Final AUS Presentation 3 Apr 14
description
Transcript of Final AUS Presentation 3 Apr 14
MINISTRY OF PUBLIC WORKSRoads administration
1 of 125
Sheikh JABER AL-AHMAD AL-SABAHCauseway Project (SJSC)
MINISTRY OF PUBLIC WORKSRoads administration
2 of 12503-04-2014
MINISTRY OF PUBLIC WORKS األشـــــغـــال الـعــــامـةوزارة
AGREEMENT NO. EF/R/214 214/ھـ ط / رقم أ إتفـــاقـيـة
For Design Review and Construction Supervision Works for Sheikh JABER AL-AHMAD AL-SABAH Causeway Project (SJSC) for Contract RA/140 Main Link (SUBIYAH LINK) and Contract RA/214 (DOHA LINK)
ـل ـى تنفيألجـ راف عل ـم واإلش ـعة التصـــمي ذ مراجال/مشروع جـسر الشيخ د الصباح ألعم ـابر األحم ج
ـ ط د ھ ر 140/العق ىالجس بية( الرئيس لة الص ) وصد ال العق وأعم
) جسر وصلة الدوحة( 214/ھـ ط
STATE OF KUWAITدولـــــــة الــــكــــويت
MINISTRY OF PUBLIC WORKSRoads administration
3 of 125
• Planning and Progress of the Project, (M. Abou Leil)
• Basic Design Status and Geometric Design, (Rami)
• Bridges Structure, (Dante)
• Infrastructures & Buildings, (Robbie)
• Geotechnical and Marine, (Shadi)
• Environmental Management and Monitoring, (Chris)
• Bridge Construction Sequence, (Araby)
Presentation Agenda
MINISTRY OF PUBLIC WORKSRoads administration
4 of 125
Planning and Progress of the Project
(M. Abou Leil)
MINISTRY OF PUBLIC WORKSRoads administration
5 of 125
Project Profile
Project: Sheikh Jaber Al-Ahmad Al Sabah Causeway (SJSC) Main Link Location: Kuwait City to Subiyah New Town, across Kuwait BayContract Period: 1827 days ( from 03-Nov-13 till 03-Nov-18) Employer: Ministry of Public Works (MPW), Kuwait represented by H.E. Minister of
Public WorksThe Engineer: Assistant Under-Secretary Roads (MPW)Consultant: Dar Al Handasah – SSH – TYLIN InternationalContractor: Hyundai Engineering & Construction Co. Ltd.
Combined Group Contracting Co. (KSCC)Designer: SYSTRAICE: AECOM
MINISTRY OF PUBLIC WORKSRoads administration
6 of 125
Time ControlAs on: 31-Mar-14
MINISTRY OF PUBLIC WORKSRoads administration
7 of 125
Progress of WorkAs on: 31-Mar-14
MINISTRY OF PUBLIC WORKSRoads administration
8 of 125
Details of Overall Physical Progress
Design, Build, Completion and Maintain Sheikh Jaber Al-Ahmad Al-Sabah Causeway Project(Main Link), Contract NO. RA/140 As of 31-Mar-2014
Stage Sub-stage WeightValue
Previous Month This MonthAccmulative Remarks
(Milestones in Progress)Feb-2014 (M4) Mar-2014 (M5)
Plan(%) Actual(%) Plan(%) Actual(%) Plan(%) Actual(%)
1 Planning 1.1 Mobilization(PM No.1, 3) 8.50 7.51 7.46 0.51 0.63 8.02 8.09 PM No.1, 3
2 Design 2.1 Basic Design(PM No.2) 1.00 0.90 0.99 0.10 - 1.00 0.99 SM No.2-1
2.2 Detailed Design(PM No.4, 5) 2.00 - - - - - - PM No.4, 5
3 Execution 3.1Temporary Works(SM No.7-1, 7-2, 7-7, 22-1, 22-2,24-1, 24-2, 25-1, 25-2)
9.85 5.05 6.00 0.85 0.65 5.90 6.65 SM No.7-1, 7-2, 22-1, 24-1, 25-1
3.2 Permanent Works(Remaining Milestones) 76.15 1.55 1.46 0.22 0.43 1.77 1.89 SM No.11-1, 11-2, 12-1, 30-1
4 Completion 4.1 Taking Over Certificate(PM No.34) 2.50 - - - - - -
Progress Ratio 100.00 15.01 15.91 1.68 1.71 16.69 17.62
▣ Abbreviation : PM(Primary Milestone), SM(Secondary Milestone)
MINISTRY OF PUBLIC WORKSRoads administration
9 of 125
Site Activities
- Temp. Jetty (Subiyah) 100 % Completed.
- Temp. Channel Dredging (Subiyah) 100 % Completed.
- Installation of Artificial Reef : 984 / 984EA 100 % Completed.
- Geotechnical Investigation in Shwaikh, Subiyah & Marin Completed 100 %
- Pilot Piles onshore and offshore completed 100 %.
- Client’s Site offices Completed 100 % for Contractor 89 %.
- Reclamation area in Shuwaikh - 39 % in Progress.
- Soil improvement working platform in Subiyah 31 % in Progress.
- Relocation of KPA fence 39 % in Progress.
- Site clearance in Ghazali street 65 % in Progress.
