SCOPE AND OBJECTIVES OF THE STUDY ....................................................................................... 7
1.6 STRUCTURE OF EIA REPORT .............................................................................................................. 7
1.7 SUMMARY .................................................................................................................................................. 9
CHAPTER 2.................................................................................................................................... 10
PROJECT DESCRIPTION ........................................................................................................... 10
2.0 GENERAL ................................................................................................................................................. 10
2.1 TYPE OF PROJECT ................................................................................................................................ 10
2.2 NEED OF THE PROJECT ...................................................................................................................... 10
2.3 PROJECT LOCATION ............................................................................................................................ 11
2.3.1 Project Site Location ............................................................................................................................. 11
2.3.2 Site Selection Criteria ........................................................................................................................... 13
2.3.3 Salient Features Study Area ................................................................................................................. 14
2.3.4 Climatic Conditions ............................................................................................................................... 15
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxiv 2018_ECSS_EIAI1_1800028
2.4 RESOURCE REQUIREMENT ............................................................................................................... 16
2.4.1 Land Requirement ................................................................................................................................ 16
2.4.2 Man Power ........................................................................................................................................... 18
2.4.3 Energy requirement .............................................................................................................................. 18
2.4.4 Water Requirement .............................................................................................................................. 18
2.4.5 Capital Requirement ............................................................................................................................. 19
2.5 RAW MATERIALS AND PRODUCT ..................................................................................................... 19
2.5.1 Raw Material Requirement .................................................................................................................. 19
2.5.2 Product Details ..................................................................................................................................... 20
2.6 MANUFACTURING PROCESS ............................................................................................................. 21
2.6.1 Pulping Process ..................................................................................................................................... 21
2.6.2 Stock Preparation ................................................................................................................................. 23
2.6.3Paper Making ......................................................................................................................................... 23
2.6.4Converting & Finishing .......................................................................................................................... 23
2.6.5Description of Soda Recovery Plant ...................................................................................................... 25
2.6.6 Description of Captive Power Plant ...................................................................................................... 25
2.6.7 Material Balance for Proposed 600 TPD .............................................................................................. 27
2.7 AUXILIARY SYSTEM .............................................................................................................................. 27
2.7.1 Rice Husk Handling System ................................................................................................................... 27
2.7.2 Fly Ash Handling System ....................................................................................................................... 29
2.8 POLLUTION POTENTIAL& ITS CONTROL MEASURES ................................................................ 30
2.8.1 Air Environment .................................................................................................................................... 30
2.8.2 Water Environment .............................................................................................................................. 31
2.8.3 Solid/Hazardous Waste ........................................................................................................................ 33
2.8.4 Noise Environment ............................................................................................................................... 34
2.9 OCCUPATIONAL HEALTH AND SAFETY .......................................................................................... 34
2.10 ASPECT - IMPACT ANALYSIS ........................................................................................................... 35
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxv 2018_ECSS_EIAI1_1800028
2.11 PROJECT IMPLEMENTATION SCHEDULE .................................................................................... 35
2.12SUMMARY ............................................................................................................................................... 36
CHAPTER-3 ................................................................................................................................... 37
DESCRIPTION OF THE ENVIRONMENT ................................................................................ 37
3.0 INTRODUCTION ...................................................................................................................................... 37
3.1 BASELINE STUDY AREA AND PERIOD ............................................................................................ 37
3.2 METHODOLOGY ..................................................................................................................................... 38
3.2.1 Frequency of Sampling ......................................................................................................................... 38
3.2.2 Method of Environmental Sampling and Analysis ............................................................................... 39
3.3 MICROMETEOROLOGY ........................................................................................................................ 42
3.3.1 Temperature ......................................................................................................................................... 43
3.3.2 Humidity ............................................................................................................................................... 43
3.3.3 Wind Speed and Wind Direction .......................................................................................................... 45
3.3.4 Wind Rose ............................................................................................................................................. 45
3.3.5 Wind & Cyclone Vulnerability ............................................................................................................... 47
3.3.6 Interpretation of Micrometeorological Data ........................................................................................ 47
3.4 AIR ENVIRONMENT ............................................................................................................................... 47
3.4.1 Selection of Sampling Locations ........................................................................................................... 48
3.4.2 Frequency and Parameters for Sampling ............................................................................................. 50
3.4.3 Methodology for Sampling and Analysis .............................................................................................. 50
3.4.4 Quality of Ambient Air .......................................................................................................................... 50
3.4.5 Summary of Ambient Air Quality.......................................................................................................... 52
3.4.6 Interpretation of Ambient Air Quality Data ......................................................................................... 52
3.5 NOISE ENVIRONMENT ......................................................................................................................... 52
3.5.1 Sources of Noise Pollution .................................................................................................................... 52
3.5.2 Noise Level in the Study Area ............................................................................................................... 52
3.5.3 Summary of Noise Data ........................................................................................................................ 55
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxvi 2018_ECSS_EIAI1_1800028
3.5.4 Interpretation of Noise Data ................................................................................................................ 55
3.6 LAND ENVIRONMENT ........................................................................................................................... 55
3.6.1 Land Use Pattern of the Study area ...................................................................................................... 55
3.6.2 Drainage Map ....................................................................................................................................... 58
3.7 GEOLOGY ................................................................................................................................................ 59
3.7.1 Earthquake Vulnerability ...................................................................................................................... 60
3.8 HYDROGEOLOGY .................................................................................................................................. 60
3.9 TRAFFIC STUDY ..................................................................................................................................... 63
3.9.1 Interpretation of Traffic Study .............................................................................................................. 64
3.10 SOIL QUALITY ....................................................................................................................................... 64
3.10.1 Summary of Soil Data ......................................................................................................................... 66
3.10.2 Interpretation of Soil Data .................................................................................................................. 67
3.11 WATER ENVIRONMENT ..................................................................................................................... 67
3.11.1 Reconnaissance .................................................................................................................................. 67
3.11.2 Water Quality ..................................................................................................................................... 67
3.11.3 Sampling and Analysis ........................................................................................................................ 67
3.11.4 Ground Water ..................................................................................................................................... 67
3.11.5 Summary of Ground Water Quality .................................................................................................... 72
3.11.6 Interpretation of Ground Water Quality Data ................................................................................... 72
3.11.7Surface Water ...................................................................................................................................... 72
3.11.8 Summary of Surface Water Quality .................................................................................................... 77
3.11.9 Interpretation of Surface Water Quality Data .................................................................................... 78
3.12 ECOLOGY AND BIODIVERSITY ........................................................................................................ 78
3.12.1 Methodology Adopted for the Study of Flora and Fauna .................................................................. 78
3.12.2 Floral Diversity of the Study Area ....................................................................................................... 78
3.12.3 Interpretation of Ecology and Biodiversity ......................................................................................... 83
3.13 SOCIO-ECONOMIC ENVIRONMENT ............................................................................................... 83
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxvii 2018_ECSS_EIAI1_1800028
3.13.1 Socio-Economic Survey Methodology ................................................................................................ 83
3.13.2 Demography ....................................................................................................................................... 84
3.13.3 Population Density ............................................................................................................................. 84
3.13.4 Sex Ratio ............................................................................................................................................. 85
3.13.5 Literacy Rate ....................................................................................................................................... 86
3.13.6 Economic Aspects ............................................................................................................................... 88
3.13.7 Amenities ............................................................................................................................................ 91
3.13.8 Interpretation of Socio Economic Data .............................................................................................. 93
3.14 SUMMARY .............................................................................................................................................. 93
CHAPTER – 4 ................................................................................................................................ 96
ANTICIPATED ENVIRONMENT IMPACT AND MITIGATION MEASURES ...................... 96
4.0 GENERAL ................................................................................................................................................. 96
4.1 IMPACTS IDENTIFICATION DURING CONSTRUCTION PHASE ................................................. 96
4.1.1 Matrix Representation.......................................................................................................................... 97
4.1.2 Air Environment .................................................................................................................................... 99
4.1.3 Water Environment ............................................................................................................................ 100
4.1.4 Soil Environment ................................................................................................................................ 100
4.1.5 Noise Environment ............................................................................................................................. 101
4.1.6 Land Use/ Land Cover ......................................................................................................................... 102
4.1.7 Hydrogeology ..................................................................................................................................... 102
4.1.8 Geology ............................................................................................................................................... 103
4.1.9 Solid/Hazardous Waste ...................................................................................................................... 103
4.1.10 Risks and Hazards ............................................................................................................................. 103
4.1.11 Ecology and Biodiversity ................................................................................................................... 104
4.1.12 Socio-Economy ................................................................................................................................. 104
4.2 ANTICIPATED ENVIRONMENTAL IMPACTS DURING OPERATION PHASE .......................... 105
4.2.1 Matrix Representation........................................................................................................................ 105
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxviii 2018_ECSS_EIAI1_1800028
4.2.2 Air Environment .................................................................................................................................. 108
4.2.3 Water Environment ............................................................................................................................ 119
4.2.4 Soil Environment ................................................................................................................................ 120
4.2.5 Noise Environment ............................................................................................................................. 122
4.2.6 Land Use/Land Cover .......................................................................................................................... 122
4.2.7 Hydrogeology ..................................................................................................................................... 122
4.2.8 Geology ............................................................................................................................................... 123
4.2.9 Solid/Hazardous Wastes ..................................................................................................................... 123
4.2.10 Risk & Hazards .................................................................................................................................. 124
4.2.11 Ecology and Biodiversity ................................................................................................................... 125
4.2.12 Socio-Economic ................................................................................................................................ 127
4.3 SUMMARY .............................................................................................................................................. 129
CHAPTER – 5 .............................................................................................................................. 130
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE) ............................................... 130
5.0 GENERAL ............................................................................................................................................... 130
5.1 Alternative for Sites & other Aspects................................................................................................... 130
5.2 SUMMARY .............................................................................................................................................. 132
CHAPTER – 6 .............................................................................................................................. 133
ENVIRONMENTAL MONITORING PROGRAM .................................................................... 133
6.1 GENERAL ............................................................................................................................................... 133
6.2 NEED FOR ENVIRONMENTAL MONITORING ............................................................................... 133
6.3 MONITORING PLAN & PROGRAM ................................................................................................... 133
6.4 INFRASTRUCTURAL REQUIREMENT ............................................................................................. 136
6.5 ENVIRONMENT MANAGEMENT CELL ............................................................................................ 136
6.6 CURRENT & PROPOSED PRACTICES FOR ENV. PROTECTION ............................................ 137
6.6.1 Handling of Raw Materials and Mitigation Measures ........................................................................ 137
6.6.2 Risk Assessment and Damage control ................................................................................................ 137
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxix 2018_ECSS_EIAI1_1800028
6.6.3Compliance to the recommendations of CREP guidelines .................................................................. 137
6.7CONCLUDING REMARKS .................................................................................................................... 138
6.8 SUMMARY .............................................................................................................................................. 140
CHAPTER – 7 .............................................................................................................................. 141
ADDITIONAL STUDIES ............................................................................................................. 141
7.0 GENERAL ............................................................................................................................................... 141
7.1 PUBLIC HEARING ................................................................................................................................. 141
7.1.1 Advertisement and Photographs........................................................................................................ 142
7.2 EIC STUDY ............................................................................................................................................. 146
7.3 RISK ASSESSMENT AND SAFETY MANAGEMENT ..................................................................... 146
7.3.1 Introduction ........................................................................................................................................ 146
7.3.2 Objective, Philosophy and Methodology of Risk Assessment ............................................................ 146
7.3.3 Hazardous Material, Process & Safety ............................................................................................... 147
7.4 OCCUPATIONAL SAFETY & HEALTH PROGRAM ........................................................................ 149
7.4.1 Construction and Erection .................................................................................................................. 150
7.4.2 Operation and Maintenance .............................................................................................................. 150
7.4.3 Hospital facilities ................................................................................................................................ 150
7.4.4 Factory medical officer ....................................................................................................................... 151
7.4.5 Ambulance van ................................................................................................................................... 151
7.4.6 First aid box ........................................................................................................................................ 151
7.4.7 Periodic medical examination ............................................................................................................ 151
7.4.8 Management plan for occupational health & safety ......................................................................... 151
7.5 FIRE FIGHTING SYSTEM AND EMERGENCY MANAGEMENT .................................................. 153
7.5.1 Firefighting system ............................................................................................................................. 153
7.5.2 Emergency Management ................................................................................................................... 154
7.6 RISK ASSESSMENT STUDY .............................................................................................................. 155
7.6.1 Hazard Identification .......................................................................................................................... 156
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxx 2018_ECSS_EIAI1_1800028
7.6.2 Hazard Assessment and Evaluation .................................................................................................... 157
7.6.3 MCA Scenarios and Consequences Analysis ....................................................................................... 159
7.6.4 Definitions & Explanation of Terms Used ........................................................................................... 160
7.6.5 Possible Accident Scenario ................................................................................................................. 161
7.6.6 SAFETY HAZARD .................................................................................................................................. 164
7.6.7 Safety organization ............................................................................................................................. 167
7.6.8 Observations & Recommendations .................................................................................................... 168
7.7 ONSITE EMERGENCY PLAN AND DISASTER MANAGEMENT PLAN ..................................... 169
7.8 OFFSITE EMERGENCY PLANS ........................................................................................................ 177
7.9 SUMMARY .............................................................................................................................................. 180
CHAPTER – 8 .............................................................................................................................. 182
PROJECT BENEFITS ................................................................................................................ 182
8.0 GENERAL ............................................................................................................................................... 182
8.1 EMPLOYMENT POTENTIAL ............................................................................................................... 182
8.2EMPLOYMENT POTENTIAL ................................................................................................................ 183
8.3DIRECT REVENUE EARNING TO THE NATIONAL & STATE EXCHEQUER ............................ 184
8.4INFRASTRUCTURAL BENEFITS ........................................................................................................ 184
8.5 OTHER TANGIBLE BENEFITS ........................................................................................................... 184
8.6 SUMMARY .............................................................................................................................................. 184
CHAPTER – 9 .............................................................................................................................. 186
COST BENEFIT ANALYSIS ..................................................................................................... 186
9.0 GENERAL ............................................................................................................................................... 186
9.1 APPLICABILITY OF CBA AND SUMMARY ...................................................................................... 186
CHAPTER – 10 ............................................................................................................................ 187
ENVIRONMENTAL MANAGEMENT PLAN ........................................................................... 187
10.0 GENERAL ............................................................................................................................................. 187
10.1 OBJECTIVES OF EMP ....................................................................................................................... 187
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxi 2018_ECSS_EIAI1_1800028
10.2 ENVIRONMENTAL MANAGEMENT PLAN ..................................................................................... 187
10.2.1 Land Environment & Solid/Hazardous Waste Management ........................................................... 187
10.2.2 Air Environment Management ......................................................................................................... 189
10.2.3 Water Environment .......................................................................................................................... 192
10.2.5 Noise Environment ........................................................................................................................... 202
10.2.6 Occupational Health & Safety .......................................................................................................... 203
10.3 TRANSPORATION/TRAFFIC MANAGEMENT PLAN FOR VEHICLES .................................... 205
10.4 CLEANER PRODUCTION PRACTICES ......................................................................................... 206
10.4.1 Conservation of Water ..................................................................................................................... 206
10.4.2 Conservation of Raw Materials& Fuel .............................................................................................. 207
10.4.3 Conservation of Energy .................................................................................................................... 207
10.5 DRAINAGE & RAINWATER HARVESTING PLAN ........................................................................ 207
10.5.1 Rainwater Harvesting (Recharging) System ..................................................................................... 207
10.6 BUDGETARY PROVISIONS FOR EMS .......................................................................................... 209
10.7 ENVIRONMENTAL MANAGEMENT CELL (EMC) ........................................................................ 209
10.8 CORPORATE ENVIRONMENTAL RESPONSIBILITY ................................................................. 210
10.9 SUMMARY ............................................................................................................................................ 211
CHAPTER-11 ............................................................................................................................... 212
SUMMARY & CONCLUSION ................................................................................................... 212
11.1 INTRODUCTION.................................................................................................................................. 212
11.2 PROJECT DESCRIPTION ................................................................................................................. 212
11.3 DESCRIPTION OF THE ENVIRONMENT ....................................................................................... 212
11.4 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES ............................ 214
11.5 ANALYSIS OF ALTERNATIVES ....................................................................................................... 215
11.6 ENVIRONMENTAL MONITORING PROGRAM ............................................................................. 215
11.7 ADDITIONAL STUDIES ...................................................................................................................... 215
11.8 PROJECT BENEFIT ............................................................................................................................ 215
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxii 2018_ECSS_EIAI1_1800028
11.9 ENVIRONMENTAL COST BENEFIT ANALYSIS ........................................................................... 215
11.10 ENVIRONMENTAL MANAGEMENT PLAN .................................................................................. 216
11.11 CONCLUSION AND RECOMMENDATION .................................................................................. 216
CHAPTER – 12 ............................................................................................................................ 217
DISCLOSURE OF CONSULTANT ENGAGED ..................................................................... 217
12.0 GENERAL ............................................................................................................................................. 217
12.1 BRIEF RESUME AND NATURE OF CONSULTANCY ................................................................. 217
12.2 NAME OF EIA TEAM MEMBERS/ FUNCTIONAL AREA ASSOCIATES ................................... 217
12.3 LABORATORY INVOLVED FOR BASELINE MONITORING AND OTHER ANALYSIS ......... 218
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxiii 2018_ECSS_EIAI1_1800028
LIST OF TABLES
Table 1.1 Project Co-ordinate ............................................................................................................................. 2
Table 1.2 Regulatory Framework ....................................................................................................................... 6
Table 1.3 Structure of EIA report ........................................................................................................................ 7
Table 2.1 - Salient Features of the Project Site ............................................................................................. 14
Table 2.2 - Climate Type and Details .............................................................................................................. 15
Table 2.3-Water Consumption Details ............................................................................................................ 18
Table 2.4 Cost Break Up ................................................................................................................................... 19
Table 2.5-Requirements of Raw Materials ..................................................................................................... 19
Table 2.6- Product Details ................................................................................................................................. 20
Table 2.7- Transportation of Product ............................................................................................................... 20
Table 2.8: Details of Cooling Tower ................................................................................................................. 27
Table:2.9- Air Pollution Control Details ........................................................................................................... 30
Table 2.10 - Wastewater Generation Details ................................................................................................. 31
Table 2.11–Solid and Hazardous Waste Details ........................................................................................... 34
Table 2.12 - Aspect Impact Analysis ............................................................................................................... 35
Table 2.13 - Project Implementation Schedule .............................................................................................. 36
Table 3.1 Frequency of Environmental Monitoring ........................................................................................ 38
Table 3.2 Method of Environmental Sampling and Analysis........................................................................ 39
Table 3.3 Meteorological Condition of Study Area ........................................................................................ 42
Table 3.4 Ambient Air Quality Monitoring Locations in the Study Region ................................................. 49
Table 3.5 Details of Analysis Method .............................................................................................................. 50
Table 3.6 Min, Max, 98th Percentile and Average Value of PM10 and PM2.5 ......................................... 50
Table 3.7 Min, Max, 98th Percentile and Average Value of SO2 and NOx ............................................... 51
Table 3.8 Min, Max, 98th Percentile and Average Value of CO .................................................................. 51
Table 3.9 Noise Monitoring Locations in the Study Region ......................................................................... 53
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxiv 2018_ECSS_EIAI1_1800028
Table 3.10 Noise Monitoring report during day time ..................................................................................... 54
Table 3.11 Noise Monitoring report during night time ................................................................................... 54
Table 3.12 Land use Pattern of Study Area ................................................................................................... 57
Table 3.13 Traffic Study Report ........................................................................................................................ 63
Table 3.14 Existing Traffic Scenario with respect to LOS ............................................................................ 63
Table 3.15 Details of Soil sampling location ................................................................................................... 65
Table 3.16 Soil Sample Analysis Result ......................................................................................................... 65
Table 3.17 Details of Ground Water sampling locations .............................................................................. 69
Table 3.18 Ground water Analysis Results..................................................................................................... 70
Table 3.19 Details of Surface Water Sampling Locations ............................................................................ 73
Table 3.20 Surface water Analysis Results .................................................................................................... 74
Table 3.21 Bacteriological Analysis of surface Water ................................................................................... 75
Table 3.22 Standard limit as per IS 10500:2012 for Microbiological parameters ..................................... 75
Table 3.23 Trees in the Study area .................................................................................................................. 78
Table 3.24 List of Shrubs in the study area .................................................................................................... 80
Table 3.25 List of Herbs in the study area ...................................................................................................... 81
Table 3.26 List of Climbers in the study area ................................................................................................. 81
Table 3.27 List of Grass in the study area ...................................................................................................... 81
Table 3.28 List of Mammals in the Study area ............................................................................................... 81
Table 3.29 List of Birds in the Study area ....................................................................................................... 82
Table 3.30 List of Reptiles in the Study area .................................................................................................. 82
Table 3.31 Details of Population in Study Area ............................................................................................. 84
Table 3.32 Details of Sex Ratio in Study Area ............................................................................................... 85
Table 3.33 Details of Literacy Rate in Study Area ......................................................................................... 86
Table 3.34 Details of Occupational Structure ................................................................................................. 88
Table 4.1: Impact Matrix with Mitigation Measures (Construction Phase) ................................................. 97
Table 4.2: Severity Criteria for Magnitude of Impacts ................................................................................... 97
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxv 2018_ECSS_EIAI1_1800028
Table 4.3: Score range for beneficial and adverse impacts ......................................................................... 97
Table 4.4: Environmental Impact Matrix without Mitigation (Construction Phase) ................................... 98
Table 4.5: Impact on Air Environment and Mitigation Measures ................................................................. 99
Table 4.6: Impact on Water Environment and Mitigation Measures ......................................................... 100
Table 4.7: Impact on Soil Environment and Mitigation Measures ............................................................. 100
Table 4.8: Impact on Noise Environment and Mitigation Measures ......................................................... 101
Table 4.9: Impact on Land Cover/ Land Use and Mitigation Measures ................................................... 102
Table 4.10: Impact on Hydrogeology and Mitigation Measures ................................................................ 102
Table 4.11: Impact on Geology and Mitigation Measures .......................................................................... 103
Table 4.12: Impact due to Solid/ Hazardous waste and Mitigation Measures ........................................ 103
Table 4.13: Impact of Risk and Hazards and Mitigation Measures .......................................................... 103
Table 4.14: Impact on Ecology and Biodiversity and Mitigation Measures ............................................. 104
Table 4.15: Impact on Socio Economic and Mitigation Measures ............................................................ 104
Table 4.16: Environmental Impact Matrix with Mitigation (Construction Phase)..................................... 105
Table 4.17 - Impact Matrix with Mitigation Measures (Operation Phase) ................................................ 106
Table 4.18 - Environmental Impact Matrix without Mitigation (Operation Phase) .................................. 107
Table 4.19– Vehicles required daily ............................................................................................................... 108
Table 4.20 - Recommendations on Traffic Capacity as per IRC 2010 ..................................................... 108
Table 4.21 - Modified Traffic Scenario and LOS .......................................................................................... 109
Table 4.22 - AQI Index ..................................................................................................................................... 110
Table 4.23 - AQI Values for Different Parameters ....................................................................................... 111
Table 4.24 - Stack Data for Air Modeling ...................................................................................................... 113
Table 4.25 - Resultant Concentration Value ................................................................................................ 116
Table 4.26 - Impact and Mitigation Measures on Air Environment ........................................................... 117
Table 4.27 - Impact and Mitigation Measures on Water Environment ..................................................... 119
Table 4.28 - Impact and Mitigation Measures on Soil Environment ......................................................... 120
Table 4.29 - Impact and Mitigation Measures on Noise Environment ...................................................... 122
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxvi 2018_ECSS_EIAI1_1800028
Table 4.30 - Impact and Mitigation Measures on Land Cover/ Land Use ................................................ 122
Table 4.31 - Impact and Mitigation Measures on Hydrogeology ............................................................... 122
Table 4.32 - Impact and Mitigation Measures on Geology ......................................................................... 123
Table 4.33 - Impact and Mitigation Measures due to Solid/Hazardous Wastes ..................................... 123
Table 4.34 - Impact and Mitigation Measures due to Risk & Hazards ..................................................... 124
Table 4.35 - Impact and Mitigation Measures due to Ecology and Biodiversity ..................................... 125
Table 4.36 - Impact on Socio Economic and Mitigation Measures ........................................................... 127
Table 4.37 - Environmental Impact Matrix with Mitigation (Operation Phase) ........................................ 128
Table 5.1 - Alternative for other Parameters ................................................................................................ 130
Table 6.1: Monitored Stack Emission Characteristics ................................................................................. 134
Table 6.2: Effluent Characteristics ................................................................................................................. 135
Table 6.3: Compliance to the Charter on CREP for large Pulp and Paper industry .............................. 137
Table 7.1 – Time bound action plan of the issues raised during public hearing ..................................... 143
Table 7.2 - Properties of storage chemicals used at the mill ..................................................................... 148
Table 7.3 - Properties of Hazardous Chemical ............................................................................................ 148
Table 7.4 - Properties of Hazardous Chemical ............................................................................................ 149
Table 7.5 - Work Place Monitoring in the Industrial Premises ................................................................... 152
Table 7.6 - Health Evaluation of Workers ..................................................................................................... 153
Table 7.7- Preliminary hazard analysis for process and storage areas ................................................... 158
Table 7.8 - Preliminary hazard analysis for the whole plant in general .................................................... 158
Table 7.9: Threshold values of the Hazardous Chemicals ....................................................................... 161
Table 7.10: Atmospheric Condition Assumed .............................................................................................. 162
Table 7.11: Source Strength considered ..................................................................................................... 162
Table 7.12: Threat zone of toxic gas concentration (AEGL Value).......................................................... 163
Table 7.13: Hazards and its control measures for Chlorine Dioxide ........................................................ 164
Table 7.14: Important Telephone No. ............................................................................................................ 180
Table 7.15: List of vehicles .............................................................................................................................. 180
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxvii 2018_ECSS_EIAI1_1800028
Table 8.1 - CER Expenditure .......................................................................................................................... 183
Table 10.1 - Waste Disposal Details .............................................................................................................. 188
Table 10.2 - Technical Specification of ESP ................................................................................................ 191
Table 10.3: Existing equipment‟s with dimensions, volume and retention time ...................................... 194
Table 10.4: Characteristics of Raw Effluent at the Inlet and Effluent after Treatment after Expansion
............................................................................................................................................................................. 195
Table 10.5 - Species Selection for Pollution Control ................................................................................... 199
Table 10.6 - Traffic Management Plan .......................................................................................................... 205
Table 10.7: Rainwater Harvesting Calculation ............................................................................................. 208
Table 10.8 - Cost Break-Up for Environment Management System (EMS) ............................................ 209
Table 10.9 -CER Plan with 5 Years Break-UP ............................................................................................. 210
Table12.1 -EIA Team Member ....................................................................................................................... 217
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxviii 2018_ECSS_EIAI1_1800028
LIST OF FIGURES
Figure 1.1 - Location Map of Proposed Area 3
Figure 2.1- Photographs of Site (Clockwise) 12
Figure 2.2 - Google Earth Image (Short View) 13
Figure 2.3 - Google Earth Image (Long View) 14
Figure 2.4- Plant Layout 17
Figure 2.5 – Process flow diagram of CPP 26
Figure 2.6: Rice Husk handling system 28
Figure 2.7 – Rice Husk Handling System 29
Figure 2.8 - APC for Boiler Flue gases and scheme of Ash Handling 30
Figure 2.9 - Water Balance Diagram for Existing Paper Manufacturing Process 32
Figure 2.10 - Water Balance Diagram for proposed Paper Manufacturing Process 33
Figure 3.1 Study Area Map 37
Figure 3.2 Photograph showing the sampling activity 42
Figure 3.3 Graphical Presentation for the month wise Temperature Variation 43
Figure 3.4 Graphical Presentation for the month wise Humidity Variation 44
Figure 3.5 Wind Rose Diagram 46
Figure 3.5(A) Wind & Cyclone Vulnerability Map 47
Figure 3.6 Map showing the Study Region location of Ambient Air 49
Figure 3.7 Map showing the study region location of Noise 53
Figure 3.8 Methodology Used for Land use Classification 56
Figure 3.9 Land Use 57
Figure 3.10 Land Use Statistics 58
Figure 3.11 Drainage Map 59
Figure 3.12 Earthquake Vulnerability Map 60
Figure 3.13 Map showing the study region location of Soil 65
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xxxix 2018_ECSS_EIAI1_1800028
Figure 3.14 Map showing the study region with locations for Ground Water 68
Figure 3.15 Map showing the locations for Surface water 73
Figure 3.16: Graph of Literacy Rate 88
Figure 3.17 Occupational Structure of Study Area 90
Figure 4.1: Impact Quantification Matrix 98
Figure 4.2 - Isopleths for Concentration of PM 114
Figure 4.3 -Isopleths for Concentration of SO2 115
Figure 4.4 - Isopleths for Concentration of NOx 116
Figure-7.1: Source Strength in case of Chlorine Dioxide gas escape 163
Figure-7.2: Isopleths result of Toxic threat zone 163
Figure 10.1– Schematic Flow Diagram of ESP 192
Figure 10.2–Existing ETP schematic Flow Diagram 195
Figure 10.3 –Proposed ETP schematic Flow Diagram 196
Figure 10.4 - Flow Diagram of Chemical Recovery Plant 197
Figure 10.5 - Greenbelt Development Layout 199
Figure 10.6 Photographs of Existing Green Belt 202
Figure 10.7 – Existing Rainwater Harvesting System 208
Figure 10.8 -Organogram of Environmental Management Cell 210
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xl 2018_ECSS_EIAI1_1800028
LIST OF ANNEXURES
Annexure-I: ToR Letter .................................................................................................................................. 219
Annexure-II: Existing EC & its Compliance ............................................................................................. 220
Annexure-III: Existing Consents & its compliance ................................................................................ 221
Annexure-IV: Land Details ........................................................................................................................... 222
Annexure-V: Water Permission in English & Punjabi language ........................................................ 223
Annexure-VI: MoU of Fly Ash ...................................................................................................................... 224
Annexure-VII: Undertaking for Fly Ash ..................................................................................................... 225
Annexure-VIII: Agreement of Lime Sludge .............................................................................................. 226
Annexure-IX: Health Records ...................................................................................................................... 227
Annexure-X: Details of Fire Equipments & Hydrants ........................................................................... 228
Annexure-XI: MSDS........................................................................................................................................ 229
Annexure-XII: EHS Policy ............................................................................................................................. 230
Annexure-XIII: CREP Compliance Report ................................................................................................ 231
Annexure-XIV: NABET Certificate .............................................................................................................. 232
Annexure-XV: Hydro Geological Study .................................................................................................... 233
Annexure-XVI: MoU With FMO/Hospitals ................................................................................................. 234
Annexure-XVII: Public hearing Proceedings ........................................................................................... 235
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat xli 2018_ECSS_EIAI1_1800028
ABBREVIATIONS
1. APC-Air Pollution Control Device
2. APHA – American Public Health Association
3. CPCB-Central Pollution Control Board
4. MoEF-Ministry of Environment, Forest and Climate Change
5. BOD – Biological Oxygen Demand
6. CER-Corporate Environment Responsibility
7. COD – Chemical Oxygen Demand
8. CPP-Captive Power Plant
9. DMP-Disaster Management Plan
10. EC – Environmental Clearance
11. ECC – Emergency Control Center
12. EIA – Environmental Impact Assessment
13. EMC – Environmental Management Cell
14. EMP – Environmental Management Plan
15. EQS- Environmental quality Score
16. ESP – Electrostatic Precipitator
17. ETP-Effluent Treatment Plant
18. GLC- Ground Level Concentration
19. GoI - Government Of India
20. PPCB – Punjab Pollution Control Board
21. HSD – High Speed Diesel
22. IMD –Indian Meteorological Department
23. KLD-Kilo liter per day
24. LU-Land Use
25. MPN – Most Probable Number
26. NOx – Oxides of Nitrogen
27. PPE- Personnel Protective Equipments
28. PRDS-Pressure Reducing and Desuperheating System
29. QA – Quality Assurance
30. QC- Quality Control
31. RA-Risk Assessment
32. RSPM – Resiparable Suspended Particulate Matter
33. RWH-Rain Water Harvesting
34. SO2 – Sulphur Dioxide
35. SPM – Suspended Particulate Matter
36. TPA - Metric Tonne Per Annum
37. WBD - Water balance Diagram
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 1 2018_ECSS_EIAI1_1800028
CHAPTER 1
INTRODUCTION
1.0 PRELUDE
The worldwide Paper industry is experiencing steady growth, supported primarily by the constantly
rising demand for paper for both writing/printing and packaging applications. The paper can be
obtained primarily as a forest product modified further in a paper mill. Forests are the source of
sustainability and survival for a large populace as well as the most precious renewable resources
contributing towards the economic development. The increased demand for forest products, fast
population growth, urbanization, a higher rate of economic growth and trade liberalization are exerting
greater pressure on these resources. Hence, a reliable and environmentally viable alternative for this
is the waste paper/ agro residue based paper production. India is self-sufficient in terms of raw
materials, technology and strong scientific background as well as the long proven expertise in
producing quality paper products from these raw materials.
The Government of India, as per its policy has given emphasis on Sustainable Development as a part
of any developmental activity. Along with industrial growth, environmental protection is an integrated
criterion for this concept. In line with this policy, Ministry of Environment, Forests and Climate Change
(MoEF&CC) New Delhi has defined „Environmental Clearance‟ (EC) framework under the
Environmental Protection Act, 1986. As per the EIA Notification - 2006, prior EC is required for
establishing/expanding the industry/development projects.
M/s Satia Industries Limited is located atMuktsar – Malout Road, PO : Village Rupana, Dist: Sri
Muktsar Sahib, Punjab – 152032, falling under Large Scale Category manufacturing of Writing &
Printing Paper along with CPP for which the company had obtained Consent To Establish and
Operate from Punjab Pollution Control Board. The company proposes to enhance the capacity of
existing products under the category “Pulp and Paper Industries”.
1.1 PURPOSE OF THE REPORT
The purpose of this EIA/EMP report is to identify, predict and evaluate the environmental impacts of
the proposed actions and mitigating the biophysical, social, and other relevant effects of development
proposals prior to major decisions being taken and commitments made. Thus, EIA studies integrate
the environmental concerns of developmental activities into the process of decision-making. The
project will be developed using the state of art technology, adopting modernized machineries and
equipment, with waste minimization techniques.
The purpose of this report is to identify, predict and evaluate the environmental impacts for proposed
expansion of Paper Industry located at Muktsar – Malout Road, PO : Village Rupana, Dist: Sri
Muktsar Sahib, Punjab – 152032.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 2 2018_ECSS_EIAI1_1800028
1.2 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT
1.2.1 Identification of the project
Satia Industries Limited proposes to enhance the production capacity of Writing & Printing Paper
from 300 TPD to 600 TPD and proposes to install 14 MW Captive Power Plant along with existing 30
MW CPP. The proposed expansion will be carried out using the state of art technology, adopting
modernized machineries and equipment and novel process technologies, with waste minimization
techniques.
1.2.2 Identification of the Project Proponent
Satia Industries Limited (SIL) has been promoted by Dr. Ajay Satia in the year 1984, who toiled hard
during initial period of militancy in Punjab and made this Project viable and model unit with his hard
work, sincerity and excellent team building spirit now having three paper machines at Muktsar –
Malout Road, PO : Village Rupana, Dist: Sri Muktsar Sahib, Punjab – 152032, which is
manufacturing 300 TPD of eco-friendly paper using agricultural residues (Wheat Straw, Sarkanda,
Baggasse, Cotton Sticks), Wood Base (Wood, Veneer & Bamboo Chips) as raw material.
With the entry of second generation of the family Shree Chirag Satia, Executive Director entering the
family business, SIL intends to increase its present production capacity from 300 TPD to 600 TPD
by expanding its project and adding a 14.0 MW CPP.
1.3 BRIEF DESCRIPTION OF PROJECT
1.3.1 Nature, Size and Location of the Project
M/s Satia Industries Limited is a Large Scale unit located atMuktsar – Malout Road, PO : Village
Rupana, Dist: Sri Muktsar Sahib, Punjab – 152032 having total plot area of 45.55 Acres (Existing
36.02 acres and new land of 9.53 acres) & total investment after proposed expansion will be Rs. 500
Crores. The proponent wishes to enhance the Production capacity of Existing Products from 300 TPD
to 600 TPD as well introduce higher capacity of turbine (CPP) i.e. existing 30 MW +additional 14 MW.
The center co ordinates is 30025‟15.86” N Latitude & 72031‟12.71” E Longitude. The project site is
well connected by rail and road. Nearest railway station from project site is Sri Muktsar Sahib. The
location map of the proposed project is shown as Figure No: 1.1.
Approx. four corners Latitudes and Longitudes of the proposed project are as under:
Table 1.1 Project Co-ordinate
Corner Latitude Longitude
A 30°25'11.10"N 74°31'19.16"E
B 30°25'24.87"N 74°31'18.11"E
C 30°25'16.49"N 74°30'54.78"E
D 30°25'06.74"N 74°31'0.93"E
Sri Muktsar Sahib is the biggest railway station in the study area. Beside the rail connectivity, the site is
also well connected by road network. There is a good network of roads in the area which contributes to
the development and economic growth of the area. TheState highway No.41 has given a further boost
to the economic growth of this area. The other major road is State Highway No. 41 (Bhatinda –
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 3 2018_ECSS_EIAI1_1800028
Bhisiana – Sri Muktsar Sahib). Almost every village in the district is now well connected to each other
by a Pucca road. This will help the local people to commute easily as well as allow the transport of Raw
materials & finished Products.
Figure 1.1 - Location Map of Proposed Area
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 4 2018_ECSS_EIAI1_1800028
1.3.2 Importance to the Country and Region
Demand –Supply Gap
The Writing Printing Paper is used for text books, stationary,note books of all sizes,MF Board paper.
Since our products are approved by quality conscious users which are multinational companies;we
intend to cater the ever increasing demand in India as well as in the Export Market. After globalization
of Indian market, demand for paper is increasing but quality paper manufacturing is not growing at the
same pace. Hence, the company shall fill up this gap by proposing expansion in quality paper making
in an environment friendly manner. The annual global paper and paperboard production was
approximately 382.0 million tonnes in 2006. It increased to 402.0 million tonnes in 2010 and is
expected to increase to 490.0 million tonnes by 2020. The global pulp and paper industry consists of
about 5000 industrial pulp and paper mills, and an equal number of very small companies.
Paper and Paperboard Production – Global Market, 2002-20 (In million tonnes)
INDIAN PAPER INDUSTRY SCENARIO
India is the 15th largest paper producer in the world. It provides employment to nearly 1.5 million
people and contributes Rs. 25.0 billion to the government's exchequer. In the last 55 years, the
number of paper mills has increased from just 17 mills in 1951 to more than 666 units engaged in the
manufacture of paper and paperboard.
Due to the increasing regulation and raw material prices, companies are increasingly using more non-
wood based raw materials over the years. In 2006, around 70 % of the total production was based on
non-wood raw materials/waste paper.
321.4 328.1 360.0 366.0 382.0 402.0
490.0
2002 2003 2004 2005 2006 2010 2020
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 5 2018_ECSS_EIAI1_1800028
According to Indian Paper Manufacturers Association (IPMA), consumption of paper in India is set to
double from the current 7.0 million tonnes per annum by 2015 (v) Market Scenario (domestic market,
Export Possibility ).
Breakdown of Different Paper Consumption and Production Details
S. No. Type of Paper Consumption (MMTPA) Production (MMTPA)
1. News print 22.60 11.10
2. Writing Printing 40.11 38.45
3. Paper Board 52.65 50.50
Projected Production & Consumption (2024-2025)
S. No.
Type of Paper Consumption (MMTPA) Production (MMTPA)
1. Production of Paper, Paper
Board, News print
23.5 Million Tonnes (Baseline scenario)
36.9 million Tonnes (Optimistic Scenario)
22.0 Million Tonnes (Baseline scenario)
33.4 million Tonnes (Optimistic Scenario)
Existing products manufactured in the country will be very much economical as compared to
Imports of the same.Moreover the export of the same will earn extra revenue generation for our
country.
4.9
6.7
9.1
12.2
4.5
6.1
8.2
9.5
2005 2010 2015 2020
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 6 2018_ECSS_EIAI1_1800028
Export Possibility
Existing products have high export potential. Also these products have very good potential in
the local market.
Additional capacities of product range required over & above the unit‟s existing capacities, as
the company expects strong growth of exports to the extent of 40-50%. Local market also
shows strong growth potential.
Domestic / export Markets
The Writing Printing Paper is used for stationary purpose, printing note books of all sizes and similar
other applications. These are having very good demand in domestic as well as international markets.
1.4 REGULATORY FRAMEWORK AND ENVIRONMENTAL CLEARANCE
The applicability of the SO 1533 for the proposed project was explored by considering different
possibilities and provisions made in the said EIA notification, SO 1533 amended on 14th September
2006. Agro residue based paper manufacturing plant falls under the category no. 5(i), Category “A” i.e.
pulp and paper manufacturing as per the provision of the S.O. 1533, EIA notification-2006. Also
installation of 14.0 MW Captive Power Plant (CPP) based on rice husk and biogas as fuel shall be done
within existing plant premises. General condition (“Power plants up to 15MW, based on biomass and
using auxiliary fuel such as coal / lignite /petroleum products up to 15% are exempt”) applies to
proposed CPP project, thus EC will not be applicable under the category no. 1(d).
Table 1.2 Regulatory Framework
S. No. Activity Aspect Legal Regulation
1. Paper
Manufacturing
Process
Air o Factory License
o The Factories Act, 1948
o The Custom Act, 1962
o Water (Prevention and Control of Pollution) Act,
Rules and Amendments, 1974, 1977, 1978, 1988
o Environment (Protection) Act, 1986
o Environment (Protection) Rules, 1991
o Air (Prevention and Control of Pollution) Act, Rules
and Amendments, 1981,1982, 1983, 1987
o Indian boiler act amendment 2015
o National Ambient Air Quality Standards, 2009
o Noise Pollution (Regulation and Control) Rules and
Amendments, 2000, 2006, 2010
o Solid/Hazardous Waste (Management and
Handling) Rules, 2000, 2016
o Environment (Protection) Act, 1986
o Environment (Protection) Rules, 1991
o Environment Impact Assessment Notification and
Noise
Water
SE
2. Storage,
transportation and
handling of materials
& Fuel
Air
Noise
Soil
SHW
SE
Risk &
Occupational
Hazards
3. Operation of CPP Air
Water
Noise
SHW
SE
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 7 2018_ECSS_EIAI1_1800028
Risk &
Hazards
Amendments, 2006, 2015
o Environmental Standards Notification and
Amendments, 1993
o The Public Liability Insurance Act, Rules and
Amendments, 1991, 1992, 1993
o The Motor Vehicles Act, 1988 and The Central
Motor Vehicle rules, 1989
o E-Waste (Management and Handling) Rules, 2011
as amended to date.
1.5 SCOPE AND OBJECTIVES OF THE STUDY
Detailed EIA/EMP report has been prepared in line with approved ToR issued by MoEFCC, New
Delhi, vide letter no.IA/PB/IND/89926/2018. MoEF&CC File No. J-11011/196/2014-IA II (I)] dated 16
April, 2019 and a copy of the same is attached as Annexure I and as per generic structure as per the
guideline provided by EAC. The EIA Study for the proposed project is limited to the project site and
study area of 10 km surrounding the project site. As per the guideline of Ministry of Environment
Forests & Climate Change (MoEF&CC) the scope of study includes detailed characteristics of
environmental components viz. Air, Noise, Water, Land, Biological and Socio-economic for one
season. For the purpose of environmental assessment, the villages in the surrounding areas have
been surveyed and relevant data has been collected.
1.6 STRUCTURE OF EIA REPORT
The generic structure of the EIA report as per the guideline provided by MoEF&CC is illustrated in the
following tabulated format.
Table 1.3 Structure of EIA report
S.
No. EIA Structure Contents
1. Introduction Purpose of the Report
Identification of project and project proponent
Brief description of nature, size, location of the project and its
importance to the country, region.
Scope of the study – details of regulatory scoping carried out (As per
terms of reference).
Site Selection Criteria
2. Project Description Type of project
Need for the project
Location details showing general location, specific location, project
boundary and project site layout.
Size or magnitude of operation
Project description including drawings showing project layout,
components of project etc.
Proposed schedule for implementation,
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 8 2018_ECSS_EIAI1_1800028
S.
No. EIA Structure Contents
Technology and process description,
Schematic representations of the feasibility drawings which give
information important for EIA purpose.
Description of mitigation measures incorporated into the project to
meet environmental standards, environmental operating conditions, or
other EIA requirements
3. Description of the
Environment
Study area, period, components and methodology.
Establishment of baseline for valued environmental components, as
identified in the scope.
Study Period: 1stDecember 2018 to 28thFebruary 2019
Base maps of all environmental components.
4. Anticipated
Environmental
Impacts and
Mitigation Measures
Details of Investigated Environmental impacts due to project location,
possible accidents, project design, project construction, regular
operations.
Measures for minimizing and / or offsetting adverse impacts identified.
Assessment of significance of impacts (Criteria for determining
significance, Assigning significance),
Impact scores and Mitigation measures
Air quality modeling
Air Quality Index
5. Analysis of
Alternatives
(Technology and
Site)
In case, the scoping exercise results in need for alternatives:
Analysis of Alternatives and Other Technology
Selection of alternative
6. Environmental
Monitoring Program
Technical aspects of environmental monitoring for the effectiveness of
mitigation measures (including measurement methodologies,
frequency, location, data analysis, reporting schedules, emergency
procedures, detailed budget and procurement schedules)
7. Additional Studies Risk Assessment
Disaster Management Plan
8. Project Benefits Physical Benefits
Ecological Benefits
Social Benefits
Other tangible Benefits
9. Environmental Cost
Benefit Analysis
Not applicable as it is not recommended on scoping stage and project
is located in notified industrial area.
10. Environment
Management Plan
Description of the administrative aspects of ensuring that mitigation
measures are implemented and their effectiveness monitored, after
approval of the Clearance. The Chapter consists of:
- Mitigation Measures for Impacts
- Pollution Prevention Plan
- Greenbelt Development Plan
- Waste Management Plan
- Environment Management Cell
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 9 2018_ECSS_EIAI1_1800028
S.
No. EIA Structure Contents
- Budgetary Provisions for EMS
11. Summary and
Conclusion
Overall project brief and justification for implementation of the project,
12. Disclosure of
Consultant Engaged
The names and details of the Consultants engaged in Preparing the
EIA Report.
1.7 SUMMARY
Satia Industries Limited is a pioneer in development, manufacturer of quality paper products and
marketing in domestic and international markets. Now Satia Industries Limited proposes to enhance
the capacity of existing products from 300 TPD to 600 TPD and proposes CPP of 14 MW along with
existing 30 MW at Muktsar – Malout Road, PO : Village Rupana, Dist: Sri Muktsar Sahib, Punjab –
152032.
The project falls under 5(i) of Schedule of list of industries of EIA Notification 2006.The Draft EIA
report has been prepared for submission to Punjab SPB. The Draft EIA report has been prepared for
Conducting the Public Hearing. A final EIA thereafter will be prepared incorporating the details of PH &
finally submitted to MoEF&CC for Appraisal & Obtaining EC.
-------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 10 2018_ECSS_EIAI1_1800028
CHAPTER 2
PROJECT DESCRIPTION
2.0 GENERAL
This chapter describes the type, need, location, size or magnitude of the project, operational
activities, technology to be used and other related activities. It also provides a condensed description
of the aspects which are likely to cause environmental effects to the surrounding environment and
mitigation measures provided to meet environmental standards. Capital investment provided for
environmental management plan to achieve the statutory norms.
2.1 TYPE OF PROJECT
M/s SATIA INDUSTRIES LIMITED is located at Muktsar –Malout Road, PO : Village Rupana, Dist:
Sri Muktsar Sahib, Punjab – 152032, falling under Large Scale Category manufacturing products as
mentioned under for which the company had obtained Environment Clearance vide no. F. No. J-
11011/196/2014/IA-II (I dated 29-05-2018) attached as Annexure-II and Satia has obtained Consent
To Operate from Punjab Pollution Control Board vide No. CTOA/Fresh/MKS/2018/7687794 Dated:
09/07/2018 and CTOW/Fresh/MKS/2018/7687650 Dated: 09/07/2018 attached as Annexure-III. The
company proposes to enhance the capacity of existing products under the category “Pulp and Paper
Industries”. The total investment of Rs.500.0 Crores is proposed for the expansion of the project.
2.2 NEED OF THE PROJECT
For developing countries like India, forests are sustenance and survival for a large populace. The
increased demand for forest products, fast population growth, urbanization, higher rate of economic
growth and trade liberalization are putting pressure on the forest resources. The demand for food to
feed increasing population causing extension in agriculture and shifting cultivation resulted into
decline in area under forests. During the last two decades, India witnessed annual depletion of forest
cover at the rate of 253 square kilometers. As a result, the need for developing alternatives for forest-
based products has arisen lately.
Paper manufacturing is a highly capital, energy & water intensive industry and is also considered as
one of the high pollution potential industry within the Indian economy. Paper industry is mainly
classified as - wood-based, agro-based and recycled based paper. The Indian paper industry is a
large consumer of forest-based raw material i.e. wood. Large numbers of trees are annually cut off for
the papermaking industry. Modernization in production techniques, equipments& technology along
with a sustainable outlook is a need of the present times. Adoption of more efficient and cleaner
technologies in the manufacturing the products are most effective in increasing the productivity and
also integrate economic, environmental, and social development objectives. In India, high availability
of agro waste could be a feasible solution for paper manufacturing mills with minimal impacts on the
forest &environment. In addition, use of agro residues as raw material would also resolve the pressing
issue of stubble burning by the farmers in the region.
Consumption of Writing paper is increasing day by day and the demand forecast for the current
financial year is 1.135 million tons and is expected to grow @ 6% during the next 3-4 years.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 11 2018_ECSS_EIAI1_1800028
According to estimates, large mills account for around 52% of paper production. According to Indian
Paper Manufacturers Association (IPMA), consumption of paper in India is set to double from the
current 7.0 million tonnes per annum by 2015. The annual global paper and paperboard production
was approximately 382.0 million tonnes in 2006. It increased to 402.0 million tonnes in 2010 and is
expected to increase to 490.0 million tonnes by 2020.Additional employment will be generated due
to modernization of the plant.
2.3 PROJECT LOCATION
2.3.1 Project Site Location
The proposed project shall be located at Muktsar –Malout Road, PO: Village Rupana, Dist: Sri
Muktsar Sahib, Punjab – 152032. The company had obtained Consent to Establish and Operate from
Punjab Pollution Control Board for existing unit. The industry shall apply for all the relevant
clearances before starting the expansion project. The total investment of Rs. 500.0 Crores is
proposed for the up expansion of the existing plant. Total land area acquired for the proposed
expansion project is 9.53 Acres with 36.02 acres land of existing plant (300TPD). Total area after
expansion (600TPD) will be 45.55 Acres. Land Documents are attached as Annexure IV.
The proposed expansion project site lies on 30025‟15.86” N Latitude & 74031‟12.71” E Longitude. M/s
Satia Industries Limited located at Muktsar – Malout Road, PO: Village Rupana, Dist: Sri Muktsar
Sahib, Punjab – 152032 is centrally located on Muktsar –Malout Road connecting Sri Muktsar Sahib
and Malout. Short view and Long view of Google Earth is depicted as Figure 2.2 and 2.3 respectively.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 12 2018_ECSS_EIAI1_1800028
Figure 2.1- Photographs of Site (Clockwise)
1. Side View 2. Raw material handling 3. Cooling tower 4. Power house 5. View of ETP 6. Godown
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 13 2018_ECSS_EIAI1_1800028
2.3.2 Site Selection Criteria
Site selection was guided by many factors like availability of infrastructures, land, water sources, fuel,
transportation, power etc.
Specific site selection criteria was considered the project as under.
The land for the expansion is already in the possession of project proponent as expansion to be
executed in the existing premises.
The existing project site is well connected by road to State Highway No. 41 (Beside the Road ).
Majority of the raw materials are available from the nearby areas.
Easy availability of manpower for the expansion project.
In addition to the above, the following factors within the study area (10 km) have also been
considered:
There is no National Park or Wild Life Sanctuary.
There are no metropolitan cities.
There are no ecologically sensitive areas.
Figure 2.2 - Google Earth Image (Short View)
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 14 2018_ECSS_EIAI1_1800028
At Present, the proposed expansion is being planned & hence it is very easy to do the expansion in
the existing industrial premises as the existing unit has a well developed infrastructure, available
resources local man power availability and set working systems.
Figure 2.3 - Google Earth Image (Long View)
2.3.3 Salient Features Study Area
The salient features of the project site are mentioned in below table:
Table 2.1 - Salient Features of the Project Site
S. No.
Particulars Details
1. Approx. Geographical Co-ordinates of the project site
Corner Latitude Longitude
A 30°25'11.10"N 74°31'19.16"E
B 30°25'24.87"N 74°31'18.11"E
C 30°25'24.74"N 74°31'15.27"E
D 30°25'22.86"N 74°31'15.13"E
E 30°25'22.77"N 74°31'10.96"E
F 30°25'20.93"N 74°31'10.90"E
G 30°25'20.77"N 74°31'02.53"E
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 15 2018_ECSS_EIAI1_1800028
H 30°25'18.92"N 74°31'02.29"E
I 30°25'18.87"N 74°31'03.04"E
J 30°25'16.47"N 74°31'02.77"E
K 30°25'16.49"N 74°30'54.78"E
L 30°25'11.17"N 74°30'57.81"E
M 30°25'10.63"N 74°31'00.77"E
N 30°25'06.74"N 74°31'00.93"E
O 30°25'05.45"N 74°31'06.18"E
P 30°25'08.26"N 74°31'06.45"E
Q 30°25'08.37"N 74°31'10.98"E
R 30°25'09.26"N 74°31'11.00"E
S 30°25'09.20"N 74°31'12.71"E
T 30°25'08.26"N 74°31'12.58"E
U 30°25'08.06"N 74°31'16.91"E
V 30°25'07.10"N 74°31'16.94"E
W 30°25'07.20"N 74°31'19.67"E
X 30°25'09.58"N 74°31'19.47"E
Y 30°25'09.54"N 74°31'17.65"E
Z 30°25'10.88"N 74°31'17.82"E
2. Elevation above mean sea level 197 m
3. Topography of the Plant Site Flat Terrain
4. Nearest Village Rupana – 1.20 km. (S)
5. Nearest City Sri Muktsar Sahib – 7.00 km. (N)
6. Nearest Town Sri Muktsar Sahib – 7.00 km. (N)
7. Nearest Highway State Highway NH 16 – at 0.00 km. (E)
8. Nearest Railway station Sri Muktsar Sahib Railway Station – 8 km. (N)
9. Nearest River Arniwala Canal – 2.5 km. (S)
10. Union Territory Chandigarh – 265 km. (NEE)
11. Ecologically sensitive areas included within 10 km radius from project site
No ecologically sensitive area such as National Park, Wild life sanctuary, reserved forest etc. present within 10 km radius
12. Sites of Historical/ Archaeological Importance
None within 10 km radial periphery
Note: All the above-mentioned distances are the aerial distances from the project site.
2.3.4 Climatic Conditions
Since Sri Muktsar Sahib District is located in North India of Punjab state, the climate of Sri Muktsar
Sahib District is characterized as a temperate climate.
Table 2.2 - Climate Type and Details
Climate Type Details
Climate Semi-Arid
Seismic Zone III (Moderate)
Maximum Temperature 47OC
Minimum Temperature 3OC
Average annual Temperature 37.4OC
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 16 2018_ECSS_EIAI1_1800028
Average annual Rainfall 425 mm
Wind Speed 3 – 14 km/h
Annual average Relative Humidity 57.0 %
Max Rain Period July to September
2.4 RESOURCE REQUIREMENT
2.4.1 Land Requirement
The SIL has an administration building, laboratory, Effluent treatment plant, dosing storage tanks and
sludge storage facility etc. The existing facilities will be used for proposed expansion. Total land area
acquired for the proposed expansion project is 9.53 Acres with 36.02 acres land of existing plant
(300TPD). Total area after expansion (600TPD) will be 45.55 Acres, (184341m2) which is already in
possession of SIL.
Land breakup:
LAND DETAILS SHEET FOR 600 TPD PAPER PRODUCTION
Particulars Existing 300
TPD Proposed 300
TPD Total 600 TPD
Survey Numbers Unit
26/1/1, 26/2/2, 13, 61/18, 23, 22, 19/1, 20, 21, 11/1, 10, 1, 5/1, 5/2, 6/1, 6/2, 15, 16, 25, 24, 17, 14, 7/1, 7/2, 4, 60/3, 8/1, 8/2, 60/13, 18, 19, 20, 16, 25/2, 2/2, 1, 2, 3, 10, 79/9, 8, 13/1, 13/2
R43//18,19/1,21,22,23. R61//26/1/1,1/1. R79//5/1,5/2,6,7. R78//1,2.
(Old) - 26/1/1, 26/2/2, 13, 61/18, 23, 22, 19/1, 20, 21, 11/1, 10, 1, 5/1, 5/2, 6/1, 6/2, 15, 16, 25, 24, 17, 14, 7/1, 7/2, 4, 60/3, 8/1, 8/2, 60/13, 18, 19, 20, 16, 25/2, 2/2, 1, 2, 3, 10, 79/9, 8, 13/1, 13/2
(New) R43//18,19/1,21,22,23. R61//26/1/1,1/1. R79//5/1,5/2,6,7. R78//1,2.
Land in Acres Acres 36.02 9.53 45.55
Land Square meter m2 145813 38527 184341
Green Belt proposed area m2 36453 24379 60832
Percentage of green belt % 25.0 63.3 33.0
Paper Machine & Converting proposed area
m2 5818 5680 11498
Pulp Mill m2 1250 812.5 2062.5
Stock Preparation m2 1800 1425 3225
Utility m2 2525 1522 4047
Layout Plan showing location of Manufacturing Unit, Storage Area, Wastewater Treatment Plant,
Water Storage Area, Emergency Vehicle Location, Assembly Point, Greenbelt Area, Internal Road,
Entry and Exit Gate, Parking etc. is depicted as Figure 2.4.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 17 2018_ECSS_EIAI1_1800028
Figure 2.4- Plant Layout
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 18 2018_ECSS_EIAI1_1800028
2.4.2 Man Power
There will be very good opportunity of employment generation directly and indirectly due to proposed
expansion project. Presently there are 1100 numbers of employees. There will be additional 500
numbers of employees, thus total 1600 numbers of employees after proposed expansion.
2.4.3 Energy requirement
a) Power
S. No.
Particulars Quantity, MW Source
Existing Proposed Total
1. Power – Electricity 30 14 44 Is being/will be obtained from In-
house CPP.
b) Fuel
S.
No. Fuel
Quantity, TPD Source
Existing Proposed Total
1. Rice Husk 500 400 900 Local Suppliers
2. Black Liquor 400 300 700 In-House
c) Steam Requirement
S. No.
Particulars Quantity, TPD Source
Existing Proposed Total
1. Steam
Requirement 3000 2880 5880
Will be obtained by existing as well as proposed Boiler.
2.4.4 Water Requirement
The total water requirement after expansion will increase from 16,500 to 24,000 KLD and it will be met
from Arniwala Canal available near the site. No ground water shall be drawn for the expansion; hence,
no NOC/permission from CGWA is required. Water supply permission for additional water from
Concerned Department is attached as Annexure V- A & B (Punjabi –A & English-B)
Table 2.3-Water Consumption Details
Particulars Existing
(KLD) Proposed
(KLD) Total (KLD)
Domestic 60 27 87
Gardening 70 32 102
Industrial
Pulp Mill 8,167 3,708 11,875
Paper Machine 5,400 2,452 7,852
DM Plant & Boiler 1,423 655 2078
Cooling (Make up Water) 1,380 626 2,006
Total Industrial 16,370 7,441 23,811
Grand Total(A+B+C) 16,500 7,500 24000
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 19 2018_ECSS_EIAI1_1800028
2.4.5 Capital Requirement
After expansion, total cost for the proposed manufacturing plant will be Rs. 500.0 Crores, which
include cost of land, building and civil work, plant and machinery purchase, utility/plant machineries,
environment management system and others. Capital cost, cost towards environmental
management plan etc. are mentioned in Table 2.4.
Table 2.4 Cost Break Up
Sr.
No. Description
Cost
(Rs. in Lacs)
1. Land for Plant & Machinery 626.95
2 Building 5175.05
3 Plant & Machinery 30875.00
4 Pre-operative Cost 1323.00
5. Erection Cost 1000.00
6. Up-gradation of Chemical Recovery Boiler 3000.00
7. Evaporator in Chemical Recovery Section 1500.00
8. Caustic-zing in Chemical Recovery Section 500.00
9. Power Boiler 75 TPH with ESP 2500.00
10. Up-gradation of Un-bleach and Bleach in Agro Pulp Street 500.00
11. Up-gradation of Un-bleach and Bleach in Wood Pulp Street 1500.00
12. Backwater Treatment (Micro Drum Filters & Disc Filters) 400.00
13. Up-gradation of ESP of Recovery Boiler 500.00
14. HRSCC, Aeration and MBBR System 500.00
15. Jet Aeration System 100.00
Total Cost 50000.00
2.5 RAW MATERIALS AND PRODUCT
2.5.1 Raw Material Requirement
Table 2.5-Requirements of Raw Materials
S.No Name of Raw Materials Existing
(TPD) Proposed
(TPD) Total (TPD)
1. Imp. Waste Paper 0.000 35.300 35.300
2 Imp. Wood Pulp 0.000 32.600 32.600
3 Paper Additives 7.579 4.421 12.000
4 Soap Stone 65.650 52.350 118.000
5 Wheat Straw, Sarkanda, Bagasse
533.000 105.000 638.000
6 Wood Chips 150.000 205.600 355.600
7 Caustic 130.450 52.350 182.800
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 20 2018_ECSS_EIAI1_1800028
S.No Name of Raw Materials Existing
(TPD) Proposed
(TPD) Total (TPD)
8 Liquid Oxygen 6.120 000 6.120
9 Chlorine Dioxide 3.400 4.600 8.000
10 Oxy Bleach Booster 000 4.400 4.40
11 Lime 95.200 32.200 127.400
Total 991.4 528.8 1520.3
The unit is situated at Village Rupana (Muktsar) and there is no problem in transportation of finished
goods and raw materials. Major raw materials i.e. wheat straw and sarkanda is available in the
region. Ludhiana is situated at only 150 km away from the site and all the urgent requirement of
stores, spares, consumables and chemicals are met out within 3-4 hours.
Transportation of raw material and finished products is a major activity of the mill. All raw materials
and finished products are transported by road. SIL has sufficient area and adopted adequate
measures to mitigate transportation of existing mills activities as well as for proposed project. The
mill has already provided separate areas for loading & unloading of raw materials. Proper parking
areas are also in place for all vehicles i.e. trucks etc. wherever required
2.5.2 Product Details
Satia Industries Ltd. is engaged in the production of Writing and Printing Paper mainly from virgin
pulp and after proposed expansion, the major raw materials shall be agricultural residues such as
wheat straw, Sarkanda, Wood/Veneer Chips, Imported Wood pulp and Waste Paper.
Product profile is given in Table below.
Table 2.6- Product Details
S. No
Product Capacity Remarks
Unit Existing Proposed Total
1. Writing and Printing Paper TPD 300
300
600
Expansion
2. Co-generation Captive
Power Plant MW 30
14
44
Table 2.7- Transportation of Product
S. No.
Product Physical
State Dispatch
Packing & Means of transportation
1. Writing & Printing Paper Paper Domestic &
Export Market
Roll &sheet form through
trucks/containers
Transportation of Raw Material
S.No. Raw Material Source Distance in km Mode of
Transport
1. Wheat Straw & Sarkanda, Cotton sticks
Nearby Areas 100 km radius Road
2. Rice husk Nearby Areas 100 km radius Road
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 21 2018_ECSS_EIAI1_1800028
3. Wood and Veneer chips Nearby Areas 100 km radius Road
4. Bamboo Nearby Areas 100 km radius Road
5. Imported waste paper & pulp
Through dealer Overseas Sea route/road
2.6 MANUFACTURING PROCESS
Paper Manufacturing Process
The paper manufacturing process is divided in the following stages:
1. Pulping Process
2. Stock Preparation
3. Paper Making
4. Converting & Finishing
The description of the process is given below.
2.6.1 Pulping Process
Raw Material Furnish: The raw material for agro pulping is wheat straw, Sarkanda and Bagasse for
Wood based pulp it is wood & veneer chips; Indian and imported waste paper and imported pulp.
Agro residues are processed through wet washing system which includes De-duster, turbo paddler
and aqua separator for the removal of non-cellulosic material like dirt/mud/sand and chlorides and is
squeezed by aqua separator followed by screw press for de-watering of the raw material. The
wastewater is sent to clarifier. About 75% of clarified effluent is re-circulated and other part is sent to
biogas plant.
Continuous Cooking: Cooking of raw material is carried out in continuous digester to get soft and
uniform pulp resulting in drastic reduction of bleaching chemicals and gain in pulp strength and
brightness. The purpose of the cooking is to chemically dissolve the lignin from raw material in order
to obtain bleachable grade pulp.
The main components of digester are–
Metering Screw
Pin Feeder
Equalizing Screw
Screw Feeder
Cold Blow Discharge
The squeezed raw material is fed to digester along with steam and caustic lye solution for cooking
under desired conditions with variable speed screw which slowly conveys the material to be cooked in
homogenized compact condition for uniform cooking.
After cooking, the pulp is cooled down by injecting cold black liquor into cold blow discharge. The
pulp is blown out from the cold blow discharge into the top dome of the blow tank, from there the pulp
drops into the blow tank by itself and is diluted to pump able consistency with black liquor.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 22 2018_ECSS_EIAI1_1800028
The fresh water/ machine back water is heated up to 65 – 70ºC with blow tank flash steam. This hot
water is used in wet washing plant and pulp washing.
Un-bleach Pulp Washing, Refining, Screening and Cleaning: The Pulp from blow tank is
processed through vibrating screen and then 3 stage counter–current washing followed by Twin-Roll
Presses (TRP) .TRP output consistency around 30.0 % It helps to reduce the black liquor carryover
from unbleached wash plant to bleach plant. This minimizes the bleaching chemical consumption and
helps to minimize the pollution load.
ECF Bleaching Process: SIL has already employed Oxygen delignification and Chlorine dioxide
bleaching to eliminate elemental chlorine bleaching to reduce pollution load as well as AOX level.
Current bleaching Sequence is ODL D0 (EOP) D1 to make brown pulp into white up to desired level
of brightness.
ODL – Oxygen Delignification
D0 – Chlorine Dioxide First Stage.
EOP – Alkali Extraction with Oxygen & Hydrogen Peroxide or by using Oxy Bleach Booster
ODL Oxygen Delignification: The unbleached pulp mixed with oxygen is sent to oxygen reactor.
The waste water of filtrate can be used in the brown stock washers for counter current washing, TDS
of ODL back water contains pollution load of organic lignin and coloring materials which will be utilized
by burning it in recovery boiler to produce steam and power. ODL stage also helps to reduce pollution
load in bleach effluent.
D1- Chlorine Dioxide Second Stage
After commissioning of Twin Roll Press unbleached pulp consistency has increased from 12% to 30%
and back water so generated from chlorine dioxide stage is taken in system for dilution. This reduces
the water consumption as well as bleaching chemicals. The ODL D0 EOP D1 System is considered
as environment friendly process as less organic waste will be discharged in the waste water from the
bleach plant.
To reduce water consumption & effluent generation, following steps have already been taken:-
Installed 2 no. of disc filters the output of these units will give 3 type of water i.e., cloudy, clarity
& super clarity
Cloudy backwater will be used for pulp dilution
Clarity backwater will be used for pulp washing as well as washing of washer mesh
Super clarity backwaterafter treatment in micro drum filters(2 no.) will be used to replace the
fresh water consumption at low pressure showers for wire, felt and rolls cleaning as well as
chemical preparation in stock preparation.
Wood Pulping: Wood chips are fed to the digester for cooking in the presence of Sodium Hydroxide
at required temperature to retain cellulosic content and separate lignin which gets dissolved in black
liquor. When cooking is complete; the contents of the digester are transferred to blow tank. The entire
contents of the blow tank are sent to pulp washers where the black liquor is separated from the pulp
.The pulp then proceeds through various stages of washing and bleaching as in agro pulp bleaching
process.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 23 2018_ECSS_EIAI1_1800028
Imported Wood Pulp Processing: Wood Pulp received in bales/reels is loaded in hydra pulper for
disintegration, from where it is taken to a separate chest after refining to get desired freeness. Refined
pulp is stored in a chest from where it is sent to stock preparation section.
Waste paper imported and from local market is taken in high consistency pulper for separation of ink
particles from the pulp and then passed through two stage deinking cells for removal of ink and
dispersed for reducing the size of any ink particle left in the system to a level where these are invisible
to the naked eyes. This pulp is too stored in the tower or the chests.
2.6.2 Stock Preparation
Different type of pulps are mixed in stock preparation in different proportion as per the quality of
paper required along with other additives like AKD, PAC, whitening agent, wet end additives and
fillers etc. From mixing chest, pulp is sent to machine chest for papermaking to the head box after
cleaning in centri-cleaners and pressure screen.
2.6.3Paper Making
This process involves sheet formation and dewatering the pulp of less than 1% consistency in
different stages starting at Wire part using gravitational force and vacuum to take out water from the
pulp and the drained water is used for pulp stock dilution. Excess backwater is taken to Saveall for
clarification and the clarified water is also used in the process and the pulp mill.
In Press part, water is removed further by passing the web between two rotating rolls along with press
felt. Here, when the web is pressed between rolls, the water squeezes out and felt absorbs it. This
process of pressing is done in three stages. The water absorbed by the felt is sucked through
vacuum.
There after the water removal is done by evaporation by passing paper web over steam heated dryers
in drying section. The temperature of dryers is maintained and monitored continuously for gradual
drying to final dryness and passed through Calendar rolls for achieving smoothness and then reeled
on jumbo rolls.
2.6.4Converting & Finishing
The converting process of paper comprises in two operations:
Sheeting
Rewinding
The paper rolls are cut into sheets at duplex/synchro cutter or into reels at Rewinder as per the order
and size given by the customer and then packed into bundles of 50-60 kg each and reels too are so
packed to avoid least transit damage.
The flow diagram of the Manufacturing Process is given below.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 24 2018_ECSS_EIAI1_1800028
AGRO & WOOD BASED RAW MATERIALS PROCESS
Raw Material dedusting & Washing
Cooking
Washing
Screening + Cleaning
Bleaching
STOCK PREPARATION
(Bleached Agro Pulp + Wood Pulp + Chemical Additives)
Paper Making
Converting Section (Roll & Sheet Form )
Finishing Section
Finished Go-down
Dispatch
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 25 2018_ECSS_EIAI1_1800028
2.6.5Description of Soda Recovery Plant
The company has already two chemical recovery boilers of 50TPH and 25 TPH (stand by) capacities
to treat black liquor generated during wheat straw pulping and wood chips pulping. In this expansion,
Company proposes to upgrade existing 25 TPH stand by boiler to 75 TPH and 50 TPH old recovery
boilers will remain as stand by after proposed expansion.
The brief description of existing CRP is given below. The plant is divided into three sections:
Multiple Effect Evaporator (To concentrate weak black liquor to Strong Black Liquor )
Chemical Recovery Boiler
Causticizing Plant.
i). Multiple Effect Evaporators (MEE): MEE is capable to convert weak black liquor of 10-12%
consistency to over 60-65% consistency in falling film multiple effect evaporators at a low pressure of
3-3.5 kg/cm2. Vapour generated in the process are condensed and used in pulp mill for pulp washing.
ii). Recovery Boiler: Concentrated black liquor is fired in boiler where the Organic component acts
as fuel and the inorganic part settles at the bottom of the boiler as smelt. The smelt is dissolved in
weak white liquor called green liquor. The high pressure steam so generated will be used to generate
power.
iii). Causticizing Plant: The Green liquor (Approx. 23-25 % as Sodium carbonate) generated from
Chemical recovery boiler will contain mostly Sodium Carbonate; is treated with Calcium Hydroxide
solution to produce Sodium Hydroxide and Calcium Carbonate. The Calcium Carbonate comes as
waste that will be used for land filling and is also given to cement plants.
2.6.6 Description of Captive Power Plant
Paper manufacturing is a continuous process, requiring electrical power and steam as two major
inputs. Hence, a Cogeneration Power Plant/Captive Power Plant (CPP) is being/will be installed to
achieve both these inputs simultaneously. A CPP shall also be beneficial for uninterrupted power
supply, which shall also help in minimization of production loss and power transmission losses from
the grid.
The proposed captive Co-generation power plant will consist of two Nos. 75 TPH high pressure
Boiler, Turbo-Generator sets (Turbine Generator with auxiliary rotating equipment‟s), Pressure
reducing and de-superheating station, Rice Husk and Black Liquor handling and supply system,
Condenser along with condensate extraction pumps, piping & valves, Compressed Air system for
instrumentation and utilities, Ash handling system, pollution control equipment, chimney, Electrical
distribution system, Instrumentation and control system for Boiler and Turbine, Cooling Tower and
Cooling Tower pumps for lube oil cooler and other Auxiliaries and DM plant for boiler feed water.
The raw material for boiler shall be water, Rice Husk and Black Liquor. The boiler feed water shall be
of specified quality which is a treated raw water. The fuel shall be fired in presence of combustion air
in the boiler, where hot flue gases are evolved and the liberated heat associated with the flue gases
shall be removed continuously. The steam shall be generated continuously due to feed water. Steam
from power boiler shall be fed to a single extraction cum condensing turbine. shall be used for various
operations of the plant such as De-inking of re-cycling papers, Paper machine for drying of paper,
Boiler & Turbine accessories like De-aerator, Ejectors, Turbine sealing glands etc. The balance steam
shall be condensed and the condensate shall be recycled to boiler feed tank. The Electrical
distribution system shall include H.T. & L.T. distribution panels, motors, starters, circuit breakers,
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 26 2018_ECSS_EIAI1_1800028
switch gears, plant protection devices like lightening arrestors, earthing and cables etc. During power
generation, the energy transformation in the entire cycle shall be from thermal energy to mechanical
energy and then to electrical energy. The flue gases from the economizer shall be taken to
electrostatic precipitator (ESP), thereby discharging the clean flue gases in to open atmosphere
through a Chimney. Ash collected from Boiler and bottom silo shall be subjected to conditioning,
which is proposed to be used in filling of the low lying areas, forestry plantation, for brick
manufacturing & give to Cement Plants.
The steam will be supplied to the steam turbine where the pressure energy will be converted to
mechanical energy developing shaft work. The steam turbine drives the Generator, where the Electric
power is generated at rated parameters/quality and it will be supplied through the electrical network to
the consuming units/grid. Existing available grid power will be used as a backup for power plant.
Figure 2.5 – Process flow diagram of CPP
Proposed Captive Power Co-generation Plant will consist of the following plant/equipment:
High pressure Boiler (75 TPH each) of latest technology.
Turbo – Generator (TG) Sets: Turbine Generator with auxiliaries.
Rice Husk and Black Liquor handling and supply system.
Condenser along with condensate extraction pumps, piping & valves.
Compressed Air System for instrumentation and utilities.
Ash handling system.
Pollution control equipment and Chimney.
Electrical and Electrical Distribution System.
Instrumentation and control system (DCS) for Boilers and Turbine.
Cooling tower and cooling water pumps for lube oil cooler and other Auxiliaries.
D.M. plant for boiler feed water.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 27 2018_ECSS_EIAI1_1800028
Table 2.8: Details of Cooling Tower
S.
No. Description 15 MW
1. Type- water cool Induced draft counter flow
2. Recirculation flow, m3/hr 4200
3. No of Cells 03
4. COC – Cycles of concentration 05
2.6.7 Material Balance for Proposed 600 TPD
2.7 AUXILIARY SYSTEM
2.7.1 Rice Husk Handling System
A standard Rice Husk handling system (Fig. 2.7) with screening and conveying system is already
installed for the existing CPP and same shall be implemented even after the proposed expansion.
There is a screen, conveyor & elevator.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 28 2018_ECSS_EIAI1_1800028
Figure 2.6: Rice Husk handling system
Following measures is already taken during rice husk transportation, handling and storage and shall
be continued after the proposed expansion.
Additional Greenbelt shall be provided in and around the premises area, around the rice husk
stack yard and along the roads to minimize the generation of fugitive dust.
For transportation, loading & unloading of goods, closed conveyor belt system is/shall be
provided.
Enclosures for transport vehicles/storage vessel, spraying of water on road & ground is/shall be
effectively implemented to control the dust problem. During the operation phase proper EMP
shall be in place for handling of rice husk.
The trucks used for transporting the goods are/will be covered by the tarpaulin and overloading
in trucks shall not be allowed, to prevent the dusting and spillage of goods from the truck.
Regular Air monitoring and inspection of the environmental management practices is/shall be
carried out and the necessary documents & records shall be maintained.
A fire hydrant system line is/shall be provided for immediate response to the unlikely
spontaneous combustion in the stored fuel.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 29 2018_ECSS_EIAI1_1800028
Figure 2.7 – Rice Husk Handling System
2.7.2 Fly Ash Handling System
A standard fly ash handling system is already installed for the existing CPP and same shall be
implemented after the proposed expansion. The fly ash collected in Economizer and APH shall be
designed to collect fly ash in dry form in the silo. From the silo, fly ash shall be dispatched to trucks.
The ash collected in the hoppers of ESP will be discharged in the silo by gravity. Level in the silo will
be controlled by level controllers provided on silo. Whenever the level exceeds, the pneumatic valve
opens and ash is being/shall be conveyed to ash hopper through pipes with the help of compressed
dry air.
At the discharge point of ash silo, ash conditioner is being/shall be put where water spay shall be done
for duct free loading of trucks/lorry under the ash silo. Finally ash is being/shall be taken by contractor
for brick making/filling of low lying area. APC for ash handling is attached as below.MOU for fly ash
disposal is attached as Annexure VI. No ash pond is/will be constructed to store the fly ash.
Undertaking for the same is attached as Annexure VII.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 30 2018_ECSS_EIAI1_1800028
Figure 2.8 - APC for Boiler Flue gases and scheme of Ash Handling
2.8 POLLUTION POTENTIAL& ITS CONTROL MEASURES
Based on the overall process study/manufacturing details etc. following are the details of pollution
potential v/s. mitigation measures proposed by the company in areas of wastewater management, air
pollution, hazardous waste handling and management respectively as per the details given below:
2.8.1 Air Environment
Satia Industries Limited has 01 boiler of 50 TPH capacity and 02 boilers of 75 TPH capacity each.
Moreover, SIL has two Recovery boilers of 25 and 50 TPH capacity. Whereas the Chemical recovery
Boiler is run through the Black Liquor, the other boilers run on rice husk as well as biogas generated
from UASB digester. The steam requirement for the proposed expansion plant shall be met from the
proposed 75 TPH boiler, which will run on rice husk and biogas generated from UASB digester. The
other 50 TPH recovery boiler will be kept as standby.
There is/will be No Process Gas Emission.
Table:2.9- Air Pollution Control Details
#
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
Remarks
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 31 2018_ECSS_EIAI1_1800028
EXISTING
1. Power Boiler
(50 TPH) 50
Rice Husk
270 TPD
PM SOx NOx
ESP Existing
2. Power Boiler
(75 TPH) 65
Rice Husk
400 TPD
ESP Existing
3. Power Boiler
(75 TPH) 65
Rice Husk
400 TPD
ESP Existing
4. Recovery
Boiler (25 TPH)
50 Black Liquor
200 TPD
ESP Existing
5. Recovery
Boiler (50 TPH)
65 Black Liquor
400 TPD
ESP Existing
PROPOSED
1. Power Boiler
(75 TPH) 65
Rice Husk
400 TPD
PM SOx NOx
ESP Proposed
2.
Recovery Boiler
(Existing 25 to 75
TPH)
65 Black Liquor
680 TPD
ESP Proposed
Note: There will be No Process Gas Emissions from proposed project.
2.8.2 Water Environment
Paper industry is one of the water intensive industry, so two types of effluents are generated in
the integrated pulp & paper plants, i.e., black liquor & mill effluent. Black liquor, which is highly
polluted, is treated in Chemical Recovery plant to produce value added product - Sodium hydroxide.
Balance mill effluent is treated in conventional effluent treatment plant to achieve the prescribed
norms of final discharge.
Table 2.10 - Wastewater Generation Details
Category Existing
KLD Proposed
KLD Total KLD
(A) Domestic 60 27 87
(B) Industrial
Wet Washing System 4800 2127 6927
Pulp Mill 8804 4190 12994
Paper Machine 00 00 00
DM Plant/Boiler 311 220 531
Cooling Tower 660 300 960
Total Industrial 14575 6837 21412
Total 14635 6864 21499
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 32 2018_ECSS_EIAI1_1800028
Figure 2.9 - Water Balance Diagram for Existing Paper Manufacturing Process
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 33 2018_ECSS_EIAI1_1800028
Figure 2.10 - Water Balance Diagram for proposed Paper Manufacturing Process
2.8.3 Solid/Hazardous Waste
The entire quantity of hazardous waste will be handled and disposed as per Hazardous Waste
(Management, Handling and Trans Boundary Movement) Rules - 2016. The source of hazardous
waste generation from plant is/will be ETP Sludge (Category 32.3) from wastewater treatment and
is/will be sent to cardboard manufacturers.
Power Plant ash will also be the main solid waste which is/will be collected in silo and from silo, fly ash
is/will be disposed for brick manufacturing and land filling in an eco-friendly manner.
Lime sludge will be sent to cement plant for their use in cement manufacturing and agreement in this
regard has been signed and attached as Annexure VIII.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 34 2018_ECSS_EIAI1_1800028
Table 2.11–Solid and Hazardous Waste Details
2.8.4 Noise Environment
The noise levels will be primarily generated due to industrial activities like mechanical movement and
material handling in unit. Noise may generate from motors, vehicular movement, generators, etc.
General noise levels within plant will be expected to remain below 75 dB (A). In order to mitigate the
noise levels during the operational phase, a green belt will be developed around the periphery of the
plant. However, at places where noise levels may exceed the permissible limit, acoustic enclosure will
be provided.
2.9 OCCUPATIONAL HEALTH AND SAFETY
The project proponent is committed towards the health and safety of workers. All the necessary
measure is being/will be planned for occupational health of the employees. Routine medical
examination of each person will be carried out as a systematic program on a regular basis. Medical
surveillance for the workers working in risk zone will be carried out regularly and annual report of the
health status of workers for the same will be maintained which is attached as Annexure IX. Safe
Operating Procedures (SOP) for different works/activities are/will be in place.
S.
No. Type Source
Quantity, TPD Disposal
Existing Proposed Total
Hazardous Waste
1. ETP Sludge
(Category:32.3) ETP 10.00 7.00 17.00
Disposedto local cardboard
manufacturers.
2. Lime Sludge
Causticizing 173.00 54.35 227.35
Calcination in Cement
Plants
Solid Waste
1. Fly Ash Boiler
House 63.75 51.25 115.00
For brick manufacturing &
filling of the low lying areas
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 35 2018_ECSS_EIAI1_1800028
2.10 ASPECT - IMPACT ANALYSIS
Table 2.12 - Aspect Impact Analysis
Activity Environmental
Attribute Cause
Impact Characteristics
Nature Duration Reversibility Significance
Transportation Activity
Manufacturing
Process
Operation of CPP
Air Quality Exhaust
Emissions Negative MidTerm Reversible
High, basic activity of the project
Noise Levels Noise
Generation Negative MidTerm Reversible
Low, due to noise protection measures
Risk and Hazards
Injury to man, cuts, trips, falls, etc.
Negative Short Term Irreversible Medium due to loss
of property and injury to manpower
Water Quality Wastewater
disposal Negative MidTerm Irreversible
Minor, due to treatment of effluent
before disposal
Sewage / Industrial
Wastewater Generation
Water Quality Wastewater
disposal Negative Short Term Reversible
Minor, due to treatment of
wastewater before disposal
Storage and Handling of Materials
Noise Levels Noise
Generation Negative Short Term Reversible
Low, due to noise protection measures
Work Zone Air Quality
Dust Generation
Negative MidTerm Reversible Low, due to
confined area
Risk and Hazards
Accidents Negative Short Term Irreversible Low, due to injury to
manpower
Solid Waste Disposal
Land and Soil Generation of Solid Waste
Negative MidTerm Reversible Low, proper
collection and disposal
Green Belt Development
Ecology Planting of
Trees Positive Long Term Reversible
High, Positive Impact
Air Quality Dust barrier Positive MidTerm Reversible Low, Positive Impact
Noise Noise barrier Positive Short Term Reversible Low, Positive Impact
LU/LC Conservation
of Land Positive Long Term Reversible
Medium, Positive Impact
Soil Increase in soil fertility
Positive Long Term Irreversible Medium, Positive
Impact
Water Water
consumption Negative MidTerm Irreversible
Low, due to water circulation
Employment Generation
Socio Economic Status
Direct and Indirect
employment Positive Long Term Irreversible
High, the project will Generate
Employment
2.11 PROJECT IMPLEMENTATION SCHEDULE
The project will take approximately 18 months after all the statutory clearances from SPCB for site
clearance and power plant clearance are received. The various activity-wise and time-wise charts are
given below for the project implementation.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 36 2018_ECSS_EIAI1_1800028
Table 2.13 - Project Implementation Schedule
S. No.
Description Period Period in Months
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1. Notice to Proceed
Zero Date
2. Basic Engineering and
Approvals 2
3. Detailed Engineering
6
4. Civil/Construction Work
10
5. Equipment Supply to Site
8
6. Pre Commissioning
3
7. Commissioning 1
8. Performance Test
1
2.12SUMMARY
The proposed project envisages enhancement of existing paper manufacturing by Satia Industries
Ltd. (SIL) located at Muktsar –Malout Road, PO: Village Rupana, Dist: Sri Muktsar Sahib, Punjab –
152032. Production capacity will be increased from 300TPD to 600TPD. The expansion of falls
under Category 5 (i) - “A” i.e. Paper Manufacturing from Wastepaper and the proposed project will
also install an additional 14.00MW CPP. The project site has an area of 45.55 Acres.Expansion will
be done in existing premises. Total cost for the proposed project will be Rs.500.0 crores.There will
be additional 500 numbers of employees, thus total 1600 numbers of employees after proposed
expansion. After proposed expansion, total water requirement for domestic and industrial purposes
with cited requirement of 87 KLD and 23,811KLD respectively.And PM, SOx and NOx will be
generated from existing and proposed Boiler. Hazardous Wastes like ETP Sludge, Lime Sludge and
Solid waste like Fly Ash generated from the project will be handled and managed as per Hazardous
Wastes Rules, 2016.
----------------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 37 2018_ECSS_EIAI1_1800028
CHAPTER-3
DESCRIPTION OF THE ENVIRONMENT
3.0 INTRODUCTION
The baseline environmental quality is assessed through field studies within the probable impact zone
for various components of the environment viz. Air, Noise, Water, Soil, Ecology & Bio diversity and
Socio-economy. The baseline environmental study has been conducted for the study region within 10
km radius. An exhaustive attempt has been made in the current chapter to disclose all possible
baseline status of environmental quality in the study area, which further serves as the basis for
identification, prediction and evaluation of impacts. Villages covered within study region are shown in
the Figure 3.1.
Figure 3.1 Study Area Map
3.1 BASELINE STUDY AREA AND PERIOD
The baseline environmental study has been conducted for the study region within 10 km radius of the
project site for the period 1stDec 2018 to 28th Feb 2019. An exhaustive attempt has been made in the
current chapter to disclose all possible base line status of environmental quality in the vicinity of the
project, which further serves as the basis for identification, prediction and evaluation of impacts. Study
area map covering all the villages are shown in the Figure 3.1.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 38 2018_ECSS_EIAI1_1800028
3.2 METHODOLOGY
The baseline environmental study was carried out for the various environmental components viz, Air,
Water, Soil, Ecology and Biodiversity, Socio Economy and Noise. A desktop study was carried out to
select the sampling locations and site visit was done by our field area experts. After the site visit,
locations were finalized. During the submission of field area expert report and discussion looking to
the extent of impact, 5 km radius was considered as core zone and rest 5 km radius was considered
as buffer zone. All the locations have been selected within 10 km radius from the project site as per
the requirement of TOR and environmental samples were collected from the selected locations of the
study area. Before starting the survey activity for ecology and bio diversity, secondary data were used
as reference during the desktop survey for listing the species of study zone and planning the survey.
In case of socio economy, secondary data have also been used for deciding the parameters to be
surveyed during socio economic data collection. As a secondary source of data, for Ecology and
Biodiversity survey various publications by the government of India and literature available on internet
site were used. Some photograph showing the monitoring and survey activities are presented in
Figure 3.2.
3.2.1 Frequency of Sampling
Details of frequency of environmental sampling considered for the study are illustrated in Table 3.1.
Table 3.1 Frequency of Environmental Monitoring
Attributes
Sampling
Locations Parameters Frequency
A. Air Environment
Micro-meteorological Data
Nr. Project Site Temperature, Relative Humidity, Precipitation Wind direction, Wind Speed.
Hourly data for the period 1stDec 2018 to 28th Feb 2019.
Ambient Air Quality 8 numbers of locations in the study area of 10 km radius.
PM2.5, PM10, SO2, NOx and CO
24 hour basis except CO, twice a week during study period
B. Noise 8 numbers of locations in the study area of 10 km radius.
Noise Levels in dB (A). Once in Study Period.
C. Water
Ground Water Samples from 8 numbers of locations within 10 km radius from the project site.
Physical, Chemical, Microbiological and Heavy Metal.
Once in Study Period.
Surface Water Samples from 3 numbers of locations within 10 km radius from the project site.
Physical, Chemical, Microbiological and Heavy Metal.
Once in Study Period.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 39 2018_ECSS_EIAI1_1800028
D. Soil Quality Samples from 4 numbers of locations within 10 km radius from the project site.
Physical, Chemical Characteristics, Soil Texture.
Once in Study Period.
3.2.2 Method of Environmental Sampling and Analysis
The methods adopted for environmental sampling and analysis are illustrated in following Table 3.2
Table 3.2 Method of Environmental Sampling and Analysis
Attributes
Methods
Sampling/Preservation Analysis/data analysis
A. Air Environment
Micro-meteorological
Data
Data collected on hourly basis using
wind monitor as per CPCB Guideline &
IS 8829. NA
Ambient air quality As per IS: 5182, CPCB & AWMA. As per IS:5182,CPCB & AWMA
B. Noise Instrument : Sound level meter Survey carried out as per CPCB
guideline.
C. Water
Ground Water and
Surface Water
Standard Methods for Examination of
Water and Wastewater, 23rd edition,
APHA 2017.
IS 3025 & Standard Methods for
Examination of Water and
Wastewater, 23rd edition, APHA 2017.
D. Soil Quality
IS 2720, Soil Testing in India
(Department of Agriculture &
Cooperation).
IS 2720, Laboratory developed
Method as per NABL requirement and
Book - Soil Testing in India
(Department of Agriculture &
Cooperation).
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 40 2018_ECSS_EIAI1_1800028
Barkandi Village – Ambient AirBhangchari Village – Ambient air
Goniana Village-Ground Water Muktsar Village-Ground Water
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 41 2018_ECSS_EIAI1_1800028
Rupana Village-Surface Water Sotha Village-Surface Water
Barkandi Village – Soil Project Site – Soil
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 42 2018_ECSS_EIAI1_1800028
SE Survey Project Site –Noise
Figure 3.2 Photograph showing the sampling activity
3.3 MICROMETEOROLOGY
The study of micro meteorological data helps to understand the variations in the ambient air quality
status in that region. The prevailing micrometeorological condition at project site plays a crucial role in
transport and dispersion of air pollutants. The persistence of the predominant wind direction and wind
speed at the project site decide the direction and extent of the air pollution impact zone. The principal
variables which affect the micrometeorology are horizontal transport and dispersion, convective
transport and vertical mixing and topography of the area towards local influences.
Micrometeorological data were collected by using the wind monitor as per CPCB guideline which was
installed near project site. All the micrometeorological data were collected on hourly basis.
Meteorological conditions of the study area are presented in Table 3.3.
Table 3.3 Meteorological Condition of Study Area
Month Temperature (oC) Relative Humidity (%)
Wind Speed
(km/hr)
Min. Max. Min. Max. Min. Max.
Dec'18 3.4 26.2 23.0 97.0 0.1 12.3
Jan'19 4.1 22.1 21.0 96.0 0.1 19.0
Feb'19 5.8 23.1 33.0 98.0 0.1 21.0
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 43 2018_ECSS_EIAI1_1800028
3.3.1 Temperature
During the study period minimum temperature was recorded 3.4oC on 30th Dec 2018 and maximum temperature was recorded as 26.2oC on
02nd Dec 2018. Temperature data were collected on hourly basis during the study period. Variation of temperature is graphically presented in
Figure 3.3.
Figure 3.3 Graphical Presentation for the month wise Temperature Variation
3.3.2 Humidity
Humidity affects the nature and characteristics of pollutants in the atmosphere as it is the measure of amount of moisture in the atmosphere.