- Temporary Bridge : 76% in progress
MINISTRY OF PUBLIC WORKSRoads administration
10 of 125
Progress Photos
Site Overview of Temporary Jetty Operation of Temporary Jetty
Temp. Jetty (Subiyah) 100 % Completed
MINISTRY OF PUBLIC WORKSRoads administration
11 of 125
Dredging of Cutter Suction Dredger
Temp. Channel Dredging (Subiyah) 100 % Completed.
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
12 of 125
Delivery of Artificial Reefs Installation of Artificial Reefs
Installation of Artificial Reef : 984 / 984EA 100 % Completed.
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
13 of 125
Geotechnical Investigation at Main Bridge Geotechnical Investigation at Approach Bridge North
Geotechnical Investigation in Shwaikh, Subiyah & Marine Completed 100 %
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
14 of 125
Axial Load Test for Pilot Pile atShuwaikh Bridge
Lateral Load Test for Pilot Pile atShuwaikh Bridge
Pilot Piles onshore and offshore completed 100 %
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
15 of 125
Client’s Site Offices - External Client’s Site Offices - Internal
Client’s Site offices Completed 100 % and Contractor’s offices 89 %.
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
16 of 125
Reclamation Stage 1 - Shuwaikh Reclamation Stage 1 - Shuwaikh
Reclamation area in Shuwaikh - 40 % in Progress.
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
17 of 125
Temporary Bridge ConstructionShuwaikh
Temporary Bridge ConstructionShuwaikh
Temporary Bridge - 76 % in Progress.
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
18 of 125
Assembly of Marine Batching Plant Construction of Steel Casting Yard
Temporary Works at Subiyah Area
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
19 of 125
Jack up Barge
Mobilization of Marine Equipment
Progress Photos
MINISTRY OF PUBLIC WORKSRoads administration
20 of 125
Work Item2013 2014 2015 2016 2017 2018
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Major Design Works
Temporary Works
Piling Works (1537 Piles)
Substructure Works (1236 piers)
Superstructure Cast in Situ
Box Girders Fabrication (1052)
Box Girder Installation
Asphalt and final finishes
T & C /Closeout Activities
Overall Summary Schedule for Main Project ElementsStart Date 03‐Nov‐13 Completion Date 03‐Nov‐18
03‐Nov‐13 31‐Mar‐15
03‐Nov‐13 30‐Sep‐15
17‐Aug‐14 15‐Jun‐17
20‐Aug‐14 11‐Dec‐17
01‐Apr‐15 07‐Apr‐18
02‐Feb‐15 26‐Nov‐17
05‐Jul‐15 14‐Jan‐18
05‐Nov‐16 02‐Aug‐18
13‐May‐18
Construction of Bridge Main Elements
MINISTRY OF PUBLIC WORKSRoads administration
21 of 125
Basic Design Deliverables,Sample of Basic Design Submittals,
Design Review Status,Geometric Design
(Rami)
MINISTRY OF PUBLIC WORKSRoads administration
22 of 125
Basic Design Deliverables,
Basic Design divided into 4 Parts• Basic Design Part 1 (20 Documents)• Basic Design Part 2 (50 Documents)• Basic Design Part 3 (13 Documents)• Basic Design Part 4 (16 Documents)
MINISTRY OF PUBLIC WORKSRoads administration
23 of 125
Sample of Basic Design Submittals (Page ½)Document No Revision Category/ TitleDesign Basis
RA140‐10‐GEN‐AD‐TR‐00811 A1 PREAMBLE
RA140‐10‐GEN‐AD‐TR‐00812 A3 GENERAL
RA140‐10‐ROE‐RW‐TR‐00813 A5 HIGHWAY AND ROAD
RA140‐10‐RSI‐MW‐TR‐00815 A4 ISLAND AND EMBANKMENT
RA140‐10‐ISE‐EM‐TR‐00817 A7 ENGINEERING INSTALLATIONS & SERVICES
Alignment Design
RA140‐21‐ROE‐AL‐TR‐01801 A3 ALIGNMENT DESIGN REPORT
RA140‐21‐GEN‐AL‐DW‐01150 A2 ALIGNMENT OFF‐SHORE DRAWING PACKAGE
OFFSHORE BRIDGE ‐ 60M SPAN APPROACH & SUBIYAH BRIDGES
RA140‐21‐BRG‐CW‐TR‐03812 A1BASIC DESIGN OFFSHORE BRIDGE ‐60M TYPICAL SPAN SUBSTRUCTURE ANALYSIS
RA140‐21‐BRG‐CW‐TR‐03813 A1BASIC DESIGN OFFSHORE BRIDGE ‐60M TYPICAL SPAN SUPERSTRUCTURE ANALYSIS
RA140‐21‐BRG‐CW‐TR‐03815 A1BASIC DESIGN OFFSHORE BRIDGE ‐60M SPAN SUPERSTRUCTURE TRANSVERSAL ANALYSIS
RA140‐21‐BRG‐CW‐DW‐03020 A2 BASIC DESIGN OFFSHORE BRIDGE ‐60M SPAN DRAWINGS PACKAGE
MINISTRY OF PUBLIC WORKSRoads administration
24 of 125
Sample of Basic Design Submittals(Page 2/2)Document No Revision Category/ TitleOFFSHORE BRIDGE ‐ 40M SPAN SHUWAIKH BRIDGE
RA140‐21‐BRG‐CW‐TR‐03822 A1BASIC DESIGN OFFSHORE BRIDGE ‐40M TYPICAL SPAN SUBSTRUCTURE ANALYSIS
RA140‐21‐BRG‐CW‐TR‐03823 A1BASIC DESIGN OFFSHORE BRIDGE ‐40M TYPICAL SPAN SUPERSTRUCTURE ANALYSIS
RA140‐21‐BRG‐CW‐TR‐03824 A1BASIC DESIGN OFFSHORE BRIDGE ‐40M SPAN SUPERSTRUCTURE TRANSVERSAL ANALYSIS