Humidity helps suspended particulate matter to coalesce and grow in size to settle under the gaseous pollutants by providing them aqueous
medium. During the study period minimum Humidity was recorded 21% on 15th Jan 2019 and maximum Humidity was recorded as 98% on 21st
Feb 2019. The variation in humidity is represented graphically in Figure 3.4.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Min. 12 12 11 11 10 10 10 8. 7. 8. 9. 9. 8. 7. 6. 6. 7. 6. 5. 5. 5. 7. 5. 4. 3. 4. 3. 3. 3. 3. 4. 5. 4. 5. 4. 6. 5. 5. 6. 6. 6. 8. 8. 6. 5. 5. 6. 5. 5. 6. 9. 9. 5. 5. 5. 4. 4. 5. 4. 4. 7. 9. 6. 5. 6. 7. 11 8. 8. 8. 7. 7. 8. 10 10 8. 8. 10 10 10 10 12 10 9. 9. 10 10 10 9. 10
Max. 25 26 23 23 23 21 23 23 21 19 21 17 19 21 22 21 22 21 23 20 22 21 17 19 20 18 18 17 18 19 19 17 18 19 19 15 17 17 19 21 22 19 17 19 19 20 17 19 20 21 20 17 18 16 16 18 17 18 17 19 16 15 16 20 21 21 22 19 16 17 18 20 21 20 23 17 17 21 20 20 20 20 21 20 21 23 22 20 20 19
0.0
5.0
10.0
15.0
20.0
25.0
30.0
Tem
per
atu
re (
oC
)
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 44 2018_ECSS_EIAI1_1800028
Figure 3.4 Graphical Presentation for the month wise Humidity Variation
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Min. 34 37 53 52 53 55 49 44 40 62 51 69 47 40 41 23 30 28 33 41 32 49 74 53 37 57 52 36 57 46 44 60 61 48 45 73 63 56 40 34 28 51 60 46 37 21 52 42 45 36 42 80 80 61 56 44 44 30 39 25 48 75 66 46 44 42 45 70 78 55 44 42 39 50 53 80 79 52 51 63 57 69 70 47 42 33 42 52 47 46
Max. 82 84 83 88 85 87 87 85 82 84 86 85 86 84 84 76 80 86 87 85 85 83 97 88 87 86 87 84 89 88 86 86 96 90 86 84 85 86 87 82 83 81 85 90 80 81 90 89 85 84 81 95 92 93 92 84 81 80 84 85 85 88 92 86 87 84 86 89 91 88 84 84 74 85 90 93 91 90 87 93 90 95 98 81 81 83 85 85 80 78
0
20
40
60
80
100
120
Hu
mid
ity
(%)
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 45 2018_ECSS_EIAI1_1800028
3.3.3 Wind Speed and Wind Direction
Hourly wind speed data were collected for the period 1st Dec 2018 to 28th Feb 2019 with the help of
wind monitor. The rate of dispersion, diffusion and transportation of pollutants in the atmosphere
mainly depend on wind speed and its direction. Wind direction and velocity data have been collected
during the study period. Dominant wind direction in the study period was from NW –SE during the
study period.Wind speed was observed from 0.1 to 12.3 km/hr in the month of Dec 2018, from 0.1 to
19.0 km/hr in the month of Jan 2019 and from 0.1 to 21.0 km/hr in the Month of Feb 2019. Month-wise
maximum and minimum wind speed data are tabulated in Table 3.3.
3.3.4 Wind Rose
Wind rose diagram is a graphical representation of the magnitude and direction of wind speed
considering all the directions. From the knowledge of wind rose one can easily predict the direction
and extent of spreading of the gaseous and particulate matter from the source. Wind rose diagram
has been prepared by using hourly wind velocity and dominant wind direction data and is presented in
Figure 3.5
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 46 2018_ECSS_EIAI1_1800028
Figure 3.5 Wind Rose Diagram
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 47 2018_ECSS_EIAI1_1800028
3.3.5 Wind & Cyclone Vulnerability
The India Meteorological Department (IMD) is the nodal government agency that provides weather
services related to cyclones in India. However, IMD has not identified cyclone prone districts following
any specific definition though the districts for which cyclone warnings are issued have been identified.
On the other hand, for the purpose of better cyclone disaster management in the country, it is
necessary to define cyclone proneness and identify cyclone prone coastal districts. It is also
necessary to decide degree of hazard proneness of a district by considering cyclone parameters so
that mitigation measures can be prioritized.Wind and cyclone vulnerability is shown in Figure 3.5(A).
Figure 3.5(A) Wind & Cyclone Vulnerability Map
3.3.6 Interpretation of Micrometeorological Data
Wind rose diagram indicate that dominant wind direction was NW-SE during the study period and
wind speed range was 0 to 21.0 km/hr. Minimum detection for wind speed was 0.1km/hr therefore
wind speed can be considered that wind speed was in the range of 0.1 to 21 km/hr. Based on the
wind direction and wind speed it is interpreted that maximum dispersion of air pollutant will be in SE
direction during the period of Dec to Feb.
3.4 AIR ENVIRONMENT
Air is the Earth‟s atmosphere having the gases in which living organisms live and breathe but air is
being deteriorated day by day due to the anthropogenic and natural sources. In present scenario
Industrialization, Energy production and the burning of fossil fuels has polluted the air environment.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 48 2018_ECSS_EIAI1_1800028
Ambient air quality monitoring was carried out for the assessment of the existing status of background
air quality in the study area. This will be useful for assessing the conformity of the ambient air quality
to the standards even after commencement of the proposed project.
3.4.1 Selection of Sampling Locations
Following points were considered during the selection of Ambient Air Quality Monitoring locations.
Topography/terrain of the study area,
Regional synoptic scale climatologically norm‟s,
Densely populated areas within the region,
Location of surrounding Industries,
Representation of regional background,
Facility for Ambient Air Monitoring,
Representation of valid cross – sectional distribution in downwind direction,
Avoidance of proximity of roads, construction activity or any other perturbing activity which
may be temporary in nature, which may lead to some erroneous conclusions.
Availability of manpower, electricity, approach, sturdy structure and protection of samplers.
Dominant Wind Direction.
To establish the baseline status around the project site of the study region, monitoring was conducted
for 8 numbers of locations during 1stDec 2018 to 28th Feb 2019. At the time of location selection
previous micrometeorological data was referred and general wind pattern in the study region was
considered for the selection of minimum one location in the downwind direction and one location in
upwind direction. However, ambient air monitoring locations were selected in all the directions looking
towards the possibility of change in wind pattern during the study period. Ambient Air Quality
monitoring locations are presented in Figure 3.6 and Table3.4.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 49 2018_ECSS_EIAI1_1800028
Figure 3.6 Map showing the Study Region location of Ambient Air
Table 3.4 Ambient Air Quality Monitoring Locations in the Study Region
Code Location Distance/Direction Latitude and Longitude
Selection Criteria
A1 Project site -- 30°25'16.17"N 74°31'17.96"E
--
A2 Rupana 2.02 km S 30°24'10.72"N 74°31'23.99"E
Crosswind
A3 Sotha 5.16 km SE 30°22'56.41"N 74°33'4.92"E
Downwind
A4 Chak Giljiwala 8.81 km SSE 30°21'9.01"N 74°34'4.32"E
Downwind
A5 Barkandi 2.89 km E 30°25'40.09"N 74°33'2.56"E
Crosswind
A6 Goniana 3.41 km NNW 30°26'42.22"N 74°29'57.43"E
Upwind
A7 Muktsar 4.60 km NNE 30°27'41.49"N 74°31'58.41"E
Crosswind
A8 Bhangchiri 6.45 km SW 30°23'8.62"N 74°28'6.10"E
Crosswind
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 50 2018_ECSS_EIAI1_1800028
3.4.2 Frequency and Parameters for Sampling
Sampling team was appointed with one FAE and Technical Assistant to carry out Ambient Air Quality
Monitoring for 8 numbers of locations within 10 km radius from the project site. Sampling and analysis
was carried out as per CPCB, IS 5182 & EPA and instrument operation manual for the parameters
PM2.5, PM10, SO2, NOx and CO. After the completion of sampling, samples were brought to the
laboratory in Ice box and filter box for analysis. Frequency of sampling was twice a week during study
period.
3.4.3 Methodology for Sampling and Analysis
Samples were collected by using the PM10 and PM2.5 micron dust samplers at suitable height from
obstruction free area as per the availability of the facility. Sampling and Analysis was carried out as
per CPCB Guideline, instrument operational manual and National Environmental Engineering
Research Institute. Detail of reference method is presented in Table 3.5.
Table 3.5 Details of Analysis Method
Sr. No. Parameters Test Method
i. Particular matter (PM 2.5) SOP No. WI/5.4/02-B/03,Issue No.1
Date:01/01/2010, CPCB Guideline
ii. Particulate Matter (PM10) IS 5182 (Part 13):2006/Reaffirmed 2012
iii. Sulphur Dioxide (SO2) IS 5182 (Part 2):2001/Reaffirmed 2012
iv. Oxide of Nitrogen (NOx) IS 5182 (Part 6):2006
v. Carbon monoxide (CO) Methods of Air Sampling & Analysis AWMA,
APHA (CO Analyser)
3.4.4 Quality of Ambient Air
Minimum, maximum, average and 98th percentile values for the parameters PM2.5, PM10, SO2, NOx
and CO are tabulated in Table 3.6 to Table 3.8 to describe the quality of Ambient Air.
Table 3.6 Min, Max, 98th Percentile and Average Value of PM10 and PM2.5
Code
PM10 (µg/m3) PM2.5 (µg/m3)
Min. Percentile
98th Max. Avg. Min.
Percentile
98th Max. Avg.
A1 71.3 88.4 88.6 80.3 36.3 48.0 48.3 41.2
A2 68.2 85.1 85.7 77.0 35.6 45.0 45.4 39.6
A3 70.5 86.9 88.2 79.8 35.9 47.5 47.7 41.1
A4 69.5 86.1 86.4 78.0 35.7 46.1 46.8 40.5
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 51 2018_ECSS_EIAI1_1800028
A5 65.7 82.5 82.6 74.3 34.7 44.1 44.1 39.2
A6 62.5 76.0 76.2 70.9 32.8 42.8 43.5 38.2
A7 67.0 81.3 81.4 75.0 33.4 44.3 45.6 38.6
A8 64.2 77.5 78.1 70.7 34.3 41.0 41.1 36.9
NAAQ Standard
limit 100 60
Table 3.7 Min, Max, 98th Percentile and Average Value of SO2 and NOx
Code
SO2 (µg/m3) NOX (µg/m3)
Min. Percentile
98th Max. Avg. Min.
Percentile
98th Max. Avg.
A1 11.7 16.6 16.7 14.5 16.2 21.5 21.5 19.3
A2 10.9 15.5 15.8 13.0 15.4 20.1 20.1 17.6
A3 11.2 15.8 16.1 13.5 15.8 20.4 20.5 18.3
A4 10.2 15.2 15.3 13.1 15.6 20.4 20.4 18.0
A5 10.3 15.2 15.5 12.7 15.2 19.5 19.5 17.4
A6 9.6 14.6 14.7 12.5 14.2 18.8 18.8 17.0
A7 11.2 15.1 15.1 12.9 15.4 19.3 19.3 17.4
A8 10.5 15.3 15.7 13.2 14.8 19.6 19.8 17.8
NAAQ Standard
limit 80 80
Table 3.8 Min, Max, 98th Percentile and Average Value of CO
Code CO(µg/m3)
Min. Percentile 98th Max. Avg.
A1 558 649 650 609
A2 512 596 598 562
A3 525 622 624 578
A4 520 612 614 570
A5 475 571 578 508
A6 450 504 505 473
A7 488 553 556 514
A8 462 530 534 486
NAAQ Standard limit 2000
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 52 2018_ECSS_EIAI1_1800028
3.4.5 Summary of Ambient Air Quality
During the study PM2.5 was observed in the range of 32.8 – 48.3 µg/m3. Maximum
concentration of PM2.5 was found at Project Site.
PM10 was observed in the range of 62.5 – 88.6 µg/m3. Maximum concentration of PM10 was
found at Project Site.
SO2 concentration was observed in the range of 9.6 – 16.7 µg/m3, which is well within the
standard limit.
NOx concentration in was observed in the range of 14.2- 21.5 µg/m3, which is well within the
standard limit.
Monitoring and analysis was also carried out for CO. Result for the CO was found well within
the desired range.
3.4.6 Interpretation of Ambient Air Quality Data
All the results of ambient air quality parameters have been found well within the limit as per NAAQS.
Based on comparison study of results for tested parameters with NAAQS, it is interpreted that
ambient air quality of studied locations is good. This interpretation relates to the sampling carried out
and results found for particular locations and study period.
3.5 NOISE ENVIRONMENT
The objective of the baseline noise survey was to identify existing noise sources and to measure
background noise levels at the sensitive receptors within the study area. Peoples‟ perception of noise
varies depending on number of factors including their natural sensitivity and hearing ability, past
experience of sound, cultural factors and the time of day at which sound is experienced. Continuous
sound is perceived quite differently from intermittent sound at the same level. High or continuous
noise levels may cause permanent loss of hearing ranging from reduced perception at certain
frequencies to total deafness. At comparatively lower levels noise may have psychological effects
including disturbance of sleep, annoyance and irritation.
3.5.1 Sources of Noise Pollution
The sources of noise pollution in the study area are industrial noise, noise due to commercial
activities, noise generated by Community, Vehicular traffic etc.
3.5.2 Noise Level in the Study Area
Noise level monitoring was carried out with the help of sound level meter at 8 different locations fall
under residential, industrial and high noise generating source. Noise sampling locations are presented
in Figure 3.7 and Table 3.9. Analysis results are presented in Table3.10 and Table3.11.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 53 2018_ECSS_EIAI1_1800028
Figure 3.7 Map showing the study region location of Noise
Table 3.9 Noise Monitoring Locations in the Study Region
Code Location
Distance from
project
site/Direction
Latitude and
Longitude Selection Criteria
N1 Project Site (Nr.
Main Gate) -
30°25'16.72"N
74°31'17.77"E Industrial Area
N2 Project Site (Nr.
ETP area) -
30°25'14.54"N
74°31'0.64"E Industrial Area
N3 Project Site (Nr.
Gardening area) -
30°25'16.26"N
74°31'13.66"E Industrial Area
N4 Project Site (Nr.
ADM building) -
30°25'15.66"N
74°31'16.83"E Industrial Area
N5 Rupana 1.84 km S 30°24'16.73"N
74°31'23.05"E Residential Area
N6 Goniana 3.16 km NNW 30°26'36.96"N
74°30'5.11"E Residential Area
N7 Barkandi 3.01 km NE 30°25'43.81"N
74°33'6.02"E Residential Area
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 54 2018_ECSS_EIAI1_1800028
N8
1 meter away from
National Highway-
16
1.38 km N 30°26'1.06"N
74°31'16.06"E
Road (Noise generating
source)
Table 3.10 Noise Monitoring report during day time
Code Lmin dB
Ld dB(A) Lmax
dB
Limit dB(A) as per Noise Pollution (Regulation and Control) Rules,2000
N1 63.1 66.6 70.1 75
N2 64.5 67.7 71.4 75
N3 56.8 60.4 64.6 75
N4 58.1 62.6 66.5 75
N5 46.6 49.8 53.8 55
N6 47.1 50.1 54.1 55
N7 47.5 50.5 54.4 55
N8 72.1 77.4 82.6 -
Table 3.11 Noise Monitoring report during night time
Code Lmin dB
Ln dB(A)
Lmax
dB
Limit dB(A) as per Noise Pollution (Regulation and Control) Rules,2000
N1
59.4 62.8 66.2 70
N2
60.2 63.6 66.8 70
N3
52.1 55.4 58.6 70
N4
54.4 58.1 62.0 70
N5
40.4 42.8 44.6 45
N6
40.7 43.1 44.8 45
N7
39.8 42.5 44.3 45
N8
67.3 72.1 76.8 -
Note: Day time –6.00 AM to 10.00 PM, Night time – 10.00 PM to 6.00 AM
Noise standards have been designated for different types of land use i.e. residential, commercial,
industrial areas and silence zones, as per „The Noise Pollution (Regulation andControl) Rules, 2000,
Notified by Ministry of Environment and Forests, New Delhi, February 14, 2000. Different standards
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 55 2018_ECSS_EIAI1_1800028
have been stipulated forday (6 AM to 10 PM) and night (10PM to 6 AM). The noise level study shows
that the noise levels are meeting the acceptable norms. 3.5.3 Summary of Noise Data
Equivalent noise level varies from 60.4 to 67.7 dB (A) at Project Site and it is 4986 to 50.5 dB
(A) in residential area during day time.
Equivalent noise level varies from 55.4 to 63.6 dB (A) at Project Site and it is 42.5 to 43.1 dB
(A) in residential area during night time.
Noise level monitoring was carried out 1 meter away from National Highway- 16 and
equivalent noise level was recorded 77.4 dB (A) during day time and 72.1 dB (A) during night
time as per factory act 1948 noise level exposure limit for 8 hrs.is 90 dB (A).
3.5.4 Interpretation of Noise Data
Based on noise level data obtained during the survey for residential area and industrial area, it is
interpreted that noise levels are within the standard norms prescribed by MoEF & CC. Looking
towards the increase in noise generating sources it is suggested that there is need to apply noise
reducing devices at noise generating sources and generate public awareness.
3.6 LAND ENVIRONMENT
3.6.1 Land Use Pattern of the Study area
Studies on land use aspects of eco system play an important role to identify sensitive issues and to
take appropriate action for maintaining ecological homeostasis in the region. The main objective of
this section is to provide a baseline status of the area, so that temporal changes due to the proposed
project on the surroundings can be assessed in future.
Data Used: United States Geological Survey (USGS) Satellite Data: Land sat 8 cloud free data has
been used for Land use /Land cover analysis, Satellite Sensor–OLITIRS multi-spectral digital data
has been used for the preparation of land use/ land cover map of present study. Survey of India
reference map on 1:50,000 scales have been used for the preparation of base map and geometric
correction of satellite data. Ground trothing has been carried out to validate the interpretation
accuracy and reliability of remotely sensed data, by enabling verification of the interpreted details and
by supplementing with the information, which cannot be obtained directly on satellite imagery.
Methodology: The methodology used for the study consists of following components.
Methodology Adopted for Thematic Data Extraction from the Satellite Imageries
ERDAS image processing 10.0 software and ARC/GIS 10.0 software were used for the project.
ERDAS 10.0 image processing software was used for digital processing of the spatial data. Digital
image processing techniques were applied for the mapping of the land use land cover classes of the
provided area from the satellite data. Methodology used for land use classification and mapping is
presented in figure 3.8.Land use map is presented in figure 3.9. Land Use Statistic (10 km) is
presented in figure 3.10 and Table 3.12.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 56 2018_ECSS_EIAI1_1800028
Figure 3.8 Methodology Used for Land use Classification
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 57 2018_ECSS_EIAI1_1800028
Figure 3.9 Land Use
Table 3.12 Land use Pattern of Study Area
(Source: Land use mapping and primary survey of the area)
% Area sq
km Land Use
Land Cover
Area sq km
%
12.53 41.45 Settlement Settlement 41.45 12.53
3.31 10.94 Waterbody Waterbody 10.94 3.31
14.62 48.36 Range Land
Grass Land
28.41 8.59
Trees 14.52 4.39
Scrub Land
5.43 1.64
69.54 230.06 Agriculture
Crop Land 186.75 56.45
Fallow Land
43.31 13.09
100 330.82 Total 330.82 100
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 58 2018_ECSS_EIAI1_1800028
Figure 3.10 Land Use Statistics
3.6.2 Drainage Map
A drainage Map describes that an area of land where all surface water from rain or from some other
sources converges to a single point at a lower elevation, usually the exit of the basin, where the waters
join another body of water, such as a river, lake, reservoir, estuary, wetland, sea, or ocean. This map
tool is used to search for documents while viewing map features. Drainage Map of studied region is
presented in Figure 3.11.
12.53 3.31
8.59
4.39
1.64
56.45
13.09
Land use Statistic(10 KM)
Settlement
Waterbody
Grass Land
Trees
Scrub Land
Crop Land
Fallow Land
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 59 2018_ECSS_EIAI1_1800028
Figure 3.11 Drainage Map
3.7 GEOLOGY
The area forms a part of Satlej sub basin and main Indus basin alluvial plains. The topography of the
district is almost flat. It has an average elevation of 200m amsl, and slopes gently towards south and
south-west. The district is dotted with a number of isolated sand dunes of varying dimensions. The
sand dunes are of longitudinal type and do not show any preferred alignment. There is no river
flowing through the district. A number of artificial drains criss cross the district which carries the
excess run off during rains. The soils in the district have largely developed on alluvium the material
laid by rivers under the dominant influence of climate over space and time. It has two types of soil viz
the sierozem soils and desert soil.
Sierozem soils: The soils are light yellowish brown to pale brown in colour. Soils are calcareous and
usually have kankars at a depth of 0.75m to 1.25m. These are deficient in nitrogen phosphorous and
potash. Salinity and alkalinity are the serious problems particularly in the irrigated area. Wind erosion
is also the common feature in the tract. These soils are found in whole of Muktsar blocks, Kotbhai
block, in northern and eastern part of Malout blocks and eastern, central and southern part of Lambi
block.
Desert soil: These soils are light brown to yellowish brown and are deficient in nitrogen phosphorous
and potash. Wind erosion is a serious problem here. These soils are found in southern and western
part of Malout and Lambi blocks of the district. Gram, wheat, barley, bajra , jawar , cotton and mustard
are the principal crops in whole of the area.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 60 2018_ECSS_EIAI1_1800028
3.7.1 Earthquake Vulnerability
Vulnerability assessment helps in deciding the extent of the damage in particular area. Two main
approaches towards vulnerability assessment are predicted vulnerability and observed vulnerability
Vulnerability extent can be expressed with the help of Map. Showing the Earthquake Vulnerability is
depicted on Figure 3.12.
Figure 3.12 Earthquake Vulnerability Map
3.8 HYDROGEOLOGY
On the basis of two exploratory boreholes drilled by CGWB (1) Kumharwala, Lambi Block) during
1974-78) and Kotbhai Block HQ during 1999, the aquifer system belongs to huge aquifer system of
Indus plains. It cannot primarily of quaternary alluvial sediments. The areahas both unconfined and
confined aquifer. In general unconfined condition exists only upto 30m depth. The proportion of
permeable beds at deeper depth is generally low. At Kumharwala drilling down to the depth of 422m
was done. At the depth of 416m Nagaur clay stone has been encountered indicating that the alluvium
thickness is 416m and beyond this depth Nagaur clay stone occurs. Transmissivity 3.13X10-2 and
hydraulic conductivity was computed to be 34.78m/day. At Kotbhai, drilling was done upto 331m. At
both the places, well was constructed down to the depth of 54.0 and 53.0 m respectively because of
poor quality beyond this depth. At Kumharwala even the EC of constructed well is 4557 which is not fit
for drinking purposes. The area is underlain by unconsolidated formation comprising sand, silt and
clays etc. Extensive moderately thick unconfined to confined aquifer exists down to the drilled depth
of about 30m bgl . In the district the ground water is generally saline at all levels except at local
patches. There is wide lateral variation in the chemical quality depending upon the proximity of the
area to the surface irrigation channels.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 61 2018_ECSS_EIAI1_1800028
Ground Water Resources
Ground water resources estimation of the district was done in 2011 for each individual block. Perusal
of the estimates reveals that overall stage of development in the district is of 69%. The ground water
developments of three blocks are below 100% and have been categorized as safe for ground water
development. The ground water development of each block is as follows Kotbhai (Gidder Baha)-
101%, Lambi-41%, Malout-61%, Muktsar-78%. The block wise ground water resources potential in
the district has been assessed as per GEC 97 as on 31.3.2011.
Ground water Resources of Muktsar District, Punjab as on 31.03.2011
Block
Name
Net Annual
Ground
water
Availability
(Ham)
Existing
Gross
Ground
Water
Draft for
Irrigation
(Ham)
Existing
Gross
Ground
Water
Draft
for all
uses
(Ham)
Allocation
domestic
industrial
up to next
25 years
(Ham)
Net Ground
water
Availability
for future
irrigation
development
(Ham)
Stage of
Ground
water
Development
Category
of Block
GIDDER
BAHA 15893 15578 16043 464 -150 101 Safe
LAMBI 20458 8241 8455 213 12003 41 Safe
MALOUT 16433 9415 9992 578 6440 61 Safe
MUKTSAR 25130 18391 19596 1205 5535 78 Safe
Total 77924 51625 54085 2460 23829 69 Safe
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 62 2018_ECSS_EIAI1_1800028
Source:Central Ground Water Board, Ministry of Water Resources, River Development and
GangaRejuvenation, Government of India
Status of Ground water Development
In whole of the district, irrigation is based on both canal and tubewell supplies. The main stress is on
canal water because the whole of the district has an intense network of canal system. The two major
canals Sirhind feeder and Sirhind canal are the main source of water supply which are further divided
into various distributaries and minors. From the data available from Agriculture Deptt. , Punjab, about
96% of the district is being irrigated by canal water and only 4% of the area is irrigated by tube wells.
Tube wells are of shallow depth ranging from 25-55 m.bgl. There are 12184 electric operated tube
wells and 17136 are diesel operated tube wells in the district. From the water level monitoring data
available in CGWB, only two wells are showing decline i.e. Muktsar and Bhamial . The decline at
Muktsar (2002 to 2011) is 0.031 m/yr whereas at Bhaliana, decline is 0.21 m/year (2002 to 2011)
which is a nominal decline in 10 years (2002 to 2011) whereas all the other wells are showing rise in
water levels ranging from 0.008 m/yr (Labianwali) to 0.322 m/yr (Kuthian wali).
The water level of district ranges between 2-5 m whereas only a small portion i.e. east of Kotbahai is
more than 5m. Northern and western part of Muktsar block and southern and central part of Lambi
block fall in less than 2m category whereas rest of district falls in 2-5m category in post monsoon
2011. Whereas based on pre monsoon water level 2011, majority of the district comes under 2-5m
category except two patches near Lambi and NW of Kotbhai . All the blocks fall in the safe category
ranging from 41 to 101% of development.
AQUIFERS MANAGEMENT PLAN FOR MUKTSAR BLOCK:
Salient Information
Population (2011) Rural-1,88,732
Urban-
Total-1,88,732
Rainfall 2014 (Muktsar District) Average annual rainfall -391 mm
Average Annual Rainfall (Muktsar –II block) 377 mm
Agriculture and Irrigation Major Crops- Rice, Wheat
Net Area Sown- 731 sq.km
Total Irrigated Area- 1239.60 sq.km
Water Bodies & Canal Irrigation: Water bodies available in the villages for the storm water and
untreated waste water of villagers, that can be used for irrigation after treatment. The canal irrigation
is available in the Muktsar block.
Ground Water Resource Availability: Ground Water Resources available in the combined group of
aquifers. The resources are calculated as per Dynamic ground water resources (2013) and In-storage
ground water resources up-to fresh water. Block is categorized as safe as per Ground Water
Assessment 2013.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 63 2018_ECSS_EIAI1_1800028
Ground water Extraction: Information regarding the abstraction from different Aquifers is not
available, but there are drinking water supplies from tube wells tapping combined aquifer and
separate aquifer could not be assessed separately.
Source:Central Ground Water Board, Ministry of Water Resources, River Development and
GangaRejuvenation, Government of India
3.9 TRAFFIC STUDY
Proposed project connects to State Highway 16 and State Highway 41. Proposed project will attract to
commercial vehicles. As a result traffic load will also increase on highways. To assess the traffic load,
4 no. of surveyors were appointed to survey the State Highway 16 and State Highway 41.
Traffic data collected continuously for 24 hours by visual observation and counting of vehicles under
three categories, viz., heavy motor vehicles, light motor vehicles andtwo/three wheelers. As traffic
densities on the roads are high, two persons were deployed simultaneously at each station during
each shift- one person on each of the two directions for counting the traffic. At the end of each hour,
fresh counting and recording was undertaken. Total numbers of vehicles per hour under the three
categories were determined. Traffic study is conducted on State Highway 16 and State Highway 41
from 2nd and 3rd Jan 2019.
Table 3.13 Traffic Study Report
S.
No.
Vehicles
Distribution
No. of Vehicles/Day
Passeng
er Car
Unit
(PCU)
Total No. of
Vehicle in PCU
Total No. of
Vehicle
(PCU)/Hour
SH-16 SH-41 SH-16 SH-41 SH-16 SH-41
1. Cars 2580 2866 1.0 2580 2866 108 119
2. Buses 748 806 3.0 2244 2418 94 101
3. Trucks 2718 2912 3.0 8154 8736 340 364
4. Two wheelers 4585 5066 0.5 2293 2533 96 106
5. Three wheelers 1558 1704 0.75 1169 1278 49 53
Total 12189 13354 16440 17831 687 743
Table 3.14 Existing Traffic Scenario with respect to LOS
Road V (Volume in
PCU/hr)
C (Capacity in
PCU/hr)
Existing V/C
Ratio LOS
SH-16 687 1250 0.55 Good
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 64 2018_ECSS_EIAI1_1800028
V/C LOS Performance
0.0-0.2 A Excellent
0.2-0.4 B Very Good
0.4-0.6 C Good/Average/Fair
0.6-0.8 D Poor
0.8-1.0 E Very Poor
3.9.1 Interpretation of Traffic Study
LOS values have been calculated based on traffic data for SH-16 and SH-41 and it has been found
0.55 and 0.59 respectively. LOS value indicates that the performance of SH-16 and SH-41 are good.
3.10 SOIL QUALITY
4 numbers of samples were collected from different locations within 10 km radius to assess the base
line status of soil. Analysis was carried out for physico-chemical parameters as well as the
parameters to define the texture class. Soil samples were collected by using core cutter and brought
to the laboratory in polythene bags. Standard procedures have been followed for soil sampling and
analysis. Soil sampling locations are presented in Figure 3.13 and tabulated in Table 3.15. Results
are presented in Table 3.16.
SH-41 743 1250 0.59 Good
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 65 2018_ECSS_EIAI1_1800028
Figure 3.13 Map showing the study region location of Soil
Table 3.15 Details of Soil sampling location
Code Location Distance from the
project site/Direction
Latitude and
Longitude Selection Criteria
S1 Project Site - 30°25'21.15"N
74°31'13.97"E Non- Agricultural Land
S2 Muktsar 4.63 km NNE 30°27'41.84"N
74°32'1.43"E Non-Agricultural Land
S3 Barkandi 2.96 km E 30°25'29.18"N
74°33'7.97"E Agricultural Land
S4 Bhangchiri 6.26 km SW 30°23'1.51"N
74°28'22.33"E Agricultural Land
Table 3.16 Soil Sample Analysis Result
S. No Parameters Unit S1 S2 S3 S4
1 Water Holding Capacity % 45.48 43.68 49.14 52.22
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 66 2018_ECSS_EIAI1_1800028
2 Porosity % 48.26 47.49 52.78 53.90
3 Bulk Density 1.34 1.36 1.27 1.24
4 Particle Size Distribution
a. Sand % 52.34 55.12 48.52 45.58
b. Silt % 29.24 27.66 31.34 29.28
c. Clay % 18.42 17.22 20.14 25.14
5 Texture - Sandy Loam
Sandy Loam
Loam Loam
6 Cation Exchange Capacity meq/100 g 22.7 21.5 27.6 30.3
7 pH - 7.24 7.38 7.12 7.44
8 Electrical Conductivity dS/m 0.38 0.35 0.44 0.48
9 Sodium Absorption
Ratio(SAR) - 0.34 0.35 0.43 0.45
10 Exchangeable Sodium
Percentage(ESP) % 3.52 3.72 3.99 4.0
11 Exchangeable Calcium meq/100g 14.4 13.6 16.4 18.3
12 Exchangeable Magnesium meq/100g 7.2 6.8 9.6 10.4
13 Exchangeable Sodium meq/100g 0.8 0.8 1.1 1.2
14 Exchangeable Potassium meq/100g 0.3 0.3 0.5 0.4
15 Organic Carbon(OC) % 0.68 0.60 0.74 0.86
16 Total Nitrogen % 0.059 0.052 0.064 0.074
17 Nitrate N mg/100g 6.8 7.4 8.1 8.5
18 Total Phosphorus mg/100g 13.6 14.8 15.8 16.3
19 Total Iron mg/100gm 188.4 184.5 166.6 158.2
20 Total Zinc mg/100gm 6.2 5.7 5.4 5.1
21 Total Copper mg/100gm 3.8 3.3 2.8 2.4
22 Total Boron mg/100gm 2.6 2.5 2.2 1.8
23 Total Chromium mg/100gm 0.82 0.75 0.70 0.66
3.10.1 Summary of Soil Data
The soils of the study region are Sandy loam to loam based on different soil separates (sand,
silt and clay).
Water holding capacity varies from 43.68 to 52.22%.Soils of the study region may considered
having the good water holding capacity < 35.2.
The soil is categorized as deep black having > 1m depth and lower layers are having calcium
nodules.
The pH of the soil samples narrowly ranged from 7.12 to 7.44 during the study period. The soil
EC also varied from 0.35 to 0.48 dS/m and ESP ranged from 3.5 to 4.0. These parameters
indicate that soils are normal as EC is> 0.8 dS/m.
Exchangeable calcium and magnesium was found in the range 13.6 to 18.3 meq/100gm and
6.8 to 10.4 meq/100gm.
SAR value for soil was found in the range 0.34 to 0.45 with ESP in the range 3.52 to 4.0%.
Soils having the SAR <2.0 and ESP< 15% are considered non sodic i.e non saline.
Organic carbon was found in the range of 0.6 to 0.86 %. Soils having the organic carbon ( >
0.5 -0.75 % ) are consider with medium organic status.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 67 2018_ECSS_EIAI1_1800028
Considering only 2% available phosphorus based on total P, soils are classified as poor (>28
kg P2O5/ha) in available P. The results relating to total Fe, Cu, Cr, B and Zn do not show
alarming concentrations in different soil samples.
3.10.2 Interpretation of Soil Data
Based on soil analysis data it is concluded that soils are normal from salinity point of view as SAR is
<2.0 and ESP is < 15%. The soils are having medium in nitrogen, low in phosphorus and potassium.
The levels of total Fe, Cu, Cr, B and Zn are within the safe limits. However, for successful greenbelt
development liberal quantity of organic manure is recommended. Soils of studied locations are
suitable for plantation as well as for agricultural purpose.
3.11 WATER ENVIRONMENT
Physical, Chemical and Microbiological factors influencing water quality are so interrelated that a
change in any water quality parameter may trigger other changes in a complete network of
interrelated variables. Selected water quality parameters for surface and ground water resources
along with biological indicators within study region have been used for water environment and
assessing the impact on it by proposedproject. A study on water environment aspects of ecosystem
plays an important role in environmental assessment to identify water related sensitive issues.
3.11.1 Reconnaissance
As a significant part of predefined framework of the present study water samples were collected from
selected locations. The Reconnaissance survey was undertaken and monitoring locations were
finalized based on:
Presence, Location and uses of major water bodies in the region,
Type and Location of Industrial/residential areas, their intake and effluent disposal locations,
Likely areas that can represent baseline conditions.
3.11.2 Water Quality
With the start of water quality study, the water resources in the study area were divided into two
categories for getting ideal upshot of baseline status of water quality of the region. These two
categories as determined are:
Ground water resources (tube well, open well, springs etc.)
Surface water resources including ponds, river, canals.
3.11.3 Sampling and Analysis
All the water samples were collected and analyzed as per “Standard Methods for Examination of
Water & Wastewater”, APHA 23rd edition, 2017. Water Samples for the analysis of physico-chemical
parameters were collected in plastic carboy and parameter wise preserved onsite as per the
technique defined in the book of APHA, 23rd edition, 2017. Temperature, pH and DO were analyzed
onsite and samples were brought to the laboratory for the analysis of remaining parameters.
3.11.4 Ground Water
To assess the quality of ground water, samples were collected from 8 numbers of locations for the
analysis of physico-chemical and microbiological parameters. Ground water sampling locations are
presented in Table 3.17 and Figure 3.14. Analysis results are presented in Table 3.18.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 68 2018_ECSS_EIAI1_1800028
Figure 3.14 Map showing the study region with locations for Ground Water
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 69 2018_ECSS_EIAI1_1800028
Table 3.17 Details of Ground Water sampling locations
Code Location Distance from the project
site/Direction Latitude and Longitude Source
GW1 Project Site - 30°25'16.50"N
74°31'19.43"E
Hand Pump
GW2 Rupana 0.42 km S 30°25'2.63"N
74°31'19.70"E
Hand Pump
GW3 Sotha 5.10 km SE 30°22'58.47"N
74°33'4.25"E Tube Well
GW4 Chak Giljiwala 8.80 km SE 30°21'9.37"N
74°34'4.09"E Hand Pump
GW5 Barkandi 2.95 km E 30°25'29.92"N
74°33'7.33"E Bore well
GW6 Goniana 3.14 km NW 30°26'35.06"N
74°30'3.49"E Hand Pump
GW7 Muktsar 4.64 km NNE 30°27'42.30"N
74°32'1.03"E Hand Pump
GW8 Bhangchiri 6.64 km SW 30°23'12.82"N
74°27'53.94"E Hand Pump
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 70 2018_ECSS_EIAI1_1800028
Table 3.18 Ground water Analysis Results
S. No. Parameters Unit GW1 GW2 GW3 GW4 GW5 GW6 GW7
GW8
Drinking Water Specification IS 10500: 1992 (Reaffirmed 2012)
Desirable Limit
Permissible Limit
1. Temperature 0C 21.5 22.5 22.0 21.5 22.5 21.5 22.5 22.0 -- --
2. pH @ 250C pH Unit 7.20 7.90 7.64 7.94 7.50 7.04 7.56 7.27 6.5 – 8.5 No Relaxation
3. Colour Hazen <5 <5 <5 <5 <5 <5 <5 <5 5 15
4. Odour -- Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable --
5. TDS @ 1800C mg/L 1405 282 218 832 792 2254 916 438 500 2000
6. Conductivity µmho/cm 2248 418 319 1342 1266 3658 1460 662 -- --
7. Turbidity NTU 2.1 0.8 0.5 1.4 1.6 2.8 1.8 1.0 1 5
8. TSS mg/L <2 <2 <2 <2 <2 <2 <2 <2 -- --
9. Total Hardness as
CaCO3 mg/L
586 168 154 112 386 1200 240 268 200 600
10. Calcium mg/L 74 45 44 30 52 164 16 24 75 200
11. Total Alkalinity as
CaCO3 mg/L
330 156 122 126 346 580 450 200 200 600
12. Chloride mg/L 400 52 40 298 178 875 144 92 250 1000
13. Magnesium mg/L 97 13.5 11 9 62 192 49 50 30 100
14. Sulphate mg/L 298 18 18 122 114 192 124 70 200 400
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 71 2018_ECSS_EIAI1_1800028
15. Total Phosphorus
(PO4-P) mg/L
2.3 1.5 1.2 1.6 1.8 2.6 1.5 1.7 -- --
16. Sodium mg/L 280 34 20 260 150 360 210 60 -- --
17. Potassium mg/L 18 9 4 6 11 64 70 8 -- --
18. Fluoride mg/L 0.6 0.4 0.4 0.5 0.5 0.7 0.6 0.5 1.0 1.5
19. Phenolic Compound mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.001 0.002
20. Oil and Grease mg/L <1 <1 <1 <1 <1 <1 <1 <1 -- --
21. Dissolved Oxygen mg/L 5.1 5.4 5.4 5.2 5.1 5.2 5.2 5.3
-- --
22. Nitrate mg/L 0.6 0.5 0.5 0.6 0.6 0.7 0.6 0.5 45 No Relaxation
23. Total Nitrogen mg/L 1.3 1.1 1.0 1.2 1.2 1.5 1.3 1.1 - -
24. Iron mg/L 0.28 <0.1 <0.1 0.18 0.20 0.42 0.26 0.12
0.3 No Relaxation
25. Copper mg/L <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05 1.5
26. Boron mg/L 0.12 0.06 0.05 0.08 0.06 0.15 0.08 0.05 0.5 1.0
27. Chromium mg/L <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 0.05 No Relaxation
28. Zinc mg/L 0.17 <0.1 <0.1 0.15 0.12 0.20 0.14 <0.1 5 15
29. Total Coliform Present/Ab
sent Absent
Absent Absent Absent
Absent Absent Absent Absent Shall not be detectable in
any100 ml of sample
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 72 2018_ECSS_EIAI1_1800028
3.11.5 Summary of Ground Water Quality
The test results were compared with the Drinking Water Specification: IS: 10500, 1992 (Reaffirmed
2012) and it is summarized as under.
pH was observed in the range of 7.04 – 7.94, which meets with drinking water desirable norms.
Turbidity was found in the range of 0.5 – 2.8 NTU.
Total Dissolved Solid (TDS) were recorded in the range of 218 - 2254 mg/L with minimum at
Sotha village and maximum at Goniana village.
Conductivity varies from 319 to 3658 µmho/cm. The ratio of TDS to conductivity was observed in
the range of 0.6 to 0.65 which is within the desired range.
Total Hardness was in the range of 112 - 1200 mg/L with minimum at Chak Giljiwala village and
maximum at Goniana village.
Total Alkalinity was found in the range of 122 - 580 mg/L with minimum at Sotha village and
maximum at Goniana village.
Chloride was found in the range of 40 to 875 mg/L and Sulphate varies from 18 to 298 mg/L.
Iron was found in the range of <0.1-0.42 mg/L with minimum at Rupana and Sotha village and
maximum at Goniana village.
As microbiological parameters MPN analysis was also carried out and it was found Nil.
3.11.6 Interpretation of Ground Water Quality Data
Based on comparison study of test results with drinking water norms, it is interpreted that water
qualities of most of the studied locations meet with the drinking water standards as per IS 10500:
2012 except Goniana village. Ground water sample collected from project site, Rupana, Sotha, Chak
Gilijiwala, Barkandi, Muktsar and Bhangchiri can be used in drinking as well as in other domestic and
irrigation purpose. Ground water sample collected from Goniana village should not be used in drinking
as it contains TDS, Total Hardness, Chloride and Iron more than prescribed limit but it can be used in
other domestic purpose as well as in irrigation also. These interpretations are based on comparison
study with standard for tested parameters only as per IS 10500: 2012.
3.11.7Surface Water
To assess the quality of Surface water, samples were collected from 3 numbers of locations for the
analysis of physico-chemical and microbiological parameters. Frequency of sampling was once during
the study period. Sampling and analysis was carried out as per “Standard Methods for Examination of
Water and Wastewater 23rd edition, 2017. Surface water sampling locations are presented in the
Table 3.19 and Figure 3.15. Analysis results are presented in Table 3.20 & 3.21.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 73 2018_ECSS_EIAI1_1800028
Figure 3.15 Map showing the locations for Surface water
Table 3.19 Details of Surface Water Sampling Locations
Code Location
Distance from the
project
Site/Direction
Latitude and
Longitude Source
SW1 Rupana 0.48 km SSW 30°25'0.82"N 74°31'15.79"E
canal
SW2 Sotha 4.94 km SE 30°23'5.50"N
74°33'5.02"E Pond
SW3 Chak Giljiwala 8.64 km SE 30°21'17.48"N
74°34'8.23"E pond
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 74 2018_ECSS_EIAI1_1800028
Table 3.20 Surface water Analysis Results
S. No.
Parameters Unit SW1 SW2 SW3
Drinking Water Specification IS 10500: 1992/(Reaffirmed 2012)
Desirable Limit
Permissible Limit
1. Temperature 0C 20.5 21.0 20.5 - -
2. pH @ 250C pH Unit 7.75 7.62 7.23 6.5 – 8.5 No Relaxation
3. Colour Hazen 6 8 5 5 15 4. Odour - Unobjectionable Unobjectionable Unobjectionable Agreeable - 5. TDS @ 180
0C mg/L 168 214 212 500 2000
6. Conductivity µmho/cm 264 338 318 - - 7. TSS mg/L 8 14 12 - -
8. Total Hardness as
CaCO3 mg/L
100 118 116 200 600
9. Calcium mg/L 27 28 27 75 200
10. Total Alkalinity as
CaCO3 mg/L
88 100 92 200 600
11. Chloride mg/L 46 56 58 250 1000 12. Magnesium mg/L 8 11.6 12 30 100 13. Sulphate mg/L 1.2 9.6 13.5 200 400 14. Total Phosphorus mg/L 1.4 2.2 1.9 - - 15. Sodium mg/L 24 34 34 - - 16. Potassium mg/L 3 4 3 - - 17. Fluoride mg/L 0.5 0.8 0.7 1.0 1.5 18. Phenolic Comp. mg/L <0.1 <0.1 <0.1 0.001 0.002 19. Oil and Grease mg/L <1 <1 <1 - - 20. Dissolved Oxygen mg/L 5.1 4.9 5.0 - - 21. COD mg/L 10 16 12 - - 22. BOD(3 days at 27
0C) mg/L <4 6 4 - -
23. Nitrate mg/L 0.6 0.8 0.7 45 No Relaxation 24. Total Nitrogen mg/L 1.2 1.6 1.4 - - 25. Iron mg/L 0.26 0.32 0.36 0.3 No Relaxation
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 75 2018_ECSS_EIAI1_1800028
26. Copper mg/L <0.05 <0.05 <0.05 0.05 1.5 27. Boron mg/L 0.06 0.12 0.08 0.5 1.0 28. Chromium mg/L <0.03 <0.03 <0.03 0.05 No Relaxation 29. Zinc mg/L 0.12 0.16 0.15 5 15
Table 3.21 Bacteriological Analysis of surface Water
Code Total coliform Fecal coliform Escherichia coli Fecal Streptococci
Most Probable No (MPN): No/100 mL
SW1 16 12 <1.8 <1.8
SW2 20 18 <1.8 <1.8
SW3 18 16 <1.8 <1.8
Table 3.22 Standard limit as per IS 10500:2012 for Microbiological parameters
S.
No. Organisms Requirements
1. All water intended for drinking:
a) E. coli or thermo tolerant coliform bacteria
Shall not be detectable in 100 ml sample
2.
Treated water entering the distribution system:
a) E. coli or thermo tolerant coliform bacteria
Shall not be detectable in 100 ml sample
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 76 2018_ECSS_EIAI1_1800028
b) Total coliform bacteria Shall not be detectable in 100 ml sample
3.
Treated water in the distribution system:
a) E. coli or thermo tolerant coliform bacteria
b) Total coliform bacteria
Shall not be detectable in 100 ml sample
Shall not be detectable in 100 ml sample
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 77 2018_ECSS_EIAI1_1800028
1) Immediate investigative action shall be taken if either E.coli or total coliform bacteria are detected.
The minimum action in the case of total coliform bacteria is repeat sampling; if these bacteria are
detected in the repeat sample, the cause shall be determined by immediate further investigation.
2) Although, E. coli is the more precise indicator of fecal pollution, the count of thermo tolerant coli
form bacteria is an acceptable alternative. If necessary, proper confirmatory tests shall be carried out.
Total coliform bacteria are not acceptable indicators of the sanitary quality of rural water supplies,
particularly in tropical areas where many bacteria of no sanitary significance occur in almost all
untreated supplies.
3) It is recognized that, in the great majority of rural water supplies in developing countries, fecal
contamination is widespread. Under these conditions, the national surveillance agency should set
medium-term targets for progressive improvement of water supplies.
3.11.8 Summary of Surface Water Quality
The following description is based on the analysis of the samples:
During the analysis pH of the samples was found in the range of 7.23 – 7.75.
TDS analysis was also carried out for surface water sample and it was found in the range of 168-
214 mg/L.
TSS was found in the range of 8 – 14 mg/L.
Total Hardness ranges from 100 –118 mg/L with maximum in the water sample of Sotha village
and minimum in Rupana village.
DO is one of the important parameter to indicate towards the contamination of organic matter. DO
level decrease as soon as organic contamination increases. During analysis DO was found in the
range of 4.9-5.1 mg/L.
COD and BOD analysis was also carried out during the study period and results were found more
than the expected value for the Rivers. Various literatures show that BOD should be less than 4.0
mg/L for the better survival of aquatic life.
Total Nitrogen was found in the range of 1.2 – 1.6 mg/L.
Iron content was found in the range of 0.26- 0.36 mg/L and other heavy metals were found well
within the limit.
MPN test was also carried out for the surface water sample and it was found positive. E-coli and
Streptococci test was found negative. It indicates towards the faecal contamination in surface
water body.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 78 2018_ECSS_EIAI1_1800028
3.11.9 Interpretation of Surface Water Quality Data
River water qualities for the samples collected from different surface water bodies are contaminated
with organic matter and microbes. Total coliforms have been reported in all sample, it indicated
towards the faecal pollution in surface water bodies. Results of other tested parameters meet with the
drinking water norms. Based on comparison study with drinking water norms it is concluded that
these water sources can be used for irrigation purpose and it can also be used in drinking after
conventional treatment followed by disinfection.