RA140‐21‐BRG‐CW‐DW‐03010 A2 BASIC DESIGN OFFSHORE BRIDGE ‐40M SPAN DRAWINGS PACKAGE
MAIN BRIDGE
RA140‐21‐BRG‐CW‐TR‐04801 A2 MAIN BRIDGE ‐ SUPERSTRUCTURE REPORT
RA140‐21‐BRG‐CW‐TR‐04802 A2 MAIN BRIDGE ‐ SUBSTRUCTURE REPORT
RA140‐21‐BRG‐CW‐TR‐04812 A2 MAIN BRIDGE ‐ SUBSTRUCTURE ANALYSIS
RA140‐21‐BRG‐CW‐TR‐04813 A2 MAIN BRIDGE ‐ SUPERSTRUCTURE ANALYSIS
RA140‐21‐BRG‐CW‐DW‐04000 A2 MAIN BRIDGE ‐ DRAWING PACKAGE
MINISTRY OF PUBLIC WORKSRoads administration
25 of 125
Design Review Status
Letter subject Letter Reference / Date
Received Date Reply Date
Basic Design Part 1 MPW letter 16/4-153-4996 dated 10/12/2014HDEC letter- KUSCA-MPW-HD-13-0203 dated 28/11/2013
December 10, 2013 K13099/14/0218 – 04/02/2014 (Completed Part 1 Responses)
Basic Design Part 2 MPW Letter 140/1/ھـ ط dated 13/01/2014HDEC letter – KUSCA-MPW-HD-13-0240 dated 31/12/2014
January 13, 2014 K13099/14/0450 – 08/03/2014 (Completed Part II Responses)
Basic Design Part 3 Revised SubmissionRA140-DAH-HD-14-0010 dated 15/01/2014
January 15, 2014 K13099/14/0557 – 25/03/2014(Completed Part 1, 2, 3 and 4)
Basic Design Part 4 RA140-DAH-HD-140-0019 dated 30/01/2014
January 30, 2014 K13099/14/0557 – 25/03/2014(Completed Part 1, 2, 3 and 4)
Part 1, 2,3 and 4 Completed (Primary Cycle)
MINISTRY OF PUBLIC WORKSRoads administration
26 of 125
Geometric Design• General Layout• Alignment• Main components• Lane Width• Typical Sections
• Missing Basic Documents• Approved Traffic Study, Traffic Counts and Approved Conceptual Drawings
• Design Issues (Under Discussion)• Transition length for Causeway• Weigh Bridge at Shuwaikh Area• Minimum Gradient• Interchanges• Non-reflection of rest area
MINISTRY OF PUBLIC WORKSRoads administration
27 of 125
General Layout
MINISTRY OF PUBLIC WORKSRoads administration
28 of 125
Alignment 1/5
MINISTRY OF PUBLIC WORKSRoads administration
29 of 125
Alignment 2/5
MINISTRY OF PUBLIC WORKSRoads administration
30 of 125
Alignment 3/5
MINISTRY OF PUBLIC WORKSRoads administration
31 of 125
Alignment 4/5
MINISTRY OF PUBLIC WORKSRoads administration
32 of 125
Alignment 5/5
MINISTRY OF PUBLIC WORKSRoads administration
33 of 125
Alignment – Port Access Road
MINISTRY OF PUBLIC WORKSRoads administration
34 of 125
Alignment – Bay Island North/ South Access
MINISTRY OF PUBLIC WORKSRoads administration
35 of 125
Main components
MINISTRY OF PUBLIC WORKSRoads administration
36 of 125
Lane Width (1/2)
MINISTRY OF PUBLIC WORKSRoads administration
37 of 125
Lane width (2/2)
MINISTRY OF PUBLIC WORKSRoads administration
38 of 125
Typical Sections (1/2)
MINISTRY OF PUBLIC WORKSRoads administration
39 of 125
Typical Sections (2/2)
MINISTRY OF PUBLIC WORKSRoads administration
40 of 125
Missing Basic Documents• Approved Traffic Study, Traffic Counts and Approved Conceptual
DrawingsDespite the effort done thankfully by MPW, We have not received the approved traffic study (by KM and MOI) for the project which should include the Traffic counts (approved by MOI), also we didn’t receive a copy from the approved design presented to KM and MOI.The following is to be noted:• The traffic study for the project is one of the most important fundamental
elements for the design of the project, starting from the number of lanes,determine the level of service, type and configuration of interchanges /intersections.
• The traffic count data that are based on the study of traffic is also a major keyelement to calculate the pavement structure for the different type of roads.
• The approval of design at concept stage by either KM and MOI will avoid anymajor modification during the preliminary stage (Basic Design).
MINISTRY OF PUBLIC WORKSRoads administration
42 of 125
Design Issues (Under Discussion)
Curve No. Curve Radius (m)Current Transition In-
Length (m)
Allowable maximum Transition In-
Length (m)
AASHTO and KHDM
Current Transition out-Length (m)
Allowable maximum Transition out-
Length (m)
AASHTO and KHDM
4 2000 180 220 3125 220
5 25000 4000 775 4000 775
6 8000 1125 438 1125 438
•Transition length for Causeway The KHDM and AASHTO are very clear and strict about the maximum allowable length for the transition curve which shouldn’t exceed √24R in addition to what stated into KHDM,and as per AASHTO, safety problems have been found to occur on spiral curves that are long.
Such cases were investigated as per below table:
Transition Length for Causeway Extracted from Employer’s Concept Design Drawing RA/140/1001-2
MINISTRY OF PUBLIC WORKSRoads administration
43 of 125
• Weigh Bridge at Shuwaikh Area
• The proposed location of weigh Bridge in Shuwaikhinterchange will result in the constraint of the length ofmerge/diverge Taper which is not in line with thedesign standards.
• It will also have an effect on weaving length betweenWeigh Bridge Taper and approach junction with visitorcenter road.
Design Issues (Under Discussion)
MINISTRY OF PUBLIC WORKSRoads administration
45 of 125
• Minimum GradientThe Design criteria for the project clearly mentioned thatthe minimum desirable longitudinal gradient forsatisfactory drainage is 0.5%.The drawings submitted show a minimum gradient 0%.
Design Issues (Under Discussion)
MINISTRY OF PUBLIC WORKSRoads administration
47 of 125
Mainline Design Speed (km/h)
Mainline Design Speed for connecting Roadways (km/h)
Slips(KHDM)
Slips(Basic Design)
Loops(KHDM) Loops
(Basic Design)
100 70 50 50 40120 90 70 50 40
The ramps (or connecting roadways) within a grade-separated interchange shouldnormally have a lower design speed than the mainline
• Interchanges
Design Issues (Under Discussion)
MINISTRY OF PUBLIC WORKSRoads administration
50 of 125
• Non-reflection of rest areaRest area already built by RA126 project was notconsidered in the Employer’s Concept Design Drawings.
Current design of the Interchange does not comply withKDM requirement and overlapping occurs betweenacceleration lane of vehicles from the ramp of theInterchange and vehicles approaching towards restarea.
Design Issues (Under Discussion)
MINISTRY OF PUBLIC WORKSRoads administration
60 of 125
Bridges Structure
(Dante)
MINISTRY OF PUBLIC WORKSRoads administration
61 of 125
BASIC DESIGN REVIEW
BRIDGE STRUCTURE
MINISTRY OF PUBLIC WORKSRoads administration
62 of 125
PROJECT OVERVIEW
MINISTRY OF PUBLIC WORKSRoads administration
63 of 125
MINISTRY OF PUBLIC WORKSRoads administration
64 of 125
MINISTRY OF PUBLIC WORKSRoads administration
65 of 125
DESIGN REVIEW
What has been done?
MINISTRY OF PUBLIC WORKSRoads administration
66 of 125
Basic Design Submittals
• DESIGN BASIS - BRIDGES (1 submittal)• ONLAND BRIDGES
– Ghazali Transition (4 submittals)– Shuwaikh Port Bridges (4 submittals)– Shuwaikh Port Interchange (4 submittals)– Shuwaikh Port Interchange Ramps (4 submittals)
• OFF-SHORE BRIDGES – 60M Span Bridges (Approach & Subiyah Bridges) (4 submittals)– 40M Span Bridges (Shuwaikh Bridges) (4 submittals)– 39M Span Bridges (Bay Island Embankment Bridges) (3 submittals)
• MAIN BRIDGE (SIGNATURE BRIDGE) (5 submittals)• SHUWAIKH & SUBIYAH EMBANKMENT & INTERCHANGE
– Subiyah U-Turn Bridge (3 submittals)– Subiyah KOC Bridge (3 submittals)– Subiyah Bridge (3 submittals)– Subiyah Culvert (2 submittals)– Road & Embankment (4 submittals)
• ENGINEERING INSTALLATIONS & SERVICES – Structural Health Monitoring System (2 submittals)– Dehumidification (2 submittals)– Bridge Access & Ventilation (2 submittals)
• Total 54 Submittals
MINISTRY OF PUBLIC WORKSRoads administration
67 of 125
Basic Design Review — Primary Cycle
No. Item Contractor Submittal Status Design Review Status
1 Off‐Shore Bridges Complete Comments Provided
2 On‐Shore Bridges Complete Comments Provided
3 I‐Girder Bridges Complete Comments Provided
MINISTRY OF PUBLIC WORKSRoads administration
68 of 125
Basic Design Review — Second Cycle
No. Item Contractor Response Status
Design Review Status
1 Off‐Shore Bridges Response Provided Review in Progress
2 On‐Shore Bridges In Progress In Progress
3 I‐Girder Bridges In Progress In Progress
MINISTRY OF PUBLIC WORKSRoads administration
69 of 125
Aspects of Review
DURABILITY• Layers of protection• Stainless Steel Reinforcement• Controlled Permeability
Formliner
Having in mind the future maintenance of the bridge
MINISTRY OF PUBLIC WORKSRoads administration
70 of 125
Aspects of Review
CONSTRUCTABILITY• Connection between girders• Casting by Tremie Method• Pier Cap connection
Having in mind the future maintenance of the bridge
MINISTRY OF PUBLIC WORKSRoads administration
71 of 125
Aspects of Review
DESIGN• Bridge Articulation• Bearing Type• Mono-pile
Having in mind the future maintenance of the bridge
MINISTRY OF PUBLIC WORKSRoads administration
72 of 125
Bridge Articulation
• Replacing bearings on 36-km long bridge is a maintenance challenge
• Input on local experience with elastomeric bearings
• Contractor to perform life cycle cost optimization to justify choice of bearings
•Having in mind •the future maintenance •of the bridge
MINISTRY OF PUBLIC WORKSRoads administration
73 of 125
Summary
BRIDGE STRUCTURE BASIC DESIGN REVIEW COMPLETED
WE ARE IN THE PROCESS OF RESOLVING COMMENTS WITH THE CONTRACTOR