3.12 ECOLOGY AND BIODIVERSITY
Mainly two types of Vegetation cover are on the earth surface. One is self-growing and another is
cultivated. Plants are renewable resource and useful to living organism in many ways. It is therefore
the role of man in manipulating and changing vegetation population. Due to lack of awareness
deforestation is occurring which in turn is responsible for imbalance of ecosystem. The main objective
of the ecological survey is aimed to find out baseline status of flora and fauna of the study region. An
ecological survey of the study area was conducted particularly with reference to listing of species and
assessment of the existing baseline ecological (terrestrial and marine ecosystem) conditions in the
study area.
3.12.1 Methodology Adopted for the Study of Flora and Fauna
The EB surveys have been conducted as per our QMS Quality Procedure for Ecology and
Biodiversity for conducting ecology and biodiversity study.
Study Area:314.317sq.km.
Core Zone: Projects site and 5 km radii w.r.t. project site.
Buffer Zone: 10 km radii w.r.t. project site.
Study Period: 1st Dec 2018 to 28th Feb 2019
List of Villages: Rupana, Sotha, Chak Giljiwala, Barkandi, Goniana, Muktsar, Bhangchiri
3.12.2 Floral Diversity of the Study Area
The objective of this floral inventory of the study area is to provide necessary information on floristic
structure in the study area for formulating effective management and conservation measures. The
climatic, edaphic and biotic variations with their complex interrelationship and composition of species,
which are adapted to these variations, have resulted in different vegetation cover, characteristic of
each region (Ohasi, 1975).
Trees: Total28species oftrees belong to 17 families are enumerated from the study area.
Table 3.23 Trees in the Study area
S. No. Family and Scientific Name Vernacular Name
1 Fabaceae
1/1 Albizzia lebbek Kala Siris
2/2 Butea monosperma Palas/Dhak
3/3 Cassia fistula Amaltas
4/4 Dalbergia sissoo Shisham
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 79 2018_ECSS_EIAI1_1800028
5/5 Delonix regia Gulmohar
6/6 Tamarindus indica Imli
7/7 Pongamia glabra Sukhchain
2 Moraceae
8/1 Artocarpus integrifolia Kathal
9/2 Ficus religiosa Pipal
10/3 Ficus bengalensis Bargad
11/4 Morus alba Shehtut
3 Mimosaceae
12/1 Albizia procera White Siris
4 Moringaceae
13/1 Moringa oleifera Suhanjna drum stick
5 Meliaceae
14/1 Azadirachta indica Neem
15/2 Melia azadarach Drek Barma (China Berry
16/3 Cedrela toona Tun
8 Bignoniaceae
17/1 Jacaranda mimosifolia Jakranda
9 Myrtaceae
18/1 Eucalyptus hybrid Safeda
19/2 Syzygium cuminii Jamun
10 Phyllanthaceae
20/1 Phyllanthus emblica Amla
11 Arecaceae
21/1 Phoenix sylvestris Khajur
12 Combretaceae
22/1 Terminalia arjuna Arjan
14 Annonaceae
23/1 Polyalthia longifolia Ashok
15 Anacardiaceae
24/1 Mangifera indica Mango/Aam
16 Caricaceae
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 80 2018_ECSS_EIAI1_1800028
Shrubs: Total10species of Shrubs belong to 8 families are enumerated from the study area.
Table 3.24 List of Shrubs in the study area
S.No. Family name & Scientific Name Vernacular Name
1 Fabaceae
1/1 Acacia Arabica Kikar
2/2 Bauhinia speciosa Kachnar
2 Rosaceae
3/1 Rosa indica Rose
3 Apocynaceae
4/1 Carissa carnadas Karonda
4 Rutaceae
5/1 Citrus limon Lemon
5 Myrtales
6/1 Callistemon lanceolatus Bottle brush
6 Salicaceae
7/1 Populus indica Poplar
7 Poaceae
8/1 Bambusa spp Bambu
8 Rhamnaceae
9/1 Zizyphus numularia Jharberi
10/2 Zizyphus mauritiana Ber
Herbs: Total4 species of Herbs belong to 3 families are enumerated from the study area
25/1 Carica papaya Papita
17 Apocynaceae
26/1 Narium odorum Kaner
27/2 Melia azedarach Bakrain
28/3 Alstonia scholaris Chitwan
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 81 2018_ECSS_EIAI1_1800028
Table 3.25 List of Herbs in the study area
S. No. Family name & Scientific Name Vernacular Name
1 Amaranthaceae
1/1 Pupalia lappacea Chirchita
2 Solanaceae
2/1 Datura metal Dhatura
3/2 Solanum nigrum Mokoy
3 Musaceae
4/1 Musca sapientum Banana/Kela
Climbers: Total 1species of Climbers belong to 1 families are enumerated from the study area.
Table 3.26 List of Climbers in the study area
S.No. Family Name & Scientific Name Vernacular Name
1 Nyctaginaceae
1/1 Bougainvillea spectabilis Baganvilas
Grass: Total 2species of Grass belong to 1 families are enumerated from the study area.
Table 3.27 List of Grass in the study area
S.No. Family Name & Scientific Name Vernacular Name
1 Poaceae
1/1 Cynodon dectylon Dub
2/2 Setaria glauca Sarkanda
Fauna:
There was no endangered species observed during faunal survey, list of fauna detail summarized in
Table 3.28 to 3.30.
Table 3.28 List of Mammals in the Study area
S. No. Scientific Name Common Name Schedule as per
WPA 1972
1. Boselaphus tragocamelus Blue bull Schedule III
2. Funambulus palmarum Squirrel Schedule IV
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 82 2018_ECSS_EIAI1_1800028
3. Herpestes edwardsi Common Mongoose Schedule II
4. Lapus nigricollis Rabbit Schedule IV
5. Macaca mulatta Rhesus Monkey Schedule II
6. Rattus rattus House rat Schedule V
7. Sus scrofa Wild Boar Schedule III
Table 3.29 List of Birds in the Study area
S. No. Scientific Name Common Name Schedule and
Status
1. Bubulcus ibis Cattle egret Cattle egret
2. Columba livia Blue rock pigeon Schedule IV
3. Corvus splendens House crow Schedule V
4. Passer domesticus House sparrow Schedule IV
5. Cuculus varius Hawk cockoo
6. Dinopium benghalense lesser golden-backed
woodpecker Schedule IV
7. Eudynamys scolopacea Koel Schedule IV
8. Coracias benghalensis Indian Roller Schedule IV
9. Francolinus francolinus Kala titar Schedule IV
10. Gallinula chloropus Water hen Schedule II
11. Gallicrex cinerea Wild cock Schedule IV
12. Nycticorax nycticorax Night Heron Schedule V
13. Orthotomus sutorius Common Tail Schedule IV
14. Motacilla alba White wagtail Schedule IV
15. Accipiter badius Shikra Schedule IV
16. Acridotherestristis Common Myna Schedule IV
17. Alcedoatthis Common King Fisher Schedule IV
18. Vanellusleucurus White tailed lapwing Schedule IV
19. Corvusmacrorhynchos Jungle Crow Schedule IV
20. Bubo bubobengalensis Great horned Owl Schedule IV
21. Phononotus café Red vented bulbul Schedule IV
Table 3.30 List of Reptiles in the Study area
S. No. Scientific Name Common Name Schedule as per
WPA,1972
1. Chameleon species Girgit Schedule IV
2. Hemidactylis species House Lizard -
3. Naja naja Indian Cobra Schedule II
Source: Primary Survey and Forest Department, Shri Muktsar Sahib District
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 83 2018_ECSS_EIAI1_1800028
3.12.3 Interpretation of Ecology and Biodiversity
Dominant trees observed in the study region were Amaltas, Gulmohar, Shisham and kali shirish.
There was no reserved forest recorded during the survey in the study region. Area is devoid of dense
forest as a result no schedule -1 wild life was observed during the survey. Common mammal of the
study region was Blue bull, Squirrel, Common mongoose and rabbit were seen. Although the soil of
study region is clay loam, which favors the plant growth but looking to the density of plant it may also
be suggested to improve the quality of environment as well as ecology and bio diversity by planting
more trees. Due to lack of natural habitat, less numbers of wild mammals were observed. Number of
species and density of wild mammals can be increased by promoting/ facilitating the growth of
bushes. There was no endangered species observed during primary survey.
3.13 SOCIO-ECONOMIC ENVIRONMENT
Socioeconomics (also known as socio-economics or social economics) is the social science that
studies how economic activity affects social processes. In general it analyses
how societies progress, stagnate, or regress because of their local or regional economy, or the global
economy.
In order to assess and evaluate the likely impacts arising out of any new or existing projects in socio-
economic environment, it is necessary to gauge the apprehension of the people in the surrounding
areas. Socio-economic survey serves as an effective tool for fulfilling this requirement.
The rapid industrialization of the study region has greatly influenced the socio economic and health
environment in the villages. Increasing industrialization and population density has increased
pressure on resources, civic amenities and public infrastructure. Economic conditions of the local
people have improved with the increasing industrialization and greater employment opportunities.
The socio-economic environment includes demography structure, population density, literacy level,
and employment levels. The data establish a baseline for the prediction of likely impacts of the
proposed activity on the socio-economic environment. Secondary information pertaining to the study
area villages was collected from Government Agencies, Census data for the year 2011, and statistical
abstracts to compile the socio-economic data.
3.13.1 Socio-Economic Survey Methodology
Socio-economic survey tools provide a means of improving understanding of local resou rce
management systems, resource use and the relative importance of resources for households and
villages. They can also be used to elicit insights on interaction with government decision-making
systems, community perceptions of trends and priority issues, and community-based institutions and
their role in the sustainable use and conservation of natural resources.
Data Collection: Following steps were considered for the collection of primary data:
1. Identification of Study Area: The study area was identified before carrying out the survey. All the
related information which could affect the prosperity, development & literacy were also collected.
2. Site Visit: Location wise survey plan & format for data collection were prepared for site visit. Data
regarding Land Characteristics, Population, Literacy, Workers and Amenities were collected during
the survey.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 84 2018_ECSS_EIAI1_1800028
Analysis of Data: The data collected by primary survey were verified with secondary data collected
from sources like Government Agencies, Census data for the year 2011, and statistical abstracts.
3.13.2 Demography
Almost all villages in the study area are experiencing a rapid growth of population due to
industrialization. The total population of study region is summarized in Table 3.32.
3.13.3 Population Density
Population density in the study area varies from 63 - 3559 person/sq. km. Details of the same are
tabulated in Table 3.31.
Table 3.31 Details of Population in Study Area
Villages No. of
Household Total
population Total area
(sq.km)
Population density
(Person/sq.km)
Ballamgarh 633 3317 10.16 326
Bhangchari 795 4134 12.87 321
Barkandi 510 2750 8.21 335
Bhagsar 1500 7669 31.04 247
Bhullar 854 4483 15.94 281
ChakDuhewala 288 1690 8.30 204
ChakTamkot 204 978 5.13 191
ChakMahanBhaddar 106 521 8.25 63
ChakGiljewala 258 1476 2.59 570
Chibranwali 533 2738 8.70 315
Dabra 187 1056 7.05 150
Duhewala 392 1984 8.43 235
Dhigana 360 1779 8.53 209
Fatuhiwala 525 2666 10.26 260
Goniana 758 3729 8.70 429
KhundeHalal 464 2246 9.92 226
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 85 2018_ECSS_EIAI1_1800028
Mehrajwala 337 1701 7.03 242
Rohurianwali 528 2727 9.76 279
Rupana 1916 9079 24.53 370
SanguDhaun 488 2607 8.34 313
Sotha 710 3639 13.27 274
Muktsar (M Cl) 23644 116747 32.80 3559
Thandewala 1356 6814 21.60 315
UdeKaran 730 3940 13.93 283
Total 38,076 1,90,470 295.34 9,998
3.13.4 Sex Ratio
The sex ratio i.e. the number of females per 1000 males is in range of 841 - 1118 with lowest in
ChakDuhewala village and highest in ChakMahanBhaddar village. The Sex ratio i.e. the number of
females per 1000 males indirectly reveals certain sociological aspect in relation to female births, infant
mortality among female children. Details of the same are tabulated in Table 3.32.
Table 3.32 Details of Sex Ratio in Study Area
Zone of Study Male
Population Female
Population Total
Population
Sex Ratio
(Female to 1000 Male)
Ballamgarh 1736 1581 3317 911
Bhangchari 2190 1944 4134 888
Barkandi 1482 1268 2750 856
Bhagsar 4100 3569 7669 870
Bhullar 2369 2114 4483 892
ChakDuhewala 918 772 1690 841
ChakTamkot 514 464 978 903
ChakMahanBhadda
r 246 275 521 1118
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 86 2018_ECSS_EIAI1_1800028
ChakGiljewala 745 731 1476 981
Chibranwali 1411 1327 2738 940
Dabra 575 481 1056 837
Duhewala 1054 930 1984 882
Dhigana 911 868 1779 953
Fatuhiwala 1403 1263 2666 900
Goniana 1943 1786 3729 919
KhundeHalal 1181 1065 2246 902
Mehrajwala 897 804 1701 896
Rohurianwali 1399 1328 2727 949
Rupana 4939 4140 9079 838
SanguDhaun 1384 1223 2607 884
Sotha 1885 1754 3639 931
Muktsar (M Cl) 61725 55022 116747 891
Thandewala 3602 3212 6814 892
UdeKaran 2084 1856 3940 891
Total 1,00,693 89,777 1,90,470 -
3.13.5 Literacy Rate
The literacy level of the study area is summarized in Table 3.33and graphically presented in Figure
3.16.
Table 3.33 Details of Literacy Rate in Study Area
Zone of Study
Literate Literacy (%)
Male Female Total Male Female Total
Ballamgarh 1058 784 1842 60.94 49.59 55.53
Bhangchari 1291 982 2273 58.95 50.51 54.98
Barkandi 781 551 1332 52.70 43.45 48.44
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 87 2018_ECSS_EIAI1_1800028
Bhagsar 2283 1639 3922 55.68 45.92 51.14
Bhullar 1323 1027 2350 55.85 48.58 52.42
ChakDuhewala 529 355 884 57.63 45.98 52.31
ChakTamkot 312 231 543 60.70 49.78 55.52
ChakMahanBhaddar 131 124 255 53.25 45.09 48.94
ChakGiljewala 397 333 730 53.29 45.55 49.46
Chibranwali 783 638 1421 55.49 48.08 51.90
Dabra 326 226 552 56.70 46.99 52.27
Duhewala 617 450 1067 58.54 48.39 53.78
Dhigana 587 452 1039 64.43 52.07 58.40
Fatuhiwala 746 556 1302 53.17 44.02 48.84
Goniana 1062 779 1841 54.66 43.62 49.37
KhundeHalal 599 423 1022 50.72 39.72 45.50
Mehrajwala 531 386 917 59.20 48.01 53.91
Rohurianwali 878 677 1555 62.76 50.98 57.02
Rupana 3093 2139 5232 62.62 51.67 57.63
SanguDhaun 906 614 1520 65.46 50.20 58.30
Sotha 1162 907 2069 61.64 51.71 56.86
Muktsar (M Cl) 44089 34157 78606 71.43 62.08 67.33
Thandewala 2251 1706 3957 62.49 53.11 58.07
UdeKaran 1301 974 2275 62.43 52.48 57.74
Total 67,036 51,110 1,18,506 - - -
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 88 2018_ECSS_EIAI1_1800028
Figure 3.16: Graph of Literacy Rate
Among all the villages of study area Muktsar (M Cl) is having high literacy rate i.e. 67.33 %. There is
not much difference between female literacy rate and male literacy rate in the study region. Female
literacy rate is an important indicator for social change.
3.13.6 Economic Aspects
Economic aspects of the study area include the economic structure of the people of the surrounding
area. It can be predicted that economic structure of the study area will be improved with time,
because it consists large industrial estate and hence there are more employment opportunities.
According to working status, whole population of the study area is divided into,
Marginal workers
Non workers
Main workers
Census department has defined 10 categories of workers in Main workers. It consists of cultivators,
agricultural, labourer those engaged in livestock, forestry, fishing, mining and quarrying,
manufacturing, processing and repairs in household industries and other services. Workers engaged
in the work for a period less than 6 month during the reference year falls under marginal workers.
Workers engaged in unpaid household duties e.g. students, retired person, dependents etc. falls
under non-workers. Detail of occupational structure is shown in Table 3.34.
Table 3.34 Details of Occupational Structure
Zone of Study
Total Workers
Non Workers
(%)
Main Workers
(%)
Marginal Workers
(%)
0
10
20
30
40
50
60
70
80
% L
iter
acy
Villages
Literacy (%) Male Literacy (%) Female Literacy (%) Total
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 89 2018_ECSS_EIAI1_1800028
Ballamgarh 54.69 37.14 8.17
Bhangchari 65.70 31.64 2.66
Barkandi 57.02 32.47 10.51
Bhagsar 65.82 31.46 2.71
Bhullar 69.11 28.31 2.59
ChakDuhewala 52.31 33.14 14.56
ChakTamkot 64.62 33.03 2.35
ChakMahanBhaddar 62.96 6.91 30.13
ChakGiljewala 70.05 29.54 0.41
Chibranwali 60.41 39.30 0.29
Dabra 63.83 35.42 0.76
Duhewala 66.48 30.39 3.13
Dhigana 65.71 27.54 6.75
Fatuhiwala 53.83 35.41 10.77
Goniana 61.81 30.46 7.72
KhundeHalal 68.08 31.79 0.13
Mehrajwala 58.55 39.39 2.06
Rohurianwali 63.59 31.79 4.62
Rupana 60.91 29.23 9.86
SanguDhaun 63.60 29.34 7.06
Sotha 67.30 30.50 2.20
Muktsar (M Cl) 65.48 30.91 3.61
Thandewala 60.52 37.26 2.22
UdeKaran 64.42 31.78 3.81
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 90 2018_ECSS_EIAI1_1800028
Mehrajwala village has significant employment i.e. 39.39 % as main workers, while the lowest
employment as main workers in ChakMahanBhaddar i.e. 6.91 %. Almost all the villages have more
than 50 % people as non-workers. Rapid industrialization in the last two decades has resulted in
significant changes in the occupational profile of the local people. There is an overall trend among the
youth to opt for employment in service sector and move away from traditional occupation.
Figure 3.17 Occupational Structure of Study Area
0
10
20
30
40
50
60
70
80
% o
f W
ork
ers
Villages
Non Workers (%) Total Workers Main Workers(%) Total Workers Marginal Workers (%)
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 91 2018_ECSS_EIAI1_1800028
3.13.7 Amenities
Village
Name
Govt.
Primar
y
School
Govt
Vocatio
nal
Training
CentreIT
I
Govt.
PHC
&SC
Tap
Water
Untreate
d
River&
Canal
Total
Sanitation
Campaign
Telephon
e
/Mobile
Public/Pvt
modeof
transporta
tion
Metal
Road
Commerci
al
Bank
Agriculture
Credit
Society
Community
Centre
Self
Help
Groups
Ballamgarh Yes No Yes Yes Yes Yes Yes Yes Yes No No Yes No
Bhangchari Yes No No No Yes No Yes Yes Yes No Yes No No
Barkandi No No No Yes No No Yes Yes Yes No Yes No No
Bhagsar Yes No No Yes Yes No Yes Yes Yes Yes Yes No No
Bhullar Yes No No Yes Yes No Yes Yes Yes Yes No No No
ChakDuhew
ala
No No No No No Yes No Yes Yes No No No No
ChakTamko
t
No No No No No Yes No Yes Yes No No No No
ChakMahan
Bhaddar
Yes No No Yes No No Yes Yes Yes No No No No
ChakGiljew
ala
No No No No No No Yes Yes Yes No No No No
Chibranwali Yes No Yes Yes Yes Yes Yes Yes No No Yes No No
Dabra Yes No No Yes No No Yes Yes Yes No No Yes No
Duhewala No No No No No No Yes Yes No No No No No
Dhigana Yes No No Yes No No Yes Yes Yes No No No No
Fatuhiwala Yes No No Yes No No Yes Yes Yes No Yes No No
Goniana Yes No No Yes No No No Yes Yes No Yes No No
KhundeHala
l
No No No Yes Yes Yes Yes Yes No No Yes No No
Mehrajwala No No No Yes Yes No Yes Yes Yes No No No No
Rohurianwal
i
No No No No No No Yes Yes Yes No Yes No Yes
Rupana No No No No No No Yes Yes Yes Yes Yes Yes No
Sangu
Dhaun
No No Yes No No No Yes Yes Yes No Yes No Yes
Sotha No No Yes No Yes No Yes Yes Yes No No No No
Muktsar(MC
)
Yes Yes No Yes Yes Yes No Yes Yes Yes Yes Yes Yes
Thandewala No No No No No No Yes Yes Yes No Yes No Yes
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 92 2018_ECSS_EIAI1_1800028
Ude Karan No Yes No Yes No No Yes Yes No No No No No
Source: Census 2011, Muktsar District
Primary Socio economic Survey & Census
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 93 2018_ECSS_EIAI1_1800028
3.13.8 Interpretation of Socio Economic Data
During the primary survey it was observed that almost pakka road facility is available in all villages
within 10 km radius. Literacy rate of the study region is from 48.44 to 67.33%. When compared to other
places, these villages exhibit lower rate of literacy thus there is need to promote education among more
and more people. Almost all the villages have more than 50% people as non-workers. It indicates that
the problem of unemployment can be solved by providing proper training and education. There is also
need to establish more industries so that maximum number of employment can be generated.Basic
amenities like Education facilities Health care facilities, water supply, electric power supply, mode of
transportation etc. are available in all villages.
3.14 SUMMARY
Ambient Air Quality Monitoring
Sr. No.
Criteria Pollutants
Unit Maximum Value
Minimum Value
98th Percentile
Value
Prescribed Standard
1. PM10 µg/m3 88.6 62.5 88.4 100
2. PM2.5 µg/m3 48.3 32.8 48.0 60
3. SO2 µg/m3 16.7 9.6 16.6 80
4. NOX µg/m3 21.5 14.2 21.5 80
All the results of ambient air quality parameters have been found well within the limit as per NAAQS. Based on comparison study of results for tested parameters with NAAQS, it is interpreted that ambient air quality of studied locations is good. This interpretation relates to the sampling carried out and results found for particular locations and study period.
Noise Monitoring
Sr. No.
Parameter Unit Maximum Value Minimum Value Prescribed Standard
1. Leq (Day) dB(A) 77.4 49.8 -
2. Leq(Night) dB(A) 72.1 42.8 -
Based on noise level data obtained during the survey for residential area and industrial area, it is interpreted that noise levels are within the standard norms prescribed by MoEF & CC. Looking towards the increase in noise generating sources it is suggested that there is need to apply noise
reducing devices at noise generating sources and generate public awareness. Soil Qualityand Characteristics
Sr. No.
Parameter Unit Maximum Value Minimum Value
1. pH - 7.44 7.12
2. Electrical Conductivity dS/m 0.48 0.35
3. Sodium meq/100gm 1.2 0.8
4. Potassium meq/100gm 0.5 0.3
5. Phosphorous mg/100gm 16.3 13.6
6. Total Nitrogen % 0.074 0.052
Based on soil analysis data it is concluded that soils are normal from salinity point of view as SAR is <2.0 and ESP is < 15%. The soils are having medium in nitrogen, low in phosphorus and potassium. The levels of total Fe, Cu, Cr, B and Zn are within the safe limits. However, for successful greenbelt development liberal quantity of organic manure is recommended. Soils of studied locations are suitable for plantation as well as for agricultural purpose.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 94 2018_ECSS_EIAI1_1800028
Ground Water
Sr. No.
Parameter Unit Maximum Value
Minimum Value
Desirable Limit
Permissible Limit
1. pH - 7.94 7.04 6.5-8.5 No
Relaxation
2. TDS mg/L 2254 218 500 2000
3. TSS mg/L < 2 < 2 - -
4. Total Hardness mg/L 1200 112 200 600
5. Chloride mg/L 875 40 250 1000
6. Total Alkalinity mg/L 580 122 200 600
7. Fluoride mg/L 0.7 0.11 1.0 1.5
8. Iron mg/L 0.42 < 0.10 0.3 No
Relaxation
Based on comparison study of test results with drinking water norms, it is interpreted that water qualities of most of the studied locations meet with the drinking water standards as per IS 10500: 2012 except Goniana village. Ground water sample collected from project site, Rupana, Sotha, chak Gilijiwala,Barkandi,Muktsar and Bhangchiri can be used in drinking as well as in other domestic and irrigation purpose. Ground water sample collected from Goniana village should not be used in drinking as it contains TDS, Total Hardness, Chloride and Iron more than prescribed limit but it can be used in other domestic purpose as well as in irrigation also. These interpretations are based on comparison study with standard for tested parameters only as per IS 10500: 2012.
Surface Water
Sr. No.
Parameter Unit Maximum Value
Minimum Value
Desirable Limit
Permissible Limit
1. pH - 7.75 7.23 6.5-8.5 No Relaxation
2. TDS mg/L 214 168 500 2000
3. DO mg/L 5.1 4.9 - -
4. COD mg/L 16 10 - -
5. BOD mg/L 6 < 4.0 - -
River water qualities for the samples collected from different surface water bodies are contaminated with organic matter and microbes. Total coliforms have been reported in all sample, it indicated towards the faecal pollution in surface water bodies. Results of other tested parameters meet with the drinking water norms. Based on comparison study with drinking water norms it is concluded that these water sources can be used for irrigation purpose and it can also be used in drinking after conventional treatment followed by disinfection.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 95 2018_ECSS_EIAI1_1800028
Ecologyand Biodiversity
Dominant trees observed in the study region were Amaltas, Gulmohar, Shisham and kali shirish. There was no reserved forest recorded during the survey in the study region. Area is devoid of dense forest as a result no schedule -1 wild life was observed during the survey. Common mammal of the study region was Blue bull, Squirrel, Common mongoose and rabbit were seen. Although the soil of study region is clay loam, which favors the plant growth but looking to the density of plant it may also be suggested to improve the quality of environment as well as ecology and bio diversity by planting more trees. Due to lack of natural habitat, less numbers of wild mammals were observed. Number of species and density of wild mammals can be increased by promoting/ facilitating the growth of bushes. There was no endangered species observed during primary survey.
Socio Economic
During the primary survey it was observed that almost pakka road facility is available in all villages within 10 km radius. Literacy rate of the study region is from 48.44 to 67.33%. When compared to other places, these villages exhibit lower rate of literacy thus there is need to promote education among more and more people. Almost all the villages have more than 50% people as non-workers. It indicates that the problem of unemployment can be solved by providing proper training and education. There is also need to establish more industries so that maximum number of employment can be generated.Basic amenities like Education facilities Health care facilities, water supply, electric power supply, mode of transportation etc. are available in all villages.
-------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 96 2018_ECSS_EIAI1_1800028
CHAPTER – 4
ANTICIPATED ENVIRONMENT IMPACT AND
MITIGATION MEASURES
4.0 GENERAL
This chapter provides basis for assessment and management tool that evaluates the possible positive or
negative impacts that a proposed project may have on the environment. The purpose of the assessment
is to ensure that decision makers consider the ensuring environmental impacts when deciding to proceed
with a project.
The chapter aims at controlling pollution at the source level to the extent possible with the available and
affordable technology followed by treatment measures before they are discharged. The proposed project
would create impact on the environment in two distinct phases:
i. During the construction phase which may be regarded as temporary or short term and
ii. During the operation phase which would have long term effects.
The construction and operational phase of the proposed project comprises various activities each of
which will have an impact on some or other environmental parameters. Various impacts during the
construction and operation phase on the environmental parameters have been studied and mitigation
measures for the same are discussed briefly below and elaborated in the subsequent sections.
4.1 IMPACTS IDENTIFICATION DURING CONSTRUCTION PHASE
This phase involves the activities like erection of civil structures, erection of equipment and machinery,
green belt development etc. Air, Water, Noise and Land Environment are likely to be affected by the
activities, although aesthetics and socio-economic factors are also identified. But the impacts will be
marginal and for short term only. The green belt development will have positive impacts.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 97 2018_ECSS_EIAI1_1800028
4.1.1 Matrix Representation
Table 4.1: Impact Matrix with Mitigation Measures (Construction Phase)
Activities
Environmental Attributes
Air
Wate
r
So
il
No
ise
LU
/LC
Hyd
ro
Geo
log
y
Geo
log
y
SH
W
Ris
k
Hazard
ou
s
Eco
log
y &
Bio
div
ers
ity
So
cio
Eco
no
mic
Transportation of construction material
and operation of machineries
✔ - ✔ ✔ - - - - ✔ ✔ ✔
Storage and handling of construction
material ✔ ✔ ✔ ✔ - - - - ✔ - -
Civil Construction Activities
✔ ✔ ✔ ✔ ✔ - - ✔ ✔ - ✔
Disposal of Construction Debris
✔ - ✔ - - - - ✔ - - -
Wastewater-Sewage Disposal
- ✔ ✔ - - - - ✔ - - -
Additional Greenbelt Development
✔ ✔ ✔ ✔ ✔ ✔ - - - ✔ -
Employment Generation
- ✔ - - - - - ✔ - - ✔
Table 4.2: Severity Criteria for Magnitude of Impacts
S. No.
Category Description of Category Impact
Adverse Beneficial
1. No Impact - 0 0
2. No Appreciable
Impact Short Term Reversible -1 1
3. Significant Impact Long Term Reversible -2 2
4. Major Impact Irreversible but of Lesser
Extent -3 3
5. High Impact Irreversible but of Medium
Extent -4 4
6. Permanent Impact Severe Irreversible Impact -5 5
Table 4.3: Score range for beneficial and adverse impacts
S. No.
Total Score Outcome
1. +ve / -ve Beneficial Impact / Adverse Impact
2. 0-150 No appreciable Beneficial Impact / Adverse Impact
3. 151-300 Appreciable but reversible adverse impact-mitigation measures are needed
4. 301-450
Significant adverse impacts: most of the impacts are reversible. Mitigation measures are crucial.
5. 451-600
Major adverse impacts; most of the impacts are reversible. Alternative site selection to be considered.
6. >600 Permanent irreversible impact; alternatives to the project need to be explored
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 98 2018_ECSS_EIAI1_1800028
Pro
ba
bilit
y
Impact
Very Low
1
Low
2
Medium
3
High
4
Very High
5
Very High 5 5 10 15 20 25
High 4 4 8 12 16 20
Medium 3 3 6 9 12 15
Low 2 2 4 6 8 10
Very Low 1 1 2 3 4 5
Figure 4.1: Impact Quantification Matrix
Table 4.4: Environmental Impact Matrix without Mitigation (Construction Phase)
Activities
Environmental Attributes
Total
Air
Wate
r
So
il
No
ise
LU
/LC
Hyd
ro
geo
log
y
Geo
log
y
SH
W
Ris
k
Hazard
ou
s
Eco
log
y a
nd
Bio
div
ers
ity
So
cio
Eco
no
mic
Transportation of construction material
and operation of machineries
-6 - -2 -6 - - - - -6 -4 -2 -26
Storage and handling of construction
material -4 -2 -2 -4 - - - - -6 - - -18
Civil Construction Activities
-8 -4 -2 -6 -4 - - -6 -16 - -2 -48
Disposal of Construction
Debris -2 - -2 - - - - -6 - - - -10
Wastewater-sewage Disposal
- -6 -4 - - - - -4 - - - -14
Additional Greenbelt Development
+4 -2 +4 +4 +2 +2 - - - +4 - +18
Employment Generation
- -4 - - - - - -4 - - +9 +1
Total -16 -18 -8 -12 -2 +2 0 -20 -28 0 +5 -97
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 99 2018_ECSS_EIAI1_1800028
4.1.2 Air Environment
Table 4.5: Impact on Air Environment and Mitigation Measures
Project Activity Impact Mitigation Measures
Transportation of construction material and operation of machineries
Fugitive Dust Emissions due to vehicle Movement may deteriorate the quality of Air.
Exhaust emissions from vehicles and equipment deployed during the construction phase is also likely to result in marginal increase in the levels of SO2, NOx and PM which leads to respiratory ailments like asthama and other dust related problems to the human health.
Excavated soil and construction debris will be sprinkled with water and kept moist.
The Malout –Sri Muktsar Sahib (SH-16) is well developed paved road. Also Company has developed Cement concrete road in project premises. It shall reduce the dust emission due to transportation.
Trucks used for transportation of construction materials shall be covered with tarpaulin sheet to avoid dust dispersion at site.
Only valid PUC certified vehicle is being/will be used for the transportation of materials and equipment.
Concrete batching plants will be located at a minimum distance of 500 meters from any residences and will be equipped with dust control equipment such as fabric filters or wet scrubbers to reduce the level of dust emissions.
Storage and handling of construction material
Spillage and fugitive emissions of construction materials
Stomatal index may be minimized due to dust deposit on leaf which reduces crop yield and deteriorate crop quality.
Construction materials will be covered with tarpaulin sheets throughout the construction phase to avoid dust generation.
Barricading will be done at the construction area.
Civil Construction Activities
Increase of dust and airborne particulates
Regular water sprinkling will be done to control dust emission.
Personnel Protective Equipment (PPEs) will be provided to the construction workers. Hence there will be no significant impacts on their health due to the dust particle.
Disposal of Construction Debris
Construction debris and disposed domestic garbage may create nuisance due to odour generation.
Separate bins will be provided for storage of Garbage/Wastes and will be disposed off adequately.
Wastewater-sewage disposal
Odour generation due to sewage disposal may create nuisance to the people
Existing sanitation facilities will be provided to construction workers.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 100 2018_ECSS_EIAI1_1800028
Project Activity Impact Mitigation Measures
Additional Greenbelt Development
Positive impact due to greenbelt development as it will act natural barrier for dust and noise emission.
Existing greenbelt plantation would reduce the impacts during the construction phase.
The impact will be confined within the project boundary and is expected to be negligible outside the plant boundaries.
Implementation of plantation plan for trees & plants
SIL has already developed Greenbelt and it shall be further enhanced as per norms after grant of EC for proposed expansion
4.1.3 Water Environment
Table 4.6: Impact on Water Environment and Mitigation Measures
Project Activity Impact Mitigation Measures
Civil Construction Activities
Decrease the ground water level due to consumption of water
The water will be sourced from Arniwala Canal and hence potential impact on groundwater resources is not envisaged as No ground water will be abstracted for construction purpose.
Wastewater-sewage Disposal
Untreated sewage may have negative impact.
Existing sanitation facilities shall be provided to construction workers. Sewage will be disposed through septic tank.
Employment Generation
Water resource depletion due to water consumption
No groundwater will be used. The water will be sourced from Arniwala Canal.
4.1.4 Soil Environment
Table 4.7: Impact on Soil Environment and Mitigation Measures
Project Activity Impact Mitigation Measures
Transportation of construction material and operation of machineries
Lands may get contaminated from the spillage of chemicals such as fuels, oils, paints and other construction chemicals and concrete. This normally happens when these materials are transported in open or loosely capped containers.
Control measures will be needed for oily residues such as transformer oil and lubricants in the case of accidental or unexpected release. Transformer oil is supplied in drums from an imported source
Oily residues and fuel and any contaminated soil residues will be captured at source and refueling and maintenance will take place in dedicated areas away from surface water resources. Contaminated
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 101 2018_ECSS_EIAI1_1800028
Project Activity Impact Mitigation Measures
residues and waste oily residues will be disposed at a site agreed with the local authority
Civil construction activities
The excavated earth material if stacked loosely may result into runoff resulting in loss of topsoil.
As the proposed project is an expansion project, No major excavation will be carried out.
Excavated earth (if any) shall be stored in stockpiles and covered with plastic/tarpaulin sheets or stored in closed room and reused for landscape development along the corridor.
Storage and handling of construction material
Soil contamination due to handling and storage of construction material.
Oil spillage can affect physical and chemical properties of the soils.
The construction material & diesel /oil to be used for various construction activities shall be stored in designated storage yards to reduce the spills into unwarranted areas.
Good practices of storage and material handling will be carried out.
Spillage control will be carried out by disposing the affected soil at adequate place
Transportation and Disposal
of Construction
Debris
Contamination of the soils of surrounding area due to construction materials such as cement, sand, oils, etc.
The construction wastes shall be utilized for PCC works, road construction and other filling requirement etc.
Wastewater-sewage Disposal
Unmanaged sewage can also contribute to contamination of soil.
The wastewater generation during the construction period will be from the sanitary units provided for the constructional workers.
This wastewater will be treated in existing septic tanks and discharged into soak pits.
Additional Greenbelt Development
Positive impact as improvement in soil texture due to binding of top soil materials and root structure.
The greenbelt development will control the soil erosion due to wind and runoff water.
Regular maintenance of greenbelt will be done.
4.1.5 Noise Environment
Table 4.8: Impact on Noise Environment and Mitigation Measures
Project Activity Impact Mitigation Measures
Transportation of construction material and operation of machineries
Continuous Noise Pollution
affects the human working
efficiency.
Only valid PUC Certified vehicle will be used for the transportation of materials and equipment.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 102 2018_ECSS_EIAI1_1800028
Project Activity Impact Mitigation Measures
Civil Construction Activities
It is anticipated that powered
mechanical equipment and
some local labour with hand
tool methods will be used to
construct the sub-project
works.
Powered mechanical
equipment can generate
significant noise and
vibration.
The cumulative effects from
several machines can be
significant. Noise and
vibration from the
construction of the towers
would not be a major
consideration as there are no
schools or hospitals present
near the construction site.
Construction activities shall be allowed only during day time.
Machinery used for construction will be of high standard reputed make and will adhere to International standards. These standards itself take care of noise pollution control / vibration control and air emission control.
Lubrication will be carried-out periodically for rotation machinery.
Use of well-maintained construction equipment as well as vehicles used for transportation.
Vibration control damped tools shall be used and the number of hours that a worker uses them must be limited.
Provision of PPEs like earmuffs/earplug to avoid adverse effects of noise on occupational health and hearing capacity of workers as well as planning of working hours and shift of workers.
Storage and handling of construction material
Additional Greenbelt Development
Plant parts such as stems, leaves, branches, wood, etc. absorb sound. Rough bark and thick, fleshy leaves are particularly effective at absorbing sound with their dynamic surface area for absorbing sound.
SIL has already developed Greenbelt and it shall be further enhanced as per norms after grant of EC for proposed expansion
4.1.6 Land Use/ Land Cover
Table 4.9: Impact on Land Cover/ Land Use and Mitigation Measures
Project Activity Impact Mitigation Measures
Additional Greenbelt Development
No major impact as land is already developed and expansion will be carried out in existing premises.
Green belt development will lead to permanent change in land cover pattern at the site as a direct impact.
Greenbelt area will be developed which will result in beneficial impacts on land cover of the project area.
4.1.7 Hydrogeology
Table 4.10: Impact on Hydrogeology and Mitigation Measures
Project Activity Impact Mitigation Measures
Proposed Projects falls in already developed Notified Industrial Area and water will be sourced from Arniwala Canal so there will be no Impact on Hydrogeology.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 103 2018_ECSS_EIAI1_1800028
4.1.8 Geology
Table 4.11: Impact on Geology and Mitigation Measures
Project Activity Impact Mitigation Measures
No impact is envisaged on the geology of the area due to construction activities.
4.1.9 Solid/Hazardous Waste
Table 4.12: Impact due to Solid/ Hazardous waste and Mitigation Measures
Project Activity Impact Mitigation Measures
Civil Construction Activities
The excavated earth material if stacked loosely may result into runoff resulting in loss of top soil.
As the proposed project is an expansion project, No major excavation will be carried out.
Excavated earth shall be stored in stockpiles and covered with plastic/tarpaulin sheets or stored in closed room and reused for landscape development along the corridor.
Transportation and Disposal of Construction Debris
Due to construction activity construction waste will be generated may cause negative impact, if not disposed properly.
Fuel leakage/ spillage used for construction equipment or vehicles may cause land contamination.
Fuel leakage/spillage shall be mitigated by providing properly lined storage area.
The construction wastes shall be utilized for leveling work etc.
Care shall also be taken that stagnant pools are not formed at the site during the construction phase.
Separate bins will be provided storing Garbage/Wastes and will be disposed off adequately.
Wastewater-sewage Disposal
Employment Generation
The solid wastes generated from the domestic activities of construction workforce and sewage generation may cause land contamination.
Existing sanitation and drinking water facilities will be provided for construction workers.
Sewage generated will be disposed properly through existing soak pit to avoid any adverse impacts on land.
4.1.10 Risks and Hazards
Table 4.13: Impact of Risk and Hazards and Mitigation Measures
Project Activity Impact Mitigation Measures
Transportation of construction material and operation of machineries
Chances of accident may increase due to proposed construction activity.
All the activities will be carried out under the supervision and control of the management.
The Vehicles must be maintained in good repairs and checked thoroughly at least once a week by the competent person authorized by the Management.
Safety equipment such as helmet, goggles, ear plug, etc., shall be provided.
Civil Construction Activities
Storage and handling of construction material
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 104 2018_ECSS_EIAI1_1800028
4.1.11 Ecology and Biodiversity
Table 4.14: Impact on Ecology and Biodiversity and Mitigation Measures
Project Activity Impact Mitigation Measures
Transportation of construction material and operation of machineries
Transportation of Construction material by the trucks/dumper will disturb the movement of animal and birds.
Fugitive emission from vehicle movement will form a layer in leaves thus reducing the gaseous exchange process. This ultimately affects the growth of plants.
Sewage discharge from the proposed activity can contaminate the soil and ultimately effect the growth of plants.
Transportation of products and raw material should be minimize in the morning and evening and cannot be done in night.
During the site visit, it was observed that there is no forest land, or ecologically sensitive areanear the project site. Hence impact on the same is not envisaged.
The proposed activities do not envisage destruction of habitat and feeding or breeding area of faunal species. Further, development of plantation will provide habitat, food and breeding areas for small animals and insects. Thus a positive impact is envisaged.
Green belt Development
Greenbelt development may cause positive impacts on the flora by enhancement of green spaces
Generation of habitats for avifauna i.e. positive impact.
Regular watering and maintenance of the greenbelt for sustained plant growth.
4.1.12 Socio-Economy
Table 4.15: Impact on Socio Economic and Mitigation Measures
Project Activity Impact Mitigation Measures
Transportation of construction material and operation of machineries
The construction phase will generate employment opportunity of in the skilled as well as unskilled categories. Although the workforce requirement will be temporary in nature, it will be met from the local population hence there will be positive impact.
Construction workers will require essential basic infrastructure facilities viz. safe drinking water, adequate sanitation, etc. will have temporary impact on the existing facilities.
The contractor will provide all existing facilities to the workers to reduce the impact on the existing facilities in the study area.
Local businessmen will get opportunity to supply construction materials.
Demands generated from the employees working at site for basic facilities will increase the local business activity of the area.
Any development, either temporary or permanent will support the family of many villagers. Thus, positive impacts are envisaged on socio-economic environment.
Civil Construction Activities
Employment Generation
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 105 2018_ECSS_EIAI1_1800028
Table 4.16: Environmental Impact Matrix with Mitigation (Construction Phase)
Activities
Environmental Attributes
Air
Wate
r
So
il
No
ise
LU
/LC
Hyd
ro
geo
log
y
Geo
log
y
SH
W
Ris
k
Hazard
ou
s
Eco
log
y a
nd
Bio
div
ers
ity
So
cio
Eco
no
mic
To
tal
Transportation of construction material
and operation of machineries
-2 - -1 -2 - - - - -4 -2 +4 -7
Storage and handling of construction
material -2 - -1 -2 - - - - -2 - - -7
Civil Construction Activities
-4 -2 -2 -4 -2 - - -2 -4 - +12 -8
Disposal of Construction
Debris -1 - -2 - - - - -2 - - - -5
Wastewater-sewage Disposal
- -2 -2 - - - - -1 - - - -5
Greenbelt Development
+4 - +2 +4 +4 +4 - - - +4 +2 +24
Employment Generation
- -4 - - - - - -2 - - +9 +3
Total -5 -8 -6 -4 +2 +4 0 -7 -10 +2 +27 -5
Highest cumulative score (-8) received for Civil Construction Activities parameter. Highest total (+24)
received for Greenbelt Development which is beneficial for environment. Total Cumulative Score for
various Environmental Parameters with implementation of adequate mitigation measures is -5 during
construction.
4.2 ANTICIPATED ENVIRONMENTAL IMPACTS DURING OPERATION
PHASE
This phase of the project is important because it generates long-term impacts as the project
implementation phase starts. The primary impacts causing likely deterioration will be in Air, Water,
Noise and Land/Soil due to the gaseous emissions, vehicular movement, and discharge of liquid
effluent. Identification of impacts during operation phase is given in Table 4.16 and 4.17
4.2.1 Matrix Representation
The potential impacts during construction and operation phases are presented in the form of a matrix in
Table 4.16. The scores for various parameters and activities are presented in table-4.17.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 106 2018_ECSS_EIAI1_1800028
Table 4.17 - Impact Matrix with Mitigation Measures (Operation Phase)
Activities
Environmental Attributes
Air
Wa
ter
So
il
No
ise
LU
/LC
Hy
dro
geo
log
y
Ge
olo
gy
SH
W
Ris
k &
Ha
zard
EB
So
cio
Ec
on
om
ic
Transportation of
Materials & Manpower ✔ - - ✔ - - - - ✔ ✔ ✔
Storage& Handling of
Raw Material &
Product
✔ - ✔ - - - - ✔ ✔ - -
Resource Utilization - ✔ - - - ✔ - - - ✔ ✔
Fuel Handling ✔ ✔ - - - - - ✔ ✔ - ✔
Operation of CPP ✔ ✔ - ✔ - - - ✔ ✔ - ✔
Manufacturing
Process ✔ ✔ - ✔ - - - ✔ ✔ - -
Domestic Wastewater
Generation - ✔ ✔ - ✔ - - - - - -
Industrial Wastewater
Generation - ✔ ✔ - ✔ - - - - ✔ ✔
Solid Waste Disposal - ✔ ✔ - - - - ✔ - - -
Recruitment ✔ ✔ - ✔ - - - ✔ - - ✔
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 107 2018_ECSS_EIAI1_1800028
Table 4.18 - Environmental Impact Matrix without Mitigation (Operation Phase)
Activities
Environmental Attributes
Air
Wa
ter
So
il
No
ise
LU
/LC
Hy
dro
geo
log
y
Ge
olo
gy
SH
W
Ris
k &
Ha
zard
EB
So
cio
Ec
on
om
ic
To
tal
Transportation of Materials & Machinery
-12 - - -16 - - - - -9 -4 -6 -47
Storage & handling of Raw material &
Product -8 - -8 - - - - -4 -4 - - -24
Resource Utilization
- -4 - - - -4 - - - -4 -3 -15
Fuel Handling -9 -12 - - - - -4 -8 - -4 -37
Operation of CPP -12 -20 - -25 - - - -8 -12 - -4 -81
Manufacturing Process
-12 -20 - -12 - - - -9 -8 - - -61
Domestic wastewater generation
- -4 -4 - -2 - - - - - - -10
Industrial wastewater generation
- -16 -9 - -2 - - - - -6 -4 -37
Solid Waste Disposal (ISW, HSW, MSW)
- -6 -6 - - - - -8 - - - -20
Recruitment - -6 - -4 - - - -4 - - +25 +11
Total -53 -88 -27 -57 -4 -4 0 -37 -41 -14 +4 -321
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 108 2018_ECSS_EIAI1_1800028
4.2.2 Air Environment
Emissions from Transportation Vehicles
Raw Material requirement for Paper
Existing – 29,742 TPM
Proposed – 15,865 TPM
Total – 45,607 TPM
The other sources likely to be affecting the pollutant concentrations in project area would be vehicular and
vessels emission due to transportation in proposed project. Transportation Vehicles requirement after
proposed expansionwill be approximate 76 Nos. of trucks will be required for raw material and 30 Nos. for
products and 80 Nos. for fuel per day. Thus, total 186 Nos. of trucks will be arriving / leaving the project
site in a day. Internal RCC road network and separate entry/exit gate will be provided for smooth
functioning of the traffic. Adequate parking space for trucks is provided at the project site.