MINISTRY OF PUBLIC WORKSRoads administration
74 of 125
Infrastructures & Buildings,Authorities Approval,
(Robbie)
MINISTRY OF PUBLIC WORKSRoads administration
75 of 125
PROJECT INFRASTRUCTURE• Potable Water Network• Sanitary Network & WWTP• Storm Water Drainage Network• Electrical Distribution Network• Irrigation Network• External Fire Fighting Network
PERMANENT BUILDINGS• Administration Buildings
Shuwaikh Port South Bay Island North Bay Island Subiyah
• Visitor Centre
• 26 ‘Building Structures’ in total• Each Building Design includes –
Architecture Structural MEP Interior Design
Project Overview – Infrastructure & Buildings
MINISTRY OF PUBLIC WORKSRoads administration
76 of 125
Doc. Number Document Title Current Status
RA140-21-ISE-EM-TR-07855 Water Supply System Basic Design Report B
RA140-21-ISE-EM-TR-07856 Irrigation System Basic Design Report B
RA140-21-ISE-EM-DW-07550 Water Supply And Irrigation Drawing Package B
Basic Design Review Findings – Key Points• Further coordination needed to confirm connections points at Shuwaikh & Subiyah• Possible requirement for P/Stations dependent on Pressures at connection points • Proposed that Potable Water would be used to augment Irrigation System – not permitted by MPW or MEW
POTABLE WATER & IRRIGATION
Infrastructure Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
77 of 125
SEWAGE SYSTEM & WWTP Doc. Number Document Title Current Status
RA140-21-ISE-EM-TR-07831 Waste Water Treatment Plant Design Condition B
RA140-21-ISE-EM-TR-07832 Waste Water Treatment Plant Basic Design Report B
RA140-21-ISE-EM-DW-07300 Waste Water Treatment Plant Drawing Package B
RA140-21-ISE-EM-TR-07860 Sewage System Basic Design Report B
RA140-21-ISE-EM-DW-07600 Sewage System Drawing Package B
Basic Design Review Findings – Key Points• Septic Tanks proposed for ‘remote’ buildings – SSH has asked Contractor to consider Holding Tanks
STORM WATER DRAINAGE SYSTEMDoc. Number Document Title Current Status
RA140-21-ISE-EM-TR-07850 Storm Drainage System Basic Design Report B
RA140-21-ISE-EM-DW-07500 Storm Drainage System Drawing Package B
Basic Design Review Findings – Key Points• Proposed system has drainage to the sea – not permitted by KEPA; specific approval required• Connection to Storm Water Network in Shuwaikh Port
Infrastructure Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
78 of 125
ELECTRICAL DISTRIBUTION & MAIN BRIDGE LIGHTING
Doc. Number Document Title Current Status
RA140-21-ISE-EM-TR-07811 Electrical Basic Design Report B
RA140-21-ISE-EM-DW-07100 Electrical Drawing Package B
RA140-21-ISE-EM-TR-07841 Basic Design Main Bridge Lighting B
RA140-21-ISE-EM-DW-07400 Basic Design Main Bridge Lighting Drawing Package B
Basic Design Review Findings – Key Points• Electrical design is not compliant MEW standards• Main areas of non-compliance are –
Transformers Rating (i.e. size) Proposed Girder Substation Proposed 11kV Onshore Substation will be ‘Package Type’ Proposed 132kV Major Substation
• Proposed Maintenance Access for Girder Substation
Infrastructure Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
79 of 125
PROPOSED GIRDER SUBSTATIONS(3D Render)
Key Concerns• Method of Installation/Replacement • Maintenance Access• Fire Fighting Systems
Infrastructure Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
80 of 125
Infrastructure Basic DesignPROPOSED GIRDER SUBSTATIONSSan Francisco/Oakland New Bay Bridge
Substation installed inside Girder
MINISTRY OF PUBLIC WORKSRoads administration
81 of 125
BRIDGE HVAC SYSTEMSDoc. Number Document Title Current Status
RA140-21-ISE-EM-TR-07829 Dehumidification System B
RA140-21-ISE-EM-DW-07290 Dehumidification Drawing Package B
RA140-21-ISE-EM-TR-07845 Bridge Access & Ventilation Report B
RA140-21-ISE-EM-DW-07450 Bridge Access & Ventilation Drawing Package B
Basic Design Review Findings – Key Points• Needs further coordination on total BUA’s & expected Air Conditioning Loads with MEW
EXTERNAL FIRE FIGHTING SYSTEMSDoc. Number Document Title Current Status
RA140-21-ISE-EM-TR-07865 Basic Design Report On External Fire Fighting W
RA140-21-ISE-EM-DW-07650 Drawing Package On External Fire Fighting W
Basic Design Review Findings – Key Points• Overdesign of Fire Pump System (overdesign will not approve – must meet exact KFD requirement)• No Fire Fighting System for proposed Girder Substation
Infrastructure Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
82 of 125
Bay Island North• Causeway Administration Building (MPW)• Sea Rescue Operation Centre Building (MoC)• Administration Support Building (MoD)• Fire Station Building (KFD)• Coat Guard Operation Centre (MoI)• Traffic Monitoring & Control Centre (Traffic Police)• Substation• WWTP
Bay Island South• Causeway Administration Building (MPW)• Sea Rescue Operation Centre Building (MoC)• Administration Support Building (MoD)• First Aid Centre (MoH)• Fire Station Building (KFD)• Coat Guard Operation Centre (MoI)• Traffic Monitoring & Control Centre (Traffic Police)• Substation• WWTP
Permanent Buildings Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
83 of 125
BUILDINGS – ADMINISTRATION BUILDINGS
Doc. Number Document Title Current Status
RA140-21-BUI-AR-TR-08821 Architecture Basic Design Report B
RA140-21-BUI-AR-DW-08200 Architecture Drawing Package B
RA140-21-BUI-AR-DW-08300 Structure Drawing Package B
RA140-21-BUI-EM-DW-09200 Installations & Systems Drawing Package B
Basic Design Review Findings – Key Points• End-user requirements need to be confirmed• Exterior finishes need to be revised (take account of exposure to sea water)• Minimal Landscaping design submitted• No Interior Design submitted (must also coordinated with End-user requirements)• Buildings Workshop with Designer held on 02/04/2014
Permanent Buildings Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
84 of 125
Proposed Visitor Centre Design
Permanent Buildings Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
85 of 125
BUILDINGS – VISITOR CENTRE
Doc. Number Document Title Current Status
RA140-21-BUI-AR-TR-08811 Visitor Center Basic Design Report B
RA140-21-BUI-AR-DW-08100 Visitor Center Architecture Drawing Package B
RA140-21-BUI-EM-DW-09100 Visitor Center Installations & Systems Drawing Package B
Basic Design Review Findings – Key Points• End-user requirements need to be confirmed• Building Design is not compliant with new KFD requirements (e.g. only 1 elevator provided)• Landscaping Design to be finalised• Interior Design to be finalised (also coordinated with End-user requirements)• Buildings Workshop with Designer held on 02/04/2014
Permanent Buildings Basic Design
MINISTRY OF PUBLIC WORKSRoads administration
86 of 125
Geotechnical and Marines,
(Shadi)
MINISTRY OF PUBLIC WORKSRoads administration
87 of 125
Geotechnical and Marine (1/23)
• Basic Design Overview – Geotechnical and Marine
• Geotechnical• Onshore-Offshore Bridge Foundations • Ground Improvement and Embankment Stability• Pavement and Material Design
• Marine• Dredging Works• Reclamation Works• Slope/edge protection• Marina Design
MINISTRY OF PUBLIC WORKSRoads administration
88 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations
1. On-Land Bridge – Ghazali Transition2. Shuwaikh Port Bridge3. Shuwaikh Port Interchange4. Offshore Bridge – 40m Span Shuwaikh Bridge5. Bay Island South6. Approach Bridge South7. Main Bridge8. Approach Bridge North9. Bay Island North10. Offshore Bridge – 60m Span Subiyah Bridge11. Subiyah Interchange Bridge
Geotechnical and Marine (2/23)
MINISTRY OF PUBLIC WORKSRoads administration
89 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations • On Land Bridge – Ghazali Transition
• No geotechnical investigation reports received to date• Subsurface profile comprises of 1.5m-6m thick layer of fill underlain by Silty to
Clayey loose to very dense sand till the end of boreholes (-17m FGL)• As per the basic design, the bridge is supported on piles (2.5m in diameter,
lengths from 20m to 31m FGL)
Geotechnical and Marine (3/23)
MINISTRY OF PUBLIC WORKSRoads administration
90 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations • Shuwaikh Port Interchange
• Soil stratigraphy at the subject site is 12m of soft clay interchanging with loose sand followed by very dense sand to 40m depth.
• Drilled shafts are 28m length (FGL) and 2.5m diameter (as per Basic design).
Geotechnical and Marine (4/23)
MINISTRY OF PUBLIC WORKSRoads administration
91 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations • Offshore Bridge – 40m Span Shuwaikh Bridge
• Soil stratigraphy at the subject site is 9m of medium dense sand followed by 6m of dense sand then very dense sand to 39m.
• Drilled shafts are 26m long and 2.5m diameter (as per Basic design).
Geotechnical and Marine (5/23)
Sand
MINISTRY OF PUBLIC WORKSRoads administration
92 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations • Main Bridge
• The soil stratigraphy at the main bridge site is 10m of soft clay followed by very dense Sand to 28m.
• The foundations of the Main Bridge consist of drilled shafts of 3.0m diameter and varying lengths starting from 30 m at piers to 53 m at Pylon.
Geotechnical and Marine (6/23)
MINISTRY OF PUBLIC WORKSRoads administration
93 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundation • Approach Bridges (South & North)
• Soil stratigraphy at the subject site comprise of 12m of soft clay overlying a layer of dense sand stretching 3m in depth followed by very dense sand down to 45m depth.
• Drilled shafts’ lengths range between 31m to 35m from seabed level with diameters of 3m (as per Basic design).