Table 4.19– Vehicles required daily
S.
No. Details Requirement Quantity
1. Total Trucks
a. Total Trucks of Finished Goods 600 TPD 30Trucks/Day
b. Total Trucks of Raw Material 1521 TPD 76.05~76 Trucks/Day
c. Total Trucks of Fuel 900TPD 45 Trucks/Day
Total Trucks per day 151 trucks/day
On an average, depending on the production capacity, raw material requirement and fuel requirement,
186 trucks will be arriving/ leaving the project site on a daily basis.
Impact Due to Transport: The sources likely to be affecting the pollutant concentrations in project
area would be vehicular emission due to transportation in proposed project. On account of various
associated activities, there will be increased vehicular traffic on connecting roads. Generation of
gaseous emissions is therefore, of primary concern. Mode of transportation of each incoming and
outgoing material is presented in below and for computation of traffic modeling studies frequency of
vehicles has been calculated.
Impact on Traffic Density:
Enhanced Traffic on Road Adequacy: With present level of traffic and the increase in existing
traffic due to the project during operational phase has been estimated by comparison with the
recommendations stipulated by Indian Road Congress (IRC).
Table 4.20 - Recommendations on Traffic Capacity as per IRC 2010
S.
No. Category of Road Maximum PCU/hr. Dispatch Ratio (%)
1. SH - 16 1250 20
Source: IRC:SP:37:2010
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 109 2018_ECSS_EIAI1_1800028
Part A
It is estimated that 186 Nos. of trucks per day will required for product and raw material handling.
Traffic load on internal and external road is calculated as under,
Total trucks = 186 truck/Day
Frequency of trucks (Nos. of truck x cycle x up and down) = 186 x 1 x 2 = 372 Nos./Day
PCU/Day (Nos. of truck x 3) = 372 x 3 = 1116 PCU/Day
PCU per hour = 46.50
Part B
Total No. of employee = 1600 Nos.
Cars of the employees = 50 Nos.
Two wheelers of the employees = 400 Nos.
Frequency of cars (Nos. of cars x cycle x up and down) = 50 x 1 x 2 = 100 Nos./day
PCU / day (Nos. of car x 1) = 100 x 1 = 100 PUC/day
Frequency of two wheelers (Nos. of two wheelers x cycle x up and down) = 400 x 1 x 2 = 800 Nos./Day
PCU/Day (Nos. of two wheeler x 0.5) = 800 x 0.5 = 400 PUC/Day
Total PCU/Day= 400 +100 = 500
PCU per hour = 20.80
Grand Total PCU/Hr. (A+B) = 46.50 + 20.80 = 67.30 PCU/Hr.
Table 4.21 - Modified Traffic Scenario and LOS
# Road Increased
PCUs Modified V C
Modified V/C
Ratio
Modified V/C Ratio
1. SH-16 67.30 x 20%
=13.46 505+13.46 = 518.46 1250.00 0.41 C
The LOS value from the project will be the almost same as before i.e.“C” “Good” for the National
highway and “C” “Good” for the State Highway falling in the study area. So, the additional load on the
carrying capacity of the concern roads is not likely to have any significant adverse effect.
Company has planned to undertake following mitigation measures for reducing impact:
Regular water sprinkling will be done and all vehicle will be of valid PUC Certified.
The high traffic congestion during peak hours only; hence the movement of trucks will be
minimized in peak hours.
The commitment “Traffic movement will not be done in Peak hours” will be included in our
policy.
All Truck drivers will be trained for the traffic rules and traffic movement.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 110 2018_ECSS_EIAI1_1800028
Air Quality Index
The Minister for Environment, Forests & Climate Change Shri Prakash Javadekar launched The National
Air Quality Index (AQI) in New Delhi on 17thSeptember 2014 under the Swachh Bharat Abhiyan. It is
outlined as „One Number- One Colour - One Description‟ for the common man to judge the air quality
within his vicinity. The index constitutes part of the Government‟s mission to introduce the culture of
cleanliness.
Air Quality Index (AQI) is one such tool for effective dissemination of air quality information to people.
For the same an Expert Group comprising medical professionals, air quality experts, academia,
advocacy groups, and SPCBs was constituted to conduct a technical study by IIT Kanpur. IIT Kanpur
and the Expert Group recommended an AQI scheme in 2014.
There are six AQI categories, namely Good, Satisfactory, Moderately polluted, Poor, Very Poor, and
Severe. The proposed AQI will consider eight pollutants (PM10, PM2.5, NO2, SO2, CO, O3, NH3, and Pb)
for which short-term (up to 24-hourly averaging period) National Ambient Air Quality Standards are
prescribed. Based on the measured ambient concentrations, corresponding standards and likely health
impact, a sub-index is calculated for each of these pollutants. The worst sub-index reflects overall AQI.
AQI to be calculated by using the pollutant concentration data, the following table, and the following
equation (linear interpolation):
Where,
Ip = the index for pollutant p
Cp = the rounded concentration of pollutant p
BPHi = the breakpoint that is greater than or equal to Cp
BPLo = the breakpoint that is less than or equal to Cp
BPHi = the breakpoint that is greater than or equal to Cp
IHi = the AQI value corresponding to BPHi
ILo = the AQI value corresponding to BPLo
AQI is divided into six categories
Table 4.22 - AQI Index
Air Quality index (AQI) values
Levels of health concern
Description Color
0 – 50 Good Minimal Impact Dark Green
51 - 100 Satisfactory Minor breathing discomfort to
sensitive people Light Green
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 111 2018_ECSS_EIAI1_1800028
101 – 150 Moderate Breathing discomfort to the
people with Lung, heart disease, children and other adults.
Lemon Yellow
151- 200 Poor Breathing discomfort to people
on prolonged exposure Yellow
201 – 300 Very Poor Respiratory illness to the people
on prolonged exposure Red
301 - 500 Severe Respiratory effects even on
healthy people. Brown
Source: Central Pollution control board series CUPS/8z/2014-15
Table 4.23 - AQI Values for Different Parameters
S. No.
Locations SUB INDEX
AQI PM10 PM2.5 SO2 NO2 CO
1. Project site 80 69 18 24 61 80
2. Rupana 77 66 16 22 28 77
3. Sotha 80 69 17 23 29 80
4. ChakGiljiwala 78 68 16 23 29 78
5. Barkandi 74 65 16 22 25 74
6. Goniana 71 64 16 21 24 71
7. Muktsar 75 64 16 22 26 75
8. Bhangchiri 71 62 17 22 24 71
AQI of 8 locations is recorded satisfactory in study area. The AQI for all 5 parameters has been
calculated for running 8-hr averages. It can be seen that for pollutants air quality is good or
satisfactory.
From the above representative table of air quality index for 10 km radius of project site,
responsible parameter for pollution is PM10. Maximum AQI and responsible parameter for
pollution are recorded in project area are PM10& PM2.5 with satisfactory pollution.
Air Modeling
To identify the incremental load on ambient air quality, it is necessary to assess the impact of existing
ambient air quality with respect to the proposed emission. In order to predict the impact of air pollutants
on ambient air quality, the incremental Ground Level Concentration (GLC) has been computed using
Industrial Source Complex – Short Term (AERMOD) model, which is a steady-state Gaussian plume
model.
The stack is considered as point source to predict impact on ambient air quality during operational
phase. The prediction has been done by using AERMOD View model prescribed by CPCB/MoEF&CC.
About the Software
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 112 2018_ECSS_EIAI1_1800028
The American Meteorological Society/Environmental Protection Agency Regulatory Model Improvement
Committee (AERMIC) was formed to introduce state-of-the-art modeling concepts into the EPA's air
quality models.
AMS/EPA Regulatory Model (AERMOD) is a steady-state plume model. It is designed to apply to source
releases and meteorological conditions that can be assumed to be steady over individual modeling
periods (typically one hour or less). AERMOD view has been designed to handle the computation of
pollutant impacts in both flat and complex terrain within the same modeling framework.
AERMET is an input data processor that is one of the regulatory components of the AERMOD modeling
system. It incorporates air dispersion based on planetary boundary layer turbulence structure and
scaling concepts.
Meteorological Parameters
Surface meteorological data at project site was collected for summer season, 2018. The hourly
meteorological data considered during this period were:
Wind speed;
Wind direction;
Ambient atmospheric temperature;
Cloud cover;
Relative Humidity
Following parameters were considered for dispersion modeling – Point source:
Emission rate of pollutants
Stack details as listed below:
Internal diameter at top of stack;
Height of stack;
Exit gas velocity;
Exit gas temperature.
Meteorological data for the project area has been obtained for the period starting from December 2018
to February 2019. To assess the impact of air emissions from various continuous point sources, air
dispersion modeling study has been conducted with the help of AERMODversion 8.9.0 model of Lakes
Environmental Software. Detailed description has been given as below:
Predicted GLC due to Proposed Project: The main source of air pollution isdue to the operation of the
plant is the Boiler stack. The contribution to GLCs for the pollutants i.e. particulate matter, SO2 and NOx,
were predicted over the study area proposed project considering the worst scenario.
Receptor Locations: Total 8 receptors were generated with a polar grid from the entre of the proposed
project and extended to 10 km. Apart from these receptors; the sampling locations were also taken into
account to assess the incremental load on the baseline environmental scenario.
Stack Emission Details:Values of all parameters related to emission characteristics include:
Exit gas temperature and velocity
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 113 2018_ECSS_EIAI1_1800028
Stack top diameter and height from ground level
Site specific and monitored details considered for input data
The emissions from the boiler operated using fuel have been estimated using the emission factors
suggested in various references. Details of emission source (furnaces), stacks and estimated emissions
from the stacks are given below:
Table 4.24 - Stack Data for Air Modeling
Equal Concentration Contour Plots (Isopleths): The proposed air emissions of various parameters
i.e. PM, SO2 and NOx have been stimulated in AERMOD models and based on the final output contour
of maximum ground level concentration for sampling location are plotted. Isopleths of each parameter
are depicted as Figure 4.2 to 4.4.
S. No. Stack attached to
Height of stack (m)
Diameter at top (m)
Velocity and temperature
(m/sec) of exit gas (°C)
Emission Conc. Air Pollution Control
Equipment
1 Power Boiler- 75 TPH
65 meter height 2.8 meter diameter
8 m/sec and 140 °C
PM< 150 mg/Nm3
SO2 : <100 ppm NOX : < 50 ppm
Electrostatic Precipitator (ESP)
2 Recovery boiler-75TPH
65 meter height 2.8 meter diameter
12 m/sec and 140 °C
PM< 150 mg/Nm3
SO2 : <100 ppm NOX : < 50 ppm
Electrostatic Precipitator (ESP)
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 114 2018_ECSS_EIAI1_1800028
Figure 4.2 - Isopleths for Concentration of PM
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 115 2018_ECSS_EIAI1_1800028
Figure 4.3 -Isopleths for Concentration of SO2
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 116 2018_ECSS_EIAI1_1800028
Figure 4.4 - Isopleths for Concentration of NOx
Summary of Predicted GLC’s
The summary of maximum ground level concentrations (GLC) for the proposed project is listed in Table
4.25.
Table 4.25 - Resultant Concentration Value
Location Background Average Conc.
(µg/m3)
Incremental Conc.
(µg/m3)
Resultant Conc.
(µg/m3)
PM µg/m3 (Permissible Limit :100 µg/m3)
Project site 80.3 1.09 81.39
Rupana 77.0 0.99 77.99
Sotha 79.8 0.56 80.36
ChakGiljiwala 78.0 0.50 78.5
Barkandi 74.3 0.35 74.65
Goniana 70.9 0.49 71.39
Muktsar 75.0 0.57 75.57
Bhangchiri 70.7 0.33 71.03
SO2 µg/m3 (Permissible Limit :80 µg/m3)
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 117 2018_ECSS_EIAI1_1800028
Location Background Average Conc.
(µg/m3)
Incremental Conc.
(µg/m3)
Resultant Conc.
(µg/m3)
Project site 14.5 1.91 16.41
Rupana 13.0 1.74 14.74
Sotha 13.5 0.99 14.49
ChakGiljiwala 13.1 0.88 13.98
Barkandi 12.7 0.63 13.33
Goniana 12.5 0.87 13.37
Muktsar 12.9 1.00 13.9
Bhangchiri 13.2 0.58 13.78
NOx µg/m3 (Permissible Limit :80 µg/m3)
Project site 19.3 0.44 19.74
Rupana 17.6 0.40 18
Sotha 18.3 0.23 18.53
ChakGiljiwala 18.0 0.20 18.2
Barkandi 17.4 0.14 17.54
Goniana 17.0 0.20 17.2
Muktsar 17.4 0.23 17.63
Bhangchiri 17.8 0.13 17.93
Interpretation
When predicted 24 hourly ground level concentrations of PM, SO2 and NOx emissions from the source is
added to background maximum monitored values, resultant values remain well below the prescribed
National Ambient Air Quality Standards at all the locations. Hence, there is no significant impact is
anticipated on the ambient air quality of the area due to the proposed project.
As part of precautionary measure, to minimize the likely environmental impacts on air environment due
to the proposed project, necessary mitigation measures are also described in the chapter.
Table 4.26 - Impact and Mitigation Measures on Air Environment
ProjectActivity Impact Mitigation Measures
Transportation of Raw
Materials and Products
PM, SO2 and NOx will be
generated from vehicular
movement.
Impact on human health due to
accidental release of raw
Vehicles with valid PUC Certified
vehiclesis being/will be used for
the transportation of materials and
Machinery.
The trucks used for transporting
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 118 2018_ECSS_EIAI1_1800028
materials into the atmosphere.
Agricultural crops can be
affected due to high
concentration of various air
pollutants.
the goods are being/will be
covered by the tarpaulin and
overloading in trucks shall not be
allowed to prevent the dusting.
Additional greenbelt will be
developed in and around the
project premises area, around the
storage yards and along the roads
to minimize the fugitive dust
generation.
Storage & handling of
Raw material & Product
Dust emissions from handling
of raw material
loading/unloading operations.
Impact on human health due to
accidental release of raw
materials into the atmosphere.
Good material handling practices
will be carried out.
Regular water sprinkling will be
done on roads to avoid dust
generation from handling.
Fuel Handling Dust generation during
loading/unloading of Rice Husk
will affect the respiratory tract
of living beings.
High amount of dust generation
will have impact on plants and
will reduce their stomatal index
The trucks used for transporting
the goods will be covered by the
tarpaulin and overloading in trucks
shall not be allowed.
Rice Husk will be stored properly.
For transportation of Rice Husk to
the boiler closed conveyor belt will
be provided.
The sprinkling of water will be
done along the internal roads in
the plant in order to control the
dust arising due to the movement
of vehicular traffic.
Good material handling practices
will be carried out.
Operation of CPP Ash generation can increase fly
ash dust in the premises and
reduce crop yield.
Generation of air pollutants like
Particulate Matter (PM) into the
atmosphere.
From the air quality modeling it
can be predicted that air quality
impacts are minimum on the
Highly efficient four fields ESP is
being/will be provided to reduce
the particulate matter emissions
from the boiler.
Adequate stack height is being/will
be provided for adequate
dispersal of pollutants.
Fly Ash will be stored in silo and
disposed off for reusing in cement
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 119 2018_ECSS_EIAI1_1800028
surrounding population as
maximum concentration will be
predicted at E direction at 1.95
km, where there is no village.
industry.
Fly ash is being/will be stored in
silo and directly fill up in
transportation vehicles through
pneumatic ash conveying system.
Ash is being/will be transported by
closed bulkers/full body trucks
duly covered after loading to
potential users.
Moreover, from air modeling
study, it has been proved that the
air emission from the proposed
project will not increase in
significant manner.
4.2.3 Water Environment
Table 4.27 - Impact and Mitigation Measures on Water Environment
ProjectActivity Impact Mitigation Measures
Resource utilization Resource depletion due to
water consumption/ withdrawal
from surface water source.
Water is being/will be obtained
from Arniwala Canal,hence no
impact on ground water is
envisaged.
Fuel handling Particulate matter from Rice
Husk handling and
transportation will affect the
nearby water body.
Good Rice Husk handling
practices will be carried out.
Covered trucks will be used for
Rice Husk transportation.
Manufacturing Process
Operation of CPP
High quantity of water will be
used in manufacturing process
and Captive Power Plant
operation.
Adverse Impact due to
resource deletion.
Industrial effluent will treated in
ETP and Partly treated water will
be reused in Manufacturing
process and remaining will be
discharged CETP for further
treatment and ultimate disposal
to deep Sea through GIDC
disposal pipeline.
Water consumed in CPP will be
optimized to maximum possible
COCs to reduce overall water
consumption.
Evaporation losses from the CPP
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 120 2018_ECSS_EIAI1_1800028
will be minimized by energy
efficient coolers/condensers and
evaporators.
Domestic wastewater
generation
Industrial wastewater
generation
Domestic and industrial waste
water generation.
Water quality of rain water may
get degraded due to mixing of
wastewater with rainwater due
to run off.
Nearby surface water will get
polluted due to disposal or
spillage/leakage/runoff of the
wastewater into the water
body.
Sewage is/will be treated in STP.
Separate and Closed drainage
pipes with proper lined surfaces
is being/will be laid down for the
drainage network for rainwater
runoff.
Water will be reused at maximum
extend and remaining treated
water is being/will be will be used
of cultivation.
Solid/Hazardous waste
Disposal (ISW, HSW,
MSW)
Impact of poor solid waste
management on ground water.
The leachate produced from
waste storage site contains
harmful substances which are
likely to contaminate ground
water.
Mixing of solid waste (fly ash)
will adversely impact on
physico-chemical
characteristics of surface
water.
All the wastes is being/will be
handled and disposed according
to the Waste Management
Rules, 2016.
Wastes is being/will be stored in
adequate storage yard with
paved/lined surfaces.
Fly ash is being/will be stored in
silo and directly fill up in
transportation vehicles through
pneumatic ash conveying
system.
Fly ash is being/will be always
kept in moist condition so that
particles of the same will not
travel at large distance.
Good waste management and
handling practices is being/will
be adopted for waste
management.
4.2.4 Soil Environment
Table 4.28 - Impact and Mitigation Measures on Soil Environment
ProjectActivity Impact Mitigation Measures
Storage of Material Soil contamination due to Prevention of oil & grease/fuel
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 121 2018_ECSS_EIAI1_1800028
spillage and leakage from
storage of materials.
getting mixed with soil.
Earmarked separate storage yard
with paved/lined surfaces is
being/will be provided for storage
of fuel and other raw material.
Good practices for storage and
material handling will be followed.
Leachate from the storage area
will be sent to collection tank of
ETP for treatment and dilution of
the same.
Domestic wastewater
generation
Domestic wastewater
contains high amount of
organic matter, nutrients and
some heavy metals which
mix in soil and their high
quantity is toxic to plants
beyond a certain limit.
Domestic sewage is being/will be
treated in STP.
Industrial wastewater
generation
If untreated industrial effluent
will be discharged directly
disposed on land or water
body they can disrupt
physicochemical properties
of soil.
Total industrial Waste Water
Generation will be 21412 KL/Day,
which is being/will be treated in
adequate existing primary and
secondary effluent treatment plant
and finally treated effluent will be
used for cultivation.
Solid waste Disposal Soil degradation due to
waste disposal.
Sludge generation from
effluent treatment plant.
Wastes are being/will be stored in
adequate storage yard with
paved/lined surfaces.
ETP Sludge is being/will be
discarded by selling to cardboard
manufacturers.
Wastes is being/will be handled/
disposed according to the Waste
Management Rules, 2016.
Due to absence of any wet ash
storage facilities at site, soil and
ground water contamination related
risks due to handling of ash at the
site are not envisaged.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 122 2018_ECSS_EIAI1_1800028
4.2.5 Noise Environment
Table 4.29 - Impact and Mitigation Measures on Noise Environment
ProjectActivity Impact Mitigation Measures
Transportation of
Materials & Manpower
Noise generation from rotating
equipment decreases the
efficiency of a man and causes
lack of concentration and
Blood Pressure.
Loud noise from the turbine of
CPP may pose health hazards
to the workers working nearby.
Transportation activity is
being/will be carried out only
during day time.
Valid PUC Certified vehicles is
being/will only be used.
Regular maintenance &
lubrication of equipment/
vehicles are being/will be
carried out.
Provision of ear muffs and ear
plugs to prevent continuous
noise exposure risk to
employees working on site.
Acoustic enclosures are
being/will be provided whenever
possible.
Rubber padding is being/will be
provided with pumps and
motors to reduce the vibration.
Operation of CPP
Manufacturing
process
Noise at work can harm
worker‟s health. The most well-
known effect of noise at work
is loss of hearing.
Earmuffs, earplugs is being/will
be provided to workers.
4.2.6 Land Use/Land Cover
Table 4.30 - Impact and Mitigation Measures on Land Cover/ Land Use
ProjectActivity Impact Mitigation Measures
The proposed expansion will be carried out in already acquired 38527m2 adjoining land.
4.2.7 Hydrogeology
Table 4.31 - Impact and Mitigation Measures on Hydrogeology
ProjectActivity Impact Mitigation Measures
Resource Utilization Resource depletion due to water
consumption/ water withdrawal
Water is being/will be obtained
from Arniwala Canal.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 123 2018_ECSS_EIAI1_1800028
from surface water. Water conservation measures
will be undertaken.
Rain water harvesting is
being/will be carried out for
reuse of water for ancillary
purposes will give positive
impact.
4.2.8 Geology
Table 4.32 - Impact and Mitigation Measures on Geology
ProjectActivity Impact Mitigation Measures
No impact on geology will be there.
4.2.9 Solid/Hazardous Wastes
Table 4.33 - Impact and Mitigation Measures due to Solid/Hazardous Wastes
ProjectActivity Impact Mitigation Measures
Operation of CPP
Manufacturing Process
Recruitment
Domestic wastewater
generation
Industrial Wastewater
generation
Solid waste Disposal
Waste generation and
problems due to improper
management, handling and
disposal of Solid/hazardous
waste.
Handling and disposal of used
oil, discarded containers, fly
ash, plastic waste, fiber
sludge, de-inking sludge, ETP
sludge.
Waste minimization practices
will be adopted.
Wastes is being/will be stored
in separate earmarked storage
area.
ETP sludge from wastewater
treatment is being/will be
disposed by selling to
cardboard
Fly ash shall be sold to brick
manufacturing unit for co
processing.
Since no wet ash handling
methods will be adopted at the
proposed at the proposed
facility, ash pond is not
envisaged.
All the wastes is being/will be
handled/ disposed according to
the Waste Management Rules,
2016.
Storage Impacts on environment due to Implementation of good waste
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 124 2018_ECSS_EIAI1_1800028
Coal Handling spillage/leakage, dust
generation during handling,
transportation and storage of
materials.
handling practice will be done.
Separate earmarked storage
area with pacca floor/lining will
be provided for the waste
storage.
Closed area/ covered area will
be provided for storage of coal.
Solid waste management plan
has been prepared and
followed strictly. Same practice
will be followed after
expansion.
Ash handling Impacts on environment due to
fugitive emission generation
during handling, transportation
and storage of ash.
Regular sprinkling and wetting
of ash shall be done.
Ash is being/will be stored in
closed silo as existing practice.
4.2.10 Risk & Hazards
Table 4.34 - Impact and Mitigation Measures due to Risk & Hazards
ProjectActivity Impact Mitigation Measures
Transportation of
Materials & Manpower
Storage & handling of
Raw material & Product
Chances of accident due to
vehicle collision
Injury to manpower during
handling and storage
All transportation is being/will
be carried out directly under
the supervision and control of
dedicated team.
First aid kits and training is
being/will be imparted to the
workers/employees.
Fire Extinguishers is being/will
be provided.
Good material handling
practices will be implemented.
Workers is being/will be
provided with adequate PPEs
like safety shoes, helmets and
gloves while working in storage
area to safeguard them against
potential risks.
Health checkups are being/will
be organized at regular
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 125 2018_ECSS_EIAI1_1800028
intervals.
Operation of CPP
Coal Handling
Fire and explosion may occur. Fully automatic system will be
installed for CPP operation.
Spark arrestors will be placed
at potential places of fire
hazard for early detection of
spark.
Fully equipped fire-fighting
system will be provided.
Onsite and Offsite DMP will be
in place to deal with any
emergencies.
Smoking is being/will be strictly
prohibited in fire sensitive area.
Manufacturing Process Accidents due to machinery
failure/improper function of
machineries.
Accidents due to
carelessness/less attention of
workers during plant operation.
Fire Extinguishers are
being/will be provided.
Safety Training is being/will be
provided to the employees.
For working in the machine
area, strict adherence to SOPs
is being/will be implemented.
Workers are being/will be
provided with adequate PPEs
like safety shoes, helmets and
gloves while working in
manufacturing area.
A budget of approx. Rs.
50Lakh is allotted for OH&S.
4.2.11 Ecology and Biodiversity
Table 4.35 - Impact and Mitigation Measures due to Ecology and Biodiversity
ProjectActivity Impact Mitigation Measures
Transportation of
Materials & Manpower
Fugitive emission from vehicle
movement will form a layer in
leaves thus reducing the
gaseous exchange process.
All transportation within the main
working is being/will be carried
out directly under the
supervision and control of the
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 126 2018_ECSS_EIAI1_1800028
This ultimately affects the
growth of plants.
Also, common animals found
in the study region may get
affected by the dust and
gaseous emission from
transportation activity.
management.
Good material handling
practices is being/will be
followed.
Vehicles with valid PUC
Certificate will only be allowed
within the premises.
Vehicles is being/will be strictly
instructed to follow traffic rules
and speed limits. Traffic violators
will be penalized.
Green belt will be encouraged to
mitigate the emission level.
Plantation will be carried out on
approach roads and nearby
vicinity.
Budget of Rs. 20-30 Lakhsis
allotted for green belt
development and maintenance.
Resource Utilization Utilization of water resources
will create a stress impact on
the surface water source,
thereby indirectly impacting the
flora and fauna.
Water is being/will be obtained
from Arniwala Canal.
Water conservation measures
and reusing of the same will be
undertaken for reduction in
water quantity to be consumed.
Water consumed in CPP will be
optimized to maximum possible
COCs to reduce overall water
consumption.
Evaporation losses from the
CPP will be minimized by energy
efficient coolers/condensers and
evaporators.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 127 2018_ECSS_EIAI1_1800028
Industrial wastewater
generation
Wastewater discharge from the
proposed activity can
contaminate the soil and
ultimately effect the growth of
plants.
Wastewater will be damage
aquatic as well as terrestrial
habitat if discharge without
treatment.
Domestic wastewater is/will be
treated in STP.
Industrial effluent will be treated
in the ETP and treated water will
be used for cultivation.
Treated effluent will be disposed
through closed pipeline.
4.2.12 Socio-Economic
Table 4.36 - Impact on Socio Economic and Mitigation Measures
Potential Aspect Impacts Mitigation Measures
Transportation of
Materials &
Machinery
Manufacturing
process
Operation of CPP
Coal handling
Increase in transportation
vehicles and traffic near the
connected roadways.
Thus, impacts on surrounding
population due to traffic
congestion, increased noise
and air emissions from
vehicles.
Vehicles with valid
PUCCertificateare being/will
be used for the transportation
of materials and Machinery.
No manual handling of rice
Husk,closed conveyor belt will
be provided.
Implementation of Good
material handling practices.
Mitigation measures suggested
for noise and air environment
will be strictly followed.
PPEs are being/will be
provided to workers.
Resource utilization
24000 KLD of fresh water
requirement during the
operation phase.
Land requirement due to
proposed project.
Power requirement during the
operation phase
Water is being/will be obtained
from Arniwala Canal.
Land requirement for proposed
project is already in the
possession of proponent and
hence no new land will be
procured.
Existing power is obtained
from in house CPP and
PSPCL, after proposed
expansion power will be
obtained from CPP.
Industrial wastewater Problems associated with the Effluent is being/will be
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 128 2018_ECSS_EIAI1_1800028
generation disposal of 21412 KLD of
effluent, indirectly affecting the
water body where ultimate
disposal takes place.
treated in Effluent Treatment
Plant (ETP).
Recruitment Direct and indirect employment
generation due to proposed
project and related service
sectors.
Local people of nearby villages
will benefit from the CSR
activities to be undertaken by
the proponent.
During the operation phase
around 500 nos. of people get
direct recruitment.
Preference will be given to
local people during the
operation phase.
Local service providers may
be appointed for allied works
and services
All the CER activities will be
based on the
needs/requirements of the
local people
CER plan has been designed
keeping in mind the socio-
economic status of the local
people
A budget of Rs. 375 lakhs has
been allocated for welfare
activities of nearby villages.
Most of the welfare activities
will be aimed at providing
funds towards infrastructure
development for child and girl
education, health, hygiene,
and skill development.
Table 4.37 - Environmental Impact Matrix with Mitigation (Operation Phase)
Activities
Environmental Attributes
Air
Wa
ter
So
il
No
ise
LU
/LC
Hy
dro
geo
log
y
Ge
olo
gy
SH
W
Ris
k &
Ha
zard
EB
So
cio
Ec
on
om
ic
To
tal
Transportation of Materials & Machinery
-6 - - -4 - - - - -4 -1 -2 -17
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 129 2018_ECSS_EIAI1_1800028
Storage & handling of Raw material & Product
-2 - -2 - - - - -1 -2 - - -7
Resource Utilization - -2 - - - -2 - - - -1 -2 -7
Fuel Handling -4 -4 - - - - -1 -2 - - -11
Operation of CPP -6 -8 - -8 - - - -4 -4 - - -30
Manufacturing Process -4 -4 - -2 - - - -2 -2 - - -14
Domestic wastewater generation
- -2 -2 - -1 - - - - - - -5
Industrial wastewater generation
- -4 -2 - -1 - - -1 - -2 -1 -11
Solid Waste Disposal (ISW, HSW, MSW)
- -2 -1 - - - - -2 - - - -5
Recruitment - -1 - -1 - - - -1 - - +35 +32
Total -22 -27 -7 -15 -2 -2 0 -12 -14 -4 +30 -75
Total Cumulative Score for various Environmental Parameters with implementation of adequate mitigation
measures is -75 during operation phase which indicates that there will not be any significant adverse
impact on the environment.
4.3 SUMMARY
The proposed project has no major adverse impact on surrounding environment. The CPP will be
equipped with 99.9% efficient four field ESP for mitigation of air pollutant sources. Hazardous waste will be
sent to TSDF facility, authorized recyclers and refiners. Appropriate construction & operation techniques
will be implemented to minimize the impacts on the environment. Proper upkeep and maintenance of
vehicles and APCM will reduce the impact on air environment. Adequate arrangements for waste disposal
from ETP will be undertaken. Greenbelt will be developed in surrounding of plant and common land.
Budget of Rs. 20-30 Lakhs is allotted for green belt development. A budget of Rs. 15crores capital and Rs.
1 crores recurring cost for EMP. Positive impact is envisaged on Socio economic environment. The
allocated budget for CER has been prepared of Rs. 375 Lakhs for development of local populace. Proper
PPEs will be provided to all the workers& budget of approx. Rs. 50 lakhsis allotted for OH&S.
-------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 130 2018_ECSS_EIAI1_1800028
CHAPTER – 5
ANALYSIS OF ALTERNATIVES (TECHNOLOGY &
SITE)
5.0 GENERAL
As the proposed project is capacity enhancement project, alternative site has not been considered.
Since, by nature, the project is an expansion project, the existing premises of operational unit is the most
convenient site for the expansion project. Moreover, all the utilities and infrastructure facilities are
available in the present set up. Hence, the existing premise with available infrastructure and ease of
operation is the best option available for the expansion.
5.1 Alternative for Sites & other Aspects
Some alternatives considered during EIA study are discussed below:
Table 5.1 - Alternative for other Parameters
S.
No. Particular
Alternative
Option 1
Alternative
Option 2 Remarks
1. Site Selection Existing Site New Site Existing site is preferred.
Benefits:
Existing land already in
possession of proponent
Plant has acquired additional
land for proposed expansion.
All common infrastructure
and utilities of existing unit
can be shared.
Site selection criteria are
given in 2.3.2 in chapter-2.
2. Technology Agro based
&Wood based
Waste paper
based
Agro residue based technology
is/will be preferred.
Benefits:
Easy availability of agro
residues in this region
Economical operational cost
Addresses stubble burning
issue
Conserving depleting forest
cover.
Environmental friendly
compared to wood based.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 131 2018_ECSS_EIAI1_1800028
3. Employment Local employment Outsource
employment
Local employment is/will be
preferred.
Benefits:
Provides employment to local
people along with financial
benefit.
No residential
building/housing is required.
Improvement of socio
economic status of the region.
4. Labour
Transportation
Public transport Private transport Private transport is/will be
preferred.
Local labours will be deployed
so they will either reach plant by
bicycle or by foot or by own
vehicle.
Benefits:
Cost of transportation for men
will be negligible.
5. Raw Material
and Product
Transportation
Public transport Private transport Private transport is/will be
preferred.
Material will be transported
through trucks on the contract
basis using private transport.
Benefits:
It will give indirect
employment
6. Water
Requirement
Arniwala Canal
water
Groundwater Surface Water withdrawl from
Arniwala Canal is preferred
against groundwater. It is
situated at a distance of approx.
2.5 km from the industry
Benefits:
No ground water
resource depletion.
TDS level is low in
comparison to
groundwater
Ample quantity available
in canal
7. Power
Requirement
Captive power
plant
Electricity
Board
Captive power plant
Benefits:
Transmission losses from
power station are avoided.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 132 2018_ECSS_EIAI1_1800028
Cost is low as the CPP serves
dual purpose i.e. power
requirement and steam
requirement.
8. Road Pakka road Kachcha road Pakka Road
Road is already developed for
existing Unit.
5.2 SUMMARY
No alternative site has been proposed for the proposed expansion project because expansion will be
done at existing premises only and all the infrastructure are readily available for industrial development.
However, some alternatives were considered for planning and designing of the various facilities
proposed at the proposed expansion.
.
------------------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 133 2018_ECSS_EIAI1_1800028
CHAPTER – 6
ENVIRONMENTAL MONITORING PROGRAM
6.1 GENERAL
Environmental monitoring is the measurement of environmental parameters at regular intervals over an
extended period of time. Monitoring allows the assessment of environmental and biological changes in
an ecosystem. All the project activities shall be monitored to ensure that appropriate environmental
mitigation activities are being implemented and to identify areas where Environmental Management
Plan compliance is not satisfactory. Hence, Environmental quality monitoring of critical parameter is
very essential in the routine activity schedule of project operation. An Environmental Monitoring
Programme shall be scheduled for the following major objectives:
To verify the result of the impact assessment study in particular with regards to new developments.
To follow the trend of parameters which have been identified as critical.
To check or assess the efficiency of controlling measures.
To monitor effectiveness of control measures.
Regular monitoring of environmental parameters to find out any deterioration in environmental
quality.
6.2 NEED FOR ENVIRONMENTAL MONITORING
Environmental monitoring is critical to knowing whether the quality of our environment is getting better
or worse. Information gathered through environmental monitoring is important to many different
decision makers.
6.3 MONITORING PLAN & PROGRAM
Environmental Monitoring Schedule of Existing Facilities followed by SIL:
The Post Project Monitoring (PPM) plan is prepared considering the following:
i. The proposed pollution control measures for air, liquid effluents and solid waste disposal;
ii. The monitoring requirements for ensuring the statutory as well as process data; and
iii. The organizational/institutional set-up required for effective environment management plan
implementation and post-project monitoring along with the laboratory development, manpower
and budgetary requirements
The stack monitoring is being carried out at regular interval internally and by deputing outside
approved pollution control laboratory. Discharge effluent monitoring is carried out on daily basis in the
in-house laboratory.
Air Environment
Regular ambient air quality monitoring system is recommended for analyzing the variations in ground
level concentrations.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 134 2018_ECSS_EIAI1_1800028
Satia Industries Ltd. can carry out the post project monitoring work on its own or by hiring services of
a competent agency. M/s Satia Industries Ltd. also desires to carry out the post project monitoring on
its own.
Existing Continuous Emission Sources at SIL
The following two types of stacks were monitored for emissions and its characteristics:
i. Rice husk fired boilers.
ii. Black liquor fired boiler
Results of emission monitoring are given in Table 6.1 and discussed below:
The main air pollutant emitted by above sources at SIL is SPM.
Emissions were monitored at the port holes on stacks with the help of stack monitoring kit capable to
draw samples under iso-kinetic conditions. SPM samples were collected in cellulose thimbles and
gaseous pollutants were first absorbed into appropriate absorbing media and then analyzed by
colorimetric/volumetric methods. Standard procedures as per ISI/APHA/EPA were followed.
Emission Characteristics of Boilers
Rice husk fired boiler is the main contributors of SPM which were observed to be 78.04 mg/Nm3 from
the stack provided with ESP. The concentrations of all pollutants were in compliance to the limits
prescribed by PPCB.
Table 6.1: Monitored Stack Emission Characteristics
# Stack Details 50 TPH Boiler
50TPH
Recovery
Boiler
75TPH
Power
Boiler
75 TPH
Boiler
1. M.O.C. M.S. R.C.C. R.C.C. R.C.C.
2. Internal diameter (m)
Top 2.5 2.5 2.8 2.8
Bottom 2.8 5.5 2.8 2.8
3. Height (m) from
ground level 50 65 m 65 m 65 m
4. Fuel Consumption Rice Husk Black Liquor Rice Husk Rice Husk
270 TPD 400TPD 400 TPD 400 TPD
5. SPM (mg/N m3) 75 95 78 90
Noise Environment
Monitoring of noise levels are essential to assess the efficiency of maintenance schedules and noise
protection measures undertaken.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 135 2018_ECSS_EIAI1_1800028
A good quality audiometric sound pressure level meter will be essential for this purpose. Audiometric
test is also helpful in monitoring the effectiveness of ear protection devices and of noise abatement
programmes. The assessment should be performed under the supervision of health officials.
Water Environment
Wastewater should be analyzed regularly for the parameters of concern as stipulated by Punjab
Pollution Control Board (PPCB) is given below
pH
Dissolved Oxygen
Chemical Oxygen Demand (COD)
Bio-chemical Oxygen Demand (BOD)
Oil and Grease
Total Suspended Solids
AOX
Following sampling locations are monitored periodically:
Influent to wastewater to treatment plant.
Inlet and outlets of individual treatment units.
Final effluent before reuse or disposal
Daily analysis of influent and effluent of wastewater treatment plant is recommended during
commissioning. Sampling and analysis of wastewater from individual treatment units, depending on
type of treatment facility provided, may be carried out for relevant parameters once in a month.
Composite samples should be prepared by collecting half hourly samples for characterizing
wastewater. Methods of sample collection and preservation will be as per IS: 2488.
The samples of effluents at various steps of treatment are collected and analyzed as follows:
Characteristics of Final Effluent
The samples of treated effluent were collected from effluent channel during the study period and were
analyzed for pH, BOD, COD, TS, TDS and TSS. The pH of the final effluent was found to be 7.2-7.4.
The COD and BOD in the final effluent was less than the prescribed value of 250 mg/l and 30 mg/L
respectively. Results of effluent treatment are given in Table 6.2.
ETP is operated & maintained properly. Outgoing effluent was observed to be complying with the
prescribed limits. The existing ETP is capable of handling and treating the effluent generated after the
proposed expansion of the plant.
Table 6.2: Effluent Characteristics
# Parameter Unit Biogas Plant Bleach Combined Final
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 136 2018_ECSS_EIAI1_1800028
Inlet Outlet Influent Influent Effluent
1. Flow m3/day 6927 6927 12994 21,499 21,499
2. pH - 6.7-6.9 7.0-7.2 7.0-7.5 7.2-7.3 7.2-7.3
3. BOD ppm 700-800 250-300 550-650 500-550 25-30
4. COD ppm 2600-2800 700-800 1400-1500 1200-1300 225-250
5. TDS ppm 1600-1800 1600-1800 1600-1800 1600-1800 1600-1800
6. TSS ppm 2000-2500 200-250 200-300 250-300 40-50
7. Oil &
Grease mg/L - - - - < 2
Laboratory
An independent environmental laboratory with facilities for chemical analysis is already in operation. A
separate air-conditioned dust-proof room exists for analytical instruments. The laboratory is equipped
with instruments so that pH, suspended solids, oil and grease, BOD and COD and air pollutants are
analyzed.
Land Environment
The ground water and top soil in the neighboring areas should be analyzed for the relevant
parameters presented under the baseline information at least once in six months. The average
canopy height of the green belts, number and types of plant species should be enumerated once in
two years using suitable techniques for vegetation sampling.
This monitoring programme will help in observing the physio-chemical properties of the soil, infiltration
rates and changes in ground water quality and ground water table because the effluent is used in the
irrigation of plantation maintained by industry. Also species of birds and small animals encountered in
the improved ecosystem may be recorded. Monitoring of surface soils and waters at intervals of 5
years may provide useful guidelines for taking remedial measures, in time, for the present and future
developmental activities.
6.4 INFRASTRUCTURAL REQUIREMENT
SIL will be purchasing the necessary equipment‟s like high volume sampler, fine dust sampler and
gaseous attachment kit for the sampling of ambient air. SIL is already equipped with water testing
laboratory to carry out routine wastewater testing for BOD, COD, pH, acidity, alkalinity, TSS, TDS etc.
6.5 ENVIRONMENT MANAGEMENT CELL
An Environmental Management Group exists in the organization to look into the environmental issues
and ensure that mitigation measures are properly carried out. The Environmental Management group
comprise of General Manager, Manager, Assistant Manager, Shift Engineers and Environmental
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 137 2018_ECSS_EIAI1_1800028
Scientists. The environmental scientists and shift engineers are responsible for ensuring
environmental monitoring as per appropriate guidelines and procedures.
6.6 CURRENT & PROPOSED PRACTICES FOR ENV. PROTECTION
6.6.1 Handling of Raw Materials and Mitigation Measures
SIL has sufficient area and adopted adequate measures to mitigate transportation of existing mills
activities as well as for proposed expansion project. The mill has already provided separate areas for
loading & unloading of raw materials. Proper parking areas are also in practice for all vehicles i.e.
trucks etc. wherever required. Awareness is also inculcated among transporters to avoid overloading
of material and spillages of raw material.
6.6.2 Risk Assessment and Damage control
SIL has already identified hazards associated activities and their preventive measures to mitigate
environmental risk inside the premises & its vicinity. Toxic release / fire /explosive areas have already
been identified for risk assessment and damage control for emergency preparedness and response.
SIL is already following emergency plan, which is approved by concerned authority. A separate Safety
Department exists with Safety Officers having fire tenders/fire extinguishers.
6.6.3Compliance to the recommendations of CREP guidelines
The Central Pollution Control Board has issued a Corporate Responsibility for Environmental
Protection (CREP) for the treatment of paper plant effluent. The compliance to the provisions of CREP
is followed and is given in the (Table 6.3).
The mill is complying with the CREP conditions as per the direction of CPCB as under –
Table 6.3: Compliance to the Charter on CREP for large Pulp and Paper industry
Conditions Present status
Discharge of AOX( kg/Ton of paper)
a) AOX 1.5 kg/ton of paper within 2 years b) AOX 1.0 kg/ton of paper in 5
years
With the introduction of Oxygen Delignification (ODL), and use of Elemental Chlorine free bleaching, the discharge of AOX is maintained well
below 1kg/ton of paper production
Installation of Lime Kiln
Since MoU has been signed with UltraTech Cement (Aditya Birla Group) for reuse of Lime sludge in cement plant so installation of lime kiln is not needed immediately.
Waste water discharge ( M3/T of paper)
With the maximum use of machine backwater and various other steps.to reduce the fresh water consumption, the water discharge per ton of paper production falls well within the latest prescribed limits and is 55 m3/ton
against prescribed limit of 75 m3/ton
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 138 2018_ECSS_EIAI1_1800028
Odour control by burning the reduced sulfur emissions in the Boiler/Lime Kiln
There is no use of Sulphur containing material in our plant; hence odour control is not required.
Utilization of treated effluent for irrigation Treated effluent is being utilized for plantation.
Colour removal from the effluent Treated effluent has very little colour as it is agro based plant
Summary of Environmental improvements in the Existing Mills Consequent upon proposed
expansion:
In order to offset some of the major environment impacts from above said expansion plan, SIL will be
adopting proactive approach to further improve environment status of existing plant as follows:
i. Proper maintenance of existing and new ESP for recovery boiler and rice husk fired boiler to
achieve SPM level within permissible norms.
ii. Not much increase in existing water consumption which will be attained by reducing existing water
consumption and maximizing recirculation of back water in existing unit.
iii. Not much increase in volume of final effluent discharge.
iv. No increase in maximum contract demand of electricity from grid.
v. No new DG Sets will be installed.
6.7CONCLUDING REMARKS
The study of air emissions, ambient air quality, disposal and use of treated effluents of SIL, observed
impacts of SIL on different components of the environment, land use pattern, human settlements,
assessment of the provisions of effluent management of SIL and in view of common environmental
concerns and critical targets, and our past association following conclusions are made.
During the field data collection for the EIA study, particular attention was paid to the sources of air
emissions, ambient air quality, additional water requirements, effluent treatment and its disposal along
with likely impacts on the surrounding environment with respect to human settlements and water
bodies.
Main environmental concerns and critical targets in the case of SIL plant are identified in above
section. As the expansion at SIL is going to be achieved by replacing/ adding a few equipments so it
is not going to change the air or water environment much. The marginal increase in pollution shall be
controlled by existing pollution control equipment‟s.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 139 2018_ECSS_EIAI1_1800028
The surrounding air quality (after meeting the prescribed standards), ground water availability, quality
and surface water quality are affected to a manageable extent as far as environmental deterioration is
concerned.
Migratory, abatement, control measures and management plans in respect of likely concerns and
critical targets and their protection measures has been one of the primary concerns of this EIA report.
The conclusions on the above measures are as follows:
The suspended particulate matter from rice husk fired boilers has been controlled with the installation
of Electrostatic precipitators.
A common ecological impact of a paper plant could be from deforestation; wood being the basic raw
material. It is pertinent to mention here that the proposed expansion of the plant mainly depends on
agro residue based raw material.
For an industry with extensive use of water for its processes there always is an apprehension that the
source of water withdrawal may be adversely affected. The entire requirement of water of SIL is met
from canal water. Hence there will be no adverse impact on groundwater.
About 17.0 tonnes of ETP sludge will be recovered by SIL every day through primary clarifier, which
shall be sold to various parties for manufacturing of board. 227.3 TPD of lime sludge shall be
generated after expansion, which will be sent to cement plant for its use in cement manufacturing.
There is no environmental concern on account of handling and disposal of solid wastes. Additional
sludge generated after expansion will be easily utilized by these vendors.
There are no likely impacts of SIL on other environmental components such as meteorology,
topography and geology, fresh water ecology, terrestrial flora and fauna, amenities, mineral resources
and mining, archaeology, cultural, religious and land use. The influx of labour force, migration of
outsiders is unlikely to cause any significant socio-cultural disruptions. However, there shall be large
economic gains to the study area.