Geotechnical and Marine (7/23)
MINISTRY OF PUBLIC WORKSRoads administration
94 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations • Offshore Bridge – Subiyah Bridge
• The ground surface level of Subiyah Offshore Area ranges from 3.35m PWD to -3.56mPWD. The stratigraphy of this area comprises clay layers lying on dense sand layers.
• As per the basic design, the bridge is supported on piles (3m in diameter, 49m long fromseabed level).
Geotechnical and Marine (8/23)
MINISTRY OF PUBLIC WORKSRoads administration
95 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations• Subiyah Interchange Bridge
• The soil stratigraphy at the Subiyah interchange bridge site is Silty Sand. • The foundations of Subiyah interchange bridge are spread footings.
Geotechnical and Marine (9/23)
MINISTRY OF PUBLIC WORKSRoads administration
96 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Onshore-Offshore Bridge Foundations • SUMMARY
• Approval of foundation design for construction shall not be concluded till the receipt of:1. Detailed design2. Geotechnical site investigation reports3. Approved Method Statement4. Pile load test results5. Effect of scour depth.
Geotechnical and Marine (10/23)
MINISTRY OF PUBLIC WORKSRoads administration
97 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Ground Improvement and Embankment Stability
• Subiyah Embankment
• Current ground surface elevation is +3.0m PWD (about 2m of reclamation), deep compaction is not anticipated.
• Improvement of natural compressible (soft clay) foundation soils was considered necessary to meet project serviceability (settlement) requirements.
• Preloading with the use of Prefabricated Vertical Drains (PVD) was selected as the ground improvement technique.
Geotechnical and Marine (11/23)
MINISTRY OF PUBLIC WORKSRoads administration
98 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Ground Improvement and Embankment Stability
• Bay Island North
Geotechnical and Marine (12/23)
• Current seabed level is about -4.0mPWD (about 9m of reclamation isrequired to reach the target level +5mPWD for Bay Island North platform)• Improvement of natural compressible(soft clay) foundation soils wasconsidered necessary to meet projectserviceability and stability requirements• Preloading with the use of PVD (only)was proposed by the Contractor(tender design implements stonecolumns at the perimeter bund as well)as the ground improvement technique.
MINISTRY OF PUBLIC WORKSRoads administration
99 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Ground Improvement and Embankment Stability
• Bay Island South
• Current seabed level is about -1.0~-2.0m PWD (about 6~7m of reclamation is required to reach the target level +5m PWD for Bay Island South platform)
• Soft soils require ground improvement to meet project serviceability and stability requirements
Geotechnical and Marine (13/23)
MINISTRY OF PUBLIC WORKSRoads administration
100 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Ground Improvement and Embankment Stability
• Shuwaikh Embankment
• Current ground level is about +2.0m PWD (about 3m of reclamation is required to reach the target level +5m PWD for Shuwaikh embankment platform)
• Reclamation area is divided into two parts according to soil type: Stage (I) no need for ground improvements. Stage (II) on soft/ loose soils that require ground treatment to meet project serviceability and stability requirements
Geotechnical and Marine (14/23)
MINISTRY OF PUBLIC WORKSRoads administration
101 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Pavement and Material Design
• Pavement cross-sections were submitted for the following locations as per Concept design drawings:
• Shuwaikh Interchange• Subiyah Interchange
• Detailed pavement design calculations for each pavement section are not yet submitted
• Approval of final pavement design for construction shall be concluded upon the receipt of traffic volumes and defining the subgrade strengths at each location
Geotechnical and Marine (15/23)
MINISTRY OF PUBLIC WORKSRoads administration
102 of 125
• “BASIC DESIGN” REVIEW FINDINGS• Marine Works
• Subiyah Embankment Slope Protection Works• Shuwaikh Embankment Slope Protection Works• Bay Island North – Dredging, Reclamation, Slope Protection Works and Marina Design• Bay Island South– Dredging, Reclamation, Slope Protection Works and Marina Design• Temporary Access Channel at Subiyah – Dredging Works
Geotechnical and Marine (16/23)
MINISTRY OF PUBLIC WORKSRoads administration
103 of 125
Geotechnical and Marine (17/23)
• “BASIC DESIGN” REVIEW FINDINGS• Marine Works
• Subiyah Embankment
• Suwaikh Embankment
Subiyah Embankment slope protection cross section
Subiyah Embankment layout
Shuwaikh Embankment layout Shuwaikh embankment slope protection cross section
MINISTRY OF PUBLIC WORKSRoads administration
104 of 125
Geotechnical and Marine (18/23)
• “BASIC DESIGN” REVIEW FINDINGS• Marine Works
• Bay Island North
• Bay Island South
Bay Island North slope protection cross section Bay Island North layout
Bay Island South layout Bay Island South slope protection cross section
MINISTRY OF PUBLIC WORKSRoads administration
105 of 125
Geotechnical and Marine (19/23)
• “BASIC DESIGN” REVIEW FINDINGS• Marine Works
• Dredging Works