It can be seen from the assessment of impacts that the proposed operation of SIL will not have
significant impacts on the surrounding environment. Proper arrangements for proper collection and
treatment of effluents and reuse of water would not affect water environment adversely. Proper
pollution control measures proposed for boilers and recovery system would ensure that air and water
environment do not have any adverse impact. It is concluded that with the adoption of proposed
mitigation and enhancement measures, there will be improvement in the development of commercial
activities, generation of direct and indirect employment opportunities and the overall quality of life in
the surrounding area.
The findings, positive steps taken by SIL and recommendations emerging out of the Environmental
Impact Assessment studies suggest that the environmental concerns presented by SIL due to their
current operations and after expansion shall be taken care of by adequate control measures and
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 140 2018_ECSS_EIAI1_1800028
proper management plans proposed as above. Therefore, it is requested that the proposed expansion
of Satia Industries Ltd. at Muktsar for the manufacture of 600 TPD writing and printing paper from
agro based raw material along with 14 MW CPP may be accorded prior environmental clearance.
6.8 SUMMARY
Project proponent will develop an environmental and safety department, which will undertake measures
for environmental protection and mitigation of environmental impacts. Sample for environment monitoring
will be collected as per the guidelines provided by MoEFCC/CPCB /PPCB. Monitoring of environmental
parameters within the plant premises will be carried at selected location as per guideline. Hazardous
waste will be disposed/off as per Hazardous Waste Management Rules 2016. Pre-medical check-up will
also be carried out at the time of employment.
---------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 141 2018_ECSS_EIAI1_1800028
CHAPTER – 7
ADDITIONAL STUDIES
7.0 GENERAL
An additional study including Public Hearing, Risk Assessment (RA), Disaster Management Plan and
Occupational Health & Safety has been carried out for the proposed project to identify main hazards, to
review the effectiveness of selected safety measures and to expand the safety measures in order to
achieve a zero risk culture at the company. The study has been incorporated in the Environmental
Impact Assessment (EIA) report to support the Environmental Management Plan.
As per the EIA notification dated 14th September 2006, the first technical presentation i.e. the ToR
presentation was done on 20.2.2019. The MoEFCC issued the ToR‟s vide letter File. No. J-
11011/196/2014-IA II (I)] dated April 16, 2019 for expansion in production capacity from 300 to 600 TPD
writing and printing paper and 14.0 MW Co-Gen power plant. The public hearing for this proposed
expansion project will be conducted at project site, village Rupana, District –Muktsar (Punjab).
7.1 PUBLIC HEARING
As per the provisions of Notification No. S.O. 1533 dated 14/09/2006 and its subsequent amendment
S.O. 3067(E) dated 01/12/2009, Ministry of Environment and Forests, Government of India, New Delhi,
public hearing is conducted for M/s. Satia Industries Limited located at Village Rupana, District Sri
Muktsar Sahib, Punjab for proposed Expansion of Paper Production with capacity from 300 TPD to 600
TPD along with CPP of 14.00 MW. The Public Hearing held on 04/07/2019 at 12.00 pm at the main gate
of the industry located in the revenue estate of village Rupana, District Sri Muktsar Sahib., which is
covered under sector 5 (i) category “A” of above referred Notification under the supervision of Dr. Richa
Sharma (IAS), Dr. Manohar lal Chauhan, Environmental Engineer (Mega) PPCB- Patiala , Shri Ravi Pal,
Asstt. Environmental Engineer, PPCB-Regional Office Bhatinda and District Magistrate of Sri Muktsar
Sahib.
In this context, Punjab Pollution Control Board issued the public notice of 30 days in English and Punjabi
Language in The Tribune News Paper and Ajitjalandhar and local Punjabi News paper on 04/06/2019 for
getting responses from public and intimating time, date and venue of the public hearing. The copy of
public hearing proceedings attached as Annexure XVII. Time bound action plan of the issues raised
during public hearing is given in Table 7.1.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 142 2018_ECSS_EIAI1_1800028
7.1.1 Advertisement and Photographs
Advertisement in English and Punjabi News Paper
Public Hearing Photographs
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 143 2018_ECSS_EIAI1_1800028
Table 7.1 – Time bound action plan of the issues raised during public hearing
Sr.No
Name & Address of the person
Detail of query/statement/information/ clarification sought by the person present`
Reply of the query/statement/information/clarification given by the project proponent`
1. Sh. Hardev Singh, Sarpanch Village Rupana, District Sri Muktsar Sahib
He welcomed the Addi. Deputy Commissioner , Sri Muktsar Sahib, officers and the public present. He expressed his happiness over the expansion of the project from 300 TPD to 600 TPD. He further stated that with the expansion of the Industry, people of Village Rupana will get employment from the project. With the expansion of the industry, shopkeepers & other poor families of the area will get more benefit from it. He also stated that there are very less industries in Punjab. There is development of the area with the industrialization. All the people of the area and especially farmers are very happy with the expansion of the project. There will be no disadvantage with the expansion of the industry. He Congratulated the project management for the expansion. He demanded that the employment should be given to the local people. He further stated that if any worker of the industry make any mistake, then he should not be retrenched from the industry.
No Comments required.
2. Sh. Bohar Singh, r/o village Rupana, District Sri Muktsar Sahib
He welcomed all the officers & public for and on behalf of Village Rupana. Agriculture is backbone of any economy. He further stated that the industry has given direct & indirect employment to the people of the area. With the expansion of the industry, there will be generation of employment opportunities.
No Comments required.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 144 2018_ECSS_EIAI1_1800028
He also stated that with the burning of paddy, air pollution is caused. The Paddy straw is being purchased by the industry with which farmers of the area are getting benefits and pollution caused due to burning of paddy is reduced to some extent. He also stated that the industry has constituted trust, Which is organizing eye camps and doing other welfare works for the people of the area. He congratulated the project management for the expansion of the industry. He also stated that the industry should increase its production capacity from 300 TPD to 1200 TPD, So that the people of the area may get more employment and development of the area may increase.
3. Sh. Jaswinder Singh Pitta, Press Reporter
He stated that the public hearing is being conducted in a transparent manner. The industry has given employment to the people of the area. He wanted that more projects should be established in the area. The education is interlinked with the industry.
No Comments required.
4. Dr. Jagan Nath Grover, Rupana, District Sri Muktsar sahib
He stated that the youth is going to abroad with which there is loss of economy to the country. He further stated that the industries are generating employment opportunities. He requested that more industries should be established in the area. He demanded that more trees/plants be planted to clean the environment
Environmental consultant of the company informed that the industry has proposed to develop green belt around the boundary of the plant in an area of 60832 sqm.
5. Sh. Harjit Singh, President, Village Rupana, District Sri Muktsar Sahib
He stated that the industry is going to increase its production capacity from 300 TPD to 600 TPD, for which public is being conducted. He
Environmental consultant of the company informed that the plantation has been carried out in area of 540 acres.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 145 2018_ECSS_EIAI1_1800028
welcomed the same. He further stated that every industry has positive & negative impacts. He thanked the management as expansion of the industry will create more employment opportunities. The industry should develop more green belt.
6. Sh. Harvinder Singh, Village Goniana, District Sri Muktsar sahib
He stated that the industry is taking land of the farmer on lease in which trees/plants are being planted. He further stated that farmers are taking water from the industry, which has no effect on the crops of the farmers. The paddy of the area is being used as fuel in the industry with which pollution caused due to burning of paddy straw has been reduced to some extent. The industry has constructed two rooms in the govt. school of their village. The industry has got treatment free of cost of poor people of the area. He congratulated the management of the project.
Environmental consultant of the company informed that the industry has spent Rs.173 Lacs during the last three years for doing welfare activities in the near villages. He further informed that the industry has proposed to spend about Rs.3.75 Crores for doing philanthropic activities for the selective villages.
7. Sh. Kamaljit Singh Brar, r/o village Rupana, District Sri Muktsar Sahib
He Wanted that the quantity of water, which is used in the process by the industry, may be reduced.
Environmental Consultant of the company informed that at present the industry is using water@16500 m3/day for manufacturing of Paper @300 TPD and other activities in the industry. He further informed that the industry is going to increase its production capacity two times, but after expansion the unit, water requirement of the industry will be 24000 m3/day, as such, the industry has already proposed to reduce the water quantity in the process. He also informed that the industry has proposed to upgrade/modify its existing effluent treatment plant to handle the effluent to be generated after the expansion of the unit. He assured that proper treatment system will be in place to treat the effluent to be generated from the industry. Environmental Engineer (Mega),Punjab Pollution Control Board, Patiala informed that he has been informed by the Asstt.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 146 2018_ECSS_EIAI1_1800028
Environmental Engineer, Punjab Pollution Control Board. Regional Office, Bathinda that the industry has already installed effluent treatment plant of adequate capacity to control the water pollution from the industry. He further informed that as informed by the Asstt. Environmental Engineer, Punjab pollution control board, Regional office, Bhatinda that the industry has already installed online monitoring system, which is connected with the head office of CPCB & PPCB and the phone numbers of the concerned operator & officer concerned are flashed on the monitor also.
7.2 EIC STUDY
In compliance to ToRs of the Ministry of Environment, Forests & Climate Change, land use data and
satellite imagery for the area is obtained and is included in this section.
Broadly the study area is Rural which is classified into traditional categories such as areas under
Forests, Cultivated land (Irrigated and Unirrigated), Cultivable Waste land and „Area Not Available for
Cultivation‟. In compliance to the ToRs of MoEFCC land use data for the area was obtained from
Environmental Information Centre (EIC) based on the land use map and satellite imagery.
7.3 RISK ASSESSMENT AND SAFETY MANAGEMENT
7.3.1 Introduction
Satia Industries Ltd. is an existing agro-based Integrated Pulp and Paper Mill with captive power
generation unit located at Rupana Distt. Muktsar (Punjab). Presently the unit is involved in
manufacturing of writing and printing paper with the production capacity of 300 TPD and now, the unit
intends to enhance the production capacity to 600 TPD. The Risk Assessment Study for the proposed
project has been carried out and all the details are elaborated in this chapter. Based on the findings &
recommendations of RA report, management plan has also been prepared and included.
Risk Assessment is defined as a continuous and integrated process of identification, evaluation and
measurement of risks, along with their potential impact on the organization.
The benefits of risk assessment include the following:
• Prevention or reduction in occurrence of accidents.
• Mitigation of the severity and/or consequences by the way of improved process techniques, fire
protection systems, arrangements of storage, inventory monitoring to fit production
requirements.
• Confidence building in employees by improving competency.
• Preparedness and prompt response to deal with any accident.
7.3.2 Objective, Philosophy and Methodology of Risk Assessment
Objective:
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 147 2018_ECSS_EIAI1_1800028
The principle objective of this study is to identify major risks in the manufacturing and to evaluate on-site
& off-site consequences of identified hazard scenarios. To give effective mitigation of hazards in terms
of suggestions for effective disaster management, suggesting minimum preventive and protective
measures & change of practices to ensure Occupational Health and Safety.
Philosophy:
The following aspects and areas are covered in this study;
• Identification of major risk areas.
• Hazard identification / Identification of failure cases
• Consequential analysis of probable risks / failure cases
• Determination of the probable risk by releasing of chemical due to leakage of storage tank and
catastrophic failure.
• Risk assessment on the basis of the above evaluation & risk acceptability
• Minimum preventive & protective measures to be taken to minimize risks to maximum possible
extent.
• Giving pointers for effective disaster management
• Suggesting other measures to further lower the probability of risk
Methodology:
Design data, built in safety systems has been studied. Mutual discussions has been carried with the
officials. Safety related individual system is discussed. Hazard identification exercise is conducted
taking into consideration of materials, material handling methods, operating procedures, built in safety in
reactors, operating parameters and safety measures to be taken in proposed plant. Few areas like
process building, storage of hazardous chemicals, to evaluate safety systems in the event of any
abnormalities occurring. Containment failure scenario related to storage area is considered for hazard
analysis and consequences of such containment failures are considered in detail. Thus, this study is
mainly oriented towards actual risks rather than chronic risks.
7.3.3 Hazardous Material, Process & Safety
7.3.3.1 Hazardous Products
No hazardous product is produced in the mill.
7.3.3.2 Hazardous Raw Materials
Hazardous substances may be classified into two main classes: Flammable substances and Toxic
substances. Flammable substances or the vapours arising in some reaction require interaction with air
for their hazard to be realized. Toxic substances are those whose exposure may result in occupational
diseases in the human beings in vicinity. The mail and only product of the unit is writing and printing
paper which is non-hazardous. The basic raw materials for the manufacturing of writing and printing
paper will be agro waste like wheat straw, rice husk, and sarkanda along with the few hazardous
chemicals like, Chlorine Dioxide. Hazardous characteristics of the major flammable/ toxic materials
employed in different stages of production are listed in Table 7.2 and the details of hazardous properties
are listed in following Table 7.3.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 148 2018_ECSS_EIAI1_1800028
Table 7.2 - Properties of storage chemicals used at the mill
Chemical Codes/Label TLV BP MP
0C
Sodium Hydroxide Corrosive 2 mg/m3 1390 318.4
TLV: Threshold Limit Value BP: Boiling Point MP: Melting Point
Table 7.3 - Properties of Hazardous Chemical
7.3.3.4 Safety Measures for Transportation, Storage & Handling
General Safety Measures for Storage
For the safe storage company has provided the following safety measures.
• Sufficient storage area will be provided and will be kept away from service/ maintenance
buildings to ensure that spreading of fire in storage area can be prevented.
• Display boards has been provided on all storage tanks which includes the name of the product,
stored material of construction, calibration of tanks and date of painting.
• The level indicators are provided to see the exact liquid level inside the tank and to avoid
spillage.
• All the storage tanks are provided with dyke wall and transferring pumps which helps to reduce
the risk of tank leakages.
• Raw material is properly stored in stacks and the sufficient space if provided between two
stacks. Temp. of each stack of raw material is checked every week to avoid the possibility of
auto combustion and proper record is maintained.
• Proper earthing is provided to all storage tanks to prevent the firing due to static charges.
• Water filled chamber is provided on silencer pipe of each and every vehicle before allowing it to
enter in storage area.
Property Unit Chlorine Dioxide
Boiling point °C 11
Vapour Pressure atm 1
Flash point °C NA
Freezing point °C -59
Density Kg/m3 1.54
Ambient Saturation Conc ppm 1,000,000
TLV/TWA ppm 0.1
IDLH ppm 5
LEL % 10
UEL % NA
Hazardous Classification -- Hazardous, Toxic & Non-
Flamable
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 149 2018_ECSS_EIAI1_1800028
• Hazardous display board and national fire prevention association code are displayed on all
storage tanks.
• Temperature indicator and pressure gauge are provided to all storage tanks.
• Smoking is strictly prohibited in mills premises heat &/or smoke detection with alarm system will
be provided at designated locations.
• Fire hydrants is provided in storage yard and fire fighting equipments (fire extinguishers, water-
bucket, sand buckets and hydrant points) are provided at designated locations in the plant area.
• The management will prepare the booklet on disclosure of information to general public,
workers and authorities.
The details of raw material storage, handling and transportation are given in following Table 7.4.
Table 7.4 - Properties of Hazardous Chemical
Name of
Chemical
Ph
ys
ica
l
Fo
rm
Typ
e o
f
Sto
rag
e
Sto
rag
e T
an
k
Ca
pa
cit
y
Ma
x. S
tora
ge
Ca
pa
cit
y
Sto
rag
e
Pre
ss
ure
Kg
/cm
2
Sto
rag
e
Tem
p. °C
So
urc
e
Mo
de
of
Tra
ns
po
rtati
on
Chlorine
Dioxide Gas
Storage
Tank 50 m3 100 m3 Atm. Amb. Local
Self
Manufacturing
7.3.3.5 Safety Measures for preventive maintenance
The safety measures in form of the general Do's & Don'ts for safety in process & other plant area are as
below:
• Do not work on equipment without permission from plant head and maintenance head.
• Keep proper and adequate fire extinguisher near work area.
• Use proper PPE‟s.
• Do not allow any employment without pre-medical check-up or without checking fitness.
• Check all motors are disconnected and fuse pulled out before maintenance.
• Work in any equipment must be done under supervision.
• Make sure all process lines are disconnected.
• Additional safety measures in form of the checklist covering Do's & Don'ts of preventive
maintenance, manufacturing utility staff for safety related measures should be updated timely
and made available to all concern department & personnel and its use must be ensured by
safety officer.
7.4 OCCUPATIONAL SAFETY & HEALTH PROGRAM
Occupational safety and health (OSH) is an area concerned with protecting the safety, health and
welfare of people engaged in work or employment. The goals of occupational safety and health
programs include fostering a safe and healthy work environment. OSH may also protect co-workers,
family members, employers, customers, and many others who might be affected by the workplace
environment.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 150 2018_ECSS_EIAI1_1800028
OSH can also be used for moral, legal, and financial reasons. All organizations have a duty of care to
ensure that employees and any other person who may be affected by the companies undertaking
remain safe at all times. Moral obligations would involve the protection of employee's lives and health.
Legal reasons for OSH practices relate to the preventative, punitive and compensatory effects of laws
that protect worker's safety and health. OSH can also reduce employee injury and illness related costs,
including medical care, sick leave and disability benefit costs.
Health hazards associated with the occupation are called occupational hazards. In industry due to
handling of toxic and hazardous substance there are possibilities of developing occupational diseases.
Occupational health needs attention both during construction & erection and operation & maintenance
phases. However, the problem varies both in magnitude and variety in the above phases.
7.4.1 Construction and Erection
The occupational health problems envisaged at this stage can mainly be due to unconditional acts and
condition at site. To overcome these hazards necessary protective equipment‟s will be provided to
workers. Height job will done under supervision. Training will be provided to workers periodically related
to the job. Good housekeeping will be maintained in construction area.
7.4.2 Operation and Maintenance
The problem of occupational health, in the operation and maintenance phase is primarily due to noise
and chemical exposure. The necessary personal protective equipment‟s are/ will be given to workers as
per the job. Following personnel protective equipment‟s is/ will be provided.
Industrial safety helmet
• Face shield with replaceable acrylic vision
• Punk Type safety goggles for dust protection
• Chemical splash proof goggles
• Eye/ Face shower & eye wash bottles
• Gum boots
• Welders equipment for eye and face protection
• Cylindrical type earplug
• Emergency chlorine leakage control kit
• Ear muffs
• PVC apron
• Full body harness
• Water gel blankets
• Asbestos and rubber hand gloves
• Acid/Alkali proof PVC hand gloves
• Self contained breathing apparatus
• Boiler suit
• Electrically tested electrical resistance hand gloves
7.4.3 Hospital facilities
Satia Industries had made formal agreements with nearby hospital (Bansal Nursing Home ,6 km from
SIL, Dr. Mukesh Bansal-MBBS,MS,Ph.No.-01633-262023 and Guru Nanak Hospital ,6 km from SIL, Dr.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 151 2018_ECSS_EIAI1_1800028
Madan Mohan Bansal-MBBS,MD,Ph.No.01633-240686) to attend affected persons during emergency/
accident.
7.4.4 Factory medical officer
A qualified doctor has been appointed as Factory Medical Officer (FMO) (Dr. Sandeep Singh Sandhu-
MBBS, Mo.9872622642) on retainer ship basis. Paramedical Staff will be employed additionally.
7.4.5 Ambulance van
Ambulance van facility is available with the company 24x7.
7.4.6 First aid box
First aid box is located at security room, control room, admin building etc. at in the plant; training is
given to employees for First Aid.
7.4.7 Periodic medical examination
The medical checkup program is being conducted as pre-employment and post-employment check-up
programs. Pre employment check up has been mandatory and tests like chest x rays, audiometry,
spirometry vision testing, ECG, haemogram (examination of the blood), urine (Routine and
Microscopic), complete physical examination i.e. Musculo-skeletal disorders (MSD), backache, pain in
minor and major joints, fatigue, etc. are being/will be conducted.
Medical check-up of all the employees is being/will be carried out periodically by qualified medical
officer and health records are maintained in prescribed format.
Employed Workers are/will be medically examined by a qualified medical practitioner/Factory Medical
Officer, in the following manner:
• Once in a period of 6 months, to ascertain physical fitness of the person to do the particular job
and to ascertain the health status of all the workers in respect of occupational health hazards to
which they are exposed and in cases where in the opinion of the Factory Medical Officer it is
necessary to do so at a shorter interval in respect of any workers;
• In periodic and premedical examinations, various parameters are being checked. Viz. Liver
Function Tests, Chest X-rays, Audiometry, Spirometry, Vision testing (Far & Near vision, color
vision and any other ocular defect) ECG and other parameters as will be found necessary as
per the opinion of Factory Medical officer.
7.4.8 Management plan for occupational health & safety
Following management plan has been proposed so that exposure of the workers can be kept within
Permissible Exposure Level (PEL)/Threshold Level value (TLV) to protect their health;
1. To formulate and implement an Environmental management Plan (EMP) for OHS with following
aims:
To keep airborne concentration of toxic and hazardous chemicals below PEL and TLV.
Protect general health of workers likely to be exposed to such chemicals
Providing training, guidelines, resources and facilities to concerned department for occupational
health hazards.
Permanent changes to workplace procedures or work location to be done if it is found necessary
on the basis of findings from workplace Monitoring Plan.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 152 2018_ECSS_EIAI1_1800028
2. EMP be formulated on the guidelines issued by Bureau of Indian Standards on OHS
Management Systems: IS 18001:2000 Occupational Health and Safety Management Systems.
3. EMP is incorporated in Standard Operating Procedure also.
4. The EMP includes measure to keep airborne concentration of toxic and hazardous chemicals
below its PEL and TLV, like
a) Leak surveys
b) Separate storage for toxic chemicals
c) Exhaust ventilation
d) Proper illumination
e) On‐line detectors toxic chemicals like chlorine
f) Close processes to avoid spills and exposures
g) Supply of proper PPEs like air mask, berating canisters, SCBA sets, on‐line breathing
apparatus at the places where there is possibility of presence of toxic chemicals
h) Decontamination procedure for empty drums and carboys.
i) Regular maintenance program for pumps, equipment, instruments handling toxic and
corrosive chemicals
j) Display of warning boards
k) Training to persons handling toxic and corrosive chemicals
l) All First Aid Measures such as Flushing bottles for eyes with plenty of water, Flushing bottles
for skin with plenty of water while removing contaminated clothing and shoes and flush skin
with plenty of soap and water, not to induce vomiting, fluid and electrolytes as antidotes
have been made available.
5. Workplace Monitoring Plan
Each workplace must be evaluated to identify potential hazards from toxic substances or harmful
physical agents. It is in concern that a workplace Monitoring Plan to be prepared & implemented
in consultation with FMO and Industrial Hygienists. The work zone monitoring has been
conducted in the industry during the study period with respect to following parameters such as
PM2.5, PM10, TSPM, SO2, NOx, Noise, etc.
Table 7.5 - Work Place Monitoring in the Industrial Premises
# Location PM10
(24 h) (µg/m3)
PM2.5
(24 h) (µg/m3)
SO2
(24 h) (µg/m3)
NO2
(24 h)
(µg/m3)
Noise dB(A)
1. Pulp Mill 88.9 48.2 32.6 20.3 67.8 - 88.9
2. Paper Machine 82.5 44.8 24.5 22.8 79.0 - 91.0
3. Power Plant 74.6 32.9 18.6 26.9 92.9 - 99.4
4. Main Gate 78.7 36.0 11.8 18,4 42.5 - 69.9
6. Health Evaluation of Workers
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 153 2018_ECSS_EIAI1_1800028
The management has derived a plan to check and evaluate the exposure specific health status
evaluation of workers.
Workers have been checked for physical fitness with special reference to the possible health
hazards likely to be present where he/she is being expected to work before being employed for
that purpose. Basic examinations like Liver Function tests, chest x ray, Audiometry, Spirometry
Vision testing (Far & Near vision, color vision and any other ocular defect) ECG, etc. are carried
out. However, the parameters and frequency of such examination are decided in consultation
with Factory Medical Officer and Industrial Hygienists.
While in work, all the workers are periodically examined for the health with specific reference to the
hazards which they are likely to be exposed to during work. Health evaluation is carrying out
considering the bodily functions likely to be affected during work. The parameters and frequency of such
examination are decided in consultation with Factory Medical Officer and Industrial Hygienists Plan of
monthly and yearly report of the health status of workers with special reference to Occupational Health
and Safety. Details of Health evaluation of workers is placed in Table 7.6.
Table 7.6 - Health Evaluation of Workers
To which chemicals workers are exposed directly or indirectly
Whether these chemicals are within TLV/Permissible exposure levels as per ACGIH recommendation
What measures company have taken to keep these chemicals within PEL/TLV
How the workers are evaluated concerning their exposure to chemicals during
pre‐placement and periodical medical monitoring
What are onsite and offsite emergency plan during chemical disaster
Chlorine Dioxide Within TLV Limit Conc.: BDL
Local exhaust ventilation, personnel protective equipment,
Lung Function Test, Examination of Respiratory and eyes, chest roentgenogram, x-ray if necessary
1. Fire hydrant system and foam monitor 2. Trainer fire fighter 3. Sand bucket stand
7.5 FIRE FIGHTING SYSTEM AND EMERGENCY MANAGEMENT
7.5.1 Firefighting system
Necessary fire fighting arrangements at each strategic location of the mill specifically, the raw
material storage yard, finished product godown, chemical godown and all the electrical penal
rooms are covered by suitable kind of fire extinguishers and fire hydrant networks. At different
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 154 2018_ECSS_EIAI1_1800028
strategic locations, fire hose boxes (containing fire hose pipes and gun metal nozzles) are
provided.
Mock drill & training is/will be conducted at scheduled intervals.
Fire fighting is/ will be available 24x7 in the premises.
7.5.2 Emergency Management
Emergency Planning:
Emergency siren and wind sock has been installed.
On Site emergency Plan is prepared.
Tele Communication system and mobile phone are used in case of emergency situations for
communication.
First Aid Boxes and Occupational health centre are made at site.
Safety Practices in the Work Area:
We inform our all employees of the potential hazards of contact with chemicals and train them in
appropriate first-aid procedures.
Chemical handling areas are clearly marked and restricted to qualified, trained personnel only.
Emergency Procedures
In case of emergencies, follow recommended first aid and emergency response procedures
adopted.
Transportation Emergencies
In emergency situations resulting from vehicle accidents:
Notify the local police, fire departments, emergency responders and the carrier.
Isolate the area.
Any person not dressed in proper protective clothing and not using a NIOSH approved self-
contained breathing apparatus should be kept a safe distance away.
Call to the supplier.
Seek immediate medical assistance for those injured and follow recommended first aid
procedures.
Leaking Containers
When handling leaking bottle personnel protective clothing, goggles and NIOSH approved self-
contained breathing equipment must be worn.
Clear contaminated area of non-essential personnel and send them to assembly point.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 155 2018_ECSS_EIAI1_1800028
There should be provision of proper ventilation. Scrub the floors and equipment with soap and
water.
First Aid Procedure
Immediate medical assistance is required if chlorine dioxide and hydrogen peroxide are inhaled
or has contacted the eyes or skin.
If chlorine dioxide and hydrogen peroxide has been inhaled, move exposed person to fresh air. If
not breathing, if breathing is irregular or if respiratory arrest occurs, provide artificial respiration
or oxygen by trained personnel. Loosen tight clothing such as a collar, tie, belt or waistband. Get
medical attention immediately.
For skin contact, immediately flush skin with plenty of water for at least 15 minutes while
removing contaminated clothing and shoes. To avoid the risk of static discharges and gas
ignition, soak contaminated clothing thoroughly with water before removing it. Wash clothing
before reuse. Clean shoes thoroughly before reuse. Get medical attention immediately.
If hydrogen peroxide comes in contact with the eyes, check for and remove any contact lenses.
Immediately flush eyes with plenty of water for at least 15 minutes, occasionally lifting the upper
and lower eyelids. Get medical attention immediately
In all cases of injury, obtain immediate medical attention. Provide emergency personnel with
information about all materials used by the person and provide appropriate information and first
aid procedures.
Details of Fire equipment‟s and Hydrants are attached as Annexure X.
7.6 RISK ASSESSMENT STUDY
Risk involves the occurrence or potential occurrence of some accidents consisting of an event or
sequence of events. The description of the tasks of the various phases involved in the risk analysis is
detailed below. The study aims to analyze the risk associated with the following scenarios in the pulp &
paper mill:
i) Hazards associated with various processes
ii) Raw material storage in the plant.
The risk analysis assessment study covers the following:
Identification of potential hazard area;
Identification of representative failure cases;
Assessment of the overall suitability of the site from hazard minimization and disaster
management point of view;
Furnishing of specific recommendations on the minimization of the worst accident possibilities;
and
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 156 2018_ECSS_EIAI1_1800028
Preparation of broad Disaster Management Plant (DMP), On-site Emergency Plan, which
includes Occupational Health & Safety Plans.
7.6.1 Hazard Identification
Hazard is an inherent property of a substance, agent, and source of energy or situation having potential
of causing undesirable consequences.
Identification of hazards in pulp & paper mill is of primary significance in the analysis, quantification &
cost effective control of accidents involving chemicals and process. Estimation of probability of an
unexpected event and its severity form the basis of quantification of risk in terms of damage to property,
environment or personnel as:
Risk = Probability X Severity
Therefore, the type, quantity, location and conditions of release of a toxic or flammable substance have
to be identified in order to estimate its damaging effects, the area involved and the possible
precautionary measures required to be taken.
The following two methods of hazard identification have been employed in the study:
Identification of major hazards based on Manufacture, Storage, And Import Of Hazardous
Chemicals Rules (MSIHC Rules), 2000 Government Of India, as amended till date.
Process Hazard Analysis (PHA) is a method to evaluate and identify credible hazardous
scenarios. PHA is a thorough, orderly, systematic approach for identifying, evaluating, and
controlling the hazards of processes involving hazardous chemicals.
The probable potential hazards are classified as under:
1. Storage Hazards:
All the hazardous materials used during the manufacturing activity are stored in drum/tank/cylinder.
Storage hazard can be evaluated based on the storage of various materials. The condition of event like
catastrophic failure of storage tank, ruputure of pipe connected to storage tank, small crack and leakage
in the tank may lead to storage hazard.
2. Fire hazards:
Fire hazard can be evaluated based on storage quantity and flammability of materials stored. The
condition of events like spillage, leakage of material could leads to fire. Equipment failures, presence of
open flame or spark in the area, static charge accumulation, open live cables and reaction between
incompatible materials are some of the reasons which lead to the occurrence of fire.
3. Toxicity Hazard:
Toxic substances affect in three ways by ingestion, absorption & inhalation. Adequate provision of
safety along with personnel protective equipment are made, breathing apparatus and emergency kit are
provided at various locations of the installation.
4. Explosion Hazard:
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 157 2018_ECSS_EIAI1_1800028
Release of energy in a rapid and uncontrolled manner gives rise to explosion. Identified locations
having explosion hazards are in tank and storage area (warehouse). Extra care shall be taken by
providing rupture disc, pressure release valve and temperature controller. In addition, fire and explosion
hazard is identified as catastrophic failure of storage tanks area.
5. Corrosive Hazard:
Corrosion is a chemical reaction-taking place at the surface of metal. The corrosive chemicals have
their typical hazard when it comes in contact with human tissues. Most corrosive substances produce
chemical burns, while certain chemical produce deep ulceration. Other has detailing effect on skin and
may cause dermatitis. This also has adverse effects on weakening the strength of material in contact.
6. Mechanical Hazard:
Following mechanical hazards are identified which can cause any unforeseen event which will again
result in accident.
Handling of cranes, trolleys, construction machineries.
Handling of mechanical equipment‟s like shovel, forklift, etc.
Handling of raw material MS Scrap, products and various mechanical accessories.
Maintenance workshop etc.
7. Electrical Hazard:
Use of various electrical instrument, electrical appliances may cause electrical hazards during use of
various appliances.
7.6.2 Hazard Assessment and Evaluation
Preliminary Hazard Analysis (PHA)
It is based on the philosophy “prevention is better than cure”. Safety is relative and implies freedom
from danger or injury. But there is always some element of danger or risk in anything we do or build.
The purpose of preliminary hazard analysis is to identify early in the design process the potential
hazards associated with, or inherent in, a process design, thus eliminating costly and time consuming
delays caused by design changes made later. This also eliminates potential hazard points at design
stage itself. A preliminary hazard analysis is carried out initially to identify the major hazards associated
with storages and the processes of the plant. This is followed by consequence analysis to quantify
these hazards. Finally, the vulnerable zones are plotted, for which risk reducing measures are deduced
and implemented. There are various process activities involved in this pulp and paper mill operations
like raw material handling and preparation, chemical pulping bleaching of pulp stock preparation paper
making & processing except for chemical pulping, pulp bleaching and chemical recovery from black
liquor, all the other processes involve purely mechanical operations that are not complex or hazardous.
Chemical pulping involves cooking of raw material with sodium hydroxide. Sodium hydroxide is a mildly
hazardous chemical in nature. The washing and paper manufacturing process contains no involvement
of any hazardous chemicals as such. Oxygen delignification and chlorine dioxide bleaching are used to
eliminate elemental chlorine bleaching i, e. The purpose of introducing elemental chlorine free bleaching
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 158 2018_ECSS_EIAI1_1800028
(ECF bleaching) in the process is to reduce pollution load as well as AOX level. Bleaching process
including ODL, chlorine dioxide, alkali extraction, hydrogen peroxide, oxygen i.e. (ODL, EOP, pulping
sequence) is being employed which reduces pollution load in treated waste water and improve product
quality. Hence, no major hazards with the potential for any emergency situation exist in the process
plant.
A preliminary hazard analysis is carried out initially to identify the major hazards associated with
storages and the processes of the plant. This is followed by consequence analysis to quantify these
hazards. Finally, the vulnerable zones are plotted, for which risk reducing measures are deduced and
implemented. The various process activities involved in this pulp and paper mill operations are:
Raw material handling and preparation
Chemical Pulping
Bleaching of pulp
Stock Preparation
Paper Making & Processing
Except for chemical pulping, pulp bleaching and chemical recovery from black liquor, all the other
processes involve purely mechanical operations that are not complex or hazardous. Chemical pulping
involves cooking of raw material with sodium hydroxide at temperatures below 175ºC. No major
hazards are expected from this process. Sodium hydroxide is a mildly hazardous chemical in nature.
The washing and paper manufacturing process contains no involvement of any hazardous chemicals as
such. Hence, no major hazards with the potential for any emergency situation exist in the process plant.
The other hazards related to boiler operation and other storage areas are given in Table 7.7 and
preliminary hazard analysis for whole of the plant is given in Table 7.8.
Table 7.7- Preliminary hazard analysis for process and storage areas
Equipment Process Potential Hazard
Provision
Power Transformer
-- Fire &
Explosion All electrical fittings and cables are
provided as per the specified standards
Switch Yard Control Room
- Fire in cable trenches and
switches
All electrical fittings and cables are/will be provided as per the specified standards
Caustic Used in chemical pulping
Leakage Standby storage tank provided to empty up
the leaking tank.
Table 7.8 - Preliminary hazard analysis for the whole plant in general
PHA Category
Description of plausible hazards
Recommendation Provision
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 159 2018_ECSS_EIAI1_1800028
Environmental Factors
Any leakage and eventuality of source
of ignition -
All electrical fittings and cables are provided as per the specified standards. All
motor starters are flame proof.
Fire hazard in the storage facility.
A well-designed fire protection including
mechanical foam, dry powder and fire
buckets are provided.
Fire extinguishers of medium capacity are
provided at all potential fire hazard places. In addition to the above, fire hydrant
network is/will be provided.
7.6.3 MCA Scenarios and Consequences Analysis
A Maximum Credible Accident (MCA) can be characterized as the worst credible accident. In other
words an accident in an activity, resulting in the maximum consequence distance that is still believed to
be possible. A MCA analysis does not include a quantification of the probability of occurrence of the
accident. Another aspect, in which the pessimistic approach of MCA studies appears, is the
atmospheric condition that is used for dispersion calculations.
The Maximum Credible Loss (MCL) scenarios have been developed for the facility. The MCL cases
considered, attempt to include the worst “Credible” incidents-what constitutes a credible incident is
always subjective. Nevertheless, guidelines have evolved over the years and based on basic
engineering judgment, the cases have been found to be credible and modeling for assessing
vulnerability zones is prepared accordingly.
The objective of the study is emergency planning, hence only holistic & conservative assumptions are
used for obvious reasons. Hence, though the outcomes may look pessimistic, the planning for
emergency concept should be borne in mind whilst interpreting the results.
This has been done for weather conditions having wind speed 3.0 m/s. In Consequence Analysis,
geographical location of the source of potential release plays an important role. Consideration of a large
number of scenarios in the same geographical location serves little purpose if the dominant scenario
has been identified and duly considered.
The Consequence Analysis has been done for selected scenarios by ALOHA (version 5.4.1.2) of EPA.
The details of software used for MCA analysis are described below.
A computer based version ALOHA 5.4.1.2 is used to calculate toxic and explosive effect of the
accidental release of liquid chemicals within the plant area.
ALOHA (Areal Locations of Hazardous Atmosphere) is a computer program designed especially
for use by people responding to chemical release as well as for emergency planning and
training.
ALOHA was jointly developed by the National Oceanic and Atmospheric Administration (NOAA)
and the Environment Protection Agency (EPA).
The mathematical model is based on the Emergency Response Planning Guidelines (ERPGs)
which gives Toxic Levels of Concern (LOCs) to predict the area where a toxic liquid
concentration might be high enough to harm people.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 160 2018_ECSS_EIAI1_1800028
ALOHA models key hazards-toxicity, flammability, thermal radiation (Heat), and over pressure
(expansion blast force)-related to chemical releases that result in toxic gas dispersion, fire and/or
explosion.
7.6.4 Definitions & Explanation of Terms Used
EPRG-1: The maximum concentration in air below which it is believed nearly all individuals could be
exposed for up to one hour without experiencing other than mild transient adverse health effects or
perceiving a clearly defined objectionable odour.
EPRG-2: The maximum airborne concentration below which it is believed that nearly all individuals
could be exposed for up to 1 hour without experiencing or developing irreversible or other serious health
effects or symptoms which could impair an individual's ability to take protective action.
ERPG-3: The maximum airborne concentration below which it is believed that nearly all individuals
could be exposed for up to 1 hour without experiencing or developing life-threatening health effects.
AEGL-1: The airborne concentration of a substance above which it is predicted that the general
population, including susceptible individuals, could experience notable discomfort, irritation, or certain
asymptomatic no sensory effects. However, the effects are not disabling and are transient and
reversible upon cessation of exposure.
AEGL-2: The airborne concentration of a substance above which it is predicted that the general
population, including susceptible individuals, could experience irreversible or other serious, long-lasting
adverse health effects or an impaired ability to escape.
AEGL-3: The airborne concentration of a substance above which it is predicted that the general
population, including susceptible individuals, could experience life-threatening health effects or death.
IDLH: IDLH is an estimate of the maximum concentration in the air to which a healthy worker could
be exposed without suffering permanent or escape-impairing health effects.
LEL: LEL is the minimum concentration of fuel in the air needed for a fire or an explosion to occur if an
ignition source is present. If the concentration is below the LEL, there is not enough fuel in the air to
sustain a fire or an explosion -- it is too lean.
UEL: UEL is the maximum concentration of fuel in the air that can sustain a fire or an explosion if an
ignition source is present. If the concentration is above the UEL, there is not enough oxygen to sustain
a fire or an explosion -- it is too rich (much like an engine that cannot start because it has been flooded
with gasoline).
STEL: The concentration to which workers can be exposed continuously for a short period of time
without suffering from
Irritation
Chronic or Irreversible tissue damage
Narcosis of sufficient degree to increase injury, impair self-rescue or materially reduce work
efficiency and provide that the daily TLV-TWA is not exceeded.
TWA: The time-weighted average concentration for a normal 8-hour workday and a 40-hour
workweek, to which nearly all workers may be repeatedly exposed, day by day, without adverse effect.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 161 2018_ECSS_EIAI1_1800028
Source Strength: The source strength is either the rate the chemical enters the atmosphere or the burn
rate, depending on the scenario. A chemical may escape very quickly (so that source strength is high),
as when a pressurized container is ruptured, or more slowly over a longer period of time (so that source
strength is low), as when a puddle evaporates.
Threat zone: It represents the area within which the hazard level (toxicity, flammability, thermal
radiation, or overpressure) is predicted to exceed the Level of Concern (LOC) at some time after a
release begins.
Evaporation Puddle: Choose Puddle from the Source submenu under the set up menu to model a
liquid that has spilled and formed a puddle on the ground. ALOHA can model the puddle either as an
evaporating puddle or, if the chemical is flammable, as a Pool Fire. Choose Puddle when a puddle has
already formed on the ground and is not changing in area. If liquid is continuing to leak from a tank and
spilling into a puddle (so that the puddle's area and volume are increasing) choose Tank from the
Source submenu instead. Check the "Tank source" help topic to learn more about this option.
Toxic Threat zone: A Toxic Level of Concern (LOC) is a threshold concentration of an airborne
pollutant, usually the concentration above which a hazard may exist.
Threat at Point: It represents the specific information about the hazards at point of interest (such as
schools and hospitals) in and around the threat zones.
7.6.5 Possible Accident Scenario
Major two raw materials, chlorine dioxide and hydrogen peroxide, are used for the manufacturing
activity area hazardous, which are hazardous in nature. The details of storage and properties of
hazardous chemical are given earlier in Table-7.3 & Table-7.4 and the threshold value of these
hazardous chemicals is mentioned in the Table- 7.9.
Different scenarios for occurrence of any accidents due to storage/usage of hazardous chemicals are
prescribed below;
Scenario-A: Release of chemical due to leakage and form evaporating puddle (not burning)
Scenario-B: Release of chemical due to leakage and form burning puddle (pool fire)
Scenario-C: Release of chemical due to catastrophic failure (Bleve)
During the current analysis only Scenario- A is considered for both hydrogen peroxide and chlorine
dioxide because Scenario- B & C is not applicable as the chemical is non-flamable. The atmospheric
condition and possibilities of source strength considered at the time of accident are given in Table-7.10
and 7.11
Table 7.9: Threshold values of the Hazardous Chemicals
Sr.
No. Hazardous Chemicals
Threshold Value*
AEGL / ERPG-1 AEGL / ERPG-2 AEGL / ERPG-3
1. Chlorine Dioxide 0.15 ppm 1.1 ppm 2.4 ppm
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 162 2018_ECSS_EIAI1_1800028
*AEGL: Acute Exposure Guideline Levels (For Chlorine Dioxide)
ERPG: Emergency Response Planning Guidelines (For H2O2)
Table 7.10: Atmospheric Condition Assumed
Particulars Details
Wind 3.0 meters/second
Ground Roughness Open Country
Cloud Cover 0 tenths
Air Temperature 40° C
Stability Class C
Relative Humidity 50%
Table 7.11: Source Strength considered
Particulars For Chlorine Dioxide
Tank/Cylinder Diameter 1.0 m
Tank/Cylinder Length 1.15 m
Tank/Cylinder volume 900 kg
InternalTemperature 40° C
Chemical Mass in Tank 2.89 Kg
Circular Opening Diameter 1 inches
Opening from Drum bottom 0.5 m
Internal Pressure at Failure 1.2 atm
Percentage of Tank Mass in Fireball --
Scenario-A1: Release of Chlorine dioxide due to leakage and form evaporating puddle (Not burning)
a) Source Strength
In case of chlorine dioxide gas escape from cylinder by a hole of 1 inch, then approximate average
sustained release rate will be 28.2 g/Sec and hence approx. 1.69 Kg of gas will be released in one
minute as shown in the below Figure-7.1.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 163 2018_ECSS_EIAI1_1800028
Figure-7.1: Source Strength in case of Chlorine Dioxide gas escape
b) Threat Zone
Toxic Threat Zone
Model output and Isopleths result of Toxic threat zone for gas release is given in Table 7.12&Fig. 7.2.
Table 7.12: Threat zone of toxic gas concentration (AEGL Value)
Threat Zone Concentration, ppm Threat Zone
Red 2.4 237 m
Orange 1.1 352 m
Yellow 0.15 862 m
Figure-7.2: Isopleths result of Toxic threat zone
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 164 2018_ECSS_EIAI1_1800028
c) Threat at point
In case of leakage of chlorine dioxide gas from drum through hole and not burning, the
significant effects will be up to 862 m in case of toxic threat zone. Thus the effect in case of any
accident will remain in surrounding of the unit only and there will be no significant concentration or
effect at a far distance to the nearest habitat area.
7.6.6 SAFETY HAZARD
Safety of plant personnel and equipment‟s is of utmost importance irrespective of plant size.
Units should bring its environment, health and safety policy and follow it. The need of safety is to
protect and serve the mankind, to search and suggest the safe ways of behaviour and keeping the safe
working. The concept of safety has developed through three stages: Accident Prevention, Total Loss
prevention and Total Loss Control. The chemical poses more of Occupational Health Hazard, while fuel
posses more of safety / accidental hazards. Hazard & risk assessment has been carried out for
exposure to harmful dust / vapours, liquid pool evaporation or boiling and leakage‟s in confined space.
The hazards involved and its control measures for the chemicals which are being handled or stored in the
premises are given in Table 7.13:
Table 7.13: Hazards and its control measures for Chlorine Dioxide
Types of hazard
/ exposure
Acute hazards /
symptoms Prevention First aid / fire fighting
Fire Not combustible
but enhances
combustion of
other substances,
Oxidising agent
No open flames, No
sparks, and No smoking.
Self-contained breathing
apparatus with a full facepiece
operated in pressure demand or
other positive pressure mode.
Explosion Reacts violently
with organics,
phosphorus,
potassium
hydroxide and
sulphur, causing
fire and explosion
hazard
Provide exhaust ventilation
or other engineering
controls to keep the
airborne concentrations of
vapors below their
respective
threshold limits value.
Ensure that eyewash
stations and safety
Fight fire from maximum distance
or use unmanned hose holders
or monitor nozzles.
Cool containers with flooding
quantities of water until well after
fire is out
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 165 2018_ECSS_EIAI1_1800028
showers are proximal to
the work-station location.
Inhalation Slightly
hazardous in
case of inhalation
(lung sensitizer)
Ventilation, local exhaust,
or breathing protection.
Move to fresh air.
If breathing has stopped, give
artificial respiration.
If breathing is difficult, give
oxygen. Call a doctor.
Skin Irritation to skin Protective gloves and
boots.
In case of contact, immediately
flush skin with plenty of water for
at least 15 minutes while
removing contaminated clothing
and shoes. Cover the irritated
skin with an emollient. Cold
water may be used.Wash
clothing before reuse.
Thoroughly clean
shoes before reuse. Get medical
attention immediately.
Eyes Irritation Safety goggles,
face shield or eye
protection in combination
with breathing protection.
Check for and remove any
contact lenses. In case of
contact, immediately flush eyes
with plenty of water for at least
15
minutes. Cold water may be
used. Get medical attention
immediately.
Ingestion Nausea, vomiting,
or loss of
consciousness.
Do not eat, drink, or smoke
during work.
Do NOT induce vomiting unless
directed to do so by medical
personnel. Never give anything
by mouth to an unconscious
person. Loosen tight clothing
such as a collar, tie, belt or
waistband. Get medical attention
if symptoms appear.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 166 2018_ECSS_EIAI1_1800028
Observation and Recommendation to prevent exposure to chemicals are as follows:
Safety guards (enclosures) is/will be provided on the moving parts of the machines.
Safety hand rails are also provided around the heavy machineries.
Standard operating procedures (SOP) also provided near the machines to read before
operation. It is available in Hindi and English Language which can be easily readable to the
workers.
Personal Protective Equipment (PPE) like goggles, safety shoes, helmet, apron, earplugs,
facemask & clothing is/will be provided to employees as per the job requirements
First aid kit is/will be provided at every working location.
Hand trolley is also used occasionally for manual handling and movement of the raw material
and products.
Proper ventilation is/will be provided throughout the plant.
Eating in plant premises will be strictly prohibited except canteen.
Facilities that allow work clothes to be separated from personal clothes, and for washing /
showering after work are provided.
Policy for periodic health checks will be implemented.
Use of filter respirators when exposed to dust.
Following actions are being taken to ensure safety
1. Procedures of safe shut down and isolation.
2. Actions to be taken if emergency arise from any fire, explosion, collapsing of structures or
equipments etc.
3. Workers are fed with the knowledge of safety measures and controls.
4. The workers are/will be trained for the operation of artificial respiratory equipment such as self
contained breathing equipment.
5. Rehearsals are done so that on-site personnel can fully train themselves for the emergency.
6. Emergency boards are/will be provided at the various places in Punjabi, Hindi and English to
materialize the emergency.
7. Suggestions from the workers will always be welcomed to modify the system as well as to make
system more reliable and effective.
8. Material Safety data Sheet (MSDS) of the chemical used and products are made available at the
place of use also attached here as Annexure -XI.
9. Storage and process areas are posted with “No Smoking” signs. Smoking is prohibited throughout
the factory. All management staff, executives are responsible to ensure compliance.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 167 2018_ECSS_EIAI1_1800028
10. Adequate ventilation is provided in process area so that airborne concentration does not exceed
threshold limit value.
11. On site and off site emergency plan has been prepared.
12. Annual mock drill is regularly carried out to train and aware the workers and other employees in
case of emergency situation as a part of on-site emergency. Record of the same are maintained
regularly.
13. Assembly Point has been decided where all the employees and worker should meet at the time of
emergency occurrence.Counting of workers and employees take place immediately at assembly
point and compared with those present.
14. To provide appropriate instruction, training, retraining and supervision to employees in health and
safety, first aid and to ensure that adequate publicity is given to ensure proper implementation of
fire prevention methods and an appropriate fire fighting service together with training facilities for
personnel involved in this service; To organize collection, analysis and presentation of data on
accident, sickness and incident involving people injury or injury to health with a view to taking
corrective, remedial and preventive action; To promote through the established machinery, joint
consultation in health and safety matters to ensure effective participation by all employees
15. To publish/notify regulations, instructions and notices in the common language of employees
16. To prepare separate safety rules for each type of occupation/processes involved in a plant
17. To ensure regular safety inspection by a competent person at suitable intervals of all buildings,
equipments, work places and operations.
7.6.7 Safety organization
A safety organization is formed in the mill comprising of Technical Director as the Incident
controller. A detailed organization chart of safety organization is given below prescribing the roles of
different personnel‟s roles and responsibilities.
Safety Committee
Safety committee in the mill is formed comprising of HODs and workers in 50:50 ratio. A total of
14 members are part of this committee. A quarterly meeting of the safety committee is started from
November – 2007. The committee shall discuss their plan of action for implementation of safe working
habits among the employees and labourers. They shall also discuss about the accidents happened
during the previous quarter and failure/ negligence to be identified to prevent the accidents in future. A
report of the same shall be sent to the Chief Inspector of factories & boiler for their reference & record.
Details of Inspection Procedures & Systems
The inspection of various equipments like pressure vessels, lifting tools and tackles, etc. are
being carried out on regular basis through an external agency of repute. The agency also issues
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 168 2018_ECSS_EIAI1_1800028
certificate for the proper maintained equipments. A copy of the same is available with maintenance
department in the mill.
Vital Records & methods to their safeguard
All the vital records of the industry are safeguarded in a room and all the necessary measures
like fire fighting arrangement etc. are taken to prevent any danger to the records.
Information to Workers & Public
Safety Awareness among workers
The mill has a full-fledged training room with state-of-the-art training facilities like multimedia
projector, a laptop (computer), trained professionals and subject matter experts to train the employees
& labourers about the hazards present in the mill. All the employees and labourers are given training
bout the mill operations and their work that they supposed to do with respect to safety aspects. The
safety department has films about safety to show to their workers. The training record of each of the
worker is maintained in the personnel department.
Public Awareness and Disclosure of information
The mill does not pose any disaster that may release to environment and affect the people living
in the surrounding. But, to avert any eventuality, the mill is planning to educate people living in the
vicinity about the hazards that are present in the premises.
7.6.8 Observations & Recommendations
From the Risk Analysis studies conducted, it would be observed that by and large, the risks will be
confined within the boundary walls in case of fire & explosion, it will create OFF-site emergency situations
and required more attention and emergency preparedness for combat such situations. To minimize the
consequential effects of the risk scenarios, following steps are being taken.
All the pipelines, equipment & machines are color coded as per the BIS standards mentioned to
protect from corrosion. Also, there is clear demarcation of safe passage routes, emergency exits &
fire exits, safe assembly points etc. in different sections of the plant.
The work permit system is started in the mill on experimental basis and with-in-a few weeks are
expected to be implemented fully in whole of the plant. For its full implementation, the various
training programs are being organized in the mill to train different users from different sections.
The maintenance departments have maintained the entire breakdown/ periodic maintenance
records and the routine maintenance are being carried out strictly as per the schedule. Daily log
books are maintained in the respective departments and all the precautions are taken before doing
any work to prevent the chances of accident, however minor it is.
Plant should meet provisions of the manufacture, storage & import of Hazardous
Chemicals Rules, 2000 & the Factories Act, 1948.
Emergency siren has been provided in the plant to declare emergency.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 169 2018_ECSS_EIAI1_1800028
Emergency handling facilities to be maintained in tip top condition at all time.
Safe operating procedure has been prepared for hazardous process and material handling process.
Safety devices and control instruments to be calibrated once in a year.
Periodic on site emergency mock drills and occasional off site emergency mock drills are
conducted, so those staffs are trained and are in a state of preparedness to tackle any emergency.
Safety manual has been prepared and the same is distributed to all employees and nearby public.
Manual call points for fire location identification to be installed in plant premises.
Induction safety course to be prepared and trained all new employees before starting duties in
plant.
7.7 ONSITE EMERGENCY PLAN AND DISASTER MANAGEMENT PLAN
As emergency is said to have risen when operators in the plant are not able to cope with a
potential hazardous situation i.e. loss of an incident causes the plant to go beyond its normal operating
conditions, thus creating danger. When such an emergency evolves, chain of events which affect the
normal working within the factory area and / or which may cause injuries, loss of life, substantial
damage to property and environment both inside and around the factory takes place and a DISASTER
is said to have occurred. It is necessary for all industries must prepare a Disaster Plan for their
respective operations. The various steps involved in the Disaster Management Plan can be
summarized as follows:
1. Minimize risk occurrence (Prevention)
2. Rapid Control (emergency response)
3. Effectively rehabitate damaged areas (Restoration)
Disaster Management Plan is evolved by careful scrutiny and interlinking of
a. Types and causes of disaster
b. Technical know-how
c. Resource availability
DMP is the term used to express, unpredicted accident /burst/failure of system, causing there by
injury to a large number of persons in and around the mill. For such eventualities, management plan is
prepared as how to tackle disaster and what steps to be taken in case of disaster. This is to ensure that
in case of disaster there may not be a chaos and all the steps are taken with cool and composed
mind. This will definitely reduce the casualties and ensure proper treatment to the victims. The
Disaster Management Plan enumerated in the following pages cover the steps required for
handling any type of emergency at Satia Industries Limited, Muktsar. The safety and health policy
(under Factories Act, 1948) of Satia Industries Ltd, Muktsar is attached as Annexure XII
Identification of hazard
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 170 2018_ECSS_EIAI1_1800028
At the Satia Industries Ltd. the following hazards are envisaged:-
(i) Bursting of digesters.
(ii) Fire in the raw material section where agriculture waste, rice husk stored
Siren Sounding System
S.No. Type of system Type of siren sounding
1 Fire 2 minutes continuous siren
2 Pressure vessel failure 1 minutes siren after every
10 seconds break silence
3 All other After every 5 seconds break silence
inhalations
First aid
Move the affected person immediately to an uncontaminated area, remove contaminated
clothing and wash contaminated parts of body with plenty of water, call a physician and obtain medical
assistance at the earliest.
Failures of pressure vessel
Following preventive measures have been taken to avoid the disaster:-
Each digester is/will be tested internally and externally after every six months and proper
record is maintained.
Hydraulic testing of each digester is performed annually and proper record is
maintained.
Safety valve is provided in each digester and these are tested periodically and proper
record is maintained.
Extra lid locking arrangement is/will be provided for each digester.
Each digester is provided with rigid forged lever and release bolt.
Each digester and its steam line is provided with pressure gauges.
Lock switch (electrical) is provided in each digester so that only the responsible person
can operate the digester.
A register is maintained to keep the record regarding the checking of lid, lid lock, release
bolt etc. before steaming the digester (after closing the lid, lid lock release valve etc. by
operator) these are checked by Shift Incharge/Supervisors on duty and essential entries
are made in the register specially kept for this purpose only then operator can run the
digester.
Safe operating procedure is displayed at various places on operating floor.
Corrosive chemical
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 171 2018_ECSS_EIAI1_1800028
Satia Industries Ltd. has caustic lye and hydrochloric acid storage tanks.
I. Cautionary notices are displayed on board.
II. Precautions to be taken are displayed on board.
III. Floor area is smooth and having adequate drainage system.
IV. Suitable protective wear for hands and feet, suitable apron, face shield, chemical safety goggles
etc. are provided.
V. Tanks and pipe lines are periodically checked and proper record is maintained.
VI. Adequate fresh water supply is there in the area.
VII. Each tank is equipped with level indicator system.
VIII. All flanges in pipe lines are wrapped with PVC sheet.
Fire
The hazardous in mill falls into three categories:-
(a) The storage of raw material.
(b) The paper manufacturing process.
(c) The finished stock storage.
In the paper manufacturing process moisture content, is retained sufficiently enough not to offer
any favourable climate for combustion. However, at the end, paper has 6-7% moisture content and if it
catches fire accidentally will burn instantly. The process includes dry or mechanical friction also.
Types of Disaster:
a. Due to Fire and Explosion
b. Due to Vapour Cloud
c. Due to Toxic Gas Release from:
i. Within the Unit
ii. External Sources
d. Hurricane, Flood, Cyclone and other Natural Calamities
This plan is developed to make best possible use of resources to:
Reduce possibilities of accident.
Contain the incident and control it with minimum damage.
Safeguard others
Rescue the victims and treat them suitable.
Identify the persons affected/ dead.
Inform relatives of the causalities.
Provide authorative information to the news media.
Preserve relevant records and equipment needed as evidence incase of any inquiry.
Rehabilitate the affected areas.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 172 2018_ECSS_EIAI1_1800028
The primary purpose of the on-site emergency plan is to control and contain the incident and so
as to prevent from spreading to nearby plant. It is not possible to cover every eventuality in the
plan and the successful handling of the emergency will depend on appropriate action and decisions
being taken on the spot. Following three staged activities suggested as they are co-related and
provide better points for emergency preparedness, emergency action and subsequent follow up.
A) Pre-emergency activity
The following are the details of Pre-emergency plan:
Internal Safety Survey
It is to be conducted by Safety department.
• To identify various hazards in plant area.
• To check protective equipment of workability.
• To check various safety installations.
• To check fire system, fire water pumps, water shower etc.
• To suggest extra modification required.
Third Party Survey
Experts of consultants can conduct Third Party Survey.
• To identify various hazards inside the factory.
• To conduct survey on available safety equipments.
• To check built in safety system for its efficiency.
• To suggest modification/new additions in the system.
Non-Destructive Testing (NDT)
• To prepare a list of equipments/pipe lines for non-destructive testing.
• To prepare a plan for replacements/repairs as per testing reports.
• To maintain plant wise record to compare with the last period.
Safety valve Testing
• To prepare a lists in the plant.
• To prepare a periodic schedule for their testing & maintaining record.
• To prepare a plan for replacements/repairs.
Fire Fighting system Testing
• To prepare a list of fire hydrants, fire fighting appliances, fire water pumps and other available
appliances and maintain the record.
• To plan for testing schedule.
• To replace defective equipments/accessories.
• To check fire water pumps capacity.
• To check all the fire fighting equipments/appliances under fire services for operability.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 173 2018_ECSS_EIAI1_1800028
Mock drills
• Internal mock drill to be conducted for training the workers.
• Periodic drills to be conducted to check the performance of workers and equipments.
• To know the draw backs/defects of the system and its corrective actions.
Training
• To operate regular training of the employees for handling various safety equipments.
• To train workers for fire emergency.
• To educate workers for different type of emergency.
Personal Protective Equipments (PPE)
• To arrange for sufficient quantity of personal protective equipments.
• To train workers to use each PPE.
• To maintain them in good condition.
Communication
• To maintain internal/external communication system in good working condition.
• To modify the siren sound for emergency.
• To install wind-sacks to indicate wind direction.
Emergency Lights
• To check and maintain the emergency lights in control room and selected areas.
• To keep sufficient number of torches in supervisor‟s cabin/plant and in each department.
Emergency Control Room
• To identify the place of emergency control room.
• To identify the alternative emergency control room.
• To keep sufficient quantity of PPE in control rooms.
• To provide proper telephone system in emergency control room.
• To provide plan of the factory showing hazardous points and emergency control point in
emergency control room.
Assembly Points
• To identify the location for assembling the plant emergency staff and co-ordinate in case of
emergency.
• To utilize the services of others to fix assembly points for non essential workers and to
assemble in case of emergency.
• Considering the kind of disaster & wind direction administrative block & canteen have been
marked as assembly points for the workers who are not working during the execution of
emergency plan.
Liaison with State Authorities
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 174 2018_ECSS_EIAI1_1800028
• To keep liaison with police, fire brigade, factory inspector, collector, local hospital and keep
them informed.
• To inform them about the requirement in advance.
• To keep them informed about mock drills.
Following preventive measures have been taken to avoid disaster
1. Storage area is enough and away from important buildings, especially vital production
and service buildings to ensure that fire is storage area can be prevented from
spreading to the building.
2. Raw material is properly stored in stacks and the sufficient space if provided between
two stacks.
3. Temperature of each stack of raw material is checked every week to avoid the
possibility of auto combustion and proper record is maintained.
4. Water filled chamber is provided on silencer pipe of each and every vehicle before
allowing it to enter in storage area.
5. Smoking is strictly prohibited in mills premises.
6. Hydrants are provided at various points in storage yard.
7. Storage yard is within boundary and at a safe distance from the boundary to avoid fire
from outside the wall.
8. Entire mill is divided in different zones to avoid spread of fire from one zone to other.
9. Fire fighting equipments (fire extinguishers, water-bucket, sand bucket, hydrant
points) are provided at various places in the plant area so that prompt action can be
taken at smouldering stage. Blue print showing location of hydrants is attached.
10. Process area is kept neat and clean.
B) Emergency Organisation
Under these activities, the staffs in the plant at various levels with pre-assigned duties is
expected to work in a coordinated manner to meet emergency situation, remove the emergency
conditions and bring the plant to normal with the help of resources available within and outside the
plant. Availability and correct use of different means of communication and control is an important time
activity.
In case of any accident failure of pressure vessel burst/major fire etc. which may turn into a
disaster, concerned operator or assistant operator/watchman on duty will inform to the On-duty shift In
charge/Supervisor/Security Officer and after that he shall turn back to control the emergency until and
unless Shift In charge comes at the spot. Shift In charge/ Security Officer will inform at one to the
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 175 2018_ECSS_EIAI1_1800028
Rescue Force Co-ordinator and Department Head and then he shall have full control until Rescue
Force Co-ordinator and his crew does not reach at the spot. Department Head shall inform firstly to the
Chief Emergency Co-ordinator and then Chief Plant Co-ordinator after that he shall reach at the spot of
mishap. He shall access the situation and initiate remedial measures.
Sequence of action in case of various types of emergencies (Fire and Leakage of chemicals):
• Any person noticing fire or explosion or leakage of chemicals from pipeline or other equipment,
should attract attention of nearby personnel by using siren available within premises.
• The area is checked clear of people and organize emergency shutdown of the plant/
equipment.
• The total quantity of chemical leaked is ascertained and discharge of Air pollutants through
stack is stopped.
• Other persons in the area should help the injured persons to go out of the place i.e. at
open area and immediately arrange for first aid.
• Simultaneously by telephone he should contact the emergency control centre.
• He should inform the Incident controllers and key personnel depending upon the nature of
emergency.
• He will also guide the outside agency emergency aid services till the incident controller/ site
main controller reaches to the site of Incident.
• As soon as Incident controller/site main controller reaches to the site of incident he will take
charge of the situation and guide/advice in tackling the emergency.
• It is necessary to know that everyone on the site should be accounted for and that the relatives
of causalities have been informed. As plant is small there is no problem of accounting the
personnel. It is necessary to have an up dated list of the names of people at site on holidays
and weekly off days.
• If the situation is not likely to be controlled by the available sources incident controller/site main
controller will assess the situation and declare the emergency as “OFF SITE EMERGENCY”.
• The incident controller/site main controller will continue to do the available resources to control
and contain the emergency till the outside authorities and aid services reaches to the incident
site.
• After District Authority reaches to the site, it will extend all the necessary help, assistance and
give required information/data as when required to control & contain the emergency.
CHIEF EMERGENCY CO-ORDINATORS:-
President (Work)
He shall be responsible for :- (a) Shifting of victims to the hospital if required. (b) Arranging
vehicles to bring the persons/experts required to take care of the incident like doctor etc. (c) Get in
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 176 2018_ECSS_EIAI1_1800028
touch with hospital/nursing homes to get him, prepared to take care of the victims. (d) Contacting other
factories. (e) To take help of the police & fire brigade. (f) Inform Govt. Authorities. (g) To inform new
Agencies. (h) Liaison with govt. bodies.
Following officers and their staff will assist the Chief Emergency Co- ordinator:-
V.P. (P&A): 1. contacting other factories 2. C.M.O./Nursing Homes 3. Police Station.
SR.G.M. Raw Material 1. Shifting of victims to the hospitals. 2. Arrangement of vehicles.
V.P. (Finance): 1. Factory gate
EMERGENCY RESCUE FORCE CO-ORDINATOR:-
Sr. security officer/security officer/Sr. security supervisor shall be responsible for controlling of
disaster shifting of victims from the spot and first aid of victims. Members of team and allocation of
duties are as follows:-
Controlling Crew: Operator on duty, shift In charge on duty, Electrician on duty, fitter on duty, trained
persons on duty, security guards on duty.
CHIEF PLANT CO-ORDINATOR PRESIDENT (WORKS): He shall be responsible for operation of
plant he will take steps to normalizing the mill working after disaster.
COMMUNICATION CO-ORDINATOR V.P. (P&A)
He shall be responsible for communication with the people inside & outside the plant. He shall
keep contact with district authorities, fire brigade, media agencies & workers of the plant. He will be
assisted with his office-staff, security supervisor & liaison officer. He shall also take roll call of the
people in the plant. He will further keep constant touch with Chief Emergency Co-coordinator & apprise
him of the situation.
C) Post – Emergency Activities
A post-emergency base activity of steps taken after the emergency is over so as to establish the
reasons of the emergency and preventive measures to be taken.
The main steps involve:
• Collection of records
• Conducting inquiries and preventive measures.
• Making Insurance claims
• Inquiry reports and suggestions Implementations
Emergency Preparedness Plan (EPP)
EPP involves the constitution of the emergency committee and its preparedness for any
eventuality occurred within and outside of the plant.
The Emergency Plan Organization plan is given in figure below.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 177 2018_ECSS_EIAI1_1800028
(Gases Leakages if any )
Operator/Asstt. Operator
Shift Incharge/Supervisor
Emergency Rescue Force Co-ordinator Section Head
Rescue Force Co-ordinator Chief Emergency Emergency Plant
Victims shifting crew Co-ordinator Co-ordinator
(To dispensary) for Utility Crew
First Aid Mech. Maint. Crew
Elect. Maint. Crew
Factory Gate Civil Maint. Crew
Shifting of victims to the Hospitals Production Crew
Transport
Other Factories
Police
Government Agencies
Liaison News Agencies
7.8 OFFSITE EMERGENCY PLANS
Role of management
1. Immediately sound district administration giving details of accident and impending
risk involved.
2. Sound the fire fighting agencies to be ready for any emergency response.
3. Contact meteorological department to work out the probable course of vapour cloud.
4. Dispatch emergency response vehicle with public address system to warn the public
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 178 2018_ECSS_EIAI1_1800028
of concerned area advising best escape route.
5. Contact Government transport agencies in case of evacuation are required.
6. Contact public health department giving them details of Antidotes/medicines.
7. Contact local police department and inform them of the disaster and area where
effective policing may be required to maintain law and order.
8. Give true story in media so that rumour and confusion could be minimised.
Role of district administration
1. To keep watch on overall situation after the accident.
2. To give direction to nearby hospital of the area, giving them details of accident and
activating them to receive causalities. Designated members of the team should reach
hospital and organise relief operation.
3. To give direction to metrological department and get the data of wind direction from
them, based on this they have to arrive at vapour clouds path and the most likely
localities which shall get affected.
4. Direction to transport agencies and organise evacuation if required.
5. Direction to police department and organise proper security arrangements.
6. Direction to media people and give them the right picture so that rumour mongering
and confusion could be minimized.
7. Organise dry runs of its emergency response programme so that people are aware
of this programme and respond fast to the instructions of his team in an actual
disaster.
8. The proper communication systems should exist so that in an actual situation,
information flows fast.
Role of police
On receipt of information, Police will organise:
- Maintain law and order situation.
- Stoppage of traffic from both ends of the road (Malout –Muktsar Road) if required depending upon
the wind direction.
- Cordoning of the affected areas. Information may be collected from factory gate emergency centre.
- Warning to the people living in the adjacent area for evacuation and safe escape routes if necessary.
- Restricting the entry of unauthorised persons.
- Vigilance in liaison with factory employees against anti-social elements.
- Set up separate communication control point with police head-quarters for reinforcement of required
services giving situation report.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 179 2018_ECSS_EIAI1_1800028
- Extending help in removing of injured persons to the nearest first aid Centre/Hospital, completing legal
formalities in case of any casualty.
- Rescue operation of people affected in nearby localities.
Role of medical service
- To depute doctors and nurses to the factory/affected area with ambulance and provide immediate
medical relief to casualties.
- Transport serious casualties to hospital as deemed necessary.
- Seek help from nearby Hospitals for the following antidotes, emergency occupational medicines etc.
along with the services of expert Doctors
a. Injection dexamethasone.
b. Injection methanlene.
c. Injection avil.
d. Benadril.
e. Philips milk of magnesia.
f. Lasagnas (Victims halls, streusels)
g. Eye Drops.
h. Nose Drops.
i. Glucose Ms.
j. Brancodylitors Injection
k. Transfusion Apparatus.
l. Medicated oxygen cylinder
Role of meteorological department
- Convey early notification of impending changes in weather condition to district authority and factory.
Role of Muktsar municipality
- Arranging temporary shelter for affected/evacuated people.
- Arranging drinking water at site.
- Arranging Snacks etc. for combating team/affected people.
Role of fire brigade
Chief fire officer along with other employees has to rush to the site and give assistance if required.
Role of transport officer District Transport Officer Muktsar
- Control the traffic movement/divert traffic through alternate route if required.
- Arranging vehicles
The list of important telephone no. is given in Table 7.14
List of vehicles is given as Table 7.15. Beside these vehicles, Vehicles from other sources may also be
arranged at the time of requirement.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 180 2018_ECSS_EIAI1_1800028
Table 7.14: Important Telephone No.
Sr. No. Name of Officials Telephone No
1 Hon'ble Dy. Commissioner 01633-263643
2 Sr. Superintendent of Police 01633-263810
3 Dy. Superintendent of Police 01633-263643
4 S.D.M. 01633-262031
HOSPITALS
1 Civil Hospital 01633-262175
2 Mission Hospital 01633-262616
3 Adesh Hospital 01633-262184
4 Rural Hospital 01633-262064
5 Police Station City 80543-70100
6 Police Station Sadar 01633-262028
7 National Insurance Co.Ltd. 01633-262679
8 Fire Brigade Muktsar 01633-262101
9 S.D.O (Telephone) 01633-260742
Table 7.15: List of vehicles
Sr. No Vehicle Number Type of Vehicle
1 PB-30L-9007 Cruiser
2 PB-30T-6215 Bollero
3 PB-30H-9190 Bus
4 PB-30N-4426 Bus
5 PB-04AA-2626 Ambulance
6 PB-30B-9099 Fire Brigade
7 PB-30G-0291 Car
8 PB-30J-3396 Car
9 CH-01PU-2306 Car
10 CH-01AX-6786 Car
7.9 SUMMARY
As a part of the EIA study, an additional study including Risk Assessment (RA) has been carried out for
the proposed project. Public hearing is applicable to proposed project as per MoEFCC‟s OM dated
27/04/2018 as proposed project is fall under Pulp and Paper Industry Cat. 5 (i).The Risk Assessment
addresses major hazards and reviews the effectiveness of selected safety measures and to expand the
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 181 2018_ECSS_EIAI1_1800028
safety measures in order to achieve a safety culture at the industry. The Risk Assessment also
encompasses Disaster Management Study and Occupational Health & Safety.
---------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 182 2018_ECSS_EIAI1_1800028
CHAPTER – 8
PROJECT BENEFITS
8.0 GENERAL
The pulp and paper industry is one of oldest of the core industrial sectors. The socio-economic
importance of paper has its own value to the country's development as it is directly related to the
industrial and economic growth of the country. Although paper has many uses, its most important
contribution to modern civilization is its use as a medium to record information. The pulp and paper
industry offers an incredible opportunity to work with other science and engineering professionals in a
truly high-tech environment that produces environmentally responsible products. The proposed
expansion project at the existing site is well situated and connected by road. These form significant
assets to the proposed project at Village Rupana, Muktsar. Further the project would have lesser stress
on environmental due to manufacture of paper from agricultural residue which has dual benefit of
conservation of wood and other resource apart from solving the disposal problem of agro-residues
which indicates sustainable industrial development. Greenbelt development planned by the proponent
for the proposed project would also add in to the physical infrastructure by adding aesthetic value in the
existing scenario.
Satia Industries Limited (SIL) managed by a professional board of directors proposes the proposed
project. The project envisages expansion in manufacturing capacity of paper production and installation
of CPP at Muktsar – Malout Road, PO.: Village Rupana, Dist: Sri Muktsar Sahib, Punjab – 152032. The
proposed expansion project will transport raw materials, coal, construction materials, equipment and
machineries.
8.1 EMPLOYMENT POTENTIAL
The direct & indirect employment potential of the project would be significantly beneficial for the area.
Skilled and Semi-skilled employment potential in terms of indirect employment of the area will be non-
marginal and will usually remain widespread across a long region. As the proposed modernization
project takes place indirect employment is likely to grow further. Overall assessment of the employment
and income effects indicates that the project has strong positive direct as well as indirect impact on
employment and income generation of the area. Modern paper manufacturing facilities use state-of-the-
art automation and intelligent systems that offer a safe and exciting environment for engineers and
skilled technicians to apply their expertise and education. The persons from different discipline
including Chemical, Mechanical, Electrical, Computer, Electronics and Environmental Engineering find
employment opportunities in pulp and paper industry. Satia Industries Limited has been recruiting
professional in all the specified fields from all over the country with competitive pay packages.
Unemployment for un-skilled workers is quite common in the study area. It is expected that substantial
portion of the investment in this project will trickle down to the local people in the form of employment
and income.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 183 2018_ECSS_EIAI1_1800028
8.2EMPLOYMENT POTENTIAL
Owing to the Primary survey and secondary data, the socio –economic situation portal for 24 villages
located in the radial distance of 10 km suggest the following intervention programs are recommended
under the corporate social responsibility as under:
Since the total sanitation campaign is only 25% of the villages, it is recommended to take it as
priority intervention programs.
The average work participation rate is only 35.6% and that too largely based on cultivation
(70%); followed by labour work (20%) and only 10% for service sector, it is strongly
recommended to start National Skill Development program for the resident youth population to
provide employment.
Since the basic medical facilities is present in only 16.7% of villages, it is strongly
recommended to start mobile health van facilities to make avail health facilities to the resident
population of these villages.
Since only 41% of the villages have natural water facilities and 59% of the villages are having
dry status, it recommend to start lift irrigation program as well as recharge ground water to avail
the water for both drinking and domestic use for the resident population.
Since the Self-help groups are largely witnessed in all the 16.7% of villages, it is recommended
to start micro-credit scheme linked with income generation activities for the young population of
the villages.
The company since its inception is doing philanthropic work and during the last three financial years,
the amount spend in doing philanthropic activities in the nearby villages is around Rs.173 lakhs
approximately - largely expenditure made on developing school infrastructure, Panchayat
infrastructure, eradication of Poverty and hunger, empowerment of women, rural medical camps and
related preventive activities etc.
The project cost is 500.0 Crores; falling under II slab of OM22-65/2017-IA.III Dtd. 1stMay 2018; hence
0.75% of project cost has been allocated for the Corporate Environment Responsibility (CER) i.e.3.75
Crores for doing philanthropic activities for the selective villages and the details is as follows:
Table 8.1 - CER Expenditure
# CER Activity Cost (Rs. in Lacs)
1. Drinking water facility in nearby village 45.0
2 Health and hygiene facilities in nearby village 75.0
3 Plantation in community areas 65.0
4 Skill Development & Training Program 80.0
5 Education related activities 110.0
Total Cost 375
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 184 2018_ECSS_EIAI1_1800028
The villages would be different for each year however the management reserves the decisions
for repeating the philanthropic services in the same villages owing to the need of the community.
The current expenses are tentative and largely will be replaned owing to the demand and
necessity of the community
The budget heads of each activities may vary owing to the demand and also some new activities
later would be added under these assigned budget
8.3DIRECT REVENUE EARNING TO THE NATIONAL & STATE EXCHEQUER
The Indian Paper Industry accounts for about 1.6% of the world production of paper and paperboard.
The estimated turnover of the industry is Rs 25,000 crore approximately and its contribution to the
exchequer is around Rs. 2918 crore. The industry provides employment to more than 0.12 million
people directly and 0.34 million people indirectly. The mills use a variety of raw material viz. wood,
bamboo, recycled fibre, bagasse, wheat straw, sarkanda, etc.; approximately 35% are based on
chemical pulp, 44% on recycled fibre and 21% on agro-residues. The geographical spread of the
industry as well as market is mainly responsible for regional balance of production and consumption.
Over all paper consumption (including newsprint) has now touched 8.86 million tons and per capita
consumption is pegged at 8.3 kg. So far, the growth in paper industry has yielded the growth in GDP on
an average 6-7 per cent over the last few years. Paper consumption is poised for a big leap forward in
synchrony with the economic growth and is estimated to touch 13.95 million tons by 2015-16. The
futuristic view is that growth in paper consumption would be in multiples of GDP and hence an increase
in consumption by one kg per capita would lead to an increase in demand of 1 million tons. With
different taxes including direct and indirect taxes, the pulp & paper industry provides a great return to
the national and state exchequer.
8.4INFRASTRUCTURAL BENEFITS
With the expansion of SIL, there is likelihood of renovation of the existing infrastructure in terms of
storage space for raw material, finished products and installation of new equipment‟s.
8.5 OTHER TANGIBLE BENEFITS
SIL will be an agro-residue based pulp & paper mill so it will reduce the consumption of wood for the
manufacture of paper; moreover, it solves the problem of disposal of agro-residues like wheat straw
and bagasse which are the main raw materials in SIL. The boilers used for the generation of steam
uses rice husk as a fuel rather than using some conventional fuels. In addition, the biogas produced
during anaerobic decomposition of wet washing effluent reduced the organic load of effluents and the
biogas produced is also used as a fuel in boilers which further reduced the requirement of raw material
in boiler.
8.6 SUMMARY
The proponent is very enthusiastic in promoting various welfare activities as a part of moral & social
responsibility. The group has contributed a lot in the field of education, health & other social
responsibilities. Even after the proposed project, the proponent will give physical, social, economic and
ecological benefits to the local population such as development of infrastructure, green cover, social
aids, employment, etc. The proponent has allocated a budget of Rs. 375 lakhs for CER Plan. Through
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 185 2018_ECSS_EIAI1_1800028
local employment and various CER activities it will also give social benefit to the local people and due
to resource conservation it will also give environmental benefit.
--------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 186 2018_ECSS_EIAI1_1800028
CHAPTER – 9
COST BENEFIT ANALYSIS
9.0 GENERAL
Project Cost Benefit Analysis (CBA) is an analytical way to make an educated decision. This involves a
comparison of the costs of an action with considerations of the benefits associated with that action. CBA
assists the regulators to evaluate the benefits and challenges imposed by the upcoming activity in
commercial terms with respective to the impact on the environmental scenario such as human
wellbeing, quality of life and environmental wellbeing.
An important component of a CBA is a base situation which is a situation when no changes take place.
All decisions are then compared to the base situation. Once the base and a relevant time period are
established, benefits and costs can be calculated in terms of human and environmental well-being. In
this case, a benefit is defined as anything that increases human well-being, and a cost is anything that
decreases it. CBA aims to maximize economic efficiency at a point where marginal benefits and
marginal costs are equal.
9.1 APPLICABILITY OF CBA AND SUMMARY
During the scoping/ToR stage, no recommendation of environmental cost benefit analysis was
suggested by the appraisal committee.
Moreover, Proposed expansion of paper manufacturing project of capacity 600 TPD along with 14 MW
CPP will be developed atMuktsar – Malout Road, PO.: Village Rupana, Dist: Sri Muktsar Sahib, Punjab
– 152032. Hence, conducting a detailed CBA is deemed not necessary for this particular project.
-------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 187 2018_ECSS_EIAI1_1800028
CHAPTER – 10
ENVIRONMENTAL MANAGEMENT PLAN
10.0 GENERAL
The Environmental Management Plan (EMP) constitutes an important part of the EIA report. The main
purpose of EMP is to minimize the identified potential environmental impacts to be generated from the
proposed project and to mitigate the consequences. SATIA INDUSTRIES LIMITED, on basis of the
impacts identified, sets targets to reduce the negative impacts, plans and decides action plan to achieve
the target effectively and efficiently. EMP ensures an effective implementation methodology and
alternatives for mitigation measures planned/recommended to reduce or eliminate the adverse impacts
to maximum possible extent during the operation of the proposed project.
10.1 OBJECTIVES OF EMP
In order to develop an EMS, an organization has to identify the impacts, set targets to reduce the
negative impacts, plan and decide the targets as well as set proper and appropriate steps to achieve
the targets effectively and efficiently.
To comply with all the regulations stipulated by Central /State Pollution Control Boards related to
applicable laws.
To create good working conditions.
To encourage support and conduct developmental works for the purpose of achieving
environment standards and to improve methods of environment management.
Streamline environmental activities to add value to efficiency and effectiveness.
To encourage and achieve highest performance and response from individual employees and
contractors.
To plan out the complete strategy to take care of stakeholder engagement.
To contribute significantly for sustainable development.
10.2 ENVIRONMENTAL MANAGEMENT PLAN
10.2.1 Land Environment & Solid/Hazardous Waste Management
Construction Phase
Vegetation clearance will not be a major issue as the proposed project will be carried out in open
land with no vegetation, which is dedicated for industrial purpose only.
The major problem will be disposal of excess excavated earth generated during construction
phase which shall be well handled by landfills to level the low lying areas. Excavated earth will be
covered by plastic/tarpaulin sheets unless it is disposed off. Also a part of the earth material will
be used in the Green Belt Development.
Good waste handling practices will be implemented.
Separate earmarked storage area with pucca floor/lining will be provided for the storage of fuel.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 188 2018_ECSS_EIAI1_1800028
Further, the proponent has planned to develop the Green Belt Area within the premises, which
shall prove to be beneficial from all aspects and shall effectively compensate the minor impacts.
Care shall be taken that domestic sewage of construction workers is not disposed off on land, it
will only be disposed off in septic tank/soak pit.
No wastewater from construction site will be allowed to dispose off on land.
Sanitation facilities will be provided to the workers for maintaining sanitation and clean
surroundings.
Regular monitoring/ checking/ inspection of the sewage network system will be done to avoid
clogging of sewers and thereby sewer overflow is avoided.
Operation Phase
For storage and handling of Non-hazardous Solid Waste and Hazardous Waste adequate storage area
with pacca flooring will be provided. All the waste shall be disposed as per Hazardous Waste disposal
Rules 2016.
A separate earmarked storage area shall be provided with sign boards/labels for storage of
hazardous waste.
The storage area will be properly lined to prevent mixing of waste spillages into the soil/land.
Proper Handling & transportation facility for Hazardous waste will be provided.
Storage silos will be provided for fly ash and dense pneumatic system will be provided for fly ash
collection.
Rice Husk will be stored in closed storage yard with pucca flooring, closed conveyor belt shall be
provided for transfer of rice Husk.
Treatment, Storage & Disposal mode for the same will be followed as per Hazardous Waste
(Storage, Handling & Trans-boundary Movement) Rules, 2016.
100% utilization of ash by brick/cement manufacturing industry.
ETP Sludge will be disposed by selling to cardboard manufacturers.
Regular monitoring/ checking/ inspection of the sewage network system will be done to avoid
clogging of sewers and thereby sewer overflow will be avoided.
a. Details of Hazardous Waste Generation & Disposal:
Table 10.1 - Waste Disposal Details
S.
No. Type
Source Quantity, TPA Disposal
Existing Proposed Total
Hazardous Waste
1. ETP Sludge
(Category: 32.3) ETP 10.00 7.00 17.00
Dispose off to local
cardboard
manufacturers.
2. Lime Sludge Causticizing 173.75 76.05 227.30 Disposed to Cement
Plants (MoU attached)
Solid Waste
1. Fly Ash Boiler
House 63.75 51.25 115.00
Filling of the low lying
areas, forestry plantation,
for brick manufacturing
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 189 2018_ECSS_EIAI1_1800028
b. Storage of Solid/Hazardous Waste:
Solid and hazardous waste will be stored separately. Adequate storage area will be provided
of the storage of the same.
Hazardous waste will be stored in yard within the plant boundary with pacca flooring, prior to
final disposal as per MoEFCC Guidelines/Notification.
Separate Hazardous waste will be stored in designated storage area with concrete flooring
and covered shed will be provided for storage of solid/hazardous waste.
c. Transportation of Solid/Hazardous Waste:
Properly packed & labeled waste will be transported through dedicated vehicle to end user
facility.
Closed/covered trucks will be used for waste transportation.
d. Disposal of Solid/Hazardous Waste:
Provision of Solid/Hazardous waste collection system & storage area confirming the guidelines
provided by CPCB for Solid/hazardous waste generation.
Lime sludge will be disposed of by selling to Cement Industry.
ETP Sludge from waste water treatment will be collected and disposed of by selling to local
cardboard manufacturers.
Regular training will be carried out for employees engaged in Solid Waste Management Works.
10.2.2 Air Environment Management
Construction Phase
Potential sources of air pollution during project construction will be (i) dust emissions due to vehicle
movement and (ii) exhaust emissions from diesel generators and construction equipment. The impact on
air quality during construction phase will be minimized by adopting following mitigation measures:
Dust suppression by regularly spraying water on roads and work sites will be practiced.
Wetting or covering stockpiles, the proper location of material stockpiles and covering loaded
trucks during the transportation of material will be ensured.
Loading/Unloading of construction materials will be done in a proper way to avoid dust generation.
Use of low-emission vehicles and, wherever feasible, construction equipment powered by
electricity will be preferred.
Maintenance of engines and use of vehicles with valid PUC Certificates. Contractors will be
required to strictly implement these measures.
Engines of idle vehicle machineries/equipment shall be turned off.
Regular inspection for proper implementation of mitigation measures will be done.
Barricading will be done at the construction site.
Operation Phase
Company will adopt the following mitigation measures to reduce the impact on air environment:
Vehicles with valid PUC certified will be used for the transportation of materials and Machinery.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 190 2018_ECSS_EIAI1_1800028
The trucks used for transporting the goods will be covered by the tarpaulin and overloading in
trucks shall not be allowed to prevent the dusting.
Strict adherence will be implemented for maintenance schedule including lubrication for various
machinery/ equipment.
Good material handling practices will be carried out.
Regular water sprinkling will be done on roads and stock yards (if any) to avoid dust generation
from handling.
Highly efficient ESP is being/will be provided to reduce the flue gas emissions from the CPP.
Online monitoring station for Regular ambient air quality monitoring will be provided within the
premises for PM, SOx and NOx.
Regular ambient air quality monitoring through third party will be carried out within premises and
in the nearby area for PM, SOx and NOx.
Greenbelt around the factory will be developed for reducing the air pollution and attenuation of
noise.
No odour will be generated as proposed project is waste paper based. However general
measures like good housekeeping, proper disposal of effluent and sewage, not allow water to be
stagnant, etc
Good house-keeping will be maintained in the premises.
Periodic monitoring of work area will be carried out to check the secondary emission.
Rice Husk and Fly Ash handling practices:
Following practice shall be followed for transportation; storage and handling of rice husk and fly ash to
reduce the fugitive emission.
The trucks used for transporting rice husk and fly ash will be closed truck or covered by the
tarpaulin.
Regular water sprinkling will be done on fly ash.
Rice Husk will be transferred to boiler through closed conveyor belt to reduce the chance of
fugitive emission.
High efficient Electrostatic Precipitator (ESP) is being/will be provided as APC device with boiler.
Adequate stack height of i.e. 65 m each with Stack Monitoring Facilities (SMF) will be provided for
better dispersion of pollutants.
No ash pond will be constructed for storage of fly ash. Fly ash will be stored in closed silo.
Dense pneumatic system shall be provided for handling of fly ash.
Electrostatic Precipitator (ESP): Electrostatic dust precipitation is the most economical and widely
applied method for de dusting and demisting of gases. An Electrostatic Precipitator (ESP) will remove
dust particles from a flowing gas using a force of an induced electrostatic attraction (i.e like charges
repel, unlike charges attract).
Construction and Working: The ESP will have two or more fields, which will operate independently
from each other. The specially contoured plate collecting electrodes arranged parallel to the gas stream
shall be suspended by top supports from the suspension beam.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 191 2018_ECSS_EIAI1_1800028
The lower ends of the electrodes shall be held in rapping bars. Discharge electrodes held in
frames will be located between the rows of collecting electrodes. The discharge system of
each field shall be supported on solid HT porcelain insulators located at ESP top.
The flue gases after economizer will be channeled through ducts to the precipitator and evenly
distributed over the whole section by means of distribution baffles. The negative high tension
produced by the HT sets shall be applied to the discharge electrodes.
At the tips of these electrodes, a corona effect will be produced due to the high voltage. This
corona effect shall separate the gas molecules negative and positive ions. Now the negatively
charged particles will be attracted by positively charged collecting electrodes.
The discharge system and the collecting electrodes shall be periodically cleaned by means of
rapping devices. The dust falling down into the hoppers will be extracted by the dust
conveying system.
Components in ESP are Electrodes, high voltage transformer, rectifier, Insulators and Hopper.
Table 10.2 - Technical Specification of ESP
S. No. Particulars Unit Details
1 ESP Model 3423/4F
2 Design Volume Am3/h 187690
3 Design Temperature Deg. C 140-150
4 Maximum Inlet Dust Load g/Nm3 22
5 Outlet Emission Mg/Nm3 30
6 Moisture in Gas %V/V 14.87
7 Collection Area m2 9321
8 Specific Collection Area M2/m3/s 143.56
9 No. of Gas Passages No 1
10 Velocity through ESP m/s 0.63
11 No of Fields No 04
12 Migration Velocity Cm/s 4.6
13 Treatment Time Sec 28.7
14 Dust Collection Efficiency % 99.93
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 192 2018_ECSS_EIAI1_1800028
Figure 10.1– Schematic Flow Diagram of ESP
10.2.3 Water Environment
Construction Phase
Water requirement during the construction phase will be obtained from Arniwala Canal. No ground
water shall be used for construction activity.
Further the proponent will ensure to implement good operation practices to minimize the use of
water so as to reduce the consumption of water to maximum possible extent.
Proper drinking water facility will be made available to the construction workers.
Due care will be taken to avoid formation of stagnant pools, which may cause damage to the
aesthetic condition as well as other environmental & socioeconomic factors.
Proper sanitary facility will be provided for construction worker during the construction phase and
waste will be treated in soak pit system.
Operation Phase
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 193 2018_ECSS_EIAI1_1800028
During the operation phase of proposed project, total24,000 KLD water will be required which will
be sourced from Arniwala Canal.
Adequately designed sewerage treatment plant for domestic effluent.
Total industrial effluent will be treated in modified ETP.
Water consumed in CPP will be optimized to maximum possible COCs to reduce overall water
consumption.
Evaporation losses from the CPP will be minimized by energy efficient coolers/condensers and
evaporators.
Sewage will not be allowed to release in the river/canal water. Domestic sewage is/will be treated
in the septic tank/soak pit.
Good waste management and handling practices will be adopted for waste management to
prevent mixing of wastes into water/wastewater.
Properly lined/paved surfaces will be provided within the premises to prevent leakage/spillage of
untreated sewage into the land and groundwater sources.
All the wastes will be handled/ disposed according to the Waste Management Rules, 2016.
Online continuous pH meter, TOC analyzer and flow meter will be at provided at the final outlet of
the ETP.
Regular monitoring of water, wastewater and sewage shall be done as per the monitoring
schedule planned as a part of Environmental Monitoring Plan.
Rain water harvesting schemes will be included as part of water conservation measures.
Maintaining records of water consumption, water characteristics and sewage characteristics.
Maintenance of good housekeeping to avoid contamination of storm water.
Description of Effluent Treatment Plant
Bio Gas Plant:
The effluent from the wet washing is passed through four numbers of settling pits for removal of sand
and grit and then passed on to the DSM screens to remove light weight raw material particles through
it. These are collected and sent back to the process for cooking. The clear effluent is then fed to
equalization tank where the pH & alkalinity is maintained by adding lime to it. The effluent is then
passed to the primary clarifier where the settled sludge is scrapped and pumped into Mark saveall for
thickening. The clean effluent is collected in buffer tank meant to provide residence time prior to feeding
in the anaerobic reactor.
There are two UASB rectors in parallel with a capacity of 3500 m3 each to treat wet wash effluent. The
methane gas is collected on top of the reactors with the help of 3-fold hood, provided to catch even
minor gas generation. The gas is collected in a gas holder and sent to boilers to produce steam. The
effluent is separated from the gas and is taken into two nos. of tube settlers. This helps in removing the
excess anaerobic sludge from the effluent and the collected sludge is recycled back into the anaerobic
reactor. The overflow of the reactors is finally cleared in the secondary clarifier. Then the effluent mixed
with bleach effluent is fed in to primary clarifier. Nutrients in the form of Urea & DAP are fed in a certain
ratio of BOD: N: P (100: 2.5: 0.5).
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 194 2018_ECSS_EIAI1_1800028
The sludge generated from both the primary clarifiers is dewatered by sludge press and centrifuges.
The excess sludge from both secondary clarifiers is recalculated within the respective system. The
filtrate (having approximately 75% moisture) is sold to cardboard manufacturers.