Temporary Access Channel Dredging at Subiyah Temporary access channel layout
Navigation Channel Dredging at Bay Island South Navigation Channel Dredging at
Bay Island North
MINISTRY OF PUBLIC WORKSRoads administration
106 of 125
Geotechnical and Marine (20/23)
• “BASIC DESIGN” REVIEW FINDINGS• Marine Works
• Marina Design
Bay Island North Marina Basin LayoutBay Island South Marina Basin Layout
MINISTRY OF PUBLIC WORKSRoads administration
107 of 125
• STATUS OF CURRENT WORKS• Geotechnical Works
• Onshore geotechnical site investigation works – 199 boreholes completed - 13 boreholes left• Offshore geotechnical site investigation works – 597 boreholes completed• Pilot Pile testing (Offshore and Onshore) - 12 pilot pile tests carried out to date
Geotechnical and Marine (21/23)
MINISTRY OF PUBLIC WORKSRoads administration
108 of 125
Geotechnical and Marine (22/23)
• STATUS OF CURRENT WORKS• Geotechnical Works (Cont’d)
• Shuwaikh Embankment – Stage I reclamation works - Ongoing• Subiyah Platform backfilling – 30% completed to date
MINISTRY OF PUBLIC WORKSRoads administration
109 of 125
Geotechnical and Marine (23/23)
• STATUS OF CURRENT WORKS• Marine Works
• Temporary Access Channel Dredging at Subiyah - Completed• Geotextile laying at Bay Island North - Initiated
MINISTRY OF PUBLIC WORKSRoads administration
110 of 125
Environmental Management and Monitoring
(Chris)
MINISTRY OF PUBLIC WORKSRoads administration
111 of 125
Environmental Management and Monitoring (1/9)
• Ecological mitigation - New Vegetation habitat;• Waste management;• Pollution prevention and control;• Environmental monitoring –
• Pollution, physical and chemical monitoring;• Biological and ecological monitoring;
MINISTRY OF PUBLIC WORKSRoads administration
112 of 125
Contractor Progress -• Completion (100%) of artificial reef & new vegetation habitat
Environmental Management and Monitoring (2/9)
MINISTRY OF PUBLIC WORKSRoads administration
113 of 125
Contractor progressConstruction environmental management
Pollution prevention – use of integrated bunding and drip trays
Waste and chemical management – use of contained and secure chemical storage
Environmental Management and Monitoring (3/9)
MINISTRY OF PUBLIC WORKSRoads administration
114 of 125
Contractor progressEnvironmental monitoring (March 2014)
Pollution / Physical:•Air quality - 100% (6 sites, 1 site lost);•Noise – 100 % (4 sites, 3 active)•Current and tides (not scheduled);•Water quality – 100 % (21 sites);•Dredging (not scheduled*);•Sediment chemistry – 100% (21 sites)
Biological:•Avifauna – 100% (4 sites);•Algal beds (April start);•Fish and shrimp – 17% (30 sites) •Benthic infauna – 100 % (21 sites);
•Noise monitoring (Shuwaikh) •Air quality station •Water quality
Environmental Management and Monitoring (4/9)
MINISTRY OF PUBLIC WORKSRoads administration
115 of 125
Air quality – Dust and Diffusion Tubes
Sediment quality and benthic infauna
Air quality - Real time AQMS analysers
Environmental Management and Monitoring (5/9)
MINISTRY OF PUBLIC WORKSRoads administration
116 of 125
Progress• Inspection of all contractor monitoring activities undertaken to date – best practice monitoring procedures observed;• Verification of full and successful completion of New Vegetation Habitat installation (100%);• Environmental audits undertaken at both Shuwaikh and Subiyah;• Excellent coordination between contractors, EWC and Dar
Environmental Management and Monitoring (6/9)
MINISTRY OF PUBLIC WORKSRoads administration
117 of 125
Verification of NVH by GPS and Echo Sounder
Environmental Management and Monitoring (7/9)
MINISTRY OF PUBLIC WORKSRoads administration
118 of 125
Verification of NVH by dive survey
Environmental Management and Monitoring (8/9)
MINISTRY OF PUBLIC WORKSRoads administration
119 of 125
Key areas of focus – April 2014• Inspections of seasonal monitoring:
• Algal beds (to start in April: 25 locations);• and Fish and Shrimp monitoring (25 locations
remaining).
• Establishment monitoring of New Vegetation Habitat –Scheduled end of April and end of May.
• Continue to work with contractors regarding development of key environmental management activities:
• Spill Response – Marine environment;• Pollution prevention - Terrestrial;• Chemical and waste management.
Environmental Management and Monitoring (9/9)
MINISTRY OF PUBLIC WORKSRoads administration
120 of 125
Bridge Construction Sequence
(Araby)
MINISTRY OF PUBLIC WORKSRoads administration
121 of 125
Bridge Construction Sequence
Program For The Superstructure Installation
05‐Jul‐15
05‐Jul‐16
10‐Sep‐16
01‐Aug‐17
09‐Apr‐17
21‐Aug‐17
10‐Jul‐16
08‐Apr‐17
Dismantle, Transfer & Assemble L/G10‐Jul‐16 – 08 Sep‐16
28‐Feb‐16
14‐Jan‐18
8.0km
15.0km
4.0km
2.5km
MINISTRY OF PUBLIC WORKSRoads administration
122 of 125
•Construction of Bridge Main Elements - Video Animations
Fabrication and Installation Works
MINISTRY OF PUBLIC WORKSRoads administration
123 of 125
•Construction of Bridge Main Elements - Video Animations
Continuous Works of Box Girder
MINISTRY OF PUBLIC WORKSRoads administration
124 of 125
Bridge Construction Sequence
•Production Lines:
- Total 4 Lines- 3 lines for 60 m span.- 1 line for 40 m span
•Production Rate:One girder/2-days/ 1-line
•40 Box Girders /Month
Superstructure Fabrication
MINISTRY OF PUBLIC WORKSRoads administration
125 of 125
THANK YOU