Effluent Treatment Plant:
Effluent from Bio Gas Plant, Bleaching section of pulp mill and other minor streams are mixed in the
bleach pit prior to feeding in the primary clarifier. The solids are allowed to settle down in the primary
clarifier and the clear water is passed to Aeration Tank no. 1. The effluent is provided with urea & DAP
along with re-circulated MLSS from the intermediate clarifier to maintain the levels of MLSS in aeration
tank. The AT-1 is equipped with 1390 nos. of 300 mm dia. disc diffusers and one turbo blower of
capacity of 8400 Nm3/hr and 6 No. of jet aerators are provided for maintaining dissolved oxygen level in
the tank. Jet aerators are connected with pure oxygen injection system to increase the dissolved
oxygen level and increase the efficiency of the system. The effluent from AT-1 is then pumped into the
two nos. of intermediate clarifier for removing the MLSS from it which is pumped back into aeration tank
no.1. The semi clear effluent from intermediate clarifier is passed to AT-2 which is equipped with 1390
numbers of tubular diffusers and one blower of 4200 Nm3/hr. AT-2 is also equipped with 4 numbers of
surface jet aerators connected with pure oxygen injection system to increase the dissolved oxygen
level and increase the efficiency of the system. The overflow of AT-2 is sent to final clarifier for more
clarity. The final effluent is discharged into the plantation area where eucalyptus plantation is
developed to consume the total quantity of effluent into the plantation area. In order to replace fresh
water requirement part of quantity reused in ETP for cleaning of diffusers, and Sludge washing to
replace fresh water.
Table 10.3: Existing equipment’s with dimensions, volume and retention time
S. No.
Particulars Dimensions (m) Volume
(m3) Retention Time
(h)
1. (Biogas Plant) Primary Clarifier 20 (dia.), 3.5(SWD) 1099 4.5
2. Equalization Tank 8 m x 8 m x 3.5 m 224 0.45
3. Buffer Tank 28.0 (dia.), 3.0(SWD) 1846 7.0
4. UASB Reactor 1 & 2 23.6 (dia.), 7.8 (SWD) 3500 28.0
5. Secondary Clarifier 26 (dia.), 3.5 (SWD) 1857 6.0
6. (ETP ) Primary Clarifier 30 (dia.), 3.8 (SWD) 2685 4.00
7. Aeration Tank-1 67.4 m x 46.2 m x 5 m 15570 23.0
8. Intermediate Clarifier No.1 18 (dia.), 3.86 (SWD) 982 1.5
9. Intermediate Clarifier No.2 18 (dia.), 3.86 (SWD) 990 1.5
10. Aeration Tank-2 59.5 x 42.8 x 4.35 11078 16.0
11. Final Clarifier 28.7(dia.) , 4.6 (SWD) 2975 4.5
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 195 2018_ECSS_EIAI1_1800028
Table 10.4: Characteristics of Raw Effluent at the Inlet and Effluent after Treatment after
Expansion
Parameter Influent Effluent after Treatment
Flow (m3/day) 21,499 21,499
pH 7-7.6 6.5-8.5
Suspended solids (mg/l) 400-500 <50
BOD (mg/l) <250 <30
COD (mg/l) <800 <200
Modifications proposed in ETP plant include
Machinery up gradation like pumps, air blowers, pipelines, valves etc. to handle the increased hydraulic
load.
Introduction of Decanters in Bio Gas plant and ETP for excess MLSS removal from system and the same
sludge will be used in our own plantation as Manure
Increasing hydraulic load of COD/BOD in both streams to control outlet of Biogas Plant COD/BOD, the
industry will introduce one more High Rate Solid Contact Clarifier (HRSCC) after anaerobic treatment.
Addition of pure oxygen injection system through Jet aerators in aeration tank for better organic reduction
and it will increase SOT efficiencies.
The industry will introduce primary aeration after anaerobic followed by MBBR technology to reduce
COD/BOD load on secondary effluent treatment plant.
Up gradation of Final clarifier to HRSCC to reduce TSS carry over.
Figure 10.2–Existing ETP schematic Flow Diagram
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 196 2018_ECSS_EIAI1_1800028
Figure 10.3 –Proposed ETP schematic Flow Diagram
Chemical Recovery Plant:
SIL has state of the art Chemical Recovery Plant which was first commercially employed energy
efficient technology to treat Black Liquor.
CRP is one of the Best Available Technology (BAT) with high energy efficiency and reduced emissions.
The company has already two chemical recovery boilers of 50TPH and 25 TPH (stand by) capacities to
treat black liquor generated during wheat straw and wood chips pulping. In this expansion, Company
proposes to upgrade existing (RB1) 25 TPH stand by boiler to 75 TPH and (RB2) 50 TPH will remain
as stand by.
The brief description of existing CRP is given below. The plant is divided into three sections:
Multiple Effect Evaporator (To concentrate weak black liquor)
Chemical recovery boiler
Causticizing Plant
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 197 2018_ECSS_EIAI1_1800028
Figure 10.4 - Flow Diagram of Chemical Recovery Plant
10.2.4 Biological Environment
Construction Phase
Proposed project is located in Rupana Village located app. 5.50 km away from Sri Muktsar Sahibcity in
South direction.
The construction workers shall be instructed to clear the area at the earliest.
During the construction phase no impacts on flora and fauna are envisaged.
Further the management shall carry out Green Belt Development & Management Plan for the
proposed project.
The upbringing of Green Belt will prove to be an ideal dwelling place for diversified flora and
fauna and also adds to the aesthetic beauty of the area, hence regular care for maintenance &
protection shall be taken by the proponent.
Operation Phase
During the operation of the proposed project, no major harm will be caused to the ecology as there will
be no major source of pollution after implementation of mitigation measures for pollution control using
necessary technology/method/system. Further, the greenbelt development in the project area shall
improve the existing ecological condition of the area. Thus no special mitigation measures are required
for ecology conservation during the operation phase. As it is already discussed in previous chapters,
that no major harm will be caused to the ecology as the area is free from any form of human
settlement, forests, national parks, etc. However, as it is noticed that the greenbelt development will
improve the ecological condition of the area, following care shall be taken as mitigation measures:
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 198 2018_ECSS_EIAI1_1800028
Management shall ensure that all possible efforts are being made to maintain healthy greenbelt
developed in & around the plot area.
The management shall also provide all necessary materials/requisites for development,
maintenance & protection of the greenbelt.
Regular irrigation, fertilization & pest control program shall be a part of routine activity during the
operation phase.
The upbringing of Green Belt will prove to be an ideal dwelling place for many avifauna and
terrestrial fauna, hence care shall be taken to avoid any harm to the faunal community being
settled in the greenbelt.
Regular records of greenbelt development activities with necessary statistics will be maintained.
Greenbelt Development Plan:
The company shall developed extensive greenbelt within the premises as per guidelines given in
layout. A greenbelt will be developed around the periphery and within the plant premises. The
greenbelt landscape plan will provide benefits to improve beautification. It will also result in the
prevention of land degradation due to construction activities; enhancing the canopy cover as a wind
breaker wall and restrict the carry away of the Particulate Matter (PM) outside the premises as well as
for noise abatement. After the project implementation, regular assessment will be done to make sure
that greenbelt is growing adequately with all necessary works like thick plantation, rearing, irrigation,
fertilization, re-plantation (if required), pest control and other factors. Regular records of the greenbelt
development as suggested in environmental monitoring plan will be maintained.
Multi-layered plantation comprising of medium height trees (6-8m height) and shrubs (3-5m height) will
be proposed for the green belt. The plan comprises of a five year program from 1st year to 5th year for
greenbelt development.
(i) Plan for 1st year (Trees/Saplings Plantation)
The work plan for the first year, during the construction phase
- Digging of pits and soil conditioning
- Planting of saplings
- Surveillance maintenance and irrigation of the saplings to achieve maximum survival
(ii) Plan for 2nd year (Additional Trees/Saplings Plantation + Replacing Dead Trees)
The work plan for the second and third year
- Maintenance and irrigation of species planted earlier.
- Survey of the area to identify the locations for replantation and causality replacement
- Removal of dead trees and replantation based on specific location requirements
- Maintenance and irrigation of plants to achieve a targeted survival rate of 75%.
(iii) Plan for 3rd and 4th year (Replacing Dead Trees + Maintaining the Greenbelt)
The work plan for the fourth year
- Maintenance and irrigation of species planted earlier.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 199 2018_ECSS_EIAI1_1800028
- Survey of the area to identify the locations for replantation and causality replacement
- Removal of dead trees and replantation based on specific location requirements
- Maintenance and irrigation of plants to achieve the targeted rate at 100%.
(iv) The work plan for subsequent years comprises (Maintenance)
- Maintenance of plantation.
- Clearing of afforested areas to remove undesirable species
- Replacement of dead and diseased/malformed species with new ones
Figure 10.5 - Greenbelt Development Layout
Selection of Species for Greenbelt
Selection of plants for green belt plantation will be made on following criteria:
• The plant should be a fast growing species.
• It should have deep root system.
• Should bear the leaves for a longer period.
• Should be a local species.
• Should have good survival rate.
Table 10.5 - Species Selection for Pollution Control
Plant Species Habit Tolerance Limit Stomatal Index Mode of
Regeneration
Acacia auriculiformis Tree T 10.9 Seeds
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 200 2018_ECSS_EIAI1_1800028
Azadirachtaindica Tree T 29.2 Seeds
Bougainvillea
spectabilis Shrub T 32.53 Cutting
Delonixregia Tree S 14.38 Seeds / stem
cutting
Ficusreligiosa Tree T 18.70 Stem cutting /
Seeds
Ficusbengalensis Tree T 21.72 Stem cutting /
Seeds
Hibiscus rosa-sinensis Shrub T 23.2 Stem cutting
Lantana camara Shrub T 12.13 Seeds / cutting
Neriumindicum Shrub T 15.7 Cutting
Polyathialongifolia Tree S 22.27 Seeds
Syzygiumcumini Tree T 20.60 Seed, cutting,
grafting, budding
Terminaliacatapppa Tree T 20.9 Seeds
Thespesiapopulneoides Tree T 29.81 Seeds/ cutting
Source: Guidelines for Greenbelt Development, CPCB, March, 2000.
All the above mentioned species are ideally suited for the ecological habitat of Sri Muktsar Sahib
Region, Punjab. Their planting should be interspersed with each other to create mixed canopy of the
plants and the ideal distance for planting all trees is 3 m X 3 m. SIL has already developed Greenbelt
and it shall be further enhanced as per norms after grant of EC for proposed expansion.
Preservation and Maintenance of the Green Cover
The success of a designed greenbelt/landscape depends upon the growth of vegetation over an
extended period of time; therefore maintenance of greenbelt/landscape is also a design component.
The following steps will be followed for maintaining a healthy green belt and landscape:
Regularly watering the plant depending on the rainfall, wind conditions, moisture and drainage
pattern. Too much or too little water can also damage a plant.
Watering shall be done such that there is time to allow the water to percolate deeply and
uniformly.
Grasses and landscapes will be watered with the help of sprinklers, so as to avoid wastage of
water.
Adequate mulching must be maintained near the roots of the plants or even on the soil to retain
moisture, suppress weeds, increase water percolation and reduce soil erosion.
Plants must be regularly fed with organic manure to fulfill their nutrient requirement.
Regular hoeing, cutting, trimming, mowing and removing weeds should be carried out for
maintaining the greenbelt.
For the Calculation of Cost for Green belt Development, following parameters have been considered.
For Capital Cost
a) Cost of Sapling (Trees)
b) Shrub/Herbs
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 201 2018_ECSS_EIAI1_1800028
c) Transportation Charges
d) Planting cost (Including soil workings, pits etc.)
e) Fencing Cost
For Recurring Cost:
a) Cost of drip irrigation
b) Annual weeding and soil working
c) Req. of water for irrigation
d) Fertilization Cost
e) Security and Vigilance
A budget of Rs.20 Lakhs as a capital cost and Rs. 5 Lakhs per Annum as a recurring cost has been
allocated for green belt development.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 202 2018_ECSS_EIAI1_1800028
Figure 10.6 Photographs of Existing Green Belt
10.2.5 Noise Environment
Construction Phase
Following measures will be taken for abatement of noise during construction phase:
The proponent will ensure that no noise hazard is caused due to noise generation during the
course of construction works. For this purpose, the proponent will ensure that the workers are
provided with individual personal protective equipment‟s like ear muffs or ear plugs in areas with
high exposure to noise.
Further, it will also be ensured that periodic and regular maintenance of the equipment, machines
and spare parts is carried out which shall include lubrication, replacement of defective parts etc.
in order to bring down the decibel of noise to maximum possible extent. Idle vehicles/machines
and equipment will be switched off.
Noise generation due to movement/operation of vehicles & equipment/ machineries shall be well
managed by restricting the movement/operation during night hours.
Regular lubrication & preventive maintenance shall be done to reduce noise generation.
Further, the vehicles will strictly adhere to the Traffic Management Plan, which will specifically
aim at reducing the nuisance due to noise generation.
Operation Phase
The fact that the proposed project is situated at a distance of human settlement, significant impact on
human settlement is not envisaged. The company shall develop a green belt around the periphery of
the premises, which will act as a barrier to the propagation of noise from the factory premises. This will
further reduce the noise levels appreciably. It is recommended to measure and maintain records of
noise level at various places within and outside the factory premises. Following measures will be
adopted for abatement of noise during the operation phase:
The major noise producing equipment such as turbine, Pumps, fans, compressor, etc. will be
statically and dynamically balanced and rubber padding will be provided, wherever possible.
A well formulated and strictly implemented Traffic Management Plan will be in place to mitigate
noise impacts due to transportation vehicles.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 203 2018_ECSS_EIAI1_1800028
All vehicles shall maintain speed limit inside the premises and unusual acceleration of engine &
loud horns shall be prohibited.
Adequate greenbelt shall be developed and maintained around the plant premises to help in
attenuation of noise.
Regular lubrication & preventive maintenance shall be done
totools/equipment‟s/machinery/vehicles reduce noise generation.
Due to power plant operations, noise pollution arises from Turbine, Compressor, Generator
Room, etc. higher noise level will be felt only near the active working areas
Owing to the above fact, use of PPE like ear plugs and ear muffs is made compulsory near the
high noise generating machines.
The personnel shall be provided breaks in their working hours, with the continuous exposure not
increasing three hours.
Periodic monitoring of noise levels as per post-project monitoring plan shall be done on regular
basis.
10.2.6 Occupational Health & Safety
Construction Phase
SIL has planned to appoint/hire construction firms and the construction work will be carried out by well-
known contractors. However, occupational health & safety will be the prime focus during the
construction stage. Occupational health & safety of the construction workers will be ensured with the
following measures:
The management shall ensure that all workers/employees shall be provided with basic Personnel
Protective Equipment‟s (PPEs) like ear plug/muff, safety helmet, safety gloves, safety goggles,
safety shoes etc.
The management shall also ensure that the quality of these PPEs will properly checked before
providing to the workers. It shall also be ensured that all the safety equipment are placed
properly and are available instantaneously when required.
Management will also ensure to have safety and first aid facility for the workers/employees
engaged in the working of the plant in order to provide them with necessary treatments in case of
accidental mishaps or their health breakdown.
Necessary training will be imparted to the required workers/ employees in various aspects, viz.
handling of the materials, precautionary measures to be taken while working, how to use the
safety equipment, etc. so as to make all workers literate, thus minimizing the chances of any
accidental mishaps.
Proper care will be taken to provide the migrant laborers with clean hygienic residence
accompanied by basic amenities like drinking water, sanitation, etc.
Arrangements for medical facilities will also be made in case of any disturbance in health during
the course of work.
The following measures shall be taken to provide basic facilities to the workers:
All the basic facilities like tap water, sanitation, drinking water, lunch space will be provided.
First aid box, free medicines, etc. will be available within the project site.
Adequate PPEs will be provided to all workmen during construction phase.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 204 2018_ECSS_EIAI1_1800028
Operation Phase
The proponent is very much concerned in terms of health, safety and environment protection. The
proponent is committed towards safety and proponent has prepared „Health, Safety & Environment
Policy‟.
The company has already engaged a qualified Safety Manager and a Doctor for regularly checking
health of the employees. Additionally, medical aid will also be arranged with the help of local hospital.
Annual health check of the employees will also be carried out and records will be maintained. Regular
training to the employed personnel in safety, firefighting and first aid will be provided. A budget of
approx. 50 Lakhs has been allotted for Occupational Health & Safety.
Safety Measures:
The following key safety measures will be implemented in the proposed project:
1. Safety Training is being/will be provided to the employees.
2. Safety Sirens with Alarm System in case of emergency is being/will be provided.
3. Emergency Control Room is being/will be established.
4. Assembly points is being/will be defined for safe gathering of the employees during the times of
emergency.
5. Fire Hydrant System will be installed.
6. Fire Extinguishers are being/will be provided.
7. Mock drills are being/will be periodically conducted and factors like response time will be evaluated.
8. Fire squad team is being/will be formed for handling any emergency situation & regular training of
squad team will be conducted.
9. First Aid Facility and training is being/will be provided.
10. Personal protective gears and equipment‟sis being/will be provided to employees.
11. Health check-ups are being/will be organized at regular intervals.
12. Safety / Health records are being/will be maintained.
Housekeeping
Proper housekeeping is an essential part of sound environmental management. Good housekeeping
practices will be carried out during the operational activities of the proposed project. It will be rigorously
seen that there is no accumulation of wastes, especially combustible wastes inside the plant area.
In summer dry grasses & vegetation growing inside the plant area will be cut and removed. All
firefighting equipment and warning devices will be kept in perfect working conditions at all the times. It
will be seen that all personnel are aware of the implications of environmental pollution and simple
practices to avoid pollution and untidy workplaces.
General DOs and DON’Ts for preventive maintenance:
- DOs
o Store fuel and hazardous waste in isolated space
o Covered confine area by personnel enclosure,
o Immediately report leaks, spills or failures of the engineering controls.
o Post "NO SMOKING" signs in area.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 205 2018_ECSS_EIAI1_1800028
- DON’Ts
o Don‟t enter hazard prone area without PPE.
o Do not use with incompatible materials.
o Do not take any flammable material inside the fuel storage area.
10.3 TRANSPORATION/TRAFFIC MANAGEMENT PLAN FOR VEHICLES
According to the proposed requirement of the project, the material handled at the project site is large.
The proponent has developed a good network of internal peripheral roads with separate entry and exit
for the safety and access requirements to various buildings and yards and same is beingmaintained
throughout the year.
As a part of EIA study the EMP for traffic management is presented in the following table:
Table 10.6 - Traffic Management Plan
Objective To ensure that there is smooth traffic within and outside the facility for the duration
of the construction phase and operation phase
Concern Trucks, lorries, tankers/dumpers and other vehicles may cause traffic jam outside
and within the premises.
Impacting Activity Mitigation Measures
Measures for management
Location &
Timing Responsibility Monitoring
Vehicular
movement
Controlled vehicular
movement
(preferably with
clearly demarcated
entry/exit) with
adequate supervision
Within and
immediately outside
the site -
Construction &
Operation Phase
Contractor/
Project
Manager during
construction
phase.
Security and
concerned
departments
during
operation
phase.
Security-in
charge and
Security
Team
Demarcation of
separate vehicular
lanes and pedestrian
routes/footpaths
Within the site -
Construction &
operation phase
Contractor/
Project
Manager during
construction
phase.
Security and
concerned
departments
during
operation
phase.
Security
Team
Vehicle entry and exit Within and Contractor/ Security-in
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 206 2018_ECSS_EIAI1_1800028
scheduling so that
traffic congestion is
not created on the
external road leading
to the site
immediately outside
the side -
Construction &
operation phase
Project
Manager during
construction
phase.
Security and
concerned
head of
department
during
operation
phase.
charge and
Security
Team
10.4 CLEANER PRODUCTION PRACTICES
Cleaner Production (CP) is defined as the continuous application of an integrated preventive
environmental strategy applied to processes, products and services to increase overall efficiency and
reduce risks to the environment including human beings. Unlike the pollution control which is an after
event „react and treat‟, CP is a forward looking approach, „anticipate and prevent‟.
The following CP actions have been defined for the proposed project as a part of their integrated
preventive environmental strategy:
10.4.1 Conservation of Water
The conservation program for the proposed project activity shall aim at reducing wastage of water, raw
materials, power and fuel.
Water Conservation and Rainwater Harvesting:
Water free turbo blower for machine vacuum requirement against traditional water ring
vacuum pump.
Multi-circulation of process water to bring down overall water consumption.
Mechanical seal instead of conventional gland packing. It allows us to recirculate the fresh
water and reuse same water after cooling.
Flow meters will be installed at the inlet, ETP and the outlet of both.
For conservation of water maximum water will be reused in process.
Treated sewage will be used for gardening purpose.
Low volume water sprinklers will be installed for gardening and water sprinkling purposes.
Use of more native plants for greenbelt development that require little water to thrive in the
locality.
Watering the landscapes in the morning to prevent water loss due to evaporation.
Adding mulch surrounding the trees to prevent water loss through evaporation.
Conduct regular surveys and awareness programs for water conservation at an employee
level.
Regular inspection, checking and maintenance of valves, taps, flow meters and other
equipment.
Provision of low flush toilets in the administrative building.
Rain water harvesting (RWH) shall be implemented for water conservation.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 207 2018_ECSS_EIAI1_1800028
10.4.2 Conservation of Raw Materials& Fuel
A designated earmarked material storage area will be provided for better handling of raw
material, products and wastes.
Proper handling, loading and unloading practices will be followed for reducing material
wastage.
Rice Husk and Black Liquor will be used as fuel.
Use of closed trucks for transportation of material to avoid material loss.
Material recovery during the paper production, excess water from the disc filter shall be
removed and fibers retaining on the filter will be used back on the paper machine.
10.4.3 Conservation of Energy
The proponent proposes a new Captive Power Plant (CPP) along with existing CPP which will
meet the steam as well as power requirement of the plant.
The manufacturing process will be fully automated to reduce energy losses.
Solar lighting shall be installed at ETP and storage area.
Energy efficient machineries, fixtures and equipment will be used.
The company will train and educate employees in areas of energy conservation.
The company will carry regular internal and external audits to identify areas for improvement.
Energy audit will be used as a tool for monitoring purpose.
Periodic monitoring of unit/plant/department wise for energy consumption.
Preparing annual energy activity plan.
Company shall explore possibility of harnessing solar energy for various infrastructure operations. Unit
will also assess the use of Energy Efficient Lighting, Transformers, Use of Energy Efficient Motors,
electrical appliances to minimize the energy consumption.
10.5 DRAINAGE & RAINWATER HARVESTING PLAN
The effectiveness of the drainage system depends on proper cleaning of drainage pipes/channels etc.
Regular checking before & during the monsoon will be done to see that none of the drains/drainage
facilities are clogged and are efficient to collect the rainwater under rain water harvesting program. The
clogged drains will be cleaned up immediately on report of any clogging or blockage. This checking and
cleaning will be meticulous during the monsoon season, especially if heavy rains are forecasted.
10.5.1 Rainwater Harvesting (Recharging) System
As a part of the proposed expansion project, the proponent has proposed a rainwater harvesting
system along with existing rain water harvesting for collection of rainwater for utilization in the project
activities. Rain water that runs off streets, terraces, parking area and internal road of the industrial
premises will be collected. The effectiveness of the system depends on proper cleaning of drainage
pipes/channels etc. Regular checking before & during the monsoon shall be done to see that none of
the rainwater drains/facilities are clogged and are efficient to collect the rainwater under rain water
harvesting program. The clogged drains shall be cleaned up immediately on report of any clogging or
blockage. This checking and cleaning shall be meticulous during the monsoon season, especially if
heavy rains are forecasted.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 208 2018_ECSS_EIAI1_1800028
The first rainwater is being/will not be collected and it will be allowed to be discharged as storm water.
The subsequent rainwater is being/will be conveyed to the rainwater collection system. Rainwater
falling on the entire main shop roof will be transferred to storage tank through closed pipes/separate
drain channels. This water is being/will be utilized for ancillary purposes (such as ash quenching, fire-
fighting and gardening) thereby reducing the water consumption.
Table 10.7: Rainwater Harvesting Calculation
S. No.
Area Particulars
1. Total Area available for Water Harvesting
: Roof Top Area: 11128 m2 Paved Area: 5900 m2
2. Average annual Rainfall : 380 mm
3. Total Rain Water that can be harvested per year
: (5900) * (380) * (0.5) =1121 m3 (11,128) * (380) * (0.8)=3383 m3
Total : 4504 m3
The normal annual rainfall of the Muktsar district is 380 mm in 22 days. Considering the area available,
4500 m3
of rainwater can be conserved annually. The groundwater level in this area is 5-6 m below
ground level. During the rainy season water logging takes place in this area. So it is not advisable to
allow the harvested water to recharge the ground water through dug well. Instead of recharging, the
rainwater is being/will be stored in underground storage tanks and ruse for ancillary purposes. A budget
of Rs. 20 Lakhs is allotted for Rain Water Harvesting.
Rain water harvesting pit is being/will be made to collect the rain water fromroof top, open area and
paved area based on the above data consideration.
Figure 10.7 – Existing Rainwater Harvesting System
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 209 2018_ECSS_EIAI1_1800028
10.6 BUDGETARY PROVISIONS FOR EMS
The total cost for the project will be Rs. 500.0 Crores. The capital cost of environmental control
measures, Solid/Hazardous Waste Management Facility, Greenbelt Development, Safety, and
Monitoring etc. would be Rs. 15Crores. The greenbelt, safety measures and other components of the
EMP shall be implemented along with the commissioning of the proposed project. The annual recurring
cost of environmental control for the proposed project has been estimated to be Rs. 1.0 Crore/annum
of the total EMS cost. The Budgetary Provision made for environmental management is briefly
illustrated below:
Table 10.8 - Cost Break-Up for Environment Management System (EMS)
S.
No. Particulars
Total Cost
(Rs. Crores)
1. Air Pollution Management
15.00
2. Water Pollution Management
3. Occupational Health And Safety
4. Solid Waste Disposal and Management
5. Green Belt Development and Rain Water Harvesting
10.7 ENVIRONMENTAL MANAGEMENT CELL (EMC)
Satia Industries Limited has formulated an Environmental Management Cell for its industry, which
involves personnel of plant level as well as corporate level for interaction with technical & statutory
bodies to deal with environmental requirements/issues at all level. Sr. Vice President heads the
Environmental Management Cell with personnel involving Environmental Manager and Subordinates.
The EMC carries out the monitoring of the noise level, analysis of water etc. and keeps the regional /
local statutory body informed about the status of pollution control. The periodicity of monitoring will be
governed by the directives from statutory authorities and prevailing regulations. The action plan of EMP
will be updated every year with respect to the results achieved and to plan activities for the next year.
Implementation of EMP and responsibility
Various measures have been suggested in the EMP for mitigation of impacts. These have to be
implemented according to the suggestions and monitored regularly to prevent any lapse. It is the prime
responsibility of Head of EMC to ensure that any non-conformity are addressed, the EMP is
implemented & operated efficiently to prevent/control pollution during operational phase of proposed
project as well as to improve the environmental health of the area. The head of EMC shall be
responsible for reporting any non-compliance to higher authority and stakeholders. It is the
responsibility to each personnel of EMC & to ensure that the subordinates function efficiently as per
their responsibility to proper implementation of EMP to practice ideal methodology/procedures for
prevention /control of pollution as well as improvement of environmental health.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 210 2018_ECSS_EIAI1_1800028
ENVIRONMENTAL MANAGEMENT CELL
Figure 10.8 -Organogram of Environmental Management Cell
10.8 CORPORATE ENVIRONMENTAL RESPONSIBILITY
The company also proposes to carry out social welfare activities for the welfare of local community. The
company has proposed a detailed CER Plan. Under this plan, the proponent has allocated a budget of
Rs. 3.75 Crores i.e. 0.75 % of the total cost of Rs. 500.0 Crores to be spent within a period of 5 years.
Activities under the following areas have been identified and shall be carried out:
Free Health Services
Education and Youth Development
Infrastructure Development
Miscellaneous activities
Table 10.9 -CER Plan with 5 Years Break-UP
S.
No. Description
Year
Total 1st
Year
2nd
Year
3rd
Year
4th
Year
5th
Year
1. Drinking Water Facility in
nearby Village 15.00 15.00 15.00 - - 45.00
2. Health and Hygiene facilities
in nearby Village 10.00 15.00 15.00 15.00 20.00 75.00
3. Plantation in Community
Areas 5.00 10.00 15.00 15.00 20.00 65.00
4. Skill Development & Training Program
10.00 10.00 20.00 20.00 20.00 80.00
5. Education related Activities 20.00 20.00 20.00 25.00 25.00 110.00
Total (Rs. in Lakhs) 60.00 70.00 85.00 75.00 85.00 375.00
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 211 2018_ECSS_EIAI1_1800028
10.9 SUMMARY
Thus, the proponent will carry out above mentioned activities under the Environmental Management
Plan for various Environmental attributes like Air Environment, Water Environment, Biological
Environment, Noise Environment and Occupational Health & Safety. Apart from this, measures like
Traffic Management Plan, Cleaner Production Practices, Greenbelt Development Plan, Rainwater
Harvesting Plan and Drainage/Sewage Network have been proposed. An Environment Management
Cell (EMC) will be formulated for addressing the different environmental aspects of the proposed
project. A budget of Rs. 15.00crores has been allocated for the Environment Management System
(EMS). Also, the proponent will carry out social welfare &upliftment activities in the nearby villages for
the local population and their economic as well as social upliftment. The budget allocated for the
same is Rs. 375.00 lakhs which will be spent within a time frame of 5 years. Thus, the project will also
entail positive benefits to the society in terms of economic and social upliftment of the same.
-------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 212 2018_ECSS_EIAI1_1800028
CHAPTER-11
SUMMARY & CONCLUSION
11.1 INTRODUCTION
Satia Industries Limited is a pioneer in development, manufacturer of quality paper products and
marketing in domestic and international markets. Now Satia Industries Limited proposes to enhance
the capacity of existing products from 300 TPD to 600 TPD and proposes CPP of 14 MW along with
existing 30 MWat Muktsar – Malout Road, PO : Village Rupana, Dist: Sri Muktsar Sahib, Punjab –
152032.
The project falls under 5(i) of Schedule of list of industries of EIA Notification 2006.The Draft EIA
report has been prepared for submission to Punjab SPB. The Draft EIA report has been prepared for
Conducting the Public Hearing. A final EIA thereafter will be prepared incorporating the details of PH &
finally submitted to MoEF&CC for Appraisal & Obtaining EC.
11.2 PROJECT DESCRIPTION
The proposed project envisages enhancement of existing paper manufacturing by Satia Industries
Ltd. (SIL) located at Muktsar –Malout Road, PO: Village Rupana, Dist: Sri Muktsar Sahib, Punjab –
152032. Production capacity will be increased from 300TPD to 600TPD. The expansion of falls
under Category 5 (i) - “A” i.e. Paper Manufacturing from Wastepaper and the proposed project will
also install an additional 14.00MW CPP. The project site has an area of 45.55 Acres.Expansion will
be done in existing premises. Total cost for the proposed project will be Rs.500.0 crores.There will
be additional 500 numbers of employees, thus total 1600 numbers of employees after proposed
expansion. After proposed expansion, total water requirement for domestic and industrial purposes
with cited requirement of 87 KLD and 23,811KLD respectively.And PM, SOx and NOx will be
generated from existing and proposed Boiler. Hazardous Wastes like ETP Sludge, Lime Sludge and
Solid waste like Fly Ash generated from the project will be handled and managed as per Hazardous
Wastes Rules, 2016.
11.3 DESCRIPTION OF THE ENVIRONMENT
Ambient Air Quality Monitoring
Sr. No.
Criteria Pollutants
Unit Maximum Value
Minimum Value
98th Percentile
Value
Prescribed Standard
1. PM10 µg/m3 88.6 62.5 88.4 100
2. PM2.5 µg/m3 48.3 32.8 48.0 60
3. SO2 µg/m3 16.7 9.6 16.6 80
4. NOX µg/m3 21.5 14.2 21.5 80
All the results of ambient air quality parameters have been found well within the limit as per NAAQS. Based on comparison study of results for tested parameters with NAAQS, it is interpreted that ambient air quality of studied locations is good. This interpretation relates to the sampling carried out and results found for particular locations and study period.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 213 2018_ECSS_EIAI1_1800028
Noise Monitoring
Sr. No.
Parameter Unit Maximum Value Minimum Value Prescribed Standard
1. Leq (Day) dB(A) 77.4 49.8 -
2. Leq(Night) dB(A) 72.1 42.8 -
Based on noise level data obtained during the survey for residential area and industrial area, it is interpreted that noise levels are within the standard norms prescribed by MoEF & CC. Looking towards the increase in noise generating sources it is suggested that there is need to apply noise
reducing devices at noise generating sources and generate public awareness. Soil Qualityand Characteristics
Sr. No.
Parameter Unit Maximum Value Minimum Value
1. pH - 7.44 7.12
2. Electrical Conductivity dS/m 0.48 0.35
3. Sodium meq/100gm 1.2 0.8
4. Potassium meq/100gm 0.5 0.3
5. Phosphorous mg/100gm 16.3 13.6
6. Total Nitrogen % 0.074 0.052
Based on soil analysis data it is concluded that soils are normal from salinity point of view as SAR is <2.0 and ESP is < 15%. The soils are having medium in nitrogen, low in phosphorus and potassium. The levels of total Fe, Cu, Cr, B and Zn are within the safe limits. However, for successful greenbelt development liberal quantity of organic manure is recommended. Soils of studied locations are suitable for plantation as well as for agricultural purpose.
Ground Water
Sr. No.
Parameter Unit Maximum Value
Minimum Value
Desirable Limit
Permissible Limit
1. pH - 7.94 7.04 6.5-8.5 No
Relaxation
2. TDS mg/L 2254 218 500 2000
3. TSS mg/L < 2 < 2 - -
4. Total Hardness mg/L 1200 112 200 600
5. Chloride mg/L 875 40 250 1000
6. Total Alkalinity mg/L 580 122 200 600
7. Fluoride mg/L 0.7 0.11 1.0 1.5
8. Iron mg/L 0.42 < 0.10 0.3 No
Relaxation
Based on comparison study of test results with drinking water norms, it is interpreted that water qualities of most of the studied locations meet with the drinking water standards as per IS 10500: 2012 except Goniana village. Ground water sample collected from project site, Rupana, Sotha, chak Gilijiwala,Barkandi,Muktsar and Bhangchiri can be used in drinking as well as in other domestic and irrigation purpose. Ground water sample collected from Goniana village should not be used in drinking as it contains TDS, Total Hardness, Chloride and Iron more than prescribed limit but it can be used in other domestic purpose as well as in irrigation also. These interpretations are based on comparison study with standard for tested parameters only as per IS 10500: 2012.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 214 2018_ECSS_EIAI1_1800028
Surface Water
Sr. No.
Parameter Unit Maximum Value
Minimum Value
Desirable Limit
Permissible Limit
1. pH - 7.75 7.23 6.5-8.5 No Relaxation
2. TDS mg/L 214 168 500 2000
3. DO mg/L 5.1 4.9 - -
4. COD mg/L 16 10 - -
5. BOD mg/L 6 < 4.0 - -
River water qualities for the samples collected from different surface water bodies are contaminated with organic matter and microbes. Total coliforms have been reported in all sample, it indicated towards the faecal pollution in surface water bodies. Results of other tested parameters meet with the drinking water norms. Based on comparison study with drinking water norms it is concluded that these water sources can be used for irrigation purpose and it can also be used in drinking after conventional treatment followed by disinfection.
Ecologyand Biodiversity
Dominant trees observed in the study region were Amaltas, Gulmohar, Shisham and kali shirish. There was no reserved forest recorded during the survey in the study region. Area is devoid of dense forest as a result no schedule -1 wild life was observed during the survey. Common mammal of the study region was Blue bull, Squirrel, Common mongoose and rabbit were seen. Although the soil of study region is clay loam, which favors the plant growth but looking to the density of plant it may also be suggested to improve the quality of environment as well as ecology and bio diversity by planting more trees. Due to lack of natural habitat, less numbers of wild mammals were observed. Number of species and density of wild mammals can be increased by promoting/ facilitating the growth of bushes. There was no endangered species observed during primary survey.
Socio Economic
During the primary survey it was observed that almost pakka road facility is available in all villages within 10 km radius. Literacy rate of the study region is from 48.44 to 67.33%. When compared to other places, these villages exhibit lower rate of literacy thus there is need to promote education among more and more people. Almost all the villages have more than 50% people as non-workers. It indicates that the problem of unemployment can be solved by providing proper training and education. There is also need to establish more industries so that maximum number of employment can be generated.Basic amenities like Education facilities Health care facilities, water supply, electric power supply, mode of transportation etc. are available in all villages.
11.4 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION
MEASURES
The proposed project has no major adverse impact on surrounding environment. The CPP will be
equipped with 99.9% efficient four field ESP for mitigation of air pollutant sources. Hazardous waste will
be sent to TSDF facility, authorized recyclers and refiners. Appropriate construction & operation
techniques will be implemented to minimize the impacts on the environment. Proper upkeep and
maintenance of vehicles and APCM will reduce the impact on air environment. Adequate arrangements
for waste disposal from ETP will be undertaken. Greenbelt will be developed in surrounding of plant and
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 215 2018_ECSS_EIAI1_1800028
common land. Budget of Rs. 20-30 Lakhs is allotted for green belt development. A budget of Rs.
15crores capital and Rs. 1 crores recurring cost for EMP. Positive impact is envisaged on Socio
economic environment. The allocated budget for CER has been prepared of Rs. 375 Lakhs for
development of local populace. Proper PPEs will be provided to all the workers& budget of approx. Rs.
50 lakhsis allotted for OH&S.
11.5 ANALYSIS OF ALTERNATIVES
No alternative site has been proposed for the proposed expansion project because expansion will be
done at existing premises only and all the infrastructure are readily available for industrial
development. However, some alternatives were considered for planning and designing of the various
facilities proposed at the proposed expansion.
11.6 ENVIRONMENTAL MONITORING PROGRAM
Project proponent will develop an environmental and safety department, which will undertake
measures for environmental protection and mitigation of environmental impacts. Sample for
environment monitoring will be collected as per the guidelines provided by MoEFCC/CPCB /PPCB.
Monitoring of environmental parameters within the plant premises will be carried at selected location
as per guideline. Hazardous waste will be disposed/off as per Hazardous Waste Management Rules
2016. Pre-medical check-up will also be carried out at the time of employment.
11.7 ADDITIONAL STUDIES
As a part of the EIA study, an additional study including Risk Assessment (RA) has been carried out
for the proposed project. Public hearing is applicable to proposed project as per MoEFCC‟s OM dated
27/04/2018 as proposed project is fall under Pulp and Paper Industry Cat. 5 (i).The Risk Assessment
addresses major hazards and reviews the effectiveness of selected safety measures and to expand
the safety measures in order to achieve a safety culture at the industry. The Risk Assessment also
encompasses Disaster Management Study and Occupational Health & Safety.
11.8 PROJECT BENEFIT
The proponent is very enthusiastic in promoting various welfare activities as a part of moral & social
responsibility. The group has contributed a lot in the field of education, health & other social
responsibilities. Even after the proposed project, the proponent will give physical, social, economic
and ecological benefits to the local population such as development of infrastructure, green cover,
social aids, employment, etc. The proponent has allocated a budget of Rs. 375 lakhs for CER Plan.
Through local employment and various CER activities it will also give social benefit to the local people
and due to resource conservation it will also give environmental benefit.
11.9 ENVIRONMENTAL COST BENEFIT ANALYSIS
During the scoping/ToR stage, no recommendation of environmental cost benefit analysis was
suggested by the appraisal committee.
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 216 2018_ECSS_EIAI1_1800028
Moreover, Proposed expansion of paper manufacturing project of capacity 600 TPD along with 14 MW
CPP will be developed atMuktsar – Malout Road, PO.: Village Rupana, Dist: Sri Muktsar Sahib,
Punjab – 152032. Hence, conducting a detailed CBA is deemed not necessary for this particular
project.
11.10 ENVIRONMENTAL MANAGEMENT PLAN
Thus, the proponent will carry out above mentioned activities under the Environmental Management
Plan for various Environmental attributes like Air Environment, Water Environment, Biological
Environment, Noise Environment and Occupational Health & Safety. Apart from this, measures like
Traffic Management Plan, Cleaner Production Practices, Greenbelt Development Plan, Rainwater
Harvesting Plan and Drainage/Sewage Network have been proposed. An Environment Management
Cell (EMC) will be formulated for addressing the different environmental aspects of the proposed
project. A budget of Rs. 15.00crores has been allocated for the Environment Management System
(EMS). Also, the proponent will carry out social welfare &upliftment activities in the nearby villages for
the local population and their economic as well as social upliftment. The budget allocated for the
same is Rs. 375.00 lakhs which will be spent within a time frame of 5 years. Thus, the project will
also entail positive benefits to the society in terms of economic and social upliftment of the same.
11.11 CONCLUSION AND RECOMMENDATION
The proposed project of Satia Industries Limited proposes to enhance the capacity of existing products
from 300 TPD to 600 TPDand proposes CPP of 14 MW along with existing 30 MW at Muktsar –
Malout Road, PO : Village Rupana, Dist: Sri Muktsar Sahib, Punjab – 152032. The proposed
expansion will be beneficial to the already running business of the company.
The EIA study has been carried out with respect to the TORs awarded by MoEF. All the impacts likely
to have an effect on the environment have been identified and efficient/adequate mitigation measures
have been proposed for the same.
Considering the probability of likely impacts, the proponent has planned adequate mitigation measures
and EMP. Further, the proponent also undertakes CER activities which shall have beneficial impacts on
the socio-economic environment. Measures like rainwater harvesting, energy conservation and
greenbelt development are also noteworthy. Looking to the overall project scenario, employment
potential and allied development plans; it has been noticed that the proposed project would significantly
help in the improvement of the society and nation at large. The proponent has/will provide ETP for
adequate treatment. Utmost care has been taken while planning the drainage network to ensure that
there is no possibility of runoff, spillage or disposal of water on land/water body. Adequate methodology
for collection, handling and transportation of solid waste will be in place to ensure that there is no
adverse impact of solid waste on the environment. Adequate Air Pollution Control Device such as ESP
is attached to the boiler for controlling air pollution. The CPP stack of adequate height is also provided
for pollutant dispersion. All the relevant safety norms with latest technology have been incorporated in
the proposed project. Hazards and associated risks, safety and security provision associated with the
project activities appear to be acceptable. Hence the project in totality may be considered
environmentally safe.
-------------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 217 2018_ECSS_EIAI1_1800028
CHAPTER – 12
DISCLOSURE OF CONSULTANT ENGAGED
12.0 GENERAL
Satia Industries Limited has appointed Eco Chem Sales and Services (ECSS) for carrying out this
Environmental Impact Assessment Study as per the EIA notification, 2006 as amended till date. ECSS
has approved EIA coordinators and Field Area Experts for undertaking Environmental and related
studies in twenty two (22) approved sectors by NABET, Quality Council of India, New Delhi.
12.1 BRIEF RESUME AND NATURE OF CONSULTANCY
ECO CHEM SALES and SERVICES (ECSS) is one of the leading companies in the field of
Environmental Consultancy Service providers in India. We are NABET Accredited consultant for
conducting Environmental Impact Assessment Studies (EIA) and obtaining Environmental Clearances.
We also take up services which include and are not limited to Environment Monitoring and Testing,
Environment Audit, Risk Assessment Studies, Turnkey solutions, Operation and Maintenance contracts
and obtaining various statutory clearances from Ministry of Environment, Forest and Climate Change
(MoEFCC) and State Pollution Control Boards. ECSS also has branch offices in Vapi, Dahej and
Vadodara, Gujarat.
The accreditation certificate number NABET/EIA/1720/SA 085 is valid up to 20th Feb. 2020.
12.2 NAME OF EIA TEAM MEMBERS/ FUNCTIONAL AREA ASSOCIATES
Following experts are involved in EIA report preparation as team member other than NABET approved
experts mentioned in declaration.
Table12.1 -EIA Team Member
Name of Internal
Team Member/ FAA
Activity / Area Involvement – Actual Work Performed
Dr. Amit Dhir
Project
Consultant and
Coordinator
Verification of Technical data, Compiling Various Technical
details from Different Departments and Assisting as EIA
Consultants in Preparation of EIA/EMP reports.
Mrs.Rekha shah Quality Check
Project planning; Understanding of project; Discussion with
client; Guidance in writing & modification in Contents; Impact
Assessment; Review of EIA/EMP report.
Mr.Meet Shah
Assisting in
EIA Report
Writing and
WP
Assisting in EIA Report Preparation, Water sampling,
analysis and report making. Assisted to FAE for identification
of impacts and mitigation measures, and contribution to EIA
documentation
Ms. Pruthvi Patoliya AQ Assisted FAE for Air Quality modeling, identification of
impacts and mitigation measures, and contribution to EIA
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 218 2018_ECSS_EIAI1_1800028
Name of Internal
Team Member/ FAA
Activity / Area Involvement – Actual Work Performed
documentation
Ms.Unnati Desai AP Assisted to FAE for identification of impacts and mitigation
measures, and contribution to EIA documentation
Mr. Rajat Gondaliya LU Assisted FAE for preparation of landuse maps of study area
& report writing
Mrs. Nazneen Mansuri
Solid and
Hazardous
Waste
Management
(SHW)
Assisted FAE for identification of impacts and mitigation
measures
Mr. Parth Malavia RH Assisted to FAE for identification of impacts and mitigation
measures, and contribution to EIA documentation
12.3 LABORATORY INVOLVED FOR BASELINE MONITORING AND
OTHER ANALYSIS
Baseline Monitoring and Analysis has been done by ECSS in-house NABL Approved Laboratory
Ecosystem Resource Management Pvt. Ltd. (ERM). ERM having valid NABL Certificate number TC-
6603 is valid up to 25th October 2019.
------------------
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 219 2018_ECSS_EIAI1_1800028
Annexure-I: ToR Letter
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 220 2018_ECSS_EIAI1_1800028
Annexure-II: Existing EC & its Compliance
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 221 2018_ECSS_EIAI1_1800028
Annexure-III: Existing Consents & its compliance
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 222 2018_ECSS_EIAI1_1800028
Annexure-IV: Land Details
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 223 2018_ECSS_EIAI1_1800028
Annexure-V: Water Permission in English & Punjabi language
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 224 2018_ECSS_EIAI1_1800028
Annexure-VI: MoU of Fly Ash
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 225 2018_ECSS_EIAI1_1800028
Annexure-VII: Undertaking for Fly Ash
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 226 2018_ECSS_EIAI1_1800028
Annexure-VIII: Agreement of Lime Sludge
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 227 2018_ECSS_EIAI1_1800028
Annexure-IX: Health Records
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 228 2018_ECSS_EIAI1_1800028
Annexure-X: Details of Fire Equipments & Hydrants
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 229 2018_ECSS_EIAI1_1800028
Annexure-XI: MSDS
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 230 2018_ECSS_EIAI1_1800028
Annexure-XII: EHS Policy
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 231 2018_ECSS_EIAI1_1800028
Annexure-XIII: CREP Compliance Report
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 232 2018_ECSS_EIAI1_1800028
Annexure-XIV: NABET Certificate
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 233 2018_ECSS_EIAI1_1800028
Annexure-XV: Hydro Geological Study
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 234 2018_ECSS_EIAI1_1800028
Annexure-XVI: MoU With FMO/Hospitals
SATIA INDUSTRIES LIMITED EIA/EMP Report for Proposed Expansion of paper production with capacity from 300 TPD to 600 TPD along with CPP of 14.00 MW
Eco Chem Sales & Services, Surat 235 2018_ECSS_EIAI1_1800028
Annexure-XVII: Public hearing Proceedings